You are on page 1of 6

APPENDIX TO THE CONDITIONS OF CONTRACT

Clause

4.1(a) Officer(s) empowered to approved variations according to the limits as set out in
Treasury's Instruction No. 202 as amended

Financial Limits - Jadual II Officer

(a) Jika harga asal kontrak tidak melebihi RM10 juta dan jumlah Satu Jawatankuasa yang dipengerusikan oleh
perubahan kerja terkumpul yang dicadangkan tidak melebihi Pegawai Penguasa yang dinamakan di dalam
10% daripada nilai Kontrak ATAU jika harga asal kontrak Kontrak
melebihi RM10 juta dan jumlah perubahan kerja yang
dicadangkan tidak melebihi RM1 juta

(b) Jika harga asal kontrak tidak melebihi RM20 juta dan jumlah Lembaga Perolehan Agensi
perubahan kerja terkumpul yang dicadangkan tidak melebihi
20% daripada nilai kontrak ATAU jika harga asal kontrak
melebihi RM20 juta dan jumlah perubahan kerja terkumpul
yang dicadangkan tidak melebihi RM4 juta.

(c) Dalam Semua hal lain. Ketua Setiausaha Perbendaharaan

4.1(b) Officer(s) empowered to take


action on behalf of the
Government in respect of:

Clauses 51, 52, 53, 58 and 66 … … … Setiausaha Bahagian Pembangunan


Kementerian Pendidikan Tinggi
13 Performance Bond

Amount of Guarantee … … … … … … … RM 5% of Contract Sum

Guarantor Bank/Insurance Company/


Finance Company … … … … … … … … To be submitted by the Contractor

Guarantee No. … … … … … … … … … To be submitted by the Contractor

15 Minimum insurance cover for any one accident or


series of accidents arising out of one event … … … RM 200,000.00

Policy No. : To be submitted by the Contractor

Contract Period + 12 month + 3 month +


Period of insurance : 14 days

15.1(b) Amount of excess … … … … … … … … … RM Up to Contractor


51
APPENDIX TO THE CONDITIONS OF CONTRACT - (Cont'd)

Clause

17 SOCSO Scheme registration number … … … To be submitted by the Contractor

18 Amount to be added to full value


of Contract Sum as the insured sum … … … … RM not applicable

Total Amount Insured … … … … … … … … RM Full Value of Contract Sum

Policy No. : To be submitted by the Contractor

Period of insurance : Contract period only

18(b) Amount of excess … … … … … … … … … RM Up to Contractor

Date of Closing of Tender


21.2 Date of Tender … … … … … … … … … … as stipulated in the Tender Notice

28.1 Value of work to be executed including


materials and goods to be delivered before
First Interim Certificate will be issued … … … … RM 1,000.00

28.2 Value of work to be executed including


materials and goods to be delivered before each
subsequent Interim Certificate will be issued … … RM 1,000.00

28.6 Period for honouring payment certificate


(If none stated, then within thirty (30) days Fourteen (14) days of the issue of
of the issue of the Certificate) … … … … … … Certificates

Only works for which the Contractor


34.4 Work covered by P.C. Sums for which the Contractor has the requisite head and subhead
will be permitted to tender … … … … … … as a Government Contractor

38.2 'Date for Possesssion' of the Site … … … … … To be fixed by the Government

39.1 'Date for Completion' for whole of the Works … … To be fixed by the Government

40.2 Liquidated and Ascertained Damages Current BLR on Date of Tender (%)
x Contract Sum
at the rate of … … … … … … … … … RM 365
per day
52
APPENDIX TO THE CONDITIONS OF CONTRACT - (Cont'd)

Clause

41.1 Sectional Completion:

Identification of Date for Possession Date for Liquidated &


Sections or parts [Clause 38.3] Completion Ascertained Damages

---------------- Not Applicable ---------------

48.1(a) Defects Liability Period (if none stated,


then the period is twelve (12) months) … … … … … … … Twelve (12) Months

5.3, 5.4, Percentage of on-cost charges … … … … … … … … … 5%


15.3, 17.3(b),
18.2

48.2 Percentage of on-cost charges … … … … … … … … … 10%


56.2(d)
53

You might also like