PROJECT PROFILE OF
BIO DIESEL PLANT
Capacity-5Kl, 10Kl, 20Kl
317, Sheetal Varsha Mahavir Business Park, Opp. Behrampura Police Chowki, Behrampura, Ahmedabad - 380022
goalbiooil@gmail.com | +91 8877554431, 8777457252, 7260810700
GOAL BIO OIL PVT. LTD.
Goal Bio Oil pvt.ltd. is Gujrat based manufacturing firm working World wide for plant designing, oil
manufacturing and trading in all types of lubricant oils.
ABOUT US
1. Manufacturing of bio diesel Plant
2.Establishment of Used oil recycling Plant
3.Oil polishing Plant
4.Ethanol Production Plant
5. Lubricant and grease production Plant
6. Crude Distillation Plant Production Plant
7.Plastic Pyrolysis plant
8. CBG (BIO CNG) Production Plant .
HISTORY
History of Biodiesel: Rudolph Diesel himself developed biodiesel in 1890, wherein pure vegetable oils
were used in diesel engines for agriculture, where petroleumdiesel was not available. Modern
biodiesel fuel is an outcome of research conducted in 1930s in Belgium, which is made by converting
vegetable oils into compounds called fattyacid methyl esters. Process of transesterification was used
to convert vegetable oils into fatty acid alkyl esters and use as diesel fuel replacement with lower
viscosity of vegetableoil. Biodiesel is the trade name of fatty acid methyl esters. Concerns over
environment, energy security and use of agro products brought the use of vegetable oils to the
forefront.
Biodiesel industry became house hold name in U.S. after terrorist attack of 9/11/2001,
resulting in high oil prices. Biodiesel is being used Worldwide now, due to concerns over Global
warming. The future of biodiesel lies in the world’s ability to producerenewable feedstocks such as
vegetable oils and fats to keep the cost of biodiesel competitive with petroleum.
Page-1
GOAL BIO OIL PVT. LTD.
5 KL 10 KL 20 KL
Area required 20000 Sqft (Min) 40000 Sqft (Min) 60000 Sqft (Min)
Shed Size 15000 Sqft (Min) 30000 Sqft (Min) 60000 Sqft (Min)
Height (Clear) 30 Feet 60 Feet 60 Feet
Electric Power Supply 40 Hp (Approx) 80 Hp (Approx) 80 Hp (Approx)
Page-2
GOAL BIO OIL PVT. LTD.
2022
DISTILLATION PROCESS
ESTERIFICATION PROCESS
Step3
Step2
Step1
20% 2% 0.5%
Page-3
GOAL BIO OIL PVT. LTD.
Page-4
GOAL BIO OIL PVT. LTD.
Cooling Tower
Storage Tank Total: 30 KL Storage 30KL each 4 Nos 30KL each 4 Nos 30KL each 4 Nos
Boiler 4 Lakh Calories 1 Nos 4 Lakh Calories 1 Nos 8 Lakh Calories 1 Nos
(Full Assembly)
Chimney
All Pipelines
All Valves
Note : Price may change at any time (terms and conditions apply), there will be extra cost for additional items.
Page-5
GOAL BIO OIL PVT. LTD.
• Fabrication drawing will submit for approval with 7 days from the date of receipt of P.O. and
advance payment.
• The Material shall be supplied in 25 days after approval of drawing and payment against the same
• Erection can be completed within 20 days subject to clear front availability at site.
• Sheeting can be completed within 15 weeks subject to clear front availability at site.
• Above schedule is based on cleared commercials, civil support and site clearance, any delays on
account of prescribed factors would automatically enhance the schedule accordingly.
Payment Terms
Supply Terms
• Material payment advance with Performa invoice
Erection Terms
• 50 % advance.
• 40% Running work
• 10% after work complete .
Client Scope
• Purchaser will have to provide single point three phase power supply and single tapping point
water for erection free of cost.
• Providing sufficient space near the building designated exclusively for unloading, storage,
painting works and a suitably covered store for insulation.
• Unloading , Hydra & Crane is Purchaser’s scope.
• Providing space for labor hutments near to the site.
• We hope you will find our offer in line with your requirement, however if you have any query,
please feel free to call us.
Page-6
GOAL BIO OIL PVT. LTD.
PAYMENT TERMS
• 50% in advance
• 25% after 30 days from the first payment 15% after 30 days from second payment
• 10% against delivery.
NOTE:
LABOURERS WILL BE PROVIDED BY US BUT COMMISIONING AND TRANSPORTATION COST OF THE
LABOURER WILL BE BORNE BY YOU WHICH ALSO INCLUDES FOOD AND STAY OF LABOURERS.
18% GST will be applied on the quotation given separately.
Loading responsibility will taken by us but transportation and unloading cost will be borne by you.
Main Internal wiring connection cost will not be borne by us.
This quotation is valid only for 30 days from the day given.
Any changes in the government policies may vary the pricing of the quotation.
This price quotation is only for your reference please do not provide it to anyone else.
BANKING DETAILS :-
Bank Name : CANARA BANK
Account Name : GOAL BIO OIL PVT. LTD.
Account No. : 127000253974 IFSC- CNRB0017405
Bank Address : 17405, Danapur cantonment - 801503, Patna (Bihar)