(A) 0.90 m3
(B) 0.94 m3
(C) 0.98 m3
(D) 1.00 m3
Answer: Option B
Answer: Option D
(A) 10 cm
(B) 15 cm
(C) 20 cm
Answer: Option A
4.If the formation level of a highway has a uniform gradient for a particular length, and the ground is
Answer: Option D
5.A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick
(A) 500 m3
(B) 1000 m3
(C) 1500 m3
(D) 2000 m3
Answer: Option C
6.While estimating the quantities for the construction of a building, the correct metric unit is
Answer: Option D
Answer: Option D
Answer: Option D
(B) 25 cm × 13 cm × 7.5 cm
(C) 19 cm × 9 cm × 9 cm
(D) 20 cm × 10 cm × 10 cm
Answer: Option C
11.The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30
cm, is termed as
(A) Excavation
(C) Cutting
(D) Surface excavation
Answer: Option D
12.In long and short wall method of estimation, the length of long wall is the centre to centre
Answer: Option B
13.The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
(A) 1.5 m3
(B) 2.5 m3
(C) 3.5 m3
(D) 5.0 m3
Answer: Option D
Answer: Option A
Answer: Option D
16.Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
(A) 2.0 %
(B) 2.5 %
(C) 4.0 %
(D) 5.0 %
Answer: Option D
17.The expected out turn of 2.5 cm cement concrete floor per mansion per day
(D) 10 sqm
Answer: Option C
Answer: Option D
Answer: Option A
Answer: Option A
Question No. 51
(A) 2.5 sq m
(B) 4.0 sq m
(C) 6.0 sq m
(D) 8.0 sq m
Answer: Option D
23.The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective
length L, is
(A) L + 0.42 d
(B) L + (2 × 0.42 d)
(C) L - (0.42 d)
(D) L - (2 × 0.4 d)
Answer: Option B
Question No. 59
(B) D/3 [first area + last area + 4 Even area + 2 odd areas]
(C) D/3 [first area + last area + 2 Even area + 4 odd areas]
Answer: Option B
Answer: Option D
Answer: Option D
Answer: Option D
(A) 100 mm
(B) 150 mm
(C) 200 mm
(D) 175 mm
Answer: Option B
Answer: Option A
(A) 20 minutes
(B) 25 minutes
(C) 30 minutes
(D) 40 minutes
Answer: Option C
28.If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway
(A) B + d + Sd
(B) Bd + Sd2
(C) B × d - Sd1/2
Answer: Option B
(A) 70 cm
(B) 75 cm
(C) 80 cm
(D) 90 cm
Answer: Option B
30.The expected out turn for earth work in excavation in ordinary soil per workman per day is
Answer: Option C
31.The expected out turn of brick work in cement mortar in foundation and plinth per mason per
day, is
(A) 1.00 m3
(B) 1.25 m3
(C) 1.50 m3
(D) 1.75 m3
Answer: Option B
32.The height of the sink of wash basin above floor level is kept
(A) 60 cm
(B) 70 cm
(C) 75 cm to 80 cm
(D) 80 cm
Answer: Option C
33.For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement
required, is
(A) 0.200 m3
(B) 0.247 m3
(C) 0.274 m3
(D) 0.295 m3
Answer: Option C
(A) Cub. m
(B) Sq. m
(C) Metres
Answer: Option B
Answer: Option A
35.For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
(A) 0.90 m3
(B) 0.94 m3
(C) 0.98 m3
(D) 1.00 m3
Answer: Option B
(A) 100 %
(B) 75 %
(C) 50 %
(D) 25 %
Answer: Option C
(A) 0.25 kg
(B) 0.50 kg
(C) 0.75 kg
(D) 1.00 kg
Answer: Option D
Answer: Option B
1. schedule of rates
2. tender
3. analysis of rates
Correct Answer: A
HMWS&SB 2020]
1. mensuration
2. quantity surveying
3. valuation
4. estimating
Correct Answer: B
2020]
1. centering
2. formwork
3. shuttering
4. staging
Correct Answer: C
HMWS&SB 2020]
1. sand filling m3
2. rock excavation m3
Correct Answer: C
1. 11,520
2. 115.2
3. 1,152
4. 1,15,200
