Summary of the Mineral Block

PART-A-General Information about Nandavaram –Venkatapuram


Lime Kankar Block

Features Details
1. Location
Mineral Block Nandavaram –Venkatapuram Lime
Kankar Block
Corner Points (Latitude, Longitude) 1) N 150 22’59.58162” X E 780 15’22.90418”
2) N 150 21’51.51230” X E 780 15’36.62461”
3) N 150 21’44.54637” X E 780 15’30.56632”
4) N 150 21’45.96946” X E 780 15’17.55561”
5) N 150 21’51.14760” X E 780 15’20.00179”
6) N 150 21’56.54079” X E 780 15’23.12241”
Villages 1) Sy.No.507/3, 512 to 514(P), 519 of
Nandavaram Village and
2) Sy.No. 7/1 & 5/2 of Venkatapuram Village
Tehsil/Taluka/Mandal Banaganapalli Mandal
District Kurnool
State Andhra Pradesh
2. Area (hectares/Square Kilometers) 24.739 Hects
Mineralized Area 23.368 Hects
Non-Mineralized Area 1.371 Hects
3. Exploration
Status (G2/G3/G4etc.) G2
Exploration Agency Director of Mines and Geology,
Andhra Pradesh
Total Number of Bore holes with meterage 2 Bore holes 21.5 Meters and 4 pit samples
of 37.5 Cum.
Bore hole Spacing (Density) 12.00 Hects.,
4. Quantity of Minerals (Grade-Wise)
Mineral : Lime Kankar Sl.No CaO Tonnage
Range/Grade Million tones
1 44 to 49 1.66
Total Geological Resources (Reserves) 1.66 Million tones
5. Mineralized Zones
Number of Mineral Zones Simple and contiguous bedded sidementry
deposit
Trend (Dipand Strike) Horizontal to gently dipping at 10 to 20

Total Thickness Variable and upto 4.1 meters


6. Accessibility
Nearest Rail Head Banaganapalli
Road Block can be approached 10 K.m., from
Banaganapalli town on Banaganapalli to
Nandyala State high way .
Airport Bangalore, Kadapa & Tirupathi
7. Hydrography
Local Surface Drainage Pattern (Channels) No water courses.
Rivers/ Streams Gangapuru Vagu is 2 K.m., from the block
8. Climate
Mean Annual Rainfall 330 Mille Meters
Temperatures (December) 160 c
Temperatures (June) 460 c
9. Topography
Topo Sheet Number 57 I/7
Morphology of the Area Gently undulating Topo graph
PART B
PARTICULARS OF STATUTORY LICENSES, PERMITS, PERMISSIONS, CONCESSIONS,
APPROVALS AND CONSENTS RELATED TO MINING OPERATIONS

Particulars Details/ Status


1. Forest clearance Not applicable
2. Wild life clearance (Sanctuary, reservoir Not applicable
special zone clearances)
3. Environmental clearance To be obtained by successful bidder

4. Consent to establish To be obtained by successful bidder

5. Explosive license To be obtained by successful bidder

6. Permission for mine opening To be obtained by successful bidder

7. Permission of installation/trial operation To be obtained by successful bidder


of equipment
8. Ground water clearance (Centre/ State) To be obtained by successful bidder

9. Railway siding approval To be obtained by successful bidder

10. Approval for diesel storage To be obtained by successful bidder

11. Power line from State Discom To be obtained by successful bidder

12. Clearances relating to work under an To be obtained by successful bidder


existing transmission line or shifting of the
transmission line
13. Grama Sabha Consent To be obtained by successful bidder

PART C - PARTICULARS OF LAND


Particulars Details/ Status
1. Total Concession Area 24.739 Hects.,
2. Forest Land with Status Nil
3. Government Land with Status Nil
4. Private Land with Status 24.739 Hects.,
5. Revenue survey details of the are 1) 21.544 Hects., in Sy.No.507/3, 512 to
514(P), 519 of Nandavaram Village and
2) 3.195 Hects., in Sy.No. 7/1 & 5/2 of
Venkatapuram Village