You are on page 1of 20

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/358006864

A novel framework for single-minute exchange of die (SMED) assisted by lean


tools

Article  in  The International Journal of Advanced Manufacturing Technology · April 2022


DOI: 10.1007/s00170-021-08534-w

CITATIONS READS

9 1,448

5 authors, including:

Roberto Pattaro Junior I.B. da Silva


Serviço Nacional de Aprendizagem Industrial University of São Paulo
5 PUBLICATIONS   9 CITATIONS    43 PUBLICATIONS   239 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Sustentabilidade Corporativa View project

I'm working in the Lean System View project

All content following this page was uploaded by Roberto Pattaro Junior on 15 March 2022.

The user has requested enhancement of the downloaded file.


The International Journal of Advanced Manufacturing Technology
https://doi.org/10.1007/s00170-021-08534-w

ORIGINAL ARTICLE

A novel framework for single‑minute exchange of die (SMED) assisted


by lean tools
Roberto Giani Pattaro Junior1 · Ricardo Henrique Inácio1 · Iris Bento da Silva2 · Amauri Hassui1 ·
Gustavo Franco Barbosa3

Received: 4 November 2021 / Accepted: 3 December 2021


© The Author(s), under exclusive licence to Springer-Verlag London Ltd., part of Springer Nature 2021

Abstract
Nowadays, the survival and success of companies depend on improving on-time delivery and cost reduction. To reach this
target, it is necessary to get improvements, standardization, and controlling of the manufacturing systems. Therefore, the
objective of this scientific work is to perform a case study, based on the implementation of new single-minute exchange of
die (SMED) framework in an oil and gas company. This novel framework was developed based on a practical application of
strategies such as improvements by ECRS (eliminate, combine, reduce, and simplify), standardized work (SW), and OEE
(overall equipment effectiveness) control applied to the production processes. The findings achieved in this work showed
setup time was improved by 91.6%, it moved from 1 h 44 min 56 s (6,296 s) to 8 min 52 s (532 s), and OEE increase 44.6%.
And, the setup activities were standardized. Besides, on every workpiece manufactured, its setup time was measured and
compared against to the target achieved. So, the novel framework developed has potential to provide competitiveness’ strate-
gies to different branches of the industry.

Keywords  SMED · ECRS · Standardized work · Overall equipment effectiveness · Setup time reduction

1 Introduction phases can often lead these companies to lose customers,


market space, or even to close their doors [1].
Nowadays, company such as the oil and gas sectors generates In this context, the single-minute exchange of die
wealth coupled to a business opportunity for the machining (SMED) emerges, which is fundamental to improve flex-
services branch. However, the survival of company that pro- ibility in the production processes [2–4]. This technique
vides machining services for these markets depends on their is part of the lean tools, which aims to reduce wastes in
ability to deliver with quality and on time. the production system. This quick-change, under 9 min or
When it comes to machining, from the entry order until less (single-digit minute), can be performed by the machine
the delivery of the product to the customer, there are sev- operator and preparer [5].
eral steps to be taken, and all of them require an estimated Therefore, the objective of this work was to perform
time, which it is extremely important for the success of the a case study with the implementation of proposed novel
business. However, the delays resulting from the production single-minute exchange of die (SMED) framework
assisted by lean tools in an oil and gas company. The
novel framework was developed based on SMED litera-
* Iris Bento da Silva ture review [6–8], and it was improved by ECRS (elimi-
ibs@sc.usp.br
nate, combine, reduce, and simplify) methodology [9].
1
Department of Manufacturing and Materials Engineering, Also, it was developed through standardized work (SW)
School of Mechanical Engineering, Campinas State and OEE (overall equipment effectiveness) control.
University, Campinas, SP, Brazil Thus, this article is structured as follows. “Sect. 2” pro-
2
Department of Mechanical Engineering, Sao Carlos School vides the literature about lean tools, single-minute exchange
of Engineering, University of Sao Paulo, Sao Carlos, SP, of die (SMED), and ECRS. “Sect. 3” presents the framework
Brazil
constructed and the method applied in this article; “Sect. 4”
3
Department of Mechanical Engineering, Federal University describes the study and implementation. So, “Sect. 4.15.1”
of Sao Carlos, Sao Carlos, SP, Brazil

13
Vol.:(0123456789)
The International Journal of Advanced Manufacturing Technology

shows the results and their discussion, and finally, “Sect. 6” 5S tool (sort, set-in-order, shine, standardize, self-discipline)
enclosures the findings, limitations, and recommendations. is essential for implementing and to create discipline, identify
problems, and generate improvement [17–20].
Kaizen means change for the better. It is a technique for
2 Literature review implementing continuous improvement in the company. Kai-
zen can be implemented in the following steps: establishing
2.1 Lean tools the project leader, choosing the team, identifying the process
to be improved, defining the objective, preparing the action
The fundamentals of lean manufacturing gained prominence plan, and executing [21].
in the 1980s with the publication of research conducted by Poka-yoke (PY) is the system that interrupts the operation
MIT (Massachusetts Institute of Technology) [10]. It pre- whenever defect appears [17, 22]. Standardized work (SW)
sents the continuous improvement practices implemented is a better combination of resources such as operators and
in world-class manufacturing (WCM) companies in the machines to ensure that a task is always performed in the
automotive chain. The study reported that the adoption of same way. It plays a vital role in the quality and implementa-
these concepts greatly contributed to the increase of com- tion of operating systems [23, 24].
petitiveness [11, 12]. The main characteristics and elements
of lean that distinguish it from the traditional manufacturing 2.2 Single‑minute exchange of die
paradigm are listed in Table 1.
The lean wastes that do not add value are described as The SMED is a set of techniques that make possible to run
follows [11]: an equipment setup under 9 min, not exceeding the mark of a
single-digit minute [25–28]. SMED (single-minute exchange
• transportation: excessive movement of information or of die) can evolve into OTED (one-touch exchange of die),
parts; which is the setup time of less than 1 min, as an example,
• motion: excessive movement within the layout; selecting the next part to be produced on a PLC (program-
• inventory: storage results in high-cost and low working mable logic controller). OTED can evolve into NOTED
capital; (non-touch exchange of die), which is setup time equal to
• over-processing: use of inappropriate procedures; zero practically, as an example, tool change in the machining
• waiting: long periods of inactivity; center magazine [2].
• defects: low quality of the product; The ability of companies to quick-change from one prod-
• overproduction: excessive activity that do not add value. uct to another is critical. One way to achieve this goal is to
decrease the setup time, which is the time spent between
The lean tools collaborate with the elimination and/or the manufacturing of the last workpiece (A) of a previous
reduction of wastes [13]. They are as follows: value stream batch and the production of the first workpiece (B) of the
mapping (VSM); kaizen; 5S; poka-yoke (PY); standardized next batch [29]. There are several benefits provided by a
work (SW); and single-minute exchange die (SMED). setup time reduction (STR), such as greater productivity
Value stream mapping (VSM) facilitates the visualization [30]; less waste and rework, reduced inventory and lead
of information and materials. It aims at building maps that time, and greater system flexibility [31]; and greater machine
represent both the flow of information (from the customer’s efficiency, in addition to the decrease in batch sizes [32]. It
request to the production schedule) and the flow of materials is worth noting that the quick-change programs can increase
(from the raw material to the finished goods) [14–16]. productivity by up to 70% [33].

