You are on page 1of 13

EVALUATION OF BUND STABILITY USING GEOSTUDIO

SOFTWARE WITH GROUND IMPROVEMENT METHOD


USING SAND-KEY AT RECLAMATION WORK ON SOFT SOIL
Bambang Pardoyo1,*), Kresno Wikan Sadono1), Indrastono Dwi Atmanto1),
Aden Tatag Surya Bhara Dhaksa1), Nadya Paramitha Widiasari1)
1)
Departemen Teknik Sipil, Fakultas Teknik, Universitas Diponegoro
Jl. Prof. H. Soedarto, S.H., Tembalang, Kota Semarang, 50275
*)
Email : bambangpardoyo356@gmail.com

Abstract
The use of sand-key reclamation works in soft and very soft soils to increase the
stability of the bund construction. Reclamation using the hydraulic fill method
requires a stable embankment structure to withstand the potential for landslides
from landfills, and in sea areas with very soft subgrade soils, with small undrained
cohesion values causes the bund to be unstable and do not exceed the critical limit.
The purpose of this study is to evaluate the improvement of soft soil in bund
construction so that it is stable using GeoStudio. The Bund stability analysis results
show that the value of the sand-key depth depends on the variation in the depth of
the seabed. At a seabed depth of -6 m, there is a sand-key depth of 7 m, -5 m the
sand-key depth of 10 m, -4 m thesand-key depth of 10 m, -3 m the sand-key depth is
5 m. The final safety number of 1.404,1.438,1,675, and 1.354 respectively.

Keywords: Reclamation, hydraulic fill, soft soil, bund, critical height, ground
improvement, sand-key, safety factor

INTRODUCTION needed to accommodate all activities


Substitute soil located under the which could not be facilitated in the
construction of bund can be sand or city. Beaches that are oriented to ports,
sand-key. Sand-key has been used in industry, tourism, or settlements with
the Tekong Island-Singapore shallow coastal waters must be
reclamation project to build stable reclaimed so that they can be
reclaimed land (Hoff, 2012). Land utilized (Huda, 2013).
reclamation can be said as the process One method of carrying out
of creating new land by raising the stockpiling in reclamation works is the
elevation from the seabed (Hoff, hydraulic fill method. Hydraulic fill is
2012). According to Departemen a method of stockpiling soil by filling
Kelautan dan Perikanan, 2001:19, The soil into the reclamation area which is
expansion of the city is the main constructed on each side of
reason for reclamation, so that embankments or bund (Hoff, 2012).
alternative coastal reclamations are The embankment soil in the area where
carried out for various reasons, the embankment has been built must
originally all activities were centered be stable and able to withstand soil
in the city so that a new space was pressure and the potential for slippage

166 Wahana TEKNIK SIPIL Vol. 26 No. 2 Desember 2021 166 - 178
caused by the embankment soil (Hoff, mixing piles and conventional piles
2012). A common method of hydraulic based on the expressway project from
fill is using embankments or bunds. Lianyungang in Jiangsu Province to
Because the shear strength value of Linyi in Shandong Province, The
soft soil is low and also has a low CBR results show that it can shorten the
value, one of the subgrade criteria for time of dissipation of water pressure
embankment soil needs to have a from the pores of the pile soil and
sufficient CBR value (Zaika & Suryo, further accelerate the stability of the
2019). In addition to stability consolidation of the roadbed to achieve
problems, subsidence is also a problem fast and effective consolidation of the
that occurs in embankment on soft soil soft marine clay foundation (Xie et al.,
(Balasubramaniam et al., 2010). One 2014).
of the methods used to construct stable
embankments or bund is ground MATERIALS AND METHODS
improvement with soil replacement PT. Pertamina (Persero) plans to
(Hartlen et al., 1996). expand and develop land using the
Previous research that has been reclamation method covering an area
done on soft soil improvement by of 400 hectares in the coastal waters of
preloading and PVD is this study RU-IV Pertamina Balongan - West
presents a numerical evaluation of the Java to support the need for a
strength and stability of the soil petrochemical refinery facility as a
enhanced by vacuum consolidation in research location in Table 1 and
combination with preloading Figure.1. Reclamation planning
embankments. The results showed the requires soil investigation by means of
validity of soil improvement using digging a hole (trial-pit), drilling, and
vacuum consolidation with preloading direct testing (in-situ test), obtaining
embankments (Shibata et al., 2015), the technical properties of the soil, then
replacement by Lightweight Expanded used as consideration in analyzing soil
Clay Aggregate (LECA), the results stability and settlement.
obtained showed that the decrease Soil investigation tests are
decreased with increasing thickness of carried out in onshore and offshore
the LECA replacement (Zukri et al., areas, in the form of laboratory tests
2018), By pile, The evaluation is based and field tests. From laboratory tests,
on 2D and 3D finite element analysis soil data obtained in the form of
and on the behavior of the calibrated compression index (Cc), Index
soil in the failure test and the finnish Plasticity (IP) and void ratio (e), while
railway embankment, the results of field test data in the form of drilling
which are improved stability using Standard Penetration Test (SPT).
(Mansikkamäki & Länsivaara, 2013), For the properties of the clay, the
by jet mixing piles, verified the effect N value from the SPT test (N-SPT) is
of soft marine clay foundation used. Cohesion is defined as the soil
reinforced by two new types of dry jet resisting stress resulting from the

Evaluation Of Bund Stability Using Geostudio ........... (Bambang Pardoyo, dkk) 167
attraction of soil molecules. The SI Meanwhile, the value of dry soil
unit of cohesion is the kilo Pascal volume weight (γd) and saturated soil
(kPa). According to Look (2007), unit weight (γsat) can be determined
Table 2 can be used to determine the using a soil density relationship table
type of clay based on the N-SPT value, based on the soil description given by
or based on the cohesion/strength (Cu) Look (2007) and shown in Table 3.
value of the soil.

Table 1. Coordinates of soil data point in layout image


Location Coordinate
UTM Degrees
X Y South East
A1 212910,87 9294305,51 6°22'40.23"S 108°24'17.66"
A2 212004,35 9295901,14 6°21'48.16"S 108°23'48.46"E
A3 214246,87 9295891,33 6°21'48.85"S 108°25'1.37"E
A4 214827,36 9295010,25 6°22'17.61"S 108°25'20.12"E
A5 214227,83 9294654,98 6°22'29.09"S 108°25'0.55"E
A6 213857,84 9294795,54 6°22'24.45"S 108°24'48.54"E

Figure 1. Petrochemical refinery development project land reclamation plan


(Google Earth,2021)

Table 2. Coreltion of SPT test result with clay cohesion/and strength(Cu)

168 Wahana TEKNIK SIPIL Vol. 26 No. 2 Desember 2021 166 - 178
Table 3. Relationship description of soil or rock with unit weight

After the soil properties have been = Undrained shear strength of


identified, it is continued to evaluate subsoil (kN/m2)
the stability of the bund, the number of = Factor of safety
safety, and the decrease of bunds in the = Bulk weight of embankment
embankment GeoStudio program. (kN/m3)
First, according to Hartlen Second, carry out the step of
(1996) in planning an embankment calculating the stability of the bund
work so that failure does not occur, it against the safety factor, decreasing
is necessary to make an initial estimate bunds so that the construction of the
of the critical embankment height. bund is stable by carrying out two
According to Terzaghi (1956) in calculation stages.
Hartlen (1996), the critical a) Construction stage 1
embankment height/Safe Embankment In the calculation of the construction
Height (Hs) can be calculated by phase 1 by piling up bund as high as +
Equation 1. 2.00 m above sea level, including:
1. The fill height (He) must be less
(1) than the critical height (Hcr).
2. If He < Hcr with SF > 1.3, you can
Where : proceed to the calculation phase
= Critical embankment height (m) of SF, settlement, strength gain,
= Stability value ( for consolidation time, and the number
field circle failure) of PVD, then continue with the
construction phase 2, if He < Hcr

