Professional Documents
Culture Documents
TECHNICAL SPECIFICATION
FOR
CIVIL WORKS ETP STP
Consultant: SILT-MOONLIGHT-EVERSAFE JV
Kathmandu
MCICDC
Technical Specification- Civil 2
Table of Contents
1. INTRODUCTION 8
2. GENERAL 9
2.1 Bill of Quantities (BOQ) 9
2.2 Project information BOARDS 9
2.3 project safety measures 9
2.4 DRAWINGS, INSTRUCTIONS, AND MEASUREMENTS 9
2.5 CLEARING THE SITE 10
2.6 TREES 10
2.7 MEASURING MATERIALS 10
2.8 TEMPORARY PROTECTION 10
2.9 QUALITY OF WORK 10
2.10 LEAVE CLEAN 10
2.11 SAMPLES 10
2.12 PROVISIONAL ITEMS 12
2.13 STORAGE 12
2.14 CONTRACTOR'S LABORATORY Error! Bookmark not defined.
2.15 WATER SUPPLY AND POWER SUPPLY 12
2.16 MEDICAL ARRANGEMENTS 13
2.17 LATRINES 13
2.18 NOTICE OF OPERATIONS 13
2.19 SURVEY AND DATUM FOR LEVELS 13
2.20 SUPPLY OF FUEL OILS 13
2.21 ASSISTANCE OF ENGINEERS 14
2.21.1 Meetings and Reports 14
2.21.2 Photographs 14
2.21.3 Contractor's Campus, Workshop, Stores, Offices etc. 15
2.21.4 Scaffolding, ladder etc. for Inspection 15
2.21.5 Site Office, Stationary, Furniture, Equipment, etc. 15
2.21.6 Survey Equipment for the Engineer 15
3. MATERIALS 16
3.1 SOURCES 16
3.2 INSPECTION AND ACCEPTANCE OF MATERIALS 16
3.3 SAMPLES AND TESTS 16
3.4 DEFECTIVE MATERIALS 17
3.5 TRADE NAMES AND ALTERNATIVES 17
3.6 FOREIGN MATERIALS 17
4. CONTRACT DOCUMENTS 18
MCICDC
Technical Specification- Civil 3
5. EARTHWORK 19
5.1 EXCAVATIONS 19
5.2 TIMBERING OF FOUNDATIONS/RAFTS 19
5.3 SHORING AND PROTECTION 20
5.4 DE-WATERING 20
5.5 TRIMMING AND LEVELING 20
5.6 DISPOSAL 20
5.7 MEASUREMENT 20
5.7.1 Measurement 21
5.8 SITE CLEARANCE BY REMOVAL OF GRASS, SHRUBS ETC. 21
5.8.1 Measurement 21
5.9 Filling In Plinth With Materials Brought From Outside 21
5.9.1 Materials 21
5.9.2 Measurement 21
5.10 Filling In GROUND For Land development With Materials Brought From Outside
(DOR NORMS Spec. cl. No: 909 & 910) 22
5.10.1 Compaction of Area of Back fill 22
5.10.2 Compaction Trails 23
5.10.3 Process Control 24
5.10.4 Measurement 24
5.10.5 Payment 25
5.11 SAND FILLING 25
5.11.1 Scope 25
5.11.2 Material and workmanship 25
5.11.3 Measurement 25
5.12 Compacted Fill, granular fill beneath SLABS, FOOTINGS, RAFT 26
5.12.1 Scope 26
5.12.2 Backfill in Plinth of Building and Building Premises 26
5.12.3 Common Backfill in Structures 26
5.12.4 Measurement 26
6. POLYTHENE SHEET 27
6.1 Scope 27
6.2 Measurement 27
7. CONCRETE WORK 27
7.1 PLAIN CEMENT CONCRETE (PCC) work 27
7.1.1 Materials 27
7.1.2 Mixing 27
7.1.3 Laying 27
7.1.4 Curing 27
7.1.5 Measurement 28
7.2 REINFORCED CEMENT CONCRETE (RCC) WORKS 28
7.2.1 General 28
7.2.2 Materials 28
7.2.3 Concrete Admixture 30
7.2.4 Measurement and Proportioning of Concrete Materials 31
7.2.5 Properties of Concrete 31
7.2.6 Control of Concrete 32
MCICDC
Technical Specification- Civil 4
8. MASONRY WORK 45
8.1 ONE OR MORE THAN ONE BRICK THICK (CHIMNEY MADE) 45
8.1.1 Bricks 45
8.2 Workmanship 46
8.3 Measurements 46
8.4 HALF BRICK THICK 46
8.4.1 Laying of Bricks 46
8.4.2 Mortar 46
8.4.3 Measurement 47
8.5 FLAT BRICK SOLING 47
8.5.1 Measurement 47
8.6 Machine Made bricks 47
8.7 Chimeny made brick 47
8.8 stone masonary 47
8.8.1 Mortar 48
8.8.2 Construction 48
8.8.3 Test and Standard of Acceptance 49
8.8.4 Measurement 50
8.8.5 Payment 50
8.9 Crushed Stone filling works 50
8.9.1 Stones 50
8.9.2 Sand 50
8.9.3 Laying and Compaction 50
8.9.4 Measurement 50
8.10 Stone soling work 50
8.10.1 Stones 50
8.10.2 Sand 51
8.10.3 Laying and Compaction 51
8.10.4 Measurement 51
9. FLOORING 51
9.1 Plain cement concrete 51
9.1.1 Preparation of Base 51
9.1.2 Proportion 51
9.1.3 Placing 51
9.1.4 Finishing 51
MCICDC
Technical Specification- Civil 5
9.1.5 Measurement 52
9.2 Skirting 52
9.2.1 Cement skirting 52
9.2.2 Mortar 52
9.2.3 Measurement 52
9.3 Cement punning 52
9.4 Measurement: 52
10.1 cement PLASTERING WALLS 52
10.1.1 Materials 53
10.1.2 Measurement 53
10.2 Plastering Soffits of Slabs and independent concrete surface 53
10.2.1 Measurement 54
12. PAINTING 54
12.1 Applying priming coat of approved brand 54
12.1.1 Preparation 54
12.1.2 Application 55
12.1.3 Measurement 55
12.2 Wall putty 55
12.2.1 Materials 55
12.2.2 Application 55
12.2.3 Measurement 56
12.3 Water Proof Cement Painting 56
12.3.1 Materials 56
12.3.2 Application 56
12.3.3 Measurement 56
12.4 plastic emulsion Painting (Interior) 56
12.4.1 Materials 56
12.4.2 Application 57
12.4.3 Measurement 57
12.5 Enamel Painting 57
12.5.1 Materials 57
12.5.2 Preparation of surface 57
12.5.3 Application 57
12.5.4 Measurement 57
12.6 plastic emulsion paint (exterior) 57
12.6.1 Materials 58
12.6.2 Application 58
12.6.3 Measurement 58
12.7 Frech/chapra polish 58
12.7.1 Materials 58
12.7.2 Preparation of surface 58
12.7.3 Application 58
12.7.4 Measurement 59
MCICDC
Technical Specification- Civil 6
13. ROOFING 70
13.1 STEEL TUBULAR TRUSSES AND PURLINS 70
13.1.1 Material 70
13.1.2 Fabrication 70
13.1.3 Bolting 70
13.1.4 Sealing to Tubes 70
13.1.5 Flattened Ends 70
13.1.6 Erection 70
13.1.7 Painting 71
13.1.8 Measurement 71
13.2 CGI Roofing Sheet 71
13.2.1 Quality 71
13.2.2 Laying and Fixing 71
13.2.3 Ridges and Hips 71
13.2.4 Measurement 72
13.3 Rain water gutter 72
13.3.1 Quality 72
13.3.2 Measurement 72
15. MISCELLANEOUS 75
15.1 Metal (Mild Steel-MS) grating 75
15.1.1 Measurement 75
15.2 BOUNDARY WALL USING MS GRILLS/ sQUARE HOLLOW PIPES 75
15.2.1 Materials 75
15.2.2 Installation 76
15.2.3 Measurement 76
15.3 BOUNDARY WALL USING MS Angle, post, gi mesh and Fence wire 76
15.3.1 Installation 76
15.3.2 Measurement 76
15.3.3 Payment 76
15.4 Lift Error! Bookmark not defined.
MCICDC
Technical Specification- Civil 7
MCICDC
Technical Specification- Civil 8
TECHNICAL SPECIFICATIONS
A. CIVIL WORKS
1. INTRODUCTION
a. The work shall be carried out according to the specifications whether specifically mentioned in it or
not. No extra in any form shall be paid unless it is definitely stated as an item in the bill of
quantities. Whenever the specifications are not given or ambiguous, the relevant Indian Standard
and further amendments or decision of the Engineer shall be considered as final and binding.
b. The civil works shall be carried out simultaneously with the electrical, plumbing, sanitary and other
services and in co-operation with the Contractors, if any, of the above services. The work shall be
carried on till it is completed satisfactorily. The Contractor shall keep the other Contractors
informed well in advance of the program of the work so that the proposed work is not hindered.
The Contractor shall further cooperate with other Contractors, if any, in respect of any facilities
required by them e.g., making holes in shuttering for pipes, electric conduits, fan hooks etc.
However, nothing extra shall be admissible to him for such reasonable assistance and facilities
afforded to other Contractors and the Contractor shall be deemed to have taken these factors into
consideration while quoting his rates.
c. The work shall be related to the drawings, which the Contractor is presumed to have studied.
Nothing extra will be paid for any item on its shape, location or other difficult circumstances, even
if the schedule makes no distinction as long as the item is shown in the drawings.
d. The sources of materials if stated in the specifications are for guidance only and are those from
which materials may generally be available. However, materials not conforming to specifications
shall be rejected even if they come from the stated sources. The Contractor should satisfy himself
that sufficient quantity of materials of acceptable specification is available from the stated or other
sources.
h. The most of the items are same in BOQ for all the buildings, so if the Contractor has quoted the
different prices for the same item within single contract, the minimum quoted price shall be taken
into account for all purposes by the Client/Engineers for further action whenever required.
2. GENERAL
2.6 TREES
No trees shall be cut without the permission of the Engineer. If trees have to be cut, this shall form an extra
item. For the purpose of the specification, a tree shall be defined as that having circumference of the trunk
not less than 900mm measured at 300 mm height from the existing Ground at trunk.
MCICDC
Technical Specification- Civil 10
2.11 SAMPLES
Samples of materials required for use in works shall be submitted by the Contractor for the approval of the
Engineer and after such approval these samples shall be deposited at secure place instructed by the
Engineer. The Contractor will acquire the materials as per these approved samples.
The tests to be carried out and their frequency for the quality control of the works are detailed in the
relevant Sections of these Specifications.