Table 1  Key issues of Key issue Traditional Lean (tools)


traditional versus lean
manufacturing, adapted from Lead time (LT) Bigger (process without connections) Shorter (continuous flow manufacturing—CFM)
[13]
Stock Protect production Evidence problems (just-in-time—JIT)
Lot size Bigger (economic lot) Shorter (one-piece flow)
Efficiency Increased production Add value and waste reduction (5S)
Quality Inspection on boarding Inspection at source (poka-yoke—PY)
Standardization Failure to update procedures Standardized work (SW)
Flexible Shorter Higher (single-minute exchange die—SMED)
Availability Lower Higher (overall equipment effectiveness—OEE)

13
The International Journal of Advanced Manufacturing Technology

Setup is a process that prepares the exchange for the next is recommended to reconcile the information on the shop
part to be produced. The setup activities can be divided into floor as leverage for a solid base into implementation of
external and internal. External is one that can be executed continuous improvement, standardization, and control.
while the machine is running, for example, tool transporting. The research method adopted for the development of
Internal is one that can only be executed when the machine is this work was case study. It is a form of empirical research
necessarily stopped, such as tool exchanging. Shingo started to investigate a contemporary phenomenon in its real con-
SMED in Japan, as follows [2]: text, especially when the boundaries between the phenom-
enon and the context are not well defined. This method
• 1950: at Mazda, Hiroshima, in an 800-ton press, in which usually involves the investigation of a small number of
external and internal activities were separated; cases and makes it possible to develop understandings
• 1957: at Mitsubishi, Hiroshima, in a machining used to about the object of the study, comprising its relations with
engine component, the internal activity was transferred to contextual conditions [38].
external; Industrial managers in an oil and gas company were
• 1969: at Toyota, Nagoya, in an 1000-ton press, Shingo con- interviewed, and semi-structured questionnaire was applied.
solidated the SMED technique, in 3 Shingo stages, which The manager’s interviews were directed to the collection of
are: data on the dimensions, direction, and environment of the
organization. To facilitate the understanding of how they
o Separate the internal and external activity; were treated, the characteristics of current scenario and how
p Transfer the internal into external activity; it became improvement scenario through SMED approach
q Continuously improve the activities. were analyzed. The methodology applied in this work was
based on the practical application of strategies and biblio-
• 1985: Shingo methodology was first published in the West, graphic concepts, in order to extract the results, where the
being the main reference when it comes to machine setup scenarios were compared in relation to the setup preparation
time reduction (STR). time and OEE (overall equipment effectiveness).

Lean manufacturing tools has been adopted in this work.


However, the bibliographic research reports that there are few 3.2 A novel SMED framework
studies that describe the elimination or reduction ECRS pro-
cess combining into lean [34]. A novel SMED framework was developed based on posi-
tive aspects of each article studied (see Table 2) as follows:
2.2.1 ECRS
• A literature review from 2007 to 2020 was made,
The ECRS is a process that drives continuous improvement to regarding SMED concepts;
reduction of costs and waste eliminations [9, 35]. The ECRS • It was conducted using Scopus and Google Scholar;
is supported by 5W2H [36, 37] as follows: • In the initial screening, it used key words SMED and
setup time reduction;
• E (eliminate): analyze activity (what is done?); identify if • In the refinement, it used “framework”;
the activity adds value; what is actually performed? why • In the aspects, after the redundancies it eliminated
is this activity necessary?; remain articles and it reviewed using characteristics,
• C (combine): if it is not possible to eliminate activity, can it like as Shingo stages, lean tools (VSM, 5S, OEE, SW,
be combined?; where and when is the activity performed?; poka-yoke, kaizen), and eliminate wastes;
• R (reduce): when activity cannot be eliminated, combined, • It focused articles of case study and modeling, in the
it can be balanced; who performs the activity?; research methodology;
• S (simplify): the activity needs to be simplified; how is the • Finally, it selected 12 articles [39–50].
activity being carried out? how much does the activity cost?

Regarding the lean tools’ aspect, few researches have


3 Research method considered training, but no researches have implemented
standardized work during the setup. Also, few researches
3.1 Method have followed the activities’ time of manufactured parts on
setup day by day.
To promote the application of setup time reduction (STR) Faced to that, the proposed novel SMED framework rec-
within SMED and its challenges for permanent results, it ommends for the setup time reduction, a training of the work

13

13
Table 2  A novel SMED framework
Aspects and tools [39] [40] [41] [42] [43] [44] [45] [46] [47] [48] [49] [50] Proposed

Project Team formation x x x


Data collection x x x x x x x x x x x x
Analyze x x x x x x x x x x x x
Evaluation x x x x x x x x x x x x
Shingo stages SMED implementation x x x x x x x x x x x x x
Separating internal and external activities x x x x x x x x x x x
Converting internal activity into external x x x x x x x x x x x
Streamlining all activities x x x x x x x x x x
Lean tools Hypothetical setup (kaizen training) x x
Kaizen (continuous improvement) x x
5S x x x x x
VSM current x x x x x x x
Spaghetti diagram (layout) x x x
Poka-yoke (PY) x x
5W2H x
Setup time reduction (STR) changeover x x x x x x x
Standardization x x x x x x
Standardized work (SW) x
Control (OEE) overall equipment effectiveness x x x x
ECRS ECRS x x
Eliminate activities x x x x x x x x
Combine activities x x x x
Reduce activities x x x x x
Simplify activities x x x x x
The International Journal of Advanced Manufacturing Technology
The International Journal of Advanced Manufacturing Technology

team in fundamental concepts, and a creation of an environ- 6. Standardize by SW:


ment of involvement, commitment, and motivation. After 7. Standardize the improved activities;
getting the setup time target, it is recommended to follow all 8. Draw layout activities (spaghetti diagram).
setup through the standardized work (SW). Also, the setup 9. Control by OEE (Overall Equipment Effectiveness):
time performed must be recorded, and the OEE calculated 10. Measure setup time (every time);
to be compared to the target. In this sense, our contribution 11.
Effectively control the setup time achieved
presents and highlights these innovative differences faced to (OEE = quality rate × performance efficiency × avail-
the other researches. ability);
Figure 1 highlights a new SMED framework constructed 12. Disseminate lessons learned.
(proposed in Table 2) to sustain results, which is divided in
3 phases and 10 steps, as follows:
4 Case study
I. Continuous improvement:
The oil and gas company in this case study was not
1. Establish scope the project by 5W2H; identified due to confidentiality. It was performed by
2. Choose lean tools; an intentional sample of selected people who has a real
3. Establish goals; view of the difficulties and that could bring a realis-
4. Perform kaizen training; tic opinion of the shop floor in order to contribute and
5. Setup time reduction (Shingo stages and ECRS): setup anticipate possible distortions. On this way, it can lev-
time reduction (STR) to continuously improve setup erage and decrease the response time in the search for
activities through Shingo stages (SMED) and ECRS results. Phase I of the SMED framework is presented
(Eliminate, Combine, Reduce and Simplify). as follows.

Fig. 1  A novel single-minute exchange of die (SMED) framework

13
The International Journal of Advanced Manufacturing Technology

4.1 Phase I: Continuous improvement • Improvement: 5S, spaghetti diagram, kaizen, PY (poka-


yoke), ECRS (eliminate, combine, reduce, simplify);
The metrics of the project charter were described in the • Standardization: SW (standardized work);
case based on 5W2H, as follows: (i) title: what; (ii) focus: • Control: OEE (overall equipment effectiveness);
what, how; (iii) customer: who; (iv) group: who; (v) jus-
tify: why; (vi) deliverable: what; (vii) action: what, why, 4.4 (I.3) Establish goals
and how; (viii) time: when; (ix) local: where; and (x)
resources: who, how much. In this step, the goals were as follows:

• Cost: 70% of setup time reduction;


4.2 (I.1) Establish scope the project by 5W2H • Time: reach SMED time (setup under 9 min);
• Add value (AV): improve OEE in 30%.
In this step, the project charter was developed by 5W2H,
as follows: 4.5 (I.4) Perform kaizen training

• What was the precise nature of the problem?: machining In this step, it was applied the kaizen to employee training,
setup time reduction (STR); in the special lean room of company to highlight changeo-
• Who was involved?: stakeholders; ver know-how and foster involvement and commitment (this
• When did the problem occur?: 2019 (current scenario), simulation also can be performed in FlexSim or Arena soft-
2020 (improvement scenario); ware to analyze, visualize, and improve real processes). The
• Where did the problem take place?: oil and gas company; activities were carried out on a radial drilling machine. The
• Why was the problem occurring?: cost reduction; drilling operation was accomplished with ϕ 10-mm helical
• How extensive was the problem?: impact on availability drill, jig, and fixture (see Fig. 2). The other objective of the
and delivery; kaizen training was to highlight the next phase, which was
• How much costed to solve the problem?: depend on kai- setup time reduction.
zen. This operation was divided into 18 activities with the
indication of the times of each one. Also, the activities
4.3 (I.2) Choose lean tools were classified into internal and external. Table 3 shows
the value stream mapping (VSM) filming of the activi-
The lean tools were as follows: ties performed in the kaizen. It represents the kaizen setup
and Shingo’s concept. The jig and tools were discussed so
• Assessment: VSM (value stream mapping) current film- that setup time reduction and SMED could be achieved
ing; on kaizen.

Fig. 2  Radial drilling machine


of training

13
The International Journal of Advanced Manufacturing Technology

Table 3  Setup time reduction (STR), adapted from Shingo stages IT (internal time) and ET (external time)
# Activity Time (min) Current Stage
1st 2nd 3rd
1 Define next part B 3.0 IT ET ET ET ET

2 Locate part B manufacturing route 2.0 IT ET ET ET ET


3 Request machining tooling 4.5 IT ET ET ET ET
4 Search machining tool 13.7 IT ET ET ET ET
5 Disassembly of part B tooling 6.1 IT IT IT IT 6.1 → 2.7
6 Assembly tooling from part B 10.5 IT IT IT IT 10.5 → 4.5
7 Center jig and fixture part B 4.0 IT IT ET ET ET
8 Adjust machine 5.7 IT IT IT ET ET
9 Change drill 1.2 IT IT IT 1.2 → 0.7 IT
10 Adjust tooling 4.1 IT IT ET ET ET
11 Search raw material for try-out 4.5 IT ET ET ET ET
12 Machining sample 2.0 IT IT IT 2.0 → 1.0 IT
13 Inspect part 3.1 IT IT ET ET ET
14 Readjust tooling 3,2 IT IT IT ET ET
15 Forklift bring part B box 5.1 IT ET ET ET ET
16 Return part A tooling 5.4 IT ET ET ET ET
17 Do control plan 4.5 IT ET ET ET ET
18 Release machine 1.8 IT ET ET ET ET
Total internal time (IT) (min) 84.4 39.9 28.7 18.3 8.9
Total external time (ET) (min) 0 44.5 55.7 66.1 75.5
0% 52.7% 66% 78.3% 89.5%

First stage: separating internal/external activities, the • The inspection of the control plan could be done after the
activities classified as external were: release of the machine;
• The internal setup time was reduced from 84.4 to
• Activities #1, #2, #3, #4, #11, #15, #16, #17, and #18 (see 28.7 min (66%).
Table 3);
• The external activities can be carried out in advance or Third stage: streamlining all activities, as follows:
after the setup itself;
• The remaining internal activities can only be performed • Activity #8 an encoder system was installed to control the
when the radial drilling machine was stopped; course of the column and head. This activity was trans-
• The internal setup time was reduced from 84.4 to ferred to external, as it can be performed in synchronous
39.9 min (52.7%). mode without counting the time in the internal activity.
• Activity #9 the execution time had reduced from 1.2 to
Second stage: converting internal activity into external, 0.7 min, through the quick-change system;
as follows: • Activity #12 the execution time lowered from 2.0 to
1.0  min (machining time per unit). However, in the
• Activity #7 was changed to time equal to zero. The fix- future, this internal time could be transformed into an
ture center had been modified. At the base of the fixture, external time, considering a stable and capable manu-
a shaft was added to allow the guide with the hole of the facturing process;
machine base; • Activity #14 the cutting tool was modified through a pre-
• Activity #10 was transformed from internal to external. set.
This transformation was possible after making changes • So far, the setup was reduced from 84.4 to 18.3 min
into the jig and fixture design; (78.3%);
• Activity #13 was transferred to external, because the • In the sequence, activity #5 the setup time reduced from
statistical process control (SPC) in drilling operation 6.1 to 2.7 min;
became stable and capable; • Activity #6 decreased from 10.5 to 4.5 min;

