Professional Documents
Culture Documents
ELECTRICAL PERMIT
- An application form (DPWH form No. 77-001-E) shall be
accomplished, signed and submitted by a duly registered
Professional Electrical Engineer. However, if the
installation does not exceed 20 lighting and/or receptacle
outlets or 4000 volt-amperes, 230 volts, the application
may
Section 1301.5. Clearance of Service Drops
be prepared, signed and submitted by a duly registered
- Service drop conductors shall have a clearance of:
electrical engineer or master electrician.
2.50m from the highest point of roofs over which they
pass
Building Envelope Systems
At least 3m from the ground
- that part of any building that physically separates the
At least 1m horizontally from windows, doors, porches,
exterior environment from the interior environment is
fire escapes, or or similar locations and shall be run less
called the building enclosure or building envelope.
than 1.00m above the top level of a window or opening.
“Building enclosure is the physical component of a
building that separates the interior from the exterior: it is
Section 1301.6. Wiring Methods
an environmental separator.” (Straube, J. (2017))
- Service conductors shall be installed in
rigid steel conduit or concrete encased
plastic conduit from point of service drop
to meter base and from meter base to the
disconnecting equipment. Abandoned lines shall be
removed.
SCOPE.
- PEC covers the electric conductors including optical fiber
10.3. Building Envelope Color
- Light-colored building envelope, especially the roof areas
which are the most vulnerable, can reduce heat transfer
from the outside to the inside of the building by having
surface with high solar reflectance index (SRI).
- Building metal roof surfaces shall either be colored white
or have a minimum SRI of 70. there are no exceptions to
this provision.
CONTRACTOR’S RISK
When the estimator is considering the amount of
profit to add to a bid, the amount of risk for the
contractor must also be assessed.
Risk of the contractor: losing money in the process of
a building project (or when the actual cost of
construction exceeds the estimated cost)
Only where the owner changes the scope of the work
of the contract will the contract price change. Else,
extra costs will have to be paid by the contractor.
Under a lump sum contract, the general reasons for
actual costs exceeding the estimates include:
- takeoff quantities are too low
- actual productivity doesn’t meet anticipated
productivity
- subcontractors or material suppliers fail to meet
obligations