Table of figures 3 2.5 Task packages of the Project Coordinator in the Test Laboratory 17
1 Introduction 4 2.5.1 PRU 1 Costs and duration of validation 17
The product development process (PEP) from the customer inquiry up to six months after 2.5.2 PRU 2 Capacity planning and availability 17
1.1 4
SOP 2.5.3 PRU 3 Initial sample tests 17
1.2 Terms and definitions 6 2.6 Task package of the SCM Project Manager 17
1.2.1 What is the VDA maturity level? 6 2.7 Task packages of the Plant Manager 18
1.2.2 What is a milestone? 7 2.7.1 WL 1 Approval of the offer basis 18
1.2.3 What is the PEP map? 9 2.7.2 WL 2 Investment approval 18
1.2.4 What are results, partial results, activities, task packages? 9 2.8 Task packages of the Participation Controller and the Corporate Investment Controller 18
1.2.5 What is key documentation? 9 2.8.1 CON 1 Profitability calculation (WiRe) and CON 2 Investment reservation 18
1.2.6 What is a project? 10 2.8.2 CON 3 Project controlling (finance) 18
2 Explanation of task packages in PEP 11 2.9 Task packages of the Project Manager 20
2.1 Task packages of the Project Coordinator 12 2.9.1 PMT 1 Project planning 20
2.1.1 VER 1 Inquiry decision 12 2.9.2 PMT 2 Project management 20
2.1.2 VER 2 Inquiry processing 12 2.9.3 PMT 3 Project completion 20
2.1.3 VER 3 Submission/tracking of offer 12 2.9.4 PMT 4 Project timetable prior to commissioning 20
2.1.4 VER 4 Customer commissioning 13 2.10 Task packages of the Production Engineer 20
2.1.5 VER 5 Settlement of customer project costs 13 2.10.1 IND 4 Process FMEA 20
2.2 Task packages of the Application Engineer 13 2.10.2 IND 5 Flowchart 21
2.2.1 ENT 1 Component definition 13 IND 6 Tools and operating resources - requirement specifications, acceptance, documen-
2.10.3 21
2.2.2 ENT 2 Producibility assessment 13 tation
2.2.3 ENT 3 Design FMEA (D-FMEA) 14 2.10.4 IND 8 Evaluation of measuring systems 21
2.2.4 ENT 4 Component qualification 14 2.11 Task packages of the Quality Pre-Planner 21
2.2.5 ENT 5 Verification of material//structure 14 2.11.1 Q 1 QM plans 21
2.3 Task packages of the Project Buyer 14 2.11.2 Q 2 Initial sampling of sales part 21
2.3.1 EIN 1 Determination of costs and analysis 14 2.11.3 Q 3 Test and gage concept 22
2.3.2 EIN 2 Selection, commissioning and qualification of direct material for series production 15 2.11.4 Q 4 Quality pre-planning of direct material 22
2.3.3 EIN 3 Selection, commissioning and qualification of tools and operating resources 15 2.11.5 Q 5 Process acceptance 22
2.3.4 EIN 4 Selection and commissioning of raw materials 15 2.11.6 Q 6 CCC certification (CCC = China Compulsory Certification) 22
2.3.5 EIN 5 Purchasing volumes checked and optimized 16 2.11.7 Q 7 Defective part analysis 22
2.4 Task packages of the Industrial Engineer 16 2.11.8 Q 8 Q offer 22
2.4.1 IND 1 Work system design 16 2.12 Task packages of the Plant Container Management Administrator 22
2.4.2 IND 2 Tool / investment requirements 16 2.13 Task packages of the Team Manager Production 23
2.4.3 IND 3 Calculation of manufacturing costs 16 2.13.1 PRO 1 Production readiness 23
2.4.4 IND 7 Work preparation 16 2.13.2 PRO 2 Process capability study 23
|3
1 | Introduction
Project Phase Request Quote Product- and Processdevelopment Production Preparation Pre-Series Series
Project Quality Gates QG1 QG2 QG3 QG4 QG5 QG6 QG7
duction. costs cations. The production preparation phase only starts and has
Sub-part
issued
not been made, the next
saleable/ VS
phase is not approved or
with procurement approval. This is then followed, for is only approved after measures have been defined.
The inquiry phase includes, for example, the start of example, by commissioning of suppliers, approval of
inquiry processing. During this phase, the component direct material, acceptance of the tools, operating re-
is defined in technical terms, producibility is assessed,
Responsibility Sales sources and gages, their handover to Production, cre- Project Management
system is designed, the manufacturing costs are de- The pre-series phase includes acceptance of the pro-
termined and, if necessary, a profitability calculation cess as the most important result (2-day production).
is performed. During the offer phase, for example, the The series-production phase involves, for example,
offer is prepared, sent out, tracked and revised if Sales
Responsibility nec- initial sampling, launch coordination, settlement of the Project Management
is also obtained
Project during this phase.
Quality Gates QG1 Product and pro- of QG2
costs and revenues,
QG3 completion ofQG4 the project and, QG5 QG6 QG7
Project Phase Request Quote Product- and Processdevelopment Production Preparation Pre-Series Series
Project Quality Gates QG1 QG2 QG3 QG4 QG5 QG6 QG7
Project Milestones MS1 MS2 MS3 MS4 MS5 MS6 MS7 MS8 MS9 MS10 MS11 MS12 MS13 MS14
Project start Technical Start of Calculation Completion Quote sent Startwork- Customer design First serial off-tool Process- and Process Process approval/ EMBP/ PPAP sent SOP Customer/
done definition calculation closed Meeting shop realized freeze done/ parts available Production handover SOP Veritas issued Customer description: Action date
done for realized B-Approval Customer description: approval for closed Customer description: 0-Series/ saleable/
The figure shows the seven quality gates at Veritas. production project. All other quality gates open automatically in Customer received ESWT/ VFF/ PPV/ PVL direct Material SWFT/ PVS/ non MUP yellow
costs and Sub-part saleable/ VS
The inquiry to be processed is approved for all process the system if the preconditions are fulfilled, i.e. all stip- issued
participants at quality gate 1. The offer is approved at ulated partial results and results have been achieved.
quality gate 2 so that it can be sent to the customer. The preconditions for the quality gates are described
Quality gate 3 opens on receipt of the customer com- in the chapters of the particular PEP map from Chapter
Responsibility Sales Project Management
mission. The project is therefore approved.Request
Project Phase
Veritas pro- 3 onwards.Quote Product- and Processdevelopment Production Preparation Pre-Series Series
curement approval is granted at quality gate 4. Pre-se-
ries production is approved at quality gate 5. Approval
of the launch of series production takes place at quality
gate 6. The project is completed at quality gate 7.
Responsibility Sales Project Management
Project Phase Request Quote Product- and Processdevelopment Production Preparation Pre-Series Series
Quality gate 1 is approved by the Inquiry Committee,
Project Quality Gates QG1 QG2 QG3 QG4 QG5 QG6 QG7
see Chapter 9.1, if the stipulated preconditions are ful-
Request Quote Project B-release Pre serial Serial Project
filled. Quality gate 2 is approvedreleased
with investment res- released approval Veritas released production closing
released
ervation or, when there is no need for investment, with
approval of the offer basis by the Plant Manager. Qual-
ity gate 7 is approved by the Steering Committee, see
Chapter 9.3, after validation of the completion of the
|5
1 | Introduction
Fig. 3: "VDA maturity levels for quality gates and milestones at Veritas“
RG 0 RG 1 RG 2 RG 3 RG 4 RG 5 RG 6 RG 7
Project completion,
Innovation Requirements Supply chain Release of Firs parts from Approval of
Production responsibility’s
released management is defined technical series tool and Product and
planning handing over to
for series for awarding and volumes specifications serial equipment Process
is done series, starting
development circumferences allocated availabe
requalification
MS8
Customer design
freeze done/
B-Approval Customer
received
Project Phase Request Quote Product- and Processdevelopment Production Preparation Pre-Series Series
Project Quality Gates QG1 QG2 QG3 QG4 QG5 QG6 QG7
Project Milestones MS1 MS2 MS3 MS4 MS5 MS6 MS7 MS8 MS9 MS10 MS11 MS12 MS13 MS14
Project start Technical Start of Calculation Completion Quote sent Startwork- Customer design First serial off-tool Process- and Process Process approval/ EMBP/ PPAP sent SOP Customer/
done definition calculation closed Meeting shop realized freeze done/ parts available Production handover SOP Veritas issued Customer description: Action date
done for realized B-Approval Customer description: approval for closed Customer description: 0-Series/ saleable/
production Customer received ESWT/ VFF/ PPV/ PVL direct Material SWFT/ PVS/ non MUP yellow
costs and Sub-part saleable/ VS
issued
Project Phase Request Quote Product- and Processdevelopment Production Preparation Pre-Series Series
Project Phase Request Quote Product- and Processdevelopment Production Preparation Pre-Series Series
Project Quality Gates QG1 QG2 QG3 QG4 QG5 QG6 QG7
The following figure shows the preconditions and responsibility for fulfillment of the milestones.
MS2 Technical definition performed System input: Component defined and document: Producibility assessment Application Engineer
MS3 Start of calculation of manufacturing costs System input: Test sequence complete Industrial Engineer
MS4 Profitability assessment completed Document: DBRG "Project title“ + lifetime Participation Controller
MS5 Final meeting held System input: Final meeting held Project Coordinator
Approval of QG 2: Approval of offer
MS7 Kick-off workshop held Document: Minutes of kick-off workshop Project Manager
MS8 Customer design freeze carried out/ B approval received from customer (RG*3) System input: B approval or document Project Coordinator
Approval of QG 4: Approval of procurement by Veritas
MS9 First-off series tool parts available at Veritas System input: Meeting with customer System control
Customer designation.: ESWFT/ VFF/ PPV/ PVL
MS10 Process/product approval granted for direct material and semi-finished products Document: EMPB direct material Quality Pre-Planner
MS11 Process handover completed Document: Handover report Production Engineer
Approval of QG 5: Approval of pre-series production
MS12 Process acceptance/ SOP at Veritas completed/ customer designation.: SWFT/ PVS/ non Document: Process acceptance report Quality Pre-Planner
saleable/ VS
Approval of QG 6: Approval of series production launch
MS13 EMPB sent/ customer designation: 0 series/ saleable/ MUP yellow Document: EMPB Quality Pre-Planner
MS14 SOP at customer/ deployment date System input: Date of SOP at customer System control
Approval of QG 7: Completion of project
A result comes at the end of an activity sequence. Activi- Fig. 6: "Connection between the quality gate, milestone and key documentation“
ties are individual process steps within a task package
with a defined beginning and end. Each process step is
assigned to a responsible function holder. Several func-
tion holders cooperate in each activity.
A task package is a self-contained task with a result and Quality Gate 4
is assigned to a responsible person. It has a defined start
and a defined end. The task package description contains
all the important information relating to the task package:
task package designation, responsible function holder, MS7 MS7 First serial off-tool parts available
preconditions, partial results, results and the necessary MS8 MS8 Process- and Production approval for direct Material and Sub-part issued
activities which lead to the result. Responsible and co- MS9 MS9 Process handover closed
operating function holders are assigned to the activities. Dok Dok Acceptance log
The task packages in PEP are described in Chapter 2. Dok Dok PPAP purchased parts
The task package descriptions are shown for each func-
tion holder in Chapter 12. .
Partial results divide the task package into clear units
and enable the maturity level check to be carried out at
every quality gate or milestone.
|9
1 | Introduction
According to DIN 69901-5, a project is a complex task defined responsibility for results. A project calls for in- There are four different "project types" at Veritas: In-
with a defined goal, a defined beginning and a defined terdisciplinary cooperation in a project-specific organi- novation projects, application projects, capacity exten-
end, which is characterized by limited resources and zation. sion projects and global sourcing projects.
The defined task packages in PEP at Veritas are shown in the "functional structural plan".
Logistics Concept
SCM Project Manager and Cost Calculation In this Chapter all task packages for each function
AP-Nr. SCM 1
holder are summarized - according to the sequence in
Approval of offer‘s basics Investment Approval
Plant Manager the "functional structural plan“. This chosen sequence
AP-Nr. WL 1 AP-Nr. WL 2
Project Controlling
is based on the description of the process in the PEP
Pre-investment analysis
(financial)
Investment Controller map. The detailed descriptions for each task package
AP-Nr. CON 1 AP-Nr. CON 3
Project schedule
Project planning Project Management Project conclusion
Project Manager (before LoI)
AP-Nr. PMT 1 AP-Nr. PMT 2 AP-Nr. PMT 3 AP-Nr. PMT 4
Startup coordination
Startup Coordinator
AP-Nr. SCM 3 A task has a result in a project and it is dedicated to a responsible person. Request phase Order phase
| 11
2 | Explanation of the task packages in PEP
2.1 The task packages ing price, tool costs, investments) are then transferred 2.1.4 VER 4 Customer commissioning
of the Project Coordinator to the document template "Lifetime“ which is stored in
the system for further processing - with the objective of On receipt of the customer commission, the contract
approving the offer basis. components are first checked against the offer last
2.1.1 VER 1 Inquiry decision
sent in order to obtain any corrections made to the con-
This task package involves evaluating incoming cus- Optionally, the final meeting is ultimately held. This tract by the customer. If all the necessary information
tomer inquiries regarding Veritas' product-market strat- meeting is necessary if the Inquiry Committee has stip- is complete and correct, "nomination“/ "series order“/
egy. Irrelevant customer inquiries are rejected immedi- ulated in the inquiry decision that such a meeting is es- "nomination letter“ is stored in the system and the re-
ately. Inquiries of interest to Veritas are generated in the sential. Further action regarding processing of the in- lated customer confirmation is implemented in the re-
system as a new internal inquiry and are presented to quiry is defined with the affected group of participants spective customer portal. The internal project applica-
the Inquiry Committee, see Chapter 9.1. This Committee during this meeting. tion is also sent to Project Management for handover.
makes a final decision on whether the customer inquiry
is or is not processed internally. The objective of this The second phase of the task package involves data
2.1.3 VER 3 Submission/
procedure is merely to internally integrate the customer maintenance analogous to Veritas' sales checklist in or-
tracking of offer
inquiries which appear expedient to the company. der to update all necessary information in the system.
