Professional Documents
Culture Documents
KERTAS PENERANGAN
(INFORMATION SHEET)
KOD NAMA DAN
PROGRAM / PROGRAM MT-011-2 COMPOSITE PRODUCTION
CODE AND NAME
TAHAP / LEVEL LEVEL 2
PENERANGAN / INFORMATION:
MOULD
PREPARATION
SHIPPING
1) This procedure is applied to Control Contamination Area (CCA) where the working
environment is controlled:
1) Airbus Specification:
Humidity: 75% RH
Temperature: 16.0°C ~ 26.0°C
Reference: ACT/AB TECH 0005
2) Boeing Specification:
Humidity: 70% RH
Temperature: 16.0°C ~ 25.0°C
Reference: BAC 5317
3) UTAS Specification:
Humidity: 70% RH
Temperature: 18.3°C ~ 32.22°C
Reference: RPS 17.34 (Rev F)
NO KOD / CODE NO MT-011-2:2014/C01/P(1/2) Muka: 4 Drp: 7
Raw Material 1) Raise Material Requisition Note (MRN) and record in log book.
from Warehouse 2) Issuance to Warehouse (Minimum 3 days prior to Cutting
schedule).
1) Freezer
1. Capability:
Minimum temperature control: -18°C
Approximately Size: 36ft x 36ft x 10ft
Temperature Chart Recorder
Automatic re-start – zero interruption generator back up
Alarm system – when temperature drop at below setting temperature
2. Material:
Glass Pre-preg
Carbon Pre-preg
Uni-carbon Pre-preg
Lightning-Mesh (Al) Pre-preg
Film Adhesive
Core Splice
2) Thawing
3. Purpose:
A process that the material is to warm up to the room temperature
(Temperature 18.3°C - 25.0°C, Humidity Maximum 70%RH).
In thawing room for 8 hours (minimum) to 12 hours (maximum).
Shelf life - length of time of material can be stored, under specified
environment condition without failure to meet specification.
Out Time – the time that the material retains its physical and mechanical
properties when exposed to a temperature higher than allowed by specification
4. Material Pre-preg from Warehouse Freezer:
Kitting personnel shall carried out receiving inspection and ensure the
materials is
accompanied with Serviceable Tag, Material Log & Identification Tag (MIT).
To ensure the box is physically in good condition and material inside the box is
supported at both ends.
NO KOD / CODE NO MT-011-2:2014/C01/P(1/2) Muka: 6 Drp: 7
SOALAN / QUESTION:
a. _________________________________________________________________
b. _________________________________________________________________
c. _________________________________________________________________
2. Special room for placing composite material (pre-preg) before thawing process?
____________________________________________________________________
3. What is the minimum hour’s composite material (pre-preg) need to be thaw before
cutting process?
____________________________________________________________________
4. What is the equipment use for monitoring the temperature and humidity?
____________________________________________________________________
RUJUKAN / REFERENCES: