PRICE EST NO:2023/904

DPR for Construction of Kuttiyadi Bypass


General Abstract
(Dsor year: 2018,Cost Index Applied for this estimate is 36.44%)

Sl No Heading Description Amount


1 Road And Allied Works 205021494.44

2 Other Works 363089.70

Provision for GST payments (in %) @ 18.0%

Amount reserved for GST payments 36969225.15

Total 242353809.15

Lumpsum for round off 0.00

TOTAL Rs 242353809.15

Rounded Total Rs 24,23,53,809

Rupees Twenty Four Crore Twenty Three Lakh Fifty Three Thousand Eight Hundred and Nine Only

(Cost Index Applied for this estimate is 36.44%)