Professional Documents
Culture Documents
Republika ng Pilipinas
KAGAWARAN NG KATARUNGAN
Department ofJustice
Manila
MAR 1 7 2022
This refers to your request for this Department's legal opinion on the
authority of the Public-Private Partnership (PPP) Center to access and obtain
confidential project documents.
2. The implementing agencies have the obligation to provide the PPP Center
the original signed contract and copies of project documents listed in
Annex "C" of PPP Governing Board Resolution No. 2015-09-01 or the
PPP Monitoring Framework and Protocols throughout the various stages
of a PPP project; and
3. The PPP Center has the authority to access and obtain copies of project
documents of PPP projects, particularly those that are enumerated in
Annex "C of the PPP Monitoring Framework and Protocols, even if
confidentiality clauses are stipulated in the PPP agreements.
You stated that PPP Center is mandated to: (i) monitor and facilitate the
implementation of PPP programs and projects including all the variants or
OPINION NO. ...Ji Si'TQlk
arrangements under Republic Act (R.A.) No. 6957\ as amended by R.A. No.
7718^ or the BOT law, as well as Joint Venture agreements;^ (11) manage a
central database of information on PPP programs and projects;^ (iii) submit a
report regarding the salient features or a copy of each PPP contract to Congress
and the Investment Coordination Committee (iCC) of the National Economic and
Development Authority (NEDA) Board;® and (iv) prepare reports on the
implementation of PPP programs and projects of the government for submission
to the President at the end of each year.®
You also stated that under the implementing rules and regulations (IRR) of
the BOT Law, the Implementing agencies are required to submit to the PPP
Center an original signed copy of the PPP contract within five (5) calendar days
after signing thereof^ and to periodically submit to the PPP Center all information
on the status of projects implemented by them, as well as a copy of all
unsolicited proposals that they receive and all other related documents.®
Likewise, Section 10 of Executive Order (E.O.) No. 8®, as amended by E.O. No.
136^°, directs all government agencies, including local government units, to
submit reports to the PPP Center on all projects undertaken through PPPs and
mandates the PPP Center to prescribe the frequency of submission, format and
contents, among others.
You further stated that consistent with the aforementioned mandate of the
PPP Center, the PPP Governing Board issued Resolution No. 2015-09-01^^
which directed the PPP Center to: (i) provide reports to the President, Congress,
and the ICC, the Economic Cluster, the Contingent Liability Technical Working
Group and the Development Budget Coordination Committee; (ii) review and
analyze reports and documents submitted by the implementing agency; and (iii)
document best practices and lessons learned in the PPP projects.^^ On the
other hand, the implementing agencies have the obligation to provide copies of
1 Entitled ; "An Act Authorizing The Financing, Constmction, Operation And Maintenance Of Infrastructure
Projects By The Private Sector, And For Other Purposes", dated 9 July 1990.
2 Entitled : "An Act Amending Certain Sections Of Republic Act No. 6957, Entitled An Act Authorizing The
Financing, Construction, Operation And Maintenance Of Infrastructure Pmjects By The Private Sector, And
For Other Purposes", approved on 8 May 1994.
3 Section 2(e), Executive Order No. 8, as amended by Executive Order No. 136, entitled "Reorganizing And
Renaming The Build-Operate And Transfer (BOT) Center To The Public-Private Partnership Center Of The
Philippines And Transferring Its Attachment From Tfte Department Of Trade And Industry To The National
Economic And Development Authority And For Other Purposes", also Sections 1.3(e) and 14.1 of the BOT
Law and its Implementing Rules and Regulations.
^ Section 2(f) of E.O. No. 8.
®Section 14.4 of the BOT Law IRR.
6 Section 2(h) of E.O. No. 8.
^ Section 12.1.
®Section 14.1.
® Entitled : "Reorganizing And Renaming The Build-Operate And Transfer (BOT) Center To The Public-
Private Partnership (PPP) Center Of The Philippines And Transferring Its Attachment From The Department
Of Trade And Industry To The National Economic And Development Authority And For Other Purposes",
dated 9 September 2010.