The following Table recapitulates the testing schedule for the main types of works.
Part or
component of Tests Frequency
the works
Concrete cement: acceptance tests: Conservative samples for
Materials Control tests: chemical composition physi- each supply and not less than
cal every 200t or part of it.
properties testing in case of non
MCICDC
Technical Specification- Civil 11
aggregates:
compliance of the mixes or
acceptance tests:
storage on site for longer than 1
Control tests:
month
Grading
each delivery and every 100 t or
Silt & clay content
part of it for fine aggregate and
Organic impurities
250 t or part of it for coarse
Chloride content, sulphate content, Alkali
aggregate
reactivity
As frequently as required.
water, admixtures
early works: every 6 m3 of
Concrete • lab. Trials • site trials • each class. When compliance
control tests compressive strength is established: every 20 m3 or
part of it.
Reinforcement:
quality of bricks
Brickworks for as required
quality of cement and sand
structures every 10 m3of brick work or
control tests compressive strength of
Materials mortar part of it.
mortar
as required
Masonry for quality of cement and sand
every 10m3 of masonry of part of
structures control tests compressive strength of
it
materials mortar
every 30m3 of masonry or part of
Mortar dismantling of masonry (1 m_1 m)
it
(i) They might affect the stability or safety of the works or adjacent property;
(ii) They might interfere with natural or artificial drainage or irrigation;
(iii) They may be environmentally unsuitable.
The Contractor shall not purchase or receive any borrow materials from private individuals unless the
source of such materials has been approved by the Engineer. At least 14 days before he intends to
commence opening up any approved borrow pit or quarry, the Contractor shall submit to the Engineer his
intended method of working and restoration. These shall include but not be limited to:
MCICDC
Technical Specification- Civil 12
2.15 STORAGE
Safe, dry and properly covered storage place shall be provided by the Contractor for all materials,
particularly for cement. The capacity of the cement storage go downs shall be minimum 500 bags stored at
each work site.
The contractor shall make his own arrangement for the supply of water, including portable water, for the
purpose of construction and consume by workers. The quality of the water shall be to the approval of the
engineer and suitable for the purpose for which it is intended.
Waste water shall be disposed of clear of the site to the satisfaction of the Engineer so as to cause no
damage or nuisance to the Environment and the surrounding areas.
The contractor shall make his own arrangements for the supply of electric power for the purposes of the
construction works.
The contractor shall make arrangements for treatment on the site of casualties and sick persons in first-aid
units or in such other wards as may be necessary in accordance with the appropriate regulations.
Notwithstanding the minimum requirements prescribed above, the Contractor shall be responsible for the
adequacy of all the arrangements made as per the provisions of the Contract.
2.18 LATRINES
The Contractor shall provide throughout the period of construction of the Works and shall maintain and
clean suitable and sufficient latrines for use by his employees; he shall ensure that his employees do not
foul the site but make proper use of the latrines. Sufficient water must be provided and maintained in the
toilets. Proper methods of sanitation and hygiene should be employed during the whole project duration
The contractor shall give full and complete written notice of all-important operations including setting out
to the Engineer sufficiently in advance to enable the Engineer to make such arrangements as the Engineer
may consider necessary for inspection and for any other purpose. The Contractor shall not start any
important operation without the written approval of the Engineer.
Prior to the start of the Works the Contractor will receive from the Employer a list of Project Beach Marks
and their values reference on the site.
Thereafter, the Contractor shall establish all setting out necessary for the performance of the work, to the
approval of the Engineer including levels of the original ground surface at the Site and final surveys of the
completed works for the final measurement. Levels shall close within 2.4 mm times the square root of the
length of the circuit in km.
Ground levels shall be taken jointly by the contractor and the Consultant's Representative both prior to
commencing and after completion of earthworks.
Where cross sections are ordered these shall be at 10 m intervals or at such other spacing as may be ordered
by the Engineer's Representative on Site. The location of the first cross section shall be approved by the
Engineer's Representative and each cross section shall extend a minimum distance of 10 m beyond the
limits of the new works.
MCICDC
Technical Specification- Civil 13
Form the centre line and grades established, the Contractor shall furnish and place all additional stakes,
templates and bench marks necessary for marking and maintaining points, lines and sections for layout of
the Works.
The Contractor shall be responsible for arranging and ensuring that adequate supplies of high speed diesel
oil, motor spirit, kerosene, lubricants and other petroleum products are available at all times to meet his
requirements for the purposes of or in connection with the Contract; the Contractor's particular attention is
drawn to this requirement as from time to time shortages and interruptions in the supply of fuel oils, etc.
occur in the region.
All traverse stations and reference points shall be clearly marked and protected to the satisfaction of the
Engineer.
The Contractor shall provide the Engineer with all necessary assistance for checking the setting out,
agreement of levels and any other survey or measurement which the Engineer needs to carryout in
connection with the Works during the entire period of Contract. Such assistance shall include:
(i) Provision of suitably qualified surveyors to work under the direction of the Engineer as
required.
(ii) Provision of all necessary support for these surveyors including assistants, chainmen,
labour, survey equipment (theodolite, levels, etc.), hand tools, pegs, and other incidental
material.
The survey equipment shall be of the quality approved by the Engineer.
The Contractor shall supply such assistance and plant as may be required in performing operations in
connection with the execution, examination, inspection and measurement of the Works including the
installation and surveying of benchmarks and survey stations and marks wherever and whenever the
Engineer shall deem necessary. The Contractor shall also supply such labour, either continuously or from
time to time, as may be required by the Engineer for the operation and maintenance of the laboratory, as
messengers in connection with the Works and a full-time peon over the Engineer's office at site.
Approved representative of the Contractor shall attend formal meetings at the office of the Engineer on site
or in the Clients office or in the Project Area, when called upon, for the purposes of Contract
Administration.
The contractor shall submit in duplicate to the Engineer each month a report in a manner approved by the
Engineer on his progress in the performance of the contract. Such reports shall include information
regarding delivery, manufacture, and installation etc.
2.23.2 Photographs
The Contractor shall supply negative and uncounted positive prints of photographs, postcard size, of such
proportions of the works, in progress and completed, as may be directed by the Engineer and specified
herein. The photographs shall be of two categories:
a) Progress photographs
b) Record photographs
MCICDC
Technical Specification- Civil 14
The photograph shall be indexed with date and short description of the object of the photograph. The
photographs as ordered by the Engineer shall be supplied in one negative and two prints, having signatures
of the Contractor and the Engineer of Engineer's Representative on the back of the photograph for the
purpose of attestation.
The Contractor shall construct, guard and look after the camp or campus for his workmen together with
workshops, stores, offices etc. The sites of the camp and other buildings shall be approved by the Engineer
and the standard of accommodation, ablution and canteen facilities be kept in a seemly and hygienic state
until the conclusion of the Contract. On Completion of the Contract, all buildings in the camp should be
demolished and the sites left clean and tidy with all materials and debris removed from the site. Considering
the available space of the sites, the Contractor may hire space or building(s) for such camp; workshops,
stores, offices, etc. in the nearest area of the sites and as per the approval of the Engineer. The Contractor
shall be responsible for the payment of such hired space/building(s) on time.
The Contractor shall provide safe access when requested by means of scaffolding, slings, safety belt etc. for
the Engineer to inspect at close quarters those portions of the Works not safely accessible by other means.
The Contractor shall provide (construct or hire at the nearest area of the site) and maintain at its own cost
site offices (minimum 900 Sqft area) comprising of working desks with chairs and sofa set, and steel
almirah and racks for the use of Engineer. Each office shall be equipped with electricity, water, drinking
water, latrines, electrical fans/heaters, internet facility etc. The Contractor shall employ at his own cost a
full-time office attendant/peon, one at office, to attend Engineer. The office shall be at the core satisfaction
of the Engineer.
Laser Printer Canon/Samsung/HP or equivalent (Up to A3 Paper size printing/Scanning and Photocopy) &
all types of stationary like paper, file, pencil, eraser, stapler & stapler pin, punching machine, etc. required
for Engineer at each site for whole contract period.
Subject to the availability, a set of telephone together with line may be arranged by the Project at site, at its
own cost and deliver to the Contractor for the use at site. The cost of operation, maintenance and services of
the said telephone line shall be borne by the contractor.
Such furniture and equipment shall remain the property of the Contractor.
The Contractor shall supply and maintain at his own cost survey equipment as levelling and theodolite, etc.
whenever required by the Engineer for the sole purpose of the project.
MCICDC
Technical Specification- Civil 15
3. MATERIALS
The materials supplied and used in the Works shall comply with the requirements of these Specifications.
They shall be new, except as may be provided elsewhere in the Contract or permitted by the Engineer in
writing. The materials shall be manufactured, handled and used in a workmanlike manner to ensure
completed work in accordance with the Contract. Where an Indian Standard is specified, the latest version
of the standard quoted shall be considered to apply. All related Indian standard codes of Practice must be
available at Contractor's Laboratory all the time during the tenure of the Contract.
3.1 SOURCES
The use of any kind or class of material from more than one source is prohibited, except by written
permission of the Engineer. Such permission, if granted, will set forth the conditions under which the
change may be made. The sources or kinds of materials shall not be changed at any time without written
permission of the Engineer. If the product from any source proves unacceptable at any time, the Contractor
shall make such arrangements as may be necessary to assure availability of the acceptable material, either
by alterations in plant operations or by a change of source. Claims for increased costs, which maybe
occasioned by such alterations or changes will be given consideration, unless the source of the unacceptable
material was designated in the Contract as a source of material. When any manufactured product, either
new or used, is furnished by the Employer, the location at which such material will be delivered to the
Contractor will be designated in the contract. In such cases the Contractor shall haul the materials from the
designated delivery point to point of use, and compensation for such hauling will be considered to be
included in the Contract unit price for placing the materials in the finished work.
a) The burden of proof as to the quality and suitability of alternatives shall be upon the Contractor and
he shall furnish all necessary information required by the Engineer. The Engineer shall be the sole
judge as to the quality and suitability of all alternative articles or materials and his decision shall be
final and binding.
b) Whenever the specifications permit the substitution of a similar or equivalent material or article, no
tests or action relating to the approval of such substitute material will be made until the request for
substitution is made in writing by the Contractor accompanied by complete data as to the equality
of the material or article proposed. Such request shall be made at least before two weeks to permit
approval without delaying the work.
The foreign manufacturer, producer or fabricator shall furnish to the Engineer a "Certificate of Completion"
with the specifications where required. In addition, certified manufacturer's test reports clearly identifiable
to the lot of delivered shall be submitted to the Engineer. Where structural materials requiring
manufacturer's test reports are obtained from foreign manufactures, such materials shall be furnished only
from those manufacturers already approved by the Engineer. The sufficiency of their ability to furnish only
from those foreign manufacturers, who have previously established, to be satisfied by the Engineer. The
sufficiency of them in-plant quality control as deemed necessary be the Engineer to give satisfactory
assurance of their ability to meet these specifications must be established.
