You are on page 1of 33

ISeB (2003) 1:231263 DOI: 10.

1007/s10257-003-0013-3

Information Systems and e-Business Management


Springer-Verlag 2003

Specifying information systems for business process integration A management perspective*


Joerg Becker, Alexander Dreiling, Roland Holten, Michael Ribbert
University of Muenster, Dept. of Information Systems, Leonardo-Campus 3, 48149 Muenster, Germany (e-mail: {isjobe|isaldr|isroho|ismiri}@wi.uni-muenster.de) Received: October 2002 / Accepted: April 2003

Abstract. Supply chain management and customer relationship management are concepts for optimizing the provision of goods to customers. Information sharing and information estimation are key tools used to implement these two concepts. The reduction of delivery times and stock levels can be seen as the main managerial objectives of an integrative supply chain and customer relationship management. To achieve this objective, business processes need to be integrated along the entire supply chain including the end consumer. Information systems form the backbone of any business process integration. The relevant information system architectures are generally well-understood, but the conceptual specication of information systems for business process integration from a management perspective, remains an open methodological problem. To address this problem, we will show how customer relationship management and supply chain management information can be integrated at the conceptual level in order to provide supply chain managers with relevant information. We will further outline how the conceptual management perspective of business process integration can be supported by deriving specications for enabling information system from business objectives. Key words: Business process integration, supply chain integration, supply chain process management, customer relationship management, managerial views, business objectives, data warehousing

1 Introduction In order to ensure customer satisfaction, knowledge about customers is vital for supply chains. In an ideal supply chain environment, supply chain partners

* This work has been funded by the German Federal Ministry of Education and Research (Bundesministerium fur Bildung und Forschung), record no. 01HW0196.

232

J. Becker et al.

are able to perform planning tasks collaboratively, because they share information. However, customers are not always able or willing to share information with their suppliers. End consumers, on the one hand, do not usually provide a retail company with demand information. On the other hand, industrial customers may hide information deliberately. Wherever a supply chain is not provided with demand forecast information, it needs to derive these demand forecasts by other means. Customer relationship management (CRM) thus provides a set of tools to overcome informational uncertainty. Ecient supply chain management requires the integration of business processes between supply chain partners. As a result, supply chain process management becomes necessary, focusing on global supply chain processes. One of the main resulting managerial activities is the optimization of supply chain processes beyond the borders of participating companies (Hammer 2001). Ecient optimization activities require information systems (IS), especially if they have reached the degree of complexity inherent in supply chain process management or customer relationship management. IS are vital for business process integration from an operative perspective, by enabling data exchange and integrated process ows between supply chain partners. On the other hand, IS support the managerial activities of monitoring and controlling supply chain processes. Decision support systems in particular are designed to assist managers in making better decisions (Todd and Benbasat 1999). In this context, IS are the enablers for creating competitive advantage (Johnston and Vitale 1988; Porter and Millar 1985). Because IS play such a central role, the perception, that IS form the vital backbone of an organization, instead of being simple business support tools (Henderson and Venkatraman 1999; Li and Chen 2001; Venkatraman 1994) has increased signicantly since the so-called information revolution (Porter and Millar 1985). Today, the development of information systems is faced with increased pressure from the business perspective. Ongoing discussions on the business value of IS (Hitt and Brynjolfsson 1996; Im et al. 2001; Mukhopadhyay et al.1995; Subramani and Walden 2001; Tam 1998) clearly point out that the risk awareness of IS development projects has changed. High costs and high overall failure rates of IS projects (Standish Group International 2001) have emphasized these discussions even more. Finally, a focus on IS project planning methods is needed, because inadequate IS project planning may lead to project failure. Keil states that a signicant number of IT projects (3040%) exceeding predened time restrictions and allocated resources, but never reaching their objective, will ultimately escalate and fail (Keil 1995; Keil et al. 2000). From an IT perspective, a broad variety of methods, architectures, and solutions aim at supporting the IS development process (Hirschheim et al. 1995). As an example, data warehouse architectures are well understood and data warehouse projects have been conducted over a long period. Nonetheless, many data warehouse projects fail for several reasons (Vassiliadis 2000). Some reasons for failure of data warehouse can hardly be inuenced, such as bad source data quality. Other reasons can be inuenced during the project, such as the involvement of management as targeted users of the system or management support both of which contribute to system quality and system success (Wixom and Watson 2001). The high failure rate, especially of

Specifying information systems for business process integration

233

complex IS projects, indicates that some so-called best practices for IS development are inadequate. There is a continually increasing need for methodological approaches that are theoretically suciently well-founded to handle complex IS projects (Jiang et al. 2001). The conceptual specication of information systems for business process integration from a management perspective, is an open methodological problem. Data warehouses support the management perspective technically, but their implementation is extremely costly. It is thus all the more important for the development of data warehouses to be eective and ecient. Eectiveness is achieved if the data warehouses support the desired managerial analysis. Eciency targets the amount of necessary resources for development. The critical factor for a data warehouse projects eectiveness is its value for future business. It is determined by the ability of a data warehouse environment to support essential managerial analysis. This paper aims at achieving eectiveness of data warehouses for business process integration. We introduce a specication approach for managerial views on business processes. These views are derived from business objectives, which are an essential output of managerial work. Approaches, focusing on managerial objectives as input for information systems specications have been found useful within the domain of requirements engineering (Rolland and Prakash 2000). Our approach supports the conceptual management perspective of business process integration. As an introduction to the topic, in Sect. 2, we rst provide an overview of supply chain management and customer relationship management and outline how these concepts can be integrated. Conceptually, we focus on the impact of information sharing on supply chains and describe how estimated information can replace shared information, if it is not shared by single supply chain partners. Technically, we provide an overview of enterprise application integration (EAI) for integrating business processes along supply chains. For the technical integration of business processes from a management perspective, we introduce the concept of data warehousing and describe a framework for supply chain process management. In Sect. 3, we introduce the MetaMIS approach for the specication of managerial views on business processes as a support tool of the conceptual management perspective. The problem of deriving MetaMIS specications is targeted by the denition, decomposition, and transformation of business objectives into MetaMIS model constructs. We discuss the theoretical background of business objectives, integrate them into MetaMIS, and introduce an elaborate example of an objective system. Section 4 deals with transforming the objective system into MetaMIS specications, which can be used to derive data warehouse structures. Finally, the ndings are summarized and future prospects discussed. 2 Integration of business processes 2.1 Supply chain management The objectives of supply chain management are the design, operation and maintenance of integrated value chains, so as to satisfy consumer needs most eciently by simultaneously maximizing customer service quality

234

J. Becker et al.

(Bechtel and Jayaram 1997; Christopher 1998; Hewitt 1994). SCM is currently accepted as a concept integrating inter-organizational business processes. In order to fulll its objective, it must include other concepts such as ecient consumer response (ECR), quick response, continuous replenishment and customer relationship management (Bechtel and Jayaram 1997; Stadtler 2000). The design of supply chains requires the specication of business processes and supply-chain-wide planning routines. These specications are imperative for the development of information systems which form the backbone of any supply chain integration (Miller 2001; Rohde and Wagner 2000). Information systems are widely perceived as the enabler for supply chain integration (Bechtel and Jayaram 1997; Hewitt 1994; Meyr et al. 2000). Partners in a supply chain have to perform their activities in the most ecient way, by concentrating on their core competencies (Christopher 1998). The Supply Chain Operations Reference (SCOR) model provided by the Supply Chain Council, is a reference model for structure, processes, and information ows within an inter-organizational supply chain (SCC 2001). The SCOR model contains measures for operational control and best practices for supply chain design. Five main processes characterize the SCOR model: Plan, Source, Make, Deliver and Return. The SCOR model is structured in four hierarchical levels. The main processes are dened at the top level (level one). At the second level, these main processes are clustered into process categories which depend on the underlying process model. There are three relevant business categories for the SCOR model at this level. These are Make-to-Stock, Make-to-Order, and Engineer-to-Order. Additionally, at level two, some enabling processes are identied. The highest level of detail within the SCOR model is the third level, where each process category from level two is rened by inter-related process elements. The processes and their relationships are dened by means of tables. Level four is not covered by the SCOR model, since it would contain a detailed description of the internal business processes of the cooperating enterprises. As a result, the SCOR model needs to be extended by a framework adjusting internal and external business processes. This enables the alignment of an existing process infrastructure with inter-organizational processes that result from the SCOR approach. Parallel to the SCOR model, several standardization initiatives have published documents that focus on the design of supply chain processes. The RosettaNet consortium, for example, is a non-prot group of more than 400 companies in the information technology and electronics domain. It aims at standardizing the trading networks between these companies, by providing standards for business documents such as purchase orders. Furthermore, so-called partner interface processes (PIPs), e.g. acknowledgement of receipt, serve the purpose of dening process interaction between trading partners (RosettaNet 2003). 2.2 Impact of information sharing on supply chain management Information sharing is one of the basic supply chain management concepts. Evidence of the positive eects of information sharing can be found through various approaches, where savings are estimated in an information sharing

Specifying information systems for business process integration

235

supply chain environment using simulation models (Aviv 2001; Cachon and Fisher 2000; Gavirneni and Fisher 1999; Lee et al. 2000). The focus of this section is not to quantify the eect of information sharing along supply chains and thus proving the eect, but to assume a positive eect and justify it with simple model-based explanations. The integration level of material and inventory management and the structure of order costs are the main parameters of supply chain management (Christopher 1998). We illustrate this by using a simple model of inventory development and the eects of an integrated material and inventory management on order costs (see Fig. 1). Two variables are relevant for calculating the economic ordering quantity. These variables are warehousing costs and xed costs per order (in the interest of simplicity, costs per unit are assumed to be constant and will therefore not be considered; the results would be the same if discounts on certain order sizes were deducted).