Correct Answer: C
HMWS&SB 2020]
spreading or heaping
1. C and D only
2. A and C only
3. A and D only
4. A and B only
Correct Answer: D
1. 8.142 m3
2. 81.42 m3
3. 814.2 m3
4. 8142 m3
Correct Answer: B
HMWS&SB 2020]
1. m2
2. m3
3. lumpsum
4. m
Correct Answer: A
2017]
A. 3 years
B. 2 years
C. Every year
1. Numbers
2. Area in sq.m
3. Volume in cu.m
4. Weight in kgs
Correct Answer: D
surveyor 2017]
Correct Answer: A
2017]
Correct Answer: D
49.Which of the following gives full description
1. Estimate
2. Specification
3. Rates
Correct Answer: B
1. Approximate estimate
2. Detailed estimate
3. Abstract estimate
Correct Answer: B
1. Analysis of rate
2. Rate at source
4. Local rates
Correct Answer: A
surveyor 2017]
1. Clearance
4. Conservation
Correct Answer: B
(TSPSC-AEE-2018)
Correct Answer: A
AE-2018)
Correct Answer: C
(1) duration
(2) constraint
(3) float
(4) event
Correct Answer: C
2015]
2015]
1.Analysis of rates
2.Tender
3.Schedule of Rates
Correct Answer: C
A.15.33 days
B.30.66 days
C.14.66 days
D.29.33 days
Correct Answer: A
building
building
building
Correct Answer: C
60.Which one of the following is relatively
1.service unit
Correct Answer: D
Correct Answer: C
Correct Answer: A
2017]
(2) BOT
(4) Turnkey
Correct Answer: B
(1) Annuity
(2) Dividend
Correct Answer: D
Correct Answer: A
Correct Answer: B
72.Detailed specifications includes[TSPSC AE
2015]
execution of work
materials
Correct Answer: D
items of work
items of work
of work
of work
Correct Answer: C
1. (b/d+nd2)L
2. (bd+nd2)L
3. (bd-n√d)L2
Correct Answer: B
20/Km[TSPSC AE 2015]
1. Rs. 800=00
2. Rs. 700 = 00
3. Rs.1500=00
4. Rs. 2000= 00
Correct Answer: C
1. 0.01 Cu.m
2. 0.05 Cu.m
3. 0.005 Cu.m
4. 0.001 Cu.m
Correct Answer: A
76.Calculate the quantity of earth work by midordinate method, for 200 m length of a
1. 3800 Cu.m
2. 3900 Cu.m
3. 3950 Cu.m
4. 4000 Cu.m
Correct Answer: B
Cu.m[TSPSC AE 2015]
1. Rs. 5,40,000
2. Rs. 54,000
3. Rs.18,000
4. Rs.5,400
Correct Answer: D
per m3
per m2
given[TSPSC AE 2015]
1. Rs. 50,400=00
2. Rs. 1,87,500=00
3. Rs. 1,37,100=00
4. Rs. 2,37,900=00
Correct Answer: D
1. Group-A
2. Group-B
3. Group-C
4. Group-D
Correct Answer: C
11-12-2020 AN]
1. 0.1 m2
2. 0.5 m2
3. 0.01 m2
4. 1.0 m2
Correct Answer: A
11-12-2020 AN]
Correct Answer: D
1. 4,875 m3
2. 3. 452 m3
3. 4.158 m3
4. 7.656 m3
Correct Answer: C
1. per m2
2. per m3
3. per metre
4. per number
Correct Answer: B
2. specifications
4. contingencies
Correct Answer: A
30-10-2020 FN]
1. 80% - 95%
2. 50% - 65%
3. 65% - 80%
4. 35% - 50%
Correct Answer: B
86. The unit of measurement for a half brick
1. square meter
2. cubic meter
3. meter
4. cubic foot
Correct Answer: A
30-10-2020 FN]
2. detailed estimate
4. preliminary estimate
Correct Answer: B
29-10-2020 FN]
1. insurance
2. bad debts
3. sinking fund
4. repairs fund
Correct Answer: C
4. lease in perpetuity
Correct Answer: A
2. formwork
3. excavation / earthwork
4. brickwork in manholes
Correct Answer: C
29-10-2020 FN]
slab
Correct Answer: C
92. Which of the following methods is an initial
28-10-2020 AN]
Correct Answer: D
28-10-2020 AN]
1. Corridor
2. Courtyard
3. Verandah
4. Foyer
Correct Answer: B
1. 12 m
2. 16 m
3. 18 m
4. 11 m
Correct Answer: C
1. Crossing method
2. Mid-Section method
28-10-2020 AN]
1. Trapezoidal method
2. Prismoidal method
3. Mid-section method
4. Crossing method
Correct Answer: D
