Professional Documents
Culture Documents
Bungalow Residential Boq
Bungalow Residential Boq
MATERIAL
ITEM NO. DESCRIPTION QTY UNIT UNIT COST LABOR COST
COST
I. CONCRETE WORKS
a. Footing
Portland Cement 51 bags 260.00 13,260.00 5,967.00
Fine Sand 3 cu.m 800.00 2,400.00 1,080.00
Gravel 6 cu.m 800.00 4,800.00 2,160.00
b. Column
Portland Cement 57 bags 260.00 14,820.00 6,669.00
Fine Sand 4 cu.m 800.00 3,200.00 1,440.00
Gravel 7 cu.m 800.00 5,600.00 2,520.00
c. Beams
Portland Cement 119 bags 260.00 30,940.00 13,923.00
Fine Sand 7 cu.m 800.00 5,600.00 2,520.00
Gravel 14 cu.m 800.00 11,200.00 5,040.00
d. Slabs
Portland Cement 180 bags 260.00 46,800.00 21,060.00
Fine Sand 10 cu.m 800.00 8,000.00 3,600.00
Gravel 20 cu.m 800.00 16,000.00 7,200.00
a. Footing
12mmØ RSB deformed bar x 6m 55 pcs 300.00 16,500.00 7,425.00
#16 GI Wire 5 kgs 75.00 375.00 168.75
b. Column
12mmØ RSB deformed bar x 6m 84 pcs 300.00 25,200.00 11,340.00
10mmØ RSB deformed bar x 6m 100 pcs 200.00 20,000.00 9,000.00
#16 GI Wire 26 kgs 75.00 1,950.00 877.50
d. Beams
12mmØ RSB deformed bar x 6m 263 pcs 300.00 78,900.00 35,505.00
10mmØ RSB deformed bar x 6m 250 pcs 200.00 50,000.00 22,500.00
#16 GI Wire 70 kgs 75.00 5,250.00 2,362.50
e. Slabs
10mmØ RSB deformed bar x 6m 80 pcs 200.00 16,000.00 7,200.00
#16 GI Wire 10 kgs 75.00 750.00 337.50
V. ROOFING
1/4 x 2 x 2 Angle Bar 120 pcs. 600.00 72,000.00 32,400.00
1/4 x 1 Flat Bar 50 pc. 190.00 9,500.00 4,275.00
2 x 3 C-Purlins 80 pcs. 350.00 28,000.00 12,600.00
2 x 10 C-Purlins 12 pcs. 780.00 9,360.00 4,212.00
0.60mm THK Pre-painted Longspan 400 l.m. 265.00 106,000.00 47,700.00
roofing (Rib-type)
Ridge Roll 37 pcs. 275.00 10,175.00 4,578.75
Gutter 30 pcs. 220.00 6,600.00 2,970.00
Teckscrew 2500 pcs. 2.50 6,250.00 2,812.50
e. Hardwares
Paint Thinner 5 gals 400.00 2,000.00 900.00
Lacquer Thinner 5 gals 400.00 2,000.00 900.00
Sanding paper, assorted 1 lot 5,000.00 5,000.00 2,250.00
Stupa rug 1 lot 500.00 500.00 225.00
Paint brush, assorted sizes 1 lot 5,000.00 5,000.00 2,250.00
Paint roller, assorted sizes 1 lot 5,000.00 5,000.00 2,250.00
a. Floor Tiles
500 x 500mm tiles 800 pcs 200.00 160,000.00 72,000.00
Portland Cement 20 bags 240.00 4,800.00 2,160.00
Fine Sand 3 cu.m 800.00 2,400.00 1,080.00
b. Wall Tiles
300x300mm granite tiles 600 pcs 85.00 51,000.00 22,950.00
Portland Cement 2 bags 240.00 480.00 216.00
Fine Sand 1 cu.m 800.00 800.00 360.00
c. Hardwares
Tile Grout 10 packs 270.00 2,700.00 1,215.00
Cutting disc 5 pcs 750.00 3,750.00 1,687.50
