Professional Documents
Culture Documents
PROJECT MANAGEMENT
CHAPTER 3
Construction Project
N etwor k Pl anni ng
Network Analysis
Network Analysis is the general name given to
certain specific techniques which can be used for
the planning, management and control of projects
9.2 CRITICAL PATH METHOD Data Processing by CPM Method
The project components is identified by break the
Critical Path Method (CPM) project scope into activities or activity groups. The next
It was developed in 1956 / 1957 by Remington Rand step is rearranging the activities into a chain, so we
and Du Pont to help schedule maintenance projects in can know the sequence of activities from the start to
chemical plants and construction projects. the completion of the whole project. Then, find the
forward calculation with the formula (1) and (2). The
There are several notations used in CPM to identify forward calculation moves from the initial event to the
the critical path: terminal event. The point is to calculate the fastest
event, the fastest commencement and the completion
The EARLIEST START (ES), is the earliest time an of activities (TE, ES, and EF).
activity can begin, assuming all predecessors are
done. 𝑇𝐸(𝑗) = 𝐸𝑆(𝑖,𝑗) = 0 (1)
The EARLIEST FINISH (EF), is the time before an 𝐸𝐹(𝑖,𝑗) = 𝐸𝑆(𝑖,𝑗) + 𝑡(𝑖,𝑗) (2)
activity can be completed.
The LAST START (LS), is the last time an activity can which:
start, so the completion time of the whole project will ES : The fastest start of activity
not delay. TE : The fastest event
EF : The fastest completion of activity
T : Time required for an activity
Data Processing by CPM Method
After the forward calculation, then the countdown The next step is to find the total float and free float to
calculation with the formula (3) and (4). The determine the critical path. TOTAL FLOAT (5) is the
countdown calculation moves from the event terminal amount of time at which the completion time of an
to the initial event. The objective is to calculate the activity can be postponed without affecting the fastest
latest event, the latest commencement and completion time of completion of the project as a whole. This step
of activities (TL, LS, and LF). is the critical stage or the longest implementation path,
which determines the project completion time. The
𝐿𝑆(𝑖,𝑗) = 𝐿𝐹(𝑖) − 𝑡(𝑖,𝑗) (3) CRITICAL PATH has a total float equal to zero
𝐿𝐹(𝑖,𝑗) = 𝑇𝐿 ; 𝑇𝐿 = 𝑇𝐸 (4) therefore in determining the critical path, then first
calculate the total float of each project activity.
which:
LS : The latest start of activity 𝑇𝐹 = 𝐿𝐹 − 𝐸𝑆 − 𝑡 (5)
LF : The latest completion of activity
TL : The latest event which:
t : Time required for an activity TF : Total float
LF : The earliest start of activity
ES : The fastest start of activity
t : Time required for an activity
Data Processing by CPM Method
Free Float (6) is the amount of time that the
completion of an activity can be measured without
affecting the fastest time from the start of another
activity or the fastest event of another on the network.
𝐹𝐹 = 𝐸𝐹 − 𝐸𝑆 − 𝑡 (6)
which:
FF : Free Float
EF : The fastest completion of activity
ES : The fastest start of activity
t : Time required for an activity
9.3 PROGRAM EVALUATION AND REVIEW TECHNIQUES
Program Evaluation and Review Techniques (PERT)
PERT is also known as BACK RESEARCH The time estimate used in PERT are three types. The
TECHNIQUE. It is a project management tool used to difference between these three types of time is a
schedule, organize, and coordinate tasks within a relative measure of the uncertainty of each activity:
project. It is basically a method to analyze the tasks
involved in completing a given project, especially the The MOST OPTIMISTIC TIME (Wo), is the shortest
time needed to complete each task, and to identify the possible time of completion, if all work goes well.
minimum time needed to complete the total project. The MOST PESSIMISTIC TIME (Wp), is the most
Developed by U.S. Navy Special Project Office IN likely time of completion, account possible delays.
1957 to support the U.S. Navy’s Polaris Nuclear The NORMAL TIME (Wn), is a possible completion
submarine project. Early example, it was used for the time as appropriate.
1968 Winter Olympics in Grenobole.
The time estimate used in PERT are three types. The
difference between these three types of time is a
relative measure of the uncertainty of each activity:
5 6 10 14 16 23
F
2 5 6 days
7
ES EF
A I
0 0 D1
25 25
D
B D3 J
1 4 days 3 4 6 8 8 days
10
START G 17 17
K
END
C D2 D4
E H
4 8 days
6 4 days
9
6 6 14 14 18 21
EXAMPLE OF PERT/CPM
ACTIVITY PREDECESSORS DURATION (DAYS)
Tasks
SLACK = LS -ES
A - 7 1. Create a PERT/CPM chart. SLACK = LF -EF
B - 9
C A 12 2. What is the project’s duration? ES +D =EF
D A,B 8
E D 9 3. What is the critical path?
F C,E 6
G E 5
A
LS= D -LF
START END
0 9 9 9 8 17 17 9 26 26 5 31
B D E G
0 9 9 9 8 17 17 9 26 27 5 32
SLACK = 0 SLACK = 0 SLACK = 0 SLACK = 1