After the "offer basis" has been approved, final agree-
ment on the offer values to be submitted is reached in- Customer B approval must also be obtained by the
2.1.2 VER 2 Inquiry processing
side the department. The offer is then issued and sent Project Coordinator as quickly as possible. B approval
As part of this task package, an invitation to the inquiry in full to the customer. A copy of the offer is stored in is an essential precondition to realize the fixed drawing
meeting is initially sent. The objective of the meeting is to the system. status both internally and externally.
inform all function holders involved in the process about
the new customer inquiry. Based on the related report, This is followed by the offer tracking phase, i.e. nego- 2.1.5 VER 5 Settlement of
items in need of processing are queried, the milestones tiations with the customer. Depending on target com- customer project costs
in the inquiry and offer phase are fixed, and open topics munication, various task packages of the respective
are discussed. This provides the initial basis for smooth function holders must again be carried out optionally in The costs incurred in the customer project are settled
inquiry processing and the internal inquiry is initiated. order to optimize the customer offer based on revised in the last task package of the Project Coordinator. For
Every function holder is clear who is responsible for input variables. The customer offer is sent again to the this purpose, all negotiated assumptions of costs of
what result and by when.. customer and is stored in the system. tools must first be entered in the system. On receipt of
In the second part of the task package the cost break- the related tool order, including the customer's inven-
down (CBD) is prepared based on the available re- The VER3 task package is concluded with the decision tory numbers, they are supplemented in the system.
sults. All relevant data (e.g. manufacturing costs, sell- by the customer. When the inventory numbers are entered, the responsi-
| 13
2 | Explanation of the task packages in PEP
2.2.3 ENT 3 Design FMEA 2.2.5 ENT 5 Verification 2.3 Task packages
(D-FMEA) of material/structure of the Project Buyer
Design FMEA (FMEA: Failure Mode and Effects Analy- The objective of the task package is the approved ma-
sis) is an analytical method for evaluating possible fail- terial or structure which is used to produce the prod-
2.3.1 EIN 1 Determination of costs
ures which may occur during the design of a product. uct. . For this purpose, the material/structure for the and analysis
In accordance with their importance for the customer, inquiry phase must first be defined and approved in
The Project Buyer can start his/her work in the inquiry
their likelihood of occurrence and their probability of agreement with the corresponding function holder in
phase as soon as the general data on the inquiry are
detection, these failure causes are each evaluated with Purchasing and with the Application Engineer. If the
available from the Project Coordinator and the compo-
an indicator. D-FMEA is a living document in which new corresponding application has not been approved in-
nent definition with the parts list and advance drawings
findings, e.g. complaints, are included during regular ternally, material and function tests are carried out to
of the Application Engineer have been received. The
D-FMEA reviews. There are product-specific D-FMEA grant basic approval. This takes places as part of the
Project Buyer must also examine the logistics concept
teams consisting of an Application Engineer, a Quality pre-development process. If required, general cus-
in order to take account of possible cost-related de-
Pre-Planner and a Production Engineer. A D-FMEA is tomer-specific approval is also obtained. The material/
mands on the purchasing volumes.
initially produced in this task package. This is why im- structure for manufacturing the product can then be
plementation measures are defined if necessary. During used. Finally, the IMDS data are generated so that the
The objective is to check the market availability of the
a second step these measures are examined and the material/structure can be documented during initial
required purchasing volumes and collate the maximum
D-FMEA is completed.. sampling.
costs and implementation period as quickly as possible
based on inquiries from suppliers or in-house estimates.
2.2.4 ENT 4 Component qualification It must be noted in this respect that the quantities of
indirect material (tools, equipment, gages, etc.) are pro-
During component qualification customer-specific re- cessed by the Industrial Engineer. However, if a tool is
quirements are shown in a test plan, the tests are de- required, for example, for a purchased part, responsibil-
scribed, and acceptance criteria, target values, test ity for determining the costs lies with the Project Buyer.
quantities and a timetable are agreed with the test labo-
ratory. This test plan is the DVP (design verification plan) The data determined in this task package form the basis
and the first partial result of the task package. The DVP for Veritas' binding external offer. Conscientious colla-
tests then start in the test laboratory with the produced tion is therefore the decisive factor for the receipt of the
or purchased test items. At the end of the DVP tests, the order and Veritas' subsequent profit or loss.
results are analyzed and summarized in the DVP. The
DVP and also the task package are therefore completed.
| 15
2 | Explanation of the task packages in PEP
2.3.5 EIN 5 Purchasing volumes 2.4 Task packages of the operating resources which are required for production.
checked and optimized Industrial Engineer The objective is to calculate the required capacities for
producing the products forming the subject of the in-
This task package is only processed as part of a global quiry. The Industrial Engineer compares the required
2.4.1 IND 1 Work system design
sourcing project of the customer. In this case Veritas is capacities with the available capacities and defines the
already a series supplier, but the customer wants an ad- The Industrial Engineer can start his/her work as soon necessary investments and the tools to be purchased.
ditional price discount. The purchasing volumes must as component definition has been completed and pro-
therefore be checked in this task package in regard to cessing of the inquiry has commenced. 2.4.3 IND 3 Calculation of
further price optimizations. . The Project Coordinator The objective is to plan a work system which is used to manufacturing costs
also needs a qualified estimate of developments on the calculate the manufacturing costs. Producibility must
relevant purchasing markets to ensure that the order be considered and evaluated in this case. It must be The objective is to calculate the manufacturing costs
remains with Veritas by means of a competitive offer, possible to manufacture the product with process reli- after considering all relevant costs.
but also that this does not lead to any negative busi- ability under series conditions. The Industrial Engineer
ness. must process several aspects as a precondition for Calculation parts (if necessary several, for each pro-
work system planning: Firstly, it is evaluated by means duction variant) are stored in the system. The data
of a process FMEA what production methods are to be from the task packages EIN 1, SCM 2 and IND 2 are
selected and how they are to be ensured. The flowchart included in these spreadsheet parts and are used to
can be produced simultaneously to visually depict the finally calculate the manufacturing costs. The Industrial
processing sequence. The processing times are then Engineer checks the values for plausibility and, if nec-
calculated by means of MTM and the work system is essary, the planning data (e.g. batch size). The emer-
clocked. A layout is derived from clocking and the MTM gency plan must be considered during calculation of
analysis. All the data are included in the preparation of the manufacturing costs since it may lead to additional
the work plan which is used as the basis for calculating costs. The calculation is made available in the system
the manufacturing costs. and is processed further by the Project Coordinator
and Participation Controller.
2.4.2 IND 2 Tool/
investment requirements 2.4.4 IND 7 Work preparation
As soon as the task package "Work system design" has The objective of the task package is to hand over the
been completed, the Project Coordinator can use the purchased work system, including all documents from
inquiry data (unit numbers, etc.) to define the tools and work system design IND 1, to the Team Manager Pro-
| 17
2 | Explanation of the task packages in PEP
2.7 Task packages of the 2.8 Task packages of the ment Controlling uses the data determined in the pro-
Plant Manager Participation Controller and fitability calculation to prepare a decision-making basis
the Corporate Investment for the Board of Management. Investments in excess of
2.7.1 WL 1 Approval Controller ¤ 500,000 must also be approved by the Supervisory
Board. The detailed connection between both task pa-
Offer basis
2.8.1 CON 1 Profitability ckages is shown in Figure 9 "Investment approval pro-
In this task package the profitability calculation and/or cess“.
calculation and
the lifetime are checked for completeness and compli-
CON 2 Investment reservation
ance with the stipulated target figures, and are appro- 2.8.2 CON 3 Project controlling
ved. Approval of the offer basis is the precondition for When processing the inquiry it is necessary to prepare
(Finance)
investment reservation (if required) and also for prepa- the data generated during inquiry processing (manufac-
ration of the offer by the Project Coordinator. turing costs, sales prices, investments, etc.) in a struc- In order to ensure a permanently effective management
tured form in order to create a valid economic decisi- function for controlling and to evaluate the profitability
on-making basis for the Board of Management or the of an individual project, structured and transparent pro-
2.7.2 WL 2 Investment approval
Supervisory Board. The Board of Management or the Su- ject controlling is necessary. Evaluation of the project is
Since the investments in the inquiry phase were already pervisory Board ultimately defines the price floor down to based on the customer project plan stored in the system.
reserved in task package CON 2, they only need to be which the Project Coordinator may go with the customer. This plan must always be oriented towards the award
applied for after commissioning. For this purpose, the date and the premises valid at the time. Project planning,
Production Engineer enters the required investments in The profitability calculation (WiRe) compares the ear- see PMT 1, includes manufacturing costs, investments,
the system, the Investment Cost Center Manager ap- nings (parts, tool and development sales) with the pro- tools, sales revenues, material costs and internal settle-
plies for the investments and Controlling cancels the ject costs and investments. In addition to the manufac- ments.
reservations and approves the investment cost center. turing costs of the individual sales parts, costs for tools
and development are also included in the analysis. In- As part of project controlling, the actual figures from the
vestments which are necessary for accepting the inquiry stipulated items are compared with the planning data in
must be included in the profitability calculation in order to order to then evaluate where the project differs from the
then create the basis for task package CON 2. plan. After SOP of a project, it is possible to compare
the target Rol with the actual Rol in order to measure the
Task package CON 2 uses the key figures determined profitability of the entire project.
in the profitability calculation and then reserves the re-
quired investments. Investments in excess of ¤ 50,000
must be approved by the Board of Management. Invest-
Manufacturing costs
Responsibility: Industrial Engineer
Lifetime
Responsibilty: Project Coordinator
Yes
Investment reservation
Responsibility: Corporate Investment Controller
Investment application
Responsibility: Plant Manager
| 19
2 | Explanation of the task packages in PEP
2.9 Task packages of the 2.9.2 PMT 2 Project management 2.9.4 PMT 4 Project timetable
Project Manager In this task package the Project Manager must manage
before commissioning
the project tasks up to quality gate 6. For this purpose, The objective is to prepare a project timetable for im-
2.9.1 PMT 1 Project planning he/she firstly uses the regular status meetings and portant innovation projects in the inquiry phase. This
deviation analyses, including the initiation of suitable project timetable is required for the customer offer. The
This task package starts with the handover of the pro-
measures in the event of data variances or cost dif- Project Manager produces the project timetable based
ject by the Project Coordinator to an assigned Project
ferences. If required, escalation management, change on the customer milestones from the inquiry, the com-
Manager. The objective is to prepare and approve the
management, risk management and documentation of ponent definition and the tool and investment require-
project timetable and the project cost and revenue
lessons learned are used in the lessons learned park- ments.
plan. For this purpose, the project input variables are
ing area. The last aspect is analyzed and documented
first checked, a project order containing all the key
at the end of the project. The contents of this work
data relating to the project is produced, and a detailed
package also include monitoring of the maturity level 2.10 Task packages of the
project timetable based on the partial results and re-
and its confirmation by the Quality Pre-Planner to the
sults is drawn up. A kick-off workshop is then held with Production Engineer
customer if this is necessary. The partial results of the
the participation of the entire project team. The objec-
task package are quality gate approvals.
tives of the kick-off workshop are to incorporate all par- 2.10.1 IND 4 Process FMEA
ticipating function holders, inform them about the key
data relating to the project, jointly agree the dates in In this task package a new Failure Mode and Effects
2.9.3 PMT 3 Project completion
the project timetable and therefore produce an obliga- Analysis (FMEA) is carried out and is evaluated by the
tion for all participants. In order to discover any risks The objectives of the task package are to prepare the separately formed FMEA team or the existing FMEA
in advance, the project team carries out a project risk completion of the project and hand it over to the pro- from inquiry phase, IND 1, is revised. The team mem-
analysis and formulates measures to counter the risks. duction plant responsible for series production. This bers are selected on an interdivisional basis from a
Another important part of the kick-off workshop is de- starts by sending confirmation of maturity level 6 to the wide range of function holders. The findings from the
termination of the required quantities at all production customer. At the end of the project a final workshop FMEA must be included in the design of the work sys-
stages, e.g. for tool acceptance or internal process ac- is held in which the lessons learned parking area, for tem. The existing work system is subsequently exam-
ceptance. After the kick-off workshop, the project time- example, is evaluated and processed. The results of ined in regard to the implementation of the planned
table and the cost and revenue plan are finalized and the final workshop and lessons learned, as well as the prevention measures or discovery measures.
activated by the Project Manager. comparison of target-actual costs, revenues and dead-
lines are included in the final report. Finally, confirma-
tion of maturity level 7 is sent to the customer and the
Project Manager applies for quality gate 7.
| 21
2 | Explanation of the task packages in PEP
2.11.3 Q 3 Test and gage concept phase. The task package consists of two partial results 2.11.7 Q 7 Defective part analysis
starting with necessary "internal process acceptance"
The test and gage concept is formulated in task pack- With defective part analysis a concept is formulated that
and optional "customer process acceptance“. Internal
age IND 6 by the Production Engineer. This concept is can be used to analyze a product forming the subject
process acceptance is managed by the Quality Pre-
checked by the Quality Pre-Planner and supplemented of complaint in a damage case. Different test steps are
Planner at the production plant. The preconditions are
by the contact persons. The concept is then sent to the defined here. They must be worked through consecu-
successful realization of production readiness, see PRO
customer for agreement. Agreement will enable the cus- tively until the cause of the defect forming the subject of
1, and preparation of internal process acceptance by
tomer to incorporate change requests in the sales part complaint has been determined. The concept of defec-
the Team Manager Production. Deviations may lead to
gage. If no feedback is received from the customer, the tive part analysis must be formulated for every sales part
rejection of process acceptance, which then results in
concept will be deemed to have been accepted and of Veritas.
a delivery block. If the customer requests performance
agreed within 5 working days. .
of his own process acceptance, it is also organized and
monitored by the Quality Pre-Planner at the production 2.11.8 Q 8 Q offer
2.11.4 Q 4 Quality pre-planning of plant.
direct material The quality offer (Q offer) is a currently new requirement
by individual customers in innovation projects. This re-
The objective of this task package is approval of di-
2.11.6 Q 6 CCC certification quirement involves the provision of detailed information
rect material.. It is therefore subdivided into three par- (CCC = China Compulsory Certification) to the customer regarding implementation of the project
tial results: "Quality pre-planning of direct material", during the inquiry/offer phase. Due to complexity, prep-
"Process acceptance by the supplier" and "Approval of China Compulsory Certification involves validation of
aration of the Q offer is a very time-intensive activity and
direct material“. Approval of direct material must take critical components. This is demanded by the Chinese
calls for cooperation between different function holders.
place for every new purchased part. The partial results government and is controlled by the customs authori-
"Quality pre-planning of direct material" and "Process ties. CCC affects, for example, passenger compartment
acceptance by the supplier" are only used with critical materials, brake lines, tires, etc. This certification calls
for separate tests which must be sent to the Chinese 2.12 Task package of the
purchased parts. Critical purchased parts are defined
accordingly with all participating function holders in the authorities. Samples requiring detailed photo documen- Plant Container
kick-off workshop. tation are also requested. After all the necessary docu- Management Administrator
ments have been submitted, a processing period of up
2.11.5 Q 5 Process acceptance to 6 months must be assumed. The product in question SCM 2 Packaging planning/
may not be exported to China without the corresponding
Process acceptance entails evaluation and approval of
container management
approval.
