CONTRACT
FOR SMALL WORKS
DRAFT NOTICES AND
COMMUNICATIONS
DRAFT Version 1.0 | 2022
DRAFT Notices and Communications
TABLE OF CONTENTS
INSTRUCTIONS 5
001 – Notice of ambiguity, conflict or discrepancy in the Contract – Sub-Clause 1.5 (b) 7
007 – Right of access to and possession of the full or partial Site – Sub-Clause 2.1 14
015 – Consent or no consent to the proposed Subcontractor – Sub-Clause 4.4 (b) and (c) 22
016 – Instruction to procure and employ a Nominated Subcontractor – Sub-Clause 4.4 (g) 24
019 – Consent or no consent for the replacement of Key Personnel – Sub-Clause 4.5 (e) 27
022 – Consent or no consent for the removal of the Contractor's Equipment – Sub-Clause 4.7 (a) 29
024 – Notice to Correct: Health and Safety Improvement Notice – Sub-Clauses 4.9 (d) and 11.1 32
025 – Notice of suspension for breach of health and safety obligations – Sub-Clauses 4.9 (f) and 6.6 (a) 33
026 – Instruction to terminate the Subcontractor or Nominated Subcontractor – Sub-Clause 4.9 (i) 34
027 – Request to uncover the Works for testing – Sub-Clause 4.11 (e) 35
030 – Notice of No-objection or rejection of the Contractor’s design – Sub-Clause 5.1 (c) and (d) 39
034 – Notice to suspend progress of the Works or parts of the Works – Sub-Clause 6.6 (a) 44
035 – Notice to resume progress of the Works or parts of the Works – Sub-Clause 6.6 (b) 44
036 – Notice to resume progress of the Works or parts of the Works under a prolonged suspension – Sub-Clause
6.6 (c) 45
040 – Extension of Defects Notification Period – Sub-Clause 8.1 (d) and (e) 50
044 – Instruction to carry out work under Provisional Sum – Sub-Clause 9.3 55
046 – Issue of the Final Payment Certificate – Sub-Clauses 10.7 and 10.9 56
052 – Notice of termination for the Employer's convenience – Sub-Clause 11.4 (a) 63
053 – Agreement or determination of valuation and payment after termination for Employer's convenience – Sub-
Clause 11.5 (b) 64
054 – Instruction to rectify loss or damage to the Works – Sub-Clause 13.3 (a) 65
056 – Notice of conclusion of effects from Force Majeure – Sub-Clause 14.3 (b) 67
057 – Employer’s agreement or determination on the consequences of Force Majeure – Sub-Clause 14.4 (b) 68
INSTRUCTIONS
1. This template was last updated in September 2022. If more than a few months have
passed since that date, please visit the works contract intranet page to find a link to the
Contracts for Works templates to ensure that you are using the most recent version.
Please send any feedback or suggestions on these templates to the Infrastructure and
Project Management Group (IPMG) (ipmg.publications@unops.org), to contribute to
the continuous work to improve the templates.
2. This template is for use in support of the Construction Contract for Small Works.
3. Instructions on how to use these templates are provided below. Additional questions
may be directed to IPAS Legal through the IPAS Solution Portal.
4. Contract Notices and other communications may be drafted and issued by different
roles throughout the duration of the Contract. The provided templates cover Notices
and communications that would be sent by the Employer’s Representative or by the
personnel acting on behalf of the Employer. All relevant guidance should be followed
and the General Conditions of Contract should be consulted when preparing the
communication.
5. Content to be completed is highlighted in grey, with additional instructions in brackets,
as shown in the examples below and should be completed by fully replacing all the
grey highlights with the relevant text. The final version of a completed Notice or
communication should not include any grey highlights.
For example, before completion:
“... received by the Employer on [insert date] …”
“... to give effect to the [select one: novation; assignment(s)] under this Notice …”
“The [select one or both: assignment; [and] delegation] to the Employer’s
Representative’s Assistant …”
After completion:
“... received by the Employer on 18 August 2022 …”
“... to give effect to the assignments under this Notice …”
“The assignment and delegation to the Employer’s Representative’s Assistant …”
6. When a template indicates that it requires consultation with a Legal Advisor, project
teams must follow the provided instructions and contact IPAS Legal.
7. To use a template for any Notice or communication:
Step 1. Create a copy of the UNOPS letterhead template (or another letterhead, if
relevant).
Step 2. Copy the template content starting with the date in the upper right hand
corner and including all content through the signature and any “copy to”,
“attachment” or notes at the bottom. Do not copy the title of the template at
the top of the page.
Step 3. Paste the content into the letterhead template.