Evaluation Of Bund Stability Using Geostudio ........... (Bambang Pardoyo, dkk) 169
with SF < 1.3, soil improvement is error determination of depth
carried out with the following optimum sand-key with GeoStudio
steps c. software until the optimum sand-
3. If He > Hcr, soil improvement is key depth is selected with SF > 1.3,
carried out with sand-key, sand-key proceed as step b.
depth is determined check and error b) Construction stage 2
determination of depth optimum In the calculation of the construction
sand-key with GeoStudio software stage1 by piling up bund as high as +
for SF and manual with the ordinary 6.00 m above sea level, proceed with
method for consolidation settlement steps such as construction stage 1.
and strength gain. Furthermore, the calculation of slope
4. If He > Hcr and SF < 1.3, change the stability against the number of safety
thickness of the soil improvement using the GeoStudio program and
with a sand-key, then determine the manually using the ordinary method in
sand-key depth again check and Equation 2 below (Das et al., 2002):

(2)

Where :
Fs = Factor of Safety
Cohesion undrained value (kN/m2)
flat width (m)
Weight of each piece (kN)
The angle between the center of refraction and the sliding reference point(o)
φ = shear angle in soil (o)

According to Han (2015), soil the seabed in the project layout has a
subsidence occurs in soils that are depth variation ranging from 3m to 6
loaded with static vertical loads. The m (below water level). So that the
total decrease consists of 3 components reclamation embankment or bunds
which are given in Equation 3. planning calculation will be carry out
at each depth variation. This is
(3) expected that each seabed depth
Where : variation requires a different sand-key
= Total settlement total (m) depth variation as well in Figure 2.
= Immediate settlement (m)
= Consolidation settlement (m) Soil Geotechnical Data
= secondary settlement (m) The process of stockpiling the
embankment soil itself is based on the
RESULTS AND DISCUSSION hydraulic fill method, namely by
It is known that the bathymetric spraying the soil into the reclamation
contour data that shows the depth of area, then using a soil excavator to

170 Wahana TEKNIK SIPIL Vol. 26 No. 2 Desember 2021 166 - 178
form a bund. The specifications of the kN/m3 and φ = 30o. So that the cross
embankment soil, including section in each bunds has the same
embankment fill, bund and sand-key, configuration. Cross action plan on
are determined in advance using sand reclamed area with various seabed’s
soil with γsat = 20 kN/m3, γdry = 18 depth is shown in Figure 2.

Figure 2. Cross section plan on reclaimed land with variations in seabed depth

Table 4. Offshore soil propertis recapitulation

Table 4 shows the N-SPT test data in according to Look (2007) in Table 2
the offshore area, based on the and Table 3. While Table 5 is the result
description of the relationship between of data in the onshore area.
N-SPT with strength and unit weight

Evaluation Of Bund Stability Using Geostudio ........... (Bambang Pardoyo, dkk) 171
Table 5. Onshore soil properties recapitulaion

Soil Geotechnical Data Analysis investigation were carried out on drill


While the data from the results of soil samples taken at the site. Evaluation of
investigations that have been carried slope stability required laboratory and
out in the field and in the laboratory, field test data in Figure 3 and Figure 4
both onshore and offshore. Soil following.

(a) (b)

(c) (d)

172 Wahana TEKNIK SIPIL Vol. 26 No. 2 Desember 2021 166 - 178
(e)
Figure 3. Borelog in the Balongan reclamation area on the offshore.
(a) BH 1, (b) BH 2, (c) BH 3, (d) BH 4, (e) BH 5

Figure 4. Borelog in the Balongan reclamation area on the onshore section.