a. Door
D1, Glass Door 2.1m x 1.8m 1 set 15,000.00 15,000.00 6,750.00
D2, Panel door 2.1m x 0.8 m 1 sets 8,500.00 8,500.00 3,825.00
D3, Panel door 2.1m x 1m 2 sets 8,500.00 17,000.00 7,650.00
D4, Panel door 2.1m x 0.8m 5 sets 8,500.00 42,500.00 19,125.00
D5, PVC door 2.1m x 0. 6m 1 sets 7,000.00 7,000.00 3,150.00
D6, Sliding glass door 2.1m x 0. 6m 1 sets 10,000.00 10,000.00 4,500.00
D7, Sliding glass door 2.1m x 0. 6m 1 sets 10,000.00 10,000.00 4,500.00
b. Windows
W1, Fixed window 6.6 sq.m 5,000.00 33,000.00 14,850.00
W2, Fixed + sliding window 3.84 sq.m 5,000.00 19,200.00 8,640.00
W3, Fixed + sliding window 2.55 sq.m 5,000.00 12,750.00 5,737.50
W4, Sliding window 5.28 sq.m 5,000.00 26,400.00 11,880.00
W5, Awning window 0.5 sq.m 5,000.00 2,500.00 1,125.00
IX. FORMWORKS
X. ELECTRICAL WORKS
a. Power Layout
1 sets 5,000.00 5,000.00 2,250.00
Main Distribution panel, 4 holes panel
box: ( 6-30A, 1-20A, 2-15A, 1-70A)
5.5mm2 THHN electrical wire 1 rolls 5,000.00 5,000.00 2,250.00
b. Lighting Outlet
Lighting Outlet with 9W LED bulb 15 units 300.00 4,500.00 2,025.00
Surface-typed 9W LED light/Pinlight 30 units 1,000.00 30,000.00 13,500.00
c. Convenience Outlet
CO assembly, 2 gang 21 pcs 250.00 5,250.00 2,362.50
d. Switches
Switch assembly, 3 gang 15 pcs 250.00 3,750.00 1,687.50
e. Distribution wire
THHN electrical wire, 2.0mm2 3 rolls 4,200.00 12,600.00 5,670.00
THHN electrical wire, 3.50mm2 5 rolls 4,200.00 21,000.00 9,450.00
f. Electrical Hardware
1/2" Ø conduit pipe, thick wall 30 pcs 220.00 6,600.00 2,970.00
Junction box with cover, Polyflex 81 pcs 50.00 4,050.00 1,822.50
Utility box with cover, Polyflex 81 pcs 50.00 4,050.00 1,822.50
Electrical Tape, big 10 rolls 65.00 650.00 292.50
Electrical Fittings 1 lot 5,000.00 5,000.00 2,250.00
a. Earth Works
Excavation 22 cu.m 250.00 5,500.00
Backfill, common burrow 40 cu.m 250.00 10,000.00
DETAILED ESTIMATES
ITEM MATERIAL LABOR
DESCRIPTION QTY UNIT UNIT COST
NO. COST COST
I. CONCRETE WORKS
a. Footing
Portland Cement 71 bags 265.00 18,815.00 8,466.75
Fine Sand 4 cu.m 800.00 3,200.00 1,440.00
` Gravel 8 cu.m 800.00 6,400.00 2,880.00
b. Column
Portland Cement 71 bags 265.00 18,815.00 8,466.75
Fine Sand 4 cu.m 800.00 3,200.00 1,440.00
Gravel 8 cu.m 800.00 6,400.00 2,880.00
c. Beams
Portland Cement 121 bags 265.00 32,065.00 14,429.25
Fine Sand 7 cu.m 800.00 5,600.00 2,520.00
Gravel 14 cu.m 800.00 11,200.00 5,040.00
d. Slabs/ Stairs
Portland Cement 165 bags 265.00 43,725.00 19,676.25