Fig. 1. Eects of information on material and inventory management and ordering costs. Source: (Holten et al. 2002)

236

J. Becker et al.

Warehousing costs increase linearly with increasing order quantities, since they are linked directly to the inventory level. Fixed costs per order decrease with an increasing order size, because xed costs are spread over more units. The total cost function is the sum of these two functions as shown in the top left model of Fig. 1. The development of inventory over time is shown in the top right model of Fig. 1. A certain safety stock is required to guarantee production in cases of supply shortages. For a start, we assume stock above this level. Furthermore, we assume a linear consumption function over time. Based on a given delivery time, we can determine the reorder point for the economic ordering quantity. It is important to understand that information itself has no direct business value. The eects of information on business are always indirect. Two relevant eects of improved information availability for the management of supply chain processes can be explained using the simple model in Fig. 1. Firstly, information availability enables an enterprise to reduce the average stock level by reducing safety stocks and delivery times. Using information correctly, ensures that required materials can be delivered on time. This eect is based simply on the exchange of information between partners during the course of the business process (see the center model in Fig. 1). If production planning systems of manufacturers and scheduling systems of suppliers are provided automatically with point-of-sale information from the retail partner, planning tasks can be performed with improved quality. This results in a reduction of safety stocks and delivery times, since delivery time entails not only shipment time, but also the time taken to organize the entire business transaction. Furthermore, delivery time can be inuenced in maketo-order scenarios by the lag until production for an order commences and the time it takes to produce, pack, and deliver the products to the place the logistics partner can collect them. The structure of production, logistic and organization times can be optimized and decreased dramatically. The eects discussed so far, clearly provide a case for an integrated material management such as vendor managed inventory (VMI). Secondly, information availability enables an enterprise to reduce the average stock level by increasing order frequencies. This eect is based on the duration of contracts between supply chain partners. Based on long-term agreements, the costs per order can be reduced, because some uncertainty for suppliers and manufacturers is eliminated. In the simple model introduced in Fig. 1, this results in reduced costs and a reduced optimal ordering quantity (see bottom left model in Fig. 1). This implies increasing order frequencies, which is economically logical (see bottom right model in Fig. 1). To benet from this eect, which leads to a reduced average inventory level because of reduced order sizes, an integration of material and nance management is necessary. Throughout the paper, we will use a consistent example to explain our concepts. Our example company is part of a supply chain which decided to decrease delivery times, in order to increase customer satisfaction. Products are directly shipped from company warehouses according to customer orders. The company stocks a small number of products and attempts mainly to produce just-in-time. An example of a managerial objective focusing on proting from the positive eects of information sharing along supply chains

Specifying information systems for business process integration

237

is the following (the discussion on management objectives and their role in specifying MIS will be continued in more detail in Sect. 3):  Objective Delivery Time Reduction of Business Unit Automotive Supplies: Decrease the average delivery time of all products of business unit Automotive Supplies to a maximum of 24 h within the next year. Most supply chains can potentially achieve higher customer satisfaction by reducing the delivery times of ordered products. The additional eort required to decrease the delivery times, can be justied with the savings from decreased stocks along the supply chain. The savings can be passed on to the customer, invested in improving customer service or in strengthening the supply chain. To decrease delivery times of ordered products, the eciency of operative business processes along the entire supply chain needs to be increased. A major managerial responsibility is to dene business objectives and undertake the necessary steps to deploy improved business processes. Furthermore, control mechanisms need to be implemented to monitor the degree to which business objectives have been reached. 2.3 Customer relationship management Every supply chain ultimately provides an end consumer with a product or service. The end consumers decision to buy or not to buy a product inuences a supply chains economic success, and is thus the critical element. In the interest of the entire supply chain and especially the nal partner interfacing with the end consumer, this decision needs to be inuenced positively. Customer satisfaction can be addressed in several ways. In the 1990s, a new strategic approach called relationship marketing evolved. Originating in the service or industrial marketing literature, relationship marketing focuses on the development and cultivation of long-term protable relationships (Berry 1983; Gronroos 1994; Peck et al. 1999). Following Payne, et al. (Payne et al. 1998), relationship marketing considers relationships in every direction. The customer relationship management approach, focuses only on prot-enhancing relationships with customers (Ahlert and Hesse 2002; Greenleaf and Winer 2002). Based on the notion of a customer life cycle (Ives and Learmonth 1984), a relationship can be seen as an investment, where, for example, customer relationship campaigns are conducted to achieve positive customer values at the end of the life cycle. Depending on the dierent phases of the customer life cycle, recruitment, retention, and recovery (Bruhn 2001), dierent needs of the customers occur and must be satised. A consideration of the special needs of customers, combined with individualized marketing campaigns, leads to higher sales (Gillenson et al. 1999; Stone et al. 1996) and increased retention of existing customers (Buchanan and Gilles 1990). Keeping existing customers is about ve times more protable than nding new ones (Buchanan and Gilles 1990; Reichheld 1996). Modern IS, using large amounts of customer data, enable CRM and one-to-one marketing on a mass scale (Gillenson et al. 1999). Deriving knowledge about customers is one of the main challenges confronting analytical CRM. Usually, customer buying behavior is analyzed to forecast potential products, points of time, or quantities of future orders.

238

J. Becker et al.

This knowledge is used mainly by companies in order to provide customers with what they require at a given time and place. Furthermore, this knowledge is useful for manufacturing industries, because they can adjust their product development to market requirements. In turn, this may lead to decreased delivery times, which as pointed out above, contributes potentially to customer satisfaction. 2.4 Impact of CRM information on SCM As indicated above, the design of supply chains requires the specication of supply-chain-wide planning routines as a special component of the development of information systems. The concept of advanced planning incorporates integrated supply chain planning as a core concept. Advanced planning systems (APS) support this integrated planning task (Rohde 2000). Demand planning data and demand fulllment data at the sales stage, is fed back into distribution planning and transport planning at the distribution stage. Ideally, industrial customers are able to provide their suppliers with precise demand information, obtained from collaborative forecasting with their industrial customers. Unfortunately, end consumers generally do not provide retail companies with demand information, and some industrial customers are unable or unwilling to provide demand information. Missing demand information within supply chains, prohibits the notion of integrated supply chains. To compensate for potential losses which arise from non-integrated supply chains, CRM information can substitute missing demand information to a certain degree. For example, if the component supplier is neither able nor willing to share demand data, business processes between the component and part supplier need to be optimized using CRM methods initiated by the part supplier. At the retail stage, CRM provides a set of tools for increasing the forecasting quality of retailers. Using CRM information within the supply chain, potentially maximizes the end consumers satisfaction in several respects. Firstly, eciently derived high-quality forecasting information shared with suppliers enables stock and cost reductions within SCM. Secondly, the out-of-stock problem can be reduced through higher demand data quality, given that demand will be satised. Thirdly, the bullwhip eect resulting from non-stationary demands can be reduced if the entire supply chain is provided with high-quality demand data for the nal supply chain partner. If the quality of forecasted customer demand is suciently high as to almost correspond with actual demand, the eects of sharing this information will be as they have been proven for information sharing supply chains (Aviv 2001; Cachon and Fisher 2000; Gavirneni and Fisher 1999; Lee et al. 2000). Apart from customer-related information gained by CRM, market-related information is required within the strategic planning of a supply chain. Market research is a tool for decreasing the risk of marketing and resulting product development decisions (Proctor 1997). Whereas CRM focuses on forecasting the demands of known customers, market research provides information on markets. Both CRM information and market research information need to be provided to the preliminary supply chain, in order to increase the quality of operative demand-planning processes. For this

Specifying information systems for business process integration

239

purpose, CRM should be applied to industrial customers within the supply chain. Additionally, market research is required at every stage of the supply chain. Figure 2 contains the information ows necessary to implement this concept. In Sect. 2.2, an example of a managerial objective has been introduced, that aims at proting from the positive eects of information sharing along supply chains. The denition of the objective remains constant in a noninformation sharing environment. If the customers of business unit Automotive Supplies are end consumers, they will not share demand information with our example company. Demand information may also be not available, if industrial customers are unable or unwilling to share demand information. In any event, the company needs this demand information and therefore needs to implement forecasting analysis tools. The set objective of decreasing delivery times, which are aected partially by the time required to proceed with the customer order, its production, packing, shipment, is still that of decreasing delivery times. The dierence lies in the application of methods of analytical CRM, instead of information sharing as a basic concept of SCM at the operative level. 2.5 Technical integration of CRM and SCM data The integration of supply chain management and customer relationship management can be assisted by ecient information systems and information technology. In order to support the integration of SCM and CRM, the implementation of IS needs to target the operative as well as the management perspective of the integrated concepts. From an operative perspective, enterprise application integration aims at combining IS of business partners by transmitting data between them (Buhl et al. 2001). Even if these IS are highly heterogeneous, the data in exchanged documents must not be changed, misinterpreted, or lost. Data exchange is