13
The International Journal of Advanced Manufacturing Technology

• The setup time reduction in activities #5 and #6 was pos- • Define the kaizen equipment and workpiece;
sible, because the largest number of adjustments in disas- • Establish 5S;
sembly (part A) and assembly (part B) was eliminated; • Record the setup activities VSM (value stream mapping)
• The production planning was elaborated with sequen- filming;
tial parts group, in such a way it can use a basic fixture, • Draw spaghetti current diagram;
changing only a few components. When it was necessary • Separating internal and external activities;
to change the entire fixture, try to remove the device from • Eliminate (E) unnecessary activities.
workpiece A at the rear of the machine, and enter the new
device from workpiece B, at the front; 4.7 Kaizen equipment and workpiece
• The internal setup time was reduced from 84.4 to 8.9 min
(89.5%). The equipment used in this study was a CNC vertical turn-
ing (VT); 12 tools automatic magazines, 1,400 mm diameter
4.6 (I.5) Setup time reduction (Shingo stages workpiece clamping plate, maximum height of 1,265 mm,
and ECRS) maximum permissible weight on the 12,000 kg plate, among
other characteristics can be seen in Fig. 3.
In this step, the setup process was presented in real situ- To perform the setup tests, two parts were used, and the
ation, case study, as follows: take raw material, prepare, machining occurred according to the company’s production
and transport tooling, disassembly tooling workpiece (A), schedule. The first part was processed according to the cur-
assembly tooling workpiece (B), adjust, release the machine. rent process instruction and the second part with the appli-
The setup time reduction describes the stages combined with cation of SMED framework, in order to improve the setup.
ECRS (eliminate, combine, reduce, simplify) which are pre-
sented as follows. VSM current filming
I.5.1 Separating internal and external activities as follow:
On the morning of the first day, setup concepts were pre-
• Confirm working group; sented. On the afternoon of the same day, filming was carried

Fig. 3  Raw material, vertical


turning (VT) structure, and
workpiece

13
The International Journal of Advanced Manufacturing Technology

Fig. 4  Spaghetti diagram cur-


rent

out. The VSM current filming was done with a 16-mm camera from the machine. This inefficient movement in the stock took
supported on a tripod, environment lighting, which allowed the place in the kanban sector, and others around the machine.
total view of the area. The working method of the previous setup The setup time for each activity is shown in Table 4.
and its sequence was analyzed, before any improvement was The improvement scenario will be presented in the results,
applied. After that, it was identified that the total time of this as follows.
step was with the machine stopped, in order to be fully identified I.5.2 Converting internal activities into external as
as an internal setup. The entire sequence of activity performed follow:
during assembly was digitally timed (stopwatch XL-5853).
• Converting internal activities into external;
Spaghetti diagram • ECRS analysis;

In the current scenario, based on this analysis, it was possi- o E: continuous eliminating internal activities;
ble to identify the excessive displacement (spaghetti diagram) p C: combine activities;
at different moments of the setup (see Fig. 4), especially in the q R: reduce internal and external activities;
process engineering and quality control sectors, which are far r S: simplify all activities;
Table 4  Current scenario activities (#): IT (internal time) and ET (external time)
# Description of operator setup activities Time Pre-analysis
h:min:s

1 Identify last part manufactured, locate next production order 00:01:08 IT and ET
2 Request to overhead crane 00:02:12 ET
3 Clean chips, lift the last machined workpiece 00:12:05 IT
4 Remove the last workpiece from the lathe and take it to the finished goods stock 00:04:21 IT
5 Check production order, evaluate traceability, verify raw material dimensions, select the tools 00:09:17 ET
6 Disassemble and clean tools, jaws, chuck from the last part 00:21:13 IT and ET
7 Assemble the jaws set selected for the next workpiece 00:04:32 IT and ET
8 Check if CNC program is available 00:00:15 ET
9 Go to the process engineering to request CNC program 00:11:56 Eliminate (E)
10 Check technical drawing and select the measuring instruments 00:08:33 ET
11 Request measuring instrument to the next workpiece 00:09:01 ET
12 Tools preset and wait for CNC program 00:13:17 IT and ET
13 Verify CNC program on the network, change the tools programmed did not match, confirm 00:04:07 ET
machining graph
14 Go to quality and get measuring instrument 00:02:57 ET
15 Release machining 00:00:02 IT
Total 1:44:56

13
The International Journal of Advanced Manufacturing Technology

In the improvement scenario, for the new proposal, needed for the part, and checked those that were already
Shingo’s setup methodology was applied in the visuali- available on the machine. The quality control was asked for
zation of activities to reduce the total setup time. After the necessary measuring instruments and the warehouse
observing the activities of the current setup, those internal for the missing tools on the machine. Then, the tools were
activities that could be transferred to external ones were assembled in the magazine and the preset was made. He
changed. brought the quality control measuring instruments and
The objective was to make the transfer from internal placed them on the table next to the process order that is
setup to external as much as possible. With the integra- next to the machine>
tion of the production area with the engineering area,
the production order for the next part was ready 1 h in 4.11 ECRS analysis
advance where it was possible to carry out various activ-
ities during the machining of the current (previous) part In Table  5, it can be seen how the current moving to
in the equipment. The activities were divided as follows. improvement scenario, where all activities were internal
and after the application of the SMED technique, in which
the ECRS process (eliminate, combine, reduce, and sim-
4.8 Planner plify) was used, several activities were changed from inter-
nal setup to external. In this way, there was a reduction
The production planning sequencing was carried out in in the time of the internal setup from 1 h 44 min 56 s to
advance and made available to engineering by the plan- 27 min 49 s, where the machine was 1 h 17 min 07 s avail-
ner. Manufacturing engineering performs all its activity able for production (gain 76.4%), because the activities that
in advance, according to the proposed planning in the were previously done with the stopped machine, after the
new procedure. The processing of the CNC program is proposed actions, could be performed without stopping on
completed and is already available on the machine before the equipment.
the end of the previous part’s machining. Thus, everyone I.5.3 Streamlining all aspects of the setup activities by
already had the necessary information for the process, ECRS, as follow:
being possible the accomplishment of several activities
of external setup. • ECRS streamlining;