Fine Sand 10 cu.m 800.00 8,000.00 3,600.00
Gravel 20 cu.m 800.00 16,000.00 7,200.00
TOTAL COST FOR CONCRETE WORKS 173,420.00 78,039.00
a. Footing
16mmØ RSB deformed bar x 6m 43 pcs 420.00 18,060.00 8,127.00
#16 GI Wire 8 kgs 75.00 600.00 270.00
b. Column
16mmØ RSB deformed bar x 6m 185 pcs 420.00 77,700.00 34,965.00
10mmØ RSB deformed bar x 6m 95 pcs 200.00 19,000.00 8,550.00
#16 GI Wire 12 kgs 75.00 900.00 405.00
d. Beams
16mmØ RSB deformed bar x 6m 220 pcs 420.00 92,400.00 41,580.00
10mmØ RSB deformed bar x 6m 230 pcs 200.00 46,000.00 20,700.00
#16 GI Wire 15 kgs 75.00 1,125.00 506.25
e. Slabs/Stairs
10mmØ RSB deformed bar x 6m 150 pcs 200.00 30,000.00 13,500.00
#16 GI Wire 14 kgs 75.00 1,050.00 472.50
TOTAL COST FOR STEEL REBAR WORKS 286,835.00 129,075.75
V. ROOFING
2 x 3 C-Purlins 14 pcs. 350.00 4,900.00 2,205.00
3/16 x 2" x 2" Angle bar 30 pcs. 900.00 27,000.00 12,150.00
2 x 10 C-Purlins 6 pcs. 780.00 4,680.00 2,106.00
0.60mm THK Pre-painted Longspan 100 l.m. 265.00 26,500.00 11,925.00
roofing (Rib-type)
Gutter 13 pcs. 220.00 2,860.00 1,287.00
Teckscrew 400 pcs. 2.50 1,000.00 450.00
TOTAL COST FOR CEILING WORKS 66,940.00 30,123.00
a. Door
D1, Panel door 2.1m x 1.5 m 1 sets 12,000.00 12,000.00 5,400.00
D2, Panel door 2.1m x 0.8m 2 sets 8,500.00 17,000.00 7,650.00
D3, PVC door 2.1m x 0.7m 1 sets 7,000.00 7,000.00 3,150.00
D4, Panel door 2.1m x 0. 8m 1 sets 8,500.00 8,500.00 3,825.00
D5, Aluminum door 2.1m x 0. 9m 1 sets 10,000.00 10,000.00 4,500.00
b. Windows
W1, Awning window 3.6 sq.m 5,000.00 18,000.00 8,100.00
W2, Arched sliding window 3.312 sq.m 5,000.00 16,560.00 7,452.00
W3, Sliding window 8.4 sq.m 5,000.00 42,000.00 18,900.00
W4, Sliding window 5.12 sq.m 5,000.00 25,600.00 11,520.00
W5, Sliding window 3.2 sq.m 5,000.00 16,000.00 7,200.00
W6, Sliding window 0.72 sq.m 5,000.00 3,600.00 1,620.00
W7, Awning window 0.3 sq.m 5,000.00 1,500.00 675.00
TOTAL COST FOR DOOR & WINDOW WORKS 131,060.00 79,992.00
IX. FORMWORKS
X. ELECTRICAL WORKS
1 lot 80000 36000
TOTAL COST FOR ELECTRICAL WORKS 80,000.00 36,000.00
a. Earth Works
Excavation 35 cu.m 300.00 10,500.00
Backfill, common burrow 8 cu.m 300.00 2,400.00
TOTAL COST FOR EARTHWORKS & FILLS - 12,900.00
983,605.00 476,537.25
PREPARED BY:
ENGR. DOMINIC C. DILAN MRS. DENIA MALLARE
CIVIL ENGINEER OWNER
PROJECT TITLE: PROPOSED GARAGE / STORAGE AND POWERHOUSE BUILDING
OWNER: MR. KARL-HEINZ DE WIT & MRS. JESSIE DE WIT
LOCATION: BRGY. CENTRAL WEST, BAUANG, LA UNION
DETAILED ESTIMATES
ITEM MATERIAL LABOR