Raw Material market

Basic Material market

Parts market

Component market

End consumer market

Raw material supplier

Basic material supplier

Part supplier

Component supplier

Product assembler

End consumer

Legend Supply chain information CRM demand information Market research

Fig. 2. Supply chains and markets

240

J. Becker et al.

facilitated by schema matching mechanisms. Several protocols and document standards are used for EAI purposes, such as XML or EDIFACT. Software products such as Microsofts BizTalk Server, provide a software platform for exchanging business documents. Technically, data can be exchanged using the Internet. From a management perspective, data warehouses provide an accepted architecture for the development of decision support systems. A data warehouse stores materialized views on relational representations of business processes, in order to provide relevant information for managerial decisions (Inmon 1996; Inmon and Hackathorn 1994; Inmon et al. 1997). The warehouse is the central layer of a theoretically ideal three-layer architecture connecting online transaction processing (OLTP) systems and components enabling online analytical processing (OLAP) (Becker and Holten 1998; Chaudhuri and Dayal 1997). Contributions within the eld of data warehousing range from technical discussions of databases and algorithms enabling OLAP functionality (Agarwal et al. 1996; Cabibbo and Torlone 2001; Codd et al. 1993; Colliat 1996; Gyssens and Lakshmanan 1997; Vassiliadis and Sellis 1999) to studies on the information search behavior of managers (Borgman 1998) and to papers concentrating on methodologies for information systems development (Golfarelli et al. 1998). Recently, methodological contributions (Jarke et al. 1999; Jarke et al. 2000) propose a quality-oriented framework for data warehouse development. OLAP supports adequate navigation for the purpose of managerial analysis, through so-called multi-dimensional information spaces. Business process data from OLTP systems are the source of OLAP analyses. Typically, the integration of OLTP systems and a data warehouse is based on tools performing extraction, transformation, and loading tasks (ETL) on the source data (Inmon 1996; Widom 1995). At an intra-organizational level, business-supporting information systems produce data about business transactions. For the purpose of CRM and logistical optimization (as the intra-organizational fundament of interorganizational SCM), this data can be analyzed, enabling analytical CRM and logistic optimization. Due to the fact that this data is encoded in various operational data sources, there needs to be an integrating layer to derive relevant managerial information from these data sources. This can be achieved by local data warehouses. From these data warehouses, several management reports can be generated, which support corresponding managerial activities. To support supply-chain-wide information sharing, data from operational data sources of single supply chain partners, need to be integrated in a supply-chain-wide data warehouse. This data warehouse then serves as a basis for generating managerial reports at the inter-organizational as well as intra-organizational levels. Figure 3 shows an architecture enabling the integration of inter-organizational and intra-organizational data for the purpose of supply chain process management analysis. The architecture serves analytical CRM as well as analytical SCM, implying operational CRM and SCM components within the local information systems environments. Thus, the management reports at the inter-organizational and intra-organizational levels, contain CRM and SCM information, enabling the optimization of business processes from both perspectives.

Specifying information systems for business process integration

241

Fig. 3. Technical integration of CRM and SCM data

Even if the data warehousing architecture is well understood, data warehouse success is linked directly to its additional use for the business. Additional use can be achieved by supporting the process of providing essential managerial analysis more eciently than in the past. For this reason, the development of data warehouses needs to be supported from a conceptual perspective, an unresolved methodological problem, which is considered in the next section. 3 Business objectives and managerial views on business processes As depicted in Sect. 2, supply chain management and customer relationship management enable the integration of business processes at a conceptual level. SCOR and RosettaNet are approaches for implementing supply chains from an operative perspective, supporting processes of trading networks. From a technical perspective, business process integration is targeted by several communication protocols, architectures, concepts, and software

242

J. Becker et al.

products. As one of the concepts, EAI aims at integrating information systems of business partners. From a management perspective, data warehousing provides an accepted architecture for managerial views on business processes. Data warehouses can be used for managerial intraorganizational as well as inter-organizational analysis. Even if the introduced concepts are well-understood by researchers and practitioners, there remain resolved methodological problems. Besides the operative and technical perspective, business processes have to be integrated from a conceptual management perspective. For this purpose, in this section we discuss the specication of managerial views on business processes with MetaMIS. Furthermore, we provide a detailed introduction to the denition of business objectives, which will be integrated into MetaMIS to create MetaMIS models. Finally, a detailed example is introduced, consisting of an objective system. The objectives will be decomposed to their dening components, which will be transformed into MetaMIS models in a comprehensive discussion in the next section. 3.1 Specication of managerial views with MetaMIS From a conceptual management perspective, the MetaMIS approach aims at specifying managerial views on business processes (Holten 2003). The MetaMIS approach is anchored by a meta model featuring several concepts necessary to dene a specication language for managerial views on business processes and activities (Becker and Holten 1998; Holten 1999, 2003). MetaMIS models feature a degree of formality, which allows for deriving data warehouse structures from these models (Holten 2003). The MetaMIS approach has been validated at the Swiss reinsurance company Swiss Re, where the managerial activity Group Performance Measurement has been modeled (Holten et al. 2002). MetaMIS commences with the denition of dimensions (concept Dimension). Dimensions are dened by hierarchically-ordered dimension objects (concept Dimension Object), e.g., products, customers, points in time, or customer sales representatives. Based on the enterprise theory of Riebel (1979), dimension objects can be understood as entities subject to managerial analysis. In order to prevent information overow, subsets of existing dimensions (dimension object hierarchies) need to be dened. For this purpose, dimension scopes and dimension scope combinations are introduced (Holten 1999, 2003; Holten, et al. 2002) (concepts Dimension Scope and Dimension Scope Combination). Dimension scopes are sub-trees of dimensions. Dimension scope combinations comprise dimension scopes, creating navigation spaces for managerial analysis. Dimension scope combinations dene a space of multi-dimensional objects. Referring to Riebels enterprise theory, the concept Reference Object denotes vector types within this space. Reference objects are measures, processes and states of aairs which can be subject to arrangements or examinations on their own (Riebel 1979, p. 869). The next concept required is Aspect. Aspects can be either qualitative (concept Qualitative Aspect) or quantitative (concept Quantitative Aspect, Synonym to Ratio). Management ratios are vital for specifying information in management processes. They belong to the class of interval or ratio

Specifying information systems for business process integration

243

measures (Adam 1996; Hillbrand and Karagiannis 2002; Holten 1999). Ratios are core instruments for measuring the value of companies (Copeland et al. 1990), the business performance (Eccles 1991; Johnson and Kaplan 1987; Kaplan and Norton 1992, 1996, 1997; Lapsley and Mitchel 1996) and for analyzing the nancial situations of enterprises (Brealey and Myers 1996). Synonyms found in the management accounting literature are, e.g., operating ratio, operating gure, performance measure. Ratios like gross margin dene dynamic aspects of business objects and have clearly specied meanings. Their calculation is dened by algebraic expressions (e.g. prot = contribution margin xed costs). Qualitative aspects can be used, if business facts are measured by categorical values, such as eciency or quality (Becker, Dreiling, Ribbert 2003). They belong to the class of nominal or ordinal measures. Aspects are organized into aspect systems (concept Aspect Systems). Aspect systems are structured hierarchically according to an aspects importance for a managerial analysis. A drill-down logic is implied for aspect systems, which is to be separated especially from an algebraic denition of ratios. Aspect systems are assigned to dimension scope combinations (navigation spaces), in order to create business facts (concept Fact), such as the number of products sold in a certain region by a specic customer sales representative or the turnover achieved with one customer. Business analyses usually require a comparison of business facts. In order to conduct such dynamic analyses, fact calculations can be dened, involving a variable number of business facts which are processed according to calculation expressions (Holten and Dreiling 2002) (concept Calculation Expression). Examples of fact calculations are the prot-growth rate of a business group or the variance between planned and actual turnover of a product group. Dimension scope combinations, aspect systems, and fact calculations are combined into an Information Object. Thus, it is a relation between a set of reference objects and a set of aspects with the element types being business facts. Figure 4 shows a segment of the meta model underlying the MetaMIS approach. An unresolved methodological problem is how the crucial modeling constructs such as dimensions, dimension scopes, dimension scope combinations, aspects, and information objects are derived. In the next section, we will show how business objectives can be used to derive MetaMIS structures together with personnel from various business domains. This closes the loop from dening business objectives to monitoring if they have been accomplished. 3.2 Objectives from a business perspective The designer of an information system for managerial analysis needs to know which managerial analysis the systems must to support, information that only managers or management supporters can provide. To assist the complex process of obtaining information requirement models, e.g., MetaMIS models (Holten 1999), we will show, how managers information requirements can be derived from corporate objectives. With respect to the integration of objectives into the MetaMIS approach, we discuss several objective types found in the literature. Parallel to this, we introduce meta

244

J. Becker et al.

Reference Object Structure (0,m) (0,m) Combined Reference Object CRO-Coordinates (0,m)

Dimension Object Hierarchy (0,m) (0,m) (0,m) CE-Ot-As Dimension Object (0,m) (1,1) (1,m) Calculation Expression (1,m) DO-DS-AS (1,m) (0,1)

