MATERIALS APPROVAL REQUEST

QP-PRO-015-MAR
APP 
No.
Wilde and EPC MB Documents
Sinarmas Kandu - CM EPC SCSIP VS-RS
Woolard - QS

1
EPC MB/SCSIP/VS-RS proposes sample of the material 1. Material sample
is proposed to
Kandu.

2. The sample of the


2
Proceed to Client Checked and
Rejected material is proposed
approved and Kandu requires
by Kandu minimum 5 working
days to check

Send to client for


confirmation
Confirmation
approval.

approval

by owner (APP Sinarmas Rejected


and GPG)
3. Process for
3 confirmation from
client is 2 working
Approved
days

4 Kandu to 4. Kandu distribute


If required, a presentation of the sample is provided MAR to client (copy),
distribute
and original to EPC.

A presentation is
required for materials
where the installation
process must be
understood

Received 1(one) Received 1(one)


set copy of MAR set copy of MAR Received 1(one) set of MAR original Storage of the sample of
material (by Kandu) is
adjusted with the status
and its classification.

For record keeping,

keep material
Procurement of Materials
Kandu only stores

sample approved samples.

- Material Classification:

> Structure

Monitor procurement

> Architecture

> MEP

MAR Finish.