the production process with the objective of approving The precondition for this task package is calculation of
the series process and starting the series production the logistics costs. Based on the formulated information
innovation projects
are once again examined and agreed with the customer, from different series batches. The Quality Coordinator,
| 23
3 | PEP map forInnovationsprojekte
PEP-Landkarte innovation projects
Fig. 10: "PEP map for innovation projects"
Verantwortung Vertrieb
CON 1
Wirtschaftlich-
Beteiligungscontroller keitsrechnung
erstellt
CON 2.1 CON 2.2
Corporate Investitionen reserviert/ Investitionen verbindlich
Investitionscontroller abgelehnt oder unver- reserviert/ abgelehnt
bindlich reserviert
PMT 4 PMT 1.1 Startworkshop stattgefunden
Projektterminplan
Projektmanager vor Beauftragung PMT 1.2 Projektplanung
erstellt freigegeben
IND 4.1
P-FMEA erstellt
Produktionstechniker IND 5
Flowchart erstellt
Q8 Q 1.1
Angebots- QM-Plan Prototypen erstellt
Qualitätsvorausplaner grundlage Q 2.1
freigegeben Bemusterungsabstimmungsgespräch stattgefunden
Sachbearbeiter
Administratives
Behältermanagement Werk
Teammanager Produktion
Anlaufkoordinator
innovation projects
PEP map for
QG4 QG5 QG6 QG7
EIN 3.1 Lieferanten EIN 2.2 Lieferanten für Direktes Material beauftragt EIN 2.3 Liefe- EIN 2.4 EIN 3.3 EIN 2.5 Serienbereitschaft der Lieferanten Direktes Material hergestellt EIN 3.4
vorläufig nomi- ranten für Kaufteile Projektbestellungen Projektbestellungen Einkaufsarbeiten
EIN 3.2 Lieferanten für Indirektes Material beauftragt EIN 4.3 Projektbestellungen Rohstoffe beliefert
niert für Indirektes mit Beistellung Direktes Material Indirektes Material Indirektes Material
Material EIN 4.2 Lieferanten für Rohstoffe beauftragt beauftragt beliefert beliefert EIN 4.4 Serienbereitschaft der Lieferanten Rohstoffe hergestellt abgeschlossen
IND 7
Produktionsübergabe
stattgefunden
PRU 2.2
Mess- und Prüfvorrichtungen PRU 3.1 Messbericht liegt vor
verfügbar PRU 3.2 Freigegebener Werkstoff- und Funktionsbericht liegt vor
SCM 1.3
Umsetzung
Logistikkonzept
abgeschlossen
WL 2
Investitions-
kostenstelle
freigegeben
CON 3
Report nach
Übergabe an
Standort iegt vor
ENT 5.3
Werkstoff/
Aufbau
freigegeben
| 25
3 | Preconditions for quality gates in innovation projects
Fig. 11: "Preconditions for quality gates in innovation projects"
Task packa- Result/partial result Precondition Responsibility APQP
ge number
VER 1.1 Inquiry entered in the system System input: Inquiry generation Project Coordinator 1
VER 1.2 Inquiry decision taken System input: Statistical updating of the inquiry (processing approved or reject Project Coordinator 1
inquiry)
Approval of QG 1: Approval of inquiry
VER 2.1 Start inquiry processing System input: System cycle for inquiry Project Coordinator 1
ENT 1.1 Component for inquiry defined and in line with status System input: Status "Component defined" Application Engineer 10
ENT 5.1 Material/ structure for inquiry defined System input: Material/ structure for inquiry free (status 140) Head of Pre-Development Department/ Product 10
Developer
ENT 2 Producibility assessment carried out Document: Producibility assessment Application Engineer 11
EIN 1 Costs and availabilities calculated System input: Costs and availability have been calculated Project Buyer 6
IND 1 Work system design completed Document: Document folder Industrial Engineer 16
PRU 1 Validation costs/duration entered in the system System input: Validation costs and duration Project Coordinator in the Test Laboratory 5, 21
SCM 1.1 Preparation of logistics concept Document: Logistics concept SCM Project Manager 17
SCM 1.2 Preparation of logistics calculation Document: Logistics calculation SCM Project Manager 17
IND 2 Costs and delivery dates planned for tools and investments System input: Technical data/details, document: Capacity calculation Industrial Engineer 7
PMT 4 Project timetable prepared before commissioning Document: Project timetable Project Manager 0
Q8 Q-offer prepared Document: Q offer Quality Pre-Planner 2
IND 3 Manufacturing costs calculated Document: Calculation printout Industrial Engineer 1
VER 2.2 Lifetime is available Document: Lifetime Project Coordinator 1
CON 1 Profitability calculation prepared Document: DBRG "Project title“ + lifetime Participation Controller 1
WL 1 Offer basis approved System input: Offer basis approved Plant Manager 1
VER 2.3 Final meeting held System input: Final meeting held Project Coordinator 1
CON 2.1 Investments reserved/rejected or reserved with non-binding effect System input: Investment approved/rejected/reserved with non-binding effect Corporate Investment Controller
Approval of QG 2: Offer approval
PMT 1.1 Kick-off workshop has taken place Document: Minutes of kick-off workshop Project Manager 0
PMT 1.2 Project plan approved Documents: Project timetable and project cost plan Project Manager 0
Q 1.1 QM plan for prototypes prepared Document: QM plan for prototypes Quality Pre-Planner 8
Q 2.1 Sampling coordination meeting held Document: Sampling coordination meeting held Quality Pre-Planner 22
ENT 1.2 Customer data / requirement specifications approved System input: Status of customer data approved Application Engineer 2
ENT 5.2 Material/ structure determined in line with status System input: Material/ structure determined (status 190) Head of Pre-Development Department/ Product 10
Developer
ENT 1.3 Subject group of all components in line with status in the system System input: Subject group of all components in line with status in the system Application Engineer 10
ENT 3.1 Design FMEA prepared Document: D-FMEA Application Engineer 3
ENT 4.1 Document DVP prepared System input: Status change (mailing for tests) Application Engineer 5
PRU 2.1 Capacity planning carried out System input: Capacity planning has been carried out Project Coordinator in the Test Laboratory 5, 21
ENT 1.4 Plant drawing free for IND + supplier nomination + sample construction (status Document: Plant drawings status 114 Application Engineer 10
114)
EIN 2.1 Suppliers provisionally nominated for direct material System input: Suppliers have been nominated and entered Project Buyer 6
EIN 4.1 Suppliers provisionally nominated for raw materials System input: Suppliers have been nominated and entered Project Buyer 6
IND 4.1 P-FMEA prepared Document: P-FMEA Production Engineer 13
IND 5 Flowchart produced Document: Flowchart Production Engineer 12
IND 6.1 Requirement specifications for operating resources, tools and gages produced Document: Requirement specifications, Production Engineer 7
System inputs: List of tools, test equipment list complete
Q3 Test and gage concept agreed with customer System input: Gage concept agreed/ customer informed (change of status) Quality Pre-Planner 7
EIN 3.1 Suppliers provisionally nominated for indirect material System input: Suppliers have been nominated and entered Project Buyer 7
VER 4.2 B approval of customer available System input: Customer procurement approval Project Coordinator 1
WL 2 Investment cost center approved System input: Investment approved Plant Manager
PMT 2.1 QG 4 approved System input: Approve QG 4 Project Manager 0
Approval of QG 4: Procurement approval by Veritas
SCM 2.1 Packaging planning/ container management supplier completed Document: Packaging datasheet/regulations of supplier Plant Container 17
Management Administrator
EIN 4.2 Suppliers commissioned for raw materials System input: Order confirmations are booked in the system Project Buyer 6
EIN 3.2 Suppliers commissioned for indirect material System input: Order confirmations are booked in the system Project Buyer 7
IND 6.2 Design approval for indirect material Document: Design approval for indirect material (e-mail) Production Engineer 7
Task packa- Result/partial result Precondition Responsibility APQP
ge number
| 27
3 | Preconditions for quality gates in innovation projects
ENT 1.5 Plant drawings approved (status 230) Document: Approve plant drawings status 230 Application Engineer 10
Document: Parts history 4
ENT 3.2 Measures for design FMEA completed Document: D-FMEA Application Engineer 3
EIN 2.2 Suppliers commissioned for direct material System input: Order confirmations are booked in the system Project Buyer 6
EIN 2.3 Suppliers commissioned for purchased parts with supply System input: Purchased parts with supply commissioned Project Buyer 6
Q 4.1 Quality pre-planning of direct material completed Document: QVP checklist for direct material Quality Pre-Planner 6
VER 5.1 Inventory numbers stored System input: Sales data for tools Project Coordinator
IND 6.3 Preliminary acceptance of indirect material performed Document: Acceptance report Production Engineer 7
EIN 2.4 Project orders for direct material delivered System input: Deliveries/incoming goods are booked in the system Project Buyer 6
Q 4.2 Process acceptance for suppliers of direct material completed Documents: Process acceptance report Quality Pre-Planner 6
SCM 2.2 Packaging planning/ container management completed Document: Packaging datasheet/ regulations Plant Container 17
Management Administrator
EIN 3.3 Project orders for indirect material delivered System input: Deliveries/incoming goods are booked in FOSS Project Buyer 7
Q 4.3 Direct material approved Document: EMPB direct material Quality Pre-Planner 6
IND 6.4 Tools, gages and operating resources accepted Document: Acceptance report approved Production Engineer 7
Q 1.2 QM plan for pre-series production prepared Document: QM plan for pre-series production Quality Pre-Planner 15
IND 8 Measuring system approved Documents: Measuring report, gage capability, MSA Production Engineer 14
IND 4.2 Measures for process FMEA completed Document: P-FMEA approved Production Engineer 13
PRU 2.2 Measuring and test equipment available System input: Purchased measuring and test equipment available Project Coordinator in the Test Laboratory 21
IND 7 Production handover has taken place Document: Handover report Industrial Engineer 16, 25
Q 1.3 QM plan for series production prepared Document: QM plan for series production Quality Pre-Planner 19
PRO 1 Production readiness created Document: Checklist for production readiness, emergency plan Team Manager Production 24
EIN 4.3 Project orders for raw materials delivered System input: Deliveries/incoming goods are booked in the system Project Buyer 6
EIN 4.4 Series readiness of raw material suppliers created System input: Series readiness of suppliers has been created Project Buyer 6
EIN 2.5 Series readiness of direct material suppliers created System input: Series readiness of suppliers has been created Project Buyer 6
SCM 1.3 Implementation of logistics concept completed Document: Logistics concept SCM Project Manager 17
PMT 2.2 QG 5 approved System input: Approve QG 5 Project Manager 0
Approval of QG 5: Pre-series approval
PRO 2.1 Short-term process capability exists Document: Short-term process capability study Team Manager Production 20
EIN 3.4 Purchasing of all tools and equipment completed System input: All project orders for tools and equip- Project Buyer 7
ment are completed
Q 5.1 Internal process acceptance completed Document: Process acceptance report Quality Pre-Planner 18
PMT 2.3 QG 6 approved System input: Approve QG 6 Project Manager 0
Approval of QG 6: Approval of series launch
The PEP map for
application projects
PEP map for
ENT 4.2 DVP completed
CCC printing license is available
System input: Status change of DVP approved
Documents: CCC printing license, CCC certificate
Application Engineer
Quality Pre-Planner
5
2
application projects
Q6
PRU 3.1 Measuring report is available Document: Test report MW Project Coordinator in the 21
Test Laboratory
An application project exists if the production pro-
PRU 3.2 Approved material and function report is available Document: EMPB_LAB Project Coordinator in the 21 cess at the production plant, the material and the
Test Laboratory function holder are known.
ENT 5.3 Material/structure approved System input: Material/ structure free (status 230) Head of Pre-Development 10
Department/ Product
Developer The following PEP map shows the process sequence
Q7 Defective part analysis concept agreed Document: Defective part analysis concept Quality Pre-Planner 20 and the participating function holders.
Q 2.2 EMPB sent Document: EMPB Quality Pre-Planner 22
Q 5.2 Customer process acceptance completed Document: Customer-specific acceptance report Quality Pre-Planner 18
Q 2.3 Customer approval available Document: Customer approval Quality Pre-Planner 23
PRO 2.2 Long-term process capability exists Document: Long-term process capability study Team Manager Production 20
SCM 3 Launch coordination completed Document: Handover report KSC Launch Coordinator 25
VER 5.2 Customer project costs calculated System input: Status of tool costs or development Project Coordinator 1
and cancellation costs calculated
CON 3 Report after handover to plant is available Document: Target-actual comparison Participation Controller 0
PMT 3.1 Final report approved Document: Final report Project Manager 0
PMT 3.2 QG 7 approved System input: Approve QG 7 Project Manager 0
Approval of QG 7: Completion of project
| 29
4 | PEP map
PEP-Map for application
Application Projectprojects
Fig. 12: "PEP map for application projects“
Responsibility Sales
CON 1
Economic Efficiency
Investment Controller Calculation (EEC)
created
CON 2.1 CON 2.2
Corporate Investments reserved/ Investment reserved/
Investment Control rejected or reserved Investment rejected
provisionally
PMT 1.1 Launch workshop completed
Project Manager PMT 1.2 Approval project
planning
IND 4.1
FMEA process created
Production Technician IND 5
Flow chart created
Q 1.1
QM-Plan Prototypes compiled
Advanced Quality Planner Q 2.1
Sampling coordination meeting has been held
Startup Coordinator
application projects
ENT 1.5 Working drawing released (Status 230) ENT 4.2
ENT 3.2 Measures for Design FMEA completed DVP completed
PRU 2.2
Procured metrology and PRU 3.1 The measurement report is available in the system
testing devices available PRU 3.2 The released measurement report is available in the system
SCM 1.3
Implementation
of logistics con-
cept concluded
WL 2
Investment
Approval
CON 3
Report available
after delivery
to location
| 31
4 | Preconditions for quality gates in application projects
Fig. 13: "Preconditions for quality gates in application projects"
Task packa- Result/partial result Precondition Responsibility APQP
ge number
VER 1.1 Inquiry entered in the system System input: Inquiry generation Project Coordinator 1
VER 1.2 Inquiry decision taken System input: Statistical updating of the inquiry (processing approved or reject Project Coordinator 1
inquiry)
Approval of QG 1: Approval of inquiry
VER 2.1 Start inquiry processing System input: System cycle for inquiry Project Coordinator 1
ENT 1.1 Component for inquiry defined and in line with status System input: Status of component defined Application Engineer 10
ENT 2 Producibility assessment carried out Document: Producibility assessment Application Engineer 11
EIN 1 Costs and availabilities calculated System input: Costs and availability have been calculated Project Buyer 6
IND 1 Work system design completed Document: Document folder Industrial Engineer 16
PRU 1 Validation costs/duration entered in the system System input: Validation costs and duration Project Coordinator in the Test Laboratory 5, 21
SCM 1.1 Preparation of logistics concept Document: Logistics concept SCM Project Manager 17
SCM 1.2 Preparation of logistics calculation Document: Calculation of logistics costs SCM Project Manager 17
IND 2 Costs and delivery dates planned for tools and investments System input: Technical data/details, document: Capacity calculation Industrial Engineer 7
IND 3 Manufacturing costs calculated Document: Calculation printout Industrial Engineer 1
VER 2.2 Lifetime is available Document: Lifetime Project Coordinator 1
