Professional Documents
Culture Documents
C E L I A E. L E U T E R I O,
Complainant,
POSITION PAPER
Offices, unto this Honorable Board, most respectfully submits the instant Position Paper and
This case is a complaint filed by Celia E. Leuterio for the reimbursement of the
amount of PhP9,574,132.66, plus interest, representing the full payment she made for the
purchase of an office condominium unit, with two (2) parking slots, in a condominium project
denominated as AIC Empire Tower located at ADB Avenue corner Sapphire and Garnet
Streets, Ortigas Center, Pasig City, Metro Manila, and for damages, attorney's fees and cost of
the suit.
1
PARTIES
legal age, Filipino and resides at No. 1289 Pablo Ocampo Sr. corner Lemery Streets, Manila.
“respondent”) is a private domestic corporation duly organized and existing under and by virtue of the laws of
the Republic of the Philippines with principal office address located at AIC Realty Corporation Building, Garnet
STATEMENT OF FACTS
office condominium unit and two (2) parking slots in one of respondent’s condominium
unit”) to be built at ADB Avenue corner Sapphire and Garnet Streets, Ortigas Center, Pasig
complainant and respondent’s Vice-President for Finance, Val John E. Perez, wherein the
PhP120,615.01 for forty-two (42) months and the remaining amount of PhP2,684,908.60 shall
be paid upon turnover of the condominium unit. A copy of the said Reservation Agreement is
2
5. Around the same time, complainant purchased two (2) other units from AIC
Realty Corporation, also on a pre-selling basis, to wit: Unit 611 at AIC Gold Tower located at
Garnet Road, Ortigas Center, Pasig City, for turnover in 1998, and one (1) unit at Waldorf
Towers supposed to have been built along Roxas Boulevard near the U.S. Embassy and for
turnover in 1998.
6. AIC Gold Tower suffered delays but was finally turned-over in May 1999. AIC
Waldorf Tower did not get off the ground inspite of the fact that complainant had already paid
PhP4,111,946.00.
construction works on AIC Waldorf Tower had been stopped indefinitely which respondent
8. At around this time, the AIC Empire Tower project had also slowed down and
no firm commitment on the turnover date of the condominium unit was ever given to
complainant.
Waldorf. Respondent, on its part, suggested that these payments be applied in full to the
scheduled amortization on the condominium project at AIC Empire Tower and the final
balance on AIC Gold Tower. Respondent further reassured complainant that work on AIC
10. On 28 April 1999, complainant therefore agreed that the payments she already
made for the condominium unit in AIC Waldorf Towers amounting to PhP4,111,946.00 be
apportioned and applied as payment for the other condominium units she purchased, to wit:
3
(a) PhP433,963.25 as first payment for Unit 611 of AIC Gold Tower Condominium; (b)
PhP1,362,072.64 for the condominium unit to update its monthly amortization. As to the
remaining amount of PhP2,315,911.06, respondent requested that the same be refunded to her.
A copy of the letter dated 28 April 1999 containing the aforesaid request is attached hereto as
11. Respondent, on its part, proposed that all payments made for the condominium
unit at AIC Waldorf Towers would be apportioned and applied to the unpaid amortization for
respondent as to how the payments made for the condominium unit at AIC Waldorf Towers
13. Finally, complainant agreed to the proposal of respondent that all payments be
applied to the outstanding account of the former in the condominium unit as stated in the
latter’s letter dated 16 August 2000 to complainant. A copy of the said letter is attached hereto
14. For more than eight (8) agonizing years, complainant waited for respondent to
deliver the condominium unit to her. In fact, complainant made several requests for an update
of the status of the condominium project because she noticed that no major development had
been introduced therein since she signed the Reservation Agreement. Copies of complainant’s
letters to respondent dated 27 February 2002 and 30 May 2002 are attached hereto as
15. Respondent, on the other hand, gave the complainant the same response that
construction works in the condominium project is on-going but it cannot give a specific date
4
as to when the same will be completed.
16. On 23 May 2002, respondent issued a Certification stating therein that since 30
August 2000, complainant had already paid, in full, the purchase price of the condominium
unit. A copy of the said Certification is attached hereto as Annex “F” to form an integral part
hereof.
17. Fed up with the lame excuses of respondent, complainant finally decided to
demand for the return of all the payments she had made, including interest.