DESCRIPTION QTY UNIT UNIT COST
NO. COST COST
I. CONCRETE WORKS
a. Footing
Portland Cement 35 bags 265.00 9,275.00 3,246.25
Fine Sand 2 cu.m 800.00 1,600.00 560.00
` Gravel 4 cu.m 800.00 3,200.00 1,120.00
-
b. Column -
Portland Cement 32 bags 265.00 8,480.00 2,968.00
Fine Sand 2 cu.m 800.00 1,600.00 560.00
Gravel 4 cu.m 800.00 3,200.00 1,120.00
-
c. Beams -
Portland Cement 51 bags 265.00 13,515.00 4,730.25
Fine Sand 3 cu.m 800.00 2,400.00 840.00
Gravel 6 cu.m 800.00 4,800.00 1,680.00
-
d. Slabs -
Portland Cement 52 bags 265.00 13,780.00 4,823.00
Fine Sand 3 cu.m 800.00 2,400.00 840.00
Gravel 6 cu.m 800.00 4,800.00 1,680.00
TOTAL COST FOR CONCRETE WORKS 69,050.00 24,167.50
a. Footing
12mmØ RSB deformed bar x 6m 22 pcs 420.00 9,240.00 3,234.00
#16 GI Wire 2 kgs 75.00 150.00 52.50
-
b. Column -
12mmØ RSB deformed bar x 6m 54 pcs 420.00 22,680.00 7,938.00
10mmØ RSB deformed bar x 6m 80 pcs 200.00 16,000.00 5,600.00
#16 GI Wire 5 kgs 75.00 375.00 131.25
-
d. Beams -
12mmØ RSB deformed bar x 6m 112 pcs 420.00 47,040.00 16,464.00
10mmØ RSB deformed bar x 6m 180 pcs 200.00 36,000.00 12,600.00
#16 GI Wire 10 kgs 75.00 750.00 262.50
-
e. Slabs/Stairs -
10mmØ RSB deformed bar x 6m 40 pcs 200.00 8,000.00 2,800.00
#16 GI Wire 7 kgs 75.00 525.00 183.75
TOTAL COST FOR STEEL REBAR WORKS 140,760.00 49,266.00
a. Door
D1, Electric Operating Overhead Door 2 sets 20,000.00 40,000.00 14,000.00
D2, Steel Door 2 sets 8,000.00 16,000.00 5,600.00
D3, Flush Door 1 sets 5,000.00 5,000.00 1,750.00
b. Windows -
W1, Awning window 1 sq.m 5,000.00 5,000.00 1,750.00
W2, Awning window 0.5 sq.m 5,000.00 2,500.00 875.00
W3, Awning window 1.5 sq.m 5,000.00 7,500.00 2,625.00
TOTAL COST FOR DOOR & WINDOW WORKS 76,000.00 26,600.00
VI. FORMWORKS
a. Earth Works
Excavation 20 cu.m 500.00 10,000.00
Backfill, common burrow 11 cu.m 500.00 5,500.00
TOTAL COST FOR EARTHWORKS & FILLS - 15,500.00
455,440.00 194,904.00
PREPARED BY:
ENGR. DOMINIC C. DILAN MR. KARL-HEINZ DE WIT & MRS. JESSIE DE WIT
CIVIL ENGINEER OWNER
PROJECT TITLE: 3 BEDROOM BUNGALOW WITH ROOF DECK RESIDENTIAL
OWNER: ARLYN D. PERALTA
LOCATION: PUROK 6, BRGY. BALLAY, BAUANG, LA UNION
DETAILED ESTIMATES
ITEM MATERIAL LABOR
DESCRIPTION QTY UNIT UNIT COST
NO. COST COST
I. CONCRETE WORKS
a. Footing
Portland Cement 56 bags 265.00 14,840.00 5,194.00
Fine Sand 4 cu.m 800.00 3,200.00 1,120.00
` Gravel 7 cu.m 800.00 5,600.00 1,960.00
-
b. Column -
Portland Cement 46 bags 265.00 12,190.00 4,266.50
Fine Sand 3 cu.m 800.00 2,400.00 840.00
