You are on page 1of 10

Int J Adv Manuf Technol

DOI 10.1007/s00170-015-7845-0

ORIGINAL ARTICLE

Set-up reduction in an interconnection axle manufacturing cell


using SMED
Jonathan David Morales Méndez 1 & Ramón Silva Rodríguez 2

Received: 7 May 2015 / Accepted: 13 September 2015


# Springer-Verlag London 2015

Abstract This document is about how to reduce set-up time cially for the industrial sector which must maintain pace with
using Single-Minute Exchange of Die (SMED) on an actual the daily changes in competitiveness in the global marketplace
production process of interconnection axles, starting with a [1].
production and indicators analysis, followed by time studies, In response to these challenges, the industrial sector has
and then the rolling-out of all the SMED stages. The first had to embark on a process of transforming administrative
activity carried out was observation, second assessment, and management processes and the organization of production
followed by implementation leading to standardization and systems. According to Carrizo Moreira and Torres Garcez
the generation of standard manufacturing documents. At this [2], two clear lines of action can be distinguished: the first is
point, training was carried out thereby enabling the validation strengthening technological capacity at the machine and infor-
and assessment of the versatility matrix. Finally, the produc- mation system levels which has enabled an unprecedented
tivity of the manufacturing cell was evaluated by looking at increase in productivity; and the second, without which the
the new Overall Equipment Effectiveness (OEE) indicator to first would not have been possible, is developing human cap-
demonstrate the effectiveness of SMED in reducing start-up ital. By integrating these two processes, productivity increased
times and the fine-tuning of machinery. while times went down and organizational flexibility went up
[2, 3].
Keywords Cell . Production . Productivity . SMED . Time In the case of industry, this whole process necessitated the
development of innovative capacity within the company ori-
ented towards meeting market needs. By innovation is meant
the development of tools, equipment, and ways of working,
1 Introduction among other things, that allow for developing processes and
products that guarantee the best service and therefore compet-
Over the last 20 years, trade liberalization and the consolida- itive advantage for the company [4, 5].
tion of the global economy have brought with them an in- Introducing innovation will always require organizational
crease in competitiveness in diverse economic sectors, espe- change, as is the case, for example, with implementing soft
technologies as with the Toyota production model. Thus,
Single-Minute Exchange of Die (SMED), among others, will
always require some level of process innovation because de-
* Jonathan David Morales Méndez spite having defined components that must be implemented,
moralesmendez09@gmail.com the processes need to be transformed by rigorously
Ramón Silva Rodríguez researching the company and innovating within [2, 3, 6, 7].
ramonsilva@misena.edu.co SMED can be defined as a methodology for reducing set-
1
Industrial Engineer, Universidad Manuela Beltrán – UMB, up times which requires innovation [8], thereby enabling a
Bucaramanga, Santader, Colombia company to respond rapidly and effectively to fluctuations in
2
Mechanical Engineer, SENA Centro Industrial de Mantenimiento demand while at the same time eliminating waste and reduc-
Integral (CIMI), Girón, Colombia ing lot sizes [2, 6, 9, 10].
Int J Adv Manuf Technol