CON 1 Profitability calculation prepared Document: DBRG "Project title“ + lifetime Participation Controller 1
WL 1 Offer basis approved System input: Offer basis approved Plant Manager 1
VER 2.3 Final meeting held System input: Final meeting held Project Coordinator 1
CON 2.1 Investments reserved/rejected or reserved with non-binding effect System input: Investment approved/rejected/reserved with non-binding effect Corporate Investment Controller
Approval of QG 2: Offer approval
PMT 1.1 Kick-off workshop held Document: Minutes of kick-off workshop Project Manager 0
PMT 1.2 Project plan approved Documents: Project timetable and project cost plan Project Manager 0
Q 1.1 QM plan for prototypes prepared Document: QM plan for prototypes Quality Pre-Planner 8
Q 2.1 Sampling coordination meeting held Document: Sampling coordination meeting held Quality Pre-Planner 22
ENT 1.2 Customer data / requirement specifications approved System input: Status of customer data approved Application Engineer 2
ENT 1.3 Subject group of all components in line with status in the system System input: Subject group of all components in line with status in the system Application Engineer 10
ENT 3.1 Design FMEA prepared Document:D-FMEA Application Engineer 3
ENT 4.1 Document DVP prepared System input: Status change (mailing for tests) Application Engineer 5
PRU 2.1 Capacity planning carried out System input: Capacity planning has been carried out Project Coordinator in the Test Laboratory 5, 21
ENT 1.4 Plant drawing free for IND + supplier nomination + sample construction (status Document: Plant drawings status 114 Application Engineer 10
114)
EIN 2.1 Suppliers provisionally nominated for direct material System input: Suppliers have been nominated and entered Project Buyer 6
EIN 4.1 Suppliers provisionally nominated for raw materials System input: Suppliers have been nominated and entered Project Buyer 6
IND 4.1 P-FMEA prepared Document: P-FMEA Production Engineer 13
IND 5 Flowchart produced Document: Flowchart Production Engineer 12
IND 6.1 Requirement specifications for operating resources, tools and gages produced Document: Requirement specifications, Production Engineer 7
System inputs: List of tools, test equipment list complete
Q3 Test and gage concept agreed with customer System input: Gage concept agreed/ customer informed (change of status) Quality Pre-Planner 7
EIN 3.1 Suppliers provisionally nominated for indirect material System input: Suppliers have been nominated and entered Project Buyer 7
VER 4.2 Procurement approval of customer is available System input: Customer procurement approval Project Coordinator 1
WL 2 Investment cost center approved System input: Investment approved Plant Manager
PMT 2.1 QG 4 approved System input: Approve QG 4 Project Manager 0
Approval of QG 4: Procurement approval by Veritas
SCM 2.1 Packaging planning/ container management at supplier completed Document: Packaging datasheet/regulations of supplier Plant Container 17
Management Administrator
EIN 4.2 Suppliers commissioned for raw materials System input: Order confirmations are booked in the system Project Buyer 6
EIN 3.2 Suppliers commissioned for indirect material System input: Order confirmations are booked in the system Project Buyer 7
IND 6.2 Design approval for indirect material Document: Design approval for indirect material (e-mail) Production Engineer 7
ENT 1.5 Plant drawings approved (status 230) Document: Approve plant drawings status 230 Application Engineer 10
Document: Parts history 4
Task packa- Result/partial result Precondition Responsibility APQP
ge number
| 33
4 | Precondition for quality gates in application projects
ENT 3.2 Measures for design FMEA completed Document: D-FMEA Application Engineer 3
EIN 2.2 Suppliers commissioned for direct material System input: Order confirmations are booked in the system Project Buyer 6
EIN 2.3 Suppliers commissioned for purchased parts with supply System input: Purchased parts with supply commissioned Project Buyer 6
Q 4.1 Quality pre-planning of direct material completed Document: QVP checklist for direct material Quality Pre-Planner 6
VER 5.1 Inventory numbers stored System input: Sales data for tools Project Coordinator
IND 6.3 Preliminary acceptance of indirect material performed Document: Acceptance report Production Engineer 7
EIN 2.4 Project orders for direct material delivered System input: Deliveries/ incoming goods are booked in the system Project Buyer 6
Q 4.2 Process acceptance for suppliers of direct material completed Document: Process acceptance report Quality Pre-Planner 6
SCM 2.2 Packaging planning/ container management completed Document: Packaging datasheets/ regulations Plant Container 17
Management Administrator
EIN 3.3 Project orders for indirect material delivered System input: Deliveries/incoming goods are booked in FOSS Project Buyer 7
Q 4.3 Direct material approved Document: EMPB direct material Quality Pre-Planner 6
IND 6.4 Tools, gages and operating resources accepted Document: Acceptance report approved Production Engineer 7
Q 1.2 QM plan for pre-series production prepared Document: QM plan for pre-series production Quality Pre-Planner 15
IND 8 Measuring system approved Documents: Measuring report, gage capability, MSA Production Engineer 14
IND 4.2 Measures for process FMEA completed Document: P-FMEA approved Production Engineer 13
PRU 2.2 Measuring and test equipment available System input: Purchased measuring and test equipment available Project Coordinator in the Test Laboratory 21
IND 7 Production handover has taken place Document: Handover report Industrial Engineer 16, 25
Q 1.3 QM plan for series production prepared Document: QM plan for series production Quality Pre-Planner 19
PRO 1 Production readiness created Document: Checklist for production readiness, emergency plan Team Manager Production 24
EIN 4.3 Project orders for raw materials delivered System input: Deliveries/ incoming goods are booked in the system Project Buyer 6
EIN 4.4 Series readiness of suppliers of raw materials created System input: Series readiness of suppliers has been created Project Buyer 6
EIN 2.5 Series readiness of suppliers of direct material created System input: Series readiness of suppliers has been created Project Buyer 6
SCM 1.3 Implementation of logistics concept completed Document: Logistics concept SCM Project Manager 17
PMT 2.2 QG 5 approved System input: Approve QG 5 Project Manager 0
Approval of QG 5: Pre-series approval
PRO 2.1 Short-term process capability exists Document: Short-term process capability study Team Manager Production 20
EIN 3.4 Purchasing of all tools and equipment completed System input: All project orders for tools and equip- Project Buyer 7
ment are completed
Q 5.1 Internal process acceptance completed Document: Process acceptance report Quality Pre-Planner 18
PMT 2.3 QG 6 approved System input: Approve QG 6 Project Manager 0
Approval of QG 6: Approval of series launch
ENT 4.2 DVP completed System input: Status change of DVP completed Application Engineer 5
Q6 CCC printing license is available Documents: CCC printing license, CCC certificate Quality Pre-Planner 2
PRU 3.1 Measuring report is available Document: Test report MW Project Coordinator in the 21
Test Laboratory
PRU 3.2 Approved material and function report is available Document: EMPB_LAB Project Coordinator in the 21
Test Laboratory
sion projects
Q 2.2
Q 5.2
EMPB sent
Customer process acceptance completed
Document: EMPB
Document: Customer-specific acceptance report
Quality Pre-Planner
Quality Pre-Planner
22
18
extension projects
Q 2.3 Customer approval received Document: Customer approval Quality Pre-Planner 23
Capacity extension projects may be initiated both
PRO 2.2 Long-term process capability exists Document: Long-term process capability study Team Manager Production 20
by the customer and Production. Customer capa-
SCM 3 Launch coordination completed Document: Handover report KSC Launch Coordinator 25
city extension projects are included in the form of
VER 5.2 Customer project costs calculated System input: Status of tool costs or development Project Coordinator 1
and cancellation costs calculated capacity extension inquiries. Internally, capacity in-
CON 3 Report after handover to plant is available Document: Target-actual comparison Participation Controller 0 creases can be included via the workflow "Capacity
PMT 3.1 Final report approved Document: Final report Project Manager 0 bottlenecks", see Work Instruction EDV6_AA_1551
PMT 3.2 QG 7 approved System input: Approve QG 7 Project Manager 0 in this respect. A capacity extension project exists
Approval of QG 7: Completion of project if the same production process is used at the same
production plant, but additional operating resources
and/or tools are required.
| 35
5 | PEP map forfür
PEP-Landkarte capacity extension projects
Kapazitätserweiterungsprojekte
Fig. 14: "PEP map for capacity extension projects"
Verantwortung Vertrieb
Application Engineer
CON 1
Wirtschaftlich-
Beteiligungscontroller keitsrechnung
erstellt
CON 2.1 CON 2.2
Corporate Investitionen reserviert/ Investitionen verbindlich
Investitionscontroller abgelehnt oder unver- reserviert/ abgelehnt
bindlich reserviert
PMT 1.1 Startworkshop stattgefunden
Projektmanager PMT 1.2 Projektplanung
freigegeben
IND 4.1
P-FMEA erstellt
Produktionstechniker IND 5
Flowchart erstellt
Qualitätsvorausplaner Q 2.1
Bemusterungsabstimmungsgespräch stattgefunden
Sachbearbeiter
Administratives
Behältermanagement Werk
Teammanager Produktion
Anlaufkoordinator
EIN 3.1 Lieferanten EIN 2.2 Lieferanten für Direktes Material beauftragt EIN 2.3 Liefe- EIN 2.4 EIN 3.3 EIN 2.5 Serienbereitschaft der Lieferanten Direktes Material hergestellt EIN 3.4
vorläufig nomi- ranten für Kaufteile Projektbestellungen Projektbestellungen Einkaufsarbeiten
EIN 3.2 Lieferanten für Indirektes Material beauftragt EIN 4.3 Projektbestellungen Rohstoffe beliefert
niert für Indirektes mit Beistellung Direktes Material Indirektes Material Indirektes Material
Material EIN 4.2 Lieferanten für Rohstoffe beauftragt beauftragt beliefert beliefert EIN 4.4 Serienbereitschaft der Lieferanten Rohstoffe hergestellt abgeschlossen
IND 7
Produktionsübergabe
stattgefunden
sion projects
WL 2
Investitions-
kostenstelle
freigegeben
CON 3
Report nach
Übergabe an
Standort iegt vor
| 37
5 | Preconditions for quality gates in capacity extension projects
Fig. 15: "Preconditions for quality gates in capacity extension projects"
Task packa- Result/partial result Precondition Responsibility APQP
ge number
VER 1.1 Inquiry entered in the system System input: Inquiry generation Project Coordinator 1
VER 1.2 Inquiry decision taken System input: Statistical updating of the inquiry (processing approved or reject Project Coordinator 1
inquiry)
Approval of QG 1: Approval of inquiry
VER 2.1 Start inquiry processing System input: System cycle for inquiry Project Coordinator 1
EIN 1 Costs and availabilities calculated System input: Costs and availabilities have been calculated Project Buyer 6
IND 1 Work system design completed Document: Document folder Industrial Engineer 16
SCM 1.1 Preparation of logistics concept Document: Logistics concept SCM Project Manager 17
SCM 1.2 Preparation of logistics calculation Document: Calculation of logistics costs SCM Project Manager 17
IND 2 Costs and delivery dates planned for tools and investments System input: Technical data/details, document: Capacity calculation Industrial Engineer 7
IND 3 Manufacturing costs calculated Document: Calculation printout Industrial Engineer 1
VER 2.2 Lifetime is available Document: Lifetime Project Coordinator 1
CON 1 Profitability calculation prepared Document: DBRG "Project title“ + lifetime Participation Controller 1
WL 1 Offer basis approved System input: Offer basis approved Plant Manager 1
VER 2.3 Final meeting held System input: Final meeting held Project Coordinator 1
CON 2.1 Investments reserved/ rejected or reserved with non-binding effect System input: Investment approved/ rejected/ reserved with non-binding effect Corporate Investment Controller
Approval of QG 2: Offer approval
PMT 1.1 Kick-off workshop held Document: Minutes of kick-off workshop Project Manager 0
PMT 1.2 Project plan approved Documents: Project timetable and project cost plan Project Manager 0
Q 2.1 Sampling coordination meeting held Document: Sampling coordination meeting Quality Pre-Planner 22
PRU 2.1 Capacity planning carried out System input: Capacity planning has been carried out Project Coordinator in the Test Laboratory 5, 21
Task packa- Result/partial result Precondition Responsibility APQP
ge number
EIN 4.2 Suppliers commissioned for raw materials System input: Order confirmations are booked in the system Project Buyer 6
EIN 3.2 Suppliers commissioned for indirect material System input: Order confirmations are booked in the system Project Buyer 7
IND 6.2 Design approval for indirect material Document: Design approval for indirect material (e-mail) Production Engineer 7
EIN 2.2 Suppliers commissioned for direct material System input: Order confirmations are booked in the system Project Buyer 6
EIN 2.3 Suppliers commissioned for purchased parts with supply System input: Purchased parts with supply commissioned Project Buyer 6
VER 5.1 Inventory numbers stored System input: Sales data for tools Project Coordinator
IND 6.3 Preliminary acceptance of indirect material performed Document: Acceptance report Production Engineer 7
EIN 2.4 Project orders for direct material delivered System input: Deliveries/incoming goods are booked in the system Project Buyer 6
Q 4.2 Process acceptance for suppliers of direct material completed Documents: Process acceptance report Quality Pre-Planner 6
SCM 2.2 Packaging planning/ container management completed Document: Packaging datasheets/ regulations Plant Container 17
Management Administrator
EIN 3.3 Project orders for indirect material delivered System input: Deliveries/incoming goods are booked in FOSS Project Buyer 7
Q 4.3 Direct material approved Document: EMPB direct material Quality Pre-Planner 6
IND 6.4 Tools, gages and operating resources accepted Document: Acceptance report approved Production Engineer 7
IND 8 Measuring system approved Documents: Measuring report, gage capability, MSA Production Engineer 14
IND 7 Production handover has taken place Document: Handover report Industrial Engineer 16, 25
PRO 1 Production readiness created Document: Checklist for production readiness, emergency plan Team Manager Production 24
EIN 4.3 Project orders for raw materials delivered System input: Deliveries/incoming goods are booked in the system Project Buyer 6
EIN 4.4 Series readiness of suppliers of raw materials created System input: Series readiness of suppliers has been created Project Buyer 6
EIN 2.5 Series readiness of suppliers of direct material created System input: Series readiness of suppliers has been created Project Buyer 6
PMT 2.2 QG 5 approved System input: Approve QG 5 Project Manager 0
Approval of QG 5: Approval of pre-series
PRO 2.1 Short-term process capability exists Document: Short-term process capability study Team Manager Production 20
| 39
5 | Preconditions for quality gates in capacity extension projects
EIN 3.4 Purchasing of all tools and equipment completed System input: All project orders for tools and equipment are completed Project Buyer 7
Q 5.1 Internal process acceptance completed Document: Process acceptance report Quality Pre-Planner 18
PMT 2.3 QG 6 approved System input: Approve QG 6 Project Manager 0
Approval of QG 6: Approval of series launch
PRU 3.1 Measuring report is available Document: Test report MW Project Coordinator in the Test Laboratory 21
PRU 3.2 Approved material and function report is available Document: EMPB_LAB Project Coordinator in the Test Laboratory 21
Q 2.2 EMPB sent Docent: EMPB Quality Pre-Planner 22
Q 5.2 Customer process acceptance completed Document: Customer-specific acceptance report Quality Pre-Planner 18