Operator

(1,m) Operand (0,m) CE-On-As Dimension Scope

(0,m) u,t Fact

DS-DSC-AS (0,m) Aspect (0,m)

(1,m) A-AS-As u,t Quantitative Aspect (Ratio)

Dimension Scope Combination

(0,m) Aspect System (0,m) Qualitative Aspect (0,m)

Information Object Dimension Grouping (1,m)

D-DG-AS

(1,1) Dimension (1,m) (1,m) DO-D-AS

D-HL-AS

(1,m)

DO-D-HL-AS

Hierarchy Level

(1,1)

Legend
<Identifier>

Entity Type

<Identifier>

Reinterpreted Relationship Type

Specialization (Types: - u unequivocally, e equivocally - t total, p partial)

<Identifier>

Relationship Type

(min,max)

Connector ( - min minimum cardinality, - max maximum cardinality)

Fig. 4. Segment of the MetaMIS meta model. Source: (Holten 2003)

model concepts for the dierent objective types in order to construct a meta model of objectives. The base concept introduced is Objective. According to Porter (Porter 1979), the most abstract and general business objectives are dened in a business strategy. A business strategy deals with defending and strengthening a competitive business position. It must focus on ve contending forces (Porter 1979), which are threats of entry, powerful suppliers, powerful buyers, substitute products, and jockeying for position. Based on the identication of these forces, the company is able to dene its strengths and weaknesses. Knowing the strengths and weaknesses, a strategy can be formulated consisting of the three major aspects of positioning the company within the industry, inuencing balance and forces, and exploiting industrial changes. Following Porter (Kotler 1999; Porter 1996), strategic

Specifying information systems for business process integration

245

positioning targets performing dierent activities than competitors or performing similar activities of competitors in dierent ways. Operational eectiveness is achieved, if activities are performed better than the ones of competitors. Clearly dened strategic objectives and operational eectiveness are essential to superior performance and long term protability (Porter 1996). In order to take strategic objectives into account for constructing our objective meta model, we divide Objective into two specializations of which one is the entity type Strategy, General Conditions, and Guidelines. Hierarchically structured objectives can be represented as a pyramid, where the degree of measurability increases towards the bottom (Steiner 1969). Three dierent hierarchical levels form the top of the pyramid (strategy or general conditions). These are business mission (Meert 2000), corporate identity (Birkigt et al. 1993), and policies and practices (Anso et al. 1990). Following this categorization, we introduce the meta model construct Business Mission, Corporate Mission, and Policy and Practice. A major diculty of business strategies is their non-operational character. Operational objectives are dened by a certain measure, level, time frame, and reference (Adam 1996). Objectives need to be dened operationally in order to be manageable (Latham and Kinne 1974). Usually, business strategies are not measurable. Nonetheless, operational eectiveness requires the denition of operational objectives. In order to align business strategy and operational eectiveness, the business strategy needs to be broken down into operational objectives in several steps. In the words of Porter the essence of strategy is in the activities (Porter 1996), which means that operational objectives enable management to do the right things (dened by the business strategy) right (by derived operational objectives). Types of operational objectives that can be derived from business strategies are general goals, organizational unit goals, business unit goals, and marketing-mix-based goals. General goals specify aggregated operational objectives. They can be seen as benchmarks, which help managers from dierent organizational units to specify their objectives, such as revenue or cost on a corporate level (Kupsch 1979). Organizational unit goals specify general goals at an organizational unit level. Examples are planned production department costs or planned sales department revenues (Meert 2000). Business unit goals break down organizational unit goals to the business unit level. Marketing-mix-based goals further split up business unit goals into, e.g., planned prices, promotions, places, and products. Operational Objective is introduced to the objective meta model as the second specialization of Objective. Both existing specializations are unequivocal and total, meaning that every objective either has an operational or a strategic character. Operational Objective is devided unequivocally and totally into the specializations General Goal, Organizational Unit Goal, Business Unit Goal, and Marketing-Mix-Based Goal. The Balanced Scorecard is another approach that breaks down general business objectives into operational ones (Kaplan and Norton 1992). The BSC is a top-down approach that provides managers with a comprehensive framework, translating a companys strategic objectives into a coherent set of performance measures (Kaplan and Norton 1993). Four dierent perspectives are provided. Information about traditional nancial measures are enhanced by measures of customer performance, internal processes, and

246

J. Becker et al.

innovation and improvement activities (Kaplan and Norton 2000). Thus, the BSC enables balancing between external measures such as income or revenues and internal measures like product development and learning (Kaplan and Norton 1993). Furthermore, the BSC shows cause-and-eects links, which avoid trade-os among dierent success factors. For constructing the objective meta model we need to structure objectives. Objectives can be organized hierarchically. Each objective can be part of more than one hierarchy, which leads technically to an Objective Structure as a relationship type connecting Objective with itself. We can furthermore add specializations, e.g., the categorization of Objective into the more commonly used terms Strategic Objective, Tactical Objective, and Operative Objective. The introduced specializations, however cannot be regarded as an exhaustive list of possibilities. Other specializations may exist beyond theses introduced. Depending on the modeling purpose they can be specied. Figure 5 contains the meta model constructs that have been introduced above. Objective systems, especially large ones, face a major problem: they are usually inconsistent, which means that achieving one objective, inevitably leads to the failure of another. The inherent problem, as to how strategies are

Objective Structure (0,m) (0,m) Objective

u,t

Strategy, General Condition, and Guideline

u,t

Business Mission

u,t

Strategic Objective

Corporate Identity

Tactical Objective

Policy and Practice

Operative Objective

Operational Objective

u,t

General Goal

Organizational Unit Goal

Business Unit Goal

Marketing-MixBased Goal

Legend
<Identifier>

Entity Type

<Identifier>

Reinterpreted Relationship Type

Specialization (Types: - u unequivocally, e equivocally - t total, p partial)

<Identifier>

Relationship Type

(min,max)

Connector ( - min minimum cardinality, - max maximum cardinality)

Fig. 5. Specializations of objective including objective structure

Specifying information systems for business process integration

247

formed in organizations, is targeted by major research projects in the management research community (Allison 1971; Anso 1965; Barbuto Jr. 2002; Barnard 1938; Granger 1964; Mintzberg 1973). However, we do not aim to support the denition of consistent objective systems. In fact, we assume that inconsistencies can be overcome by the approaches presented in the literature. We do support the monitoring of given objectives by comparing them to actual business developments. 3.3 Integration of objectives into MetaMIS Thus far, the MetaMIS approach for the specication of managerial views on business processes has been introduced, followed by a discussion on business objectives. To integrate business objectives into MetaMIS, the set of meta model constructs introduced in the last section, needs to be extended and connected to already existing MetaMIS modeling constructs. In contrast to non-operational objectives, operational objectives can be integrated into MetaMIS, because their dening components measure, time frame, reference, and level can be transformed into MetaMIS constructs. In order to measure an objective, we introduce the construct Objective Measure. Dierent objectives may have dierent objective measures. Financial ratios like earnings or costs are represented by the construct Quantitative Measure. Qualitative aspects such as eciency or quality are subsumed by the construct Qualitative Measure. Quantiativ and qualitative measures are generalized into the construct Aspect. Operational objectives need to be achieved within a certain time frame, e.g., one year. Furthermore, operational objectives consist of another mandatory component, a reference. Every objective must refer, for instance, to a product, product group, service, customer, or management unit. The construct Reference Object represents both time frame and objective reference as required components for dening operational objectives. Finally, the construct Objective Level is necessary to dene a quantitative or qualitative level to which the objective has to be accomplished. The objective level combines an objective measure with a reference object. Having dened the objective measure, e.g., average delivery time and a reference object such as business unit Automotive Supplies, any product, we have to set the average delivery time of any product of the business unit Automotive Supplies to a value of, e.g., 24 h. The meta model consisting of the introduced constructs and their relationships is shown in Fig. 6. MetaMIS already contains the constructs Reference Object, Quantitative Measure, and Qualitative Measure (see Sect. 3.1). The decomposed objective references will be transformed into dimension objects (see Fig. 4) which will constitute dimensions. Thus, we derive an initial set of information on the construction of navigation spaces for management analysis, which will be discussed in more detail in Sect. 4. 3.4 Dening and decomposing business objectives A sample case After we discussed the denition of operational objectives consistent with a business strategy, described a way to decompose them into their dening