4. CONTRACT DOCUMENTS
The Contractor is bound to execute and realize the Project Works covered under these Contract Documents.
These contract Documents to cover the said work shall along with that is normally understood therein
comprise of:
(a) These Contract Documents comprising of volume 1, 2 & 3 and any addenda.
(b) All Working Drawings issued are prepared by the Engineer.
(c) All site instructions made in the site order book or logbook by the Engineer.
(d) All instructions given to the contractor but the Engineer shall have form of sketches, directions
along with requests for additional data, shop drawings, measurements details etc. from the
Contractor related to this work.
(e) All shop drawings & samples approved by the Engineer.
(f) All manufacture's specifications, data brochures information etc. approved by the Engineer.
(g) All aspects of work checked & approved by the Engineer either on, or off, the project site.
(h) All samples, guidelines that the Engineer shall instruct the Contractor to follow. In particular,
covering all Works where the Contractor shall follow the existing designs, decoration, methods of
construction, finishes proportions, elevations etc. of the existing building.
(i) All aspects of Safety work (such as Safety Sign, Signal and Notice, Emergency Exit and Assembly
Point and Availability of Sufficient PPE etc.) checked & approved by the Engineer on the project
site.
MCICDC
Technical Specification- Civil 17
MCICDC
Technical Specification- Civil 18
5. EARTHWORK
Earthwork in excavation in trenches, foundation/raft foundation etc. in soil including dressing of sides,
ramming of bottom, dewatering, shoring/Shuttering, if necessary, lift up to 5 m, stacking of excavated
materials at least 4m clear from the edge of excavation within a lead of 10m and then returning the stacked
soil in 0.15m layers when required in plinth, under floors, sides of foundation, laying and depositing the
layer by properly watering and ramming and then disposing off all surplus excavated soil within the
premises of the Site or within 30m outside the site as directed. It shall be paid in m3.
5.1 EXCAVATIONS
The foundation shall be dug to the dimensions shown on the drawings and to a depth at which in the
opinion of the Engineer stratum of good hard soil is found.
The excavation shall be carefully dug out to the levels, shapes and dimensions as shown on the drawings or
as directed by the Engineer. Should any of the excavation be taken down below the specified levels, the
Contractor shall fill such excavation at his own expense with cement concrete (1:3:6) well rammed in
position until it is brought up to the proper levels; filling in with excavated materials will not be allowed for
this purpose. No extra charge will be paid unless otherwise specified in BoQ. Excavated earth shall be
stacked at least 4m away from the edge of the foundation.
The Contractor, at his own cost, shall dispose of all surplus excavated soil as directed by the Engineer.
If foundations are made broader or longer than shown on drawing or directed, the extra length and/or
breadth shall be filled in with earth rammed hard after the foundations are built by the Contractor at his own
cost.
The Contractor shall at his own expense and without extra charge, make provision for all extra excavation
in slope, pumping, dredging or bailing out water and these trenches shall be kept free from water while the
foundation work is in progress.
The Contractor shall also at his own cost remove such portions of boulders or rocks and the remains of the
old dismantled structures as are required to make the bottom of the trench horizontal and level and make the
holes thus made good by filling them with (1:3:6) Cement Concrete. If the holes happen to go below the
required foundation depth, nothing extra shall be admissible separately in the Bill of Quantities. The
trenches/ rafts shall be inspected by the Engineer before the concrete is laid therein and the trench level
shall be recorded. The filling of side of excess trench excavations shall be done in not more than 0.15m
layers. Each layer shall be watered and rammed hard before adding the next layer. Such fillings shall be
brought up to the ground level without extra charge and shall form part of the item of excavation.
MCICDC
Technical Specification- Civil 19
Near towns and all frequented places, foundation pits, well pits and similar excavation shall be securely
fenced and red lights used at night. This should be in the charge of watchmen to avoid accidents. Adequate
protective measures shall be taken to see that the foundation excavations do not affect or damage adjoining
structures. All measures required for the safety of the excavation, the people working in and near the
foundation trenches, property and the people in the vicinity shall be taken by the Contractor. The Contractor
shall be entirely responsible for any injury to life and damage to property caused by his negligence or
accidents due to his constructional operations. No extra shall be paid in this connection unless otherwise
specified.
5.4 DE-WATERING
The Contractor shall not be paid extra for bailing out or pumping out of all water which may accumulate in
the excavation or in the basement trenches during the progress of the work either from seepage, springs,
rain or any other source and shall be removed after their purpose is served.
Pumping water from any foundation enclosure or trenches/rafts shall be generally in such a manner as to
preclude the possibility of any damage to the foundation trenches, concrete or masonry or any adjacent
structures. The excavation shall be kept free from water (i) during inspection and measurement, (ii) when
concrete and / or masonry are in progress and till they come above the natural water level and (iii) till the
Engineers considers it necessary.
5.6 DISPOSAL
Disposal of the surplus earth shall be done as directed by the Engineer. Nothing extra shall be paid for
disposal made within the premises and such disposal made beyond the premises shall be paid in Cum.
5.7 MEASUREMENT
Measurement shall be made correct up to 1 cm and be the product of the length and width of the lowest step
of the footings other than circular excavation and be the product of radius of gyration ( =3.14) and actual
radius of the footings in case of circular excavation according to the drawings or the Engineer's instructions
and the depth measured vertically. Where the ground is not level, average depth shall be taken. Rate shall
be inclusive of all the Works described above.
Extra for lift beyond 5m shall be paid in m3. Extra payment shall be made for the extra lift involved beyond
5m up to 8m, under this item.
All the excavations for foundation/trenches having width less than 45cm will be treated as a manual
excavation for payment otherwise the quantity will be paid for excavation using machine.
5.7.1 Measurement
Measurement shall be the exact length, breadth and depth beyond 5m lifts.
The maximum depth of excavation or fill shall be 0.15m; 6m around the building shall be dressed and lev-
elled properly with outward slope of 1 in 100 or as per engineer's instruction. The surplus excavated mater-
ial shall be disposed of as directed. Any trees or hedges shall be measured and paid separately. The pay-
ment shall be made in square metre.
MCICDC
Technical Specification- Civil 20
5.8.1 Measurement
The quantity of site cleared shall be the product of length and breadth actually cleared.
Earthwork in filling in foundation on trenches and floor with materials from associated excavation or
borrow pit including 1 tonne roller compaction in 150 mm layers with sprinkling water required to obtain
90% density
Filling in plinth will be done in 0.15m. layers under floors including watering, ramming, consolidation and
dressing complete. It shall be paid in m3.
5.9.1 Materials
a. Sand ....................................m3
b. Earth ......... ........ ........ .......m3
c. Gravelled mixed earth……m3
The earth for filling shall be brought from already excavated soil within a lead of 30m, to be approved by
the Engineer prior to filling. If the earth from within the site is of unsuitable quality, earth shall be brought
from outside the site, which shall be measured and paid separately.
The filling work shall be done with earth/sand in 0.15 m layers, each layer being watered and compacted
thoroughly using 1 tonne Hand Roller. It shall include excavation of earth/sand, transportation, screening if
necessary, filling and all the cost of labour etc. complete.
5.9.2 Measurement
The measurement shall be taken for the consolidated thickness of earth/sand and paid in cubic meter. Pit or
stack measurement shall not be done. Quantity of earth fill under this item shall be arrived at by calculation
i.e. sum total of earth filling required in foundation trenches, over raft, pile, under floors or any other filling
less than the total quantity involved in foundation excavation.
Where necessary, the original ground shall be scarified, mixed with water, levelled
and then compacted so as to achieve the density mentioned in Table 9.2. Where the
height of embankment, as measured from formation level to the original ground level,
is less than 200 mm, the embankment foundation shall be compacted in accordance
with the requirements of Clause 910 such that the required compaction is achieved
within the upper 300 mm below formation level.
The natural moisture content and the optimum moisture content of the material to be
placed in the embankment shall be checked before start of the placing material. If
found to be out of the specified limits, the same shall be made good. Where water is
required to be added in such constructions, water shall be sprinkled uniformly and
thoroughly mixed in soil by blading or harrowing until a uniform moisture content as
specified is obtained.
MCICDC
Technical Specification- Civil 21
Moisture content, checked in accordance with IS 2720 (Part 2), at the time of
compaction shall be between 90% and 105% of the Optimum Moisture Content as
determined in accordance with IS 2720 (Part 8).
If the material delivered for fill/backfill is too wet, it shall be dried by aeration and
exposure to sun, till the moisture content is acceptable for compaction. Should
circumstances arise, where owing to wet weather, the moisture content cannot be reduced by the above
procedure, compaction work shall be suspended.
(1) If the material deposited as fill subsequently reaches a condition such that it cannot be compacted in
accordance with the requirements of the specifications the Contractor
shall
(i) Make good by removing the material off the filling area and placing suitable
material; or
(ii) Make good by tipping it elsewhere it elsewhere until it is in a suitable physical
condition for re-use; or
(iii) Make good the material by mechanical or chemical means to improve its
properties acceptable to the Engineer.
(4) Layers of material shall not exceed 150 mm compacted depth unless and until the Contractor can
demonstrate to the satisfaction of the Engineer that he can successfully Compact layers of a greater
thickness.
(5) Each layer shall be constructed in lengths suitable to the compaction and working
methods used. Materials of each layer shall be thoroughly mixed with water as
necessary to facilitate its compaction to the specified density.
(6) In cut areas, the filling shall be processed as necessary and compacted to the depth and compaction
requirements as given in Table 9.2. In the event that the Contractor is unable to achieve the minimum
compaction requirements below formation level he shall excavate and re compact in layer as necessary.
(7) Where it may be impracticable to use to conventional rollers, the compaction shall be carried out by
appropriate mechanical means such as small vibratory rollers, power
rammers or plate compactor. Care shall be taken to ensure that the compaction
equipment does not hit or come too close to any structural member so as to cause any
damage to it.
MCICDC
Technical Specification- Civil 22
MCICDC
Technical Specification- Civil 23
5.10.4 Measurement
(1) The quantities of the various classes of earthwork to be measured for payment under
the contract shall be limited to the lines, grades, slopes and dimensions shown on the
Drawing or as determined by the Engineer.
(2) Filling and backfilling compacted in place shall be measured in cubic meters by the average end area
method as computed from the original and final cross-sections of the completed work. The distance
between two end areas shall be the distance measured along central line of the road. Where due to changed
conditions, or the nature of a particular operation, or for any other reason, it is impossible or impractical to
measure the
quantities by means of average end areas, the Engineer shall compute the quantities
by a volumetric method, if in his opinion, it is the best suited method to obtain an
accurate determination.
