Agile Questionnaire

1. Scrum Master primarily performs the job of following


a. Delivery Manager
b. Team Lead
c. Facilitator
d. Administrator

2. Who is responsible for sending meeting invite for daily scrum, grooming, planning, review &
retrospective?
a. Manager
b. Product Owner
c. Any team member
d. Scrum Master

3. What should be done with daily scrum meeting if scrum master is not available?
a. Don’t attend daily scrum
b. Send daily status over mail
c. Inform to Manager & PO
d. Self-organize and start scrum with available team members

4. What if you are not able to join daily scrum meeting in person?
a. Send status update over mail
b. Inform status to scrum master
c. Inform status to team member
d. No status update required

5. Whom should work status be updated in daily scrum?


a. Team
b. Product Owner
c. Scrum Master
d. Architect

6. Do I need to be part of backlog grooming?


a. It is mandatory for each team member
b. Scrum master can alone do backlog grooming
c. PO &Scrum Master can together do backlog grooming
d. PO alone can-do backlog grooming

7. When should backlog grooming happen?


a. Before planning and after sprint close
b. Anytime between sprint
c. As and when it is required
d. It is not necessary

8. Do we need to invest time in various estimation techniques? or quick rough estimation


would work?
a. Rough estimation is fine by anyone
b. Team should try to get more details to reach around exact estimates
c. We can rely on topic experts high level estimate
d. Team must play poker to arrive at fair estimate
Agile Questionnaire

9. Who is responsible for bringing consensus among stakeholders?


a. Scrum Master
b. Product Owner
c. Architect
a. Team

10. How to update progress of my work to all the stakeholder?


a. Send mail to everyone
b. JIRA update with notification ON
c. Daily Scrum
d. Daily Scrum and JIRA Item update with Notification ON

11. What should be done if I get ad-hoc activity not part of freezed sprint?
a. Inform to scrum master and continue with ad-hoc activity
b. Discuss with team in daily scrum for suggestion (Accommodate/Deny/Add to Backlog)
c. Deny any ad-hoc activity during sprint
d. Inform manager to stop such ad-hoc requirement

12. Is it fine if I have pushed my JIRA items multiple times to next sprint?
a. JIRA items can be pushed any number of times as long as team is informed
b. No, pushing JIRA item may have impact on appraisal
c. JIRA items can be pushed any number of times as long as PO is informed
d. JIRA items can be pushed any number of times as long as all stakeholders are informed

13. What if I encounter dependency for my backlog item(s) that doesn’t allow me to proceed?
a. Wait till dependency is resolved
b. Work on another team member’s backlog item
c. Discuss with team in daily scrum and pick up new item from backlog in current sprint
d. Work on Innovations

14. What if my JIRA Item estimation effort and completion effort deviation is too high?
a. I must do RCA and inform to manager
b. I must do RCA and discuss with team in retrospective meeting for improvements
c. No discussion required
d. Keep more buffer next time

15. Who reviews the JIRA item development when it is not reported by PO?
a. JIRA Item creator
b. JIRA Item reporter
c. Scrum Master
d. Team

16. Who is responsible for tracking development review feedback?


a. Product Owner
b. Scrum Master
c. Individual Team Member for their individual objects
d. Architect
Agile Questionnaire

17. What if I am not happy with something (work related) during current sprint?
a. Discuss with Scrum Master
b. Discuss with Product Owner
c. Discuss with Manager
d. Discuss with team in Retrospective Meeting

18. Who is responsible for tracking retrospection feedback implementation?


a. Product Owner
b. Scrum Master
c. Individual Team Members
d. Architect

19. Who is responsible for Delivery in Agile?


a. Scrum Master
b. Product Owner
c. Architect
d. Team

20. Who is final decision maker in Agile?


a. Scrum Master
b. Product Owner
c. Architect
d. Team