248

J. Becker et al.

components, and structured these components within a model, we now introduce a comprehensive case. The main objective has been introduced in Sect. 2.2 and is consistent with the general goal of long-term protability according to the management approach CRM:  Objective Delivery Time Reduction of Business Unit Automotive Supplies: Decrease the average delivery time of all products of business unit Automotive Supplies to a maximum of 24 h within the next year. The time frame for the objective is next year. Furthermore, it refers to all products of business unit Automotive Supplies. The time frame combined with the reference constitutes the reference object. Average delivery time is a quantitative measure. If a time value (not a time frame) is assigned to the reference object, this value becomes a business fact. Since delivery time is composed of production time and shipment time, the objective is broken down into two sub-objectives. The rst sub-objective has been set as follows:  Objective Increase Production Eciency: Increase production eciency at assembly line V8 engine in factory alpha from level 8 to level 9 within the next year. As in the case of the main objective, the time frame is next year. The reference of the objective is assembly line V8 engine in factory alpha. Eciency is a qualitative measure, which can be expressed by the values (categories) zero to ten. The eciency categories can be calculated by algorithms, which consider various inuencing variables or are derived by an auditing process, where trained personnel set the eciency based on their observations. The second sub-objective to decrease delivery times refers to the shipping eciency:  Objective Increase Shipping Eciency: Increase shipping eciency of products shipped out of factory alpha by any logistic partner from level 8 to level 9 within the next year. The time frame again is next year. It refers to factory alpha, any logistic partner, and any product and is measured by the qualitative measure eciency. Both sub-objectives are measured qualitatively. In order to derive the eciency measures for both sub-objectives deterministically, each is split up again into three sub-objectives. Production eciency is described by the following objectives:  Objective Rejection Rate Reduction: Decrease the average rejection rate of product group Original Equipment Engines products at assembly line V8 engine in factory alpha from 0.4 to 0.2% within the next year, without increasing the rejection rate of other product groups products assembled at this line,  Objective Machine Defect Rate: Decrease average machine defect rate of machines at assembly line V8 engine in factory alpha from 0.7 class A defects per week to 0.3 within the next year,  Objective Lead Time Reduction: Achieve an average lead time reduction during production of any single product of product group Original Equipment Engines at assembly line V8 engine in factory alpha from 256 min to 240 min within the next year. On the other hand, shipment eciency is broken down into these three objectives:

Specifying information systems for business process integration

249

 Objective Decrease Just-In-Time Deviation of Logistic Partners: Decrease the average just-in-time deviation of any logistic partner for any product shipped from factory alpha with an appropriate transportation to 5 min within the next year (Just-In-Time deviation is the time dierence between planned and actual collection of a customer order by a logistics partner),  Objective Decrease Packing Time: Decrease the average packing time of factory alpha warehouse workers for any customer order to one hour within the next year,  Objective Reduce Warehousing Costs: Reduce the total costs of factory alpha warehouse to e 500,000 within the next year. These six objectives can each be decomposed into their dening components. Table 1 gives an overview of the entire objective system by decomposing each objective to time frame, reference, measure, and level. The dening components of decomposed operational objectives are structured according to the model constructs introduced in Fig. 6. In order to monitor the degree to which an objective has been accomplished, operational objectives need to be transformed into plan scenarios. After the end of the planning period has been reached, deviation analyses help to compare these plan scenarios to the actual business development. The next section shows how objectives can be transformed into plan scenarios. 4 Deriving MetaMIS models from business objectives 4.1 Constructing dimensions Having dened operational objectives and structured them hierarchically, we are now able to create a conceptual model of the information system supporting managerial analysis. We rst need to dene dimensions which consist of hierarchically-structured dimension objects. As a rst step, the initial set of objective references taken from the denitions of operational objectives can be decomposed. The objects of the Reference column in Table 1 represent such decomposed objective references, which will be redened as dimension objects and structured hierarchically. They thus form the basic structure of what will be a dimension. This process is complex creative work. Even so, without a methodological approach such as the one presented here, no assistance with this process would be available. Questioning managers on basis of the specied operational objectives is imperative for deriving further insights into the structures of the information systems supporting managerial analysis. Our example objective Rejection Rate Reduction states that rejection rates of other product groups products must not increase. This inevitably leads to the question as to which other product groups should be considered for managerial analysis. The plan scenario that needs to be set up, will include the objective level of the product group Original Equipment Engines, which needs to be decreased according to the objective. Furthermore, it includes the objective levels of all other product groups which must not exceed the respective levels from the previous year. The identication of dimensions can be assisted by answering the question of whether the elements of operational objective references are structured in an n:m relationship or in a 1:m relationship. The rst case implies the

250

Table 1. Operational objective components Reference next year next year next year average delivery time eciency average rejection rate Time Frame Measure Level 24 hours 9 0.2%

Main Objective Sub-Objective Level 1 Sub-Objective Level 2

Delivery time reduction of business unit automative Supplies Increase production eciency

Rejection rate reduction

Machine defect rate next year

next year

Lead time reduction

average machine defect rate average lead time eciency

0.3 class A defects per week 240 min

Increase shipping eciency

next year next year

9 average just-in-time deviation next year next year average packaging time total costs 5 min

business unit automative supplies, any product assembly line V8 engine, factory alpha products of product group original equipment Engines, assembly line V8 engine, factory alpha machines, assembly line V8 engine, factory alpha single products of product group Original equipment, assembly line V8 engine, factory alpha factory alpha, any logistics partner factory alpha, any logistics partner, product

Decrease just-in-time deviation of logistics partners Decrease packaging factory alpha warehouse time workers, customer, order Reduce warehousing costs factory alpha warehouse

1h 500,000 e J. Becker et al.

Specifying information systems for business process integration

251

Objective Structure (0,m) (0,m) Objective Strategy, General Condition, and Guideline

u,t

Operational Objective

(0,m)

OO-OL-AS

Quantitative Aspect (Ratio)

u,t

Objective Measure

(0,m)

Objective Level

(0,m)

Qualitative Aspect

Reference Object

(0,m)

Legend
<Identifier>

Entity Type

<Identifier>

Reinterpreted Relationship Type

<Identifier>

Relationship Type

(min,max)

Connector ( - min minimum cardinality, - max maximum cardinality)

Specialization (Types: - u unequivocally, e equivocally - t total, p partial)

Fig. 6. Objective meta model

modeling of two dimensions (because dimensions are hierarchical constructs of dimensions objects) whereas in the latter case, only one dimension is modeled. This decision needs to be made carefully. It needs to be identied whether this 1:m relationship occurs only temporarily, just as objective references of operational objectives, or generally. If it occurs generally, it is imperative to know, if the relationship might be changed by an ongoing business strategy. As mentioned above, identifying dimensions is a complex process which directly inuences data warehouse structures. It can be seen as a strategic decision during the MIS specication process. In our example objectives from Table 1, there are eleven types of fundamentally dierent entities, business units, assembly lines, warehouses, factories, product groups, workers, products, logistic partners, time entities, orders, and customers. Now, does an assembly line always belong to one factory or can it be spread over more than one factory? Is it possible that a factory runs more than one assembly line? Do workers work in one factory

252

J. Becker et al.

(at one assembly line) or are they allocated to more factories (assembly lines)? Is a product always assigned to exactly one product group? Questions like these have been made possible by the denition of operational objectives with the proposed method. They need to be answered by responsible personnel from business domains to specify the management-supporting information system. Implying 1:m relationships between business units, product groups, and between product groups and products, these three dierent entity types can be aggregated within one dimension Product. If, furthermore, all other entity types are bound by n:m relationships, each will be structured in one dedicated dimension. Only warehouses and assembly lines have been aggregated within one dimension, because allowing analysis between these entity types would serve no purpose. To distinguish plan scenarios from actual business developments, we need the dimension Version. Version is a dimension consisting of the dimension objects Actual, and several plans such as Plan, Plan optimistic, Plan pessimistic, or Forecast. Due to the fact that we transform objectives into plan scenarios to compare them to future business development, we need to add a dimension object of Version to each business fact. If it is a planned fact, a reference to a plan-version is necessary. In case of actual business facts, the Version dimension object Actual is referenced. Deviation analysis later compares business facts that dier only in the reference component of the dimension Version. Figure 7 contains all dimensions necessary to build the MIS environment, which allows for the managerial activity monitor delivery time. After the identication of dimensions, their basic structure of dimension objects which have been derived from operational objectives needs to be completed. Other dimension objects that will further be necessary to answer the managers questions, need to be added. Basically, this means that all relevant products of all product groups (product group Original Equipment Engines and all others obtained from the answer to the question derived from the operational objective Rejection Rate Reduction) are added to the product dimension. In this case, the product dimension would be extended by the products, product groups, and business units shown in Fig. 7. This procedure needs to be repeated for every identied dimension. 4.2 Constructing navigation spaces for managerial activities The denition of business objectives rst needs to be followed by the managerial activity of undertaking the necessary steps to implement improved business processes. Secondly, management must monitor the degree to which the dened business objectives have been achieved. To address the problems of information overow and information misuse, we need to dene dimension scopes for specic managerial monitoring activities. To monitor the objective Increase Production Eciency introduced in Sect. 3.4, we need to dene six dimension scopes. As time can be limited to all time dimension objects of the sub-hierarchy 2004, the rst dimension scope Time by Month Year 2004 consists of all days and months in 2004 and the year 2004 itself. All other time entities are blanked out. Five more dimension scopes are built similarly. The dimension scope Factory Factory Alpha reduces all factories of the dimension Factory to Factory Alpha, Product

Specifying information systems for business process integration

253

Product Automotive Supplies Original Equipment OE Engines OE Chassis Components OE Electronic Components

Production and Storing Facilities Assembly Line V8 Engine Machine V8 - JH7765K Machine V8 - HJG5RF4

Assembly Line Chassis Components Factory Alpha Warehouse

Replacement Electronic Components Engine Parts Electronic Parts Personnel Assembly Line V8 Engine Foreman Machine V8 - JH7765K Foreman Workplace 1 Industrial Supplies Services Machine V8 - HJG5RF4 Foreman Time by Month January 2004 February 2004 Assembly Line Chassis Components Foreman Factory Alpha Warehouse Foreman Workplace 2

