Professional Documents
Culture Documents
ASME2003 Station 38019
ASME2003 Station 38019
net/publication/267498500
CITATIONS READS
8 7,402
3 authors, including:
All content following this page was uploaded by Rainer Kurz on 22 December 2015.
GT2003-38019
ABSTRACT NOMENCLATURE
This paper discusses issues that influence the decision on A = Area
the arrangement of compressors and the type of equipment in a = Elevation
gas pipeline compressor stations. Different concepts such as C = Constant
multiple small units versus single large units are considered,
c = Cost
both regarding their impact on the individual station and the
D = Diameter
overall pipeline. The necessity of standby units is discussed.
Various concepts for drivers (gas turbine, gas motor and electric e = Pipeline Efficiency
motor) and compressors (centrifugal and reciprocating) are fDW = Darcy Weisbach Friction Factor
analyzed. SG = Specific Gravity Relative to Air
H = Head
The importance of considering all possible operating conditions ki = Constants
is stressed. With the wide range of possible operating
L = Length
conditions for the pipeline in mind, the discussion will be
brought into the general context of operational flexibility, N = Speed
availability, reliability, installation issues, remote control, and Ns = Specific Speed
operability of gas turbine driven centrifugal compressors NPV = Net Present Value
compared to other solutions such as electric motor driven P = Power
compressors or gas engine driven reciprocating compressors. p = Pressure
The impact of different concepts on emissions and fuel cost is Q = Volumetric Flow (Capacity)
discussed.
R = Gas Constant
Among the assumptions in this paper are the performance r = Discount Rate
characteristics of the compressor. It will be outlined how these T = Temperature
performance characteristics influence the conclusions. t = Time
V = Flow Velocity
INTRODUCTION W = Mass Flow
The pressure and flow characteristics of pipelines and other x = Distance Coordinate
factors may influence the arrangement of compressors in a Z = Compressibility Factor
station as well as the type of equipment used. Besides the r = Density
question about series or parallel arrangements in a station, the
more general question arises about the number of units, standby h = Efficiency
requirements, type of driver, and type of compressor.
95
operating scenarios has to be studied. Figure 3 (Kurz [3]) shows
90 operating points of a compressor station gathered during six
85 months of operation. Due to hourly, daily and monthly
variations in demand, the only way to cover the large range of
80
flow and head requirements efficiently was to install three gas
75 turbine driven centrifugal compressors. Depending on the
demand, the station either operates one, two or all three of the
70
High Backsweep
compressors. The map shows the operating envelopes of the
65
Moderate Backsweep
60 3
With modern compressors and stages with a wide operating range, it is
0 0.1 0.2 0.3
usually possible to have identical stages for both the low pressure and the
SPECIFIC SPEED, Ns high pressure compressor in a series application. Intercooling is usually not
necessary nor does it typically yield significant savings.
4
The gas turbine used to drive mechanical equipment is usually of the two-
Figure 1. Impeller efficiency versus specific speed for shaft design. The power turbine thus allows variable speeds in the range of at
various well-designed impellers (Rogers [6]). least 50-to-100% speed.
LOAD VARIATION
REL ETA_TH
0.8 0.8
0.6 0.6
0.4
0.4
0.2
0.2
0
50 60 70 80 90 100 0
0 96 192 288 384 480
LOAD, %
HOURS
Figure 2. Typical two-shaft gas turbine relative thermal
efficiency (hth/hth(100%load)) versus load (P/Pmax.) for different Figure 4. Averaged load variation for four stations of an
gas turbines. The steeper drop in thermal efficiency with interstate pipeline during summer and winter scenarios,
part load is associated with dry-low-emissions engines. Case B.