Step 4. Complete the template by filling in all of the text highlighted in grey. Do so by
fully selecting the highlighted grey text, inclusive of the square brackets, and
writing to replace the content.
a. Contract: the contract title and contract ID should exactly match the
information in the oneUNOPS (oU) Contract Management module.
Step 4. Delete any option that is not applicable as well as the yellow highlighted text
and the yellow notes box.
Step 5. Select all the text and apply the highlight colour “none”. This will fully remove
all the grey highlights from the completed letter.
Step 6. Ensure that person issuing signs the communication, either digitally or
manually, in the space following “Sincerely,”.
Step 7. Send the Notice or communication to the Contractor’s Representative,
copying all those identified and any others as deemed might be necessary to
be copied, and including any relevant attachments. Notices and other
communications may be physically delivered to an address, or sent or
transmitted as a document, signed, scanned and attached in an email, as
detailed in Sub-Clause 1.3 [Notices and Other Communications].
8. All templates for Notices and communications are listed consecutively based on the
corresponding Sub-Clause from the General Conditions of Contract and assigned a
unique ID number accordingly. For more advanced sorting, refer to the complete List
of Contract Notices and Communications.
001 – Notice of ambiguity, conflict or discrepancy in the Contract – Sub-Clause 1.5 (b)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
➔ Option 1: If notifying
In reference to Sub-Clause 1.5 (b) [Priority of Documents] of the General Conditions, the following [select
one: ambiguity; conflict; discrepancy] has been identified in a document forming the Contract: [insert details
of the affected contract document and the identified ambiguity, conflict or discrepancy].
The Contractor is hereby instructed to follow the [select one: clarification; instruction] as follows: [insert
clarification or instruction to be followed by the Contractor].
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
005 – Consent or no consent to change the Joint Venture composition or legal status
– Sub-Clause 1.11 (a) (ii)
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
006 – Consent or no consent to use the name, emblem, official seal or abbreviation of
the Employer or the United Nations – Sub-Clause 1.13 (a)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
Subject: [Select one: Consent; No consent] to use the [select one or several:
name; emblem; official seal; [and] abbreviation] of the Employer or the United Nations
This communication is in reference to Sub-Clause 1.13 (a) [Publicity and Use of the Name or Emblem of the
Employer and the United Nations] of the General Conditions and to the Contractor’s communication with
reference number [insert reference number] dated [insert date] and received by the Employer on [insert date],
requesting the Employer’s permission to make use of [select one or several: the name; the emblem; the official
seal; [and] the abbreviation] of the Employer or the United Nations in connection with [insert details of intended
purpose of disclosure as requested by the Contractor].
➔ Option 1: Consent
The Employer hereby permits the Contractor to [insert details of the permission] for the sole purpose of
[insert purpose].
➔ Option 2: No consent
The Employer does not permit the Contractor to [insert details of the request] for the following reasons:
[insert reasons].
This communication does not in any way relieve the Contractor from any of its warranties, obligations or liabilities
under or in connection with the Contract.
Sincerely,
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
007 – Right of access to and possession of the full or partial Site – Sub-Clause 2.1
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
Subject: Right of access to and possession of the [select one: full; partial] Site
In reference to Sub-Clause 2.1 [Right of Access to the Site] of the General Conditions,
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ The date of access must not be later than the date stated in the Schedule 2.2 [Site Plan] or if no such time is
stated in the Schedule, must be within such times as may be required to enable the Contractor to proceed in
accordance with the dates for access to and possession of the Site identified in the original Programme.
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 3.1 (a) [Employer’s Representative] of the General Conditions, the Employer advises
that [insert name] has been appointed as the Employer’s Representative effective from [insert date].
The Employer’s Representative shall carry out duties and exercise authorities as specified in or implied by the
Contract.
The Employer’s Representative shall have no authority to amend the Contract or to relieve either Party of or
waive any duty, obligation or responsibility under or in connection with the Contract.
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 3.2 (a) [Employer’s Representative’s Assistants] of the General Conditions, the
Contractor is hereby notified that [insert name] has been assigned as the Employer’s Representative’s Assistant
effective from [insert date].
Furthermore, the following duties of the Employer’s Representative are assigned and authority delegated to the
Employer’s Representative’s Assistant: [list the specific duties assigned and authority delegated and/or any
exclusions].
Sincerely,
Signed by: [insert full name of the Employer’s contact person or the Employer’s Representative]
[Select one: For and on behalf of the Employer; Employer’s Representative]
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This Notice is in reference to Sub-Clause 3.2 (a) [Employer’s Representative’s Assistants] of the General
Conditions and to the Employer’s Notice with reference number [insert reference number] dated [insert date],
whereby [insert name] was appointed as the Employer’s Representative’s Assistant, assigned the specified
duties and delegated authority.