(a) BH 67, (b) BH 89, (c) BH 110

Evaluation Of Bund Stability Using Geostudio ........... (Bambang Pardoyo, dkk) 173
If the seabed is at a depth of -6 the height of the bund elevation at
m, the allowable height of the bund construction stage 1 is determined
embankment so that it does not exceed EL.+2.0m, then a review is carried out
the safe height value is 2.58 m or is on several sand-key depths, namely
located at an elevation of -3.42 m, 4,6,7,10 m. Calculation of sand-key
where reclamation has a target stability check and error against the
elevation on the EL. +4.00. The selected sand-key depth variation on a
elevation is still below sea level, which 6 m seabed in Table 6 and sand-key +
is very difficult to operate the project bund at construction stage 2 in Table 7.
(needed for embankment height above Calculation of Sand-key Stability
sea level). To overcome very soft clay Check and Error with GeoStudio and
subsoil conditions, several options can ordinary manual of 0.008, While the
be carried out, for example using soil calculation of Check and Error
improvement, namely by soil Stability Sand-key + bund with
replacement under the bund using GeoStudio and manual ordinary is
sand-key. Because the bund stockpile 0.193. Similarly, the results of
height did not meet the final calculating the total decrease
embankment target height (target immediately due the accumulation of
elevation at EL. +4.00, the reclamation bunds in calculation stage 1 and
and bund embankment was carried out calculation stage 2 in Table 8. The
using the stage construction method, recapitulation of the evaluation results
and the initial assumption was that the of slope stability and soil improvement
landfill was in two stages. The first with Sand-key materials for
stage is stockpiling to an elevation of construction phase 1 and construction
+2 m above sea level, and in the phase 2 includes safety factor,
second stage, stockpiling is to an settlement and final elevation of the
elevation of +4 m above sea level. desired and stable bund, can be seen in
Calculation of sand-key (soil Table 9 and Table 10.
replacement) under the bund, where

Table 6. Check and error stability of sand-key depth variation at construction stage 1

Table 7. Check and error stability of sand-key depth variation at construction stage 2

174 Wahana TEKNIK SIPIL Vol. 26 No. 2 Desember 2021 166 - 178
Table 8. The result of total settlement and final elevation at construction stage 1 and
construction stage 2

Table 9. Recapitulation of sand-key head base on variation of seabed depth


(construction stage 1)

Table 10. Recapitulation of sand-key head base on variation of seabed depth


(construction stage 1)

Seabed Relationship, Safety Factor, factors of safety, settlement, and final


Settlement and final elevation. elevation at construction stage 1 and
The relationship between the selected construction stage 2 in Figure 5, Figure
seabed and san-key depths to the 6 and Figure 7 below.

Seabed and Safety of Faktor


1,700
1,650
Safety of faktor

1,600 y = 0,0182x + 1,4641


1,550
1,500 y = 0,0182x + 1,4641
1,450
1,400
1,350
1,300
2 3 4 5 6 7
Seabed (m) Linear (Construction stage 1)
Linear (Construction stage 1)

Figure 5. Seabed Relationship and safety factor

Evaluation Of Bund Stability Using Geostudio ........... (Bambang Pardoyo, dkk) 175
Based on Figure 5, shows that the Based on Fig. 7, shows that the deeper
deeper the seabed, the trend of the the seabed, the trend of the final
safety factor is increasing, both elevation on the bund, tends to
construction stage 1 and construction decrease and its value is negative at
stage 2. Based on Figure 6, shows that construction stage 1, Conversely the
the deeper the seabed, the trend of deeper the seabed, the trend of final
settlement is increasing in construction elevation, tends to increase in
stage 1, and conversely the deeper the construction stage 2 according to the
seabed, the trend of settlement is desired elevation with a value of + 4
decreasing at construction stage 2. m.

Seabed and Settlement


2,4000
2,2000 y = 0,1102x + 1,6498
Settlement (m)

2,0000
1,8000
1,6000
y = -0,0342x + 1,8202
1,4000
1,2000
1,0000
2 3 4 5 6 7
Linear (Construction stage 1)
Seabed (m)
Linear (Construction stage 2)

Figure 6. Seabed and settlement relationship

Seabed and Final elevation


6,0000
y = 0,0342x + 4,1798
Fuinal elevation(m)

4,0000
2,0000
0,0000
2 3 y = -0,1102x
4 + 0,3502
5 6 7
-2,0000
-4,0000
-6,0000 Linear (Construction stage 1)
Settlement (m)
Linear (Construction stage 2)

