Professional Documents
Culture Documents
Note On Flexible Budgeting and Variance Analysis
Note On Flexible Budgeting and Variance Analysis
During the reporting period, a total of 2,500 patients had an exam and cleaning, and the total costs of the de-
partment were $40,000. The flexible budget for Tanglewood would look as follows:
Note that, although it would appear initially there was a budget overrun of $8,000 ($32,000 - $40,000), in
fact only $2,000 was a “spending” overrun. The remaining $6,000 can be attributed to the volume change,
which the manager could not control.
Factors Other than Volume. Although the flexible budget is a partial answer to the problem
of aligning responsibility with control, it does not answer all the important questions. Returning to
the above example, we might still have some questions about the negative $2,000 spending variance.
Among the possible explanations are: (1) a higher hygienist wage rate, (2) higher per-unit supply
costs, (3) more hygienist time per procedure, (4) more supply usage per procedure, (5) usage of
different kinds of supplies, and (6) higher fixed costs.
Since the answer most likely is contained in one or more of the above factors, we might wish to
explore the issue even further. If, for example, more hygienist time than budgeted were used, we
might wish to know why. Were there new hygienists on the job who required training and thus
were slower than anticipated in exams and cleanings? Or were there some patients for whom exams
and cleanings were more complex than others, resulting in more time needed to complete the proce-
dures? Or perhaps patients arrived late, and scheduling was disrupted, slowing the hygienists
down? And so on. While accounting techniques cannot answer all the above questions, the tech-
nique of variance analysis permits us to look into some of the possibilities.
VARIANCE ANALYSIS
Variance analysis is an accounting technique that permits a close examination of the difference
between budgeted and actual information. The technique allows us to break the difference into cate-
gories that are potentially meaningful for managerial action. In most organizations, the difference,
or variance, between budgeted and actual performance can be explained by five factors:
TCG318 • Note on Flexible Budgeting and Variance Analysis 3 of 10
_____________________________________________________________________________________________
1. Volume (number of units of activity (products or services)
2. Mix of units of activity
3. Revenue per unit of activity (selling price)
4. Rates paid for inputs (such as labor wages and cost per unit of raw materials)
5. Usage and efficiency of inputs (usage of raw materials and efficiency of labor)
Variance analysis can be used to determine the amount of the total change between budget and
actual that is associated with changes in each of these factors. Ordinarily, the variance for each fac-
tor is considered separately. There are three reasons for the separation: (1) each variance typically
has a different cause, (2) different variances usually involve different responsibility center manag-
ers, and (3) different variances require different types of corrective action. Thus, if responsibility for
different factors has been assigned to a different responsibility center managers, variance analysis
helps senior management to work with each responsibility center manager to determine the reasons
for the variance and the kinds of corrective action that might be taken.
Basic techniques for calculating these variances are shown below; more complex techniques are
described in cost accounting textbooks. In many situations, computer programs are available, or can
be developed easily on spreadsheet software, to perform the actual calculations.
A Graphic Illustration. The concept of variance analysis can be illustrated graphically. Con-
sider the example of labor costs. Total labor costs for a given employee or category of employees
can be calculated using the number of hours worked and the wage rate per hour. Assume that our
labor budget is $4,000, resulting from an estimate of 100 hours of work at $40 per hour. Graphi-
cally, this can be represented by a rectangle, with the vertical axis indicating the wage rate and the
horizontal axis the number of hours, as follows:
$/hour
$40
$4,000
100 hours
Assume now that our actual labor costs for the period in question were $6,000. A typical
budget report might indicate the variance as follows:
Item Budget Actual Variance
Labor cost $4,000 $6,000 $(2,000)
Although the report indicates a $2,000 negative variance, i.e., actual expenses greater than
budget, it does not indicate why the variance occurred. More specifically, in this instance, it does not
tell us whether the cause was a higher wage rate than anticipated, more hours than anticipated, or
some combination of the two.
If the variance were solely the result of a higher wage rate, it could be viewed as follows:
$/hour
$60
$2,000
$40
100 hours
TCG318 • Note on Flexible Budgeting and Variance Analysis 4 of 10
_____________________________________________________________________________________________
If, on the other hand, it were a result solely of more hours than budgeted, it could be viewed as
follows:
$/hour
$40
$2,000
Finally, if it were a result of a combination of both a higher wage rate and more hours, the vari-
ance could be depicted by several wage/hour combinations; one example is shown below:
$/hour
$50
$1,000 $200
$40
$800
1. For an expense variance related to use, subtract the actual use from the budgeted use and multiply the result
by budgeted rate. If actual use exceeds budgeted use, the result will be a negative number; if actual use is be-
low budgeted use, the result will be positive.
2. For an expense variance related to rate, subtract the actual rate from the budgeted rate and multiply the result
by actual use. If the actual rate exceeds the budgeted rate, the result will be a negative number; if the actual
rate is below the budgeted rate, the result will be positive.
1. For a revenue variance related to volume, subtract budgeted volume from actual volume and multiply the
result by budgeted selling price. If actual volume exceeds budgeted volume, the result is a positive number;
if actual volume is below budgeted volume, the result is negative.