Gravel 5 cu.m 800.00 4,000.00 1,400.00
-
c. Beams -
Portland Cement 121 bags 265.00 32,065.00 11,222.75
Fine Sand 7 cu.m 800.00 5,600.00 1,960.00
Gravel 14 cu.m 800.00 11,200.00 3,920.00
-
d. Slabs/ Stairs -
Portland Cement 111 bags 265.00 29,415.00 10,295.25
Fine Sand 6.5 cu.m 800.00 5,200.00 1,820.00
Gravel 12.5 cu.m 800.00 10,000.00 3,500.00
TOTAL COST FOR CONCRETE WORKS 135,710.00 47,498.50
a. Footing
16mmØ RSB deformed bar x 6m 40 pcs 420.00 16,800.00 5,880.00
#16 GI Wire 4 kgs 75.00 300.00 105.00
-
b. Column -
16mmØ RSB deformed bar x 6m 96 pcs 420.00 40,320.00 14,112.00
10mmØ RSB deformed bar x 6m 150 pcs 200.00 30,000.00 10,500.00
#16 GI Wire 8 kgs 75.00 600.00 210.00
-
d. Beams -
16mmØ RSB deformed bar x 6m 170 pcs 420.00 71,400.00 24,990.00
10mmØ RSB deformed bar x 6m 220 pcs 200.00 44,000.00 15,400.00
#16 GI Wire 25 kgs 75.00 1,875.00 656.25
-
e. Slabs/Stairs -
10mmØ RSB deformed bar x 6m 100 pcs 200.00 20,000.00 7,000.00
#16 GI Wire 12 kgs 75.00 900.00 315.00
TOTAL COST FOR STEEL REBAR WORKS 226,195.00 79,168.25
V. ROOFING
2 x 3 C-Purlins 14 pcs. 350.00 4,900.00 1,715.00
3/16 x 2" x 2" Angle bar 32 pcs. 900.00 28,800.00 10,080.00
2 x 10 C-Purlins 6 pcs. 780.00 4,680.00 1,638.00
0.50mm THK Pre-painted Longspan 95 l.m. 265.00 25,175.00 8,811.25
roofing (Rib-type) -
Gutter 13 pcs. 220.00 2,860.00 1,001.00
Teckscrew 475 pcs. 2.50 1,187.50 415.63
TOTAL COST FOR CEILING WORKS 67,602.50 23,660.88
a. Door
D1, Panel door 2.1m x 1.5 m 1 sets 8,500.00 8,500.00 2,975.00
D2, Panel door 2.1m x 0.8m 2 sets 7,000.00 14,000.00 4,900.00
D3, PVC door 2.1m x 0.7m 1 sets 5,000.00 5,000.00 1,750.00
b. Windows -
W1, Awning window 4.8 sq.m 4,500.00 21,600.00 7,560.00
W2, Arched sliding window 5.76 sq.m 4,500.00 25,920.00 9,072.00
W3, Sliding window 0.72 sq.m 4,500.00 3,240.00 1,134.00
TOTAL COST FOR DOOR & WINDOW WORKS 78,260.00 27,391.00
IX. FORMWORKS
X. ELECTRICAL WORKS
1 lot 30000
TOTAL COST FOR ELECTRICAL WORKS - 30,000.00
a. Earth Works
Excavation 22 cu.m 500.00 11,000.00
Backfill, common burrow 8 cu.m 500.00 4,000.00
TOTAL COST FOR EARTHWORKS & FILLS - 15,000.00
659,402.50 325,790.88
PREPARED BY:
ENGR. DOMINIC C. DILAN ARLYN D. PERALTA
CIVIL ENGINEER OWNER
PROJECT TITLE :3-STOREY RESIDENTIAL BUILDING WITH ROOF DECK
OWNER: ABRAHAM MENDOZA
LOCATION: BRGY. BACCUIT NORTE , BAUANG, LA UNION
DETAILED ESTIMATES
ITEM MATERIAL LABOR
DESCRIPTION QTY UNIT UNIT COST
NO. COST COST
I. CONCRETE WORKS
a. Footing
Portland Cement 230 bags 265.00 60,950.00 27,427.50