Nowadays, SMED is vital because it allows for the reduc- Next, the axle is milled or turned to give it a cylindrical
tion of set-up and fine-tuning time that has a direct impact on surface in accordance with the specific model using state of
productivity and production efficiency [11]. Reducing set-up the art computer numeric controlled (CNC) equipment, sup-
times means that productivity is affected in a controlled man- ported by computer programming which stores the exact spec-
ner and to the least degree possible, which becomes key when ifications for each model of interconnection axle.
a company manufactures a wide range of products. The piece then goes through the rolling process to produce
Despite the fact that SMED is nothing new, few studies on notches that are created using teethed blocks that pass along
the application of it are available and those that are have had the length of the axle in opposite directions, one above and
the exchange of ideas as their focus [12–15]. For this reason, one below until the whole piece is notched. This process
the objective of this document is to present the implementa- should be carried out at both ends of the interconnection axel.
tion of a pilot SMED process that was carried out in a metal- What follows is the machine process of making slots in the
working factory in the city of Bucaramanga, Santander, Co- notched surface where the retaining rings are located to pre-
lombia during 2012. The development of a SMED methodol- vent the outer joint yoke and the collar flange from separating
ogy for the manufacture of interconnection axles is shown: from the interconnection axle. A slotting lathe is used for this,
how it was possible to reduce set-up times and directly affect which is made up of two tool carriers where the fabricated
the efficiency and productivity of the production cell leading tungsten tools for each width of slot are located.
to the establishment of new indicators that show the scope of A critical process in the production line is that of heat
the work developed and the improvements that were obtained. treatment [17] by way of induction hardening machines that
This article is divided into four sections: (1) an introduc- use solid-state generators functioning at a frequency not lower
tion; (2) materials, methods, SMED methodology and its ap- than 3 kHz. The magnetic field vibrates at the
plication to an interconnection axle manufacturing cell; (3) abovementioned frequency causing intermolecular friction
results and discussion; and (4) conclusions. that raises the temperature in a matter of seconds. This effect
is generated using a very expensive electrolytic copper coil.
The tempering process [18] is done by heating the piece to
2 Materials and methods temperatures ranging between approximately 800 and 900 °C
and then instantly cooling it in a bath of water and a special
The implementation of SMED on a production line of one of tempering oil. The purpose of the heat treatment is to give the
the components of a homokinetic shaft, in this case an inter- piece a hard and tough exterior designed through engineering
connection axle, is shown in this article. This axle is a key and at the same time flexibility due to its soft core.
component given that it connects with the outer joint yoke (the It is during this process that the traceability of the axle is
component coupled to the wheel of the vehicle) at one end and registered to facilitate determining the specific manufacturing
the collar flange (component coupled to the vehicle’s gearbox) conditions during its performance.
at the other end. The complexity of the process rests on the programming
and set-up, given the number of devices used and the destruc-
2.1 Analysis of the interconnection axle cell tive testing that should be carried out on the previously tem-
pered piece. The destructive strength test [19] consists of cut-
The line that was looked at consists of 12 machines, 7 opera- ting the piece into the required number of sections indicated
tions and has the capacity to produce 40,000 interconnection by the control plan for the specific reference that is being
axles per month during 3 shifts of 8 h each, and a productivity programmed and then submitting each section to a polishing
of 8 pieces per man-hour. The line already implements stan- process at a sanding bench followed by a metallographic anal-
dard manufacturing programs based on the lean manufacturing ysis [20] in order to determine whether it complies with the
philosophy [16], including the 5Ss, standardized work, kaizen, tempering specifications for each part number.
poka-yoke, and autonomous maintenance, among others. Lastly, the interconnection axle is subjected to an inspec-
The interconnection axle is constructed from calibrated tion for cracks that can form during the heat treatment or could
steel rods in accordance with the requirements of each model; be a result of defects in the raw material. This is carried out
the raw material comes from international steel producers who using a special machine which generates a magnetic field
deliver lots of 6-m long rods. The manufacturing process for around the piece, showers it with a liquid in which magnetic
the interconnection axles begins with cutting the rods into the particles are suspended, and at the same time emits ultraviolet
correct segment lengths based on the specifications of the light which shows whether cracks or deposits exist that can
number of each part. adversely affect the functioning of the interconnection axle in
After cutting the rods, they are centered and the interconnec- the vehicle.
tion axle is redressed which implies giving it the final length for At this point, the final inspection must be carried out to
mounting it on the machines used in the following operations. ensure that they comply with all of the technical specifications
Int J Adv Manuf Technol

