REPORT BREAKDOWN & WORKING HOUR DESEMBER

Tanggal Shift Unit Jenis Breakdown HM BD Jam mulai Jam akhir Total jam BD Keterangan
14-Dec-22 Swing Shift TR 02 PERBAIKAN TIE ROD 16:00 17:00 1.00 -TR 02 Perbaikan Tie Rod [HM : ] (16:00-17:00)
15-Dec-22 Day Shift TR 02 TROUBLE KOPLING 6619.3 15:09 16:00 0.85 -TR 02 Trouble Kopling [HM : 6619,3] (15:09-16:00)
15-Dec-22 Swing Shift TR 01 TROUBLE SPRING 16:00 18:00 2.00 -TR 01 Trouble Spring [HM : ] (16:00-18:00)
15-Dec-22 Swing Shift TR 02 TROUBLE KOPLING 6619.3 16:00 18:00 2.00 -TR 02 Trouble Kopling [HM : 6619,3] (16:00-18:00)
16-Dec-22 Day Shift TR 02 TRAOUBLE KOPLING 6624.4 8:52 11:03 2.18 -TR 02 Traouble Kopling [HM : 6624,4] (08:52-11:03)
17-Dec-22 Day Shift TR 02 PERBAIKAN HOSE DUMP 6636.9 12:00 16:00 4.00 -TR 02 Perbaikan Hose Dump [HM : 6636,9] (12:00-16:00)
19-Dec-22 Day Shift TR 02 SHIL POMPA HYDROULIC REMBES 13:20 16:00 2.67 -TR 02 Shil Pompa Hydroulic Rembes [HM : ] (13:20-16:00)
21-Dec-22 Day Shift TR 02 POMPA HYD & KNALPOT PATAH 12:21 13:19 0.97 -TR 02 Pompa Hyd & Knalpot Patah [HM : ] (12:21-13:19)
24-Dec-22 Day Shift TR 02 OLI HIDROLIK BOCOR 10:07 13:30 3.38 -TR 02 Oli Hidrolik Bocor [HM : ] (10:07-13:30)
29-Dec-22 Swing Shift TR 03 TYRE NO 4 LEAK 21:50 0:00 2.17 -TR 03 Tyre No 4 Leak [HM : ] (21:50-00:00)
30-Dec-22 Day Shift TR 03 TYRE NO 4 LEAK 8:00 16:00 8.00 -TR 03 Tyre No 4 Leak [HM : ] (08:00-16:00)
30-Dec-22 Swing Shift TR 03 TYRE NO 4 LEAK 2162.8 16:00 20:01 4.02 -TR 03 Tyre No 4 Leak [HM : 2162,8] (16:00-20:01)
30-Dec-22 Swing Shift TR 04 TYRE POS 3 LEAK 6695.8 17:05 18:00 0.92 -TR 04 Tyre Pos 3 Leak [HM : 6695,8] (17:05-18:00)
Total jam BD 34.15

Plant Model No Model Working Hours BD Hours


Hino FM 250 TI TR 01 115 2
Hino FM 250 TI TR 02 114.199999999999 17.05
Hino FM 250 TI TR 03 134.3 14.18
Hino FM 250 TI TR 04 147 0.92
Total BD Hours 34.15

NOTE : JAM BREAKDOWN DIGANTI HARI

Bogor, 09 Januari 2023


Prepared By, Checked By, Approved By,

Chandra Halim W Frisdo Hendra Wijaya


Spv Produksi PT. MPU Project Manager
REPORT BREAKDOWN & WORKING HOUR JANUARI
Tanggal Shift Unit Jenis Breakdown HM BD Jam mulai Jam akhir Total jam BD Keterangan
3-Jan-23 Day Shift TR 02 PENGGANTIAN TANGKI FUEL 6717.2 10:57 11:30 0.55 -TR 02 Penggantian Tangki Fuel [HM : 6717,2] (10:57-11:30)
4-Jan-23 Day Shift TR 02 PERBAIKAN PER HANGER 12:00 16:00 4.00 -TR 02 Perbaikan Per Hanger [HM : ] (12:00-16:00)
4-Jan-23 Day Shift TR 04 PER PATAH 6726.2 14:40 16:00 1.33 -TR 04 Per Patah [HM : 6726,2] (14:40-16:00)
4-Jan-23 Swing Shift TR 02 TROUBLE BUSHING PER DEPAN 16:00 0:00 8.00 -TR 02 Trouble Bushing Per Depan [HM : ] (16:00-00:00)
4-Jan-23 Swing Shift TR 04 TROUBLE PER KIRI BELAKANG PATAH 17:00 0:00 7.00 -TR 04 Trouble Per Kiri Belakang Patah [HM : ] (17:00-00:00)