Q 2.3 Customer approval available Document: Customer approval Quality Pre-Planner 23
PRO 2.2 Long-term process capability exists Document: Long-term process capability study Team Manager Production 20
SCM 3 Launch coordination completed Document: Handover report KSC Launch Coordinator 25
VER 5.2 Customer project costs calculated System input: Status of tool costs or development and cancellation costs Project Coordinator 1
calculated
CON 3 Report after handover to plant is available Document: Target-actual comparison Participation Controller 0
PMT 3.1 Final report approved Document: Final report Project Manager 0
PMT 3.2 QG 7 approved System input: Approve QG 7 Project Manager 0
Approval of QG 7: Completion of project
Anfrage- Angebots-
Projekt Meilensteine MS1 freigabe MS2 MS3 MS4 MS5 Freigabe MS6
Application Engineer
EIN 5
Einkaufsumfänge
Projekteinkäufer geprüft und
optimiert
IND 3
Herstellkosten
Industrial Engineer ermittelt
Projektkoordinator
Prüflabor
SCM Projektmanager
WL 1
Angebotsgrundlage
Werksleitung freigegeben
Funtkion
CON 1
Wirtschaftlich-
Beteiligungscontroller keitsrechnung
erstellt
Anlaufkoordinator
| 41
6 | Preconditions for quality gates in global sourcing projects
Fig. 17:"Precondition for quality gates in global sourcing projects"
Task packa- Result/partial result Precondition Responsibility APQP
ge number
VER 1.1 Inquiry entered in the system System input: Inquiry generation Project Coordinator 1
VER 1.2 Inquiry decision taken System input: Statistical updating of the inquiry (processing approved or reject Project Coordinator 1
inquiry)
Approval of QG 1: Approval of pre-series
VER 2.1 Start inquiry processing System input: System cycle for inquiry Project Coordinator 1
EIN 5 Purchasing volumes checked and optimized System input: Purchasing volumes checked and optimized Project Buyer 6
IND 3 Manufacturing costs calculated Document: Calculation printout Industrial Engineer 1
VER 2.2 Lifetime is available Document: Lifetime Project Coordinator
CON 1 Profitability calculation prepared Document: DBRG "Project title“ + lifetime Participation Controller 1
WL 1 Offer basis approved System input: Offer basis approved Plant Manager 1
VER 2.3 Final meeting held System input: Final meeting held Project Coordinator 1
Approval of QG 2: Approval of offer
Application Engineer
Application Engineer
EIN 1 EIN 2.1 Lieferanten vorläufig EIN 3.1 Lieferanten EIN 2.2 Lieferanten für Direktes Material beauftragt EIN 2.3 Liefe- EIN 2.4 EIN 3.3 EIN 2.5 Serienbereitschaft der Lieferanten Direktes Material hergestellt EIN 3.4
Kosten
EIN 1 und nominiert
EIN für Direktes
2.1 Lieferanten Material
vorläufig vorläufi
EIN g nomi-
3.1 Lieferanten EINLieferanten
2.2 Lieferanten für DirektesMaterial
Materialbeauftragt
beauftragt ranten
EIN für Kaufteile
2.3 Liefe- Projektbestellungen
EIN 2.4 Projektbestellungen
EIN 3.3 EIN 2.5 Serienbereitschaft Einkaufsarbeiten
EIN 3.4
Projekteinkäufer niert für Indirektes
EIN 3.2 für Indirektes EIN 4.3 Projektbestellungen Rohstoffeder Lieferanten Direktes Material hergestellt
beliefert
Verfügbarkeiten
Kosten und nominiert für Direktesvorläufi
EIN 4.1 Lieferanten Materialg vorläufig nomi- mit Beistellung
ranten für Kaufteile Direktes Material
Projektbestellungen Indirektes Material
Projektbestellungen Indirektes Material
Einkaufsarbeiten
Projekteinkäufer ermittelt
Verfügbarkeiten nominiert
EIN für Rohstoffe
4.1 Lieferanten vorläufig Material
niert für Indirektes
EIN
EIN3.2
4.2Lieferanten
LieferantenfürfürIndirektes
RohstoffeMaterial beauftragt
beauftragt mitbeauftragt
Beistellung beliefertMaterial
Direktes beliefert Material
Indirektes
EIN 4.3 Projektbestellungen Rohstoffe beliefert
EIN 4.4 Serienbereitschaft der Lieferanten Rohstoffe hergestellt abgeschlossen
Indirektes Material
IND 1 ermittelt
IND 2 Kosten u. Liefertermine für nominiert für Rohstoffe Material EIN 4.2 Lieferanten für Rohstoffe beauftragt beauftragt beliefert beliefert IND 7 EIN 4.4 Serienbereitschaft der Lieferanten Rohstoffe hergestellt abgeschlossen
Arbeitssystem-
IND 1 Werkzeuge
IND 2 Kostenund Investitionen geplant
u. Liefertermine für Produktionsübergabe
IND 7
Industrial Engineer gestaltung
Arbeitssystem- Werkzeuge stattgefunden
Industrial Engineer INDund
3 Investitionen geplant Produktionsübergabe
abgeschlossen
gestaltung Herstellkosten ermittelt stattgefunden
IND 3
abgeschlossen Herstellkosten ermittelt PRU 2.1
Projektkoordinator Kapazitätsplanung
PRU 2.1
PRU 3.1 Messbericht liegt vor
Projektkoordinator
Prüflabor durchgeführt
Kapazitätsplanung PRU 3.1 Messbericht liegt vor
PRU 3.2 Freigegebener Werkstoff- und Funktionsbericht liegt vor
durchgeführt
Wirtschaftlich-
CON 1 Report
CON 3 nach
Beteiligungscontroller keitsrechnung
Wirtschaftlich- Übergabe
Report nachan
Beteiligungscontroller erstellt
keitsrechnung Standort an
Übergabe iegt vor
erstellt CON 2.1 CON 2.2 Standort iegt vor
Corporate Investitionen
CON 2.1 reserviert/ Investitionen
CON 2.2 verbindlich
Corporate
Investitionscontroller abgelehnt oder
Investitionen unver-
reserviert/ reserviert/ abgelehnt
Investitionen verbindlich
Investitionscontroller bindlich reserviert
abgelehnt oder unver- reserviert/ abgelehnt
Verantwortung Projektmanagement
IND 4.1 IND 6.1 IND 6.2 IND 6.3 IND 6.4 Werkzeuge, Lehren, Betriebsmittel abgenommen
P-FMEA erstellt Lastenhefte Betriebs- Konstruktionsfreigabe Vorabnahme
Produktionstechniker IND 5 mittel, Werkzeuge, Indirektes Material Indirektes Material
IND 4.2 Maßnahmen zur Prozess-FMEA abgeschlossen
PEP map
abgeschlossen
Sachbearbeiter SCM 2.2
Verpackungsplanung/
Administratives Behältermanagement
Behältermanagement Werk abgeschlossen
PRO 1 PRO 2.1 PRO 2.2
Produktions- Prozessfähigkeit Prozess-
Teammanager Produktion bereitschaft Kurzzeit liegt vor fähigkeit
hergestellt Langzeit
liegt vor
*RG = Reifegrad gem. VDA Kdbez. = Kundenbezeichnung Teilergebnis Ergebnis
| 43
8 | Change management
Changes may be made to both the Fig. 19: "Process description of change management“
product and the process. A change
occurs if either the design or the pro-
Change request external or internal need to send to project coordinator
duction method or the production Responsible: Change Initiator
plant changes during an existing se-
ries order. A change may be instigated VER 1.1 Adjust of the change request
Responsible: Project Coordinator
externally by the customer, by a sup-
plier or internally. The Project Control-
Change request
meeting
Change request meeting
ler is responsible for entering a change
QG1 What will change? Who will be affected? How we will go ahead?
both externally and internally. The fol- Responsible: Project Coordinator / Collaboration: Application Engineer, Startup coordinator,
Industrial Engineer, Project Manager, Advanced Quality Planner / Optional: Project buyer
lowing figure describes the process.
With effect from the planned date of yes Price the change request no
across-the-board?*
milestone 8 "Customer design freeze
carried out/ procurement approval
ENT 2 Manufacturability assessment Flow according specified
from customer received", but at the Responsible: Application Engineer Task Packages
Participant: Application Engineer, Industrial Engineer, Responsible Request phase: Project Coordinator
latest 3 months before SOP, no further Project Manager, Advanced Quality Planner / no Responsible Order phase: Project Manager
changes may be made to the product Optional: Project buyer Collaboration: Application Engineer, Industrial Engineer,
Project Manager, Advanced Quality Planner
or process. These changes must be Optional: Project buyer
Manufacturability assessment green?
entered, planned and implemented
yes
after SOP.
ENT 1.1 Component for RFQ defined and with proper status
Responsible: Application Engineer
9.1 Inquiry Committee The fixed dates for the milestones are monitored by In the event of problems or differences which endanger
means of a traffic light system: the customer offer date, the Project Coordinator is able
In future all inquiries corresponding to Veritas' product-
Green: In the inquiry cycle means the completed milestones- to escalate within three stages and request the required
market strategy will be submitted to the Inquiry Commit-
are reached on time. countermeasures. The following figure show the three-
tee by the Project Coordinator prior to the processing
Yellow: At least one completed milestone was not reached on stage escalation scenario.
cycle. The Committee meets daily and comprises man- time. The inquiry item can reach the status green again
agers from Sales, Development, Purchasing, Industriali- in the further course if a following milestone is com-
pleted on time.
zation and the respective works representatives..
Red: The milestone "Customer offer by" has been exceeded.
Step 2 Actions:
Deescalation
9.2 Escalation management Step 1 not effective or a second
» Project Coordinator informes the causative function and their superiors and their
own superiors about step 2.
from the inquiry to milestone has been exceeded » Causing functions announce actions and completion date up to 12:00 a.m. on the
following day to the Project Coordinator and the superiors.
customer commissioning » Project Coordinator checks, whether milestone “Offer done” is at risk. If yes,
additional actions must be done to meet the milestone.
| 45
9 | Committees and escalations
Participants Manager of Purchasing, Research & Development, Quality Management, Supply Chain
Management, Sales, Production Management, Project Management, Testing Laboratory,
Plant Manager, Board of Management; Escalation: increase to cause function
Main tools
Step 1 Actions:
» Send information to concerned project staff
Escalation reason causes problems » Agreed actions with appointments and timeline
during project process » Documentation in project status report/actions
Escalation
Deescalation
Step 2 Actions:
» Send information to concerned project staff and their superiors
Escalation reason causes a delay in » Agreed actions with appointments and timeline
customers target dates, deviations in » Documentation in project status report/actions
product quality and/ or project costs/ » There must be a communication towards the client
-revenues
Actions:
Step 3 » Send information to concerned project staff and their superiors
Escalation reasons causes critical » Agreed actions with appointments and timeline
impacts on customers target dates, » Documentation in project status report/actions
» Escalation to steering committee and showing the consequences
product quality and/or Project cost/-
» There must be a communication towards the client
revenues
| 47
10 | Key Performance Indicator (KPI) 11 | Internal project audits
A Key Performance Indicator is a value used to measure Fig. 23: "Magic triangle of project goals“
Internal project audits
the progress or the fulfillment level of important objec-
Performance
tives or critical success factors. Internal project audits are carried out four times a year
by the internal auditor. The objective of internal project
10.1 KPIs from the inquiry audits is to ensure process quality in PEP. The project
up to customer commissioning team is informed about the audits in advance. They are
carried out based on the PEP process description. In
During the inquiry/offer phase the ongoing and com- the event of deviations, measures are formulated with
pleted inquiry items are monitored by means of the the superior of the affected function holder, are sched-
defined milestones, see Chapter 9.2. The objectives of uled and are implemented by the auditor. Internal pro-
Costs Date ject audits ensure that the stipulated processes and the
this monitoring are to measure the level of adherence to
deadlines and show the deviations in order to instigate, required quality are permanently implemented.
if necessary, measures to improve performance. Mem-
bers of the Board of Management, the affected Heads This also normally ensures that the customer is satisfied.
of Division and Departmental Heads are informed about
monitoring of the defined milestones. If improvement The success of the project can only be evaluated if the
measures are necessary, they are initiated by the Head KPIs are clearly defined in advance and were planned
of the Sales Division by inviting the affected Heads of during the planning phase, see PMT 1.
Division to a coordination meeting.
During the course of the project, the project status re-
port provides information on the success of the project
10.2 KPIs from customer
and shows whether additional measures have to be initi-
commissioning up to ated in order to guarantee project success. The follow-
six months after SOP ing KPIs are analyzed in the project status report:
The detailed work package descriptions for each work package now follow according
Task Package: Description
to the sequence in the "functional structural plan". This chosen sequence is based on
the description of the process in the PEP map. Key data relating to the task package Position at April 5, 2016
From 5. Costs and delivery times for tools and investment VER 2.2.2 IND 2
Precondition for
Preconditions (Key documentation) Designation of the precondition result/ partial
activity number 6. Calculation / internal cost breakdown (CBD) VER 2.2.2 IND 3
result number
Optional: Determination of need for and group of
1. Customer inquiry data VER 1.1.1 Customer 7. VER 2.3.1 VER 1.2
participants in final meeting
8. Optional: Approval of offer basis VER 2.3.1 WL 1
Responsible
Partial results and activities Cooperation
person (Functions) Responsible
(Function)
Partial results and activities Cooperation
Global Account Key Account person (Functions)
Activity VER 1.1.1 Examine inquiry including preliminary decision analogous to product-market strategy (Function)
Manager Manager
Issue invitation to inquiry meeting (group of participants = Decision-Making
Global Account Key Account Activity VER 2.1.1 Account Manager
Activity VER 1.1.2 Forward inquiry to be entered to Project Coordinator Sales Committee)
Manager Manager
Hold inquiry meeting, clarify open topics, schedule inquiry processing analogous to Inquiry Processing
Activity VER 1.1.3 Record inquiry in the system and generate inquiry number Account Manager Activity VER 2.1.2 Account Manager
minutes and save it in the system Team
Partial result VER 1.1 Inquiry entered in the system I System input: Inquiry generation Activity VER 2.1.3 Enter minutes of inquiry meeting in the system and save the inquiry
Optional:
Account Manager
Activity
Decision on inquiry processing Yes/No analogous to product-market strategy,
VER 1.2.2 including system input of final inquiry categorization + input of reasons and committee Committee
Partial result VER 2.1 Start inquiry processing I System input: System cycle for inquiry
members in the system Activity VER 2.2.1 Prepare CBD Account Manager
Activity VER 1.2.3 Determine Inquiry Processing Team Committee Activity VER 2.2.2 Prepare lifetime and enter in the system with the designation "LT" Account Manager
Activity VER 1.2.4 Determine need for final meeting and, if necessary, nominate the meeting participants Committee Result VER 2.2 Lifetime is available I Document: Lifetime
Optional: "No" decision: Formulate and send rejection to customer. Then invalidate
Activity VER 1.2.5 Account Manager Optional:
inquiry in the system
Activity VER 1.2.6 Optional: "Yes" decision: Inform customer about offer preparation Account Manager Activity VER 2.3.1 Organize and hold final meeting according to the stipulations from activity VER 1.2.4 Account Manager
I
System input: Statistical updating of the inquiry (processing Take joint decision regarding further action:
Result VER 1.2 Inquiry decision taken
approved or reject inquiry) 1) Approve offer basis for further processing.
Activity VER 2.3.2 Final Meeting Team
2) Make minor optimizations of the offer basis and approve for further processing.
3) Stop inquiry. Index inquiry and renewed throughput.
