Project Implimentation Schedule

Location Owner Responsible Completion Remarks Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
By %
18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 1-Nov 2-Nov 3-Nov

1 Hardware order and delivery Afiintra Office Affiintra Afiintra


2 Project Kick-Off meeting Online Afiintra/Megasteel Afiintra/Megasteel
3 Implementation
3.1 HP ProLiant ML350 G3
3.1.1 System board and battery replacement Megasteel Afiintra/Megasteel Afiintra
3.1.2 Processor installation Megasteel Afiintra/Megasteel Afiintra
3.1.3 Memory Installation Megasteel Afiintra/Megasteel Afiintra
3.1.4 Power Supply installation Megasteel Afiintra/Megasteel Afiintra
3.1.5 Hard disk installation Megasteel Afiintra/Megasteel Afiintra
3.1.6 Power up, machine testing and verification Megasteel Afiintra/Megasteel Afiintra
3.2 HP ProLiant ML350 G3
3.2.1 Hard disk replacement Megasteel Afiintra/Megasteel Afiintra

Weekend

Weekend
3.2.2 Power up, machine testing and verification Megasteel Afiintra/Megasteel Afiintra
3.3 HP Storage Modular Smart A1000
3.3.1 Replace and install smart array controller along with the battery
Megasteel Afiintra/Megasteel Afiintra
3.3.2 Replace a faulty hard disk Megasteel Afiintra/Megasteel Afiintra
3.3.3 Replace faulty power supply and blower Megasteel Afiintra/Megasteel Afiintra
3.3.4 Power up, machine testing and verification Megasteel Afiintra/Megasteel Afiintra
3.4 HP Compaq 6000
3.4.1 System board replacement Megasteel Afiintra/Megasteel Afiintra
3.4.2 Power up, machine testing and verification Megasteel Afiintra/Megasteel Afiintra
3.5 HP ProLiant ML150
3.5.1 Replace a faulty hard disk Megasteel Afiintra/Megasteel Afiintra
3.6 ALPHA Server
3.6.1 Replace a faulty hard disk for Alpha Server DS10 Megasteel Afiintra/Megasteel Afiintra
3.6.2 Replace a faulty hard disk for Alpha Server 5-333 Megasteel Afiintra/Megasteel Afiintra
3.6.3 Power up machine and hardware connectivity verification Megasteel Afiintra/Megasteel Afiintra
4 UAT & Hardware verification
4.1 Verified all new hardware installation Megasteel Afiintra/Megasteel Afiintra/Megasteel
4.2 UAT and sign off project Megasteel Afiintra/Megasteel Afiintra/Megasteel
Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
4-Nov 5-Nov 6-Nov 7-Nov 8-Nov 9-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov
Public Holiday

Weekend

Weekend

Weekend