(3) Consumption of work, levelling, watering and compaction of original ground, pumping out water and
other ancillary and incidental works necessary to complete the item as per this specification shall not be
measured for payment. They are deemed included in the measurement of the concerned item.
(4) Unless stated otherwise, Lead and Lift of excavated materials for disposal shall not be
measured for payment. They are deemed to be included in the quoted rates for the
earthwork operations irrespective of haulage distance and lift height.
5.10.5 Payment
(1) Various classes of earthworks i.e. backfilling, additional leads and lifts measured as described above
shall be paid at contract unit
rate of the respective item.
The contract unit rates shall be the full and the final compensation to the Contractor
and for the cost of:
(i) Arrangement of land as source of materials as much as needed.
MCICDC
Technical Specification- Civil 24
5.11.1 Scope
Sand filling in foundation of floor with materials from pit or riverbed as approved including machine
compaction in 150 mm layers with sprinkling water required to obtain 95% density.
Filling in plinth floor with river or mine sand brought from outside in 0.15m layers under floors including
ramming, consolidation, and dressing, all complete.
5.11.3 Measurement
The measurement shall be taken for the consolidated thickness of sand and paid in cubic meter.
5.12.1 Scope
This work is related to all types of structures that require filling with specified material in the remaining
volume or space of excavation left unoccupied by any permanent construction. Activities involved are
collection and transportation of suitable material from local borrow pits or hill side excavation, placing the
specified backfill material in layers, removal of foreign material if any, watering, compacting to required
density, lines and levels as indicated in the drawings or as directed by the Engineer. Compaction shall
proceed after the Contractor together with the Engineer identify the optimum thickness of each layer of
suitable material, its optimum moisture content, and the corresponding number of passes required for a
roller to arrive at the corresponding OMC. Prior to the start of works, the contractor shall prepare a trial
stretch to establish the above parameters and shall repeat it as often as necessary due to change in layer
thickness, borrow pits, and /or change in equipment. The Contractor may use the Standard Specifications
for Roads and Bridge Works of GON, MWOT, DOR as guide for the above purpose. Backfill, classified
according to their nature, are presented in the
following Sub-Clauses.
MCICDC
Technical Specification- Civil 25
5.12.4 Measurement
Measurement shall be taken for the consolidated thickness of granular sand and paid in m3.
6. POLYTHENE SHEET
6.1 SCOPE
Polythene Sheet having 500 micron approved by the RE shall be placed below PCC level of the building.
6.2 MEASUREMENT
The measurement shall be taken in square meter.
7. CONCRETE WORK
M10 grade cement concrete approximately (1:3:6) (1 cement: 3 sand: 6 stone aggregate 20 mm. and down
gauge) and M15 grade concrete approx. 1:2:4 (1 cement: 2 sand: 4 stone aggregate 20 mm. and down gauge
excluding cost of formwork complete as required. It shall be paid in m3.
7.1.1 Materials
Cement, sand and stone aggregate shall conform to the specifications as under Reinforced Cement Concrete
Works.
7.1.2 Mixing
All proportions of materials shall be by weight or by volume if agreed by the Engineer. Mixing shall be
done in a mechanical mixer as per specifications of Reinforced cement concrete work. However, in special
cases, hand mixing may be allowed by the Engineer, when the following procedure shall be adopted. The
several materials shall be accurately gauged in boxes or weighed and thoroughly mixed on a watertight
platform of adequate size, being turned over at least thrice till the colour is uniform and then twice when
wet. Water shall be added gradually and not more than necessary to sufficiently wet the materials. Only that
much concrete shall be mixed which can be used within half an hour. Each stack shall, however, be no
larger than consuming one bag of 50 kg of cement. All such stacks shall be placed distinct from each other.
The Contractor shall put in 10% more cement than specified without extra charges in case of
Normal/Ordinary mixer to get the required strength.
7.1.3 Laying
Concrete shall be laid in horizontal layers of not more than 0.15m thick and gently rammed.
MCICDC
Technical Specification- Civil 26
7.1.4 Curing
After laying, the concrete shall be kept wet for seven days. If cast in hot weather, it shall be covered with
gunny bags, which shall be kept constantly wet. Other work on concrete shall not start until 3 days after
laying of concrete.
7.1.5 Measurement
In cubic metre of exact length, breadth and depth. This shall be exclusive of any formwork required to
complete the item. Rate shall include all materials, Labour and Contractor's Overhead.
7.2.1 General
All R.C.C. work shall be carried out in strict accordance with these specifications, IS specifications and the
working drawings. All of mixed designed RC concrete shall be mixed with Polycarboxylate (PC) ether
based super plasticizer concrete admixtures, Remicrete-SP10 (FM), SPC-99- Engineers Plus, Perma Plast
or equivalent. Minimum 200ml per 50 kg of cement shall be used either directly on the wet concrete mix in
the concrete mixer under operation or along with gauging water to get the required strength of concrete of
25N/mm2 .
Any discrepancies in the dimensions on the drawings or any points not clear to the Contractor shall brought
to the notice of the Engineer and clarified in advance before proceeding with the work.
The Contractor shall allow for all wastage in all materials. He shall also allow for all tests of concrete
materials unless issued by the Employer. No R.C. concrete work shall be cast in the absence of the
Engineer. The Contractor's Engineer shall personally check that both the formwork and reinforcement have
been correctly placed and fixed and satisfy himself that all work preparatory to casting is completely ready
for inspection and approval and for this purpose at least 24 hours’ prior notice shall be given to the
Engineer by the Contractor.
7.2.2 Materials
The materials used in the Works shall be of the qualities and kinds specified. Materials shall be delivered to
the Works at least 30 days before it is required for use in work. Delivery shall be made sufficiently in
advance of constructional requirements to enable samples to be selected, tested and approved by the
Engineer. No material shall be used in the Works until approved. Materials failing to comply with the
approved samples and specification shall be removed within 24 hours of the instructions of the Engineer
from the Works at the Contractor's cost.
7.2.2.1 Water
Water for concrete shall be clean and free from injurious amounts of oils, acids, salts, sugars, organic
materials or other substances that may be deleterious to concrete or steel. Whenever required to do so by the
Engineer, the Contractor shall take samples of the water being used or which it is proposed to be used for
mixing concrete and test them for quality. The details of test shall be as per the recommendations in the IS:
3025-1964 (latest revision).
Permissible limits, maximum for Solids
Organic 200mg/l
Inorganic 3000mg/l
Sulphates 500mg/l
Chlorides 2000mg/l for PCC works
and 1000mg/l for RCC works
Suspended matter 2000mg/l
7.2.2.2 Cement
The cement shall be Ordinary Portland cement (OPC) of approved brand and manufacture and shall comply
in all respects with the IS 269- 1967 for Ordinary Portland Cement. It shall be delivered on the site in
packages with an unbroken seal fixed by the makers and plainly marked with the names of Brand and the
Manufacture. It shall be stored in a dry place, in regular piles not exceeding ten bags high and in such a
manner that it will be efficiently protected from moisture and contamination. Set cement should
MCICDC
Technical Specification- Civil 27
immediately be removed from the work and replaced by the Contractor at his own expense. If described
tests shall be made by taking samples of cement from stores or elsewhere from the Works, the selection of
samples and procedure for testing shall comply with appropriate IS code.
7.2.2.3 Aggregate
All aggregates shall conform to IS 383 - 1970. Aggregates shall as far as possible, be derived from a source
that normally produces aggregate satisfactory for concrete, and if requested by the Engineer the Contractor
shall supply evidence to this effect. If he is instructed to do so, the Contractor shall supply samples of the
aggregate for the purpose of making preliminary concrete test cubes as hereinafter specified.
Aggregate shall consist of naturally occurring sand and stone crushed. They shall be hard, strong, dense,
durable, clean and free from veins and adherent coating. As far as possible, flaky and elongated pieces
should be avoided.
Aggregate shall not contain any harmful materials, such as iron pyrites, coal, mica, shale or similar
laminated materials, clay, alkali, soft fragments, sea shells, organic impurities etc. in such quantity as to
affect the strength or durability of the concrete or in addition to the above for reinforced concrete, any
material which attack the reinforcement. Aggregates, which are chemically reactive with the alkalis of
cement are harmful, as cracking of concrete may take place.
a) Fine Aggregates
The fine aggregate shall be natural sand or sand derived by crushing suitable gravel or stone and shall be
free from coagulated lumps. Sand derived from a stone unsuitable for coarse aggregate shall not be used.
The fine aggregate shall conform to the requirements of IS 383 - 1970. Fine aggregate shall contain no
more than 3% of material removable by decantation test, nor more than 1% removable by dry tube. The
total of coal, clay lumps, shale, soft fragments and other deleterious substance shall not be more than 5%.
The percentage of clay lumps shall be determined by examining the various fractions that remain after the
material has been tested for grading. Any particulars that can be broken with fingers shall be classified as
clay lumps and the total percentage of clay lumps shall be determined on the basis of the total original
weight of the sample. The fine aggregate shall be well graded from fine to coarse and shall meet the
graduation requirements.
Blending will be permitted in order to meet the graduation requirements for the fine aggregate.
b) Coarse Aggregate
The coarse aggregate shall be crushed stone. The pieces of aggregate shall be angular. Friable, flaky and
laminated pieces and Mica shall only be present in such quantities as not to affect adversely the strength
and durability of the concrete as ascertained by tests on concrete cubes. After twenty-four hours’ immersion
in water, a previous dried sample shall not have gained in weight more than 5% and not more than 10% if it
is to be used in plain concrete or elsewhere as described. The coarse aggregate shall conform to the
MCICDC
Technical Specification- Civil 28
requirements of IS 383-1970. The percentage of wear at 500 revolutions of Los Angeles Rattler Test shall
not be more than 50%. The coarse aggregate shall meet the gradation of 2.
IS Percentage passing for single sized aggregate of nominal Percentage passing for graded
Sieve size aggregate of nominal size
63mm 40mm 20mm 16mm 12.5mm 10mm 40mm 20mm 16mm 12.5mm
80mm 100 - - - - - 100 - - -
63mm 85-100 100 - - - - - - - -
40mm 0-30 85-100 100 - - - 95-100 100 - -
20mm 0-5 0-2 85-100 100 - - 30-70 95-100 100 100
16mm - - - 85-100 100 - - - 90-100 -
12.5m - - - - 85-100 100 - - - 90-100
m
10mm 0.5 0-5 0-20 0-30 0-45 85-100 10-35 25-55 30-70 40-85
4.75m - - 0-5 0-5 0-10 0-20 0-5 0-10 0-10 0-10
m
2.36m - - - - - 0-5 - - - -
m
The cement shall be measured by weight, one or more complete bags containing 50 kgs being used for a
single batch of concrete and as the size of the mixer shall permit this to be done.