Fine Sand 13 cu.m 800.00 10,400.00 4,680.00
` Gravel 26 cu.m 800.00 20,800.00 9,360.00
b. Column
Portland Cement 160 bags 265.00 42,400.00 19,080.00
Fine Sand 9 cu.m 800.00 7,200.00 3,240.00
Gravel 18 cu.m 800.00 14,400.00 6,480.00
c. Beams
Portland Cement 300 bags 265.00 79,500.00 35,775.00
Fine Sand 16 cu.m 800.00 12,800.00 5,760.00
Gravel 32 cu.m 800.00 25,600.00 11,520.00
d. Slabs/ Stairs
Portland Cement 1040 bags 265.00 275,600.00 124,020.00
Fine Sand 58 cu.m 800.00 46,400.00 20,880.00
Gravel 116 cu.m 800.00 92,800.00 41,760.00
TOTAL COST FOR CONCRETE WORKS 688,850.00 309,982.50
a. Footing
16mmØ RSB deformed bar x 6m 128 pcs 420.00 53,760.00 24,192.00
#16 GI Wire 15 kgs 75.00 1,125.00 506.25
b. Column
W 8 x 24 350 kgs 420.00 147,000.00 66,150.00
W 8 x 35 300 kgs 200.00 60,000.00 27,000.00
d. Beams
W 12 x 16 190 kgs 420.00 79,800.00 35,910.00
W 10 x 16 200 kgs 200.00 40,000.00 18,000.00
e. Slabs/Stairs
10mmØ RSB deformed bar x 6m 350 pcs 200.00 70,000.00 31,500.00
#16 GI Wire 40 kgs 75.00 3,000.00 1,350.00
TOTAL COST FOR STEEL REBAR WORKS 454,685.00 204,608.25
a. Door
D1, Panel door 2.1m x 1.8 m 3 sets 15,000.00 45,000.00 20,250.00
D2, Panel door 2.1m x 0.9m 6 sets 8,500.00 51,000.00 22,950.00
D3, Panel door door 2.1m x 0.8m 9 sets 7,000.00 63,000.00 28,350.00
D4, Sliding door 2.1m x 1. 8m 3 sets 15,000.00 45,000.00 20,250.00
b. Windows
W1, Awning window 16.2 sq.m 5,000.00 81,000.00 36,450.00
W2, Arched sliding window 4.08 sq.m 5,000.00 20,400.00 9,180.00
W3, Sliding window 16.32 sq.m 5,000.00 81,600.00 36,720.00
W4, Sliding window 2.16 sq.m 5,000.00 10,800.00 4,860.00
W5, Sliding window 8.1 sq.m 5,000.00 40,500.00 18,225.00
W6, Sliding window 8.64 sq.m 5,000.00 43,200.00 19,440.00
W7, Awning window 0.3 sq.m 5,000.00 1,500.00 675.00
TOTAL COST FOR DOOR & WINDOW WORKS 387,000.00 217,350.00
IX. FORMWORKS
X. ELECTRICAL WORKS
1 lot 80000 36000
TOTAL COST FOR ELECTRICAL WORKS 80,000.00 36,000.00
a. Earth Works
Excavation 50 cu.m 300.00 15,000.00
Backfill, common burrow 10 cu.m 300.00 3,000.00
TOTAL COST FOR EARTHWORKS & FILLS - 18,000.00
2,382,190.00 ###
PREPARED BY:
ENGR. DOMINIC C. DILAN MRS. ABRAHAM MENDOZA
CIVIL ENGINEER OWNER
PROJECT TITLE: TWO STOREY RESIDENTIAL
OWNER: MR. ISAGANI BAMBAO
LOCATION: BRGY. CENTRAL WEST , BAUANG, LA UNION
DETAILED ESTIMATES
ITEM MATERIAL LABOR
DESCRIPTION QTY UNIT UNIT COST
NO. COST COST
I. CONCRETE WORKS
a. Footing
Portland Cement 46 bags 265.00 12,190.00 5,485.50
Fine Sand 3 cu.m 800.00 2,400.00 1,080.00