Total jam BD 20.88

Plant Model No Model Working Hours 0


Hino FM 250 TI TR 01 66.1000000000004 0
Hino FM 250 TI TR 02 42.5999999999995 12.55
Hino FM 250 TI TR 03 64.1999999999994 0
Hino FM 250 TI TR 04 49.5999999999995 8.333333333
Total BD Hours 20.88333333

NOTE : JAM BREAKDOWN DIGANTI HARI

Bogor, 09 Januari 2023


Prepared By, Checked By, Approved By,

Chandra Halim W Frisdo Hendra Wijaya


Spv Produksi PT. MPU Project Manager
WORKING HOUR TR 01

Tanggal Shift Unit HM Awal HM Akhir Total HM

14-Dec-22 Swing Shift TR 01 10471.3 10477.1 5.8


15-Dec-22 Day Shift TR 01 10477.1 10478 0.9
15-Dec-22 Swing Shift TR 01 10478 10480.5 2.5
16-Dec-22 Day Shift TR 01 10480.5 10486.3 5.8
16-Dec-22 Swing Shift TR 01 10486.4 10493 6.6
17-Dec-22 Day Shift TR 01 10493.4 10499.4 6.0
17-Dec-22 Swing Shift TR 01 10499.5 10502.7 3.2
19-Dec-22 Day Shift TR 01 10503.1 10507.8 4.7
19-Dec-22 Swing Shift TR 01 10507.8 10512.1 4.3
20-Dec-22 Day Shift TR 01 10512.6 10515.6 3.0
20-Dec-22 Swing Shift TR 01 10515.6 10521.8 6.2
21-Dec-22 Day Shift TR 01 10522 10525.8 3.8
21-Dec-22 Swing Shift TR 01 10525.8 10528.8 3.0
22-Dec-22 Day Shift TR 01 10528.9 10534.1 5.2
22-Dec-22 Swing Shift TR 01 10534.1 10538.2 4.1
23-Dec-22 Swing Shift TR 01 10538.8 10540.9 2.1
24-Dec-22 Day Shift TR 01 10540.9 10547.5 6.6
24-Dec-22 Swing Shift TR 01 10547.5 10552.6 5.1
26-Dec-22 Day Shift TR 01 10552.6 10556.3 3.7
26-Dec-22 Swing Shift TR 01 10556.3 10561.7 5.4
27-Dec-22 Day Shift TR 01 10561.7 10567.2 5.5
27-Dec-22 Swing Shift TR 01 10567.2 10573.1 5.9
28-Dec-22 Day Shift TR 01 10573.2 10576.4 3.2
29-Dec-22 Day Shift TR 01 10576.4 10578.7 2.3
29-Dec-22 Swing Shift TR 01 10578.9 10580.5 1.6
30-Dec-22 Day Shift TR 01 10580.6 10581.9 1.3
30-Dec-22 Swing Shift TR 01 10581.9 10587.8 5.9
31-Dec-22 Day Shift TR 01 10588 10589.3 1.3
TOTAL 115.0
2-Jan-23 Day Shift TR 01 10590.8 10594.8 4.0
2-Jan-23 Swing Shift TR 01 10594 10600.5 6.5
3-Jan-23 Day Shift TR 01 10600.8 10603.6 2.8
3-Jan-23 Swing Shift TR 01 10603.6 10609.8 6.2
4-Jan-23 Day Shift TR 01 10609.8 10616.5 6.7
4-Jan-23 Swing Shift TR 01 10616.5 10623.1 6.6
5-Jan-23 Day Shift TR 01 10623.1 10629.9 6.8
5-Jan-23 Swing Shift TR 01 10629.9 10636.5 6.6
6-Jan-23 Day Shift TR 01 10636.5 10642.9 6.4
6-Jan-23 Swing Shift TR 01 10642.4 10649 6.6
7-Jan-23 Day Shift TR 01 10649 10652.8 3.8
7-Jan-23 Swing Shift TR 01 10652.8 10655.9 3.1
TOTAL 66.1