4.9 Operator o E: eliminate or reduce waiting;


p C: combine activities;
The operator continued with the internal activities, the final q R: reduce movements in the layout; reduce internal
appointment of the last part, the activities directly linked to activities by eliminate adjustments; reduce external
the operation of the equipment, such as opening the safety activities through tool warehouse organization;
door, cleaning chips, loosening the fixing nuts, and strap- r S: simplify all activities; standardize design tools
ping the part and with the help of the overhead crane to be and release with PY (poka-yoke).
removed from the equipment and taken to the transition
stock. After removing the equipment from the last part, In this step, it will be continuous improvement to reach
the operator immediately started fixing the current part, the SMED (from 27 min 49 s to 8 min 52 s). Setup became
disassembling the nuts from the current (previous) setup, faster, the value chain became closer to the customer, and the
and cleaning the plate and the threaded holes in the guides. system improved its availability. The result of this analysis
After that, the assembly of the set of jaws selected for the is found in Table 6.
piece was carried out and the raw material was loaded in
a machine. At the end of all activities, machining started 4.12 Phase II: Standardization
with the start cycle.
In this phase, standardized work maintains equity in the
4.10 Preparer three work shifts, with different human resources, inside
the cell. This phase is that after setup time reduction
External activities were assigned to the preparer, starting (STR) is performed, it was necessary to standardize the
with the request for the overhead crane, then checking the activities. After implementing phase I, need to keep the
raw material and selecting and assembling the appropriate results achieved. Otherwise, company will not survive.
set of nuts. After that, the technician checked the techni- How keep it? There is no point in implementing the stud-
cal drawing, checked the measuring instruments and tools ied method if the result cannot have monitored. The setup

13
Table 5  Applied improvements and results
# activity Current scenario ECRS analysis Improvement scenario Obs
Internal time (IT) External Eliminate (E) Combine (C) Reduce (R) Simplify (S) Internal time (IT) External time (ET) Responsible
h:min:s time (ET) h:min:s h:min:s
Preparer Operator Planner

1 00:01:08 x 00:00:30 00:00:38 x


2 00:02:12 x 00:02:12 x
The International Journal of Advanced Manufacturing Technology

3 00:12:05 x 00:04:12 x  − 07:53


4 00:04:21 00:04:21 x
5 00:09:17 x 00:09:17 x
6 00:21:13 x 00:09:29 00:11:44 x x
7 00:04:32 x 00:03:22 00:01:10 x x
8 00:00:15 x 00:00:15 x
9 00:11:56 x  − 11:56
10 00:08:33 x 00:08:33 x
11 00:09:01 x 00:09:01 x
12 00:13:17 x 00:05:53 00:07:24 x
13 00:04:07 x 00:04:07 x
14 00:02:57 x 00:02:57 x
15 00:00:02 x 00:00:02 x
Total 1:44:56 0:27:49 0:57:18

13
The International Journal of Advanced Manufacturing Technology

Table 6  Continuous From → to Action description Time New time Responsible


improvement h:min:s h:min:s
1 I Identify next production order 00:00:30 00:00:17 Operator

3 II Automatic spray, drive overhead crane, automatic lifting 00:04:12 00:02:09 Operator
4 III Remove the last part (operator, IT) 00:04:21 00:01:23 Operator
Take the part to FG (planner, ET) Planner
6 IV Disassemble jaw—chuck with quick change 00:09:29 00:01:14 Operator
7 V Assemble jaw, chuck (operator, IT) 00:03:22 00:01:30 Operator
Pre-set tools (preparer, ET) Preparer
12 VI Assemble next part 00:05:53 00:02:17 Operator
15 VII Release machining 00:00:02 00:00:02 Operator
Total 0:27:49 0:08:52

time can return to the initial situation. Or even get bigger 4.14 (II.2) Draw layout activities (spaghetti
than when the study started. Therefore, this present phase diagram)
shows how to standardize the setup time reduction after its
implementation. Figure 6 shows cell layout and operator setup activities
described in Table 6. In relation to the route taken in the
4.13 (II.1) Standardize the improved activities improvement setup, there was a significant decrease during
(work sequence and time) the period in which the equipment was stopped.
The spaghetti diagram with the path taken by the
Figure 5 shows the standardized work sequence, what are the operator with the stopped machine, after applying the
activities, and the time (manual, automatic, walk) of each improvement by the SMED tool, can be seen in Fig. 7.
activity and diagram. The long journeys made between the machine and the

Fig. 5  Setup standardized work


(532 s = 8:52 min)

13
The International Journal of Advanced Manufacturing Technology

Fig. 6  Cell layout (VT 2) and setup activities. I. Identify next part; II. Automatic spray, drive overhead crane; III. Remove last part; IV. Disas-
semble tools; V. Assemble new tools; VI. Assemble next part; VII. Release machining

sectors of quality control, warehousing, and production with the longest journeys occurred with the machine run-
planning and control were eliminated and the activities ning, which were carried out in advance by the preparer.

Fig. 7  Spaghetti diagram
improved

13
The International Journal of Advanced Manufacturing Technology

4.15 Phase III: Control (setup time, OEE, and lessons

(parts per week)]


Stock (work-in-
learned)

 = [3] − [100
frequency = [5] process)
4.15.1 (III.1) Setup time measurement (every time)

1100
300
700

300
300
100
qty


To control setup time, it was installed a digital clock similar
to a 60″ TV monitor. This clock showed the last recorded
setup time. Next to this clock, it was showed the last setup

Setup

qty
time. The graphical tracking of time was plotted on an online

4
1
1
1
1
1
2
4
graph, indicating the year-to-date, compared to the target.

[6]/8 × 60 min
4.15.2 (III.2) Effective control of the setup time achieved

shift

1.54
1.01
1.84
2.68
0.92
0.91
0.88
0.85
by OEE (Overall Equipment Effectiveness)

month = [3] × [4] × [5] = [6]
The result of this step was controlled through OEE. Thus,
visual management was recommended to control activities

Machine load per


in the cell, which can show the work sequence of activities.
This demonstration must be didactic, in such a way that all
employees can understand by themselves.