18. This constrained complainant to refer the matter to the undersigned Law
Offices and a letter dated 16 June 2003 was sent to the respondent, personally and via
registered mail, demanding for the return of all payments made by the former in the aggregate
ONE HUNDRED THIRTY-TWO & 66/100 (PhP9,574,132.66) within ten (10) calendar
days from receipt of the said letter. Copies of the registry receipt and aforesaid letter are
attached hereto as Annexes "G" and "H", respectively, to form integral parts hereof.
complainant’s counsel and assured the latter that he would send a written proposal for the
20. Several weeks later, the undersigned Law Offices received a letter dated 10
July 2003 from Mr. Untalan stating therein respondent’s proposal. A copy of the said letter is
21. After conducting an ocular inspection of the condominium units that are being
5
offered by respondent as settlement for her demands and deliberating on the latter’s proposal,
complainant decided to reject the same and demanded for the complete refund of all payments
22. On 15 August 2003, a letter dated 08 August 2003 was sent by the undersigned
Law Offices to respondent, via DHL courier, stating therein complainant’s decision and gave
the former five (5) calendar from receipt of the said letter to refund all payments made by
complainant. Copies of the said letter and receipt issued by DHL courier are appended
herewith as Annexes “J” and “K”, respectively, to form integral parts hereof.
23. The grace period stated in the aforesaid letter had lapsed but respondent failed to abide with
24. This constrained the complainant to lodge a Complaint dated 25 August 2003
against respondent before this Honorable Office for the refund of PhP9,574,132.66, plus
damages; PhP50,000.00 as attorney's fees plus the total amount of appearance fees incurred;
25. The respondent filed its Answer dated 29 September 2003 and denied
complainant’s claim for reimbursement for lack of basis because the Reservation Agreement
appended to the latter’s Complaint was not allegedly signed by any of the representatives of
26. The claim for damages was also denied by respondent on the ground that
complainant allegedly failed to prove the factual basis for the same.
27. Lastly, respondent foisted that complainant is not entitled to attorney’s fee
6
because according to the former, the same “is only granted in exceptional cases”.
28. The instant case was set for preliminary conference on 30 October 2003.
Unfortunately, the possibility of reaching an amicable settlement had failed and both parties
were required to submit their respective position papers and draft decisions.
ISSUES:
I.
II.
ARGUMENTS/DISCUSSION:
The afore-quoted provision is clear and casts no doubt for ambiguous interpretation.
After due notice, the condominium unit buyer may desist from remitting further payments to
the owner or developer for failure of the latter to develop the condominium project according
to the approved plans and within the time limit for complying with the same. The buyer, at his
option, may ask for a reimbursement for all payments made with legal interest.
Applying the afore-quoted provision in the instant case, complainant has more reason
to demand a return of all payments she made considering that she had already paid, in full, the
purchase price of the condominium unit. Unfortunately, respondent failed to live up with its
Complainant waited for more than eight (8) agonizing years in order for the
respondent to deliver what was agreed upon. In fact, complainant made several requests for an
update of the status of the condominium project because she noticed that no major
development had been introduced therein since she signed the Reservation Agreement.
Complainant’s letters to respondent dated 27 February 2002 and 30 May 2002 (attached
8
957, to demand reimbursement on the ground that respondent failed to develop the
condominium project according to the approved plans and within reasonable time.
As eloquently held in the case of Casa Filipina Realty Corporation vs. Office of the
President (241 SCRA 165; February 7, 1995), "private respondents' refusal to continue
paying the amortization is thus based on two principal grounds: non-development of the
subdivision and encumbrance of the property subject of the sale which became apparent to
the buyer only after conducting his own investigation. As such, the case falls squarely
It is also clear form the wordings of Section 23 of P. D. No. 957, that the law vests
upon the buyer the option to demand reimbursement of the total amount paid or to wait for
further development of the subdivision or unit (Relucio vs. Brillante-Garfin, 187 SCRA
The law explicitly provides that the reason why P. D. 957 was enacted is precisely for
subdivision and condominium sellers and operators…" (P. D. No. 957; Casa Filipina
Realty Corporation case, supra). Hence, without a doubt, the complainant is entitled to be
protected under this law as her case falls squarely within the ambit of P. D. No. 957.
Truly, respondent should not only be condemned to return all payments made by the
complainant including interests, damages and cost of instituting the instant suit, but should
likewise be reprimanded and fined by this Honorable Office for engaging in fraudulent
schemes.
9
---------------------------------------------
Respondent cannot even allege that the Reservation Agreement was not signed by any
of the representatives of respondent and therefore, there was no contract to speak of in the
first place. Such flimsy argument can be easily disputed by a simple perusal of the
Reservation Agreement itself. It can be seen therein that a representative of respondent signed
for and in behalf of the latter beside the name of Val John E. Perez, Vice-President for Finance
Nonetheless, assuming that the individual who signed for and in behalf of respondent
was not authorized to do so and for that reason the Reservation Agreement was nullified and
set aside, the same would not negate the contractual relation that exists between complainant
and respondent.