The normal proportions of cement and aggregate shall comply with the quantities specified below of the
concrete described for each part of the work. The specified quantities shall be altered if instructed after
examination of the aggregate materials in samples or in bulk in order to obtain the densest concrete with
approved materials. Any such alterations within the range of 1 part of fine aggregate to 1- 1/2 parts of
coarse aggregate and 1 part of fine aggregate to 2 -1/2 parts of coarse aggregate shall be made without any
alteration in the rate of Bill of Quantities.
MCICDC
Technical Specification- Civil 29
The compressive strength (cube strength) for Portland cement concrete shall be in accordance with IS 456 –
2000 and shall not be less than that shown in the following table:
__________________________________________________
Preliminary Test: Works Test:
Grade at 28 days at 28 days
__________________________________________________
M10 15 N/mm2 10 N/mm2
2
M15 20 N/mm 15 N/mm2
2
M20 26 N/mm 20 N/mm2
2
M25 32 N/mm 25 N/mm2
___________________________________________________
The quantity of water used shall be varied to suit the moisture content of the aggregate, and shall be just
sufficient to produce a dense concrete, consistent with practical workability.
If the strength of the respective grade concrete does not meet the compressive strength as stated above, the
ratio of the cement shall be increased to meet the minimum compressive strength of the concrete.
The workability of the concrete shall be checked at frequent intervals by slump test. Where facilities exist
and if required by the Engineer, alternatively, the compacting factor test in accordance with IS: 1199, shall
be carried out. The degree of workability necessary to allow the concrete to be well consolidated and to be
worked into the corners of formwork and around on the type and nature of structure shall be based on
experience and tests within the preferred limits of consistency as specified in Table below for various types
of experience and tests within the preferred limits of consistency as specified in table below for various
types of structures.
MCICDC
Technical Specification- Civil 30
The slump test shall be done at the commencement of each grade of concrete placing and such other times
as instructed.
The apparatus used for the slump test shall be standard cone. When cone is filled it shall be raised vertically
clear of the concrete and the measurement of the slump shall be taken. Care shall be taken to prevent
vibration of the sample being tested. If the Engineer requires the use of other means for testing the
consistency of the concrete it shall be done as instructed without any extra charge.
Each layer of concrete while being placed shall be consolidated by approved methods of ramming, tamping,
or mechanical vibrations to form a dense surface free honeycombing and tolerably free from watermarks
and air holes or other blemishes. The concrete shall be tamped against the face of the formwork so as to
produce dense fair surface. The number and type of mechanical vibrations shall be approved before
consolidating by vibration. Placing and consolidation of concrete shall be done in such a manner as not to
disturb concrete already placed, and reinforcement projecting from concrete already placed shall not be
vibrated or jarred. For reinforced concrete walls each other layer of concrete placed shall be properly
consolidated by approved methods of mechanical vibrations produced by internal or external mechanical
vibration.
MCICDC
Technical Specification- Civil 31
Any water accumulating on the surface of the newly placed concrete shall be removed by approved means
and no further concrete shall be placed thereon until such water be removed. No fresh concrete shall be
brought into contact with the concrete containing cement of different type. Unless otherwise approved or
instructed, concrete shall be placed in a single operation to the full depth of slabs, beams, and members
similar to these and shall be placed in horizontal layers not exceeding 0.90m deep in walls, columns until
completion of the part of the work between construction joints as specified. At the completion of a specified
or approved part of the construction, joints of the form and in the position herein after specified shall be
made. If a temporary cessation of concrete placing is unavoidable a construction joint shall likewise be
made.
7.2.12 Vibration
7.2.12.1 Appearance
The concrete that is to be compacted by vibration should appear anything from earth dry to slightly
glistening. The mix should have the appearance of lacking in fines.
7.2.12.2 Placing
Segregation is likely to take place when the concrete is tipped into the formwork and this should be
avoided. The concrete mix should not contain surplus water and sand, which will develop segregation under
influence of vibrator compaction. The distribution of new concrete should be uniform for the whole section
and the surface kept horizontal for the whole section all the time thus ensuring the movement of concrete is
downward only. Vibrators shall not be used as a spreading or distributing agent.
The vibrators shall be of rotary out of balance immersion type or the electro-magnetic type and operate at a
frequency of not less than 4,000 cycles per minute. The vibration shall be of such a power- input as to
produce an acceleration of 1 to 3 m/sec in the mass of the compacted concrete. The vibrators shall be
provided for continuous operation.
7.2.12.5 Compactness
The concrete shall be considered fully compacted when the mortar fills the spaces between the coarse
aggregate so as to form a glistening and even surface except for slight irregularities where the coarse
aggregate breaks this smooth surface. When this condition has been attained the vibrators shall be
withdrawn slowly.
The vibrator must not be placed against the steel or the formwork. The minimum distance shall be 8 mm.
The compactor must be placed in such a position that formwork, reinforcement and recently laid concrete
may be subjected to the minimum amount of vibration.
MCICDC
Technical Specification- Civil 32
In a column, the joints shall be formed about 75mm below the lowest soffit of the beams forming into it.
Concrete in a beam shall be placed throughout without a joint, but if provision of a joint is unavoidable, the
joint shall be vertical at the point of balanced moment along the span. A joint in a suspended floor slab shall
be vertical at the face of balanced moment and at right angles to the principal reinforcement. The locations
of construction joints shall be planned by the contractor well in advance of pouring and will have to be
approved by the Engineer.
Before fresh concrete is placed the cement skin of the partially hardened concrete shall be thoroughly
removed and surface made rough by hacking, sand blasting, water jetting, air jetting or any other method as
directed by the Engineer. The rough surface shall be thoroughly wetted for about two hours and shall be
dried and coated with 1:1 freshly mixed cement sand slurry or epoxy chemical, as directed by the Engineer,
before placing the new concrete. The new concrete shall be worked against the prepared surface before the
slurry/epoxy sets. Special care must always be taken to see that the first layer of concrete placed after a
construction joint is cold. The new concrete shall be well rammed against the prepared face before the grout
sets. Joints during pour shall be treated with 1:1 freshly made cement sand slurry or epoxy only after
removing all loose materials.
i) By water covering.
ii) By covering of surface with water - impervious paper.
iii) By application of approved impervious membrane.
Surface from which forms have been removed before the curing period has elapsed shall be protected as
specified for surfaces not covered by forms. Membrane cutting shall not be used on surfaces required to
receive additional concrete or concrete fill, nor on cement finish coats that are to receive dust proofing or
hardening treatments, nor during hot weather.
Water curing shall be performed by keeping the concrete surface wet by ponding, by continuous spraying
or by covering the surface with an approved water- saturated covering such as 2.5 mm. of sand or sawdust,
or by one or more layers of burlap. The exposed concrete surfaces shall be saturated with water throughout
the full stipulated curing period, they shall be kept sufficiently wetted with clean water to reduce cracks and
to prevent joints from opening in the forms.
The impervious membrane curing compound shall be an approved non bituminous, colorless, liquid,
sealing compound in atomized form so as to preserve the natural color of the concrete. The curing
compound shall be applied as soon as surface water has disappeared from concrete surfaces with approved
pressure spraying equipment in accordance with the manufacturer's directions and in sufficient thickness to
form an effective water seal. No compounds shall be used which will adversely affect the subsequent
installation of finished flooring.
MCICDC
Technical Specification- Civil 33
Joints of sheet membrane used for curing shall be lapped at least 150 mm. and sealed with water proof tape
as recommended by the manufacturer. Polyethylene sheet shall be considered the water-impervious paper
for purposes of interpretation of this item. No liquid curing compound may be used without specific written
approval of the Engineer regarding type, manufacturer, location and extent of use and application
procedures.
7.2.15 Finishes
The concrete surface shall in general be smooth enough. However, immediately after stripping form work,
minor defects and honey combed areas shall be patched and holes filled before the concrete is thoroughly
dry, patch areas shall be chipped away to 2.5 mm. depth, with regular edges perpendicular to the surface.
Area to be patched shall be thoroughly wet including the areas at least 150mm. wide entirely surrounding
them, just prior to placing the patching mortar. Mortar shall be of the same material and portions as used for
the concrete, without coarse aggregate. A sufficient quantity of white cement shall be substituted for part of
the ordinary cement so that the patching mortar, when dry, will match the surrounding concrete. Water in
the mix shall be kept to a minimum and mortar shall be re tempered without adding during which time it
shall be mixed to prevent setting. The mortar shall be thoroughly compacted into place, screened so as to
leave the patch slightly higher than surrounding surfaces, left undisturbed for one to two hours to permit
initial shrinkage and finished to match the adjoining work. Where patches exceed 2.5 mm depth, they shall
be trimmed and wet as specified, after which the opening shall be filled to within 2.5 mm. of the surface.
After sufficient shrinkage time has elapsed, the patching shall proceed as described above. Patches shall be
kept wet for five days. Tie holes left by the withdrawal of rods, or holes left by removal of ends of ties shall
be filled solidly with mortar. For holes passing entirely force mortar through the wall, starting at the back
face, shall be used. When hole is completely filled, excess mortar shall be struck off with a cloth flush with
the surface. Holes not passing entirely through walls shall be filled solidly with mortar. Any excess mortar
shall be struck off with a cloth on the wall surface. The surface of non-shuttered faces concrete work other
than slabs shall be smoothed with a wooden float (or if approved with a steel trowel) to give a finish equal
to that of the rubbed down shuttered faces. Concealed concrete faces shall be left as it is except that
honeycombed surfaces shall be made good.
The top faces of slabs not intended to be surfaced shall be levelled and floated to a smooth finish at the
levels or falls shown on the drawings or elsewhere.
The floating shall not be executed to the extent of bringing excess fine material to the surface. Ribbed
surfaces of slabs shall where instructed be formed at the time of taming and leveling. Indentation in slab or
stair surfaces shall be formed by approved implements giving the depth and patterns instructed. The top
faces of slabs intended to be covered with screed, granolithic or similar surfacing shall be left with a spade
finish.
The soffits of slabs and faces of walls intended to be rendered shall be roughened by approved means to
form a key. Concrete surfaces to take finishes other than those specifically referred to herein shall be
prepared in an approved manner to suit the finish as instructed.
MCICDC
Technical Specification- Civil 34
If the test be instructed to be made for the reason (f) the Contractor shall make the test and shall be
reimbursed for all cost relating thereof irrespective of the result of the test.