1284
min

738
484
884

440
436
420
409
4.15.3 (III.3) Lessons learned dissemination

unit = [1] + [2]/[3] = [4]
In this step, lessons learned was disseminated that spread
Total time per
to other neighboring lathes in the cell throughout the site.
Table 7  Training analysis (production order = 100 part/week; one shift = 8 h; one month = 20 working days)

The team demonstrated to others the success of the project

1.84
1.21
1.11
1.07
1.10
1.09
1.10
1.09
min
through sharing within the seminar. This fact must be sup-
ported by reward, recognition, involvement, commitment,
Machining time

and motivation through human resources area.


per unit [1]

min

1
1
1
1
1
1
1
1
5 Results and discussion
Lot size [3]

5.1 Training
1200
100
400
800

400
400
200
100
qty
gain = {[n] − [n + 1]}/

Training inside the proposed SMED framework is recom-


[n] × 100, in minutes

mended to present the concepts of Shingo stages in setup


time reduction. So, it is essential for the involvement and
Setup time

commitment of the work team to disseminate the achieved


52.7

78.3
89.5

results. The training seeks to understand the needs of inven-


66
%




tory reduction, since those people involved prefer to opt for


Setup time [2]

the economical lot, compensating the setup time. Also in the


training, it is clarified that the setup time reduction provides
a greater flexibility to meet the customer’s order, as well as
84.4
84.4
84.4
84.4
39.9
28.7
18.3
8.9
min

the batch size can be reduced, in such a way that the total
time per unit approximates to the cycle time.
Current scenario
Shingo stage

In the training, the initial analysis of Table 7 predicts that


production manager prefers the scenario 2, approaching the
economic lot, because in his opinion the cost is not so high,
1
2
3

and the inventory will be consumed within the month. How-


Scenario [n]

ever, considering SMED time, the best decision is scenario


8, which has the lowest machine load, lowest cost, best flex-
ibility, and lowest inventory.
1
2
3
4
5
6
7
8

13
Table 8  Current, improvement, and continuous improvement scenario activities [IT (internal time) and ET (external time)]
# Current scenario ECRS Improvement scenario Continuous improvement scenario
Description Time Analysis IT ET Preparer Operator Planner # Description New IT
h:min:s h:m:s h:m:s (operator and preparer, planner) h:m:s

1 Identify last part manufactured, locate 00:01:08 IT, ET C 00:00:30 00:00:38 x I Identify next production order (operator) 00:00:17
next production order 17 s
2 Request to overhead crane 00:02:12 ET C 00:02:12 x
3 Clean chips, lift the last machined part 00:12:05 IT C 00:04:12 x II Automatic spray, drive overhead crane, 00:02:09
R automatic lifting (operator) 129 s
4 Remove the last part from the lathe and 00:04:21 IT R 00:04:21 x III Remove the last part (operator, IT) 00:01:23
take to the finished goods stock Take the part to FG (planner, ET) 83 s
5 Check production order, evaluate 00:09:17 ET C 00:09:17 x
traceability, verify raw material
The International Journal of Advanced Manufacturing Technology

dimensions, select the tools


6 Disassemble and clean tools, jaws, chuck 00:21:13 IT C 00:09:29 00:11:44 x x IV Disassemble jaw, chuck with quick 00:01:14
from the last part ET change (operator, preparer) 74 s
7 Assemble jaws set selected for the next 00:04:32 IT, ET C 00:03:22 00:01:10 x x V Assemble jaw set (operator, IT) 00:01:30
part Pre-set tools (preparer, ET) 90 s
8 Check if CNC program is available 00:00:15 ET C 00:00:15 x
9 Go to the process engineering to request 00:11:56 Eliminate E x
CNC program
10 Check technical drawing and select the 00:08:33 ET C 00:08:33 x
measuring instruments
11 Request measuring instrument 00:09:01 ET C 00:09:01 x
12 Tools pre-set, wait for CNC program 00:13:17 IT, ET S 00:05:53 00:07:24 x VI Assemble next workpiece (operator) 00:02:17
137 s
13 Verify CNC program and machining 00:04:07 ET E 00:04:07 x
14 Go to quality and get measuring 00:02:57 ET C 00:02:57 x
instrument
15 Release machining 00:00:02 IT C 00:00:02 x VII Release machining (operator) 00:00:02
2 s
01:44:56 00:27:49 00:57:18 00:08:52
6296 s 1669 s 3438 s 532 s

Legend: #3 has been reduced: 07:53 (473 s); #9 was eliminated: 11:56 (716 s), total = 1669 (IT) + 3438 (ET) + 473 (#3) + 716 (9) = 6296 s

13
The International Journal of Advanced Manufacturing Technology

Table 9  Case study Scenario SMED Shingo ECRS OEE (%) Setup time
framework stages
Before After Gain
h:min:s h:min:s %

Current x x x 56 → 73 (30.4% increase) 01:44:56 00:27:49 73.5


Continuous x x x 73 → 81 (10.9% increase) 00:27:49 00:08:52 68.1
improvement 56 → 81 (44.6% increase) 01:44:56 00:08:52 91.6

5.2 5S tool results through continuous improvement, standardized work,


and control of key indicators.
In the other point of view, the 5S tool was highlighted. It Table 9 shows the results of case study developed. In the
supported the work environment, under ergonomic aspects. current scenario, the company reached the two-digit time,
And, it still kept the proper use of the tooling, the order of which was already significant for the operation. In sequence,
the artifacts related to the setup, the cleaning of the environ- the SMED framework was fully applied in 4 in the continu-
ment, the standardization of activities, and the discipline ous improvement scenario. This fact will achieve SMED
in the machine. These factors allowed the development of time, and it will also keep the result obtained.
kaizen, so that one can find and seek excellence, through The SMED framework provided improvements, in
continuous improvement. In this case, the 5S were applied, the first implementation, with a reduction in the internal
namely, organization, ordering, cleanliness, standardization, setup time from 1 h 44 min 56 s to 27 min 49 s, making
and discipline. the machine 1 h 17 min 07 s available for the manufactur-
ing. In addition, the study had reached 8 min 52 s. Thus,
5.3 Novel SMED framework it can be noted that the reduction in the setup time had
reached 73.5% so far, in the continuous improvement sce-
The novel SMED framework was developed using nario reached 91.6%. Thus, in the case study the reduc-
researches [39–50], from which key technologies and tools tion in setup time also improved the OEE, in terms of
were subtracted. These models covered several industrial availability.
segments and manufacturing processes, such as machining, At the same time, the company also developed a plan
electro-beam welding, textile, and stamping press. Another to improve the maintenance up-time, not presented in this
highlighted point was that the article described by McIn- study, but in such a way that the combination of setup and
tosh et al. [46] is a reference used to complement Shingo’s maintenance improved availability in the final (overall
concepts [2]. equipment effectiveness) OEE = quality rate × performance
Lean tools were applied through the training and kaizen efficiency × availability, as follows:
for vertical lathe, which training conceptualized the Shingo
stages, creating involvement, commitment, and motivation. • Pre-implementation level OEE = 0.99 × 0.80 × 0.71 = 0.56
After reaching the established setup time, it was imple- (current scenario);
mented the standardized work (SW), recorded the setup • The implementation of SMED framework, the OEE
time, and controlled the respective OEE. moved to 73%, OEE = 0.995 × 0.87 × 0.84 = 0.73
(improvement scenario), representing a 30.4% of
5.4 Current, improvement, and continuous increase;
improvement scenario activities • Remedial actions, in the company, will be continued
to achieve the target goal from 73 to 81% (continuous
Table 8 shows the cycles of work carried out, from the cur- improvement scenario), representing a 44.6% of total
rent scenario, through the improvement one, until reaching increase.
the stage of continuous improvement. It was important to
explain to stakeholders that there was no point in making an Table 10 presents the application of 3 phases and 10 steps
effort, if you do not control it. of single-minute exchange of die (SMED) framework. The
Another highlight was the kaizen training that had been current scenario did not apply full standardization and con-
in the company’s special lean room. In this room, the main trol. The continuous improvement scenario achieved a per-
lean projects and their results are exposed. The success of manent result supported by full SMED framework proposed.
the implementation was the permanent demonstration of the The conclusion will be presented as follows.