2. For a revenue variance related to selling price, subtract budgeted selling price from actual selling price and
multiply the result by actual volume. If the actual selling price exceeds the budgeted selling price, the result
is a positive number; if the actual selling price is below the budgeted selling price, the result is negative.
Where ‘V’ stands for volume, ’P’ stands for selling price, and the subscripts ’a’ and ’b’ stand for
actual and budget.
Making the Computations. Let’s return now to the example illustrated above and perform
the calculations according to the above rules and formulas. Since there are no revenue variances, we
need not concern ourselves with them; we just need to calculate the expense variances. The compu-
tations are as follows:
Use (Budgeted - (Actual * (Budgeted
variance hours) hours) wage rate)
(Ub - Ua) * Rb
(100 - 120) * $40.00 = (800)
Rate (Wage) (Budgeted- (Actual * (Actual
variance wage rate) wage rate) hours)
(Rb - Ra) * Ua
($40.00 - $50.00) * 120 =($1,200)
TCG318 • Note on Flexible Budgeting and Variance Analysis 6 of 10
_____________________________________________________________________________________________
Graphically, the calculations look as follows:
Rate Variance
(Rb-Ra) * Ua
($40 - $50) * 120 = $1,200
$50 (Ub-Ua) * Rb
$1,200 (100 - 120) * 40 = $800
$40
$800
Example: The Haskell Manufacturing Company’s budgeted and actual material use for one department is as
follows:
Number of Material Direct Material
Units of Output per Unit Cost/Unit Total Cost
Budget 7,000 10 sq. feet $.20/sq. foot $14,000
Actual 6,000 12 sq. feet $.25/sq. foot $18,000
The factory manager is interested in obtaining a better understanding of the reasons behind the budget over-
run. To do so, we begin by preparing a flexible budget for the department—changing the volume from its
budgeted to its actual level while holding everything else constant at budgeted levels. We then can determine
what the budget would have been if we had known volume in advance. This budget then can be compared to
actual results, as follows:
Note that the volume variance (original budget - flexible budget) is a favorable $2,000 ($14,000
- $12,000). That is, if we had known our volume in advance, we would have budgeted $12,000
rather than $14,000. Since, to calculate the flexible budget, we held all other factors at the levels in
the original budget (10 sq. feet per unit and $.20 per sq. foot), this $2,000 positive variance is due
exclusively to the lower volume. It is favorable since it reduces expenses which, other things equal,
improves our income. (Of course, we have excluded revenue variances from the analysis. Assuming
we are paid on a per-unit basis, the fall in volume would have led to a negative revenue variance, in-
dicating a reduction in our income.)
In this example, as in many variance calculations, an unfavorable variance (i.e., one that lowers
the income of the organization) is shown in parentheses; it is sometimes called a negative variance.
A favorable (positive) variance does not have parentheses. Sometimes, unfavorable variances are
designated as “UF” and favorable variances are designated as “F”).
The spending variance (flexible budget - actual) is an unfavorable $6,000 ($12,000 - $18,000),
caused, as we can see from the data, by using two additional sq. feet per unit and paying $.05 more
per sq. foot. The combined result of the volume and spending variances is a total unfavorable vari-
ance of $4,000.
TCG318 • Note on Flexible Budgeting and Variance Analysis 7 of 10
_____________________________________________________________________________________________
We now can calculate the reasons for the spending variance. As indicated, above, a portion of
this variance is due to higher use (12 sq. feet vs. 10 sq. feet), and a portion is due to higher rate
($.25 per sq. foot vs. $.20 per sq. foot). Thus, the expense variances can be calculated as follows:
Use = (Ub - Ua)*Rb = (10 - 12)*($0.20) = ($0.40)
Rate = (Rb - Ra)*Ua = ($.20 - $.25)*12 = ($.60)
Note that these are variances per unit of output. To obtain the total variance, we need to multiply
these unit variances by the actual volume of output, i.e., the volume used in calculating the flexible
budget, as follows:
Variance per Unit * Actual Volume = Total
of Output of Output Variance
Use Variance ($.40) * 6,000 = ($2,400)
Rate Variance ($.60) * 6,000 = ($3,600)
Total ($6,000)
Alternatively, the calculations could be made in one step, as follows:
Variance (Budget - Actual ) * Other* * Actual Volume = Total Variance
Rate ($/sq. foot) (.20 - .25) * 12 * 6,000 = ($3,600)
Use (sq. feet) (10 - 12) * .20 * 6,000 = ($2,400)
Total ($6,000)
* “Other” in the case of the rate variance is the actual use of square feet per unit; in the case of the use
variance, it is the budgeted rate per square foot.
As this example demonstrates, variance analysis can help explain the reasons why actual ex-
penses deviated from budget. In the case of Haskell Manufacturing, we now can see that we saved
$2,000 in expenses as a result of producing fewer units, but our expenses increased by $3,600 be-
cause of higher prices for our raw materials and $2,400 because of a greater use of raw materials
per unit of output.
