ERECTION METHOD
PHÖÔNG PHAÙP LAÉP DÖÏNG
MS-01
LOCATION PROJECT
ÑÒA ÑIEÅM DÖÏ AÙN
MS-02
ORGANIZATION CHART
SÔ ÑOÀ TOÅ CHÖÙC
MS-03
Glover or protective sleeves/bao
tay haøn
A level ruler/ thöôùc nivo
Step 1: Checking the size of the axis's heart on the general space by steel yard and total station.
Böôùc 1: Kieåm tra tim truïc cuûa haïng muïc baèng maùy toaøn ñaïc.
Step 2: Checking the geometrical size of the steel rod's plane at crane brackets by total station.
Böôùc 2: Kieåm tra tim baûn maõ baèng maùy toaøn ñaïc.
Step 3: Checking type of anchor bolts (CO/CQ).
Böôùc 3: Kieåm tra loaïi bu loâng neo (CO/CQ)
Using steel bar from D8 to
D10 to support the steel
plate by welding./ Duøng
theùp troøn D8, D10 ñeå laøm
beä ñôõ cho baûn maõ ñònh vò,
lieân keát haøn.
Using the machine survey to check the center line, level. fix temperary steel plate with rebar steel by welding./ Install the anchor bolts on the hole
of steel plate/ INSTALL ANCHOR BOLTS
Duøng maùy toaøn ñaïc ñeå kieåm tra tim truïc, cao ñoä, chænh söûa baûn maõ, sau ñoù haøn coá ñònh beä ñôõ baèng saét. LAÉP ÑAËT BU LOÂNG NEO
Ñònh vò bu loâng neo vaøo loã baûn maõ
MS-04
Using a level ruler meters check the level of the Using a level ruler check the vertical of anchor bolts/ Fixing anchor bolts by rebar steel
top anchor bolts/ Duøng nivo ñeå caân chænh cao ñoä duøng nivo ñeå caân chænh ñoä thaúng bu loâng neo. Coá ñònh bu loâng neo baèng theùp thanh.
bu loâng neo
Step 5: Complete install anchor bolts. cover the bolt thread by sticking plaster / Böôùc 5: Hoaøn thaønh vieäc ñònh vò bu loâng neo, baûo veä ñaàu ren baèng baêng keo
ñen.
Cover the bolt thread by sticking plaster/ baûo veä phaàn ren bu
loâng baèng baêng keo ñen
- Preparing approval drawing/ Chuaån bò baûn veõ thieát keá trình duyeät
- Drawing anchor bolts plan/ Baûn veõ ñònh vò bu loâng neo
- Certificated: CO/CQ/ Chöùng chæ CO/CQ
- Necessary tools/ Caùc coâng cuï caàn thieát INSTALL ANCHOR BOLTS
LAÉP ÑAËT BU LOÂNG NEO
MS-05
S1 S14 S1 S14 S1 S14 S1 S14 S1 S14 S1 S14 S1 S14 S1 S14 S1 S14 S1 S14
Y11
8250

S14 S1 S1 S14

Y10
8250

D12 D12

D14 D14
Y9
8250

S14 S1 S1 S14

Y8
8250

S14 S1 S1 S14

Y7
8250

S14 S1 S1 S14
81250

Y6
8250

S14 S1 S1 S14

Y5
8250

S14 S1 S1 S14

Y4
8250

D12
D12

D14
D14
Y3
A - 301
8250

S14 S1 S1 S14

D12 D15 D15 D12

Y2
7000

Y1

5200 5200 7200 7200 7200 7200 7200 7200 5200 5200
64000

X1 X2 X3 X4 X5 X6 X7 X8 X9 X10 X11
MAËT BAÈNG LAÉP DÖÏNG
ERECTION PLAN
MS-06
- CRANE SELECTION - 25 TON CRANE: BOOM IS 30.5M, MAXIMUM RADIUS IS 16M=> MAXIMUM WEIGHT IS
3.35 TON./CHOÏN CAÅU 25 TAÁN: TAÀM VÔÙI 30.5M, BAÙN KÍNH LÔÙN NHAÁT 16M THÌ CAÅU ÑÖÔÏC TOÁI ÑA 3.35 TAÁN.
m
.5
0
=3
ax
Lm
Rmax =16m
SELECTION CRANE
LÖÏA CHOÏN XE CAÅU
MS-07
SELECTION CRANE
LÖÏA CHOÏN XE CAÅU
MS-08
4
3 1
ASSEMBLING RAFTERS
TOÅ HÔÏP KEØO
MS-09
TORQUE WRENCH
CAÀN XIEÁT LÖÏC
MS-10
ERECTION STEP 1
LAÉP DÖÏNG- BÖÔÙC 1
MS-11
ERECTION STEP 2
LAÉP DÖÏNG- BÖÔÙC 2
MS-12
ERECTION STEP 3
LAÉP DÖÏNG- BÖÔÙC 3
MS-13
ERECTION STEP 4
LAÉP DÖÏNG- BÖÔÙC 4
MS-14
ERECTION STEP 5
LAÉP DÖÏNG- BÖÔÙC 5
MS-15
ERECTION STEP 6
LAÉP DÖÏNG- BÖÔÙC 6
MS-16
ERECTION STEP 7
LAÉP DÖÏNG- BÖÔÙC 7
MS-17
INSTALL PANEL
LÔÏP TOÂN
MS-18