MEGASTEEL & AFIINTRA TECHNOLOGIES RESTART PROJECT

KICK OFF MEETING

25/10/2021
2:00 PM
AGENDA

• INTRODUCTION PROJECT
• PROJECT ORGANIZATION CHART
• TASK ARRANGEMENT
• PRODUCT DELIVERY
• TECHNICAL PLANNING & DISCUSSION
PROJECT INTRODUCTION

• TO POWER UP AND BURN TEST EQUIPMENT


• TO CONFIGURE AND RESTORE THE EXISTING NETWORK TO ALL SWITCH
• HARDWARE AND ACCESSORIES REPLACEMENT
• TO CHECK AND UPDATE FIRMWARE TO THE LATEST VERSION
• INSTALLATION WITH T&C
PROJECT ORGANIZATION CHART
Megasteel

Manager
General Manager
CHOK
Ryan Fong

Project Manager

Abdul Latif
Server Network

Nancy Faizal

Alpha Server Normal Server Network

Lim ( inoware ) Tasnim Han

Normal Server Network

illyas Ridzwan
EQUIPMENT DELIVERY

NO Description Status Date Issue Remarks


1 PO from Megasteel 12/10/2021
2 PO to supplier 21/10/2021 3-4weeks delivery
3 Equipment arrival to warehouse ETA 15/11/2021
4 Equipment deliver to site 1week after ETA
date
PROJECT TIMELINE
Q &A
THANK YOU