Special risks (if required)
Optional
Result
VER 2.3 Final meeting held I System input: Final meeting held
Remarks (if required)
1. Which instance presents a new inquiry to the committee depends on the complexity. Special risks (if required)
| 49
12 | Annex Task package: Descriptions for each function holder
Optional: Results of task packages (CON 1, IND 1, Activity VER 4.1.3 Place project application via the system Account Manager
4. IND 2, IND 3, IND 7, ENT 1, ENT 2, EIN 2, EIN 3, VER 3.2.3 Various
LOG 1, PRU 1) Partial result VER 4.1 Project handed over to Project Manager
I Document: Series order
Result VER 3.3 Customer decision received I System input: System updating of inquiry in line with status
Special risks (if required)
Key data relating to the task package Position at April 5, 2016 Key data relating to the task package Position at April 5, 2016
Task package designation Invoice of customer project costs Task package designation Component definition
Person responsible for task package Person responsible for the task package
Account Manager Application Engineer
(Function)
(Function)
Task package team
Task package team CAD Designer
Project Buyer (Functions)
(Functions)
Project Coordinator in the Test Laboratory
Industrial Engineer
Pre-Developer / VE Simulation
Account Support
Project Coordinator
From
Precondition for Pre-Development Product Developer (VE-PE)
Preconditions (Key documentation) Designation of the precondition result/partial
activity number
result number From
Precondition for
1. Customer approval VER 5.1.11 Q 2.3 Preconditions (Key documentation) Designation of the precondition result/partial
activity number
result number
EIN 2.4
2. Photos of supplier's tools VER 5.1.10 1. Inquiry entered in the system ENT 1.1.1 VER 2.1
EIN 3.3
3. Photos of Veritas' tools VER 5.1.9 IND 6.4.4 2. Series order ENT 1.2 VER 4.1
Responsible Responsible
Cooperation Partial results and activities Cooperation
Partial results and activities person person (Functions)
(Functions)
(Function) (Function)
Update "sales data on tool costs" in the Veritas system after receipt of the series Project Coordinator Project Coordinator
Activity VER 5.1.1 Check customer inquiry data (customer inquiry drawing, 3D model, specifications,
order Sales Activity ENT 1.1.1 Application Engineer in the Test
send performance specifications to test circulate)
Laboratory
Activity VER 5.1.2 File customer series tool order in the Veritas system Project Support
Pre-Developer,
Activity VER 5.1.3 Confirm series tool order Project Support If necessary technical agreement with customer (inquiry drawing, 3D model, Project Coordinator
Activity ENT 1.1.2 Application Engineer
specifications, performance specifications) in the Test
Activity VER 5.1.4 Create system "Tooling Master Data" in the Veritas system Project Support Laboratory
Project Coordinator Check whether customer standards and general standards are available and up to
Activity VER 5.1.5 Create and schedule tool order Project Support Activity ENT 1.1.3 Application Engineer Project Coordinator
Sales date; if not, Sourcing through Project Coordinator
Activity VER 5.2.1 Update customer inventory number - customer's own tools in the Veritas system Project Support Create component in the system, create new project if necessary and link customer
Activity ENT 1.1.4 Application Engineer VE-PE
inquiry
Partial result VER 5.1 Customer inventory numbers stored
I System input: Sales data for tools Activity ENT 1.1.5 Create component parts list in the system and transfer in line with status Application Engineer
Mark customer's own tools used by Veritas according to customer's specifications Activity ENT 1.1.6 Drawing derivation from inquiry drawings (if required) CAD Designer Application Engineer
Activity VER 5.2.2 Industrial Engineer
(inventory sign) Project Coordinator
Mark customer's own tools used by supplier according to customer's specifications Activity ENT 1.1.7 Define development costs (duration) and enter in the system Application Engineer in the Test
Activity VER 5.2.3 Project Buyer Laboratory
(inventory sign)
Organize documentation (e.g. photos) of tools, operating resources and gages used Approve customer inquiry data (customer inquiry drawing, 3D model, specifications,
Activity VER 5.2.4 Industrial Engineer Activity ENT 1.1.8 Application Engineer
by Veritas, including inventory numbers, and file in the system performance specifications)
Organize documentation (e.g. photos) of tools, operating resources and gages used Activity ENT 1.1.9 Change inquiry status in the system Application Engineer
Activity VER 5.2.5 Project Buyer
by the supplier, including inventory numbers, and file in the system
I System input: Status "component defined"
Component defined for inquiry and in line with
Partial result ENT 1.1
Activity VER 5.2.6 Invoice customer tool costs according to customer agreement Project Support status
Optional: Project Coordinator Technical verification of customer data (send drawing or 3D data) according to offer
Activity VER 5.2.7 Project Support Activity ENT 1.2.1 status regarding commissioning status, send performance specifications to test Application Engineer
Invoice development costs analogous to customer's specifications Sales
circulate)
Optional: Project Coordinator
Activity VER 5.2.8 Project Support Activity ENT 1.2.2 If necessary, adapt customer data analogous to commission Application Engineer
Invoice cancellation costs analogous to customer's specifications Sales
I costs calculated
System: Status of tool costs or development and cancellation Obtain corrected customer data (drawing, specifications, performance specifications)
Result VER 5.2 Customer project costs invoiced Activity ENT 1.2.3 CAD Designer Project Coordinator
via customer portal and remote data transmission, and then ENT 1.2.1
1. Tool photos including inventory signs must be clearly legible as otherwise the customer will not approve invoice specification. Activity ENT 1.3.1 Optional: With new developments: Check / calculate design with prototypes Application Engineer VE Simulation
Check whether material / structure is free in the system, initiate ENT5 and
Activity ENT 1.3.2 Application Engineer Test Laboratory
requalification if necessary
Remarks (if required)
Check parts list in the system and readapt if necessary, correct customer drawing
Activity ENT 1.3.3 Application Engineer
N.B.: If the customer's inventory numbers - from the customer's perspective - have not been assigned up to subresult 5.1, the project may not be status and change parts status in the system
1.
stopped. The missing inventory numbers will be requested as quickly as possible.
I System input: Subject group in line with status in the system
Subject group of all components in line with
Partial result ENT 1.3
Inclusion of Sales if the customer's payments are not received by Financial Accounting. In this case Sales provides support by contacting the status in the system
2.
customer's Purchasing Department in order to speed up payment.
| 51
12 | Annex Task package: Descriptions for each function holder
Key data relating to the task package Position at April 5, 2016 Key data relating to the task package Position at April 5, 2016
Task package designation Producibility assessment Task package designation Design FMEA
Person responsible for the task package Person responsible for the task package
Application Engineer Application Engineer
(Function) (Function)
Partial result ENT 4.1 Document DVP created I System input: Status change (trigger mailing for tests) Activity ENT 5.1.5 Create material in the system Supplier Administrator VE-FGL
Material Developer
Activity ENT 5.1.6 Create mixtures in the system VE-PE/ VE-FGL
Activity ENT 4.2.1 Create internal order for production of test items Production Planner Administrator
Activity ENT 4.2.2 Create and instruct test order in the system Application Engineer Activity ENT 5.1.7 Approve structure in the system for calculation VE-PE Application Engineer
Project Coordinator in Activity ENT 5.1.8 Check plant drawing for application and approve for calculation VE-FGL Application Engineer
Activity ENT 4.2.3 Plan test pieces (if necessary, award externally) the Test Laboratory, Project Coordinator
Pre-Developer Activity ENT 5.1.9 Define development costs and duration, and enter in the system VE-PE/ VE-FGL in the Test
Activity ENT 4.2.4 Produce test pieces and provide them the Application Engineer Production Planner Laboratory
Task package designation Selection, commissioning and qualification of direct material for series production
Person responsible for the task package
Project Buyer
(Function)
Key data relating to the task package Position at April 5, 2016
Task package team
Purchased Parts Administrator
(Functions)
Task package number EIN 1
Application Engineer
Task package designation Determination of costs and analysis
Purchasing archiving employee
Person responsible for the task package
Project Buyer
(Function) Supply Chain Manager - Direct Material Planning
Task package team Supply Chain Coordination - Finished Parts Manager
Purchased Parts Administrator
(Functions)
Head of Project Purchasing Department
From
Precondition for
Preconditions (Key documentation) Designation of the precondition result/partial From
activity number Precondition for
result number Preconditions (Key documentation) Designation of the precondition result/partial
activity number
Component definition on account of parts list and result number
1. EIN 1.1 ENT 1.1
preliminary drawing (status 230) 1. Plant drawing (PLM status 114) EIN 2.1.3 ENT 1.4
2. Customer's inquiry data EIN 1.3 VER 1.1 2. Logistics concept EIN 2.1.3 SCM 1.1
3. Logistics concept due to packaging information EIN 1.5 SCM 1.1 3. Approved plant drawing (PLM status 230) EIN 2.2.1 ENT 1.5
Procurement approval by customer and
4. EIN 2.2.1 PMT 2.1
Responsible quantity and type of required parts up to SOP
Partial results and activities Cooperation
person (Functions)
5. Packaging datasheets of supplier EIN 2.2.1 SCM 2
(Function)
6. Customer's inventory numbers EIN 2.4.1 VER 5.1
Purchased Parts
Activity EIN 1.1 Risk analysis of market availability by already qualified suppliers or new suppliers Project Buyer
Administrator 7. Veritas' inventory numbers EIN 2.4.1 EIN 2.1
Activity EIN 1.2 Conclude necessary Non-Disclosure Agreements Project Buyer
8. Approved initial sample test reports EIN 2.5.1 Q 4.2
Define procurement strategy and opportunities (make-or-buy, dual sourcing, LCC,…)
Activity EIN 1.3 Project Buyer
per parts list component
Responsible
If possible: Calculate costs and volumes of similar components to validate own cost
Partial results and activities Cooperation
Activity EIN 1.4
calculation as a reference
Project Buyer person (Functions)
(Function)
Calculate costs and dates of components (if necessary, including tools and other
Purchased Parts
Activity EIN 1.5 subsequent costs over the lifetime) by means of internal purchasing tools or external Project Buyer Activity EIN 2.1.1 Change new components from "AXAL“ to purchasing subject group "Samples"
Administrator
inquiries with offer analyses
Activity If new supplier:
Activity EIN 1.6 Provide feedback on the result relating to costs and dates in the system Project Buyer
Activity EIN 2.1.2 Handle supplier approval process according to Purchasing Manual Project Buyer
Result EIN 1 Costs and availabilities calculated I System input: Costs and availabilities have been calculated Activity EIN 2.1.3
Agree original inquiry status with supplier and/or new inquiries must be sent, if
necessary, to supplier according to the Bid List
Project Buyer
Partial result EIN 2.2 Suppliers commissioned for direct material I System input: Order confirmations are booked in the system
Task Package: Description Task Package: Description
Key data relating to the task package Position at April 5, 2016 Key data relating to the task package Position at April 5, 2016
Task package designation EIN Selection, commissioning and qualification of tools and operating resources Task package designation Selection and commissioning of raw materials
Person responsible for the task package
Person responsible for the task package Project Buyer
Project Buyer (Function)
(Function)
Task package team
Task package team Purchasing archiving employee
Production Engineer (Functions)
(Functions)
Supplier Purchasing Administrator
Purchasing archiving employee
Raw Materials Purchasing Manager
Head of Project Purchasing Department
Head of Project Purchasing Department
From
Precondition for From
Preconditions (Key documentation) Designation of the precondition result/partial Precondition for
activity number Preconditions (Key documentation) Designation of the precondition result/partial
result number activity number
result number
1. Performance specifications EIN 3.1.2 IND 6.1 Project planning (due to general data and
1. EIN 4.1.2 PMT 1.2
Plant drawings (PLM status 114), for lightweight 3D quantities)
2. EIN 3.1.2 ENT 1.4
data sets with tolerances, etc. 2. Plant drawings (status 114) EIN 4.1.2 ENT 1.4
Quantity and type of off-tool parts, including delivery Quantity, dates and delivery location of the raw
3. EIN 3.2.4 PMT 2.1 3. EIN 4.2.1 PMT 2.1
materials required up until SOP
location and dates also for interface validation
Activity EIN 3.1.4 Confirmation of capacities from suppliers has been received Project Buyer Partial result EIN 4.2 Suppliers commissioned for raw materials I System input: Order confirmations are booked in the system
Activity EIN 3.1.5 Check completeness of offers and use this to make complete offer comparisons Project Buyer Monitor raw material orders up to complete fulfillment. Foreseeable changes in the
Activity EIN 4.3.1 Project Buyer
Head of Project procedure must be reported immediately to the Project Manager
Approve contract award proposal based on the offer comparisons produced by the
Activity EIN 3.1.6 Project Buyer Purchasing
I
Head of the Project Purchasing Department System input: Deliveries/ incoming goods are booked in the
Department Partial result EIN 4.3 Project orders for raw materials delivered
system
Activity EIN 3.1.7 Send provisional nominations to suppliers (e-mail, phone call, etc.) Project Buyer
Activity EIN 4.3.1 Completely fill systems according to Purchasing Manual for series deliveries Project Buyer
Enter supplier nomination (offer comparison and decision, if necessary with reasons) Check order confirmations for all orders, clarify deviations, feedback in the system and
Activity EIN 3.1.8 Project Buyer Supplier Purchasing
in the system Activity EIN 4.3.2 Project Buyer
file in the Easy archive Administrator
Activity EIN 3.2.3 Negotiate final conditions, place orders Project Buyer
Check order confirmations for all orders, clarify deviations, feedback in the system Purchasing archiving Special risks (if required
Activity EIN 3.2.4 Project Buyer
and file in Easy Archiv employee
If necessary, compare additional agreements (bank guarantees, transfer contract,
Activity EIN 3.2.5 down payment agreement) according to order and, if necessary, carry out invoice Project Buyer Remarks (if required)
approval workflow
1. Documents which also apply to activities: Purchasing Manual
Partial result EIN 3.2 Suppliers commissioned for indirect material I System input: Order confirmations are booked in the system 2. The approval process for new raw materials is described in the pre-development process
3. Re EIN 4.1.2: Plant drawings are required to determine the unit weights and inquire about the correct raw material quantities
4. Re EIN 4.2.1: The required eBMs are circulated by the Production Engineer | 55
12 | Annex Task package: Descriptions for each function holder
From
Precondition for
Preconditions (Key documentation) Designation of the precondition result/partial
activity number
result number
Key data relating to the task package Position at April 5, 2016
1. Component defined in line with status IND 1.1 ENT 1.1
Task package number EIN 5
2. Start inquiry processing IND 1.1 VER 2.1
Task package designation Checks on the whereabouts of the order
Responsible
Person responsible for the task package Partial results and activities Cooperation
Project Buyer person
(Function) (Functions)
(Function)
Task package team Activity IND 1.1 Agree processing with semi-finished products and deadline agreement Industrial Engineer
Supplier Purchasing Administrator
(Functions)
Activity IND 1.2 Examine drawings Industrial Engineer
Purchasing archiving employee Activity IND 1.3 Select suitable production methods Industrial Engineer
From Activity IND 1.4 Process Development must be commissioned for new production methods Industrial Engineer
Precondition for
Preconditions (Key documentation) Designation of the precondition result / partial Activity IND 1.5 Decide whether new P-FMEA is required or can be taken over from comparison parts Industrial Engineer
activity number
result number
Activity IND 1.6 Evaluate possible errors Industrial Engineer
Project planning (due to general data and
1. EIN 5.1 VER 1.1 Activity IND 1.7 Determine suitable test methods Industrial Engineer
quantities)
Activity IND 1.8 File P-FMEA in the document folder "Planning documents" Industrial Engineer
Result EIN 5 Purchasing volumes checked and optimized I System input: Purchasing volumes checked and optimized Activity
Activity
IND 1.20
IND 1.21
Prepare work plan taking account of (flow chart, MTM analysis, etc.)
