Professional Documents
Culture Documents
(Core Unit)
Assessment # 2
Paper # B
Version # 1.5
Assessment Instructions:
1. Please familiarise yourself with the EIT Academic Honesty and Misconduct Policy, in order to
understand your requirements and responsibilities as a student of EIT.
2. Please refer to our Assessment, Moderation and Student Progress Procedure for
information relating to extensions. Extension requests should be submitted to your LSO at
least 3 days prior to the due date.
5. You must use the provided assessment cover page available on your Moodle student
homepage. Submissions without a cover page will not be accepted.
UNIT#_ASSESSMENT#_YOURNAME_DATE
E.g. ME501_Assessment2_SteveMackay_01Aug2019
7. You must reference all content used from other sources including course materials, slides,
diagrams, etc. Do not directly copy and paste from course materials or any other resources.
Refer to the referencing section of the EIT eLibrary on Moodle for referencing guides.
8. It is your responsibility to check that you have submitted the correct file, as revised
submissions are not permitted after the due date and time.
Important note: Failure to adhere to the above may result in academic penalties. Please refer to
the unit outline or EIT Policies and Procedures for further information.
MXX507_Assessment2_PaperB_v1.5
Master of Engineering 3
Assessment #: 2B
Weighting: 25%
Please complete your answers on the assessment cover page document available on Moodle.
Clearly label your question numbers (there is no need to copy the full question over). Include all working
out.
Question 1:
Consider a project for which you are the PM. You have to oversee the selection and installation of a
boiler for a plant.
Create a report (1,500-2,000 words) for the above based on the points below:
i. Define the objectives and scope of work of the project (work included/excluded and the
context of work)
ii. Define the specifications of the equipment and list the safety and regulatory requirements
iii. Create a list of activities and phases for the project (provide a WBS)
iv. Create a time management schedule for the activities (provide a Gantt chart)
v. Discuss how you might use PERT to take into account uncertainties in the duration and cost of
the tasks
Question 2:
Consider a project for which you are the PM. You have to oversee the construction of a food
processing plant. The plant should produce dry milk from fresh milk with a capacity of 100,000 liters
of fresh milk per day.
Create a report (1,500 – 2,000 words) for the above based on the points below:
i. Define the objectives and scope of work of the project (work included/excluded and the
context of work)
ii. Define and describe the different activities and provide a WBS
Master of Engineering 4
Marking guide:
Question 1:
• Communication style (clarity) [5 marks]
• Scope of work and objectives [5 marks]
• Specifications of the equipment (research for examples) [5 marks]
• List of activities [5 marks]
• Time management (Gantt chart, network diagrams) [5 marks]
• Extras (PERT, account for risks ...) [5 marks]
• Use of professional software for drawings [5 marks]
Question 2:
• Communication style (clarity) [5 marks]
• Scope of work and objectives [5 marks]
• Stakeholders [5 marks]
• List of activities [5 marks]
• Costs estimation (research for examples) [5 marks]
• Extras (account for risks ...) [5 marks]
• Cost control and monitoring discussion [5 marks]
END OF ASSESSMENT