The letters and correspondence between the parties are more than sufficient to prove
the existence of the contract they entered into. In fact, there was even a Certification dated 23
May 2002 (appended as Annex “F” herein) issued by respondent attesting, in clear and
concise terms, that complainant had already paid, in full, the purchase price of the
“C E R T I F I C A T I O N
This is to further certify that as of August 30, 2000, the unit has
already been fully paid. (Underscoring ours)
10
LEUTERIO.
(Signed)
PATERNO M. ABELLERA
President”
commitment on its part (the part of the respondent) as to the date of delivery of the subject
unit”.
Respondent made itself clear to complainant during and after the negotiation of the
sale of the condominium unit that the same shall be delivered to the latter sometime in the
middle of 1999. That is why the amortization of the condominium unit was spread until June
1999 in order that the full payment of the purchase price would coincide with the completion
Assuming, ex gratia argumenti, that there was no period agreed upon by both parties
insofar as the delivery of the condominium unit is concerned, fixing the same is not feasible
as the same would result only into further delay and multiplicity of suits. As eloquently held
by the Honorable Supreme Court in the case of Central Philippine University vs. Court of
"Hence, there is no more need to fix the duration of the term of the
obligation when such procedure would be a mere technicality and formality
and would serve no purpose than to delay or lead to an unnecessary and
expensive multiplication of suits."
11
To repeat, under pain of being redundant, the complainant had waited for more than
eight (8) years in order for the respondent to deliver the condominium unit. By anyone’s
standard, such length of time is more than enough for respondent to comply with its
obligation.
More importantly, there is already an admission on the part of the respondent that the
condominium project would no longer be constructed. The act of respondent, through its
complainant as settlement for her claim for reimbursement is a glaring proof that respondent
In view of the foregoing, fixing a period for respondent to construct the condominium
project and eventually deliver the condominium unit of complainant is not only preposterous,
An assiduous examination of the facts of the case will readily show that respondent
had incurred delay in the performance of its contractual obligation for its failure to construct
and complete the condominium project. As a consequence, complainant is not only entitled to
a refund of all payments she made, but she is also entitled to indemnity for the damages she
suffered as well.
The law expressly provides that "those who in the performance of their obligation
are guilty of fraud or delay and those who in any manner contravene the tenor thereof, are
12
liable for damages" (Article 1170 of the Civil Code; Barzaga vs. Court of Appeals, 268
SCRA 105)
It is worth stressing that complainant was able to comply with what was incumbent
upon her, i. e., payment of the purchase price. Respondent, on the other hand, has the
concomitant obligation to start developing and constructing the condominium project, and
deliver the condominium unit agreed upon within the stipulated period.
However, several years had already passed and no progress can be seen on the project
site as the condominium project remained undeveloped. As held in the case of Gutierez
Hermanos vs. Oria Hermanos (30 Phil. 491), "if one party performs, and the other does
not, the latter would be in default." The act of the respondent in abandoning the
In reciprocal obligations, as in the instant case, default on the part of one begins from
the moment the other party fulfills with what is incumbent upon him (Causing vs. Benser, 37
Phil. 417). Since the respondent failed to comply with its obligation, complainant has every
right to exercise her option to rescind her contractual ties with the former.
be indemnified for the damages she suffered in view of all the unnecessary anxieties and
inconveniences she has to go through as a result of the unwarranted acts of the former.
Complainant parted away more than nine (9) million pesos of hard-earned money without
Further, "a debtor who incurs delay or default is liable for damages plus interest,
13
Insurance Co., Inc. vs. Court of Appeals, G. R. No. 59919, November 25, 1986).
Attorney's fees may be granted based on the grounds enumerated under Article 2208
"x x x x
x x x x"
In the instant case, complainant was forced to engage the services of the undersigned
Law Offices to seek redress and protect her interest. Complainant has to go through the
tedious process of lodging a complaint just to enforce her rightful claims. More so, it was
quite clear that respondent acted in gross and evident bad faith in its continued and unjustified
With the foregoing, complainant should and ought to be paid by respondent for all
legal and litigation expenses the former incurred in lodging the instant complaint.
PRAYER
14
WHEREFORE, above premises considered, it is most respectfully prayed of this
Honorable Board that a Decision be handed down ORDERING the respondent to PAY the
complainant:
incurred; and
OTHER RELIEFS, just and equitable under the foregoing premises, are likewise
ALEXIS M. ESCOBEDO
Roll of Attorney No. 46807
PTR No.: 40718643: 30.01.03: Q.C.
15
IBP No.: 576148: 01.16.03: Sorsogon
16