` Gravel 5 cu.m 800.00 4,000.00 1,800.00
b. Column
Portland Cement 110 bags 265.00 29,150.00 13,117.50
Fine Sand 6 cu.m 800.00 4,800.00 2,160.00
Gravel 12 cu.m 800.00 9,600.00 4,320.00
c. Beams
Portland Cement 48 bags 265.00 12,720.00 5,724.00
Fine Sand 3 cu.m 800.00 2,400.00 1,080.00
Gravel 6 cu.m 800.00 4,800.00 2,160.00
d. Slabs/ Stairs
Portland Cement 46 bags 265.00 12,190.00 5,485.50
Fine Sand 4 cu.m 800.00 3,200.00 1,440.00
Gravel 6 cu.m 800.00 4,800.00 2,160.00
TOTAL COST FOR CONCRETE WORKS 102,250.00 46,012.50
a. Footing
16mmØ RSB deformed bar x 6m 23 pcs 420.00 9,660.00 4,347.00
#16 GI Wire 4 kgs 75.00 300.00 135.00
b. Column
16mmØ RSB deformed bar x 6m 90 pcs 420.00 37,800.00 17,010.00
10mmØ RSB deformed bar x 6m 60 pcs 200.00 12,000.00 5,400.00
#16 GI Wire 4 kgs 75.00 300.00 135.00
d. Beams
16mmØ RSB deformed bar x 6m 80 pcs 420.00 33,600.00 15,120.00
10mmØ RSB deformed bar x 6m 120 pcs 200.00 24,000.00 10,800.00
#16 GI Wire 8 kgs 75.00 600.00 270.00
e. Slabs/Stairs
10mmØ RSB deformed bar x 6m 105 pcs 200.00 21,000.00 9,450.00
#16 GI Wire 7 kgs 75.00 525.00 236.25
TOTAL COST FOR STEEL REBAR WORKS 139,785.00 62,903.25
V. ROOFING
2 x 3 C-Purlins 11 pcs. 350.00 3,850.00 1,732.50
2 x 4 C- Channel Rafter 6 pcs. 4,500.00 27,000.00 12,150.00
2 x 10 C-Purlins 6 pcs. 780.00 4,680.00 2,106.00
0.60mm THK Pre-painted Longspan 60 l.m. 265.00 15,900.00 7,155.00
roofing (Rib-type)
Gutter 10 pcs. 220.00 2,200.00 990.00
Teckscrew 200 pcs. 2.50 500.00 225.00
TOTAL COST FOR CEILING WORKS 54,130.00 24,358.50
a. Door
D1, Panel door 2.1m x 0.9m 1 sets 10,000.00 10,000.00 4,500.00
D2, Panel door 2.1m x 0.9m 1 sets 8,500.00 8,500.00 3,825.00
D3, Panel door 2.1m x 0.9m 1 sets 7,000.00 7,000.00 3,150.00
D4, Aluminum door 2.1m x 0. 9m 1 sets 8,500.00 8,500.00 3,825.00
D5, PVC door 2.1m x 0. 7m 1 sets 7,000.00 7,000.00 3,150.00
b. Windows
W1, Sliding window 2sets 3.2 sq.m 5,000.00 16,000.00 7,200.00
W2, Sliding window 2 sets 2 sq.m 5,000.00 10,000.00 4,500.00
W3, Sliding window 2 sets 1.2 sq.m 5,000.00 6,000.00 2,700.00
W4, Awning window 0.3 sq.m 5,000.00 1,500.00 675.00
TOTAL COST FOR DOOR & WINDOW WORKS 73,000.00 33,525.00
IX. FORMWORKS
X. ELECTRICAL WORKS
1 lot 25000 11250
TOTAL COST FOR ELECTRICAL WORKS 25,000.00 11,250.00
a. Earth Works
Excavation 13 cu.m 300.00 3,900.00
Backfill, common burrow 10 cu.m 300.00 3,000.00
TOTAL COST FOR EARTHWORKS & FILLS - 6,900.00
546,615.00 253,551.75
PREPARED BY:
ENGR. DOMINIC C. DILAN MR. ISAGANI BAMBAO
CIVIL ENGINEER OWNER