Professional Documents
Culture Documents
Aedd6244 1641010004997
Aedd6244 1641010004997
ROCOF:
VS:
Rate of change
of frequency Vector shift
Switch A is closed
𝑽𝑽𝒕𝒕
𝑰𝑰𝑳𝑳 = 𝑰𝑰𝑮𝑮 + 𝑰𝑰𝒈𝒈
𝑰𝑰𝑳𝑳 = 𝑰𝑰𝑮𝑮
θ: The load angle of the generator After the power island is formed, the load
current is supplied entirely by the generator.
Typical schemes
Under-voltage load shedding
رﻟﻪ ﺣﺬف ﺑﺎر وﻟﺘﺎژي
Congestion mitigation
ﮐﺎﻫﺶ ﭘﺮﺷﺪﮔﯽ ﺧﻂ
Conventional LS
Load shedding
techniques
Adaptive LS Computational
intelligent LS
Steps for under frequency load shedding
• The first stage of automatic load shedding should be
initiated @ 49Hz.(at least 5% of total consumption
1 should be shed)
∑ 𝐿𝐿𝑖𝑖 − ∑ 𝐺𝐺𝑖𝑖
A relative load excess: 𝐿𝐿 =
∑ 𝐺𝐺𝑖𝑖
Load factor
𝑑𝑑𝑑𝑑 𝑝𝑝𝑝𝑝. 𝐿𝐿 2
� 𝑝𝑝𝑝𝑝. 𝐿𝐿. 𝑓𝑓𝑠𝑠2
𝑓𝑓 = 𝑓𝑓 𝑡𝑡 = 0 𝑓𝑓 = 𝑓𝑓0 1− 𝑡𝑡
𝑑𝑑𝑑𝑑 2𝐻𝐻0 𝑠𝑠 � 2𝐻𝐻0
𝑓𝑓 = 𝑓𝑓0
As the frequency decreases, at some reduced frequency it balances the generation, and the
frequency stabilizes at that point.
% 𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟
decrement factor d d = %𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹𝐹 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟
𝑓𝑓
Load excess factor 𝐿𝐿 = 𝐿𝐿0 − 1 + 𝐿𝐿0 𝑑𝑑 1 −
𝑓𝑓0
𝑑𝑑𝑑𝑑 𝑝𝑝. 𝑓𝑓 𝑓𝑓
𝑓𝑓 =− 𝐿𝐿 − 1 + 𝐿𝐿0 𝑑𝑑 1 − 𝑓𝑓𝑠𝑠2
𝑑𝑑𝑑𝑑 2𝐻𝐻0 0 𝑓𝑓0
𝐿𝐿0
𝑡𝑡 → ∞ ⇒ 𝑓𝑓∞ = 𝑓𝑓0 1 −
1 + 𝐿𝐿0 𝑑𝑑
𝑝𝑝. 𝑓𝑓 = 0.85
𝐻𝐻0 = 10
𝐿𝐿0 = 0.3
𝑑𝑑 = 2
𝑝𝑝. 𝑓𝑓. 𝐿𝐿 𝑓𝑓2 − 𝑓𝑓1 𝑓𝑓2 < 𝑓𝑓1 ⇒ 𝑅𝑅 < 0 A decreasing frequency
Setting the load shedding relays 𝑅𝑅 = ﮐﺎﻫﺶ ﻓﺮﮐﺎﻧﺲ
𝐻𝐻 1 − 𝑓𝑓22 ⁄𝑓𝑓12
Example
For a system with 10000 MW connected load, a generating station delivering 1500 MW is lost due to a
contingency. If the aggregate inertia constant is 5 seconds, determine the settings of the under-frequency
relays which will accomplish a load-shedding plan to drop 1500 MW of load in two steps of 750 MW each.
The total relay plus interrupting time of 15 cycles may be assumed at each step.
Set the first step of the load shedding at 59.5 Hz.
10000MW
8500MW
∑ 𝐿𝐿𝑖𝑖 − ∑ 𝐺𝐺𝑖𝑖 10000 − 8500
𝐿𝐿 = 𝐿𝐿 = = 0.1765
∑ 𝐺𝐺𝑖𝑖 8500
0.5
59.5 HZ = 0.553Sec
0.9039
Frequency will decline further
Tripping delay of 15 cycles
0.9039 𝐻𝐻𝐻𝐻⁄sec 0.25 × 0.9039 = 0.226𝐻𝐻𝐻𝐻
= 0.25Sec
The load of 750 MW Load shedding
0.726
= 0.8032 Sec
0.9039
Second step
the next step of load shedding
Safety margin of 0.2 Hz 59.3 − 0.2 = 59.1𝐻𝐻𝐻𝐻
Gen Load
8500 8500
start
No
Frequency<𝑓𝑓𝑚𝑚𝑚𝑚𝑚𝑚
Voltage <𝑉𝑉𝑚𝑚𝑚𝑚𝑚𝑚
Yes
Activate UF relay Or Under voltage relay
Shed load
Frequency=50 Hz No
Voltage in range
Yes
END
Consider a system with an installed plant capacity of 10000 MW.
The largest single unit capacity being 1000 MW, Up to two such units in one generating station
The system imports 600 MW from its tie lines with the neighbors.
Set of contingencies
1. 600 MW (loss of the tie line)
2. 1000 MW (loss of one generator)
3. 1600 MW (loss of one generator and the tie line)
4. 2000 MW (loss of two generators)
5. 2600 MW (loss of two generators and the tie line).
Design a load shedding scheme of five steps:
1. 600 MW
2. 400 MW
3. 600 MW
4. 400 MW
5. 600 MW.
Underfrequency
loadshedding(UFLS)
Automatic
loadshedding
Undervoltage
loadshedding(UVLS)
Voltage stability
• Cause of instability
1. Inadequate reactive support.
2. Heavy reactive power flow
3. Heavily loaded transmission lines.
• Reactive power must be generated at or
near the load center.
• Sufficient reactive support
1. SVC (Static var compensator)
2. STATCOM (Static compensator) Two different voltages for the same power delivered.
UnderVoltage load shedding (UVLS)
• Operate as a last resort
• Undervoltage load shedding: which sheds load to prevent local area
voltage collapse.
• The goal of a UVLS scheme is to shed load to restore reactive power
relative to demand, to prevent voltage collapse and to contain a voltage
problem within a local area rather than allowing it to spread in geography
and magnitude.
• If the first load-shed step does not allow the system to rebalance, and
voltage continues to deteriorate, then the next block of load is dropped.
Typical Utility Substation Load Shedding
Long-term (slow dynamic) voltage
security and corrective actions