13
The International Journal of Advanced Manufacturing Technology

Table 10  Single-minute 3 phases I. Continuous improvement phase II. III. Control Keep results
exchange of die (SMED) Standardization
framework
10 steps I.1 I.2 I.3 I.4 I.5 II.1 II.2 III.1 III.2 III.3 –
I.5.1 I.5.2 I.5.3

Current scenario x x x x x x x x –
Continuous x x x x x x x x x x x x yes
improvement
scenario

Legend: I.1, scope; I.2, lean tools; I.3, goals; I.4, kaizen training; I.5, Shingo stages and ECRS (elimi-
nate, combine, reduce, simplify); I.5.1, separating internal and external activities; I.5.2, converting internal
activities into external; I.5.3, streamlining all aspects of the setup process; II.1 standardized work (SW);
II.2, layout (spaghetti diagram); III.1, setup time; III.2, OEE (overall equipment effectiveness); III.3, les-
sons learned

6 Conclusions Declarations 

The findings achieved in the case study showed a reduc- Ethics approval  The authors declare that the article was constructed
respecting all ethical conditions of publication.
tion in the setup time assisted by lean tools within the
SMED framework. The improvements in the current Consent to participate  All authors participated in the preparation of the
scenario can be highlighted by the setup time reduction article. In this way, the authors allow their names to be in the article.
from 1 h 44 min 56 s to 27 min 49 s and, making the
Consent for publication  Authors allow publication.
machine 1 h 17 min 07 s available for the manufactur-
ing. Besides, in the continuous improvement scenario,
Conflict of interests  The authors declare no competing interests.
the study reached 8 min 52 s, resulting a total increase of
91.6%, and the OEE (Overall Equipment Effectiveness)
has improved to 44.6%.
The main contribution of this case study was to propose
a practical method, called single-minute exchange of die
References
(SMED) framework, for manufacturing organizations sus- 1. Slack N (2013) Brandon-Jones, A., and Johnston, R. Operations
tain their competitive results. The maintenance of the results management, 7th ed. Pearson, Edinburgh, UK
will depend on the commitment developed in the training, 2. Shingo S (1985) A revolution in manufacturing. In: The SMED
the implementation of the standardized work (SW) in the system. Productivity Press, Cambridge, MA
3. Silva IB, Godinho Filho M (2019) Single-minute exchange of
activities during the setup execution, the control of the setup die (SMED): a state-of-the-art literature review. Int J Adv Manuf
time indicator, and the calculation of OEE (overall equip- Technol 102:4289–4307
ment effectiveness) in the studied cell. 4. Pacheco DAJ, Heidrich GDG (2021) Revitalising the setup
Further research should assess the method’s develop- reduction activities in operations management, Production
Planning & Control.https://​d oi.​o rg/​1 0.​1 080/​0 9537​2 87.​2 021.​
ment in companies of different segments, such as electron- 19648​81
ics, chemistry, food, pharmaceuticals, aviation, among oth- 5. Moreira AC, Pais GCS, (2011) Single minute exchange of die.
ers, that need greater flexibility and a reduced inventory to A case study implementation. J Technol Management and Innov
remain competitive. 6(1):129–146
6. Ulutas B (2011) An application of SMED methodology.
The dissemination of these concepts throughout the man- International Scholarly and Scientific Research & Innovation
ufacturing sector, in which there is a requirement to perform 5(7):100–103
setups, will bring expressive results related to increase of 7. Lozano J, Saenz-Díez J, Martínez E, Blanco J (2017) Methodol-
company’s productive capacity and reduction of delivery ogy to improve machine changeover performance on food indus-
try based on SMED. Int J Adv Manuf Technol 90:3607–3618
times that will provide customers’ satisfaction. 8. Ahmad R, Soberi MSF (2018) Changeover process improvement
based on modified SMED method and other process improve-
ment tools application: an improvement project of 5-axis CNC
Author contribution  All authors contributed to the construction of the machine operation in advanced composite manufacturing indus-
paper. try. Int J Adv Manuf Technol 94:433–450
9. Sindhuja D, Mohandas G, Madhumathi P (2012) Redesigning of
Data availability  All information, figures, and tables are in the manu- horn assembly line using ECRS principles. International Journal
script. It will not be necessary to provide other data and materials. of Engineering and Innovative Technology (IJEIT) 1(3):214–217

