Cement Mill 2 PM Shutdown - 30.01.

2023

ID Asset Code Asset Code Description Departemnt Duration 8:00 AM 10:00 AM 12:00 PM 2:00 PM 4:00 PM
1 Production Activities 8 hrs
2 Cut Feed Production 0 hrs 1/30
3 4621BM1 4621BM1 Remove coating from water Production 3 hrs
injection nozzles
4 4621BM1 4621BM1 Clean diaphragm slots Production 1 hr
5 4516AS1 4516AS1 clean air slide fabric Production 2.5 hrs
6 4516AS2 4516AS2 clean air slide fabric Production 2.5 hrs
7 Start Feed Production 0 hrs 1/30
8 Safety Activities 8 hrs
9 Energy Isolation Electrical 0.5 hrs
10 Energy De-isolation Electrical 0.5 hrs
11 Mechanical Activities 8 hrs
12 4425BC1 4425BC1 change return roller #3 Mechanical 1 hr
13 4515BC4 4515BC4 Open coupling cover Mechanical 1 hr
14 4512SR2 4512SR2 install missing air seal rings Mechanical 3 hrs
15 4615BE1 4615BE1 Repair cracked buckets Mechanical 5 hrs
16 4627FN6 4627FN6 Dismante motor Mechanical 2.5 hrs
17 4627FN6 4627FN6 Install motor Mechanical 2.5 hrs
18 4925BE1 4925BE1 Install repair strip at belt clamp Mechanical 2 hrs
19 Inspection Activities 8 hrs?
20 4512RP1 4512RP1 Check Roller Press Inspection 1 hr
21 4515BC4 4515BC4 Check overall condition Inspection 1 hr
22 4516AS1 4516AS1 Check fabric condition Inspection 1 hr
23 4516AS2 4516AS2 Check fabric condition Inspection 1 hr
24 4627FN6 4627FN6 Check impeller Inspection 0.5 hrs
25 Electrical Activities 6.17 hrs
26 4512MD1 4512MD1 Check Main Power Cables Electrical 1 hr
27 4512MD2 4512MD2 Check Main Power Cables Electrical 1 hr
28 4513FN1 4513FN1 Check Main Power Cables Electrical 1 hr
29 4627FN6 4627FN6 change motor bearings Electrical 2 hrs
30 Instrument Activities 5 hrs
31 4422WF1 4422WF1 check overall condition Instrument 1 hr
32 4422WF2 4422WF2 check overall condition Instrument 1 hr
33 4422WF3 4422WF3 check overall condition Instrument 1 hr
34 4422WF4 4422WF4 check overall condition Instrument 1 hr
35 4617BF1 4617BF1 check pulsation system Instrument 1 hr