For the purpose of a loading test on floors, roofs and similar structures and their supports, the test load shall
be equivalent to 1 and 2/3 times the superimposed load for which the Works or part thereof to be tested has
been designed. The test load shall not be applied within 90 days (or 28 days if rapid hardening Portland
cement be used) of the completing of placing of the concrete in the part of the Works to be tested, and the
latter shall not be supported during the test by shuttering or other non-permanent support. Measures shall be
taken to ensure that in the event of a failure under the test temporary support of the loaded member shall be
immediately available. The test shall proceed strictly as instructed. For the loading test on floors, roofs or
similar structures the result shall be deemed satisfactory if upon removal of the test load the residual
deflection does not exceed one-quarter of the maximum deflection after 24 hours loading. If the residual
deflection exceeds this amount the test loading shall be repeated, and the result shall be deemed to be
satisfactory if the residual deflection after removal of the second test load does not exceed one-quarter of
the maximum deflection occurring during the second test.
If the result of the loading test is not satisfactory the Engineer shall instruct that part of the Works
concerned shall be taken down or removed and reconstructed to comply with the specification, or that such
other remedial measures shall be taken as to make the Works secure. If the test is instructed to be made for
one or more of the reason (a) to (e) as herein before specified, the Contractor shall take down, remove and
reconstruct the defective work or shall take remedial measures instructed at his own cost.
7.2.17 Measurement
In calculating the contents of any R.C.C. member, for measurement proposes the dimensions adopted shall
be structural concrete members exclusive of any finish,
a) Raft, slabs and beams: It shall be measured in cum. of work done as per drawing. Measurement
shall be done for the raft concrete below the column junction to the raft slab/beam. Nothing extra
shall be paid for any odd size or shapes.
b) Beams: Measurement shall be between R.C.C. columns or resting on walls cubic meter of the work
done as shown on the drawing. The depth shall be taken from the bottom of the rib to the top of the
slab or chajja, if any. Lintels when connected to main RCC structure shall be measured as beams.
c) Columns: These shall be measured in cu.m. of work done according to the drawings from top of the
footing or raft slab to the top of slab in case of ground floor and from top of slab to the top of slab
for all other floors. Unless specified otherwise nothing extra shall be admissible for any odd size
and for any special section and shape of column i.e. square, rectangular, round, elliptical etc. and
laid at any angle as may be shown on drawings.
d) Walls: These shall be measured from end of slab / column / beam, termed wall. It shall be paid in
cubic meter excluding the finish.
e) Lintels: All lintels spanning over independent openings unrelated to main RCC structure shall be
measured under lintels, in cubic meter of the work done according to drawing. Width of the lintels
shall be taken according to wall thickness specified unless set back or projected from wall as shown
on the drawing. Unless otherwise described or shown on the drawings, bearing over the openings
shall be depth of the lintel or 150 mm. whichever is higher.
f) Stairs: These shall be measured in Cu.m. of the concrete work done as per drawing. Unless
specified otherwise nothing extra shall be admissible for steps laid in any shape or not straight in
plan.
g) Folded Staircase: The folded staircase shall be measured excluding the vertical main column. It
shall be measured for step of any shape size and paid in cubic meter excluding the finish.
MCICDC
Technical Specification- Civil 35
h) Fins and Louvers: The RCC fins or louvers as provided shall be measured and paid in cubic meter.
Nothing extra shall be allowed due to its shape, location or size.
i) Facia and parapets: These shall be measured in Cu.m. of the concrete work done as per design,
drawing, excluding of finishing. For sills all projections Upto 100mm. beyond the wall on either
side shall be made without any extra charge and these shall be inclusive of forming any pattern of
drip mould.
j) Mullions: The RCC mullions shall be measured for all the slab, walls etc. forming the water tank.
Nothing extra shall be allowed for its shape, size and location. It shall be paid in cubic meter of the
concrete work.
k) Water tank: These shall be measured in Cu.m. of the propping, shuttering and finishing the top and
facing surface smooth with neat cement slurry complete but excluding the cost of reinforcement. It
shall be paid in Cu.m.
Cement concrete M150 shall conform to as in 6.3.4. The windowsill will be of specified thickness
and size, shall be pre-cast or cast in situ with all the necessary formwork complete.
The exposed underside and the top and facing shall be plastered neatly with cement mortar 1: 3: (1
cement: 3 sand).
The grooved drip course shall be provided. The concrete shall be laid in slope as required as per
drawing or as directed.
Measurement: It shall be measured in cubic meter of the work done. The rate shall include all
materials labor complete. It shall be paid in Cu.m.
7.3 REINFORCEMENT
Thermo Mechanically Treated (TMT) Steel Reinforcement bars conforming to IS 1786-1985 or IS. 1139-
1966 shall be used in RCC works. This item shall consist of supplying and fixing TMT Steel bars including
bending, binding with 18 Gauge MS wire, placing in position including the cost of binding wire, as per
drawing. This shall be paid in kg.
Reinforcement shall be free from pitting due to corrosion, loose rust, mill scale, paint, oil, grease, adhering
earth, ice or other materials that may impair the bond between the concrete and the reinforcement or that
may in the opinion of the Engineer cause corrosion of the reinforcement.
quality, physical properties and related requirements, reinforcement of the fore-going descriptions shall
comply with appropriate parts of IS Standards Nos. 423-1966, 1139-1966 and IS. 1786-1985 for mild steel
and TMT steel respectively. Panchakanya or Himal or Jagadamba or Ambe TMT Steel is recommended to
use.
After the delivery of the reinforcement bars at site if it is found that the Manufacturer's Test Certificate for
the lot is not available or on inspection by the Engineer the reinforcement bars thus supplied are found
rusted/corroded the contractor will collect as many samples as required by the Engineer and get them tested
on his own cost in an independent laboratory.
Reinforcement shall be lapped, joined or spliced only at the positions described. Splices and like found to
be necessary elsewhere shall be formed only if and as instructed. Lapping shall be provided as shown in the
drawing and as permitted. Where practicable bars in each member shall be assembled and fixed in the form
of a rigid cage or skeleton before placing in the moulds or formwork.
Immediately before concreting, the reinforcement shall be checked for position, cleanliness, freedom from
rust or retarding liquid. Measure shall be taken to ensure that reinforcement remains correctly in position
with required cover during the placing and consolidating of the concrete.
Reinforcement projecting from work being concreted or already concreted shall not be bent from its correct
position for any reason unless approved and shall be protected from deformation for future extensions and
also shall be thoroughly coated with cement grout wash or encased in concrete or otherwise protected from
corrosion as instructed.
MCICDC
Technical Specification- Civil 37
Horizontal, vertical or inclined slabs: 15 mm. or the size of the main bars whichever is greater.
Columns: Main bars for columns not exceeding 20 mm. diameter shall be 25 mm. and the main bars in
columns exceeding 20 mm. diameter shall be 40 mm. or the size of the main bars whichever is greater.
Rectangular binders or links or helical binding, 15 mm. minimum.
General RCC Footings: 50 mm or the size of the main bar whichever is greater.
7.3.1.9 Measurement
For the purpose of ascertaining payments due to the Contractor the basis of measurements of bars or wire
reinforcement used in the Works shall be the calculated weight in kg, which shall be computed from the
sizes and lengths of the bars or wires described on the working drawings or elsewhere. No allowance in the
weight shall be made for cutting to waste, rolling margin, extra length or other tolerances. Nothing extra,
whatsoever shall be admissible on bars 12 mm and below rolled, the Contractor is deemed to have taken
this factor into consideration and quoted accordingly in the tender. The Contractor's rate for unit weight of
bars reinforcement shall be deemed to include all allowances omitted in calculating the weight and for any
other tolerances, and for providing tying wire, chairs, spacer bars, and cover blocks as specified hereinafter
for carriage and handling, for bending hooking, cranking, and for fixing and maintaining in the correct
position in the Works. Standard laps of the lengths as shown in the drawing or as instructed at site shall be
admissible. Standard hooks (9 times the diameter for each hook for mild steel) shall be added to the finished
length to arrive at the length of the bar for cutting and measurement. No hooks are required for ribbed or for
steel.
7.4 FORMWORK
Providing, placing, fixing, cantering and shuttering of plywood or steel formwork in any shape and sizes for
slabs, beams, columns, shear walls, Lintel, foundation etc including nails, propping supports and removal of
the same at any leads and lifts all complete
Supply, erection and removal of all types of formwork (cantering and shuttering) for concrete work
including the erection of all supporting structures (scaffolding) such as props, struts, etc. including nailing,
propping, strutting, wedging etc.; placing, levelling and aligning forms, applying form oil; sealing to
prevent leakage of grout; and removal of forms all complete. It shall be paid in square metre.
7.4.1.1 Design
Formwork shall be designed and constructed in such a manner that concrete can be properly placed and
thoroughly compacted without any movement in the formwork. Formwork shall be firmly supported and
adequately strutted, braced, or tied. It shall be capable of adjustment to the lines and dimensions of the
finished concrete and it shall be sufficiently strong to resist without distortion, the pressure of concrete
during its placing and compaction, and other loads to which it may be subjected. It shall not be liable to
suffer distortion under the influence of the weather. When concrete is to be vibrated, special care shall be
taken to ensure that the formwork will remain stable and the joints tight. The safety and adequacy of
MCICDC
Technical Specification- Civil 38
cantering and shuttering shall be the sole responsibility of the Contractor. The Contractor shall if required
supply to the Engineer shop drawings and calculations for the formwork he proposes to use.
7.4.1.3 Supports
Formwork shall be constructed in such a way that the formwork to the sides of members can be removed
without disturbing the soffit formwork or its supports. Props and supports shall be designed to allow the
formwork to be adjusted accurately to line and level and to be erected and removed in an approved
sequence without injury to the concrete. Supports shall be erected on sufficiently strong base to avoid injury
to any portion of the structure by its settlement. Props and bracing shall be provided for the temporary
support of composite construction where separately specified.
7.4.1.5 Sundries
Formwork shall be provided to the top surface of concrete where the slope or the nature of the work
requires it. Provision shall be made for forming holes and chases for services and for building in pipes,
conduits and other fixings, as shown on the drawings. The material and position of any ties passing through
the concrete shall be to the Engineer's approval. Except where corrosion of a metal tie is unimportant it
shall be possible to remove a tie so that no part of it remaining embedded in the concrete shall be nearer to
the finished surface of the concrete than the specified thickness of cover to the reinforcement. Any holes
left after the removal of ties shall be filled with concrete or mortar of approved composition.
MCICDC
Technical Specification- Civil 39
until the concrete has reached its design strength. Suitable curing methods should immediately follow the
removal of the formwork.
Forms for various types of structural components shall not be removed before the minimum periods
specified below and shall be subject to the approval of the Engineer.