in the final inspection document or control plan [21]. A certi- Source: authors
fied expert operator for the production line must do this Since 66.66 h equals 43 % of stoppages, 100 % of stop-
activity. pages equals 155 h/month. In addition, the availability factor
The final stage is the packing of the interconnection axles, is as follows:
taking into account the packing instructions which specify
how many are in each crate, as well as how many can be Formula 2 Availability factor
packed in a batch so as to avoid congestion in the packing
area. In this way, ease of movement is ensured and accidents
can be avoided.
All material must be identified with its own certificate and A ¼ ð1080 h−155hÞ  1080h ¼ 0:85
proof of quality control signed by the work team leader (WTL). Source: authors
These documents are handed over in the warehouse where the Where A is the availability factor
product is organized according to an inventory system. Furthermore:
Upon analysis of the phases and each of the manufacturing
activities for the interconnection axles, it was found that the Formula 3 Efficiency to quality ratio
main challenge arises with the long programming times in the
cell using the tempering machine.
There are two tempering machines in the cell respectively
labeled TCC1 and TCC2. The set-up times for each machine E  Q ¼ 0:9
on average take 160 min. This implies a productivity index for
interconnection axles of 8.0 pieces/man-hour representing a Source: authors
capacity of 30,800 units a month with three shifts a day and Where E is efficiency, Q is quality
one operator per machine, meaning 3 operators on each tem- Taking into account that the OEE is:
pering machine.
Evidently, the above creates a restriction in the production Formula 4 OEE
process, which ideally should reach an optimum of 40,000
pieces, leading to an average deficit of 9200 pieces a month.
Looking at quarterly production, it was found that
OEE ¼ A  E  Q
reprogramming occurs randomly and on average 25 times
per month for each tempering machine. It was also found that
this value has a tendency to increase as a result of the diversity All these results are presented as percentages.
of products demanded by Colombian assembly plants. In oth- Looking at all these measures, it can be inferred that
er words, on average 4000 min (66.66 h.) per month are spent efficiency and quality remain stable with respect to the
on reprogramming with a tendency to increase. standards set by the company where 90 % is required at
The real OEE [22] for the interconnection axle line is de- minimum. The prime focus of this project is freeing up
termined by the cell with the induction hardening machines set-up time in order to improve the availability factor
TCC1 and TCC2. This indicator is affected by the set-up pro- for the machine so that more can be produced in the
cess and is currently at 77 %, compared with the company same amount of time, thus increasing the OEE and pro-
goal of 85 % for all mechanized lines at the plant. ductivity simultaneously.
In reality, the negative impact on the OEE is in the order of It is important to clarify that the set-up procedures for the
43 % with respect to machine availability. The other 57 % is tempering machines also implies destroying one or two pieces
due to other factors. Given that total available time is as in order to analyze their structure and tempered qualities. Even
follows: when implementing a SMED program, it will continue to be
necessary to carry out these destructive strength tests on the
Formula 1 Total available time tempered pieces.
Analyzing the situation, it is possible to deduce that the
bottleneck in the interconnection axle production line is the
induction hardening machines where reprogramming time
takes 160 min. It takes this long due to the complexity of the
h days week
TA ¼ 2mach  22:5  6 4 set-up which includes mounting and dismounting the coil in-
day week month
ducers, aligning the coils, and adjusting the tempering param-
h−mach eters such as heating time, cooling time, the temperature and
¼ 1080
month concentration of the tempering solution, the heat output, as
Int J Adv Manuf Technol

