WORK RESUME 钻探工作日

PROJECT NAME 项目名称: PT.MERDEKA TSINSHANG INDONESIA (MTI)

DATE 日期: 7/19/2021

Project Progress 施工进度

Run by SPT/DPT
RIG Core
No Date Weather Hole No Size Day (m) Run (m) 标准贯
Number Recovery
序号 日期 天气 孔号 尺寸(mm) 当日钻孔 钻探深度 入/触探试
钻机编号 取芯收获率
深度 验

1 20210708 Rainny BH-15 SESTI-01 89 0.00 22.00 98% 11


2 20210708 Rainny BH-05 SESTI-02 89 0.00 22.00 97% 11
3 20210708 Rainny BH-10 SESTI-03 89 0.00 22.00 97% 11
4 20210708 Rainny BH-07 SESTI-04 89 0.00 21.00 97% 10
5 20210708 Rainny BH-16 SESTI-05 89 0.00 24.00 98% 12
6 20210713 Sunny BH-08 SESTI-01 89 0.00 24.00 97% 12
7 20210713 Sunny BH-09 SESTI-02 89 0.00 24.00 98% 12
8 20210713 Sunny BH-11 SESTI-03 89 0.00 20.00 96% 10
9 20210713 Sunny BH-17 SESTI-04 89 0.00 23.00 97% 11
10 20210716 Sunny BH-13 SESTI-05 89 0.00 22.00 97% 11
11 20210717 Sunny BH-12 SESTI-01 89 0.00 23.00 98% 11
12 20210717 Sunny BH-4 SESTI-02 89 0.00 22.00 96% 11
13 20210717 Sunny BH-02 SESTI-03 89 0.00 23.00 97% 12
14 20210717 Sunny BH-03 SESTI-04 89 0.00 22.00 98% 11
15 20210718 Sunny BH-01 SESTI-05 89 0.00 20.00 96% 10
16 20210718 Sunny BH-14 SESTI-01 89 0.00 23.00 97% 12
17 20210718 Sunny BH-06 SESTI-02 89 0.00 22.00 96% 11
钻探工作日报(20210719)
SIA (MTI)

Status Depth Into


Boulder
Start Date Finish Date Duration (Complete or Rock (m) 深 Comment
Position
开始时间 结束时间 持续天数 not) 是否完成钻 入岩石深度 备注
孤石位置
探 (m)

20210708 20210713 6 Complete 4


20210708 20210713 5 Complete 6
20210708 20210713 5 Complete 4
20210708 20210714 6 Complete 5
20210708 20210714 6 Complete 4
20210713 20210717 4 Complete 6
20210713 20210717 4 Complete 6
20210714 20210717 3 Complete 4
20210713 20210717 4 Complete 4
20210716 20210718 2 Complete 6
20210717 20210718 2 Complete 5
20210717 20210718 2 Complete 4
20210717 20210719 3 Complete 5
20210717 20210719 3 Complete 4
20210718 20210719 2 Complete 6
20210718 20210719 2 Complete 5
20210718 20210719 2 Complete 4