Critical Path Template 02
Critical Path Template 02
Activity Description
A Negotiate contract
B Preliminary missile design
C Design guidance system
D Select missile configuration
E Design missile frame
F Design missile fuel system
G Design rocket engine
H Final missile design
I Fabricate missile frame, fuel system and engine
J Fabricate guidance system
K Test missile frame, fuel system and engine
L Test guidance system
M Assemble completed missile
1
Ragsdale, Cliff T., Spreadsheet Modeling and Decision Analysis, A Practical
Introduction to Management Science, Course Technology, Inc., Cambridge, MA, 1995
CPM Project Management Example
ABM Design Project - Basic Relationship Diagram
C I
H
A B
J
E
D
F
G
K
L
CPM Project Management Example
ABM Design Project - Time Table, Forward Pass
time zero.
mum) earliest
**
** Calculating Slack:
Slack for activity i = LSTi - ESTi
**
**
**
**
**
**
CPM Project Management Example
ABM Design Project - Time Table, Determining Critical Path
**
Design missile frame
**
Design missile fuel system
**
Design rocket engine
** Final missile design
Fabricate missile frame, fuel system and engine
quired to perform Fabricate guidance system
they do not appear
create a Gantt chart Test missile frame, fuel system and engine
Day
chart and how it
en finished with the
o 1.
Patterns option and
chart can be further
oxes.
Design Gantt Chart
0 50 100 150 200 250 300 350 400 450 500
ntract
design
ystem
ration
frame
ystem
ngine
design
ngine
ystem
ngine
ystem
issile
Days
500