well as other time consuming tasks such as cutting, preparing, Step 2 Initial analysis of actual set-up
and analyzing the test samples. Here, we filmed the whole set-up process from the
moment that the last piece of the model in production
& Personnel involved in the process is completed until the moment in which the first piece
It was found that only 30 % of the operators are trained of the next model is produced.
to a versatility level (meaning that they have the skills to The next step was to bring the operator group to-
program the heat treatment machines) of 60 % [23]. gether with a stopwatch and a log so that they can
Considering that the tempering process is one of the carefully watch the video and note each activity that
most important and critical processes for the company, is carried out along with how long it takes. The sum
the above shows that the human resource is lacking in of all these times is the total time it takes for the set-
training to carry out this set-up. As a result, it is necessary up.
to develop technical competencies in a higher percentage Step 3 Classifying activities as internal or external
of operators in order to meet production needs while also Now, the research team classifies the activities as
guaranteeing a higher production flow when demand re- internal or external. This step in SMED requires de-
quires it. tailed attention. In this case, 7 core activities were
Other negative factors include a high staff turnover due identified:
to internal promotions or people voluntarily quitting. This
means having to train new operators all over again. & Internal activities
Lastly, it is important to mention that it is imperative to The theoretical concept, which says that the ma-
have the capacity to react to changes necessitated by ur- chine must have come to a complete halt before
gent orders and not be negatively impacted by the set-up performing the activity, was used to identify internal
times when attempting to supply a customer. In this re- activities. According to the set-up diagram and in-
gard, implementing a SMED methodology is vital so as to structions, these activities are as follows:
guarantee internal and external client satisfaction as well
as comply with the management goals and indicators of – Call up and load the program: This requires a screen
the organization. where the list of all the part numbers is registered
making it impossible to carry out this activity on
the equipment.
– Dismounting of previous devices and mounting and
2.2 SMED implementation aligning all the fixtures required to process the first
piece of the next model: Here, the operator needs to
Step 1 Selecting the process where SMED will be applied. use the entire chamber of the machine to manipulate
A number of prior visits were made to the plant to present and adjust the fixtures.
the project and focus attention on selecting an area or section & External activities
for the study. Detailed observation was made of the process, These activities can be carried out without stop-
and at the same time, trust was built with the group of opera- ping or turning off the machine. On the contrary, car-
tors involved in each step of the process described above [8, rying out various operations at the same time can
10]. speed up work.
Following this, a diagnosis was carried out primarily using
Pareto Analysis in order to identify the main causes for pro- – Print the control plan: The work team leader does this
duction stoppages. This confirmed that the set-up procedure while the operator continues with the set-up.
was one of the key problems in the production cell [24]. It was – Getting tools and fixtures ready: The work team lead-
possible to identify the deficiencies in the tempering process er must know the number of the part that is going to
in the line of production being studied as a result of this anal- be programmed as well as get the corresponding
ysis. tools and coil ready so that the operator can continue
During this stage, the research team applied basic tools with their activities and not lose time.
such as time keeping and observing the production process – Cutting the test piece: the operator moves to the cut-
in order to determine the key trouble spots in the manufactur- ting area; meanwhile, no piece should be produced
ing cell so that the emphasis of SMED could be on these. given that the result of the set-up is still unknown.
Time keeping data was registered for the critical points However, it is possible to make necessary adjust-
allowing meaningful comparisons to be made from which ments to the fixtures while programming the set-up.
new proposals were generated to reduce the problems in ques- – Metallographic analysis of the test piece: The opera-
tion and carry out standardization in each step of the process. tor takes the polished test pieces to the laboratory to
Int J Adv Manuf Technol

carry out the relevant analysis. Once this is done and line; by the same token, the ZZ2 sequence correlates
the results are known, the machine is ready for with the second document for the interconnection axle
production. production line.
– Validating the set-up: Lastly, the operator notes the The specific set-up activities described in the doc-
results obtained as well as the measurements and the ument relate to the same code assigned in the log for
machine parameters on the set-up log while the ma- this sheet. The activities to be realized by the first
chine has already begun to produce the pieces. operator are in the first document, and those to be
carried out by the second operator are found in the
Step 4 Standardization second document.
All of these activities are carried out in order to The first operator executes the activities that re-
prioritize which ones need to be standardized and quire interaction with the machine (internal activities),
improved. which are sequenced in a specific manner taking into
Now, the internal activities are examined with an account the time required for each one, while the sec-
eye to optimizing the order in which they are done in ond operator is charged with prior tasks and simulta-
the shortest possible time. Then, the external activi- neous set-up, with the goal of reducing down time.
ties are looked at as well and the order and time are Even so, these tasks are also standardized with the
specified. Given that the external activities are carried time needed for achieving each one.
out by a different operator from the one who carried All of the activities are properly diagrammed in the
out the internal ones, clear responsibilities are laid out document so that the operator can easily associate the
for each. activity with the image and is able to interpret it when
The above becomes a draft standard that is then doing the set-up. Basic Excel tools were used to create
trial run during the next three set-ups so as to do some the diagrams (see Fig. 1 for an example of the PMES
fine-tuning if necessary. Once the draft has been set- sheet).
tled, a new “set-up standard is written up.” Step 5 Validation
Once this has been done, an instruction manual for A general training was carried out for all personnel
the manufacturing standard is compiled, complete directly involved in the heat treatment process for the
with logs to ensure that the process complies with interconnection axle line as a way to validate the
all the steps as well as with the control plan. The most SMED methodology. The purpose of the training
important log is the one for the set-up and consists of was to roll out the necessary concepts and terminol-
all the related documents. The point of the standard- ogy used in implementing SMED with the group of
ization is to eliminate the waste of materials and time operators. Here, they learned about relevant aspects
that both affect productivity. such as history, background, development, and im-
All this documentation must be fully completed portant authors who developed and implemented the
and kept for at least 1 year so as to guarantee full tools in big companies. The process in which they
client knowledge about the product that they have were shown the step-by-step implementation of
acquired. Of course, it also serves as important evi- SMED was carried out with the operators of the tem-
dence for periodic audits that verify the traceability of pering machines.
the process. The operators, who themselves are experts on the
The implementation of the manufacturing stan- issues affecting the overall running of the line of pro-
dard leads to taking full advantage of the information duction, demonstrated great interest in the progress of
collected while carrying out SMED and the benefits the project and shared suggestions and expectations
accrue on the Standard Manufacturing Set-up Log during the explanation, thus demonstrating the im-
(PMES). The document is identified via a consecu- portance of their technical input in the project. At
tive sequenced number focused on standardizing the the end, the tools that would be used to implement
documents and being able to identify which produc- SMED were presented.
tion line it belongs to. Step 6 Training
The number sequence for this document is noted as It is vital in this activity to have all the necessary
such: PMES-I-XXX-ZZ1 and PMES-I-XXX-ZZ2,\ documents related to applying the SMED methodol-
and is interpreted “set-up manufacturing standard.” ogy to the set-up process, as well as refer to the
The “I” refers to the production line, the XXX se- PMES sheets and related documents that then be-
quence for the operation according to the process di- come the operators’ manual when they carry out the
agram, and the ZZ1 correlates with the first PMES programming.
document for the interconnection axle production It is vital that the training for standardization start
Int J Adv Manuf Technol