Bogor, 09 Januari 2023


Prepared By, Checked By, Approved By,

Rahmat Budi P Chandra Halim W Hendra Wijaya


Engineering Spv. Produksi Project Manager
WORKING HOUR TR 02

Tanggal Shift Unit HM Awal HM Akhir Total HM

10-Dec-22 Day Shift TR 02 7690.2 7694.8 4.6


12-Dec-22 Day Shift TR 02 7695.2 7701 5.8
12-Dec-22 Swing Shift TR 02 6597.7 6602.7 5.0
13-Dec-22 Day Shift TR 02 6602.8 6607.2 4.4
13-Dec-22 Swing Shift TR 02 6607.7 6613 5.3
15-Dec-22 Day Shift TR 02 6614.5 6619.3 4.8
15-Dec-22 Swing Shift TR 02 6619.6 6624.3 4.7
16-Dec-22 Day Shift TR 02 6624.4 6626.5 2.1
16-Dec-22 Swing Shift TR 02 6626.6 6632.9 6.3
17-Dec-22 Day Shift TR 02 6633.1 6636.9 3.8
17-Dec-22 Swing Shift TR 02 6637 6640.4 3.4
19-Dec-22 Day Shift TR 02 6641 6644.5 3.5
20-Dec-22 Day Shift TR 02 6644.5 6651.1 6.6
20-Dec-22 Swing Shift TR 02 6651.1 6657.1 6.0
21-Dec-22 Day Shift TR 02 6657.4 6660.5 3.1
21-Dec-22 Swing Shift TR 02 6661.2 6664.3 3.1
23-Dec-22 Day Shift TR 02 6664.6 6667.4 2.8
23-Dec-22 Swing Shift TR 02 6667.5 6673.8 6.3
24-Dec-22 Day Shift TR 02 6673.8 6678.4 4.6
24-Dec-22 Swing Shift TR 02 6679 6683.9 4.9
27-Dec-22 Day Shift TR 02 6684.3 6687.8 3.5
27-Dec-22 Swing Shift TR 02 6688 6693.7 5.7
28-Dec-22 Day Shift TR 02 6693.7 6696.3 2.6
29-Dec-22 Swing Shift TR 02 6696.7 6701.6 4.9
30-Dec-22 Day Shift TR 02 6701.7 6702.4 0.7
30-Dec-22 Swing Shift TR 02 6702.4 6707 4.6
31-Dec-22 Day Shift TR 02 6707.1 6708.2 1.1
TOTAL 114.2
2-Jan-23 Day Shift TR 02 6708.3 6712.1 3.8
2-Jan-23 Swing Shift TR 02 6712.1 6716.8 4.7
3-Jan-23 Day Shift TR 02 6716.8 6719.7 2.9
3-Jan-23 Swing Shift TR 02 6719.8 6724.1 4.3
4-Jan-23 Day Shift TR 02 6724.5 6726.9 2.4
5-Jan-23 Day Shift TR 02 6728.4 6731 2.6
5-Jan-23 Swing Shift TR 02 6731.1 6737.4 6.3
6-Jan-23 Day Shift TR 02 6737.7 6743.7 6.0
6-Jan-23 Swing Shift TR 02 6743.7 6750.2 6.5
7-Jan-23 Swing Shift TR 02 6750.7 6753.8 3.1
TOTAL 42.6

Bogor, 09 Januari 2023


Prepared By, Checked By, Approved By,
Rahmat Budi P Chandra Halim W Hendra Wijaya
Engineering Spv. Produksi Project Manager
WORKING HOUR TR 03