Logistics Partner Partners for Engines Partners for Chassis Components

Factory Factory Alpha Factory Beta

Customers by CRM Class Class A Customers Class B Customers

Order Order 0000001 Order 0000002

Version Plan Actual

Legend

<dimension identifier> <non-opened non-leaf dimension object identifier> <opened non-leaf dimension object identifier> <leaf dimension object identifier>

Fig. 7. Set of dimensions for managerial activity monitor delivery time

Product Group Automotive Supplies Original Equipment OE Engines focuses on engines, and Production and Storing Facilities Assembly Line V8 Engine reduces the total set of warehouses and assembly lines to assembly line V8 Engine. Version is reduced to Plan in one dimension scope (Version Plan) and Actual in another (Version Actual), which allows for comparing the business facts based on these two valuations. The dimension scope combination Production Eciency joins all six dimension scopes. It creates

254

J. Becker et al.

a navigation space for the required information of the managerial monitoring activity corresponding to the objective Increase Production Eciency. This navigation space consists of all combined reference objects which are necessary to monitor the objective Increase Production Eciency itself, and all of its sub-objectives once the respective qualitative and quantitative measures have been assigned to them. The dimension scope combination features two hierarchy levels. To create a combined reference object, one dimension object of each dimension scope of the rst hierarchy level needs to be selected. Version is split up into two dimension scopes, which means that one of its dimension scopes needs to be picked for the valuation of business facts. This is necessary, because no information would be aggregated from the versions, Actual and Plan (Holten and Dreiling 2002; Holten et al. 2002). Figure 8 contains the dimension scopes and the dimension scope combination for the managerial activity monitor production eciency. The second sub-objective Increase Shipping Eciency of the main objective Delivery Time Reduction of Business Unit Automotive Supplies requires the construction of a dierent set of dimension scopes and a dierent dimension scope combination. Four existing dimension scopes can be used for the managerial activity monitor shipment eciency, which are Time by Month Year 2004, Factory Factory Alpha, Version Plan, and
Product Product Group Automoti ve Supplies - Original Equipment - OE Engines Automotive Supplies Original Equipment OE Engines Production and Storing Facilities Assembly Line V8 Engine Assembly Line V8 Engine Machine V8 - JH7765K Factory Factory Alpha Machine V8 - HJG5RF4 Factory Alpha Version Plan Production Efficiency Time by Month Product Year 2004 Plan Version Actual Actual

Time by Month

Year 2004

January 2004 2004-01-01 2004-01-02

February 2004 December 2004

Product Group Automotive Supplies - Original Equipment - Engines Assembly Line V8 Engine

Production and Storing Facilities Factory Version Version Version Legend Plan Actual Factory Alpha

<dimension scope identifier> <dimension scope combination identifier>

Fig. 8. Set of dimensions scopes and dimension scope combination for managerial activity monitor production eciency

Specifying information systems for business process integration

255

Version Actual. Additionally, ve new dimension scopes are necessary for customers, logistic partners, orders, personnel, and production and storing facilities. Each reduces the total set of its corresponding dimensions dimension objects to the relevant one for the managerial activity. As for the managerial activity monitor production eciency, a dimension scope combination joins all of these dimension scopes (Shipping Eciency). In order to create combined reference objects, again one dimension object from the rst hierarchy level of the dimension scope combination, needs to be selected as well as one element of either one the version dimension scopes. Figure 9 contains the dimension scopes and the dimension scope combination for the managerial activity monitor shipment eciency.

Time by Month

Year 2004

Factory

Factory Alpha

January 2004 2004-01-01 2004-01-02

Factory Alpha Customers by CRM Class Class A Customers Class B Customers Any Customer

February 2004 December 2004 Logistics Partner any Logistics Partner

Order

Any Order

Order 0000001 Order 0000002

Partners for Engines Partners for Chassis Components

Personnel Production and Storing Facilities Factory Alpha Warehouse Factory Alpha Warehouse Version Plan Shipping Efficiency Time by Month Logistics Partner Factory Personnel Year 2004 any Logistics Partner Plan

Factory Alpha Warehouse Workers

Factory Alpha Warehouse Foreman Version Actual Actual

Factory Alpha Factory Alpha Warehouse Workers Any Customer

Customers by CRM Class Order Any Order

Production and Storing Facilities Version Version Version Legend Plan Actual

Factory Alpha Warehouse

<dimension scope identifier> <dimension scope combination identifier>

Fig. 9. Set of dimensions scopes and dimension scope combination for managerial activity monitor shipment eciency

256

J. Becker et al.

The introduced dimension scopes and dimension scope combinations from Fig. 8 and Fig. 9, correspond to two managerial activities of the managers responsible for production and logistics. Both managerial activities serve the purpose of reducing the delivery time of business unit Automotive Supplies as introduced with the main objective in Sect. 2.2. The activities of the higher management may just require the information, whether the delivery times have been reduced or not. The determining factors for this reduction are clear to the production and logistics managers, but in order to minimize information overow, they are not part of upper managements view on business processes. Also, the hierarchical depth of the dimensions Product and Time by Month have been reduced. In contrast to the horizontal reduction of dimensions, this reduction is made vertically. It is no longer possible to drill down from months and product groups to more detailed dimension objects such as products or days. Figure 10 contains the dimension scopes and the dimension scope combination for the managerial activity monitor delivery time of business unit automotive supplies. 4.3 Constructing aspect systems All dened business objectives from Sect. 3.4 have now been decomposed and used to construct dimensions. Furthermore, navigation spaces have been created to monitor if the business objectives have been accomplished. In the next step, aspect systems will be dened which will be assigned to navigation
Product Business Unit Automotive Supplies Time by Month January 2004 February 2004 December 2004 Version Actual Replacement Electronic Components Engine Parts Electronic Parts Delivery Time of Business Unit Automotive Supplies Product Business Unit Automotive Supplies Year 2004 Version Plan Plan Actual Year 2004

Automotive Supplies Original Equipment OE Engines OE Chassis Components OE Electronic Components

Time by Month Version

Version Version Legend

Plan Actual

<dimension scope identifier> <dimension scope combination identifier>

Fig. 10. Set of dimensions scopes and dimension scope combination for managerial activity monitor delivery time of business unit automotive supplies

Specifying information systems for business process integration

257

spaces, allowing for the construction of business facts. The decomposition of facts in Sect. 3.4, led to measures which have been used to quantify or qualify the references. As shown in Fig. 6, these measures will be transformed either into quantitative or qualitative aspects, depending on the nature of their values. To monitor the objective Increase Production Eciency introduced in Sect. 3.4 several aspects are necessary. First, production eciency is a qualitative aspect. Levels from zero to ten can be used to value production eciency. The objective Increase Production Eciency has been broken down into three sub-objectives, which have been transformed into quantitative aspects. The measures of the three sub-objectives are average rejection rate, average defect rate, and average lead time. All three aspects will be organized into an aspect system Production Eciency Measurement as sub-aspects of the aspect production eciency. For analytical purposes, the production eciency is signicant and used as a starting point. In case something is wrong, it is possible to drill-down to the inuencing aspects average rejection rate, average defect rate, and average lead time. The construction of the second aspect system for the objective Increase Shipping Eciency is similar to the construction of the aspect system for the objective Increase Production Eciency. Shipping eciency is the most signicant aspect. Three sub-aspects are derived from the sub-objectives of the objective Increase Production Eciency, which are average just-in-time deviation, average packing time, and costs. The construction of the main objectives aspect system Delivery Performance Measurement diers from the rst two aspect systems. It is constructed from three aspects, which are average delivery time, shipment eciency, and production eciency. Shipment eciency and production eciency are taken from the rst two aspect systems, but in contrast to the production and logistics management, there are no drill-down possibilities for the aspects Shipment Eciency and Production Eciency. This again is due to avoid information overow. All aspect systems for the three managerial activities monitor production eciency, monitor shipment eciency, and monitor delivery time of business unit automotive supplies are shown in Fig. 11. 4.4 Constructing information objects As pointed out above, a managerial activity which monitors if a business objective has been accomplished, needs to compare plan scenarios with actual business developments. The nature of such analyses is that the reference objects of compared business facts dier only in a value of dimension Version (Holten and Dreiling 2002; Holten et al. 2002). To compare planned facts with actual business facts, fact calculations need to be dened. Any business fact of a dimension scope combination which features the included dimension of the fact calculation, can be calculated according to the calculation expression. Figure 12 shows the fact calculation Plan Variance. It calculates a percentage, which represents the deviation by which planned aspects dier from actual aspects. The fact calculation abstracts from aspects. It can be assigned to each dimension scope combination, where part of it equals to denition of Version in Fig. 12.