PMES ABBREVIATIONS CODE:

HEAT TREATMENT / TEMPERING N/P = Part Number EDITION:

SIMBOLS P.A.P = Set-up Point DATE:


LOGO Operator
environmental risk Quality control I = instrucon PAGE:
Safety

O.P.L = One Point Lesson OPERATION:

APPLICATIONS:ABC

Symbol
Reference
Activities Responsible Register Activity descriptions
documents

Start of opera on Operator

Place certain amount of pieces in the tray, press the black buon to
1 Wash and dry pieces Operator N.A.
start the wash cycle. Then dry with compressed air.

Remove the tempered


piece with the le hand
Standard and, using the right hand,
2 Locate the piece on E2 Operator N.A. locate the un-tempered
Operaon
piece in the support plate
at sta on 2.

Operang
Instrucons and Using both hands, press the side bu ons
3 Start cycle E2 Operator N.A. on control panel 2 at the same me in
Standard order to start cycle E2
operaon manual

The piece that has been removed from E2 should be briefly checked
to idenfy signs (tempering stains) that may represent imminent
4 Visual check of HT Operator Visual Aid VI0315 N.A.
risks in the heat treatment, mainly temper penetraon that can
cause cracks to appear.

Remove the tempered piece from E1


Standard with the le hand, and with the right
5 Locate piece on E1 Operator N.A. hand locate the piece removed from
Operaon E2 for opera on 90 in the localiza on
plate.

Operang
Instrucons and Using both hands, press the bu ons on
6 Start cycle E1 Operator N.A. the E1 control panel at the same me
Standard in order to ini ate the cycle.
operaon manual

Following the P.C./


Check HT with magnatest The tempered probe removed from E1 is put onto the bobbin of the
7 Operator Standard PAP and
magnatest in order to check that the shell is hard and effecve.
Operaon

The flange is placed on the Teflon base in the case of a closed flange,
According to
8 Stamp the piece Operator N.A. or on the tripod in the case of an open one, so that the piece
control plan
remains staonary during stamping.

The operator measures the diameter of the


Following widest groove and that of the widest crack
Check for cracks and
9 Operator operaon 60 of N.A. using the gauges specified in P.C. For the
grooves in test probe corresponding opera on located at the
control plan
stamping table.

Finish the Cycle

Fig. 1 Standard manufacturing set-up (PMES) log. Source: authors of the project

from the point of versatility of the operators whom up in the versatility matrix, represented by “L”. The
must have at minimum a 40 % level in accordance training has three basic steps:
with the company standard, and this must be backed In the first step, the operator observes the expert
Int J Adv Manuf Technol