File work plan in the document folder "Planning documents"
Industrial Engineer
Industrial Engineer
Activity IND 1.22 Determine space requirements Industrial Engineer
Special risks ((if required) Prepare a production layout
Activity IND 1.23 Industrial Engineer
Activity IND 1.24 File production system design (layout) in the document folder "Planning documents" Industrial Engineer
Remarks (if required)
Activity IND 1.25 Consider given means of production at the production plant Industrial Engineer
1. Documents which also apply to activities: Purchasing Manual Activity IND 1.26 Consider available means of production in the group Industrial Engineer
Activity IND 1.27 Consider P-FMEA Industrial Engineer
Activity IND 1.28 Formulate an emergency concept Industrial Engineer
Activity IND 1.29 File risk assessment (emergency plan) in the document folder "Planning documents" Industrial Engineer
Activity IND 1.30 Summarize all data in a folder (including completed checklist) Industrial Engineer
Activity IND 1.31 Enter data (partial results) in the system Industrial Engineer
Check data relating to sales parts and semi-finished products for completeness and
Activity IND 1.32 Industrial Engineer
summarize if necessary
Key data relating to the task package Position at April 5, 2016 Key data relating to the task package Position at April 5, 2016
Task package designation Tool/investment requirements Task package designation Calculation of manufacturing costs
Person responsible for task package Person responsible for task package
Industrial Engineer Industrial Engineer
(Function) (Function)
From From
Precondition for Precondition for
Preconditions (key documentation) Designation of the precondition result/partial Preconditions (Key documentation) Designation of the precondition result/ partial
activity number activity number
result number result number
1. Work system design completed IND 2.2 IND 1 1. Work system design completed IND 3.2 IND 1
2. Costs and availability have been calculated IND 3.2 EIN 1
Responsible
Partial results and activities Cooperation 3. Calculation of test costs entered IND 3.2 PRÜ 1
person (Functions)
(Function) 4. Component defined in line with status IND 3.1 ENT 1.1
Activity IND 2.1 Agree processing with semi-finished products and deadline agreement Industrial Engineer
5. Producibility assessment carried out IND 3.8 ENT 2
Activity IND 2.2 Adopt unit numbers from the inquiry Industrial Engineer
Activity IND 2.3 Adopt data from the work plan (times, rejects, batch size, etc.) Industrial Engineer Responsible
Partial results and activities Cooperation
Activity IND 2.4 Prepare capacity requirements list and store in the system for examination Industrial Engineer person (Functions)
(Function)
Activity IND 2.5 Check capacity availability Industrial Engineer
Activity IND 3.1 Agree processing with semi-finished products and deadline agreement Industrial Engineer
Determine tools and machines, including costs, taking account of the emergency
Activity IND 2.6 Industrial Engineer Preparation of calculation parts//projects in the system
concept Activity IND 3.2 Industrial Engineer
Activity IND 2.7 Costs must be obtained from Process Development with new production methods Industrial Engineer Activity IND 3.3 Summarize all input data (purchasing, development, testing) Industrial Engineer
Prepare time schedule taking account of the dependencies with subcomponents Activity IND 3.4 Perform calculation Industrial Engineer
Activity IND 2.8 Industrial Engineer
(average empirical values)
Activity IND 3.5 Check plausibility of calculation values (benchmark) Industrial Engineer
Activity IND 2.9 Enter tools and capital goods to be purchased, including costs, in the system Industrial Engineer
Check data relating to sales parts and semi-finished products for completeness and Activity IND 3.6 Generate calculation printout Industrial Engineer
Activity IND 2.10 Industrial Engineer
summarize if necessary Activity IND 3.7 Any other variants due to risk analysis (investment, unit number, etc.) Industrial Engineer
I
Costs and delivery dates planned for tools and System input: Technical data/details Check data relating to sales parts and semi-finished products for completeness and
Result IND 2 Activity IND 3.8 Industrial Engineer
investments Document: Capacity calculation summarize if necessary
| 57
12 | Annex Task package: Descriptions for each function holder
Result IND 7 Production handover has taken place I Document: Handover report
Special risks (if required)
1. Deviations must be shown and measures must be defined in the Project Team
Partial result PRU 2.1 Capacity planning carried out I System input: Capacity planning has been carried out
Responsible
Cooperation
Head of Test Laboratory Partial results and activities person (Functions)
Project Coordinator in Department (Function)
Activity PRU 2.2.1 Determine requirements for measuring equipment or test equipment
the Test Laboratory Test Laboratory Material Testing Test
Administrator Laboratory
Head of Test Laboratory Administrator
Activity PRU 3.1.1 Parts received by the Test Laboratory Measuring Systems
Project Coordinator in Department Team Manager
Activity PRU 2.2.2 Issue and circulate eBM for measuring and test equipment
the Test Laboratory Test Laboratory Production
Administrator Application Engineer
Head of Test Laboratory Measuring Systems
Project Coordinator in Division Activity PRU 3.1.2 Create document "Test report MW" in the PLM and change to status 605 Administrator Test
Activity PRU 2.2.3 Accept and put measuring and test equipment into operation
the Test Laboratory Test Laboratory Laboratory
Administrator Measuring Systems
PRU 3.1.3 Change document "Test report MW" in the PLM status 606 and process
I System input: Purchased measuring and test equipment available
Activity Administrator Test
Result PRU 2.2 Measuring and test equipment available Laboratory
Measuring Systems
Activity PRU 3.1.4 Measure parts based on stipulations in the customer drawing Administrator Test
Special risks (if required)
Laboratory
Measuring Systems
Remarks (if required) Activity PRU 3.1.5 Prepare measuring report Administrator Test
Laboratory
Head of Test
Activity PRU 3.1.6 Sign measuring reports Laboratory Department
Measuring Systems
Initial Sample
Measuring Systems
Processor Test
Activity PRU 3.1.7 Enter measuring report in the system Administrator Test
Laboratory
Laboratory
- Function Testing
Partial result PRU 3.1 Measuring report is available I Document: Test report MW
| 59
12 | Annex Task package: Descriptions for each function holder
From
Precondition for
Preconditions (Key documentation) Designation of the precondition result/partial Key data relating to the task package Position at April 5, 2016
activity number
result number
Task package number WL 1
1. Inquiry documents SCM 1.1.1
VER 1.1 Task package designation Approval of offer basis
2. Component definition SCM 1.1.1 ENT 1.1
Person responsible for task package
3. Packaging planning/container management SCM 1.3.1 SCM 2 Plant Manager
(Function)
Task package team
Industrial Engineer
Responsible (Functions)
Partial results and activities Cooperation
person (Functions) From
(Function) Precondition for
Preconditions (Key documentation) Designation of the precondition result/partial
For direct material and raw materials activity number
result number
Plan number of required containers, logistics FTEs, equipment, stocks and areas Plant Container
Activity SCM 1.1.1 (direct material & raw materials), incorporate 3PL if necessary; plan inbound SCM Project Manager Management 1. Lifetime WL 1.1 VER 2.2
transport Administrator Economic efficiency calculation
2. WL 1.1 CON 1
For semi-finished products / finished products (optional from €50,000.00)
Plan number of required containers logistics FTEs, equipment, stocks and areas Plant Production
Activity SCM 1.1.2 SCM Project Manager
(semi-finished products/finished products) Logistician Responsible
Plant Production Partial results and activities Cooperation
Activity SCM 1.1.3 Plan production supply concept SCM Project Manager person (Functions)
Logistician (Function)
For finished parts Activity WL 1.1 Check tool set-up for completeness as well as the manufacturing costs Industrial Engineer
Plan number of required containers, logistics FTEs, equipment, stocks and areas Head of Plant Check economic efficiency calculation and/or lifetime for completeness and that
Activity SCM 1.1.4 SCM Project Manager Activity WL 1.2 Plant Manager
(finished products), include 3PL if necessary, plan outbound transport Distribution Logistics specified target figures are not undershot
Activity WL 1.3 Approve offer basis in the system Plant Manager
Activity SCM 1.1.5 Prepare draft MiFA SCM Project Manager
Partial result SCM 1.1 Preparation of logistics concept I Document: Logistics concept Result WL 1 Offer basis approved I System input: Offer basis approved
Indirect Material
Activity SCM 1.2.1 Store logistics concept in the system to obtain offer (optional) SCM Project Manager
Administrator Special risks (if required)
Activity SCM 1.2.2 Examine offer documents (optional) SCM Project Manager
Calculate logistics costs based on the offers or estimated values after taking account
Activity SCM 1.2.3 SCM Project Manager Remarks (if required)
of the offer premises
Partial result SCM 1.2 Prepare calculation of logistics costs I Document: Calculation of logistics costs
Head of Plant
Activity SCM 1.3.5 Finalize MIFA based on the defined parameters and enter in the system SCM Project Manager
Distribution Logistics
60 | Veritas PEP Manual
Activity SCM 1.3.6 Hand over to plant 3 months after SOP SCM Project Manager
Task Package: Description
From
Precondition for
Preconditions (Key documentation) Designation of the precondition result/partial
Task Package: Description activity number
result number
1. Lifetime CON 1.1 VER 2.2
2. Calculation of logistics CON 1.1 SCM 1.2
Key data relating to the task package Position at April 5, 2016
Responsible
Task package number WL 2 Cooperation
Partial results and activities person (Functions)
Task package designation Investment approval (Function)
Person responsible for task package Activity CON 1.1 Adapt format template (DBRG, cash flow) Participation Controller
Plant Manager
(Function)
Activity CON 1.2 Copy sales data to template Participation Controller
Task package team
Production Engineer
(Functions)
Activity CON 1.3 Adopt tool costs, tool revenues, investments Participation Controller
Head of Corporate Investment Controlling (C-FiCoTax - I-CON)
Activity CON 1.4 Break down material costs per part Participation Controller
From
Precondition for
Preconditions (Key documentation) Designation of the precondition result/partial Break down, dynamize personnel costs per part
activity number Activity CON 1.5 Participation Controller
result number
1. Investment reservation WL 1.1 CON 2 Activity CON 1.6 Break down operating resources per part Participation Controller
2. Customer commissioning WL 1.1 VER 3.3 Activity CON 1.7 Adjust overhead formulas Participation Controller
Update KPIs from the economic efficiency calculation in the "Decision template for the
Special risks (if required) Activity CON 1.15 Participation Controller
Board of Management" in the lifetime
Result CON 1 Economic efficiency calculation produced I Document: DBRG "Project title“ + lifetime
Special risks (if required)
1. Calculations incorrect
3. Logistics calculations may not be available, which means that the economic efficiency calculation is only meaningful to a limited extent
| 61
12 | Annex Task package: Descriptions for each function holder
Key data relating to the task package Position at April 5, 2016 Key data relating to the task package Position at April 5, 2016
Task package designation Investment reservation Task package designation Project Controlling (Finance)
Person responsible for the task package Person responsible for the task package
Corporate Investment Controlling Manager (C-FiCoTax - I-CON) Participation Controller
(Function) (Function)
Responsible
Responsible Partial results and activities Cooperation
Cooperation person
Partial results and activities person (Functions)
(Functions) (Function)
(Function)
Activity CON 2.1.1 Check data, if necessary correct and concretize investment requirements C-FiCoTax - I-CON Activity CON 3.1 Book internal hourly settlement immediately for the project to the project cost center Project Team
Activity CON 2.1.2 Transfer to investment decision template for the Board of Management C-FiCoTax - I-CON Activity CON 3.2 Specify orders and external costs in conjunction with the project cost center Project Team
Activity CON 2.1.3 Submit decision template to the Board of Management C-FiCoTax - I-CON Activity CON 3.3 Target-actual comparison (automated) Participation Controller
I
Investments reserved/ rejected or reserved with System input: Investment approved/ rejected/ reserved with non-
Partial result CON 2.1 Check plausibility of ACTUAL figures
non-binding effect binding effect Activity CON 3.4 Participation Controller Project Manager
Optional with non-binding reservation: preparation of a decision template for the
Activity CON 2.2.1 C-FiCoTax - I-CON Activity CON 3.5 Enter report in the system Participation Controller
Supervisory Board
Activity CON 2.2.2 Submit the decision template to the Supervisory Board C-FiCoTax - I-CON
Result CON 3 Report after handover to plant is available I Document: Target-actual comparison
I System input: Investment approved/rejected
Investments reserved/ rejected with binding
Result CON 2.2
effect
Special risks (if required)
Special risks (if required)
Remarks (if required)
Remarks (if required) The task package extends beyond the project management observation period and ends with EOP. Only then is it possible and meaningful to
1.
make a final and extensive evaluation of the project
After it has been handed over to the plant, the report can only provide a target-actual comparison on account of the above-mentioned restrictions.
2.