The Contractor is hereby advised that the following [select one or both: assignment of duties; [and] delegation of
authority] to the Employer’s Representative’s Assistant [select one: has; have] been revoked [select one:
effective immediately; from the date of receipt of this Notice by the Contractor]: [insert the specific details of the
duties and/or authorities revoked].
Sincerely,
Signed by: [insert full name of the Employer’s contact person or the Employer’s Representative]
[Select one: For and on behalf of the Employer; Employer’s Representative]
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This Notice is in reference to Sub-Clause 3.2 (a) [Employer’s Representative’s Assistants] of the General
Conditions and to the Employer’s Notice with reference number [insert reference number] dated [insert], whereby
[select one or both: duties were assigned; [and] authorities were delegated] to the Employer’s Representative’s
Assistant.
Further to the [select one or both: previous duties assigned; [and] authorities delegated], the following additional
[select one or both: duties are assigned; [and] authorities are delegated] to the Employer’s Representative’s
Assistant [insert name]: [list the specific duties being assigned and/or authority being delegated].
The [select one or both: assignment; [and] delegation] to the Employer’s Representative’s Assistant will take
effect from the date this Notice is received by the Contractor.
Sincerely,
Signed by: [insert full name of the Employer’s contact person or the Employer’s Representative]
[Select one: For and on behalf of the Employer; Employer’s Representative]
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 4.1 (e) [Contractor’s General Obligations] of the General Conditions, the Contractor is
required to submit monthly progress reports in relation to the Works and any health, safety, social and
environmental aspects in connection with the Works.
The Contractor is hereby requested to submit the progress report [insert the frequency and the recurring due
date]. The report shall comply with the requirements stated in Schedule 3.7 [Reporting Requirements].
Sincerely,
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This communication is in reference to Sub-Clause 4.3 (c) [Contractor's Representative] of the General Conditions
and to the Contractor’s communication with reference number [insert reference number] dated [insert date] and
received on [insert date], requesting consent to revoke the appointment of [insert name] as the Contractor’s
Representative due to the following reasons: [insert the reasons given for the revocation of the appointment].
➔ Option 1: Consent
Consent is hereby granted for the request to revoke the appointment of [insert name] as the Contractor’s
Representative. The Contractor is therefore instructed to submit the name and particulars of another suitable
replacement by [insert date].
➔ Option 2: No consent
Consent is not granted for the request to revoke the appointment of [insert name] as the Contractor’s
Representative due to the following reasons: [insert reasons].
This communication does not in any way relieve the Contractor from any of its warranties, obligations or liabilities
under or in connection with the Contract.
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This communication is in reference to Sub-Clause 4.3 (c) [Contractor's Representative] of the General Conditions
and to the Contractor’s communication with reference number [insert reference number] dated [insert date] and
received on [insert date], requesting consent for the appointment of [insert name] as the Contractor’s
Representative to replace [insert name].
➔ Option 1: Consent
Consent is hereby granted for the appointment of [insert name] as the Contractor's Representative.
➔ Option 2: No consent
Consent is not granted for the appointment of [insert name] as the Contractor's Representative for the
following reasons: [insert reasons].
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
015 – Consent or no consent to the proposed Subcontractor – Sub-Clause 4.4 (b) and
(c)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This communication is in reference to Sub-Clause 4.4 (b) and (c) [Subcontracting] of the General Conditions and
to the Contractor’s Notice with reference number [insert reference number] dated [insert date] and received by
the Employer on [insert date], requesting consent to subcontract [insert part of the Works to be subcontracted] to
the Subcontractor [insert the name of the proposed Subcontractor].
➔ Option 1: Consent
Consent is hereby granted for the request to appoint the proposed Subcontractor [insert name of proposed
Subcontractor] for the execution and delivery of [insert details of the part of the Works to be subcontracted].
The Contractor shall be responsible for the work of its Subcontractors, for managing and coordinating all the
Subcontractors’ work, and for the acts, omissions or defaults of any Subcontractor, its agents or employees,
as if they were the acts, omissions or defaults of the Contractor.
This communication shall not in any way relieve the Contractor from any of its warranties, obligations or
liabilities under or in connection with the Contract.
➔ Option 2: No consent
Consent is not granted for the request to appoint the proposed Subcontractor [insert name of proposed
Subcontractor] for the execution and delivery of [insert details of the part of the Works to be subcontracted]
for the following reasons: [insert reasons].
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
➔ There are three options set out above. Delete whichever options are not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 4.4 (g) [Subcontracting] of the General Conditions and Schedule 3.6 [Nominated
Subcontractors], the Contractor is hereby instructed to procure and employ [insert details of the Nominated
Subcontractor] to carry out the following: [insert details from the list of work identified under Schedule 3.6].
The Contractor shall be responsible for the work of its Nominated Subcontractors, for managing and coordinating
all the Nominated Subcontractors’ work, and for the acts, omissions or defaults of any Nominated Subcontractor,
its agents or employees, as if they were the acts, omissions or defaults of the Contractor.
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 4.5 (c) [Contractor's Personnel] of the General Conditions, the Contractor is hereby
required to remove [insert name(s) of Contractor’s Personnel] from the [insert “Site” or details on the personnel’s
position in connection with the execution of the Works] within [insert time period by which person must be
removed].
The Contractor is required to remove this person for the following reasons: [insert reasons as described in Sub-
Clause 4.5 (c) [Contractor’s Personnel]].
Pursuant to Sub-Clause 4.5 (d) [Contractor’s Personnel], the Contractor shall appoint or cause to be appointed a
suitable replacement person.
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This communication is in reference to Sub-Clause 4.5 (e) [Contractor's Personnel] of the General Conditions and
to the Contractor’s Notice with reference number [insert reference number] dated [insert date] and received on
[insert date], requesting consent to revoke the appointment of the Key Personnel [insert name] to the position of
[insert position] due to the following reasons: [insert the reasons given for intending to revoke the appointment].
➔ Option 1: Consent
Consent is hereby granted for the request to revoke the appointment of [insert name] to the position of [insert
position]. The Contractor is therefore instructed to submit the name and particulars of another suitable
replacement by [insert date].
➔ Option 2: No consent
Consent is not granted for the request to revoke the appointment of [insert name] to the position of [insert
position] due to the following reasons: [insert reasons].
This communication does not in any way relieve the Contractor from any of its warranties, obligations or liabilities
under or in connection with the Contract.
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
019 – Consent or no consent for the replacement of Key Personnel – Sub-Clause 4.5
(e)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
Subject: [Select one: Consent; No consent] for the replacement of Key Personnel
This communication is in reference to Sub-Clause 4.5 (e) [Contractor's Personnel] of the General Conditions and
to the Contractor’s communication with reference number [insert reference number] dated [insert date] and
received on [insert date], requesting consent for the replacement of a Key Personnel [insert name] to fill the
position of [insert position].
➔ Option 1: Consent
Consent is hereby granted for the appointment of [insert name] to the position of [insert position] replacing
[insert name and position] on the following basis: [insert details of approval or conditional approval, if any].
➔ Option 2: No consent
Consent is not granted for the appointment of [insert name] to the position of [insert position] replacing [insert
name and position] for the following reasons: [insert reasons].
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 4.6 (a) [Non-payment by Contractor] of the General Conditions, the Employer has
become aware that the Contractor has failed to pay the [select one:Subcontractor(s); Nominated
Subcontractor(s); Contractor's Personnel] in accordance with the Contract.
The Employer hereby gives this Notice to the Contractor requesting to submit reasonable documentary evidence:
1. that the [select one: Subcontractor(s); Nominated Subcontractor(s); Contractor's Personnel] [select one:
has; have] received all amounts due; or
2. that satisfies the Employer that the Contractor is reasonably entitled to withhold or refuse payment to the
[select one: Subcontractor(s); Nominated Subcontractor(s); Contractor's Personnel].
The Employer may, in its absolute discretion, pay the [select one: Subcontractor(s); Nominated Subcontractor(s);
Contractor's Personnel] the amount the Employer determines as due and for which the Contractor has failed to
submit the requested evidence.
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This Notice is in reference to Sub-Clause 4.6 (b) [Non-payment by Contractor] of the General Conditions and to
the Employer’s communication with reference number [insert reference number] dated [insert date], requesting
evidence of payments made to the [select one: Contractor’s Personnel; Subcontractor(s); Nominated
Subcontractor(s)].
The Contractor is hereby given Notice that the Employer has paid the [select one: Contractor’s Personnel;
Subcontractor(s); Nominated Subcontractor(s)] in the amount [insert the amount paid], which the Employer
determines as due and for which the Contractor has failed to submit satisfactory evidence as described in Sub-
Clause 4.6 (a) [Non-payment by Contractor].
The Employer shall recover, subject to Sub-Clause 10.12 [Set-Off], this amount paid as a debt due from the
Contractor to the Employer.
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
022 – Consent or no consent for the removal of the Contractor's Equipment – Sub-
Clause 4.7 (a)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
Subject: [Select one: Consent; No consent] for the removal of the Contractor's
Equipment
This communication is in reference to Sub-Clause 4.7 (a) [Contractor’s Equipment] of the General Conditions and
to the Contractor’s communication with reference number [insert reference number] dated [insert date] and
received on [insert date], requesting consent to remove major items of the Contractor’s Equipment from the Site.
➔ Option 1: Consent
Consent is hereby granted for the removal of the following major items of the Contractor's Equipment from
the Site: [insert major items of the Contractor's Equipment that can be removed from the Site].
The Contractor is required to return the Contractor’s Equipment to the Site by [insert date].
[insert details of any other requirements that the Contractor must follow, if applicable].
➔ Option 2: No consent
Consent is not granted for the removal of the following major items of the Contractor’s Equipment from the
Site: [insert major items of the Contractor's Equipment that cannot be removed from the Site]. This is due to
the following reasons: [insert reasons].
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 4.8 (a) [Setting Out] of the General Conditions, the Contractor is hereby instructed to
set out the Works in relation to the original points, lines and levels of reference specified in the Contract and in
accordance with the following details: [insert details here].
The Contractor shall be responsible for the correct positioning of all parts of the Works, including verifying the
accuracy of all these items of reference prior to setting out the Works. The Contractor shall rectify any error in the
positions, levels, dimensions or alignments of the Works.
Sincerely,
024 – Notice to Correct: Health and Safety Improvement Notice – Sub-Clauses 4.9 (d)
and 11.1
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clauses 4.9 (d) [Health, Safety, Social and Environment] and 11.1 [Notice to Correct] of the
General Conditions, it has been noted that the Contractor has failed to comply with the health and safety
obligations as set out in the Contract.
The Contractor is hereby issued this Health and Safety Improvement Notice to implement the necessary
corrective measures and comply with the following health and safety requirements in accordance with the
Contract: [insert the health and safety requirements that the Contractor is in breach of and needs to comply with].
The Contractor shall submit as soon as possible and no later than seven (7) days a Notice describing the
measures that will be taken to remedy the failure, and indicate the date on which such measures will be
commenced in order to comply with this Notice to Correct.
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
025 – Notice of suspension for breach of health and safety obligations – Sub-Clauses
4.9 (f) and 6.6 (a)
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 4.9 (i) [Health, Safety, Social and Environment], it has been noted that the [select
one: Subcontractor; Nominated Subcontractor] [insert the name of the Subcontractor or Nominated
Subcontractor] has [select one or both: seriously; [and] repeatedly] breached the health and safety obligations set
out in the Contract.
In light of this [select one or both: serious; [and] repeated] breach, the Contractor is hereby instructed to
terminate the services of and expel from the Site the [select one: Subcontractor; Nominated Subcontractor]
[insert the name of the Subcontractor or Nominated Subcontractor], effective immediately.
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
027 – Request to uncover the Works for testing – Sub-Clause 4.11 (e)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 4.11 (e) [Testing by the Contractor] of the General Conditions, the Contractor has
failed to give sufficient Notice before covering the following parts of the Works: [insert specific details]. The
Contractor is therefore required to uncover the following parts of the Works: [insert details of the work to be
uncovered].
The Contractor is responsible for the full cost of uncovering, testing and reinstatement of such work uncovered in
accordance with Sub-Clause 4.11 (e) [Testing by the Contractor].
Sincerely,
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In refererence to Sub-Clause 4.14 (a) [Security of the Site] of the General Conditions, the following person[s]
[select one: is; are] authorized to enter and remain on the Site effective [insert date and time] for [insert time
period of access]: [insert names and details of the person(s) authorized to enter].
Access will be in accordance with the Site access procedures developed for the Site, and the Contractor is
responsible for the health and safety of all persons authorized to be on the Site.
Sincerely,
Signed by: [insert full name of the Employer’s contact person or the Employer’s Representative]
[select one: For and on behalf of the Employer; Employer’s Representative]
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
029 – Consent or no consent for the storage and use of arms, ammunition and
explosives on the Site – Sub-Clauses 4.16 (a) and 4.23 (a)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
Subject: [Select one: Consent; No consent] for the storage and use of arms,
ammunition and explosives on the Site
This communication is in refererence to Sub-Clauses 4.16 (a) [Blasting] and 4.23 (a) [Arms, Ammunition and
Explosives] of the General Conditions and to the Contractor’s communication with reference number [insert
reference number] dated [insert date] and received by the Employer on [insert date].
➔ Option 1: Consent
Consent is hereby granted for the Contractor to store and use [insert details of arms, ammunition or
explosives allowed on the Site] for the following Works-related purposes: [insert the intended use for which
the materials will be permitted on the Site].
The Contractor shall comply with all regulations in force in the Country regarding the storage and use of
explosives.
➔ Option 2: No consent
Consent is not granted for the Contractor’s request for the following reasons: [insert reasons].
This communication does not in any way relieve the Contractor from any of its warranties, obligations or liabilities
under or in connection with the Contract.
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ Prior to issuing consent seek guidance on the local regulations from a competent in-country authority and
UNDSS related to permission and handling such materials.
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This Notice is in reference to Sub-Clause 5.1 (c) and (d) [Contractor’s Design Obligations] of the General
Conditions and to the submission of the Contractor’s design for Review dated [insert date] and received on [insert
date].
➔ Option 1: No-objection
The Review has been completed, and the following Contractor’s designs, along with the amendments
thereof, are found to be in accordance with the Contract and hereby accepted: [insert details of the
Contractor’s designs submitted, including version numbers and dates].
➔ Option 2: Rejected
The Review has been completed, and the following Contractor’s designs are not found to be in accordance
with the Contract and are hereby rejected: [insert details of the Contractor's designs that are not accepted
and reasons why they are not in accordance with the Contract].
The Contractor is therefore required to amend the Contractor’s designs and promptly resubmit them for
Review.
This Notice does not in any way relieve the Contractor from any of its warranties, obligations or liabilities under or
in connection with the Contract, including responsibility or liability for errors, omissions, discrepancies, defects
and non-compliances in the Contractor's design.
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ Any review and acceptance of design documents should be in alignment with the relevant UNOPS policy
and requirements for design review. This has to be detailed when instruction is given for the Contractor to
design parts or Sections of the Works.
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This Notice is in reference to Sub-Clause 6.3 (b) [Programme] of the General Conditions and to the Contractor’s
Programme marked [insert revision number] and dated [insert date] and received on [insert date] in accordance
with Sub-Clause 6.3 (a).
A Review of the Programme has been completed, and the Programme does not comply with the Contract. Details
of the non-compliance are as follows: [insert details as to the extent to which the Programme does not comply
with the Contract Sub-Clause 6.3 [Programme] and Schedule 3.5 [Programme Requirements]].
In accordance with Sub-Clause 6.3 (b) [Programme], the Contractor is therefore required to submit a revised
Programme within [insert number of days] days after receiving this Notice.
This Notice does not in any way relieve the Contractor from any of its warranties, obligations or liabilities under or
in connection with the Contract.
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This Notice is in reference to Sub-Clause 6.3 (b) [Programme] of the General Conditions and to the Contractor’s
fully detailed Programme marked [insert revision number] and dated [insert date] and received on [insert date] in
accordance with Sub-Clause 6.3 (a).
A Review of the fully detailed Programme has been completed, and the Contractor’s Programme is hereby given
this Notice of No-objection. Therefore, in accordance with Sub-Clause 6.3 (c) [Programme], the Programme will
be used to monitor the progress of the execution of the Works, and the Employer’s Personnel shall rely on the
Programme for the administration of the Contract.
This Notice does not in any way relieve the Contractor from any of its warranties, obligations or liabilities under or
in connection with the Contract.
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 6.3 (c) [Programme] of the General Conditions, the Contractor is hereby informed that
the current Programme no longer complies with the requirements of the Contract for the following reasons: [insert
details as required by Sub-Clause 6.3 (a) and Schedule 3.5 [Programme Requirements]].
In accordance with Sub-Clause 6.3 (c) [Programme], the Contractor is therefore required to submit a revised
programme within [insert number of days] days of receiving this communication.
This communication does not in any way relieve the Contractor from any of its warranties, obligations or liabilities
under or in connection with the Contract.
Sincerely,
034 – Notice to suspend progress of the Works or parts of the Works – Sub-Clause 6.6
(a)
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
035 – Notice to resume progress of the Works or parts of the Works – Sub-Clause 6.6
(b)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
Subject: Notice to resume progress of [select one: the Works; parts of the
Works]
In reference to Sub-Clause 6.6 (b) [Suspension by Employer] of the General Conditions, the Contractor is hereby
instructed to resume progress of [select one: the Works; parts of the Works] [select one: immediately upon
receipt of this Notice; on [insert date]]. [If resuming progress of parts of the Works, insert details of the specific
parts here].
Sincerely,
Signed by: [insert full name of the Employer’s contact person or the Employer’s Representative]
[select one: For and on behalf of the Employer; Employer’s Representative]
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
036 – Notice to resume progress of the Works or parts of the Works under a
prolonged suspension – Sub-Clause 6.6 (c)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
Subject: Notice to resume progress of [select one: the Works; parts of the
Works] under a prolonged suspension
This Notice is in reference to Sub-Clause 6.6 (c) [Suspension by Employer] of the General Conditions and to the
Contractor’s Notice with reference number [insert reference number] dated [insert date] and received by the
Employer on [insert date], requesting the Employer’s permission to resume progress of [select one: the Works;
parts of the Works] that has been under a prolonged suspension. The Contractor is hereby instructed to resume
progress of [select one: the Works; parts of the Works] [select one: immediately upon receipt of this Notice; on
[insert date]]. [If resuming progress of parts of the Works, insert details of the specific parts here].
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 8.1 (a) [Completion of Outstanding Works and Remedying Defects] of the General
Conditions, the Employer hereby gives Notice to the Contractor that [select one: defects have appeared; damage
has occurred] as a result of [insert the relevant options as listed in Sub-Clause 8.1 (a)].
Details of the [select one: defects; damage; failure to pass the tests] are as follows: [insert details of the defects
or damages or the tests].
The Contractor shall remedy the defects or damage within [insert time frame for rectification] in accordance with
Sub-Clause 8.1 (a) [Completion of Outstanding Works and Remedying Defects]. All work under Sub-Clause 8.1
[Completion of Outstanding Works and Remedying Defects] shall be executed at the risk and cost of the
Contractor.
Should the Contractor fail to rectify the defects or damage within the time frame specified in this Notice, the
Employer may carry out the work or engage another party to do so at the Contractor's risk and expense.
Sincerely,
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
040 – Extension of Defects Notification Period – Sub-Clause 8.1 (d) and (e)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 8.1 (d) and (e) [Completion of Outstanding Works and Remedying Defects] of the
General Conditions, the Employer hereby extends the Defects Notification Period by [insert number of days] due
to the following reasons: [insert reasons applicable in accordance with Sub-Clause 8.1 (d)].
Sincerely,
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 8.3 [Final Completion Certificate] of the General Conditions, a Final Completion
Certificate dated [insert date] is attached herewith, certifying that the Contractor’s obligations under the Contract
have been completed as of [insert date].
The issue of this Final Completion Certificate does not relieve the Contractor from any of its warranties,
obligations or liabilities in accordance with Sub-Clause 8.4 [Unfulfilled Obligations] or as otherwise imposed by
Laws.
Sincerely,
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 9.1 (a) [Right to Vary] of the General Conditions, the Contractor is hereby instructed
to carry out the following Variation to the Works: [insert details describing the Variation to the Works in
accordance with Sub-Clause 9.1 (b)].
The Contractor is further requested, in accordance with Sub-Clause 9.1 (c) and (d) [Right to Vary], to submit a
proposal related to this Variation instruction as soon as practicable and within fourteen (14) days of receipt of this
Notice, and before the Contractor carries out the Variation.
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This communication is in reference to Sub-Clause 9.1 (c) and (e) [Right to Vary] of the General Conditions and to
the Contractor’s proposal in response to the Notice of Variation instruction with reference number [insert
reference number] dated [insert date] and received on [insert date].
➔ Option 1: Approval
The Contractor’s proposal submitted in accordance with Sub-Clause 9.1 (c) [Right to Vary] is hereby
approved, and the Contractor shall now be bound by the Notice of Variation instruction with reference
number [insert reference number] dated [insert date], and shall execute the Variation with due expedition and
without delay in accordance with Sub-Clause 9.1 (e).
Please note that, should the Contractor be eligible for entitlements to any adjustment to the Contract Price
and/or any Extension of Time, a Claim Notice must be submitted pursuant to Clause 16 [Contractor’s Claim].
➔ Option 2: No approval
The Contractor’s proposal has not been approved.
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
➔ There are three options set out above. Delete whichever options are not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
044 – Instruction to carry out work under Provisional Sum – Sub-Clause 9.3
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 9.3 [Provisional Sums] of the General Conditions, the Contractor is hereby instructed
to carry out the following work, which is a Provisional Sum item under the Contract: [insert details of: (a) work to
be executed (including Plant, Materials or services to be supplied by the Contractor) and/or (b) Plant, Materials or
services to be purchased by the Contractor].
The Contractor is required to produce the following records in substantiation of the work carried out under the
Provisional Sum: [insert details of records to be produced, including invoices, vouchers and accounts or receipts].
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 9.4 [Daywork] of the General Conditions, the Contractor is hereby instructed to carry
out the following Variation to the Works on a daywork basis: [insert the details of the Variation].
This work shall be valued in accordance with the daywork rates and schedule included in Schedule 4.1.B
[Daywork Schedule].
The Contractor shall keep records of the hours of labour, the Contractor's Equipment and the quantities of Plants
and/or Materials used.
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
046 – Issue of the Final Payment Certificate – Sub-Clauses 10.7 and 10.9
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Attention to: [insert the full name of the Employer’s first contact person]
[insert position title], UNOPS
[insert the first contact person’s address]
[insert the first contact person's email address]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This communication is in reference to Sub-Clauses 10.7 [Final Statement] and 10.9 [Final Payment Certificate] of
the General Conditions and to the Contractor’s Final Statement dated [insert date] and received on [insert date].
Pursuant to the Contractor’s submission of a discharge in accordance with Sub-Clause 10.8 [Discharge], the
Final Payment Certificate is hereby issued.
The Contractor is entitled to the amount [insert amount and currency], which has been fairly considered as finally
due under the Contract in accordance with Sub-Clause 10.9 (a) [Final Payment Certificate] and as detailed in the
Final Payment Certificate attached herewith.
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ The Employer’s Representative must attach particulars in support of the amounts determined to be payable,
including details of any deductions or any amounts that are set-off to be paid by the Contractor in
accordance with Sub-Clause 10.12 [Set-Off] and any amounts in disagreement, including reasons for such
disagreement.
➔ The Final Payment Certificate amount shall not be issued unless the Final Completion Certificate has been
issued and the Contractor has provided the Employer with a written discharge (confirming that the total of
the Final Statement represents full and final settlement of all monies due to the Contractor).
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 10.12 [Set-Off] of the General Conditions, the Employer hereby sets-off the amount
due by the Contractor to the Employer, [insert the amount set-off] related to [insert the details related to the
amount set-off].
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ A contact person for the Employer is listed in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’. This person should be the relevant Procurement Authority
identified during the solicitation process. The contact person may change over the course of the Contract
and the most current information should always be used when issuing this communication.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
In reference to Sub-Clause 11.1 [Notice to Correct] of the General Conditions, it has been noted that the
Contractor has failed to comply with the following obligations under the Contract: [insert details as in Sub-Clause
11.1, including specific references to the applicable Sub-Clauses in the Contract].
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
052 – Notice of termination for the Employer's convenience – Sub-Clause 11.4 (a)
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
054 – Instruction to rectify loss or damage to the Works – Sub-Clause 13.3 (a)
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This communication is in reference to Sub-Clause 13.3 (a) [Consequences of Employer's Risks] of the General
Conditions and to the Contractor’s Notice with reference number [insert reference number] dated [insert date] and
received on [insert date], describing the following loss or damage: [insert description of loss or damage to the
Works].
As a consequence of [insert the relevant Employer's risk listed in Sub-Clause 13.2 [Employer’s Risks]] resulting
in loss or damage to [insert the relevant part or parts of the Works], the Contractor is instructed to rectify this loss
or damage as follows: [insert scope and extent of rectification].
This instruction shall be deemed to have been given under Sub-Clause 9.1 [Right to Vary].
Sincerely,
Copy to: [insert the full name of the Employer’s contact person], [position title], UNOPS
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
056 – Notice of conclusion of effects from Force Majeure – Sub-Clause 14.3 (b)
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.
Employer: UNOPS
Contractor: [insert the Contractor’s name as indicated in the Instrument of Agreement]
Contract: [insert the Contract title as indicated in the oneUNOPS Contract Management module]
[insert the 7-digit Contract ID as indicated in the oneUNOPS Contract Management module]
This communication is in reference to Sub-Clause 15.2 (b) [Arrangements] of the General Conditions and to the
Contractor’s communication with reference number [insert reference number] dated [insert date] and received by
the Employer on [insert date], in respect to the Contractor’s obligations under Sub-Clause 15.1 (a) [Extent of
Cover].
➔ Option 1: Approval
Approval is hereby given for the insurers and terms of insurance obtained by the Contractor. The Contractor
shall subsequently provide the Employer with evidence that the insurance policy is in force and that the
premiums have been paid.
➔ Option 2: No approval
Approval is not given for the [select one or both: insurers; [and] terms of insurance] obtained by the
Contractor for the following reasons: [insert reasons].
This communication does not relieve the Contractor from its obligation to complete the Works or from any of its
other warranties, obligations or liabilities under or in connection with the Contract.
Sincerely,
Copy to: [insert the full name of the Employer’s Representative], Employer’s Representative
NOTES
➔ It is highly recommended to consult the insurance specialist in IPAS Admin and the relevant project finance
unit for verification and to check the validity of the insurance policies submitted by the Contractor.
➔ The Employer contact person as indicated in Schedule 1.1 [Details Provided by the Employer] under
‘Employer’s address for communication’ should be the relevant Procurement Authority identified during the
solicitation process. The contact person may change over the course of the Contract and the most current
information should always be used when issuing this communication.
➔ There are two options set out above. Delete whichever option is not applicable as well as the yellow
highlighted text and this yellow notes box before sending.
NOTES
➔ Use of this template requires consultation with a Legal Advisor. Project teams must contact IPAS Legal for a
copy of the template and related support. Failure to do so may result in serious legal and commercial
consequences for UNOPS.