You are on page 1of 4

Rehabilitation and Road Opening of Cabalayangan-Sta.

Monica
Farm to Market Road
Scheduled Accomplishment to Date as of Dec. 12, 2022: 21.703%
Actual Accomplishment to date: 1.3 %
Manpower on site: 50 (including staff)
Required Manpower as of December 12, 2022: 92
Equipment on site:

 Roller Compactor- 1
 Bagger Mixer- 2
 Backhoe- 2
 Dump Truck- 2
 Pay Loader- 1
 Backhoe Dozer-1
 Backhoe with Breaker- 1
 Water Truck- 1
Activities:

 Construction of Reinforced Concrete Pipe Culvert at Station 0+019 and 0+079


 Construction of Grouted Riprap at Station 0+700 to 0+720

 Surplus Common Excavation at Station 1+800 to 1+900

 Clearing and Grubbing/ Surplus Common Excavation at Station 0+960 to 1+060


 Construction of Two Barrel Reinforced Concrete Box Culvert at Station 0+402

 Clearing and Grubbing and Surplus Common Excavation at Station 2+300 to 2+340

 Installation of Forms and Reinforcing Bars at Field Office


 Breaking of Existing PCCP at Station 0+960 to 0+1000