258

J. Becker et al.

1
67

34
57

5
9

29

Production Efficiency Measurement Production Efficiency Average Rejection Rate Average Defect Rate Average Lead Time

34
57

5
9

29 67

Shipment Efficiency Measurement Shipment Efficiency Average Just-In-Time Deviation Average Packing Time Costs

1
67

34
57

5
9

29

Delivery Performance Measurement Average Delivery Time Shipment Efficiency Production Efficiency

Legend

1
67

34
57

5
9

29

<aspect system identifier> <super-aspect (hierarchically)>

<sub-aspect (hierarchically)

Fig. 11. Aspect systems for the managerial activities monitor production eciency, monitor shipment eciency, and monitor delivery time of business unit automotive supplies

+ % -

Plan Variance Version Version Version Plan Variance := (Plan/Actual)*100 Plan Actual

Legend

+ % -

<fact calculation identifier> <dimension identifier> <dimension scope identifier>

<calculation expression>

Fig. 12. Fact calculation expression plan variance

Finally, we are able to construct information objects for the three main objectives introduced in Sect. 3.4. Each information object in our example, consists of a dimension scope combination, an aspect system, and a fact calculation expression. The information object Production Eciency assigns the aspect system Production Eciency Measurement to the dimension scope combination Production Eciency. Furthermore, the deviation analysis of planned and actual aspects is rendered possible by the fact calculation Plan Variance. Both other information objects are structured similarly. Figure 13 contains the information objects Production Eciency, Shipment Eciency, and Delivery Performance Measurement.

Specifying information systems for business process integration

259

Production Efficiency Production Efficiency


1
67

34
57

5
9

29

Production Efficiency Measurement Plan Variance

+ % -

Shipment Efficiency Shipment Efficiency


1
67

34
57

5
9

29

Shipment Efficiency Measurement Plan Variance

+ % -

Delivery Performance Measurement Delivery Time of Business Unit Automotive Supplies


1
34
57

5
9

29 67

Delivery Performance Measurement Plan Variance <information object identifier>

+ % -

Legend
+ % -

<fact calculation identifier> <dimension identifier> <dimension scope identifier>

Fig. 13. Information objects for the managerial activities monitor production eciency, monitor shipment eciency, and monitor delivery time of business unit automotive supplies

The constructed information objects consist of planned and actual business facts. Besides the planned facts that arise from plan scenarios dened by the introduced business objectives, other facts are included within these information objects. Examples are production eciency of factory alpha, shipment eciency of logistic partners, or the average delivery times for customer orders within the year 2003. These other facts are part of a dynamic managerial analysis which aims at detailing or generalizing the examined aspect of the business. 5 Summary and outlook Information Sharing is the conceptual core of inter-organizational business process integration. Positive eects of information sharing on stock levels and delivery times along supply chains have been shown. Customer relationship management has been introduced to overcome informational uncertainty if information sharing is not possible. Information systems form the backbone of any supply chain integration and complex customer relationship management analysis. Even though the information-technology side of supply chain integration is well understood by researchers and practitioners, the conceptual specication of information systems for business process integration from a management perspective remained an unresolved issue. In order to overcome the open methodological problem, we have introduced the MetaMIS approach for the specication of managerial views on business processes. In a sample case, we have shown how a system of operational sub-objectives aiming at achieving the objective of delivery time

260

J. Becker et al.

reduction, can be transformed into MetaMIS specications. These specications can be used to create data warehouse structures (Holten 2003). With the presented approach, the conceptual management perspective is assisted by rst deriving specications of managerial views from dened business objectives, and second, the development of an information system supporting managerial analysis. Our future research will focus on validating our approach in various case studies from dierent business domains. We will further develop a tool for supporting the specication of managerial views on business processes, in order to assist the development of enabling information systems from a conceptual management perspective. References
Adam D (1996) Planung und Entscheidung, 4th edn. Gabler, Wiesbaden, Germany Agarwal S, Agrawal R, Deshpande PM, Gupta A, Naughton JF, Ramakrishnan R, Sarawagi S (1996) On the computation of multidimensional aggregates. In: Proceedings of the 22nd International Conference on Very Large Data Bases, Morgan Kaufmann, San Francisco, CA, USA, pp. 506521 Ahlert D, Hesse J (2002) Relationship Management im Beziehungsnetz zwischen Hersteller, Handler und Verbraucher. In: Ahlert D, Becker J, Knackstedt R et al. (eds) Customer Relationship Management im Handel, Springer, Berlin, pp. 330 Anso HI (1965) Corporate Strategy, McGraw-Hill, New York, NY, USA Anso HI, McDonnell E, Lindsey L, Beach S (1990) Implanting strategic management, 2nd edn. Prentice-Hall, London, UK Aviv Y (2001) The Eect of Collaborative Forecasting on Supply Chain Performance. Management Science 47(10): 13261343 Barbuto Jr. JE (2002) How is Strategy Formed in Organizations? A Multi-Disciplinary Taxonomy of Strategy-Making Approaches. Journal of Behavioral and Applied Management 3(1): 6473 Barnard CI (1938) The Functions of the Executive. Harvard University Press, Cambridge, MA, USA Bechtel C, Jayaram J (1997) Supply Chain Management: A Strategic Perspective. The International Journal of Logistics Management 8(1): 1534 Becker J, Dreiling A, Ribbert M (2003) Meta Model based Approaches to Information Systems Engineering. In: Proceedings of the 2003 Information Resources Management Association Conference, Information Resources Management Association, Philapelphia, PA, USA, pp. unknown Becker J, Holten R (1998) Fachkonzeptuelle Spezikation von Fuhrungsinformationssystemen. Wirtschaftsinformatik 40(6): 483492 Berry LL (1983) Relationship Marketing. In: Berry LL, Shostack L, Upah G (eds) Emerging Perspectives on Services Marketing, American Marketing Association, Chicago, IL, USA, pp. 2538 Birkigt K, Stadler MM, Funck HJ (1993) Corporate Identity: Grundlagen, Funktionen, Fallbeispiele, 5th edn. Verlag Moderne Industrie, Landsberg am Lech, Germany Borgman HP (1998) Managers information search behaviour using Management Support Systems. Wirtschaftsinformatik 40(6): 527535 Brealey RA, Myers SC (1996) Principles of Corporate Finance, 5th edn. McGraw-Hill Companies, New York et al. Bruhn M (2001) Relationship Marketing - Das Management von Kundenbeziehungen. Vahlen, Munchen Buchanan RWT, Gilles CS (1990) Value Managed Relationship. The Key to customer retention and protability. European Management Journal 8(4): 523526

Specifying information systems for business process integration

261

Buhl L, Christ J, Ulrich P (2001) Marktstudie: Softwaresysteme fur Enterprise Application Integration, Fraunhofer-Anwendungszentrum fur Logistikorientierte Betriebswirtschaft, Paderborn, Germany Cabibbo L, Torlone R (2001) An Architecture for Data Warehousing Supporting Data Independence and Interoperability. International Journal of Cooperative Information Systems 10(3): 377397 Cachon GP, Fisher M (2000) Supply Chain Inventory Management and the Value of Shared Information. Management Science 46(8): 10321048 Chaudhuri S, Dayal U (1997) An overview of data warehousing and olap technology. ACM SIGMOD Record 26(1): 6575 Christopher M (1998) Logistics and Supply Chain Management. Strategies for Reducing Cost and Improving Service, 2nd edn. Financial Times Professional, London, UK Codd EF, Codd SB, Salley CT (1993) Providing olap (On-Line Analytical Processing) to User Analysts: An IT Mandate. White Paper, E. F. Codd & Associates Colliat G (1996) OLAP, relational, and multidimensional database systems. ACM SIGMOD Record 25(3): 6469 Copeland T, Koller T, Murrin J (1990) Valuation: Measuring and Managing the Value of Companies, John Wiley & Sons, New York, USA et al. Eccles RG (1991) The performance measurement manifesto. Harvard Business Review 69(JanuaryFebruary): 131137 Gavirneni S, Fisher M (1999) Value of Information in Capacitated Supply Chains. Management Science 45(1): 1624 Gillenson ML, Sherrell DL, Chen L-d (1999) Information technology as the enabler of one-toone marketing. Communications of AIS 2(18): article 18 Golfarelli M, Maio D, Rizzi S (1998) The Dimensional Fact Model: A Conceptual Model for Data Warehouses. International Journal of Cooperative Information Systems 7(2 & 3): 215247 Granger CH (1964) The Hierarchy of Objectives. Harvard Business Review 42(MayJune): 6374 Greenleaf E, Winer RS (2002) Putting the Customer Back into Customer Relationship Management (CRM). Advances in Consumer Research 29(1): 357360 Gronroos C (1994) From Marketing-Mix to Relationship Marketing. Towards a Paradigm Shift in Marketing. Management Decisions 28(2): 420 Gyssens M, Lakshmanan LVS (1997) A foundation for multi-dimensional databases. In: Proceedings of the International Conference on Very Large Data Bases, Morgan Kaufmann, San Francisco, CA, USA, pp. 106115 Hammer M (2001) The Superecient Company. Harvard Business Review 79(September October): 8291 Henderson JC, Venkatraman N (1999) Strategic Alignment: Leveraging Information Technology for Transforming Organizations. IBM Systems Journal 38(2/3): 472484 Hewitt F (1994) Supply Chain Redesign. International Journal of Logistics Management 5(2): 19 Hillbrand CA, Karagiannis D (2002) An Approach to Facilitate Complex Planning Issues by Means of Machine Learning Techniques Applied to Cybernetic Cause-and-Eect Models. In: Proceedings of the SCI 2002 - 6th World Multiconference on Systemics Informatics and Cybernetics, Orlando, FL, USA, pp. 5156 Hirschheim R, Klein HK, Lyytinen K (1995) Information Systems Development and Data Modeling. Cambridge University Press, Cambridge, UK Hitt LM, Brynjolfsson E (1996) Productivity, Business Protability, and Consumer Surplus: Three Dierent Measures of Information Technology Value. MIS Quarterly 20(2): 121142 Holten R (1999) Entwicklung von Fu hrungsinformationssystemen. Ein methodenorientierter Ansatz. Wiesbaden, Germany Holten R (2003) Specication of Management Views in Information Warehouse Projects. Information Systems 28 (forthcoming) Holten R, Dreiling A (2002) Specication of Fact Calculations within the MetaMIS Approach. In: Becker J, Grob HL, Klein S, Kuchen H, Muller-Funk U, Vossen G (eds) Working Papers of the Institute of Information Systems. Muenster, Germany Holten R, Dreiling A, Schmid B (2002) Management Report Engineering - A Swiss Re Business Case. In: Proceedings of the Data Warehousing 2002 Conference, pp. 421437