Before removing any formwork the contractor must notify the Engineer well in advance to enable
him to inspect the concrete if he so desires.
The times given for the removal of props are based on the assumption that the total live plus dead weight to
be supported at the time of removal is not more than one half the total design load. For horizontal members
where the loading is a higher proportion of the total design load these times may need to be increased.
The contractor shall record on the drawing or in some approved manner the date on which the concrete is
placed in each part of the work and the date on which the formwork is removed and the record shall be
checked and countersigned by the Engineer. The contractor shall be responsible for the safe removal of the
formwork. However, the Engineer may delay the time of removal if he considers it necessary. Any work
showing signs of damage through premature removal of formwork or loading shall be entirely
reconstructed at the contractor's own expense.
7.4.1.8 Tolerances
The formwork shall be so made as to produce a finished concrete true to shape, lines, levels, plumb and
dimensions as shown on the drawings subject to the following tolerances unless otherwise specified
elsewhere in this specification or drawings or directed by the Engineer.
7.4.1.10 Rate
Rate shall include the supply and storage of all material, scaffolding, equipment and labour to erect, align,
form oil and its application, seal and remove formwork for any shape, size and quantity of concrete work as
specified in the design and bill of quantities, all complete.
MCICDC
Technical Specification- Civil 40
7.4.1.11 Measurement
Measurement for payment shall be done of the area on which cantering shuttering has been done. It shall
include the application of the form oil, scaffolding and removal of the formwork as well.
8. MASONRY WORK
8.1.1 Bricks
The bricks shall be chimney burnt hand cast bricks of first-class quality. These shall be of quality approved
by the RE, free from grit and other impurities such as lime, iron and other deleterious salts. These shall be
well-burnt, sound, and hard with sharp edges and shall emit ringing sound when struck with a mallet. These
shall be of uniform size. The Brick work shall also include 3" thick RCC Horizontal Band of 1:1.5:3
nominal Mix Concrete with 2 nos. of 10 mm dia. longitudinal re-bar bind with 8mm diameter re -bar @ 10"
c/c transversally in each band at sill and lintel level and vertical bar as well with same bar and spacing as in
horizontal band, wherever specified in drawing. The rebar must be properly anchored with columns as per
drawing and instructions. (Measurement of concrete, re-bar, formwork will be done separately in respective
items). The bricks shall conform to IS 3495 and be tested in accordance with IS 1077.
Sampling:
Brick samples shall be randomly selected for testing in quantities not less than 5 bricks per one thousand for
each lot supplied for the construction works.
Acceptance Criteria:
1. Compressive Strength: The average compressive strength of the brick shall be minimum of 105
kg/sq.cm. The compressive strength of any individual brick shall not fall below the above men-
tioned minimum average compressive strength by more than 20%.
2. Water absorption: The average water absorption of the brick samples shall not be more than 15%
over the dry weight after immersion in cold water for 24 hours.
3. Efflorescence: The rating of efflorescence shall not be more than "Slight".
Mortar
Cement Mortar shall comply with IS 2250-1981: the code of practice for preparation and use of masonry
mortars. The mortar used in work shall have the strength not less than 5 N/mm2 or 7.5 N/mm2 at 28 days as
specified.
However, if provided in the Contract, cement and sand may also be mixed in specified proportions. Cement
shall be proportioned only by weight, by taking its unit weight as 1.44 ton per cubic meter and sand shall be
proportioned by volume after making due allowance for bulking.
Cement mortar shall be mixed in proportion of materials as indicated. The ingredients shall be accurately
measured by volume and shall be well and evenly mixed together in a mechanical pan mixer. Too much
water shall not be used. River sand shall be used unless otherwise specified. If hand mixing is allowed, it
shall be done in brick tanks. The gauged materials shall be put in the tank and mixed dry thoroughly. Water
in required quantity will then be added and the whole mix will be mixed again until it is homogeneous and
of uniform colour. The mortar shall be mixed for at least three minutes after addition of water in the case of
mechanical mixing. In the case of hand mixing, the mortar shall be hoed back and forth for about 10
minutes after the addition of water in order to obtain uniform consistency. Only that quantity of mortar shall
be mixed at a time which can be used completely before it becomes unworkable. Any mortar that has
become unworkable due to loss of water before elapsing the initial setting time of cement shall be rewet to
make it workable and shall be used in the works. On no account mortar shall be used after elapsing the
initial setting time of cement
MCICDC
Technical Specification- Civil 41
8.2 WORKMANSHIP
All the bricks shall be thoroughly soaked in water (preferably 12 hours and not less than 1 hour) before use
till the bubbles cease to come up. The bricks shall be laid in cement mortar bed in proper band. When
bonding, the brickwork must be set back in every course. The vertical toothing shall not be accepted. The
courses shall be truly horizontal and the work strictly in plumb. The mortar joints shall be broken vertically.
All the joints shall be raked out to a depth of 6mm to receive setting beds and / or for pointing work where
required.
The walls are to be carried up in a uniform manner with level courses and perpends strictly kept, no one
portion being built up more than 14 single courses per day. The top of the walls shall be well wetted before
the work recommences.
There shall be smooth mortared surface to receive any structural slab, beam, lintel etc. on the brick courses.
The brickwork shall be thoroughly cleaned off on completion.
8.3 MEASUREMENTS
The measurements of work shall be the product of the length, height and thickness. Deductions for doors,
windows and other openings including lintels shall be made to arrive at the net quantity of work. Nothing
shall be paid extra for forming such openings. However, no deductions shall be made for openings of areas
less than 0.1 sqm overall and for bearing of lintels, beams, girders and hold fast blocks but nothing extra
like formwork shall be paid for embedding these. Similarly, no deductions shall be made for chimney flue
left in the walls, but nothing extra shall be allowed for rendering for flue opening as specified. Brickwork as
covering to RCC structures and in continuation of the main wall shall be measured in thickness of quarter
brick unit. Unless otherwise specified nothing extra shall be admissible for cutting shape other than straight
or any cutting necessary for shaping the walls to the structural design. Rate shall be inclusive of all
necessary scaffolding, watering, cutting of bricks, curing, materials and labour.
8.4.2 Mortar
Mortar shall be 1:4(1 cement: 4 sand) mixed as per specification of item
8.4.3 Measurement
Measurement shall be done in cubic meter of the wall. Measurement of concrete, re-bar, formwork will be
done separately in respective items. Deduction shall be made as for brickwork stated in the specification.
The brick shall conform to as described in item 7.1.1. The base on which bricks are to be laid on flat shall
be levelled to slope as required and compacted properly. The bricks on flat shall be laid true to line slope
and pattern as required. The line, level etc. shall be checked by pegging. The brick shall be closely packed
with sand for compaction. The workmanship shall be to the approval of the Resident Engineer.
MCICDC
Technical Specification- Civil 42
8.5.1 Measurement
The measurement shall be the net area in square metre, a product of length and breadth and the rate shall be
for all the material and labour.
8.8.1 Mortar
Mortar for masonry shall conform to provisions under brick works.
8.8.2 Construction
The method of construction described herein shall hold good in all Clauses of this Section, wherever
applicable.
General
Construction shall be carried out in accordance with I.S. 1597-1992, Code of Practice for construction of
stone masonry, Part 1 Rubble stone masonry or Part 2 Ashlar Masonry as appropriate. All stratified stone
possessing bedding planes shall be laid with its natural bed as nearly as possible at right angles to the
direction of load. In the case of arch rings, the natural bed shall be radial. Face work groins shall be built to
a height not exceeding one meter in advance of the main body of the work and adjacent walling stepped
down on either side. Masonry face work between the groins shall then be built to a height not exceeding
MCICDC
Technical Specification- Civil 43
500 mm above the backing which shall then be brought up level with the completed face work. At no time
shall the backing be built up higher than the face work.
Except for dry rubble walling, all joints (gaps) shall be sufficiently thick to prevent stone to stone contact
and the gaps shall be completely filled with mortar. Stones shall be clean and sufficiently wetted before
laying to prevent absorption of water from mortar.
Placing loose mortar on the course and pouring water upon it to fill the gaps in stones shall not be allowed.
Mortar shall be fluid, mixed thoroughly and then poured in the joints. No dry or hollow space shall be left
anywhere in the masonry and each stone shall have all its faces completely covered with mortar of the
thickness as specified for joints.
The bed which is to receive the stone shall be cleaned, wetted and covered with a layer of fresh mortar.
All stones shall be laid full in mortar both in bed and vertical joints and settled carefully in place with a
wooden mallet immediately after placement and solidly embedded in mortar before it has set. Clean and
wet chips and spalls shall be wedged into the mortar joints and bed whenever necessary to avoid thick
joints or bed of mortar. When the foundation masonry is laid directly on rock, the bedding face of the
stones of the first course shall be dressed to fit into rock snugly when pressed down in the mortar bedding
over the rock. For masonry works over rock, a levelling course of M15/40 or M15/20 concrete 100mm
thickness shall be laid over rock and then stone masonry work shall be laid without foundation concrete
block.
In case, any stone already set in mortar is disturbed or the joints broken, it shall be taken out without
disturbing the adjoining stones and joints. Dry mortar and stones thoroughly cleaned from the joints and the
stones shall be reset in fresh mortar. Sliding one stone on top of another which is freshly laid shall not be
allowed.
Shaping and dressing of stone shall be done before it is laid in the work. Dressing and hammering of the
laid stones which will loosen the masonry shall not be allowed.
Building up face wall tied with occasional through stones and filling up the middle with stones spalls and
chips or dry packing shall not be allowed. Vertical joints shall be staggered. Distance between the nearer
vertical joints of upper layer and lower layer in coursed rubble masonry shall not be less than half the
height of the course. Masonry in a structure between two expansion joints shall be carried up nearly at
one uniform level throughout but when breaks are unavoidable the masonry shall be raked in sufficiently
long steps to facilitate jointing of old and new work. The stepping of raking shall not be more than
45 degrees with the horizontal.
Masonry shall not be laid when the air temperature in the shade is less than 3°C. Newly laid masonry shall
be protected from the harmful effects of weather.
Ashlar
All stones shall be dressed to accurate planes on the beds and joints and they shall be fair and neatly
or fine tooled on the face unless otherwise described in the BOQ.
Block-In-Course
Beds and joints shall be squared and dressed for a distance of at least 220 mm from the exposed face.
Bond stones shall form at least one sixth of the area of the exposed face and shall extend at least 900 mm
into the wall or for the full thickness of the wall if the latter is less than 900 mm. Unless described in the
contract as tooled or drafted, the exposed face of all stones shall be blocked and left rough. Arises shall be
dressed square at all beds and joints.