Mix Variances. The volume variance computed in the above problem assumed that every unit
of volume had the same variable expense associated with it. In many organizations, different types
of products and services have different unit variable expense amounts. When this is the case, the
volume variances are calculated using weighted averages of the variable expense amounts. If there is
a change in the budgeted proportions of the different product or service types, an output mix vari-
ance develops.
Input mix variances also arise with items such as raw materials and labor. This can happen if,
for example, a responsibility center manager uses a different mix of raw materials than budgeted, or
if the actual skill mix of labor differs from budget. Techniques for calculating input mix variances
are shown in most cost accounting textbooks.
Many organizations do not calculate mix variances. In these organizations, the output mix vari-
ance is automatically a part of the volume variance and the input mix variance typically is a part of
the rate variance (assuming the different types of raw materials or different skill levels for labor
have different rates).
Example: In a hospital, an output mix variance results from a change in the hospital’s case types (e.g., rela-
tively more coronary artery bypass surgery cases than influenza cases). An input mix variance comes about
when there is a change in the mix of services used to treat a given case type (e.g., more or different radio-
logical procedures ordered for each patient undergoing coronary artery bypass surgery). A second type of in-
put mix variance also could take place if the manager of, say, the radiology department used a mix of techni-
cians to take the x-rays that was different from the budget.
Managerial Uses of Variances. An important feature of variance analysis is the ability it gives
senior management to link managerial responsibility to changes in revenues and expenses. By way
of summary, Exhibit 1 lists each variance, and identifies in a general sense the department or re-
sponsibility center manager who controls it.
TCG318 • Note on Flexible Budgeting and Variance Analysis 8 of 10
_____________________________________________________________________________________________
As this exhibit suggests, operating managers ordinarily do not control the volume or mix of
services supplied, nor do they usually set wage rates for employees or control the rates paid for raw
materials and other items of expense. Consequently, variance analysis permits management to focus
attention on each individual item and the managers who control it.
Simply identifying the separate variances is not enough, however. Senior management needs to
know why a large efficiency variance arose, for example. It also needs to know what steps are under
way to correct unfavorable variances. Thus, by separating a total variance between budgeted and
actual performance into its individual components, senior management is in a better position to
discuss these steps with the appropriate responsibility center managers.
Limitations of Variance Analysis. It is important to remember that while variance analysis
can highlight the reasons for a deviation between budgeted and actual performance, and can do so
in terms of volume, rate, use, and mix, it cannot explain why a particular organizational unit was
more or less efficient than budgeted, or why volume was higher or lower than anticipated. As a
result, variance analysis can be a useful tool to assist managers in asking the right questions and in
identifying lower-level managers to whom those questions might be addressed. As with many other
accounting techniques, however, it should be considered only as a means to assist managers to learn
more about the activities of their organizations.
In using variance analysis for managerial action, it is important to recognize that few variances
can be interpreted independently from all other variances. A negative material use variance in the
factory, for example, may have arisen because the purchasing department bought some raw
materials of lower-than-anticipated quality. Thus, what appears as a positive rate variance for the
purchasing department, may have negative “downstream” consequences in the production effort.
In sum, used properly, a negative expense variance (rate or use) can be extremely valuable: it
can help to identify areas where operating improvements can take place and can allow managers to
see the financial consequences of their corrective actions. Used in a club-like way, however, it can
be quite threatening, and may even lead to unproductive conflict or reduced cooperation between
managers and their subordinates.
TCG318 • Note on Flexible Budgeting and Variance Analysis 9 of 10
_____________________________________________________________________________________________
PRACTICE CASE. OAK STREET INN
The Oak Street Inn was a small bed and breakfast located in a resort town. The inn charged a
nominal fee for a night’s stay. The following budgeted and actual figures for 1997 were available:
Actual Budget
Person-nights 10,000 12,000
Revenue $750,000 $720,000
Expenses 735,000 684,000
Income $ 15,000 $ 36,000
Questions
1. Reconcile the $30,000 increase in revenue using appropriate revenue variances.
2. Prepare a flexible budget for the Inn’s expenses. Use it and the revenue variances to
reconcile the change in income between budget and actual.
3. What additional information would you like to have to explain the difference between
the budgeted and actual income figures?
SOLUTION
Question 1
To reconcile the budgeted and actual revenue, we begin with a calculation of unit rates:
Actual Budget
Revenue $750,000 $720,000
Person-nights _10,000 _12,000
Rate per night $75.00 $60.00
We now can calculate the price variance and the sales volume variance, as follows:
Price variance [($75-$60) x 10,000] = $150,000 F
Volume variance [(10,000 - 12,000) x $60] = $120,000 UF
To reconcile the $30,000 increase, we begin with budgeted sales revenue, and use the variances to
convert it to actual sales revenue. The calculations are as follows:
Question 3
We have a good idea of the reasons underlying the revenue variance, principally a decline in
number of nights, but this was coupled with an increase in the price per night. We need more infor-
mation about the reasons for the increase in expense per night from $57.00 to $73.50. Among the
items of information we might like to have are: