You are on page 1of 19

Energy Policy 124 (2019) 180–198

Contents lists available at ScienceDirect

Energy Policy
journal homepage: www.elsevier.com/locate/enpol

An analysis of the historical trends in nuclear power plant construction T


costs: The Japanese experience

Yuhji Matsuoa,b, , Hisanori Neib
a
The Institute of Energy Economics, 1-13-1, Kachidoki, Chuo-ku, Tokyo 104-0054, Japan
b
National Graduate Institute for Policy Studies, 7-22-1, Roppongi, Minato-ku, Tokyo 106-8677, Japan

A R T I C LE I N FO A B S T R A C T

Keywords: In this study, we collected Japanese nuclear power plant construction cost data from official documents sub-
Nuclear mitted by the electric utilities and conducted a quantitative analysis of the past trends. We found that the unit
Power generation cost construction cost of Japanese nuclear power plants rose during the period from 1975 to 1980, when the “im-
Econometrics provement and standardization” programs took place, and did not increase or decline significantly after that. We
Regression
also observed significant economies of scale, even if we take into account interest during construction, as well as
Interest during construction
the so-called overnight cost. As far as we know, this study is the first attempt to analyze the total history of
Japan's nuclear power generation until the Fukushima accident from the cost perspective. The findings could
contribute to a better understanding of the economics of nuclear power, as similar studies in the United States
and France tend to exhibit different results. The analyses in this study appear to reinforce the reliability of the
cost estimation by the Japanese government, which has been used as the numerical basis for the current energy
policies in Japan.

1. Introduction 49 GW were in operation. After the accident, however, they succes-


sively stopped operation after periodic inspections, resulting in the
As in many other developed countries, nuclear power had long been cessation of all nuclear reactor operation after May 2012. In the same
accounting for a considerable share in the power generation mix in year, the newly established Nuclear Regulatory Authority (NRA) for-
Japan. Since the launch of the Tokai nuclear power plant in 1966, the mulated new regulation requirements, and it was not until September
nuclear power generation capacity continued to expand steadily, 2015 when the first nuclear power plant, Sendai unit 1, passed NRA's
reaching an output of 322 TWh in 2000, and accounting for 30% of the safety requirements and started operation. As of 2018, 15 reactors at 8
total power supply. Behind this development was the growing re- sites have passed the requirements and 9 reactors, i.e. Takahama-3 and
cognition that nuclear power can contribute greatly to a cheap and 4, Ohi-3 and 4, Ikata-3, Genkai-3 and 4, and Sendai-1 and 2, have
stable power supply in the wake of the two oil crises in 1973 and 1979. started operation, although with some judicial troubles.
Moreover, after the early 1990s, when the climate change issue began In the government's new "Long-Term Energy Supply and Demand
to attract international attention, nuclear power was also expected to Outlook" published in 2015, the target of the nuclear power share in
play a role as a large-scale low-carbon power source. In the "Long-Term 2030 was set between 20% and 22% of the total power generation,
Energy Supply and Demand Outlook (recalculation)" published by the reflecting a major downward revision from the previous plan (METI,
Japanese government in 2009, the share of nuclear power in the power 2015). Meanwhile, new nuclear power plant construction plans have
generation mix was expected to expand to 42% by 2020 and to 49% by been stagnant after the Fukushima accident, with no single reactor
2030. To achieve this, nine new nuclear reactors were supposed to be newly starting operation after the Fukushima accident as of 2018. Ex-
constructed by 2020, and the average load factor, which was around isting reactors will have a lifetime of 40 years, which can only be ex-
60% at that time, was expected to rise to the global average of 80% tended to 60 years at the maximum. This means that if Japan is to
(METI, 2009). continue relying on nuclear power even after 2030, it would be ne-
However, in the wake of the Fukushima Daiichi nuclear power plant cessary to restart new construction in the near future.
accident in 2011, the Japanese energy policy was forced to undergo In the formulation of basic energy plans by the government, one of
major changes. At the time of the accident, 54 nuclear reactors totaling the factors recognized as crucial has been the economic efficiency of


Corresponding author at: The Institute of Energy Economics, 1-13-1, Kachidoki, Chuo-ku, Tokyo 104-0054, Japan.
E-mail address: matsuo@edmc.ieej.or.jp (Y. Matsuo).

https://doi.org/10.1016/j.enpol.2018.08.067
Received 19 March 2018; Received in revised form 14 August 2018; Accepted 31 August 2018
0301-4215/ © 2018 Elsevier Ltd. All rights reserved.
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

various power sources. Before the Fukushima accident, the without estimating their overnight costs.
Subcommittee to Study Costs and Other Issues, established by the The rest of the article is organized as follows: Section 2 presents a
government in 2004, estimated nuclear power generation costs at JPY brief literature review. Section 3 describes the data used and the
279 thousand/kW (USD 2580/kW) of unit construction cost and JPY methodology. Section 4 presents the results of the analysis and a dis-
5.3/kWh (USD 49/MWh) of power generation unit cost, when assuming cussion of the results, while Section 5 provides the conclusion and
a real discount rate of 3% and an average load factor of 80% (FEPC, policy implications. The appendices include a detailed description of
2004). After the accident, arguments that this estimation has not been the data and supplementary analyses, as well as some discussions re-
properly included the “hidden costs” of nuclear power, such as the costs garding IDC and the correction of the cost data.
for research and development, public acceptance, and accident risks All the prices were converted to 2011 JPY before being used in
arose among the public. To respond to this objection, the government calculations, with USD prices also shown for reference. Since yen was
re-estimated the power generation costs extensively in 2011 and 2015 exceptionally strong in 2011 with an exchange rate of 80 JPY/USD, we
(Costs Verification Committee, 2011; Power Generation Cost Analysis converted the prices to 2016 USD at 109 JPY/USD, to avoid misleading
Working Group, 2015). In the 2015 estimation, the unit power gen- the reader.
eration cost of nuclear plants supposed to start operation in 2030 stood
at JPY 8.8/kWh (USD 83/MWh) and JPY 10.3/kWh (USD 97/MWh), 2. Literature review
excluding and including policy costs, respectively, when assuming a
real discount rate of 3% and an average load factor of 70%, which was The escalation of nuclear power plant construction costs has long
still considered to prove the cost competitiveness of nuclear power been pointed out in North America (Montgomery and Quirk, 1978;
generation after the Fukushima accident, and was recognized as one of Keng, 1985). Especially in the United States where much data has
the evidences to support the Outlook as mentioned above. In this esti- widely been made public, the rise in nuclear construction costs has been
mation, the unit construction cost of a nuclear power plant was as- subjected to many studies (Mooz, 1979; Paik and Schriver, 1980;
sumed to be JPY 370 thousand/kW (USD 3500/kW) with reference to Komanoff, 1981; Zimmerman, 1982; EIA, 1986; Cantor and
recently constructed plants in Japan, and on top of that, JPY 601 bil- Hewlett, 1988; McCabe, 1996). While many studies observe reductions
lion/unit (USD 5.7 billion/unit), which is roughly equivalent to JPY 50 in costs due to learning, it is also true that the nuclear construction cost
thousand/kW (USD 470/kW), was assumed as the additional costs for has actually been rising, and many studies attribute this escalation to
safety measures based on the actual expenses by the electric utilities to increasing regulations over time (University of Chicago, 2004). For
meet the new regulation requirements by the NRA. This means that the example, Komanoff (1981) analyzed 46 nuclear reactors constructed by
nuclear cost estimation by the government implicitly assumes that there 1978 and pointed out that the cost increase had been occasioned by the
will be no cost escalation until 2030, other than the costs for the ad- application of “more stringent and explicit regulatory standards” during
ditional safety measures which have already been revealed as actual the late 1960s and throughout the 1970s. The Three Mile Island (TMI)
expenses. To assess the validity of this implicit assumption, it would be accident that occurred in 1979 resulted in further strengthening the
indispensable to analyze the historical trends in nuclear power plant safety regulations, and the rapid rise in the construction costs thereafter
construction costs in detail, and identify the factors influencing the has been repeatedly discussed (Koomey and Hultman, 2007; Cooper,
costs. 2010; Hultman and Koomey, 2013). Another point for discussion was
In this context, this study extracts Japanese cost data from docu- the economies of scale. Some of the studies observed this explicitly,
ments by electric utilities (Electric Power Companies in Japan, with the declining unit construction costs for larger power plants;
1959–2003), and conducts a quantitative analysis using them. It aims to however, others did not find the effect significant. Even in the studies
add another frame of reference to nuclear construction cost analysis where it was observed the effect was mixed. For example, Cantor and
showing an example of the (as of early 2018) third largest nuclear fleet Hewlett (1988) showed that the scale expansion has the effect of re-
after the United States and France, and to inform policymakers in ducing the unit cost on its own, but at the same time, it leads to pro-
Japan, as well as in other countries. Its contributions to the literature longed construction lead time, eventually resulting in a rise in the unit
are as follows: First, this paper presents the costs of Japanese nuclear construction cost.
power plants, both including and excluding interest during construction In France, unlike in the United States and unlike in Japan, which is
(IDC). These data are based on the official documents submitted by the described later, detailed cost data of nuclear power plants had not been
electric utilities to the government, and as far as the authors know, they disclosed until recently. Grubler (2010) estimated the costs based on
are the first set of data made public in English that represent the total the annual expenditures for French PWR program from 1970 to 2000.
history of Japan's nuclear power generation. He observed a cost escalation of about a factor of 3.5 between 1974 and
Second, the results of the analysis lead to conclusions different from the post 1990 period, and pointed out the “negative learning” effects
those of past studies: although the Japanese nuclear industry once ex- intrinsic in the nuclear industry. He also suggested that contrary to the
perienced a cost hike in its history, the data exhibit a different trend normal scale economies, the unit cost of a nuclear power plant rises
from the so-called "negative learning" or the continuous escalation of along with the scale, due to increasing technological complexity.
the unit costs. Rather, we can see that unit construction cost in Japan It was not until 2012 that the French government disclosed com-
has been almost flat after 1990. The results of the analysis also indicate prehensive information on nuclear costs in the country, including those
that Japanese nuclear power plants show significant economies of scale. of plant construction (Cour des comptes, 2012, although Grubler, 2014
Note that these two points are not contradictory because the ten expresses doubt about the reliability of this information). Several ana-
Japanese power utilities have been constructing nuclear reactors of lyses were performed based on this (Boccard, 2014; Escobar-Rangel and
different size according to the demand scale. As described later, these Lévêque, 2015). According to Escobar-Rangel and Lévêque (2015), al-
findings are in sharp contrast to the conclusions of similar studies, though the construction costs of nuclear reactors certainly increased in
which are mainly based on U.S. and French data. France, the rise was more moderate than that estimated by Grubler
Third, this study highlights the importance of estimating the (2010). It was also pointed out that the unit construction cost had been
“overnight costs”, or the costs excluding IDC. Although it is obvious increasing in France as the reactor design evolved, which, on the other
that the costs including IDC represent the actual expenses by the uti- hand, had a significant effect on improving safety. In addition, while
lities, some studies estimate the costs of different power generation learning effect can be seen within the same design, the unit cost rose
technologies comparing the overnight costs (e.g., IAEA and NEA, 2015), along with the scale, and based on this, small modular reactors (SMRs)
causing considerable controversy. We revisited this issue and argue that were regarded as a promising option that can contribute to reducing
the cost of Japanese nuclear power plants cannot be estimated properly capital costs.

181
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

An analysis on the trend in the unit cost of nuclear power plants in conduct analyses (Koomey et al., 2017; Gilbert et al., 2017; Lovering
Japan was conducted by Marshall and Navarro (1991), who analyzed et al., 2017). In general terms, no one objects to the fact that the cost
the costs of 34 nuclear power plants constructed by the late 1980s. It including IDC is the “true” cost for the utilities. On the other hand, it
should be noted, however, that this analysis did not include the plants also seems obvious that the best way is to separate these different costs,
that started operation after 1990, and as described later, Japan hap- if we can, and estimate them separately, since the costs that are directly
pened to experience great changes in the trends in nuclear costs right affected by the interest rates are quite different in nature from other
around that year. For this and other reasons, this analysis should be expenditures. In practice, however, this issue should be said to depend
seen as only partly reflecting the Japanese experience. Meanwhile, as on the data obtained.
the cost data for these 34 units were a rare example found in English This study estimated the real overnight cost ZO, the real IDC ZI, and
literature, the data were subsequently quoted in academic literature the real total cost ZT = ZO + ZI, according to the method shown in
and used for analyses (e.g. Sovacool et al., 2014). Appendix C, using the reported construction costs. In the case of data
Analyses including the data for the plants that started operation for Japan, unlike those for the United States which only report the total
after 1990 have hardly been conducted so far. This is probably because mixed current costs, ZO is calculated in the first place from the reported
of the fact that the open literature on the construction costs are avail- overnight costs and the assumed inflation rates. ZI and ZT are estimated
able only in Japanese. Surprisingly, however, as far as the authors from ZO and the assumed interest rates. ZI is quite different in nature
know, even in the literature published in Japanese by Japanese re- from the other part of the construction costs, ZO, in that it pro-
searchers, quantitative analyses of the cost trends until the Fukushima portionally varies depending on the interest rates. Taking these situa-
accident have not been attempted, except for a preliminary analysis by tions into consideration, this study focused mainly on the real overnight
the authors of this article (Matsuo and Nei, 2018). This may be because cost ZO, while also evaluating the total cost ZT. When calculating ZO, at
this issue has not been attracting the attention of policy makers and least two methods can be used; i.e. we can use varying values according
researchers, nor has it been the subject of criticism by NGOs, as the to Eq. (C.2) in Appendix C, or use fixed values according to Eq. (C.7).
construction costs in Japan have not been escalating after the 1990s, as We tried both methods.
described later, unlike in Europe and in the United States. The tables in the Application Documents only show the total cost
Relatively new analyses include MIT (2003), which used the “total figures for some of the plants, i.e. Tomari-3, Higashi-dori, Hamaoka-3
project cost” data for Onagawa-3, Genkai-3 and 4, and Kashiwazaki- and 5, Shika-2 and Ikata-3, although they are supposed to include IDC.
Kariwa-3, 4, 6, and 7, as provided by a Japanese analyst or taken from For these plants, we calculated ZI from the total cost and assumed in-
annual reports by the utilities, and other relevant organizations. Du and terest rates in the first place, and then estimated the IDC on the reported
Parsons (2009) gathered construction costs of nuclear power plants that base, RI, assuming the same ratio RI / ZI, which ranges from 0.4 to 0.8,
began operations after 2003, i.e. Hamaoka-5, Higashi-dori, and Shika-2, as other plants of the same utility.
from press releases of the utilities and other sources, and used them for Fig. 1 shows the trends in the share of IDC, i.e. the reported IDC RI,
analysis. With these recent data, however, it is not possible to reveal the divided by the reported total cost RT. The share is no higher than 15%
full historical trends in construction costs in Japan. even in the highest case, Tokai Daini, and has considerably been de-
Lovering et al. (2016) probably represents the first attempt in the clining after 1990. This is mainly due to the decline in the interest rate.
literature published in English to show the trend of the construction The figure also shows that the ratio had been rising from 1970 to 1980,
cost from the early stage of nuclear development in Japan up to the while the interest rate had not been changed significantly. This is partly
Fukushima accident. The data used here were provided by one of the because of the upward trends in the construction period, as shown in
authors of this article (Matsuo Y.), and are based on informal hearings Fig. 2. Some doubts remain, however, as the IDC ratio was not declining
with the electric utilities. Fig. 8 in the paper is a clear visualization of during the period from 1980 to 1990, despite the downward trends in
the trends in nuclear construction costs in Japan. This was a part of an the construction period.
attempt to show the history of construction costs throughout the world, In any case, these situations in Japan differ significantly from those
and seems to have been successful in providing data from a wider range in the United States, where IDC is said to account for 46% of the total
of countries, not only the United States and France that have been construction cost (Gilbert et al., 2017). Especially, IDC has not exerted
mainly studied so far. At the same time, from the viewpoint of an any large influence on the total cost after 1990 in Japan because of the
analysis of the Japanese experience, it could be pointed out that the low interest rates.
data are based on informal hearings rather than published sources, and Fig. 3 shows the unit cost, i.e. ZO in 2011 real yen divided by the
that the paper only shows a trend in costs, and does not analyze gross capacity, versus the year of commercial operation. The unit costs
quantitatively the factor of the changes in the costs. In view of this, we of the very first plants of both boiling water reactors (BWRs) and
performed in this article quantitative analyses using official data taken pressurized water reactors (PWRs) are relatively high at around JPY
from published documents.

3. Data and methodology

3.1. Construction costs of nuclear power stations

We used the nuclear power plant construction cost data that appear
in genshiro secchi kyoka shinsei-sho (“Application document for reactor
installment license”) or genshiro secchi henkou kyoka shinsei-sho
(“Application document for the modification of reactor installment li-
cense”), referred to as the Application Documents hereafter (Electric
Power Companies in Japan, 1959–2003). A detailed description of the
data is found in Appendices B and C. It is worth mentioning that the
data include IDC, as well as other costs, which are usually referred to as
the overnight costs.
The impact of IDC on the economics of nuclear power plant con-
struction cannot be overstated. There has been considerable debate on
whether this should be included in the construction costs when we Fig. 1. IDC share and the prime lending rate.

182
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

I&S program. On the other hand, there is no reactor designed after the
program with lower unit cost than JPY 200 thousand/kW. Welch's t-test
shows that the reactors designed after the program had significantly
higher unit costs than those before the program, with a t-value of 8.50
and a p-value of 1.56 × 10–11. This means that with strong confidence,
we can say that any factor without explicit correlation with the I&S
program cannot be thought of as being the major reason for the his-
torical cost changes of Japanese nuclear power reactors, although we
cannot deny the possibility that some other event happening in the
same period, such as possibly any regulation changes or the revision of
the Building Standards Act, as described below, may partly had been a
cause of the changes. We should also note that only the first phase of
the I&S program, which lasted from FY 1975–1977, seems to have had a
great influence on the construction costs, while the effects of the second
and third phases cannot be seen obviously.
The Building Standards Act has been successively revised since its
enactment in 1950. One of the largest revisions was made in 1981, in
Fig. 2. Construction period of nuclear power plants. the wake of the Miyagi-ken-oki earthquake that took place in 1978.
Although the nuclear cost escalated prior to this revision, we cannot
deny the possibility that the plant manufacturers foresaw this revision
and reflected it in the plant designs.

3.2. Other data

Other data used as explanatory variables in this study include the


following.

3.2.1. Labor cost and material prices


Changes in construction costs are thought to reflect the changes in
labor costs and material prices. Annual wage per capita showed a re-
markable rise in Japan, from nominal JPY 1004 thousand/person (USD
2790/person with an exchange rate of 360 JPY/USD) in 1970 to JPY
4783 thousand/person (USD 33,000/person with 145 JPY/USD) in
1990 (EDMC, 2017), which means that unit labor cost almost doubled
in terms of real JPY during this period. This study used this unit labor
Fig. 3. Trends in the unit construction cost of Japanese nuclear reactors. Note:
cost in 2011 real Japanese yen, which has already been shown in Fig. 3,
“I&S” indicates that the plant reflects the results of the I&S programs.
as one of the explanatory variables.
On the other hand, the prices of steel, cement, and other construc-
200 thousand/kW (USD 2690/kW), but the succeeding plants are less tion materials roughly escalated in line with the general price level
expensive at below JPY 150 thousand/kW (USD 2020/kW). Re- (Research and Statistics, Department Bank of Japan, 2017). For this
markably, the plants that started operation in and after the 1980s are reason we did not use these prices as explanatory variables in this
much more expensive than the former ones, showing a cost hike ex- study.
ceeding the increase in labor costs. On the other hand, we do not ob-
serve any escalation of unit costs for the plants that started operation
3.2.2. Power generating capacity
after 1990.
The unit costs of large-scale facilities usually decline with increasing
As shown in the figure, most of the plants that started operation
scale. The effect of this “economy of scale”, however, is controversial
after 1984 reflect the results of the “Improvement and Standardization”
for nuclear facilities, as previously stated. Fig. 4 shows the relation
(I&S) programs which took place during FY 1975–1980 and thereafter,
led by the Japanese government, and aiming to achieve higher equip-
ment reliability and operational efficiency. For more details of the
program, the reader is referred to Appendix A.
At the same time, we note that the four plants before the programs,
which started operation in the 1980s, are more expensive than other
plants, showing almost the same level of unit costs as those of the plants
after the programs. These plants are Kashiwazaki-Kariwa-1 (construc-
tion start year: 1979 and operation start year: 1985), Fukushima Daini-
1 (construction start year: 1976 and operation start year: 1982),
Genkai-2 (construction start year: 1976 and operation start year: 1981),
and Ikata-2 (construction start year: 1977 and operation start year:
1982), in the order of unit cost from the highest. As discussed in
Appendix B, these “transitional” reactors are characterized by large
escalation in construction costs during the period of ongoing I&S pro-
grams, although they do not fully reflect the results of the programs.
Out of all the 56 LWRs, 36 reactors had higher unit costs above JPY
200 thousand/kW, of which only four reactors were designed before the
Fig. 4. Dependence of the unit cost on the capacity.

183
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

between the unit overnight cost and the gross power generating capa-
city. A mild decline in the unit cost might be observed in line with the
capacity. The two BWR units before the I&S program, shown as purple
squares, with higher unit costs, represent the “transitional” reactors
Kashiwazaki-Kariwa-1 and Fukushima Daini-1.
The significance of this correlation will be discussed later in Section
4.

3.2.3. Plant construction experience


Past experience of construction, which is in some cases equivalent to
time trends, is considered to be a factor that can have a significant
influence on the construction cost. It is widely known that the costs of
manufacturing usually decline due to learning effects, as obviously seen
in the case of solar photovoltaic panels. In the case of nuclear facilities,
several studies observe similar effects of learning by doing (University
Fig. 6. Construction lead time of Japanese nuclear reactors.
of Chicago, 2004; Jungler et al., 2008), while other studies conclude
that nuclear power is cursed with “negative learning” (Grubler, 2010),
showing increasing costs over time. 3.2.6. The effect of seismic safety standards
In this study we used the experience of reactor construction, Since Japan is a highly seismic country, particular attention has
quantified as the number of the plants previously constructed, as an been paid to the issues of seismic safety since the early stages of nuclear
explanatory variable. We can count the “experience” in many ways, e.g. development. In 1978, the Atomic Energy Commission formulated the
by counting the number of LWRs, or that of BWRs and PWRs separately, “Regulatory Guide for Reviewing Seismic Design of Nuclear Power
or that of the plants constructed by one specific manufacturer. Reactor Facilities”, which defines the Maximum Design Earthquake
Ground Motion (S1) and the Extreme Design Earthquake Ground
3.2.4. Construction period Motion (S2) as the Design Basis Earthquake Ground Motions that the
The construction period is usually regarded as a major factor in- plant designs should take into account. The magnitude of S1 is de-
fluencing the cost. Not only the IDC, but also the overnight cost itself is termined based on historical earthquake records and active faults, while
influenced by the construction period (Harris et al., 2013). We used the S2 is stronger than S1 and considered as equivalent to the earthquake
period from the Construction Start Date by IAEA-PRIS, although that could have the largest effect at the site, which is determined based
somewhat different from the JAIF data as described in Appendix B, to on seismological theory. In 2006, the Nuclear Safety Commission re-
the Commercial Operation Date by IAEA-PRIS. As can be seen in Figs. 2 vised the Regulatory Guide to integrate S1 and S2 into one Design Basis
and 5, the construction period of Japanese nuclear power plants has Earthquake Ground Motion SS, and to additionally formulate the
been stable at around five years, and its influence on the unit cost Elastically Dynamic Design Earthquake Ground Motion Sd. After the
cannot be seen clearly. Fukushima accident, the seismic standards have been thoroughly re-
viewed by the NRA. Since it could be thought that S1 and S2 assumed in
3.2.5. Construction lead time the plant designs had been affecting the construction costs, we used
The construction cost may depend on the frequency with which the these data as explanatory variables.
power plants are built. If plants of the same type are built frequently,
short-term learning may lower the cost, while a prolonged interval may 3.2.7. Reported number of accidents and failures
result in higher costs. To estimate this effect, we used the construction Higher safety is always aimed for when improving nuclear plant
lead time, defined as the period from the construction start date of the designs. Although it is not easy to quantify the risk of major nuclear
previous reactor to that of a specific reactor, measured separately for accidents due to the very low frequency of such events, it is possible to
BWRs and PWRs. Fig. 6 plots the construction unit cost versus the lead measure plant safety with a certain level of confidence by the fre-
time. The PWR with an exceptionally long lead time is that of Tomari-3 quencies of minor accidents and failures.
(construction start year: 2004), constructed twelve years after Genkai-4 This study referred to the reported number of accidents and failures
(construction start year: 1992). listed in JNES (2013) to assess plant-level safety. Fig. 7 shows the
tendency that newer reactors report smaller numbers of accidents and

Fig. 5. Relationship between the construction period and the unit construction
cost. Fig. 7. Reported number of accidents and failures.

184
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

prior to a plant. Mainly to avoid the multicollinearity with the labor


cost LC, we used the cumulative plant number before and after the first
phase of the I&S program separately.
dumTR is a dummy variable with value 1 if the plant is one of the
four “transitional” ones as described previously, and zero otherwise.
dumIS takes value 1 if the plant was designed after the I&S program.
Since the program took three phases, we considered three dummy
variables corresponding to each phase.
dumTYPE takes 1 if the plant is of a certain type, and zero otherwise.
As the “type” we differentiated the two plant types (BWR or PWR), the
three manufactures (MHI, Toshiba and Hitachi), and twin plants.
dumFOAK takes 1 if the plant is the first one, and zero otherwise. We
considered two dummy variables representing the first BWR or PWR
reactor, and the first BWR or PWR reactor constructed by a domestic
manufacture. These variables measure the learning effect in the very
first stage of nuclear development, in contrast to EXP which measures
the learning effect in the longer term.
After repeated trials using these many explanatory variables, we
Fig. 8. Average load factor. reconstructed the "standard model" only with those which significantly
affect the unit cost. The following part of this paper mainly focuses on
failures, although large fluctuations can be seen for the latest reactors, this standard model. The results of the analyses including other vari-
due mainly to the fact that these have experienced only a small number ables are shown in Appendix D.
of years of operation.
4. Results and discussion
3.2.8. Load factor
As mentioned above, one of the targets of the I&S program was to 4.1. Standard model
achieve higher load factors. Fig. 8 shows the average load factor up to
the Fukushima accident against the year of first commercial operation. Since Fig. 3 strongly suggests that some event(s) that took place
The load factor is higher for the reactors designed after the program exactly during the period of the first I&S program was the major factor
than for those before that. We must be careful, however, in judging this influencing the unit cost, we used dumIS123, a dummy variable with
effect, and a more detailed discussion is provided in Section 4. value 1 if the reactor was designed after the first phase of the program,
in the standard model. We also used dumPWR, which takes 1 if the
3.3. Methodology reactor is a PWR. Since all the reactors analyzed in this study belong to
either BWR or PWR, we could use dumBWR representing BWRs to ob-
Based on the discussion in the previous sections, the unit cost is tain exactly the same results. dumFOAK takes 1 if the reactor is either
regressed by the following equation. the first BWR (Tsuruga-1) or the first PWR (Mihama-1). We omitted
EXP, CP, LT, S, or PF in the standard model, as none of these variables
lnUCi = a0 + a1lnCAPi + a2lnLCi + a3lnEXPi + a4 lnCPi + a5lnLTi had significant effects. Thus the standard model is formulated as fol-
+ a6lnSi + a7 PFi + a8 dumTRi + a9 dumISi + a10 dumTYPEi lows:
+ a11 dumFOAKi + ui (1)
lnUCi = a0 + a1lnCAPi + a2 lnLCi + a3 dumTRi + a4 dumIS123i
where + a5 dumPWR i + a6 dumFOAKi + ui (2)

UCi: Unit construction cost in 2011 JPY thousand/kW. The unit cost UC, which is the overnight cost ZO divided by the gross
CAPi: Gross capacity in MW. capacity, was calculated in two ways, using varying expected inflation
LCi: Labor cost in 2011 JPY thousand/person-year. rates (Eq. (C.2) in Appendix C), as well as fixed rates (Eq. (C.7)). The
EXPi: Construction experience in units. results are shown in Tables 1, 2. The values in the tables are hetero-
CPi: Construction period in years. skedasticity-consistent ones using the methods of White (1980). The
LTi: Construction lead time in years. symbols ***, **, *, and † in the tables throughout the paper indicate
Si: Design Basis Earthquake Ground Motion (S1 or S2) in Gals. that the coefficients are significantly different from zero at the 0.1%,
PFi: Indexes showing performances of the reactor, i.e. the number of 1%, 5%, and 10% levels, respectively.
reported accidents and failures in 1/reactor-year, or the load factor In this standard model, all the explanatory variables are significant
in percentage points. at the 10% level, irrespective of the method used to calculate the real
dumTRi: Dummy variable representing transitional plants.
dumISi: Dummy variable representing the plants designed after the I Table 1
Result of the regression analysis of the overnight unit cost (Standard model,
&S programs.
variable inflation rates).
dumTYPEi: Dummy variable representing the plant type.
dumFOAKi: Dummy variable representing the first-of-a-kind status. Coef. Std. error t-value p-value
ui: Error term. *
Constant 3.80 1.55 2.45 1.77E− 02
ln CAP − 0.24** 0.08 − 2.87 6.00E− 03
UC is calculated as the overnight cost ZO measured in 2011 real ln LC 0.34† 0.18 1.89 6.52E− 02
Japanese yen divided by the gross capacity CAP. We additionally con- dumTR 0.52** 0.18 2.90 5.57E− 03
ducted an analysis on the real total cost divided by the capacity, ZT / dumIS123 0.67*** 0.11 6.07 1.81E− 07
dumPWR − 0.10* 0.04 − 2.44 1.85E− 02
CAP.
dumFOAK 0.39** 0.12 3.32 1.72E− 03
As EXP, we considered the number of total LWRs, that of BWRs and Adjusted R2 0.812
PWRs, and that of the plants constructed by the three manufactures,

185
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

Table 2 asserted by Marshall and Navarro (1991), the construction costs of


Result of the regression analysis of the overnight unit cost (Standard model, Japanese nuclear power plants show economies of scale, even if IDC is
fixed inflation rates). included. Although it is quite reasonable that large-scale facilities such
Coef. Std. error t-value p-value as nuclear power plants are susceptible to economies of scale, this could
be regarded as one of the striking results of the analysis, taking into
Constant 3.06* 1.45 2.11 4.02E− 02 account that similar studies in the United States and France tend to
ln CAP − 0.24** 0.09 − 2.74 8.66E− 03
exhibit the opposite results.
ln LC 0.44* 0.18 2.50 1.59E− 02
dumTR 0.35† 0.18 1.96 5.61E− 02 The coefficients are larger for dumTR and dumIS123 in Table 3 than
dumIS123 0.52*** 0.10 5.01 7.58E− 06 in Table 1. This reflects the fact that the average plant capacity is larger
dumPWR − 0.10* 0.04 − 2.53 1.45E− 02 for the plants designed after the I&S program than those designed be-
dumFOAK 0.36** 0.11 3.19 2.50E− 03
fore that.
Adjusted R2 0.769

4.2. Other models


overnight cost. Thus, we can say that the unit construction costs of
Japanese nuclear power plants were initially at relatively high levels as Regression analyses adding one or more explanatory variable(s) to
first-of-a-kind reactors and soon declined thereafter. The most influ- the standard model, using ZO and varying inflation rates, exhibit in-
ential event took place during the period from 1975 to 1980, which significance of the added variable(s). Of these, the most striking result is
exactly corresponds to the I&S program. The regression results indicate the insignificance of EXP, although easily foreseen from Fig. 3. An
that the unit cost rose by some 70–100% (50–120% if the range of the overview of the results follows:
standard errors is considered) during this period. The plants that belong
to the “transitional” period right before the I&S program, also saw cost 4.2.1. Construction experience, period and lead time
increases to a smaller extent. The unit labor cost, which almost doubled As the plant construction experience, we considered EXPt, EXPbp,
from 1970 to 1990, resulted in a cost increase of 26–36% (12–54% if and EXPm, which represent the number of reactors constructed in
the standard errors are considered). Japan, as BWRs or PWRs in Japan, and by each of the manufacturers,
The coefficient of lnCAP is significantly negative, indicating mod- respectively. We also considered the construction period CP, and the
erate economies of scale as shown in Fig. 4, with some 10–20% declines construction lead time LT, as stated above. None of the coefficients of
with a doubling of the capacity. these variables were significant, as shown in Appendix D.1.
The significance of the coefficient of dumPWR indicates that PWRs As can be seen from these results, learning effects could be seen only
have been cheaper than BWRs on average, although some of the BWRs at the very first stages, and no learning can be observed after that. At
were cheaper than PWRs of the same size, as can be seen in Figs. 3 and the same time, as opposed to what is often asserted in studies for the
4. We should also note that since Japanese utilities have exclusively United States and France, we can see no “intrinsic” negative learning
selected BWR or PWR, this variable might reflect factors other than the effect in the case of the Japanese nuclear industry.
technology itself, such as regional differences. The comparison between As for the construction period, it should be noted that the data
the two technologies requires more detailed analysis. distribute within a relatively narrow range of around 5 years. In cases of
The results using fixed, rather than varying expected inflation rates, longer-term construction, such as Olkiluoto-3 in Finland, which has
shown in Table 2 compared to Table 1, indicate smaller coefficients of been under construction for over 10 years, the factor could affect the
dumIS123 and dumTR and larger coefficients of LC. This mainly reflects construction costs.
the relatively high inflation rates until 1980, which declined rapidly Lead time does not show a significant effect, either. This means that
thereafter. They result in lower calculated ZO values for the plants the technology does not lose competitiveness by an absence of several
whose Application Document was submitted in the late 1970s, which years. It could affect the costs, however, if the lead time expands to
happens to be the period of the first and second phases of the I&S several decades as in the case of the United States and other Western
programs. countries.
Taking into account the higher adjusted R2 value, we used varying
expected inflation rates in the analyses described hereafter, although 4.2.2. Impact of the I&S programs
both methods do not lead to a significant enough difference to the re- Fig. 3 seems to show no cost escalation after the first I&S program,
sults to draw different policy implications. while the average of the unit costs of the four ABWRs reflecting the
Table 3 shows the result of the analysis using the total cost ZT, in- third I&S program is lower than those of other reactors. We analyzed
stead of ZO, divided by the gross capacity, as the unit cost UC in Eq. (2). two dummy variables dumIS23 and dumIS3, which take 1 if the plant
All the explanatory variables are significant at the 10% level. was designed after the second and third I&S programs, respectively. The
Special attention should be paid to the coefficient of lnCAP, which is results indicate the significance of neither of these variables (Appendix
significant at the 5% level, although the coefficient is slightly nearer to D.2). As we can see from these results, while nuclear plant cost esca-
zero at −0.20, compared to −0.24 in Table 1. In contrast to what was lation usually takes place with design improvements, such improve-
ments do not always result in cost escalation.

Table 3 4.2.3. Plant manufacturer and the first-of-a-kind status


Result of the regression analysis of the total unit cost (Standard model, variable
An analysis using dumM, which represents the plants constructed by
inflation rates).
Mitsubishi Heavy Industries, instead of dumPWR in the standard model,
Coef. Std. error t-value p-value shows a significantly negative coefficient of the variable (Appendix
*
D.3). This is a matter of course because the company has exclusively
Constant 3.59 1.60 2.25 2.91E− 02
ln CAP − 0.20* 0.09 − 2.23 3.05E− 02 been constructing PWRs in Japan. On the other hand, the dummy
ln LC 0.34† 0.18 1.87 6.78E− 02 variables dumT and dumH, representing Toshiba and Hitachi, respec-
dumTR 0.60** 0.20 2.99 4.41E− 03 tively, which have been in charge of the construction of BWRs, do not
dumIS123 0.77*** 0.11 6.79 1.40E− 08 influence the cost significantly.
dumPWR − 0.10* 0.04 − 2.33 2.38E− 02
In addition to dumFOAK in the standard model, we considered
dumFOAK 0.42** 0.12 3.45 1.16E− 03
Adjusted R2 0.831 dumFOAKd, which takes 1 if the plant is the first BWR or PWR con-
structed by a domestic manufacturer, and is shown to have no

186
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

significant influence on UC. This seems to be because the three do-


mestic manufacturers inherited the technologies from GE and WH in the
early stages, and when the three manufacturers started to construct
their own reactors, they had already acquired considerable experience.

4.2.4. Twin plants


dumTWIN, which takes 1 if the plant is one of the twin plants, does
not have a significant influence either (Appendix D.4). Thus, at least
from the Japanese experience, we cannot assert that twin plants are
more cost-effective than single plants.

4.2.5. Seismic safety standards


The Maximum Design Earthquake Ground Motion (S1) and the
Extreme Design Earthquake Ground Motion (S2) do not exert significant
Fig. 9. Trends in annual load factors before and after the I&S program.
influence on the unit cost (Appendix D.5). This may seem surprising
considering the importance of seismic standards for Japanese nuclear
facilities. However, since the main components of a nuclear power plant
have been proved to maintain integrity under very severe conditions
(Ohtani et al., 1992; JNES, 2006), seismic standards affect only a re-
latively minor part of the total system, such as ventilation towers, for
example. We should note that this does not mean that increased safety
measures are not expensive in the future, as those measures usually
include substantial revisions to the system, in addition to what result
from different S1 or S2.

4.2.6. Safety index and load factor


Neither INC, which indicates the reported number of accidents and
failures by JNES, nor LF, which is the average load factor by 2010,
shows a significant influence on UC (Appendix D.6).
Conversely, we estimated the influence of the I&S programs on these
indexes as follows. As for INC, we used the following equation assuming
a Poisson distribution

e−λλk
p (INC=k ) ∝ , lnλ = b0 + b1 dumIS123
k! (3)

where b0 and b1 are parameters (Table 4). The result is significant,


showing that the I&S program actually reduced the number of accidents Fig. 10. Distribution of annual load factor after 1985.
and failures by a factor of exp(-0.909)= 0.40, from 0.37 to 0.44 if
taking the standard error into account. Kariwa nuclear power plant stopped operation.
As mentioned in Section 3, the reactors designed after the I&S Fig. 10 shows the frequencies of annual load factors of all the nu-
programs exhibit higher load factors than the previous ones. We should clear power plants in Japan, from 1985 to 2006 for Kashiwazaki-
be careful, however, in concluding that this proves the higher perfor- Kariwa-1–7 which stopped operation after the 2007 earthquake, and
mance of these reactors. In the United States, for example, newly con- from 1985 to 2010 for other reactors, rounded to the nearest percentage
structed reactors have higher average load factors than older ones. point. The average load factor of the reactors after the I&S programs is
However, Koomey and Hultman (2007) argue that this does not prove higher at 75%, than that of the other pre-I&S reactors at 70%.
the better performance of the new reactors. Rather, they posit that this We can test the significance of this difference by a simple t-test,
is because of the overall operational improvements of the US reactors. which shows a t-value of 3.95 and a p-value of 8.26 × 10−6, indicating
The load factors of new plants are higher only because they started that the plants designed after the I&S programs have significantly
operation after the operational improvements, and if we compare the higher load factors than the previous ones.
load factors during the same time periods, old and new reactors make In sum, we cannot find a simple correlation between the cost of a
no significant differences. reactor and its performance. What makes a reactor safer and more ef-
In contrast, the reactors after the I&S program in Japan show higher ficient is the modification of the design, which explicitly aims for such
load factors than the older ones, as shown in Fig. 9, even if we compare improvements, an example of which is the I&S programs in the case of
the performances during the same period. The two steep declines after Japanese nuclear development.
2000 correspond to TEPCO's scandal in 2002, when all the nuclear
power stations of the company temporarily stopped operation, and the 5. Conclusions and policy implications
Niigata-ken Chuetsu-oki earthquake in 2007, when Kashiwazaki-
In this study we quantitatively analyzed the historical trends in
Table 4
Japanese nuclear power plant construction costs, using data from the
Results of the regression analysis of the reported number of accidents and
Application Documents submitted by the electric utilities. The most
failures.
striking finding is that the unit cost of nuclear reactors in Japan did not
Coef. Std. error t-value p-value show a significant change after the I&S programs that took place during
1975–1980 until the Fukushima accident in 2011. As described in
Constant − 0.396*** 0.042 − 9.54 < 2e− 16
dumIS123 − 0.909*** 0.088 − 10.28 < 2e− 16 Section 2, many studies have mentioned the historical escalation in
construction costs for nuclear power plants in Western countries. In the

187
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

United States and France, such cost increases have usually been at- lose relative competitiveness in the event of higher interest rates or
tributed to increasing regulations and/or design improvements. Al- longer construction periods, as suggested by Western studies. In this
though the Japanese experience is similar to the French in that the cost regard, we should keep in mind that energy policies aiming to develop
escalation seems to be related to design improvements, it has also been large-scale LWR programs must strive to facilitate funding as well as
demonstrated that plant design changes do not always result in cost mitigate political and socio-economic risks. In the case of Japan, the
hikes, and that unit costs can remain roughly unchanged for decades. foreseeability of the permission and construction processes seems to be
Thus we cannot observe negative learning effects “intrinsic” to nuclear particularly important for future nuclear development, given that the
power, but we should rather consider that cost escalation trends differ three nuclear power plants that were under construction at the time of
largely by country. A wider set of data, including the costs in other the Fukushima accident have not yet started commercial operation as of
countries, must be analyzed to draw general conclusions. 2018, due mainly to delayed permission processes for complyance with
In the case of Japan, this study suggests that it is not reasonable to the new regulatory standards. Electricity market liberalization, which
expect any large declines or escalations other than the explicit effects has been rapidly progressing follwing the Fukushima accident, could
arising from expected design changes. The 2015 cost estimation by the also affect the investment risks of nuclear energy. Since it is highly
government (Power Generation Cost Analysis Working Group, 2015) uncertain whether the policy measures already enacted in Western
assumes the unit cost of nuclear reactors that start operation in 2030 at countries, such as loan guarantee and FIT-CfD, would work well in
JPY 370 thousand/kW (USD 3490/kW) in 2014 real yen plus additional Japan, this issue is left as an important political challenge for the future.
safety measurement costs of JPY 50.1 thousand/kW (USD 470/kW). It could be thought that the FOAK effect observed in this study, i.e.
The latter refers to the actual expenses by the utilities to meet the new the cost decline in the very early stage of nuclear development, may
regulation requirements, and seems to be a reasonable estimation as the provide some implications to foreign counties. That is, at least a part of
additional cost for safer nuclear plants constructed in the future. The the recent cost increase in Western countries, where nuclear power
former refers to the costs of the recently constructed reactors. From the plants are being constructed after several decades of suspension, may be
results of this study, it can be concluded that adding these two cost mitigated if several reactors are constructed continuously in the future.
components is a reasonable way to obtain a future cost assumption. The coefficient of dumFOAK in Table 1, which is 0.39 ± 0.12, indicates
At the same time, we must note that after the Fukushima accident, it that early learning could reduce the cost by a factor of one third.
may be difficult to build a new nuclear power plant in Japan at least in However, if the construction cost of Hinkley Point C in the United
the near future. As shown in Fig. 6, Japan has once experienced an Kingdom, which is said to be as high as 6300 pounds per kW,1 is re-
extension of lead time of over 10 years that did not influence the plant duced by 33%, it is still at a very high level. We should consider that the
construction costs. However, we cannot deny the possibility that if the overall situations are quite different between Japan in the 1970s and
lead time would extend to several decades, the cost might increase, as Western countries with mature nuclear industries. An analysis of recent
in the cases of Europe and the United States. cost escalation in Europe and in the United States is beyond the scope of
The fact that Japanese nuclear reactors exhibit economies of scale this study.
even including IDC is also important. Japanese electric utilities have Although this study tried to analyze the cost trends of Japanese
constructed nuclear reactors ranging from medium to large size ac- nuclear power plants throughout history, more detailed analyses of
cording to the demand scale. However, the overall tendency is to several factors, including the cost difference between BWRs and PWRs,
construct larger reactors, in line with technological improvements. are called for in the future. Also, Lovering et al. (2016) suggests that the
Since nuclear facilities are susceptible to economies of scale, it would be experiences of countries other than the United States, France and
reasonable to construct larger LWRs in the future rather than small Japan, for example Korea or India, may show quite different trends.
modular reactors, at least in a country with a large electricity demand Conducting detailed quantitative analyses with larger data sets is an
like Japan. important challenge in considering the economics of nuclear power
At the same time, we should also pay attention to Japan's low in- generation.
terest rates after the 1990s, which could have been an important factor
behind the significant economies of scale. The analysis also suggests
that one major reason for the stable cost trend after the 1990s could be Acknowledgment
found in the fact that the Japanese manufacturers have been con-
structing nuclear power plants with a stable construction period of This study was partly supported by the Environment Research and
around five years, which was not the case in the United States, for Technology Development Fund (2–1704) of the Environmental
example. We cannot deny the possibility that large-scale plants may Restoration and Conservation Agency of Japan.

Appendix A. History of Japan's nuclear power plant development

A.1 Early stages of nuclear development

Following the start of civil nuclear programs in Western countries after World War II, the Atomic Energy Basic Act was enacted in Japan in 1955.
After 1957, research reactors, including Japan Research Reactor (JRR)-1–4, were constructed, and in 1963, the Japan Power Demonstration Reactor
(JPDR, 12.5 MW) started operation in the Japan Atomic Energy Research Institute (JAERI). General Electric (GE) of the United States designed the
plant, and domestic manufacturers, including Hitachi, Ltd., mainly produced the equipment.
In parallel therewith, to construct and operate a commercial nuclear reactor, the Japan Atomic Power Company (JAPC) was established in 1957.
JAPC adopted the UK-designed gas cooled reactor (GCR) for the Tokai nuclear power plant (166 MW), which started operation as the first com-
mercial nuclear reactor in Japan in 1966. The construction was promoted mainly by GE UK and the domestic Fuji Electric group.
Designs of light water reactors, including both BWRs and PWRs, were adopted for the second commercial reactor and thereafter. JAPC proceeded
with the construction of a BWR by GE and Hitachi group, and in 1970, Tsuruga power station unit 1 (357 MW) commenced operation. Following the
construction of JAPC's plants, nine out of the 10 general electric utilities also selected either BWR or PWR to construct and operate commercial
nuclear reactors. In 1970, the same year as Tsuruga-1, the Kansai Electric Power Co., Inc. started the operation of Mihama power station unit 1 (PWR,

1
https://www.theguardian.com/uk-news/2017/jul/03/hinkley-point-c-is-22bn-over-budget-and-a-year-behind-schedule-edf-admits.

188
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

340 MW) constructed by Westinghouse (WH) and the Mitsubishi Group, and in 1971 the Tokyo Electric Power Co., Inc. (TEPCO) started operation of
the Fukushima nuclear power plant (later Fukushima Daiichi nuclear power plant) unit 1 (BWR, 460 MW) constructed by GE and Toshiba group.
After that, each utility proceeded with the construction of nuclear power plants throughout the country, and, taking over from the original man-
ufacturers GE and WH, Hitachi and Toshiba for BWR and Mitsubishi Heavy Industries (MHI) for PWR became responsible for plant design and
construction.

A.2 “Improvement and Standardization” (I&S) programs

In this way, Japan started its nuclear program with the introduction of British and US technologies, and later established a mass construction
system by the three domestic manufacturers. Subsequently, led by the Ministry of International Trade and Industry (MITI), the I&S programs were
launched to improve the suitability of the designs for Japan, aiming to achieve higher equipment reliability and operational efficiency and to lower
workers’ radiation exposure, among other improvements. The first phase of the program, which started in FY 1975, selected four reactor types, i.e.
the 800 MW-class and 1100 MW-class for both BWR and PWR, and aimed to contribute to improvements with such methods as the enlargement of
reactor vessels and plant automation. The second phase of the program, which started in FY 1978, aimed for the overall improvements of plant
design and systems based on the results of the first phase, attempting to establish the “Japanese type LWR” design. Numerical targets were also set,
such as improvements in the average load factor up to 70% in the first phase and 75% in the second phase, respectively. The results of the first phase
were fully reflected in Fukushima Daini-1 (BWR, 1100 MW, construction start year: 1979) and Sendai-1 (PWR, 890 MW, construction start year:
1979) and later reactors, whereas the results of the second phase were adopted for Kashiwazaki-Kariwa-2 (BWR, 1100 MW, construction start year:
1983) and Genkai-3 (PWR, 1180 MW, construction start year: 1985) and later reactors.
In FY 1981, the third phase of the I&S program was launched, aiming for even greater safety and reliability, as well as improvements in economic
efficiency. The results of this phase were reflected in the advanced boiling water reactor (ABWR) and the advanced pressurized water reactor
(APWR) designs. The ABWR design has been adopted for four reactors, i.e. Kashiwazaki-Kariwa-6 and 7 (1356 MW each, construction start years:
1991 and 1992, respectively), Hamaoka-5 (1380 MW, construction start year: 1999), and Shika-2 (1206 MW, construction start year: 1999). On the
other hand, no APWR plant has been constructed so far.
Before the Fukushima accident in March 2011, a total of 57 commercial reactors had been built and had started operation in Japan, with one
GCR, 32 BWRs including 4 ABWRs, and 24 PWRs. Among them, the Tokai Power Station (GCR, 166 MW) stopped operation in 1998, and Hamaoka-1
and 2 (BWR, 540 and 840 MW) stopped operation in 2009. After the Fukushima accident, Fukushima Daiichi-1 to 6 (BWR, 460–1100 MW), Tsuruga-
1 (BWR, 357 MW), Mihama-1 and 2 (PWR, 340 and 500 MW), Ohi-1 and 2 (PWR, 1175 MW each), Shimane-1 (BWR, 460 MW), Ikata-1 and 2 (PWR,
566 MW each), and Genkai-1 (PWR, 559 MW), a total of 15 units, stopped operation.

Appendix B. Data used in the study

B.1 Cost data in the application documents

Marshall and Navarro (1991) used data from dengen kaihatsu no gaiyou (“Overview of power plant development”) by MITI. This was an annual
publication by the Japanese government in Japanese that contained cost data for all the thermal, hydro and nuclear power stations that were under
construction or planning, starting from the 1950s (although early publications were named differently as dengen kaihatsu no genjou, “Current status of
power plant development”) up to 1994 (MITI, 1961–1999). The cost figures had been repeatedly revised over time, exactly reflecting the changes in
the plant designs and the construction status, and Marshall and Navarro (1991) explained that they used the final figure compiled by the Japan
Atomic Industry Forum (JAIF). Unfortunately, although the Ministry of Economy, Trade and Industry (METI) has continuously been publishing this
series of books even until the present, detailed cost data have no longer been listed since the 1994 publication. Thus, it is impossible to obtain data
for all the nuclear power plants in Japan from this data source. As such, Lovering et al. (2016) show the trends in construction costs based on
informal hearings with the utilities, as stated in Section 2.
In contrast, we used the cost data that appear in genshiro secchi kyoka shinsei-sho (“Application document for reactor installment license”) or
genshiro secchi henkou kyoka shinsei-sho (“Application document for the modification of reactor installment license”), referred to as the Application
Documents in this article (Electric Power Companies in Japan, 1959–2003). These are the documents that the utilities submit to the government to
receive permission for the construction or the modification of nuclear facilities, and they are easily accessible at the National Diet Library or at the
Nuclear Regulation Agency in Tokyo. A large part of these documents is dedicated to a description of the details of the nuclear facilities, while
Appendix 3 of the documents, an example of which is shown in Table B1, lists the costs involved in construction.
It should be noted that in many cases the figures in the Application Documents were revised several times, as was the case in dengen kaihatsu no
gaiyou. When there are changes in the specifications of a nuclear facility, the utility submits a new Application Document to the government, and in

Table B1
Construction costs appearing in the Application Document for Genkai-3 and 4 (JPY million).
Unit 3 Unit 4

Land 5,391 0
Buildings 34,980 23,387
Structures 15,219 7,384
Machinery 276,293 244,386
Other equipment 6,266 8,927
Temporary facilities 20,276 5,073
General & administrative expense 35,555 29,119
Interest during construction 17,941 11,439
Sharing related cost 1,579 1,085
Contingency 3,200 6,200
Total 416,700 337,000

189
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

case the construction costs undergo major revisions due to the changes in the reactor specifications, the cost figures are shown again in a similar form
as in Table B1. In this study we used the last figures shown in this form in the Application Documents.
These three kinds of data obtained from dengen kaihatsu no gaiyou, the Application Documents, and informal hearings, are thought to be based on
the same source, that is, the data that each electric utility disclosed to the government during the period of planning and construction. Since the data
are frequently modified across time, the figures differ slightly depending on which annual value is taken. For example, the construction cost of
Kashiwazaki-Kariwa-3 used in this study, which is JPY 336.8 billion according to the Application Document submitted in 1986, coincides with the
figure in dengen kaihatsu no gaiyou published in the same year. Although this is the last figure that appears in the Application Documents, the figures
in dengen kaihatsu no gaiyou continued to be modified throughout the construction period. The final figure is JPY 325.3 billion, which appears in the
document published in 1993, the year of first commercial operation, and is exactly the same as the data obtained by the hearings. It happens to be
possible to confirm by a document of the local government (Niigata Prefecture, 2012), that this figure is indeed the final one. We must also note that
not all the data from the hearings indicate the final value. For example, the figures for Tomari-1 to 3 of Hokkaido Electric Power Company exactly
coincide with the ones in the Application Document. Since it is known that the cost figure continued to be revised after the Document according to
dengen kaihatsu no gaiyou, we can conclude that it finally took a somewhat different value, which may not have been made public in any of the
documents.
As mentioned above, this study used the last figure found in the Application Documents. Firstly, this is because, as previously explained, dengen
kaihatsu no gaiyou published after 1994 contain no cost data, and the data obtained by the hearings seem to indicate costs at different time points
depending on the company. Secondly, and more importantly, only the Application Documents contain the breakdown of the expenses as shown in
Table B1. We should pay special attention to the fact that “interest during construction” (IDC) is included here. Both Marshall and Navarro (1991)
and Lovering et al. (2016) regard the cost data from dengen kaihatsu no gaiyou or the informal hearings, which correspond to the “Total” figure in
Table B1, as “overnight costs”, or the costs excluding IDC. In this regard the two studies seem to have made serious mistakes, although we must state
here clearly that for the latter study, the responsibility lies with one of the authors of this article, who gave Lovering et al. incorrect information.
It should also be noted that the figures in the Application Documents are usually estimated costs in the design stages, rather than the actual costs
spent by the utilities. In many cases, it is supposed to be close to the final cost, but there are exceptions. One striking example is Hamaoka-5, whose
total construction cost is JPY 435.0 billion including IDC, according to the Application Document submitted in 1997. Since one of the press releases
from the utility (Chubu Electric Power Co., Inc, 2005) reveals that the actual total construction cost for the plant was JPY 360.0 billion, which is
exactly the same as the figure in the hearings, we can see that the cost underwent significant declines after the submission of the Document. This
study used this figure in the press release, rather than that in the Application Document, exceptionally for Hamaoka-5, as the discrepancy is large
only for this reactor, as long as we can confirm this using published documents. Generally speaking, it would be more appropriate to use later values
and values with a more detailed breakdown. In any case, we should always be aware that the results of analyses could be somewhat different
depending on which data are used.
We calculated the unit construction cost, dividing the real construction cost by the gross power generating capacity. While our main focus is on
the real overnight cost ZO, we also analyzed the real total cost ZT.
Table B1 shows the data for Genkai-3 and 4, which is a typical example of “twin plants.” We should pay attention to the asymmetry in the figures;
i.e. the costs for such items as “Land”, “Structures” and “Temporary facilities” are larger for unit 3, and smaller or zero for unit 4. This is because
these figures for unit 3 actually include expenses common to both units. In this regard, we used the average cost of the two plants for twin plants. The
reactors assumed as twin plants in this study are: Tomari-1 and 2, Fukushima Daini-3 and 4, Kashiwazaki-Kariwa-2 and 5, 3 and 4, 6 and 7, Ohi-1 and
2, 3 and 4, Takahama-3 and 4, and Genkai-3 and 4. Among other plants, for example, Onagawa-2 and 3 are both BWRs constructed by Toshiba, with
the same capacity of 825 MW, but since they were not constructed at the same time, we did not regard them as twin plants in this study.
The analyses in this article excluded Tokai nuclear power plant, since it is the only non-LWR commercial reactor in Japan. It would be sufficient
to mention that the plant is much more expensive than other reactors, with reported overnight cost at JPY 27 billion as a mixed current value, which
is almost equivalent to 2011 JPY 760 thousand/kW, reflecting the fact that it is the first commercial reactor and is small in size.

B.2 Construction costs of “transitional” reactors

The four "transitional" reactors described in Section 3.1 are characterized by large escalations in construction costs from the initial application to
the final stage. Tables B2 and B3 show the submission year and the reported total construction cost in each Application Document for Fukushima
Daini and Genkai power stations, respectively. The total cost of Fukushima Daini-1, for example, showed a sharp rise from JPY 98.6 billion in 1972 to
JPY 272.8 billion in 1976. As for Genkai-2, the cost rose from JPY 65.8 billion in 1975 to JPY 91.5 billion in 1976, then to JPY 133.2 billion in 1979.

Table B2
Construction costs appearing in the Application Documents for the Fukushima Daini nuclear power plant (JPY million).
Reported month Unit 1 Unit 2 Unit 3 Unit 4

Aug. 1972, partly revised in Jul. 98,600


1973
Aug. 1976 272,800
Dec. 1976 199,300
Aug. 1976, partly corrected in Jul. 272,800
1977
Dec. 1976, partly corrected in Apr. 255,800
1978
Aug. 1978 277,400 268,600
Nov. 1979 290,400 255,600
Jul. 1980 317,900 274,700
Gross capacity in MW 1,100 1,100 1,100 1,100
Construction start year 1975 1979 1980 1980
Operation start year 1982 1984 1985 1987

190
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

Table B3
Construction costs appearing in the Application Documents for the Genkai nuclear power plant (JPY million).
Reported month Unit 1 Unit 2 Unit 3 Unit 4

May 1970 41,700


May 1970, partly revised in Nov. 41,700
1970
Aug. 1974 65,800
Aug. 1974, partly corrected in Dec. 65,800
1975
Dec. 1976 91,500
Mar. 1977 91,500
Mar. 1977, partly corrected in May 91,500
1977
Feb. 1979 133,200
Oct. 1982 489,500 420,800
Nov. 1983 482,000 406,700
Aug. 1984 468,300 381,700
Sep. 1986 474,200 393,800
Apr. 1990 435,000 349,000
Nov. 1992 416,700 341,500
Aug. 1994 337,000
Gross capacity in MW 559 559 1,180 1,180
Construction start year 1971 1976 1985 1985
Operation start year 1975 1981 1994 1997

Likewise, the cost of Ikata-2 rose from JPY 79.5 billion in 1975 to JPY 106.7 billion in 1977, whereas Kashiwazaki-Kariwa-1 shows a more moderate
increase from JPY 386.7 billion in 1975 to JPY 438.0 billion in 1979.
Fig. B1 shows the unit cost (mixed current total cost divided by the capacity) versus the submission year of the Application Documents for
selected reactors (Genkai-1 to 4, Ikata-1 to 3, Fukushima Daini-1 to 4, Kashiwazaki-Kariwa-1 to 7, and Takahama-1 to 4). Each point shows one
Application Document, and the data for the same reactor are connected by a line. Notably, the unit costs have risen more rapidly than the commodity
prices during the period from 1975 to 1980, when the 1st and 2nd phases of the I&S programs were ongoing. This figure suggests that the con-
struction costs for the “transitional” four reactors may have been escalating due to the ongoing I&S program. unlike the succeeding reactors. We
should also note, however, that the unit cost of Kashiwazaki-Kariwa-1, as shown in Fig. B1, was already high at JPY 352 thousand/kW in March
1975, right before the start of the I&S program. To explain this, it would be necessary to suppose that the plant designers had been foreseeing the
trends towards I&S in advance of the official commencement of the program, or that some unknown reasons had been causing the cost escalation of
this single plant only.

B.3 Data table

The data used in this study are shown in Table B4. This table includes the construction start date and the commercial operation date by IAEA-
Power Reactor Information System (PRIS) (IAEA, 2017). The Japan Atomic Industry Forum (JAIF, 2017) reports the construction start date earlier
for some plants, while the commercial operation dates by both sources are almost interchangeable. The construction start date by IAEA-PRIS is
roughly consistent with the concrete pour date by JAIF.

Appendix C. Correction of the cost figures

It is not appropriate to use the cost figures reported by electric utilities as they are, resulting in the need for some preliminary corrections. This

Fig. B1. Trends in the reported unit construction costs. Note: Shaded area (1975–1980) denotes the period when the first and the second I&S program took place.

191
Table B4
Data used in the study.
Construction Start Commercial Capacity Plant type Manufacturer Improvement & Construction cost (mixed Construction cost excl. IDC Submission year of the
(IAEA) Operation (IAEA) (gross, MW) Standardization current JPY billion) (mixed current JPY billion) Application Document
Y. Matsuo, H. Nei

JAPC Tokai Mar− 61 Jul− 66 166 GCR GE (UK) – 29.5 27.0 1959
Tokai daini Oct− 73 Nov− 78 1100 BWR− 5 GE – 171.4 146.4 1976
Tsuruga 1 Nov− 66 Mar− 70 357 BWR− 2 GE – 30.0 27.7 1966
2 Nov− 82 Feb− 87 1160 PWR M(4 MHI 1st 372.3 319.7 1980
loop)
Hokkaido Tomari 1 Apr− 85 Jun− 89 579 PWR M(2 MHI 1st 280.0 248.3 1984
loop)
2 Jun− 85 Apr− 91 579 PWR M(2 MHI 1st 181.0 160.2 1984
loop)
3 Nov− 04 Dec− 09 912 PWR M(3 MHI 2nd 292.6 n.a. 2003
loop)
Tohoku Onagawa 1 Jul− 80 Jun− 84 524 BWR− 4 Toshiba 1st 212.3 188.4 1980
2 Apr− 91 Jul− 95 825 BWR− 5 Toshiba 2nd 267.2 255.0 1988
3 Jan− 98 Jan− 02 825 BWR− 5 Toshiba 2nd 369.0 356.1 1996
Higashidori Nov− 00 Dec− 05 1100 BWR− 5 Toshiba 2nd 428.0 n.a. 1998
Tokyo Fukushima 1 Jul− 67 Mar− 71 460 BWR− 3 GE – 42.2 40.6 1969
daiichi
2 Jun− 69 Jul− 74 784 BWR− 4 GE/Toshiba – 51.0 48.4 1968
3 Dec− 70 Mar− 76 784 BWR− 4 Toshiba – 53.1 50.6 1969
4 Feb− 73 Oct− 78 784 BWR− 4 Hitachi – 51.0 48.7 1971
5 May− 72 Apr− 78 784 BWR− 4 Toshiba – 59.4 56.6 1971
6 Oct− 73 Oct− 79 1100 BWR− 5 GE/Toshiba – 164.8 144.2 1975
Fukushima daini 1 Mar− 76 Apr− 82 1100 BWR− 5 Toshiba – 272.8 237.9 1977
2 May− 79 Feb− 84 1100 BWR− 5 Hitachi 1st 255.8 231.3 1978

192
3 Mar− 81 Jun− 85 1100 BWR− 5 Toshiba 1st 317.9 294.7 1980
4 May− 81 Aug− 87 1100 BWR− 5 Hitachi 1st 274.7 251.9 1980
Kashiwazaki 1 Jun− 80 Sep− 85 1100 BWR− 5 Toshiba – 438.0 394.5 1980
kariwa
2 Nov− 85 Sep− 90 1100 BWR− 5 Toshiba 2nd 369.4 325.5 1983
3 Mar− 89 Aug− 93 1100 BWR− 5 Toshiba 2nd 336.8 316.3 1986
4 Mar− 90 Aug− 94 1100 BWR− 5 Hitachi 2nd 342.9 321.1 1986
5 Jun− 85 Apr− 90 1100 BWR− 5 Hitachi 2nd 418.5 368.4 1983
6 Nov− 92 Nov− 96 1356 ABWR Toshiba 3rd 418.5 413.5 1991
7 Jul− 93 Jul− 97 1356 ABWR Hitachi 3rd 375.8 370.8 1991
Chubu Hamaoka 1 Jun− 71 Mar− 76 540 BWR− 4 Toshiba – 53.1 49.4 1976
2 Jun− 74 Nov− 78 840 BWR− 4 Toshiba – 81.2 75.4 1976
3 Apr− 83 Aug− 87 1100 BWR− 5 Toshiba 1st 419.4 n.a. 1983
4 Oct− 89 Sep− 93 1137 BWR− 5 Toshiba 2nd 372.0 348.3 1988
5 Jul− 00 Jan− 05 1380 ABWR Toshiba 3rd 360.0 n.a. –
Hokuriku Shika 1 Jul− 89 Jul− 93 540 BWR− 5 Hitachi 2nd 235.0 215.0 1988
2 Aug− 01 Mar− 06 1206 ABWR Hitachi 3rd 425.0 n.a. 1999
Kansai Mihama 1 Feb− 67 Nov− 70 340 PWR W(2 WE/MHI – 29.8 28.0 1966
loop)
2 May− 68 Jul− 72 500 PWR M(2 WE/MHI – 36.0 33.8 1968
loop)
3 Aug− 72 Dec− 76 826 PWR M(3 MHI – 61.5 56.8 1972
loop)
Takahama 1 Apr− 70 Nov− 74 826 PWR M(3 WE/MHI – 66.0 62.0 1969
loop)
2 Mar− 71 Nov− 75 826 PWR M(3 MHI – 55.0 50.3 1970
loop)
3 Dec− 80 Jan− 85 870 PWR M(3 MHI 1st 278.1 257.7 1980
loop)
(continued on next page)
Energy Policy 124 (2019) 180–198
Table B4 (continued)

Construction Start Commercial Capacity Plant type Manufacturer Improvement & Construction cost (mixed Construction cost excl. IDC Submission year of the
(IAEA) Operation (IAEA) (gross, MW) Standardization current JPY billion) (mixed current JPY billion) Application Document
Y. Matsuo, H. Nei

4 Mar− 81 Jun− 85 870 PWR M(3 MHI 1st 203.9 186.4 1980
loop)
Ohi 1 Oct− 72 Mar− 79 1175 PWR W(4 WE/MHI – 108.7 98.8 1972
loop)
2 Dec− 72 Dec− 79 1175 PWR W(4 WE/MHI – 77.6 71.1 1972
loop)
3 Oct− 87 Dec− 91 1180 PWR M(4 MHI 2nd 480.0 459.7 1989
loop)
4 Jun− 88 Feb− 93 1180 PWR M(4 MHI 2nd 270.0 258.0 1989
loop)
Chugoku Shimane 1 Jul− 70 Mar− 74 460 BWR− 3 Hitachi – 35.0 34.3 1969
2 Feb− 85 Feb− 89 820 BWR− 5 Hitachi 2nd 320.0 277.2 1983
Shikoku Ikata 1 Sep− 73 Sep− 77 566 PWR M(2 MHI – 48.2 44.4 1972
loop)
2 Aug− 78 Mar− 82 566 PWR M(2 MHI – 106.7 95.2 1977
loop)
3 Oct− 90 Dec− 94 890 PWR M(3 MHI 2nd 304.0 n.a. 1989
loop)
Kyushu Genkai 1 Sep− 71 Oct− 75 559 PWR M(2 MHI – 41.7 38.6 1970
loop)
2 Feb− 77 Mar− 81 559 PWR M(2 MHI – 133.2 117.7 1979
loop)
3 Jun− 88 Mar− 94 1180 PWR M(4 MHI 2nd 416.7 398.8 1992
loop)
4 Jul− 92 Jul− 97 1180 PWR M(4 MHI 2nd 337.0 325.6 1994

193
loop)
Sendai 1 Dec− 79 Jul− 84 890 PWR M(3 MHI 1st 215.1 187.0 1977
loop)
2 Oct− 81 Nov− 85 890 PWR M(3 MHI 1st 228.1 197.2 1978
loop)
Energy Policy 124 (2019) 180–198
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

has repeatedly been pointed out in studies in the United States (Komanoff, 1981; Zimmerman, 1982; EIA, 1986; University of Chicago, 2004). The
reason of this mainly lies in the fact that the figures cannot be regarded as real values. As in the case of the United States, the reported costs by
Japanese utilities are supposed to be in “mixed current prices”, which are a simple summation of nominal values in different years.
Assume that the construction of a reactor starts in year s, and ends in year f. Pt denotes the proportion of real expenditure in year t (s ≦ t ≦ f),
satisfying
f
∑t=s Pt = 1 (C.1)
We denote the real overnight construction cost in year d prices as ZO, d being the publication year of the report. d is usually slightly smaller than s,
but in some cases d lies between s and f, or rather is nearer to f. Nominal annual expenditures are calculated as ZOPtIt, in which the inflation
coefficient It in year t is defined as

f f ⎧1 (t = d )
⎪ t
It = ∏ (1 + iT )/ ∏ (1 + iT ) = ∏T = d + 1 (1 + iT ) (d < t )
T=d+1 T=t+1
⎨ d
⎪∏T = t + 1 (1 + iT )−1 (t < d ) (C.2)

where it is the inflation rate in year t. The sum of annual nominal expenditure
f
RO = ZO ∑ Pt It (C.3)
t=s

can be regarded as the reported overnight construction cost in mixed current yen. Let rt be the nominal interest rate in year t, and we can calculate
the total construction cost in mixed current yen as
f
RT = ZO ∑ Pt It Dt (C.4)
t=s

where
f
Dt = ∏T =t+1 (1+rT ) (C.5)
Interest during construction (IDC) in mixed current yen is
f
RI = RT − RO = ZO ∑ Pt It (Dt −1) (C.6)
t=s

Following Zimmerman (1982), EIA (1986) and other studies, we assume that the RT and RI calculated by these equations correspond to the total
costs and the IDC reported by the utilities, respectively. We must note, however, that the data in Japan are usually based on estimations right before
the construction. That is, if we calculate the “true” overnight cost ZO from the reported cost RO and the Eqs. (C.3) and (C.2), this means that we are
assuming that the utilities were predicting future inflation rates correctly. Another assumption could be that the utilities were assuming that the
inflation rate in the year of their estimation will last in the future, in which case we should use
t−d
⎧ (1 + id ) (d ≤ t )
It = d −1
⎨∏T = t + 1 (1 + iT ) (t < d )
⎩ (C.7)
rather than Eq. (C.2), to calculate ZO from Eq. (C.3).
It is worth mentioning that the total construction cost in mixed current yen RT is the net present value in year f, which is equivalent to the real
total construction cost in year f price. In fact, from the real overnight cost in year d prices, ZO, we can calculate the real total cost as
f
ZT = ZO ∑ Pt Dt* (C.8)
t=s

where
f f 1+rT
Dt* = ∏T =t+1 (1+rT*) = ∏T =t+1 1+iT (C.9)
and r*t denotes the real interest (or discount) rate. Thus the real total cost in year f price is
f f f f f
∏T = d + 1 (1 + iT )
ZT ∏ (1 + it ) = Z0 ∑ Pt f ∏ (1 + rT ) = Z0 ∑ Pt It Dt
t=d+1 t=s ∏T = t + 1 (1 + iT ) T=t+1 t=s (C.10)
which equals to RT in Eq. (C.4). For this reason Marshall and Navarro (1991) mention the reported RT as the “true cost.” On the other hand, the
reported overnight cost RO coincides with neither the overnight cost in year d price, ZO, nor that in year f price, ZOIf. This is why we must calculate
ZO, rather than simply use the reported values, making assumptions on the inflation rates it and the cost profile Pt. In this regard, we could say that
conducting analyses with the total cost RT could be more reasonable and reliable, if RT is reported correctly.
In the case of the Japanese data, however, the problem is that if we calculate RI from the reported total cost RT and Eqs. (C.3), (C.4), and (C.6),
and assumed inflation rates and interest rates, such as the GDP deflator and the prime lending rate (Bank of Japan, 2017), for example, the results
largely surpass the reported IDC figures (Fig. C1).
One reason for this discrepancy could be found in the fact that Japanese electric utilities have been raising money needed for capital investment
by internal and external funds (FEPC, 2016), and that there is a possibility that the reported IDC do not include financial expenses related with the
internal funds. The actual proportion of internal and external funds, which the utilities exploited for the construction of specific nuclear reactors, has
not been made public.
For this reason, if we use the reported total cost RT for analyses, we will largely underestimate the overnight costs. In this regard, this study

194
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

Fig. C1. Reported and estimated interest during construction (ratio to the overnight cost).

estimated the real overnight cost ZO from the reported cost RO and Eq. (C.3). Once ZO is calculated, it is quite easy to estimate the total cost ZT, using
the prime lending rates, for example, although the estimated values are not consistent with and are usually larger than, the reported total costs.
As for the cost profile Pt, we can make a rough estimation using the “construction in progress” (CIP) account found in annual financial documents
of the electric utilities (Electric Power Companies in Japan, 1970–2010). We can decide Pt so that the right-hand side of Eq. (C.3), with the
summation taken up to a year t during construction, rather than the final year f, equals the CIP account in the financial documents. Since each
document only contains the total figure of the CIP account for the construction of all of the nuclear facilities of one utility, we must assume a profile
curve for each utility, and minimize the difference between the estimated and reported CIP accounts.

Appendix D. Results of alternative regression models

This appendix shows the results of alternative regression models, including additional explanatory variables to the standard model. As in the
main part of the paper, the symbols ***, **, *, and † indicate that the coefficients are significantly different from zero at the 0.1%, 1%, 5%, and 10%
levels, respectively. (Tables D1–D6)

Table D1
Results of the regression analyses (Construction experience, construction period, and lead time).
Coef. Std. error t-value Coef. Std. error t-value

lnEXPt lnEXPbp
Constant 3.66† 2.09 1.75 Constant 3.73† 2.22 1.68
lnCAP − 0.24** 0.09 − 2.73 lnCAP − 0.24** 0.09 − 2.69
lnLC 0.36 0.25 1.45 lnLC 0.35 0.26 1.34
dumTR 0.52** 0.18 2.85 dumTR 0.52** 0.18 2.82
dumIS123 0.66*** 0.14 4.80 dumIS123 0.67*** 0.14 4.63
dumPWR − 0.10* 0.04 − 2.44 dumPWR − 0.10* 0.04 − 2.39
dumFOAK 0.39** 0.12 3.29 dumFOAK 0.39** 0.12 3.33
lnEXPt − 0.01 0.05 − 0.10 lnEXPbp −0.003 0.06 − 0.05
Adjusted R2 0.808 Adjusted R2 0.808
lnEXPm lnCP
Constant 4.45* 2.18 2.04 Constant 3.86* 1.54 2.51
lnCAP − 0.24** 0.09 − 2.78 lnCAP − 0.26** 0.08 − 3.44
lnLC 0.26 0.25 1.04 lnLC 0.34† 0.18 1.87
dumTR 0.52** 0.18 2.86 dumTR 0.52** 0.17 3.01
dumIS123 0.70*** 0.13 5.53 dumIS123 0.69*** 0.11 6.32
dumPWR − 0.11* 0.04 − 2.42 dumPWR − 0.10* 0.04 − 2.43
dumFOAK 0.39** 0.13 3.05 dumFOAK 0.40** 0.12 3.24
lnEXPm 0.03 0.05 0.57 lnCP 0.09 0.17 0.53
Adjusted R2 0.809 Adjusted R2 0.809
lnLT
Constant 3.87* 1.53 2.53
lnCAP − 0.24** 0.08 − 2.94
lnLC 0.33† 0.18 1.85
dumTR 0.54** 0.18 2.96
dumIS123 0.68*** 0.11 6.33
dumPWR − 0.10* 0.04 − 2.41
dumFOAK 0.40** 0.12 3.35
lnLT − 0.01 0.02 − 0.86
Adjusted R2 0.809

195
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

Table D2
Results of the regression analyses (I&S programs).
Coef. Std. error t-value Coef. Std. error t-value

dumIS23 dumIS3
Constant 4.08* 1.90 2.14 Constant 3.47* 1.66 2.09
lnCAP − 0.24** 0.09 − 2.76 lnCAP − 0.22* 0.09 − 2.39
lnLC 0.31 0.21 1.43 lnLC 0.36† 0.19 1.96
dumTR 0.53** 0.19 2.84 dumTR 0.50** 0.18 2.86
dumIS123 0.67*** 0.11 6.03 dumIS123 0.67*** 0.11 6.05
dumIS23 0.03 0.07 0.44 dumIS3 − 0.10 0.07 − 1.43
dumPWR − 0.10* 0.04 − 2.31 dumPWR − 0.11* 0.04 − 2.55
dumFOAK 0.38** 0.14 2.79 dumFOAK 0.42** 0.13 3.23
Adjusted R2 0.809 Adjusted R2 0.811

D.1 Construction experience, construction period, and lead time

lnUCi = a0 + a1lnCAPi + a2lnLCi + a3 dumTR i + a4 dumIS123i + a5 dumPWR i + a6 dumFOAKi + a7 ADDi + ui (D.1)

ADDi = lnEXPti : Cumulative number of LWRs constructed previously.


lnEXPbpi : Cumulative number of BWRs or PWRs constructed previously.
lnEXPmi : Cumulative number of BWRs or PWRs constructed previously by the same manufacturer.
lnCPi : Construction period.
lnLTi : Construction lead time.

D.2 I&S programs

lnUCi = a0 + a1lnCAPi + a2lnLCi + a3 dumTRi + a4 dumIS123i + a5 dumISi + a6 dumPWR i + a7 dumFOAKi + ui (D.2)

dumISi = dumIS23i : dummy variable with value 1 if the plant was designed after the second I&S program and zero otherwise.
dumIS3i : dummy variable with value 1 if the plant is an ABWR and zero otherwise.

D.3 Plant manufacturer and the first-of-a-kind status

lnUCi = a0 + a1lnCAPi + a2lnLCi + a3 dumTRi + a4 dumIS123i + a5 ADDi + a6 dumFOAKi + ui (D.3)

ADDi = dumMi, dumTi, dumHi : dummy variables with value 1 if the plant was constructed by Mitsubishi Heavy Industries, Toshiba, and Hitachi,
respectively, and zero otherwise.
or
lnUCi = a0 + a1lnCAPi + a2lnLCi + a3 dumTRi + a4 dumIS123i + a5 dumPWR i + a6 dumFOAKi + a7 dumFOAKmi + ui (D.4)

dumFOAKmi : dummy variable with value 1 if the plant was the first BWR or PWR constructed by a domestic manufacturer, and zero otherwise.

Table D3
Results of the regression analyses (Plant manufacturer and the first-of-a-kind status).
Coef. Std. error t-value Coef. Std. error t-value

dumM dumT
Constant 3.80* 1.61 2.36 Constant 3.73* 1.78 2.09
lnCAP − 0.26** 0.09 − 2.95 lnCAP − 0.24** 0.08 − 2.93
lnLC 0.35† 0.18 1.92 lnLC 0.35 0.21 1.66
dumTR 0.53** 0.18 2.91 dumTR 0.54** 0.17 3.16
dumIS123 0.68*** 0.12 5.89 dumIS123 0.67*** 0.13 5.09
dumM − 0.09* 0.04 − 2.09 dumT 0.07 0.05 1.45
dumFOAK 0.35** 0.12 2.82 dumFOAK 0.40** 0.12 3.28
Adjusted R2 0.808 Adjusted R2 0.804
dumH dumFOAKm
Constant 3.38* 1.66 2.04 Constant 3.48† 1.89 1.84
lnCAP − 0.23* 0.09 − 2.66 lnCAP − 0.23* 0.09 − 2.54
lnLC 0.39* 0.19 2.01 lnLC 0.37† 0.21 1.80
dumTR 0.54** 0.18 3.03 dumTR 0.52** 0.18 2.93
dumIS123 0.66*** 0.12 5.36 dumIS123 0.67*** 0.11 5.88
dumH − 0.02 0.06 − 0.43 dumPWR − 0.09* 0.04 − 2.19
dumFOAK 0.41** 0.12 3.29 dumFOAK 0.36*** 0.10 3.53
Adjusted R2 0.798 dumFOAKm 0.07 0.12 0.56
Adjusted R2 0.798 Adjusted R2 0.809

196
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

Table D4
Result of the regression analysis (Twin plants).
Coef. Std. error t-value

dumTWIN
Constant 3.78* 1.55 2.44
lnCAP − 0.23* 0.09 − 2.47
lnLC 0.33† 0.18 1.85
dumTR 0.52** 0.18 2.92
dumIS123 0.68*** 0.11 6.06
dumPWR − 0.09* 0.04 − 2.23
dumFOAK 0.40** 0.12 3.31
dumTWIN − 0.02 0.04 − 0.42
Adjusted R2 0.808

Table D5
Results of the regression analyses (Seismic standards).
Coef. Std. error t-value Coef. Std. error t-value

lnS1 lnS2
Constant 3.41* 1.66 2.06 Constant 3.36* 1.62 2.07
lnCAP − 0.24** 0.08 − 2.87 lnCAP − 0.26** 0.08 − 3.18
lnLC 0.31 0.19 1.64 lnLC 0.28 0.21 1.36
dumTR 0.54** 0.19 2.88 dumTR 0.54** 0.19 2.90
dumIS123 0.67*** 0.12 5.75 dumIS123 0.67*** 0.12 5.55
dumPWR − 0.09* 0.04 − 2.21 dumPWR − 0.10* 0.04 − 2.59
dumFOAK 0.35** 0.12 2.85 dumFOAK 0.33* 0.13 2.58
lnS1 0.11 0.10 1.14 lnS2 0.17 0.14 1.21
Adjusted R2 0.813 Adjusted R2 0.815

Table D6
Results of the regression analyses (Performance indexes).
Coef. Std. error t-value Coef. Std. error t-value

INC LF
Constant 3.64* 1.44 2.53 Constant 3.87* 1.59 2.43
lnCAP − 0.26** 0.09 − 2.95 lnCAP − 0.25** 0.08 − 3.10
lnLC 0.37* 0.17 2.23 lnLC 0.37* 0.18 2.07
dumTR 0.54** 0.17 3.09 dumTR 0.55** 0.19 2.96
dumIS123 0.70*** 0.11 6.22 dumIS123 0.69*** 0.12 5.63
dumPWR − 0.10* 0.04 − 2.50 dumPWR − 0.06 0.06 − 1.07
dumFOAK 0.35* 0.14 2.46 dumFOAK 0.37** 0.12 3.22
INC 0.11 0.10 1.11 LF − 0.30 0.28 − 1.10
Adjusted R2 0.812 Adjusted R2 0.812

D.4 Twin plants

lnUCi = a0 + a1lnCAPi + a2lnLCi + a3 dumTRi + a4 dumIS123i + a5 dumPWR i + a6 dumFOAKi + a7 dumTWINi + ui (D.5)

dumTWINi : dummy variable with value 1 if the plant is one of the twin plants, and zero otherwise.

D.5 Seismic standards

lnUCi = a0 + a1lnCAPi + a2lnLCi + a3 dumTR i + a4 dumIS123i + a5 dumPWR i + a6 dumFOAKi + a7 ADDi + ui (D.6)

ADDi = lnS1i : Maximum Design Earthquake Ground Motion (S1).


lnS2i : Extreme Design Earthquake Ground Motion (S2).

D.6 Performance indexes

lnUCi = a0 + a1lnCAPi + a2lnLCi + a3 dumTR i + a4 dumIS123i + a5 dumPWR i + a6 dumFOAKi + a7 ADDi + ui (D.7)

ADDi = INCi : Reported number of accidents and failures.


LFi : Average load factor.

197
Y. Matsuo, H. Nei Energy Policy 124 (2019) 180–198

References Keng, C.W.K., 1985. Forecasting Canadian nuclear power station construction costs.
Energy Econ. 7 (4), 241–258.
Komanoff, C., 1981. Power Plant Cost Escalation Nuclear and Coal Capital Costs,
Bank of Japan, 2017. Statistics – prime lending rates. Available at: 〈https://www.boj.or. Regulation, and Economics. Van Nostrand Reinhold Company, New York.
jp/en/statistics/dl/loan/prime/prime.htm/〉. Koomey, J., Hultman, N.E., 2007. A reactor-level analysis of busbar costs for US nuclear
Boccard, N., 2014. The cost of nuclear electricity: france after Fukushima. Energy Policy plants, 1970–2005. Energy Policy 35, 5630–5642.
66, 450–461. Koomey, J., Hultman, N.E., Grubler, A., 2017. A reply to “Historical construction costs of
Cantor, R., Hewlett, J., 1988. The economics of nuclear power further evidence on global nuclear power reactors”. Energy Policy 102, 640–643.
learning, economics of scale, and regulatory effects. Resour. Energy 10, 315–335. Lovering, J.R., Yip, A., Nordhaus, T., 2016. Historical construction costs of global nuclear
Chubu Electric Power Co., Inc, 2005. Resuming the Commercial Operation of Unit 5 at the power reactors. Energy Policy 91, 371–382.
Hamaoka Nuclear Power Plant. Available at: 〈http://www.chuden.co.jp/english/ Lovering, J.R., Nordhaus, T., Yip, A., 2017. Apples and oranges: comparing nuclear
corporate/press2004/0118_1.html〉. construction costs across nations, time periods, and technologies. Energy Policy 102,
Cooper M., 2010. Policy challenges of nuclear reactor construction, cost escalation and 650–654.
crowding out alternatives lessons from the U. S. and France for the effort to revive the Marshall, J.M., Navarro, P., 1991. Costs of nuclear power plant construction: theory and
U. S. industry with loan guarantees and tax subsidies. Available at: 〈http://citeseerx. new evidence. RAND J. Econ. 22 (1), 148.
ist.psu.edu/viewdoc/download?Doi=10.1.1.175.2423&rep=rep1&type=pdf〉. Massachusetts Institute of Technology (MIT), 2003. The future of nuclear power an in-
Costs Verification Committee, 2011. Report of the Costs Verification Committee. (in terdisciplinary MIT study. Available at: 〈http://web.mit.edu/nuclearpower/〉.
Japanese) Available at: 〈http://www.enecho.meti.go.jp/committee/council/basic_ Matsuo Y., Nei H., 2018. Assessing the Historical Trend of Nuclear Power Plant
problem_committee/008/pdf/8-3.pdf〉. Construction Costs in Japan, In: Proceedings of the 34th Conference Energy
Cour des comptes, 2012. The costs of the nuclear power sector thematic public report. Economics on Environment, 17-2. (in Japanese).
Available at: 〈https://www.ccomptes.fr/sites/default/files/EzPublish/thematic_ McCabe, M.J., 1996. Principals, agents and the learning curve: the case of steam-electric
public_report_costs_nuclear_%20power_sector_012012.pdf〉. power plant design and construction. J. Ind. Econ. 44 (4), 357–375.
Du, Y., Parsons, J.E., 2009. Update on the Cost of Nuclear Power. Center for Energy and Ministry of Economy, Trade and Industry (METI) 2009. Chouki enerugi jukyu mitoshi
Environmental Policy Research (Available at). 〈http://hdl.handle.net/1721.1/ (saikeisan). (in Japanese). Available at: 〈http://www.meti.go.jp/report/data/
45666〉. g90902aj.html〉.
Electric Power Companies in Japan (Hokkaido, Tohoku, Tokyo, Chubu, Hokuriku, Kansai, Ministry of Economy, Trade and Industry (METI), 2015. Long-term energy supply and
Chugoku, Shikoku, Kyushu, and JAPC), 1959-2003. Genshiro secchi (henkou) kyoka demand outlook provisional translation. Available at: 〈http://www.meti.go.jp/
shinsei-sho. (in Japanese). english/press/2015/pdf/0716_01a.pdf〉.
Electric Power Companies in Japan. 1970-2010. Yuuka shouken houkokusho souran, Ministry of International Trade and Industry (MITI), 1961. Dengen Kaihatsu no Gaiyou.
Printing Bureau, Ministry of Finance, Tokyo. (in Japanese). Okumura Printing co., ltd., Tokyo (in Japanese).
Energy Data and Modelling Center (EDMC), 2017. Handbook of Japan's & World Energy & Montgomery, W.D., Quirk, J.P., 1978. Cost Escalation in Nuclear Power, EQL
Economic Statistics. Energy Conservation Center, Tokyo. Memorandum 21 California Institute of Technology, California (Available at:).
Energy Information Administration (EIA), 1986. An analysis of nuclear power plant 〈https://authors.library.caltech.edu/25744/1/EQLmemo_21.pdf〉.
construction costs, DOE/EIA-0485. Available at: 〈https://www.osti.gov/scitech/ Mooz, W.E., 1979. A Second Cost Analysis of Light Water Reactor Power Plants. R-2504-
servlets/purl/6071600〉. RC, the RAND Corporation, Santa Monica.
Escobar-Rangel, L., Lévêque, F., 2015. Revisiting the cost escalation curse of nuclear Niigata Prefecture, 2012. Kashiwazaki-Kariwa genshiryoku hatsudensho no setsubi
power: new lessons from the French Experience. Econ. Energy Environ. Policy 4 (2), gaiyou. (in Japanese). Available at: 〈http://www.pref.niigata.lg.jp/genshiryoku/kk-
103–125. plant.html〉.
Gilbert, A., Sovacool, B.K., Johnstone, P., Stirling, A., 2017. Cost overruns and financial Ohtani, K., Shibata, H., Watanabe, M., Kawakami, S., Ohno, T., 1992. Seismic proving
risk in the construction of nuclear power reactors: a critical appraisal. Energy Policy tests for nuclear power plant no.1. Earthq. Eng. 3603–3608 (Tenth World
102, 644–649. Conference).
Grubler, A., 2010. The costs of the French nuclear scale-up: a case of negative learning by Paik, S., Schriver, W.R., 1980. The effect of increased regulation on capital costs and
doing. Energy Policy 38, 5174–5188. manual labor requirements of nuclear power plants. Eng. Econ. 26 (3), 223–244.
Grubler, A., 2014. The French pressurized water reactor programme. In: Grubler, A., Power Generation Cost Analysis Working Group, 2015. Report on analysis of generation
Wilson, C. (Eds.), Energy Technology Innovation Learning from Historical Success costs, etc. for subcommittee on long-term energy supply-demand outlook provisional
and Failures. Cambridge University Press, Cambridge, pp. 146–161. translation. Available at: 〈http://www.meti.go.jp/english/press/2015/pdf/0716_
Harris, G., Heptonstall, P., Gross, R., Handley, D., 2013. Cost estimates for nuclear power 01b.pdf〉.
in the UK. Energy Policy 62, 431–442. Research and Statistics Department Bank of Japan, 2017. Price Indexes Annual 2017. Sun
Hultman, N., Koomey, J., 2013. Three Mile Island: the driver of US nuclear power's de- partners co., ltd., Tokyo.
cline? Bull. At. Sci. 69 (3), 63–70. Sovacool, B.K., Gilbert, A., Nugent, D., 2014. Risk, innovation, electricity infrastructure
International Atomic Energy Agency (IAEA), 2017. Power Reactor Information System and construction cost overruns: testing six hypotheses. Energy 74, 906–917.
(PRIS). IAEA, Vienna (Available at). 〈https://www.iaea.org/pris/〉. The Federation of Electric Power Companies of Japan (FEPC), 2004. Moderu shisan ni
International Energy Agency (IAEA), Nuclear Energy Agency (NEA), 2015. Projected costs yoru kaku dengen no hatsuden kosuto hikaku. (in Japanese). Available at: 〈http://
of generating electricity 2015 edition. OECD publications, Paris. www.enecho.meti.go.jp/committee/council/electric_power_industry_subcommittee/
Japan Atomic Industrial Forum, Inc. (JAIF), 2017. World Nuclear Power Plants 2017. 010_001/pdf/001_006.pdf〉.
JAIF, Tokyo. The Federation of Electric Power Companies of Japan (FEPC), 2016. FEPC INFOBASE
Japan Nuclear Energy Safety Organization (JNES), 2006. Genshiryoku hatsuden shisetsu 2016. (in Japanese). Available at: 〈http://www.fepc.or.jp/library/data/infobase/〉.
taishin shinraisei jisshou shiken no gaiyou, JNES-SS report, 617, Japan Nuclear University of Chicago, 2004. The economic future of nuclear power a study conducted at
Energy Safety Organization, Tokyo. (in Japanese). the University of Chicago. Available at: 〈https://www.eusustel.be/public/
Japan Nuclear Energy Safety Organization (JNES), 2013. Genshiryoku shisetsu unten documents_publ/links_to_docs/cost/uoc-study.pdf〉.
kanri nempou. Japan Nuclear Energy Safety Organization, Tokyo (in Japanese). White, H., 1980. A heteroskedasticity-consistent covariance matrix estimator and a direct
Jungler, M., Lako P., Lensink S., Sark W., Weiss M., 2008. Climate change scientific as- test for heteroskedasticity. Econometrica 48, 817–838.
sessment and policy analysis technological learning in the energy sector, Report Zimmerman, M.B., 1982. Learning effects and the commercialization of new energy
500102017, NWS-E-2008-14, ECN-E–08-034. Available at: 〈http://www.ecn.nl/ technologies: the case of nuclear power. Bell J. Econ. 13, 297–310.
docs/library/report/2008/e08034.pdf〉.

198

You might also like