Tanggal Shift Unit HM Awal HM Akhir Total HM

12-Dec-22 Day Shift TR 03 2028.1 2029.6 1.5


12-Dec-22 Swing Shift TR 03 2029.6 2036.1 6.5
13-Dec-22 Day Shift TR 03 2036.7 2038.7 2.0
13-Dec-22 Swing Shift TR 03 2038.7 2045 6.3
14-Dec-22 Day Shift TR 03 2045.2 2049.8 4.6
14-Dec-22 Swing Shift TR 03 2049.8 2056 6.2
15-Dec-22 Day Shift TR 03 2056.2 2062.1 5.9
15-Dec-22 Swing Shift TR 03 5062.1 5067.3 5.2
16-Dec-22 Day Shift TR 03 2067.4 2072.7 5.3
16-Dec-22 Swing Shift TR 03 2072.7 2079.3 6.6
17-Dec-22 Day Shift TR 03 2079.4 2084.8 5.4
17-Dec-22 Swing Shift TR 03 2084.8 2088 3.2
19-Dec-22 Day Shift TR 03 2088.1 2090.1 2.0
19-Dec-22 Swing Shift TR 03 2090.1 2094.4 4.3
20-Dec-22 Day Shift TR 03 2094.6 2100.2 5.6
20-Dec-22 Swing Shift TR 03 2100.2 2104.4 4.2
21-Dec-22 Day Shift TR 03 2104.4 2106.9 2.5
21-Dec-22 Swing Shift TR 03 2107 2109.4 2.4
22-Dec-22 Day Shift TR 03 2109.5 2114.7 5.2
22-Dec-22 Swing Shift TR 03 2114.7 2118.3 3.6
23-Dec-22 Day Shift TR 03 2118.4 2122.2 3.8
23-Dec-22 Swing Shift TR 03 2122.2 2126.7 4.5
24-Dec-22 Day Shift TR 03 2126.8 2133.1 6.3
24-Dec-22 Swing Shift TR 03 2133.1 2135.6 2.5
26-Dec-22 Day Shift TR 03 2135.6 2139.1 3.5
26-Dec-22 Swing Shift TR 03 2139.1 2144.9 5.8
27-Dec-22 Day Shift TR 03 2145.3 2150.6 5.3
27-Dec-22 Swing Shift TR 03 2150.6 2154.5 3.9
28-Dec-22 Day Shift TR 03 2154.6 2157.2 2.6
29-Dec-22 Day Shift TR 03 2157.2 2159.6 2.4
29-Dec-22 Swing Shift TR 03 2159.6 2162.8 3.2
30-Dec-22 Swing Shift TR 03 2163.3 2165.3 2.0
TOTAL 134.3
2-Jan-23 Day Shift TR 03 2166.9 2172.4 5.5
2-Jan-23 Swing Shift TR 03 2172.4 2178.7 6.3
3-Jan-23 Day Shift TR 03 2178.9 2181.6 2.7
3-Jan-23 Swing Shift TR 03 2181.6 2186.9 5.3
4-Jan-23 Day Shift TR 03 2187 2193.7 6.7
4-Jan-23 Swing Shift TR 03 2193.8 2200 6.2
5-Jan-23 Day Shift TR 03 2200.1 2206.6 6.5
5-Jan-23 Swing Shift TR 03 2206.6 2212.9 6.3
6-Jan-23 Day Shift TR 03 2213.6 2219.1 5.5
6-Jan-23 Swing Shift TR 03 2219.1 2225.5 6.4
7-Jan-23 Day Shift TR 03 2226.3 2230.1 3.8
7-Jan-23 Swing Shift TR 03 2230.1 2233.1 3.0
TOTAL 64.2

Bogor, 09 Januari 2023


Prepared By, Checked By, Approved By,
Rahmat Budi P Chandra Halim W Hendra Wijaya
Engineering Spv. Produksi Project Manager
WORKING HOUR TR 04

Tanggal Shift Unit HM Awal HM Akhir Total HM


10-Dec-22 Day Shift TR 04 2021.6 2026.3 4.7
12-Dec-22 Day Shift TR 04 6554.8 6560 5.2
12-Dec-22 Swing Shift TR 04 6560 6566.1 6.1
13-Dec-22 Day Shift TR 04 6566.3 6572.5 6.2
13-Dec-22 Swing Shift TR 04 6572.5 6578.8 6.3
14-Dec-22 Day Shift TR 04 6579 6585.4 6.4
14-Dec-22 Swing Shift TR 04 6585.4 6591.6 6.2
15-Dec-22 Day Shift TR 04 6591.8 6598 6.2
15-Dec-22 Swing Shift TR 04 6598 6599.9 1.9
16-Dec-22 Day Shift TR 04 6600.3 6605.6 5.3
16-Dec-22 Swing Shift TR 04 6605.7 6610.7 5.0
17-Dec-22 Day Shift TR 04 6611.1 6617 5.9
17-Dec-22 Swing Shift TR 04 6617 6620.7 3.7
19-Dec-22 Day Shift TR 04 6620.8 6625.8 5.0
19-Dec-22 Swing Shift TR 04 6625.9 6630.1 4.2
20-Dec-22 Day Shift TR 04 6630.3 6633.3 3.0
20-Dec-22 Swing Shift TR 04 6633.4 6635.2 1.8
21-Dec-22 Day Shift TR 04 6635.3 6639.4 4.1
21-Dec-22 Swing Shift TR 04 6639.4 6642.1 2.7
22-Dec-22 Day Shift TR 04 6642.5 6647.5 5.0
22-Dec-22 Swing Shift TR 04 6647.5 6651.1 3.6
23-Dec-22 Day Shift TR 04 6651.1 6654.1 3.0
23-Dec-22 Swing Shift TR 04 6654.1 6660.2 6.1
24-Dec-22 Day Shift TR 04 6660.3 6666.5 6.2
24-Dec-22 Swing Shift TR 04 6666.5 6669.5 3.0
26-Dec-22 Day Shift TR 04 6669.5 6673 3.5
26-Dec-22 Swing Shift TR 04 6673 6678.4 5.4
27-Dec-22 Day Shift TR 04 6678.5 6681.2 2.7
27-Dec-22 Swing Shift TR 04 6681.2 6683.1 1.9
28-Dec-22 Day Shift TR 04 6683.3 6686 2.7
29-Dec-22 Day Shift TR 04 6686.1 6688.3 2.2
29-Dec-22 Swing Shift TR 04 6688.3 6693.4 5.1
30-Dec-22 Day Shift TR 04 6693.5 6694.3 0.8
30-Dec-22 Swing Shift TR 04 6694.3 6699 4.7
31-Dec-22 Day Shift TR 04 6699.4 6700.6 1.2
TOTAL 147.0
2-Jan-23 Day Shift TR 04 6700.6 6706.5 5.9
2-Jan-23 Swing Shift TR 04 6706.5 6712.8 6.3
3-Jan-23 Day Shift TR 04 6712.8 6714.9 2.1
3-Jan-23 Swing Shift TR 04 6714.5 6720.3 5.8
4-Jan-23 Day Shift TR 04 6720.4 6726.2 5.8
5-Jan-23 Day Shift TR 04 6728.9 6731.3 2.4
5-Jan-23 Swing Shift TR 04 6731.3 6737.4 6.1
6-Jan-23 Day Shift TR 04 6737.5 6742.9 5.4
6-Jan-23 Swing Shift TR 04 6742.6 6749.1 6.5
7-Jan-23 Swing Shift TR 04 6749.4 6752.7 3.3
TOTAL 49.6