1 Unit 2 Units 3 Units in Parallel units must be considered. These standby units can be arranged
such that each compression station has one standby unit, or that
some stations have a standby unit, or that the standby function
is covered by oversizing the drivers for all stations. It must be
noted that the failure of a compression unit does not mean that
HEAD
the entire pipeline ceases to operate, but rather that the flow
capacity of the pipeline is reduced. Since pipelines have a
Site Power
significant inherent storage capability ("line pack"), a failure of
at 75°F one or more units does not have an immediate impact on the
total throughput. Additionally, planned shutdowns due to
maintenance can be planned during times when lower capacities
0 are required.
0 FLOW
Standby units are not always mandatory because modern gas
Figure 3. Operating points collected over a six-month turbine driven compressor sets can achieve an availability of
period in a gas compression station, Case A (Kurz [3]). 97% and higher. A station with two operating units and one
standby unit thus has a station availability of 100 (1 - 0.032) =
99.91% (because two units have to fail at the same time in order
compressors. Also indicated are the driver power limitations, to reduce the station throughput to 50%). A station with one
based on 75°F (23.9°C) ambient temperature and site standby unit and one operating unit also yields a 99.91% station
conditions. The gas turbines allow for immediate starting availability. However, while failure of two units in the first case
capability if the need arises. Similarly, transient studies on still leaves the station with 50% capacity, the entire station is
pipeline systems (Santos [7]) can reveal the often large range of lost if both units fail in the second case. Arguably, installing two
operating conditions that needs to be covered by a compressor smaller 50% units rather than one larger 100% unit could avoid
station. An example is shown in Figure 4. Lastly, scenarios that the need for installing a standby unit.
arise from failures of one or more systems have to be
considered (Ohanian and Kurz [8]). A concept that has been discussed from time to time is the
approach to have "power" back up rather than "unit" standby on
The quest for operational flexibility can be satisfied on various a station. The idea is to have an oversized driver, operating at
levels: the compressor and the driver should have a wide part load during normal operation rather than an additional
operating range. Using multiple smaller units per station rather standby unit. In this case, the driver has to be sized such that it,
than one large unit can be another way. Here, the arrangement together with other (equally oversized) units located further
in series or in parallel will impact the flexibility. downstream along the pipeline, can pick up the duty of an
unavailable station upstream. The advantage of this concept lies
in the reduction in the number of units. The disadvantage is that
STANDBY UNITS
the gas turbine operates at part load and, thus, at lower
Because the failure or unavailability of compression units can
efficiency (Figure 2) for most of the time. Even if the larger gas
cause significant loss in revenue, the installation of standby
Tb Tim e 1.0
Q=C× ×e×
Pb
0.0375 × SG × (aend - abegin ) × pa2 ù (3)
0.5
é 2
ê pbegin - pend -
2
Z a × Ta ú
Di ê ú
2.5
ê SG × Ta × L × Z a × f DW ú
ê ú
ë û
For parallel units, the failure of one unit forces the remaining
unit to operate at or near choke, with a very low efficiency.
Identical units in series, upon the failure of one unit, would Figure 5. Operating points of a parallel (top) and a series
initially require the surge valve to open, but the remaining unit (bottom) compressor arrangement after one of the two units
would soon be able to operate at a good efficiency, thus fails at Time = 1.0.
maintaining a higher flow than in the parallel scenario. Figure 5
shows the operating point of the respective compressor after the
other unit is shut down at T = 1.0. While the remaining unit in system is built up to full capacity over a number of years. The
the series arrangement requires to recycle initially, it moves, project can then be started with fewer small units. Additional
starting at about T = 2.0, slowly to efficient operating points. units are installed later to meet the increasing demand on
compression. The expenses for portions of the equipment can,
The remaining parallel unit, on the other hand, moves further therefore, be delayed. On the other hand, if larger units are
and further into choke. At time T = 10.1 and 7.26, respectively, used, all of them have to be purchased at the beginning of the
either scenario would lead the pressure at the pipeline outlet to project. A net present value (NPV) analysis immediately reveals
drop below the minimum level (Ohanian and Kurz [8]). the advantages of the former approach (Appendix 2). It shows
Therefore, the compressor in series arrangement gives the in particular that even a higher total cost can translate into a
operator more time for corrective action. lower NPV, if parts of the cost can be deferred (Table A-3).
