You are on page 1of 3

Government of Karnataka

Summary of the Mineral Block


(to be made available on the website of e-auction platform provider)
(As per GoI Notification No:1/15/2015-M.VI Dated:02.07.2015)

Part A - GENERAL INFORMATION ABOUT MINERAL BLOCK


Features Details
1 Location
Mineral Block Kakol Gold Block
Corner Points
Between Latitudes N14⁰39’41.04” and 14⁰43’27.84”
Latitude-Longitude
Longitudes E75⁰30’00” and 75⁰34’8.76”
A = (N14°41'39.59649"), (E75°30'00.04554")
B = (N14°43'27.94824"), (E75°30'00.17531")
C = (N14°43'27.85455"), (E75°31'22.97614")
Latitude, Longitude of Corner Points
D = (N14°42'07.52943"), (E75°31'39.35880")
as per DGPS
E = (N14°42'07.19839"), (E75°32'27.70285")
F = (N14°39'41.54130"), (E75°34'08.82010")
G = (N14°39'40.98510"), (E75°31'20.21424")
Villages Kakol, Chetra, Timmapana Gudda
Tehsil/ Taluka Ranibennur
District Haveri
State Karnataka
2 Area Total area – 29.06 sq.km
Mineralised Area in Ha. Mineralised area approximation for gold
mineralisation is not attempted with G4 data as the
gold mineralisation is subjective to many factors and
Non-mineralised Area in Ha.
detailed exploration is required to ascertain the
actual extent.
3 Exploration
G4 level as per Minerals (Evidence of Mineral
Status (G1/G2/G3/G4)
Contents) Rules, 2015.
Exploration Agency Geological Survey of India
Total Number of Boreholes with
Nil
Meterage
Borehole Spacing (Density) Not Applicable
4 Quantity of Minerals (Grade-wise)
Gold -
Resources have not been estimated in G4 level
Total Geological Resources
exploration.
Due to absence of resource estimation, Value of
Value of Estimated resources of the
Concession area in Indian Rupees estimated resources is not calculated.

Information Memorandum/ Mine Block Summery Page 1


Government of Karnataka

5 Mineralised Zones
Number of Mineral Zones Not determined
Trend (Dip and Strike) Not determined
Total Thickness Not determined
6 Accessibility
Nearest Rail Head Ranibennur, Byadgi
Road 15 Km from Rannibennur railway station
Airport Hubbali
7 Hydrography
Local Surface Drainage Pattern
Dendritic drainage pattern
(Channels)
The Tungabadra tributaries such as Savalahalla,
Rivers/Streams Kerekudi Halla and Dodda Halla are the major rivers
flows throw nearby areas.
8 Climate
Mean Annual Rainfall Min: NA Max: NA Avg: 630mm.
Temperatures (December) 29°C
Temperatures (June) 30⁰C
9 Topography Undulating topography
Topo Sheet Number 48 N/9 and 48 N/10
Morphology of the Area Minor hill range
Part B - PARTICULARS OF STATUTORY LICENSES, PERMITS, PERMISSIONS,
CONCESSIONS, APPROVALS AND CONSENTS RELATED TO MINING OPERATIONS
Particulars Details/Status
To be obtained by the successful bidder where ever it
1 Forest clearance for leased area
is required
Wild life clearance (sanctuary, To be obtained by the successful bidder where ever it
2
reserve or special zone clearances) is required
To be obtained by the successful bidder where ever it
3 Environmental Clearance
is required
To be obtained by the successful bidder where ever it
4 Consent to establish
is required
To be obtained by the successful bidder where ever it
5 Explosive licence
is required
To be obtained by the successful bidder where ever it
6 Permission for mine opening
is required
Permission of installation/ trial To be obtained by the successful bidder where ever it
7
operation of equipment. is required
Ground water clearance To be obtained by the successful bidder where ever it
8
(Centre/State) is required
To be obtained by the successful bidder where ever it
9 Railway siding approval
is required

Information Memorandum/ Mine Block Summery Page 2


Government of Karnataka

To be obtained by the successful bidder where ever it


10 Approval for diesel storage
is required
To be obtained by the successful bidder where ever it
11 Power line from State Discom
is required
Clearances relating to work under To be obtained by the successful bidder where ever it
12 an existing transmission line or is required
shifting of the transmission line
To be obtained by the successful bidder where ever it
13 Grama Sabha consent
is required
To be obtained by the successful bidder where ever it
14 Consent for Operate (CFO)
is required
To be obtained by the successful bidder where ever it
15 Approval of Mine Plan from IBM
is required
To be obtained by the successful bidder where ever it
16 Others (if any)
is required
Part C - Particulars of Land
Area Details
1 Total Concession Area 2906.78 Ha
Approximately 471.61 Ha as per Land use land
2 Forest Land with Status
cover data computation.
Approximately 84.35 Ha as per Land use land cover
3 Government Land with Status
data computation.
Approximately 2350.82 Ha as per Land use land
4 Private land with Status
cover data computation.
Land use Land cover map prepared using spatial data
with Cadastral details is uploaded for ready
reference. The survey number wise details of land
status with extent as per the revenue records
5 Revenue survey details of the area (Bhoomi database) is also shared for reference.
However, the actual extent and land status of
individual survey numbers may vary in the ground.
The given reference data given to enable the bidders
to get a fair idea of the landuse and extent.

Information Memorandum/ Mine Block Summery Page 3