carry out the standard operation; in the second, the was not difficult to do given that while the set-up takes place,
operator carries out the operation alongside the ex- the other line operators remain temporarily idle.
pert; and in the third, the operator carries out the
standard operation autonomously with the expert 3.2 Layout of the work space
auditing it. The expert uses the training checklist as
a guide, with a level of 60 %. This process is carried So as to reduce search times, it was concluded that it was
out in each workspace and according the items necessary to include key elements in the workspace such as
contained in the document. The expert must ensure tools, coils, accessories, and measuring equipment. Thus, it
that the operator executes each action as stipulated in became necessary to assign a specific place for each new
the training checklist before giving a passing grade. component and modify the workspace using an activity fo-
Each point of the training should be evaluated se- cused on the 5Ss.
quentially without leaving out any of them until
100 % of the training has been covered. It is recom- 3.3 Optimizing the cutting zone and preparing the test
mendable to repeat the training as many times, and as pieces
extensively, as necessary in order to guarantee opti-
mum performance on the part of the operator. Of The principal objective of this study also forced the optimiza-
course, the training should not affect the normal flow tion of processes carried out in supporting zones such as that
of the process. of cutting and preparing the test pieces. Circular saws and
Once the training has been completed, the work sanding drums with various sanding grains and velocities are
team leader should register a 60 % versatility rating in found in this zone. In order to effectively support the set-up
the matrix and represent this with a “U” for the new process, it was deemed necessary to carry out a complete
operator able to set-up the tempering machines TCC1 maintenance program of the machines and include them in a
and TCC2 on the interconnection axle line. preventative maintenance program, as well as improve the
The versatility matrix (see Fig. 2) should be kept layout of the zone. All of this was necessary in order to ensure
up to date and signed by the work team leader and the more effective service, in other words, achieve a more rapid
production coordinator as supporting documentation flow of the test pieces through the analysis process. This re-
for both internal and external audits. sulted in reducing not only the handling time for the test pieces
but also for all the other pieces in the factory that require
support from this zone.

3 Results and discussion 3.4 Production started with quarantined pieces

At this stage, it was possible to observe the differences in how The starting assumption here is that once a test piece is pre-
each of the operators in the three different shifts carried out the pared for the metallographic analysis (cutting the piece and
set-up process. Important differences came to light in terms of polishing it on the sanders for this purpose), it is possible to
the sequence in which they did things. Also, the skill and ease observe the boundary between the soft core and the effective
with which activities were undertaken had a direct bearing on shell (tempered zone). Thus, it is possible to measure the depth
the final result and reflected personal qualities. For example, of each zone and conclude with a reasonable degree of success
one operator was much better at adjusting the fixtures and the whether satisfactory results will be achieved during the metal-
coil, while another was more skilled at getting the piece ready lographic testing or not. In this way, production could begin
for metallographic analysis. These differences facilitated the immediately, and in so doing, convert the time taken for me-
tailoring of the subsequent standardization training of those tallographic testing into productive time. Naturally, these
charged with the set-up process. pieces would be kept in quarantine until such time as the
verification requirements have been met. With positive verifi-
3.1 External and internal activities cation results, these pieces would then leave quarantine and
enter into the normal production process, and by so doing,
The understanding of what external and internal activities are increase the total number produced. This test procedure leads
lead the group to establish the need for a second set-up oper- to a cache of quarantined pieces that are clearly marked and
ator during each production shift. In other words, this lead to specially controlled with this purpose in mind.
establishing a primary operator specialized in the machine and The above enters into a process of repeated trials and anal-
a support operator who specializes in the metallographic test- ysis carried out by the company’s respective engineering au-
ing. When the two are well synchronized, the optimal total thorities at an international level for later approval. Internally,
time can be guaranteed. Giving rise to the support operator the trials will continue to be documented with an eye to
Int J Adv Manuf Technol

Fig. 2 Versatility matrix. Source:


authors VERSATILITY MATRIX
Revision Date _______________________________
Operation
Operator Milling Milling
Perforaon Threading Tempering Grinding
cycle 1 cycle 2

Carlos Pinto

Armando Castro

Nicolas Vega

Hugo Pérez

Pedro Rodriguez

Juan Santos

Level 20% Basic operator training.

Level 40% Operator able to carry out the operaon

Level 60% Operator trained to carry out set-up

Level 80% Operator trained to train and do rework.