Given the fact that the gas stored in the pipeline will help to
maintain the flow to the users, a series installation would often ENVIRONMENTAL CONSIDERATIONS
allow for sufficient time to resolve the problem. Therefore, a Any activity has to be judged by its impact on the
standby unit could be avoided. environment. This includes the requirement to keep NOx, CO,
and UHC emissions at an acceptable level. For many
operations, meeting certain maximum emission levels is a
ECONOMIC CONSIDERATIONS requirement for continuous operation. Further, the amount of
Pipeline systems usually are not operated at full capacity from CO2 produced as a result of the combustion process has to be
the very beginning of the project, but rather increase the considered. For a given fuel, the only way to reduce the amount
demand when new customers for the gas are found. Smaller of CO2 produced is to increase the engine efficiency.
units tend to be advantageous in cases where the pipeline
0.2
0.15
0.1
0.6
0.05 Series1
0 0.55
FUEL USAGE Series2
20 20
30 30
40 40
50 50
60 60
70 70
80 80
to 0
0
10 10
90 o 9
10
to
to
to
to
to
to
to
to
0.5
t
0
CLASS, % power
0.45
0.4
0.3 0.6
0.2 0.58 Series1
0.1 0.56 Series2
FUEL USAGE
0 0.54
0.52
0
30
40
50
60
70
80
90
0.5
to
to
to
to
to
to
to
to
30
40
50
60
70
80
90
10
0.48
0
5
Figure 8. Fuel usage for Case A scenarios. Series 2 is for the
Obviously, this calculation can be performed for a real scenario by taking into
steeper drop in part-load gas turbine efficiency than Series
account a large number of different operating points, with the actual engine
and compressor performance for each of these points. 1 (see Figure 2).
Series2
0.88 The emissions calculations are based on the assumption that
most DLN engines achieve a constant level of NOx emissions,
0.86 on a ppmv or mg/nm3 basis, for a load range from 50 to 100%.
Standard combustion systems achieve reduced NOx levels on a
0.84 ppmv or mg/nm3 basis at part load because the fuel-to-air ratio
is reduced at part load. CO2 emissions, on the other hand, are
0.82
entirely dependent on engine efficiency (assuming the fuel
1 2 3 4 5 composition, especially the carbon-to-hydrogen ratio, remains
NUMBER OF UNITS unchanged).
a. Case B Scenarios I, III, and V Interestingly, multiple units also provide for advantages in the
1.05 absolute amount of emissions. As outlined in Figure 10, the
Series1
1 Series2
FULL LOAD EMISSIONS,
0.92
FUEL USAGE
STD
0.95 0.9
DLN
(lb/hr)/(lb/hr)
0.88
0.9
0.86
0.85
0.84
0.8 0.82
1 2 3 4 5 0.8
NUMBER OF UNITS 1 2 3 4 5
b. Case B Scenarios I, II, and IV NUMBER OF UNITS
Figure 9. Fuel usage for Case B scenarios. Series 2 is for the Figure 10. NOx emissions for Case B comparing standard
steeper drop in part-load gas turbine efficiency than Series and DLN combustion systems (scenarios I, III, V).
1 (see Figure 2).