Figure 7. Seabed relationship and final elevation

CONCLUSION m with a final safety number of 1.404,


The Bund stability analysis results at a seabed depth of -5 m a sand-key
show that the value of the sand-key depth of 10 m is obtained with a final
depth depends on the variation in the safety number of 1.438, at a seabed
depth of the seabed. At a seabed depth depth of -4 m a sand-key depth of 10 m
of -6 m, there is a sand-key depth of 7 is obtained with a final safety number

176 Wahana TEKNIK SIPIL Vol. 26 No. 2 Desember 2021 166 - 178
of 1.675 , at a seabed depth of -3 m, Huda, M. C., 2013, Pengaturan
the sand-key depth is 5 m with the Perizinan Reklamasi Pantai
final safety number 1.354. From the Terhadap Perlindungan
result of analysis, it can be concluded Lingkungan Hidup. Perspektif,
that ground improvement using soil 18(2), 126. https://doi.org/
replacement with sand-key can make 10.30742/
the construction of embankment or Kassou, F., Bouziyane, J. Ben, Ghafiri,
bund become stable in reclamation A., & Sabihi, A., 2020, Slope
work at soft soil area. Stability of Embankments on
Soft Soil Improved with Vertical
ACKNOWLEDGEMENTS Drains. Civil Engineering
We thank to Soil Mechanics Journal, 6(1), 164–173.
Laboratory along with lecturers and Look, B., 2007, Handbook of
laboratory staff, Departemen Teknik Geotechnical Investigation and
Sipil Fakultas Teknik Universitas Design Table (Vol. 6, Issue 2).
Diponegoro. Taylor & Francis Group.
Mansikkamäki, J., & Länsivaara, T.,
REFERENCES 2013, Stability improvement
Balasubramaniam, A.S., Cai, H., Zhu, methods for soft clays in a
D., Surarak, C., & Oh, E.Y.N., railway environment. 18th
2010, Settlements of International Conference on Soil
embankments in soft soils. Mechanics and Geotechnical
Geotechnical Engineering, 41(2), Engineering: Challenges and
1-19. Innovations in Geotechnics,
Das, B.M., Endah, N., & Mochtar, I.B., ICSMGE 2013, 1317- 1320.
2002, Mekanika Tanah (Prinsip- Shibata, T., Nishimura, S., Fujii, M., &
prinsip Rekayasa Geoteknis) (Y. Murakami, A., 2015, Evaluation
Sianipar (ed.)). ERLANGGA. of strength of soft ground
Han, J., 2015, Principles and Practice improved by vacuum
of Ground Improvement. JOHN consolidation. Geotechnical
WILEY & SONS, INC. Engineering, Geotechnical
Hartlen, J., Wolski, W., Lechowicz, Z., Engineering Journal,(46)1, 95-
Szymanski, A., Baranski, T., 102.
Bergdahl, U., Carlsten, P., & Xie, S.H., Liu, S.Y., & Du, G.Y.,
Larsson, R., 1996, Embankments 2014, Evaluation of application
on Organic Soil (J. Hartlen & W. effect of soft marine clay
Wolski (eds.)). Elsevier Science foundation reinforced by new dry
B.V. jet mixing piles. China Journal
Hoff, J. V., 2012, Hydraulic Fill of Highway and Transport, issue
Manual. In Hydraulic Fill , 8-14.
Manual. https://doi.org/10.1201/ Zaika, Y., Suryo, E.A., 2019, Design
b13077 of improved lime expansive soil

Evaluation Of Bund Stability Using Geostudio ........... (Bambang Pardoyo, dkk) 177
for embankment of flexible Proceeding 20Th SEAGC- 3Th
pavement. International Journal AGSSEA Conference In
d
of GEOMATE, (17) 60, 90-95. Conjunction With22N Annual
Zukri, A., Nazir, R., Ng, K.S., 2018, Indonesian National Conference
The Settlement Evaluation of On Geotechnical Engineering,
Improved Soft Clay Using LECA Jakarta, Indonesia.
Replacement Technique.

178 Wahana TEKNIK SIPIL Vol. 26 No. 2 Desember 2021 166 - 178

You might also like