Bogor, 09 Januari 2023


Prepared By, Checked By, Approved By,
Rahmat Budi P Chandra Halim W Hendra Wijaya
Engineering Spv. Produksi Project Manager
WORKING HOURS 10 JANUARI 2023 HINO PT. MPU

Total Jam Kerja dan


Tanggal Shift Unit HM Awal HM Akhir Working Hour Problem
problem
10-Jan-23 Day Shift TR 01 10666.2 10670 3.8 3.4 7.2
10-Jan-23 Day Shift TR 02 6763.3 6769.7 6.4 1.4 7.8
10-Jan-23 Day Shift TR 03 2245.6 2252.1 6.5 1.4 7.9
10-Jan-23 Day Shift TR 04 6762.4 6769 6.6 1.4 8.0
10-Jan-23 Swing Shift TR 01 10670 10676.5 6.5 0 6.5
10-Jan-23 Swing Shift TR 02 6769.7 6776.1 6.4 0 6.4
10-Jan-23 Swing Shift TR 03 2252.2 2258.8 6.6 0 6.6
10-Jan-23 Swing Shift TR 04 6769 6775 6.0 0 6.0
TOTAL 56.4

NOTE :
- Adanya hujan di tanggal 10 Januari di jam 05:13-07:18 sehingga diperlukan maintenance jalan untuk mengatasi slippery dari jam 08:00-09:24
- Untuk TR 01 di standby kan terlebih dahulu karena cycle time belum optimal
- Jam breakdown 55,03 jam diganti di tanggal 10 Januari 2023 dengan jumlah jam kerja 56,4 jam

Bogor, 20 Januari 2023


Prepared By, Checked By, Approved By,

Rahmat Budi P Chandra Halim W Hendra Wijaya


Engineering Spv. Produksi Project Manager
Wheather Delay Shalestone
Tanggal
Hujan Licin Petir Kabut Curah Hujan

1 2.10 - - - 17.00

2 0.43 - - - 2.20

3 3.35 4.00 - - 9.50

4 - - - - 0.80

5 - - - - 0.00

6 - - - - 0.00

7 - - - - 0.00

8 3.65 - - - 15.00

9 - - - - 0.00

10 2.08 1.40 - - 3.00

11 - - - - 0.00

12 - - - - 0.00

13 3.10 5.50 1.22 - 26.00

14 0.65 - - - 17.00

15 0.32 - - - 5.00

16 - - - - 0.00

17 - - - - 0.00

18 - - - - 0.00

Total Hujan, Slippery & Unsafe Condition (Jam) 27.80

Total Curah Hujan (mm) 95.50

Bogor, 20 Januari 2023


Prepared By, Checked By, Approved By,

Rahmat Budi P Chandra Halim W Hendra Wijaya


Engineering Spv. Produksi Project Manager