13
The International Journal of Advanced Manufacturing Technology

10. Womack JP, Jones DT, Roos D (1990) The machine that changed 31. Allahverdi A, Soroush HM (2008) The significance of reducing
the world. Rawson Associates, New York setup times/setup costs. Eur J Oper Res 187(3):978–984
11. Liker JK (2004) The Toyota way: 14 management principles from 32. Mackelprang AW, Nair A (2010) Relationship between just-in-
the world’s greatest manufacturer. McGraw-Hill, New York time manufacturing practices and performance: a meta-analytic
12. Chakravorty SS, Shah AD (2012) Lean six sigma (LSS): an investigation. J Oper Manag 28(4):283–302
implementation experience. European J Industrial Eng 6(1) 33. Das B, Venkatadri U, Paney P (2014) Applying lean manufac-
13. Mann DW Creating a lean culture: tools to sustain lean conver- turing system to improving productivity of air conditioning coil
sions. New York: Productivity Press manufacturing. Int J Adv Manuf Technol 71:307–323
14. Dal Forno AJ, Pereira FA, Forcellini FA, Kipper LK (2014) 34. Burawat P (2019) Productivity improvement of carton manufac-
Value stream mapping: a study about the problems and chal- turing industry by implementation of lean six sigma, ECRS, work
lenges found in the literature from the past 15 years about appli- study, and 5S: a case study of ABC Co. J Environ Treat Tech
cation of lean tools. Int J Adv Manuf Technol. https://​doi.​org/​ 7(4):785–793
10.​1007/​s00170-​014-​5712-z 35. Suhardi B, Anisa N, Laksono PW (2019) Minimizing waste using
15. Azizi A, Manoharan T (2015) Designing a future value stream lean manufacturing and ECRS principle in Indonesian furniture
mapping to reduce lead time using SMED a study. Procedia industry. Cogent Engineering 6(1):1–13
Manuf 2:153–158 36. Nguyen V, Nguyen N, Schumacher B, Tran T (2020) Practical
16. Seth D, Seth N, Dhariwal P (2017) Application of value stream application of plan–do–check–act cycle for quality improvement
mapping (VSM) for lean and cycle time reduction in complex of sustainable packaging: a case study. Appl. Sci. 10, 6332. https://​
production environments: a case study. Production Planning & doi.​org/​10.​3390/​app10​186332
Control 28(5):398–419 37. Xue Q (2019) Research on single minute exchanging die (SMED)
17. Osada JGAP (2007) Interaction and connections among the 5S, based on lean production, Master’s degree thesis, Departament of
the SMED and poka-yoke techniques in continued improvement Mechanical & Aerospace Engineering. Politecnico di Torino
processes. Re-creaciones 139–148 38. Yin RK (2003) Case study research: design and methods. Thou-
18. Bevilacqua M, Ciarapica FE, De Sanctis I, Mazzuto G, Paciarotti sand Oaks, CA: SAGE
CA (2015) Changeover time reduction through an integration of 39. Martins M, Godina R, Pimentel C, Silva FJG, Matias JCO (2018)
lean practices: a case study from pharmaceutical sector. Assem A practical study of SMED to electro-beam machining in automo-
Autom 35(1):22–34 tive industry. Procedia Manufacturing 17:647–654
19. Drew W (2016) Process implementation through 5S laying foun- 40. Maalouf MM, Zaduminska M (2019) A case study of VSM and
dation for lean, Productivity Press SMED in the food processing industry. Management and Produc-
20. Omogbaia O, Salonitisa K (2017) The implementation of 5S lean tion Engineering Review 10(2):60–68
tool using system dynamics approach. Procedia CIRP 60:380–385 41. Ibrahim MA, Mohamad E, Arzmi MH, Rahman MAA, Saptari
21. Carnerud D, Jaca C, Bäckström I (2018) Kaizen and continuous A, Shighatullah AS, Sulaiman MA, Ali MAM (2015) Enhanc-
improvement – trends and patterns over 30 years. The TQM Jour- ing efficiency of die exchange process through single minute of
nal 30(4):371–390 exchanging die at a textile manufacturing company in Malaysia.
22. Saurin TA, Ribeiro JLD, Vidor G (2012) A framework for J Appl Sci 15(3):456–464
assessing poka-yoke devices. Journal of manufacturing system 42. Mansor MA Ismail AR Yasin MRM Halim A (2015) A framework
31:358–356 for measuring the effect of changeover time to overall equipment
23. Oliveira J, Sá JC, Fernandes A (2017) Continuous improvement effectiveness. Int Congress on Natural Sci Eng 798–806
through lean tools: an application in a mechanical company. Pro- 43. Basri AQ Mohamed NMZN (2017) The study of extended single
cedia Manuf 13:1082–1089 minute exchange of die method in 1200 tonnage tandem press line
24. Mor RS, Singh BA, S, Sachdeva A, (2019) Productivity gains for operation improvement. CIE47 Proceedings 1–7
through standardization-of-work in a manufacturing company. J 44. Tamas P (2017) Application of a simulation investigational
Manuf Technol Manag 30(6):899–919 method for efficiency improvement method. Academic Journal
25. Culley SJ, Owen GW, Mileham AR, McIntosh RI (2003) Sustain- of Manufacturing Engineering 15(2):23–30
ing changeover improvement. Proc Inst Mech Eng B J Eng Manuf 45. Mohamed BAQ, Yasir NMZN, Fazi KASHM, Fudzin HM, AF,
17(10):1455–1470 (2018) The validation of productivity on the changeover activity
26. Reik MP, Mcintosh RI, Culley SJ, Mileham AR, Owen GW at the automotive stamping press line by comparing the embedded
(2006a) A formal design for changeover methodology. Part 1: SMED framework versus SMED approach: a witness simulation
methodology and case study. Proc Inst Mech Eng B J Eng Manuf case study. IOP Conference Series: materials Science and Engi-
220(8):1225–1235 neering. https://​doi.​org/​10.​1088/​1757-​899X/​469/1/​012005
27. Reik MP, Mcintosh RI, Culley SJ, Mileham AR, Owen GW 46. McIntosh R, Owen G, Culley S, Mileham T (2007) Changeo-
(2006b) A formal design for changeover methodology. Part 2: ver improvement: reinterpreting Shingo’s “SMED” methodol-
methodology and case study. Proc Inst Mech Eng B J Eng Manuf ogy (2007). IEEE Transations on Engineering Management
220(8):1237–1247 54(1):98–111
28. Cakmakci M (2009) Process improvement: performance analysis 47. Hasabe A, Hakde A, Khandagle A, Surve K (2019) Single minute
of the setup time reduction-SMED in the automobile industry. Int exchange of dies (SMED) concept, International Research Journal
J Adv Manuf Technol 411:68–179 of. Eng Technol 06(04):4665–4669
29. Braglia M, Frosolini M, Gallo M (2017) SMED enhanced 5-whys 48. Soberi MSF Idris NI Ahmad A Muhamad N Hussain MI (2015)
analysis to improve set-up reduction programs: the SWAN Setup time reduction for 5-axis composite material’s trimming
approach. Int J Adv Manuf Technol 90(5–8):1845–1855 machine by a new framework of SMED integrated with ECSC
30. Rosa C, Silva FJG, Pinto Ferreira L, Campilho R (2017) SMED concept. Int Symposium on Adv Ergonomics & Safety 1–9
methodology: the reduction of setup times for steel wire-rope 49. Suky NSA, Bakar EA, Ansari EI, Akhtar MN (2020) Single min-
assembly lines in the automotive industry. Procedia Manufactur- ute exchange die approach setup time in labelling printing com-
ing 13:1034–1042 pany. Journal of Engineering Science 16(2):35–56

13
The International Journal of Advanced Manufacturing Technology

50. Braglia M, Frosolini M, Gallo M (2016) Enhancing SMED: Publisher's Note Springer Nature remains neutral with regard to
changeover out of machine evaluation technique to imple- jurisdictional claims in published maps and institutional affiliations.
ment the duplication strategy. Production Planning & Control
27(4):328–342

13

View publication stats

You might also like