97. the estimate prepared on the basis of the
JE 25-09-2019 FN)
Correct Answer: D
25-09-2019 FN)
(a) revaluation
(b) devaluation
(c) amortisation
(d) depreciation
Correct Answer: D
99. the unit of measurement is square metre in
Correct Answer: D
Correct Answer: D
Correct Answer: C
23-09-2019- FN)
Correct Answer: C
(a) valuation
Correct Answer: A
1) Collapsible gates
2) Rolling shutters
3) Steel doors
Correct Answer: D
24-01-2018 FN]
aggregates
aggregates
aggregates
aggregates
Correct Answer: D
106. The volume of an embankment having a
1)H[(A1+A4)/2+A2+A3]
2) H[(A2+A4)/4+A2+A3]
3) L[(A1+A4)/2-A2+A3]
4) L/3[(A1+A4)+2(A2+A3)]
Correct Answer: A
1) Brick work
2) Concrete work
3) Excavation work
4) Plinth
Correct Answer: D
24-01-2018 FN]
1) Detailed estimate
3) Preliminary estimate
4) Revised estimate
Correct Answer: D
109. The expected out turn (cubic metre) of
1)1
2) 3
3) 5
4) 10
Correct Answer: A
JE 29-01-2018 AN]
1)10%
2)14%
3)20%
4)25%
Correct Answer: C
JE 29-01-2018 AN]
1)10%
2)15%
3)18%
4)21.5%
Correct Answer: D
1)2%
2)5%
3)1 %
4)15%
Correct Answer: B
JE 29-01-2018 AN]
1)0.8
2)0.89
3)1.1
4)1.4
Correct Answer: B
1)Number
2)Kilograms
3)Running meter
4)Quintal
Correct Answer: D
JE 29-01-2018 AN]
1)300
2)500
3)1000
4)1500
Correct Answer: B
JE 29-01-2018 FN]
2) pay taxes
Correct Answer: A
1) Meter
2) Cubic meter
3) Kilograms
4) Square meter
Correct Answer: D
A.B xD x L
B.(B+B+sD)xDxL
C.(B+B+sD)xDxL/2
D.(BD+SD2)xL
Correct Answer: D
JE 25-01-2018 FN]
1) Brick work
2) Concrete work
3) Earthwork
4) Steel work
Correct Answer: D
JE 25-01-2018 FN]
1) 10
2) 12
3) 15
4) 20
Correct Answer: D
irregular embankment?
2)Mid-ordinate method
3)Simpson's method
4)Trapezoidal method
Correct Answer: C
JE 22-01-2018 FN]
1)Bags
2)Cubic meter
3)Numbers
4)Quintal
Correct Answer: D
1) 2%
2) 8%
3) 10%
4) 15%
Correct Answer: A
125. Which of the following area is included in
24-01-2018 AN]
3)Cornices
Correct Answer: B
126. Explosive required for blasting is measured
1)cubic meter
2)explosive power
3)energy released
4)kilograms
Correct Answer: D
04-03-2017 FN]
sections
Correct Answer: D
1)B/d + Sd
2)Bd + Sd2
3)Bxd-Sd1/2
4)1/2(Bd+Sd2)
Correct Answer: B
129. When not specified, the volume of steel in
22-01-2018 AN]
Correct Answer: D
130. The nominal lead and lift allowed for the
1)50 m and 2 m
2)30 m and 2 m
4)20 m and 1 m
Correct Answer: C
1)84
2)88
3)92
4)96
Correct Answer: B
03-03-2017 FN]
1)Estimation
2)Mensuration
3)Quantity Surveying
4)Valuation
Correct Answer: C
03-03-2017 FN]
1)0.1
2)0.25
3)0.4
4)0.05
1)Total floaty
2)Interfering float
3)Independent float
4)Free float
Correct Answer: D
Options:
materials
A.1200
B.1800
C.2400
D.3000
Correct Answer: C
01-03-2017 FN]
A.tender
B.schedule of rates
C.analysis of rate
D.abstact estimate
Correct Answer: B
139.Thickness of Plastering is
(a) 40 mm
(b) 6 mm
(c) 12 mm
(d)25 mm
Correct Answer: C
etc, is called
Correct Answer: D
JE 2014 AN]
Correct Answer: C
a) Petty work
b) Minor work
c) Major work
d) Minor project
Correct Answer: A
143. The weight of 10 mm diameter mild steel
01-03-2017 AN]
1)0.22 kg
2)0.32 kg
3)0.42 kg
4)0.62 kg
Correct Answer: D
01-03-2017 AN]
1) 20%
2) 15%
3) 10%
4) 5%
Correct Answer: C
about:[SSC JE 2015]
(a) 1000 kg
(b) 3625 kg
(c) 7850 kg
(d) 12560 kg
Correct Answer: C
as:[SSC JE 2015]
(a)Scrap value
Correct Answer: A
(a)Voltage
(b) Power
Correct Answer: D