Other KPIs (ROI, payoff, etc.) can of course be analyzed at the end of the project
From Responsible
Precondition for Cooperation
Preconditions (Key documentation) Designation of the precondition result/partial Partial results and activities person
activity number (Functions)
result number (Function)
Activity PMT 2.1.1 Prepare, carry out and document status meetings Project Manager Project Team
1. Project handover PMT 1.1.1 VER 4.1
Activity PMT 2.1.2 Update schedules in customer portals and prepare customer schedules if required Project Manager
Responsible Cooperation
Partial results and activities Activity PMT 2.1.3 Confirm maturity level stage 3 to customer
Advanced Quality Project Manager,
person (Functions) Planner Project Team
Head of Project
Activity PMT 1.1.1 Assign Project Manager to project Activity PMT 2.1.4 Carry out deviation analysis and introduce suitable measures Project Manager Project Team
Management Division
Check project application and generate specific project order, including draft of risk Activity PMT 2.1.5 Carry out escalation management if required Project Manager
Activity PMT 1.1.2 Project Manager Project Team
classification
Activity PMT 2.1.6 Carry out change management if required Project Manager Project Team
Activity PMT 1.1.3 Check PLM distribution list and produce project organigram if required Project Manager
Activity PMT 2.1.7 Document lessons learned in the parking area Project Manager Project Team
Head of Project
Activity PMT 1.1.4 Issue project order Activity PMT 2.1.8 Carry out risk management if required Project Manager Project Team
Management Division
Carry out planning of project costs and revenues in the system based on the input Activity PMT 2.1.9 Apply for quality gate Project Manager
Activity PMT 1.1.5 Project Manager
variables from the inquiry and offer phase
Activity PMT 1.1.6 Carry out project scheduling in the system Project Manager Partial result PMT 2.1 Quality gate 4 approved I System input: Approve QG 4
Activity PMT 1.1.7 Prepare and carry out start workshop Project Manager Project Team Advanced Quality Project Manager,
Activity PMT 2.2.1 Confirm maturity level stage 4 to customer
Planner Project Team
Activity PMT 1.1.8 In the start workshop: Plan required quantities during every stage of production Project Manager Project Team
Activity PMT 2.2.2 Carry out deviation analysis and introduce suitable measures Project Manager Project Team
Partial result PMT 1.1 Start workshop done I Document: Minutes of start workshop Activity PMT 2.2.3 Carry out escalation management if required Project Manager
Activity PMT 1.2.1 Risk Management Project Manager Project Team Activity PMT 2.2.4 Carry out change management if required Project Manager Project Team
Activity PMT 1.2.2 Finalize project cost and revenue plan and schedule Project Manager Activity PMT 2.2.5 Document lessons in the parking are Project Manager Project Team
Head of Project Activity PMT 2.2.6 Carry out risk management if required Project Manager Project Team
Activity PMT 1.2.3 Issue planning approval and therefore activate schedule
Management Division
Activity PMT 2.2.7 Apply for quality gate Project Manager
Result PMT 1.2 Project plan approved I Documents: Project timetable and project cost plan Partial result PMT 2.2 Quality gate 5 approved I System input: Approve QG 5
Advanced Quality Project Manager,
Activity PMT 2.3.1 Confirm maturity level stage 5 to customer
Special risk (if required) Planner Project Team
Activity PMT 2.3.2 Carry out deviation analysis and introduce suitable measures Project Manager Project Team
Remarks (if required) Activity PMT 2.3.3 Carry out escalation management if required Project Manager
Activity PMT 2.3.4 Carry out change management if required Project Manager Project Team
Activity PMT 2.3.5 Document lessons in the parking area Project Manager Project Team
Activity PMT 2.3.6 Carry out risk management if required Project Manager Project Team
Activity PMT 2.3.7 Apply for quality gate Project Manager
Activity PMT 3.1.6 Carry out risk management if required Project Manager Project Team Head of Project Project Manager,
Activity PMT 4.1 Assign Project Manager to project
Management Division Project Coordinator
Prepare and carry out final workshop to securing of know-how and complete the
Activity PMT 3.1.7 Project Manager Project Team Activity PMT 4.2 Carry out project scheduling in the system Project Manager Project Team
project, and document lessons learned
I
Project schedule prepared before
Head of Project Result PMT 4 Document: Project schedule
Activity PMT 3.1.8 Prepare final report and submit for approval Project Manager commissioning
Management Division
Partial result PMT 3.1 Final report approved I Document: Final report Special risks (if required)
Advanced Quality Project Manager,
Activity PMT 3.2.1 Confirm maturity level stage 7 to customer
Planner Project Team
Remarks (if required)
Activity PMT 3.2.2 Apply for quality gate Project Manager
Activity IND 4.2.1 Implement measures regarding process FMEA Production Engineer
Result IND 5 Flowchart produced I Document: Flowchart
Activity IND 4.2.2 Version and approve process FMEA in the system Production Engineer
Special risks (if required)
Result IND 4.2 Measures regarding process FMEA completed I Document: P-FMEA approved
Remarks (if required)
Special risks (if required)
1. Re 4.1.3 - With defined measures, the document must be approved "free with conditions"
| 65
12 | Annex Task package: Descriptions for each function holder
Task package designation Tools and operating resources - requirement specifications, acceptance, documentation
3. Suppliers commissioned for indirect material IND 6.2 EIN 3.2 Team Manager Production
4. Plant drawing approved IND 6.2 ENT 1.5 From
Precondition for
Preconditions (Key documentation) Designation of the precondition result/partial
5. Project orders for direct material delivered IND 6.3 EIN 2.4 activity number
result number
6. Project orders for raw materials delivered IND 6.3 EIN 4.3
1. Gage concept (performance specifications) IND 8.4 IND 6.1
7. Project orders for indirect material delivered IND 6.4 EIN 3.3
2. Production handover has taken place IND 8.3 IND 7
8. Direct material approved IND 6.4 Q 4.2
Responsible
Responsible Partial results and activities Cooperation
Cooperation person (Functions)
Partial results and activities person (Function)
(Functions)
(Function) Check measuring report from the supplier of the gages or the certificate of the
Activity IND 8.1 Production Engineer
Activity IND 6.1.1 Create objects in the system Production Engineer supplier of the test equipment, and enter in the system under the particular object
Assign objects in the system to the directly related product (automatic listing of tools Send information on the performance of gage capability or MSA to the responsible
Activity IND 6.1.2 Production Engineer Activity IND 8.2 Production Engineer
in the PLM tab "Tools" as a tool overview and test equipment list) Quality Coordinator
Activity IND 6.1.3 Produce parts-specific performance specifications (LH_II) (VA43) (tool status 114) Production Engineer Team Manager
Activity IND 8.3 Provide required series production components (e.g. 25 pieces) (see VA74) Quality Coordinator
Production
Activity IND 6.1.4 File performance specifications under the related objects in the system Production Engineer Team Manager
Activity IND 8.4 Examine capability of gages and/or measuring equipment (see VA74) Quality Coordinator
Team Manager Production
Activity IND 6.1.5 Agree performance specifications with Production Department Production Engineer
Production File documents - gage capability, MSA and measuring report - in the system relating
The gage concept must be provided to the Advanced Quality Planner for agreement Activity IND 8.5 Production Engineer
Advanced Quality to the tool (see VA74)
Activity IND 6.1.6 Production Engineer
with the customer Planner
Activity IND 6.1.7 Check and approve tool overview and test equipment list Production Engineer
Result IND 8 Measuring system approved I Documents: Measuring report, gage capability, MSA
I
Requirement specifications for operating Document: Performance specifications,
Partial result IND 6.1
resources, tools and gages produced System inputs: "List of tools, "Test equipment list" complete
Special risk (if required)
Activity IND 6.2.1 Generate purchase requisition in the system (tool status 114) Production Engineer
Activity IND 6.2.2 Send the approved plant drawing (tool status 230) Production Engineer Application Engineer
Remarks (if required)
Activity IND 6.2.3 Check the supplier's design for indirect material Production Engineer
Activity IND 6.2.4 Approve the supplier's design for indirect material Production Engineer 1. MSA = Measuring system analysis
Partial result IND 6.2 Design approval for indirect material I Document: Design approval for indirect material (e-mail)
Define components without a function (stereolithography, 3D printing, machined parts) Appl. Engineer
Activity IND 6.3.1 Production Engineer
regarding their unit number and design, and trigger eBM or work order Internal Tool Maker
Production Planner
Activity IND 6.3.2 If necessary, inspect components Production Engineer
Sample Construction
Production Planner
Activity IND 6.3.3 Supply received components to supplier or internally Production Engineer
Sample Construction
Activity IND 6.3.4 Agree date for tool acceptance Production Engineer Project Buyer
Carry out tool acceptance (construction progress control) at the supplier according to
Activity IND 6.3.5 Production Engineer
VA43
Activity IND 6.3.6 Prepare acceptance reports and enter in the system "with conditions approved" Production Engineer
66 | Veritas PEP Manual
I Document: Acceptance report
Preliminary acceptance of indirect material
Partial result IND 6.3
performed
Task Package: Description
Partial result Q 1.1 QM plan for prototypes prepared I Document: QM plan for prototypes Activity
Activity
Q 2.2.3
Q 2.2.4
Define test quantities for initial sample tests
Create initial sample order for semi-finished products in the system
Application Engineer
Initial Sampler
Advanced Quality
Activity Q 1.2.1 Revise or prepare QM plan for pre-series production Project Team Activity Q 2.2.5 Perform initial sampling of semi-finished products and make available Initial Sampler
Planner
Advanced Quality Activity Q 2.2.6 Prepare initial sampling of sales parts (check documentation) Initial Sampler
Activity Q 1.2.2 Enter family QM plan for pre-series production in the system
Planner Calculate weight of sales part and enter value in the PLM
Activity Q 2.2.7 Initial Sampler
Partial result Q 1.2 QM plan for pre-series production prepared I Document: QM plan for pre-series production Activity Q 2.2.8
Carry out initial sampling Note 1, compile documentation and enter in customer
portals and the PLM
Initial Sampler
Advanced Quality Activity Q 2.2.9 Enter EMPB in the system Initial Sampler
Activity Q 1.3.1 Prepare QM plan for series production in SCIO
Planner
Pack initial sample parts, if necessary incl. documentation, to customer and make
Advanced Quality Activity Q 2.2.10 Initial Sampler
Activity Q 1.3.2 Enter QM plan for series production as a PDF file in the system available for dispatch
Planner
Result Q 1.3 QM plan for series production prepared I Document: QM plan for series production Partial result Q 2.2 EMPB sent I Document: EMPB
Activity Q 2.3.1 Change (approve) status of sales part in the system Application Engineer
Activity Q 2.3.2 Monitor and maintain status of sampling Initial Sampler
Special risks (if required)
Activity Q 2.3.3 Obtain series approval and approve in the system Initial Sampler
Remarks(if required) Result Q 2.3 Customer approval received I Document: Customer approval
| 67
12 | Annex Task package: Descriptions for each function holder
Key data relating to the task package Position at April 5, 2016 Project Buyer
From
Task package number Q3 Precondition for
Preconditions (Key documentation) Designation of the precondition result/partial result
activity number
Task package designation Test and gage concept number
Person responsible for task package 1. Approved Veritas drawing Q 4.1 ENT 1.5
Advanced Quality Planner
(Function)
2. Initial sample order Q 4.1 EIN 2.4
Task package team
Production Engineer 3. Initial sample parts Q 4.1 EIN 2.4
(Functions)
I
System input: Gage concept agreed/ Advanced Quality Project Buyer / Supplier
Result Q3 Test and gage concept agreed with customer Activity Q 4.1.7 Quality Assurance Agreement if necessary
customer informed (change of status) Planner Integration
Advanced Quality
Activity Q 4.1.8 Process acceptance (if required) Application Engineer
Planner
Special risks (if required)
I Document: QVP checklist for direct material
Advanced quality planning of direct material
Partial result Q 4.1
completed
Advanced Quality Application Engineer /
Remarks (if required) Activity Q 4.2.1 Process acceptance (if required)
Planner Project Buyer
Key data relating to the task package Position at April 5, 2016 Key data relating to the task package Position at April 5, 2016
Partial result Q 5.1 Internal process acceptance completed I Document: Process acceptance report Result Q6 CCC printing license is available I Documents: CCC printing license, CCC certificate
Advanced Quality
Activity Q 5.2.1 Agree customer acceptance/audit
Planner
Special risks (if required)
Advanced Quality
Activity Q 5.2.2 Manage customer acceptance/audit
Planner
Advanced Quality Remarks (if required)
Activity Q 5.2.3 Coordinate deviation management
Planner
Advanced Quality
Activity Q 5.2.4 Enter customer-specific acceptance report in the system
Planner
Result Q 5.2 Customer process acceptance completed I Document: Customer-specific acceptance report
Special risks (if required)
1. Deviations are documented and monitored via the database "Task monitoring".
| 69
12 | Annex Task package: Descriptions for each function holder
Key data relating to the task package Position at April 5, 2016 Key data relating to the task package Position at April 5, 2016
Responsible Responsible
Partial results and activities Cooperation Cooperation
person (Functions) Partial results and activities person
(Function) (Functions)
(Function)
Application Engineer
Advanced Quality
Advanced Quality / Project Coordinator Activity Q 8.1 Collate information Project Team
Activity Q 7.1 Formulate and sign draft of defective part analysis concept Planner
Planner in the Test
Laboratory Advanced Quality
Activity Q 8.2 Enter information in the customer portal Project Team
Planner
Advanced Quality
Activity Q 7.2 Make defective part analysis concept available to the customer
Result Q7 Defective part analysis concept agreed I Document: Defective part analysis concept Remarks (if required)
Project Buyer
Task Package: Description
From
Precondition for
Preconditions (Key documentation) Designation of the precondition result/partial
activity number
result number
1. Calculation of logistics costs SCM 2.1.1 SCM 1.2 Key data relating to the task package Position at April 5, 2016
Activity SCM 2.2.3 If necessary, validate investment costs or additional costs for packaging & handling
Plant Container
Management
SCM Project
Manager
Result PRO 1 Production readiness created I Document: Checklist for production readiness, emergency plan
Administrator
Plant Container
SCM Project
Activity SCM 2.2.4 Approve and sign packaging datasheet Management
Manager
Special risks(if required)
Administrator
Plant Container
Prepare required eBMs for circulated quantities of packaging and place in the approval
Activity SCM 2.2.5
cycle (optional)
Management Remarks (if required)
Administrator
Packaging datasheet of customer
Plant Container
Examine offer documents (especially calculation of logistics costs) in regard to SCM Project
Activity SCM 2.2.6 Management
packaging of sales parts Manager
Administrator
Plant Container
SCM Project
Activity SCM 2.2.7 Validate different packaging with customer Management
Manager
Administrator
Plant Container
SCM Project
Activity SCM 2.2.8 Confirm packaging datasheet of the customer Management
Manager
Administrator
Plant Container
If necessary, validate investment costs or additional costs for packaging & handling SCM Project
Activity SCM 2.2.9 Management
(optional) Manager
Administrator
Plant Container
Prepare required eBMs for circulated quantities of packaging and place in the approval
Activity SCM 2.2.10 Management
cycle (optional)
Administrator
Plant Container | 71
SCM Project
Activity SCM 2.2.11 Prepare packaging instructions and store in the system Management
Manager
Administrator
12 | Annex Task package: Descriptions for each function holder
Key data relating to the task package Position at April 5, 2016 Key data relating to the task package Position at April 5, 2016
Task package designation Process capability study Ask package designation Launch Coordination
Person responsible for task package Person responsible for task package
Team Manager Launch Coordinator
(Function) (Function)
DSK (Decentral Master Data and Capacity Management) Plant Planning Manager Finished Parts
Activity PRO 2.2.1 Include and perform 2000:0 check in the work plan DSK Team Manager Result SCM 3 Launch coordination completed I Document: Handover report KSC
Activity PRO 2.2.2 Remove parts from series production on a random basis QK Team Manager
Production
Activity PRO 2.2.3 Produce performance analysis DSK Special risks (if required)
Engineering
Activity PRO 2.2.4 Carry out long-term process capability study (Cpk) QK Team Manager
Activity PRO 2.2.5 Remove 2000:0 check from the sytems (work palm) DSK Team Manager Remarks (if required
Activity PRO 2.2.6 Enter document "Long-term process capability study" in the system Team Manager DSK
Result PRO 2.2 Long-term process capability exists I Document: Long-term process capability study
Special risks (if required)
The following figure "Key documents in PEP, arranged in alphabetical order", is an Key document Task Responsibility APQP
package
overview of all key documents in alphabetical order and the corresponding assign- number.
ment to the task packages and function holders. If templates for the key documents Calculation of logistics costs SCM 1 SCM Project Manager 17
are possible, they can be found in the PLM system under the menu item "§Forms". Measuring report IND 8 Production Engineer 14
MSA IND 8 Production Engineer 14
Key document Task Responsibility APQP Emergency plan PRO 1 Team Manager Production 24
package
number P-FMEA IND 4 Production Engineer 13
Acceptance report IND 6 Production Engineer 7 Project cost plan PMT1 Project Manager 0
Final report PMT 3 Project Manager 0 Project timetable PMT1/4 Project Manager 0
Sampling coordination meeting Q2 Quality Pre-Planner 22 Process acceptance report Q4 Quality Pre-Planner 6
Documents: CCC printing license, CCC certificate Q6 Quality Pre-Planner 2 Minutes of kick-off workshop PMT 1 Project Manager 0
Checklist for production readiness PRO 1 Team Manager Production 24 Short-term process capability study PRO 2 Team Manager Production 20
Checklist for QVP for direct material Q4 Quality Pre-Planner 6 Long-term process capability study PRO 2 Team Manager Production 20
DBRG "Project title“ + lifetime CON 1 Participation Controller 1 Test report MW PRU 3 Project Coordinator in the Test Laboratory 21
EMPB direct material Q4 Quality Pre-Planner 6 QM plan for series production Q1 Quality Pre-Planner 19
EMPB_LAB PRU 3 Project Coordinator in the Test Laboratory 21 QM plan for pre-series production Q1 Quality Pre-Planner 15
Flowchart IND 5 Production Engineer 12 Defective part analysis concept Q7 Quality Pre-Planner 20
Producibility assessment ENT 2 Application Engineer 11 Series order VER 4 Project Coordinator 1
Calculation printout IND 3 Industrial Engineer 1 Target-actual comparison CON 3 Participation Controller 0
Customer approval Q2 Quality Pre-Planner 23 Handover report IND 7 Industrial Engineer 16, 25
Customer-specific acceptance report Q5 Quality Pre-Planner 18 Handover report KSC SCM 3 Launch Coordinator 25
| 73
12 | Annex Glossary
| 75
Imprint
Publisher: Veritas AG, Stettiner Strasse 1-9, 63571 Gelnhausen
veritas@veritas.ag
Texts: Jörg Becker, Melanie Brandes, Ronny Frotscher, Jörg Hapli, Mayra Herrero Calleja,
Michael Kurtze, Alexandra Röder, Mohammed Siala, Manuela Stichel, Carina Strauch,
Manuel Uftring, Alexander Wimmer, Roland Zahn, Marcus Zuther
Layout: Marcus Brandes, brandesmedia mediengestaltung