^0 Entitled : "Amending Certain Sections Of Executive Order No. 8 (S. 2010) Which Reorganized And
Renamed The Build-Operate And Transfer Center To The Public-Private Partnership Center Of The
Philippines And Transferred Its Attachment From The Department Of Trade And Industry To The National
Economic And Development Authority, And For Other Purposes^, dated 28 May 2013.
PPP Monitoring Framework and Protocols.
Section IV (4.2)(c.1) of the PPP Monitoring Framework and Protocols.
OPINION NO.
the relevant documents to the PPP Center throughout the various stages of the
PPP project.^^
However, as earlier mentioned, there have been instances where the PPP
Center was not provided a copy of the PPP contract and other relevant
documents and that some implementing agencies declined the request of the
PPP Center for copies of relevant documents by invoking the confidentiality
clauses contained in their PPP Agreements. Hence, this request for legal opinion.
In order for the PPP Center to efficiently accomplish its task and effectively
comply with its mandate, several laws, rules and regulations, and guidelines were
issued, such as the BOT law, its IRR, and the circulars, wherein implementing
agencies are required to submit to PPP Center pertinent documents relative to
PPP project. Among these are:
At the end of every calendar year, the CCPAP shall report to the President
and to Congress on the progress of all projects implemented under this
Act. (emphasis supplied)
2. Sections 12.1 and 14.1 of the Revised IRR^® of R.A. No. 6957, as
amended by R.A. No. 7718
15 Now PPP Centerpursuant to E.G. No. 144, series of2002 and E.G. No. 8 series of2010.
1® 2012 Revision of the IRR.
OPINION NO. .S. TQlk
Section 14.1 - The PPP Center
The PPP Center shall be responsible for the coordination and monitoring
of projects implemented under Contractual Arrangements or schemes
authorized under these Revised IRR. Project monitoring will be
undertaken to ensure that the project complies with these Revised IRR,
including the proponent's required environmental clearances from the
DENR. For this purpose, concerned Agencies/LGUs shall periodically
submit to the PPP Center information on the status of projects
implemented by them. In addition, ail concerned Agencies/LGUs shall
submit to the PPP Center a copy of all Unsolicited Proposals that
they receive and all other related documents. The PPP Center is also
hereby mandated to guide the Agency/LGU in the preparation and
development of the project.
At the end of every calendar year, the PPP Center shall report to the ICC,
President, and the Congress on the progress of all projects implemented
under these Revised IRR. (emphasis supplied)
Basic is the rule in statutory interpretation that when the law is clear, plain
and free from ambiguity, it must be given its literal meaning and applied without
attempted interpretation.^^ Known as the plain meaning rule, or verba legis, was
derived from the maxim index animi sermo est (speech is the index of intention)
and rests on the valid presumption that the words employed by the legislature in
a statute correctly express its intent and preclude from a different construction.^®
The rationale is because the legislature is presumed to know the meaning of the
words, to have used the words advisedly, and to have expressed its intent by the
use of such words as are found in the statute. Verba legis nan est recedendum,
or from the words of a statute there should be no departure.^®
We agree that while the contracting parties are allowed to establish such
stipulations as they may deem convenient, provided they are not contrary to law
or public policy pursuant to Article 1306 of the Civil Code, the same must be read
in conjunction with statutory and administrative regulations. Contracting parties
cannot contract away from applicable provisions of law, especially those dealing
with matters of public interest. Although the PPP contracts between the
implementing agencies and project proponents contain confidentiality and non-
Furthermore, while the State recognizes the vital role of the private sector
as a valuable partner in achieving the development goals of the country,2° the
government also has the duty to protect public interest and at the same time
uphold the sanctity ofcontracts that comply with the law. With the government's
policy of monitoring, managing, and evaluating the implementation of the PPP
projects, it guarantees the timely and accurate performance of all contractual
obligations with the end view of providing more benefits to the people.
Premises considered, we confirm that the PPP Center has the authority to
access and obtain copies of project documents of PPP projects in the country
notwithstanding the confidentiality clauses that are stipulated in the PPP
agreements; and that implementing agencies have the correlative obligation to
provide the said project documents to the PPC Center throughout the various
stages of a PPP project.
MENARDO I. GUEVARRA
Secretary
Department of Justice
CN:0202203376
20Section 20, Article 11 of the 1987 Constitution.