EQUIPMENT CONSIDERATIONS
In designing a pipeline, it is important to evaluate the most
appropriate type of compression equipment. In general, three
different concepts can be considered:
REFERENCES
The difference between GT-CC and EM-CC is the type of [1] Hsu, L.L., and Hasselfeld, D.E., 1998, “Total Cost of
driver used. While the gas turbine uses small portions of the Ownership as a Business Tool in Turbomachinery
pipeline gas as fuel, the electric motor requires a reliable source Decisions,” Turbomachinery Technology Seminar, San
of electric power. The cost of electricity is, thus, a key factor in Diego.
the life-cycle cost assessment. Unless the true7 cost of [2] Smalley, A.J., and Mauney, D.A., 1997, “Risk-Based
electricity is below about 0.02 US$/kWh, electric motor driven Maintenance of Turbomachinery,” Proceedings 26th
concepts are at a disadvantage compared to gas turbine drivers Turbomachinery Symposium, pp. 177-187, Houston,
(McKee et al. [9]). It also should be noted that, while the local Texas.
environmental impact of an EMD is low, transmission losses
and the source of electricity (which could be a pollution [3] Kurz, R., 2001, “A Question of Design,” WorldPipelines,
generating power plant) can increase the overall environmental Vol. 1, No. 1, pp. 61-64.
impact. If the necessary electricity infrastructure is not yet built, [4] Cumpsty, N.A., 1989, “Compressor Aerodynamics,”
the disadvantages become even greater. In particular, the lost Longman, Essex, UK.
opportunity cost during downtime due to an unreliable
electricity supply can be significant. It should be noted that an [5] Ohanian, S., Kurz, R., Lubomirsky, M., 2001,
electric motor drive as a system can be very reliable, as long as “Compressor Station Layout and Operation
the electrical power supply is assured. Since the key factor that Considerations,” Proceedings of the Beijing International
determines the availability of an EMD station may be the Pipeline Conference, PRC.
reliability of the power supply, multiple units per station will [6] Rogers, C, 1980, “Efficiency of Centrifugal Compressor
not increase the reliability significantly. Impellers,” Centrifugal Compressors Flow Phenomena
and Performance, AGARD CP 282
While many of the older pipeline systems in the USA still use a
[7] Santos, Sidney Pereira dos, 1997, “Transient Analysis - A
significant number of gas engine driven reciprocating
Must in Pipeline Design,” Pipeline Simulation Interest
compressors, virtually all new installations use centrifugal
Group.
compressor concepts. The reasons typically include the very
high maintenance cost of reciprocating machines, as well as the [8] Ohanian, S., and Kurz, R., 2001, “Series or Parallel
lower availability and reliability, and environmental concerns Arrangement in a Two-Unit Compressor Station,”
(emissions, lube oil, cooling fluids, etc.). Reciprocating TransASME JEng GT and Power.
7
The true cost of electricity includes the cost of generation and transmission
(both capital and operating expenses as well as transmission losses).
Ns = 11000 x 70.5 / (60 x 250000.75) = 0.244 (A-1) Table A-2. NPV Evaluation (assuming standby unit)
The specific speed for the first unit if the units are in parallel Unit Size 5,000 hp 10,000 hp 20,000 hp
is: Total First 5 x $4MM = 3 x $7.5MM = 2 x $14MM
Cost $20MM $22.5MM = $28MM
Ns = 11000 x 3.50.5 /(60 x 500000.75) = 0.103 (A-2)
Net Present $17.67MM $21.2MM $28MM
Value (10%
In this case, parallel operation would yield an impeller that Discount)
potentially has a better efficiency.
APPENDIX 2: NPV EXAMPLE – POWER DEMAND Table A-3. NPV Evaluation (assuming no standby unit)
BUILD-UP DUE TO INCREASED FLOW DEMAND
Unit Size 5,000 hp 10,000 hp 20,000 hp
Power Demand:
Total First 4 x $4MM = 2 x $7.5MM = 1 x $14MM
Year 1: 5,000 hp Cost $16MM $15MM = $14MM
Year 2: 10,000 hp
Year 3: 13,000 hp Net Present $13.67MM $13.7MM $14MM
Year 4: 15,000 hp Value (10%
Year 5 and thereafter: 20,000 hp Discount)
8
The cost figures here are based on arbitrary monetary units.