Summary of Work Done for December 2022

1. Academic
• Roof concrete topping, in-situ beam & slab – 100% completed including additional VO areas at M&E rooms.
• RC Staircase. 100% finished both side staircase.
• Laying AAC block. (GF – 90% external, 90% internal. 1st – 85% external, 75% internal).
• Delivery & fabrication of roof steel truss. 100% delivered & fabricated to site. Ready for installation. Proceed
once waterproofing completed. Planned to start January 2023.
• Waterproofing work on roof slab including water tank area. 100% completed.
• Waterproofing work on toilet area, GF right side only. 100% completed.
• Water-ponding test completed for waterproofed roof slab & waterproofed toilet area (GF right side only).
• Floor screeding work completed for toilet area; GF right side only including 300mm upturn (wall screeding)
prior to waterproofing work. 100% completed as per stated only.
• Apron Slab – 75% completed. (Remaining left = rear & front walkway area).
• Remaining Apron Slab, rear area (10%) – 100% earth leveling & backfilling work. Pending for Inspection
Chamber to be construct.
• Remaining Apron Slab, front walkway area (15%) – 100% excavation. 100% hardcore. Pending for anti-termite
& lean con. Work in progress.

2. Asrama A
• 1st floor in-situ beam, slab & concrete topping. 100% completed.
• GF RC Staircase. 30% formwork, 30% rebar in progress, left hand side only.
• Installation of 1st floor IBS column. 100% completed.
• Installation of 2nd floor IBS beam. 100% completed (Work in progress, can target to complete this week).
• 2nd floor IBS slab ready at site. 100% completed delivered. To start install on January 2023.
• 2nd floor in-situ beam & slab. 30% rebar & formwork in progress. (Work start earlier, currently in progress).

3. Asrama B
• Installation of 1st Floor Precast Column. 100% completed installed.
• Installation of 2nd Floor Precast Beam & Slab. 100% completed installed
• Ground Floor RC Staircase. 100% completed both sides.
• 2nd floor in-situ beam, slab & concrete topping. 90% formwork, 80% rebar. To be cast on January 2023.
• Laying AAC block. (GF – 60% internal, 60% external. 1st – 30% internal, 30% external).

4. Mosque
• Apron Slab. 90% completed.
• Laying AAC block. 100% completed all external & internal wall.
• Plastering work for external roof wall lower roof beam. 100% completed.
• Delivery & fabrication of roof truss. 100% completed.
• Installation of Roof Truss. 100% finished installed.
• Water proofing & water ponding test on roof slab. 100% completed.
• Water proofing & water ponding test on toilet area (all areas). 100% completed.

5. Menara Tangki Air


• 4th floor column – 100% completed.
• 5th floor suspended beam & slab – 100% completed.
• 5th floor column – 100% completed.
• 6th floor suspended beam & slab – 30% formwork & rebar. Work in progress.

6. Electrical Building
• Material Delivery for AAC block (200mm. THK). 100% delivered on site.
• Laying of AAC block. (GF – 100% internal, 80% external, 20% cannot proceed due to M&E item)
• Waterproofing work on roof slab. 100% completed.
• Waterponding test on waterproofed roof slab. 100% completed.
• Screeding work for roof slab floor. 100% completed.

7. Pump House
• Delivery of AAC block. (100mm THK). Material ready at site.