Level 100% Operator applies Lean Manufacturing

generating sufficient evidence to back up this change and with the internal activities. By freeing up set-up time, produc-
achieve a guaranteed quality result at the same time. tivity was increased from 8 to 8.8 pieces/man-hour.
The final result can be seen in the development of
the OEE indicator for the interconnection axle produc-
3.5 Adaptability tion line for the years 2010 and 2011 before SMED was
implemented, and then the positive impact generated by
The company uses the term adaptability percentage to indicate SMED from May 2012 onwards. The other thing that
what percentage of everything that is done or learned can be becomes equally clear is the decrease in the percentage
applied to other products and/or processes. Given that all of of cumulative machine stoppage causes when compared
the products produced in the factory require induction hard- with the initial Pareto diagram drafted during the anal-
ening, it can be concluded that the adaptability percentage for ysis phase of this project. In that diagram, set-up was
other products is 100 %. This then requires a well-structured the foremost cause of stoppages followed by unforeseen
plan for optimizing tempering processes which objectively maintenance.
demonstrates improvements in productivity for the plant as a Thanks to SMED, the consolidated stoppage percentage
whole. With the results of this study, there should be complete due to set-up was reduced by 22 % because the company
institutional backing for such a plan. implemented action plans based on SMED in the tempering
The application of the SMED methodology generated a cell. This 22 % equals a reduction in machine stoppage from
set-up time of 33 min if the time for each of the internal 66.6 to 34 h, meaning that the machine availability factor rose
activities is summed. A percentage of the external activities from 85 to 94 % leading to an OEE of 85 % and thus meeting
are pre-set-up, and the other percentage occurs simultaneously the target established by the company.
Int J Adv Manuf Technol

Unforeseen machine maintenance passed to the first place 4 Conclusions


causing 31 % of machine stoppages and thus having the
greatest impact on the OEE performance. The time study clearly identified activities that are car-
Lastly, the resulting time saved due to applying ried out which do not add value to the product, but on
SMED can be summarized in Fig. 3. The first column the contrary, constitute down times. The respective cor-
is a flow chart of all the activities that are included in rections were made by applying new tools and methods
the application of SMED. The second column shows the that guarantee the company’s competitiveness in the na-
reduced time for each activity and the corresponding tional and global markets.
percentage for the improvement, while the third block Applying the SMED program to set-up operations reduced
of columns shows the contribution generated for other corresponding times and in do doing achieved an increase in
production zones in the factory due to time saving that the OEE from 77 to 85 %. In addition, productivity increased
can be passed on to other zones such as the preparation from 8 to 8.8 pieces/man-hour.
of test pieces and the metallographic test laboratory By creating and applying the HMES and PMES logs, it was
among others. This speeds up production processes on possible to standardize the procedures and consequently re-
other mechanized production lines and the assembly op- duce programming times and increase productivity for this
eration in general. production line.

Contribution to other zones


FLOW CHART TIME (Minutes) Improvement
in the plant

START BEFORE SMED AFTER SMED Time Time saved for


saving Percentage 25 programs Observations
Internal External Internal External (Min) (Min)

Call up and load the program: This requires a screen where


the list of all the part numbers is registered making it 20 5 13 12 48.0%
impossible to carry out this activity on the equipment.

Dismounting of previous devices and mounting and


aligning all the fixtures required to process the first piece of Operator time
the next model: Here the operator needs to use the entire 45 20 25 55.6% 625 available to
chamber of the machine to manipulate and adjust the other areas
fixtures.

Print the control plan: The work team leader does this wile Document
15 10 5 33.3% 125
the operator continues with the set-up. printing zone

Getting tools and fixtures ready: The work team leader


must know the number of the part that is going to be
programmed as well as get the corresponding tools and coil 15 25 30 10 25.0%
ready so that the operator can continue with their activities
and not lose time.

Cutting the test piece: the operator moves to the cutting


area, meanwhile no piece should be produced given that the Cutting and
result of the set-up is still unknown, however, it is possible 40 25 15 37.5% 375 polishing
to make necessary adjustments to the fixtures while zone
programming the set-up.

Metallographic analysis of the test piece: The operator takes Laboratory


the polished test pieces to the laboratory to carry out the and
30 20 10 33.3% 250
relevant analysis. Once this is done and the results are metallographi
known the machine is ready for production. c testing zone

Validating the set-up: Lastly, the operator notes the results


obtained as well as the measurements and the machine
10 5 10 5 33.3%
parameters on the set-up log while the machine has already
begun to produce the pieces.