262

J. Becker et al.

Holten R, Dreiling A, zur Muehlen M, Becker J (2002) Enabling Technologies for Supply Chain Process Management. In: Proceedings of the International Resources Management Association, International Resources Management Association, Seattle, WA, USA, pp. 864868 Im KS, Dow KE, Grover V (2001) Research Report: A Reexamination of IT Investments and the Market Value of the Firm-An Event Study Methodology. Information Systems Research 12(1): 103120 Inmon WH (1996) Building the Data Warehouse, 2nd edn. Wiley, New York, NY, USA et al Inmon WH, Hackathorn RD (1994) Using the Data Warehouse. Wiley, New York, NY, USA et al Inmon WH, Welch JD, Glassey KL (1997) Managing the Data Warehouse. Wiley, New York, NY, USA et al Ives B, Learmonth GP (1984) The Information System as a competitive weapon. Communications of the ACM 27(12): 11931201 Jarke M, Jeusfeld MA, Quix C, Vassiliadis P (1999) Architecture and Quality in Data Warehouses. An extended Repository Approach. Information Systems 24(3): 229253 Jarke M, Lenzerini M, Vassiliou Y, Vassiliadis P (2000) Fundamentals of Data Warehouses. Berlin, Germany et al. Jiang JJ, Klein G, Discenza R (2001) Information System Success as Impacted by Risks and Development Strategies. IEEE Transactions on Engineering Management 48(1): 4655 Johnson HT, Kaplan RS (1987) Relevance Lost: The Rise and Fall of Management Accounting. Harvard Business School Press, Boston, MA, USA Johnston HR, Vitale MR (1988) Creating Competitive Advantages with Interorganizational Information Systems. MIS Quarterly 12(2): 153165 Kaplan RS, Norton DP (1992) The Balanced Score Card. Measures that Drive Business Performance. Harvard Business Review 70(JanuaryFebruary): 7179 Kaplan RS, Norton DP (1993) Putting the Balanced Scorecard to Work. Harvard Business Review 71(SeptemberOctober): 134142 Kaplan RS, Norton DP (1996) Translating Strategy into Action. The Balanced Scorecard. Boston, MA, USA Kaplan RS, Norton DP (1997) Why Does Business Need a Balanced Scorecard. Journal of Cost Management 11(3): 510 Kaplan RS, Norton DP (2000) Having Trouble with Your Strategy? Then Map It. Harvard Business Review 78(SeptemberOctober): 167176 Keil M (1995) Pulling the Plug: Software Project Management and the problem of Project Escalation. MIS Quarterly 19(4): 421447 Keil M, Mann J, Rai A (2000) Why Software Projects Escalate: An Empirical Analysis and Test of Four Theoretical Models. MIS Quarterly 24(4): 631664 Kotler P (1999) Marketing Management: Analysis, Planning, Implementation, and Control, 9th edn. Prentice Hall, Upper Saddle River, NJ, USA Kupsch P (1979) Unternehmensziele. Gustav Fischer-Verlag, Stuttgart, New York Lapsley I, Mitchel F (1996) The Accounting Challenge: Accounting and Performance Measurement. London, UK Latham GP, Kinne SB (1974) Improving Job Performance through Training in Goal Setting. Journal of Applied Psychology 59: 187191 Lee HL, So KC, Tang CS (2000) The Value of Information Sharing in a Two-Level Supply Chain. Management Science 46(5): 626643 Li EY, Chen H-G (2001) Output-driven information system planning: a case study. Information & Management 2001(38): 185199 Meert H (2000) Marketing. Grundlagen marktorientierter Unternehmensfu hrung. Konzepte Instrumente - Praxisbeispiele. Gabler, Wiesbaden, Germany Meyr H, Rohde J, Wagner M (2000) Architecture of Selected APS. In: Stadtler H, Kilger C (eds) Supply Chain Management and Advanced Planning. Concepts, Models, Software and Case Studies, Springer, Berlin, Germany et al., pp. 241249 Miller TC (2001) Hierarchical Operations and Supply Chain Planning. Springer, Berlin, Germany et al.

Specifying information systems for business process integration

263

Mintzberg H (1973) Strategy Making in Three Modes. California Management Review 16(2): 44 53 Mukhopadhyay T, Kekre S, Kalathur S (1995) Business Value of Information Technology: A Study of Electronic Data Interchange. MIS Quarterly 19(2): 137156 Payne A, Christopher M, Clark M, Peck H (1998) Relationship Marketing for Competitive Advantage - Winning and Keeping Customers. Butterworth-Heinemann, Oxford, U.K. et al. Peck H, Payne A, Christopher M, Clark M (1999) Relationship Marketing: Strategy and Implementation. Butterworth-Heinemann, Oxford, U.K. et al. Porter ME (1979) How Competitive Forces Shape Strategy. Harvard Business Review 57(March April): 137145 Porter ME (1996) What is Strategy? Harvard Business Review 74(NovemberDecember): 6178 Porter ME, Millar VE (1985) How Information Gives You Competitive Advantage. Harvard Business Review 63(JulyAugust): 149160 Proctor T (1997) Essentials of Marketing Research. Pitman Publishing, London, UK et al. Reichheld F (1996) The hidden Forces behind Growth, Prots, and lasting Value. Harvard Business School Press, Boston, MA, USA Riebel P (1979) Gestaltungsprobleme einer zweckneutralen Grundrechnung. Zeitschrift fu r betriebswirtschaftliche Forschung 31: 863893 Rohde J (2000) Coordination and Integration. In: Stadtler H, Kilger C (eds) Supply Chain Management and Advanced Planning. Concepts, Models, Software and Case Studies, Springer, Berlin, Germany et al., pp. 184194 Rohde J, Wagner M (2000) Master Planning. In: Stadtler H, Kilger C (eds) Supply Chain Management and Advanced Planning. Concepts, Models, Software and Case Studies, Springer, Berlin, Germany et al., pp. 117133 Rolland C, Prakash N (2000) Bridging the Gap Between Organisational Needs and ERP Functionality. Requirements Engineering 2000(5): 180193 RosettaNet (2003) http://www.rosettanet.org, accessed on 2003-02-01 Stadtler H (2000) Supply Chain Management. An Overview. In: H Stadtler, C Kilger (eds) Supply Chain Management and Advanced Planning. Concepts, Models, Software and Case Studies, Springer, Berlin et al., pp. 728 Standish Group International (2001) Extreme CHAOS. Research report, ordering information available at www.standishgroup.com Steiner GA (1969) Top Management Planning, 13th edn. Macmillan, New York, NY, USA Stone M, Woodcock N, Wilson M (1996) Managing the Change from Marketing Planning to Customer Relationship Management. Long Range Planing 29(5): 675683 Subramani M, Walden E (2001) The Impact of E-Commerce Announcements on the Market Value of Firms. Information Systems Research 12(2): 135154 Supply Chain Council (2001) Supply-Chain Operations Reference-Model. Overview of SCOR Version 5.0. Supply Chain Council, Pittsburgh, PA Tam KY (1998) The Impact of Information Technology Investments on Firm Performance and Evaluation: Evidence from Newly Industrialized Economies. Information Systems Research 9(1): 8598 Todd P, Benbasat I (1999) Evaluating the Impact of DSS, Cognitive Eort, and Incentives on Strategy Selection. Information Systems Research 10(4): 356374 Vassiliadis P (2000) Gulliver in the land of data warehousing: practical experiences and observations of a researcher. In: Proceedings of the International Workshop on Design and Management of Data Warehouses (DMDW2000), Stockholm, Sweden, pp. 12(1)12(16) Vassiliadis P, Sellis T (1999) A Survey of Logical Models for OLAP Databases. Sigmod Record 28(4): 6469 Venkatraman N (1994) IT-Enabled Business Transformation: From Automation to Business Scope Redenition. Sloan Management Review 35(2): 7387 Widom J (1995) Research problems in data warehousing. In: Proceedings of the International Conference on Information and Knowledge Management, ACM, New York, NY, USA, pp. 8192 Wixom BH, Watson HJ (2001) An Empirical Investigation of the Factors Aecting Data Warehousing Success. MIS Quarterly 25(1): 1741

You might also like