END

Fig. 3 Source: authors


Int J Adv Manuf Technol

After various meetings with the personnel directly involved 8. Shingo S, Dillon AP (1985) A revolution in manufacturing: the
SMED system. Productivity press, Cambridge, Massachusetts, p 30
in the production process, the activities were presented and a
9. Carrizo Moreira A, Silva Pais GC (2011) Single Minute Exchange
training plan was rolled out, taking advantage of the adapta- of Die: a case study implementation. J Technol 6(1):129–146
tion to change on the part of the operative personnel on the 10. Shingo S (2000) Sistema de Troca Rapida de Ferramenta. Bookman
line in order to guarantee relevant feedback on this SMED Companhia Ed, Porto Alegre, p 328
support tool. Within a global company, it is necessary not only 11. Holweg M (2006) The genealogy of lean production. J Oper Manag
25:420–437
to implement new tools on a daily basis but also to ensure a 12. Fogliatto F, Fagundes P (2003) Troca rápida de ferramentas:
generalized attitude of leadership which cultivates a culture of proposta metodológica e estudo de caso. Gestão Produção 10(2):
continuous improvement in worker performance. 163–181
13. McIntosh R, Culley S, Mileham T, Owen G (2000) A critical eval-
uation of Shingo’s ‘SMED’ (Single Minute Exchange of Die) meth-
odology. Int J Prod Res 38(11):2377–2395
14. Monden Y (1984) Produção sem estoques - Uma abordagem
References prática ao sistema de produção da Toyota. INAM, Sao Paulo
15. Satolo E, Calarge F (2008) Troca Rápida de Ferramentas:
1. Zambrano Vargas S (2013) La competitividad en los sectores estudo de casos em diferentes segmentos industriais. Exacta
manufacturero y de servicios. Estudio de caso. Criterio Libre 17: 6(2):283–296
177–192 16. Ndahi, H. 2006. Lean manufacturing in a global and competitive
2. Carrizo Moreira A, Torres Garcez PM (2013) Implementation of market. Technology Teacher, November 14–18.
the Single Minute Exchange of Die (SMED) methodology in small 17. Efd Induction. 2012. Aplicaciones de calentamiento por inducción.
to medium-sized enterprises : a Portuguese case study. Int J Manag España, 6–8
30(1):66–88 18. Higuera O, Florez L, Arroyave J (2008) Diseño de un sistema de
3. Womack, J.P., D. T. Jones. 1994. From lean production to the lean enfriamiento para temple de aceros. Sci Tech 14(39):170–175
enterprise. Harvard Bulletin Review, 93–104 19. Universidad de Buenos Aires. 2012. Ensayos Destructivos. Buenos
4. Dantas J, Carrizo Moreira A (2011) Novas Perspetivas Aires, 15
Tecnológicas nos Processos de Conceção e Desenvolvimento. O 20. Escuela Colombiana de Ingeniería Julio Garavito. 2011.
Processo de Inovação, Lisboa Metalografía protocolo. Bogotá, 23
5. Ibarra Miron S, Sarache Castro W, Suárez Garcia M (2004) La 21. McGovern SM, Gupta SM (2011) Disassembly line: disassembly-
estrategia de producción: una aproximación al nuevo paradigma line just-in-time in balancing and modeling. McGraw-Hill, New
en investigación en manufactura. Revista Universidad Eafit York, Chapter 27
40(136):65–77 22. De Ron A, Rooda J (2006) OEE and equipment effectiveness: an
6. Bessant J, Buckingham J (1993) Innovation and organizational evaluation. Int J Prod 44(23):4987–5003
learning: the case of computer-aided production management. Br 23. Invernizz, N. 2002. Trabajo polivalente y conocimientos
J Manag 4(4):219–235 sobre la producción. Tendencias en la industria brasilera.
7. Pinto Jiménez, I de J., R. Fernández Ortega, L. Martínez, and G. Revista Iberoamericana de Ciencia, Tecnología, Sociedad e
Kavffmann. 2006. Análisis del énfasis en la innovación en la Innovación, 3, 7.
implantación del ‘MIDDLE-UP-DOWN 24. Pérez-Duque P, Suárez-Moreno OE (2010) Aplicación para
MANAGMENTMODEL’. Un estudio evolutivo en las empresas el Diagnóstico y Control de Sistemas Productivos. Ciencia
manufactureras del país Vasco. Estudios Gerenciales, 2003, 37–60 PC 2:88–100

You might also like