Square Rubble-Coursed or Broken Courses
All stones shall be truly squared and dressed for a distance at least 120 mm from the face of the wall. Bond
stones shall be provided at the rate of at least one to every 0.8 m2 of exposed face and shall measure not
less than 150 mm x 150 mm on the face and not less
than 450 mm in length or the full thickness of the wall, whichever is the less.
Dry Random Rubble
Dry random rubble masonry shall be constructed generally to the requirements of coursed random rubble
masonry but with the omission of mortar. All stones shall be carefully shaped to obtain as close fit as
possible at all beds and joints, any interstices between the stones being filled with selected stone spalls. The
stones in courses shall be laid perpendicular to the batter face. The exposed tops or capping’s of dry
rubble structures shall be formed as shown on the Drawing.
Composite Random Rubble
MCICDC
Technical Specification- Civil 44
Materials for composite random rubble shall comply with relevant Clauses. The dry stone insets shall be
constructed when the level of the surrounding mortared masonry surround has reached the top of the dry
stone inset.
8.8.4 Measurement
Stone masonry shall be measured in cubic meters. The pointing shall be measured in sq.m.
8.8.5 Payment
The stone masonry shall be paid at the respective contract unit prices which shall be the full and
the final compensation to the Contractor.
8.9.1 Stones
All stones used for this work shall be hard, uniform in texture, free from impurities, locally the best
available from the nearest quarry or elsewhere approved by the site engineer/supervisor and crushed stone.
Samples which are not similar to the samples supplied shall be rejected. No round stone shall be used unless
broken. Stones shall be fairly regular in size and every stone shall be fitted to the adjacent stones. No stones
shall be less than 15 cm in size. It shall be used below the foundation of RCC STP and ETP tanks and the
area of Platform slab for the different equipment’s associated with the work to the required depth as shown
in the drawing, specified by the RE.
8.9.2 Sand
The sand shall conform to the Article 5.11 (specification” Civil Work”) above.
MCICDC
Technical Specification- Civil 45
8.9.4 Measurement
The measurement shall be in cubic meter of complete finish work
8.10.1 Stones
All stones used for this work shall be hard, uniform in texture, free from impurities, locally the best
available from the nearest quarry or elsewhere approved by the site engineer/supervisor. Samples which are
not similar to the samples supplied shall be rejected. No round stone shall be used unless broken. Stones
shall be fairly regular in size and every stone shall be fitted to the adjacent stones. No stones shall be less
than 15 cm in size.
8.10.2 Sand
The sand shall conform to the Article 5.11 (specification” Civil Work”) above.
8.10.4 Measurement
The measurement shall be in cubic meter of complete finish work.
9. FLOORING
Plain cement concrete M15 (1:2:4) flooring with cement, sand and stone ballast, including laying in panels
(the side of the panels shall be bounded with teak wood batten or flat iron bars of same size and fixed with
weak mortar or with nails or hooks), providing proper slope for draining wash water, all complete, in sqm.
9.1.2 Proportion
The proportion shall be 1 cement: 2 sand: 4 stone aggregate 12 mm. and down gauge by volume as
specified in the schedule. Grading of aggregate shall be as per reinforced concrete specification.
9.1.3 Placing
The screeding shall be laid to specify thickness and maintain the slope as per the drawing and instruction of
Engineer. Screeding of the flooring shall be casted in one operation.
9.1.4 Finishing
Compact first with wood float. The blows shall be fairly heavy but as consolidation takes place, light rapid
strokes shall be given. Beating shall continue till all hollows in concrete are filled with mortar cream. Then
MCICDC
Technical Specification- Civil 46
the surface shall be troweled till the moisture disappears. The surface shall be checked with straight edge.
The finish surface shall be cured for 7 days. Sample of workmanship shall be got approved prior to work.
9.1.5 Measurement
Measurement shall be the exact length and breadth. It shall be paid in Sq.m of the work done. Nothing shall
be admissible for slope, small area, corners and work in any shape. No deduction shall, however, be made
for protruding or independent columns occurring in the floor, door frame embedded in floor or any other
part, when the area involved does not exceed 0.1 sq. m. Rate shall include materials and labour complete.
9.2 SKIRTING
The thickness of the skirting shall be governed by the thickness of internal plaster. It shall project by 6 mm.
from the finished surface of the plaster. The receiving surface shall be prepared similar to that for the
plastering on walls.
9.2.2 Mortar
Mortar shall be 1 cement: 3 sand well mixed and applied as per cement plaster. When the surface becomes
even it shall be uniformly covered with a coat of neat cement mixed integrally with the hardening liquid 2
litres to 50 Kg. of cement 6 mm. thick finished smooth. The corners, angles, junctions shall be truly vertical
and or horizontal. Rounding of corners and junctions as required shall be done without any extra charge.
The finished surface shall be cured for 7 days.
9.2.3 Measurement
It shall be measured in ruining metre of the work done. The rate shall include material and labour complete.
It shall be paid in RM.
9.4 MEASUREMENT:
It shall be measured in square metre of the work done and rate shall include material and labour complete.
10. PLASTERING
MCICDC
Technical Specification- Civil 47
10.1.1 Materials
Cement shall conform to as specified under cement concrete work. Sand shall conform to as specified under
cement concrete work and 50 % fine sand shall be mixed.
The cement mortar shall be in 1:4 (1 cement: 4 sand) by volume. The ingredients shall be accurately gauged
and be well and evenly mixed together in a mechanical pan mixture, care being taken not to add more water
than is required. No mortar that has begun to set shall be used. If hand mixing is allowed, then it shall be
done in brick tanks. The gauged material shall be put in the tank and mixed dry. Water will then be added
and the whole mixed again until it is homogeneous and of uniform color. Not more than one bag of cement
shall be mixed at one time which can be consumed within half an hour of its mixing.
The joints in the brick work shall be raked out to a depth of 12.5 mm or 20mm. minimum and the surface
watered and cleaned of all dust and dirt. Concrete surfaces shall be properly racked to get adequate key. Tip
(makers) shall be provided on the surface for proper thickness and obtaining the finished plaster surface in
plumb.
The finished surface shall be minimum average 12.5 mm. on ceiling or 20mm thick on exterior wall and
12.5mm inner wall as specified in BOQ. The surface shall be finished at once by being rubbed over with
trowel till the cement appears on the surface. All corners, angles and junctions shall be truly vertical and
horizontal as the case may be and carefully and neatly finished. Rounding of corners and junctions as
required and directed shall be without extra charge. The finished plaster shall be cured for 7 days and
protected against damage. Sample of workmanship shall be approved prior to commencement of work.
10.1.2 Measurement
It shall be done in square metre of the surface over which the plaster has been done. The thickness of the
plaster shall not be taken into account except for independent columns where the measurement shall be of
finished surface allowing 12.5 mm. over the designed dimensions. Opening shall be deducted in full and
jambs and soffits shall be allowed. Each opening less than 1 sq. m. shall neither be deducted nor extra be
paid for jambs, soffits or the sides of such opening. The rate shall include rounding of all corners, junctions,
making grooves and forming drip course wherever required materials, scaffolding and curing. Unless
otherwise specified nothing extra shall be allowed for plaster on independent columns and beams, any short
width or on curved surfaces and difficult location. It shall be paid in sq. m.
Plastering the R. C. C. soffits/slab, column, shear wall with 12.5 mm. thick cement plaster 1 : 3 ( 1 cement :
3 sand 50 % coarse sand + 50 % fine sand ).
The work shall be done as per specification of item No. 10.1. The plaster shall be composed of 1 : 3 (1
cement : 3 sand) cement mortar. Cement slurry shall be used as required. Care should be taken to ensure
that the finished plaster surface shall be plump, plane, straight and true to line. All arises and corners shall
be straight, clean and sharp. All plaster work be subjected to approval of the Engineer and work failing to
meet the requirement shall be dismantled and replaced at the Contractor's expense.
9.4.1 Measurement
It shall be measured in square metre of the surface over which plaster has been done. The rate shall include
rounding of all corners, junctions and forming drip course, making grooves, material, scaffolding and
curing all complete. It shall be paid in sq. m.
MCICDC
Technical Specification- Civil 48
11.1 A. Supplying and application of Heavy duty reinforced elastomeric acrylic waterproof coating
(SUPERKOT) total 3 coats including the surface preparation, prime coat, laying of fiber net and
instructions of the Resident Engineer.
Remove all dirt, cement laitance, form release agents, curing compounds, loose particles, paints etc. by
means of acid etching, wet or dry sand-blasting or other suitable mechanical means.
Remove all protrusions, work back to sound concrete, chiselling out any honeycombed or damaged
areas.
Stop active water leakage by using quick setting compound and grouting method, if required.
10.1.2 Measurement
Measurement shall be in square metre of the actual covered area. Nothing extra shall be allowed for
smoothing any rough surface by dressing cement mortar. Rate shall include all materials, tools, labour as
well as scaffolding all complete. It shall be paid in sq. m.
11. PAINTING
The primers shall be in seal tins. These shall be of (Berger, Nerolac, Birla, KNP, Asian or Equivalent
Brand) or equivalent as per BOQ and approved by the Resident Engineer.
11.1.1 Preparation
All surfaces shall be papered by sandpaper rubbing and cleaned properly.
The surface for cement plaster shall be patched up with the thick paste of the same primer and smoothed
after drying.
In case of timber having knots and nails holes, they should be filled with stopping and knotting materials.
The knotting material shall consist of pure shellac dissolved in Methylated spirit. For stopping, Russian talc
or gaskets shall be used. The stopping shall consist of two parts of whiting (powdered chalk) , One part of
white lead mixed together in double boiled linseed oil and well kneaded. The surface thus kneaded shall be
allowed to dry up and then sand papered, or readymade approved gaskets may be used.
In case of metal, derusting shall be done and properly cleaned after sand papering.
11.1.2 Application
After preparing the surface, the priming coat shall be applied with hairbrushes and as per manufacturer's
printed instructions.
11.1.3 Measurement
Measurement shall be done in square metre. The measurements shall be as follows:
MCICDC
Technical Specification- Civil 49
Nothing extra shall be paid for short width and surface of any shape, size. This shall include for two or
more coats inclusive of materials, scaffolding and labour complete.
11.2.1 Materials
Wall Putty shall be of Berger, Birla, JK, Asian or any other equivalent brand as per BOQ and approved by
the Engineer in sealed tins.
11.2.2 Application
Before wall putty is commenced on surface, all dirt and foreign matter shall be completely removed. A
vertical stroke with another horizontal stroke shall be termed one coat. Wall putty shall be applied to the
surface with thin smooth steel plate in a number of coats to get uniform finish. After the first coat of the
paint has hardened, the second coat is applied. Similarly required number of coats shall be given to get an
even and uniform shade.
Sample of workmanship shall be approved by the Resident Engineer prior to commencement of work.
11.2.3 Measurement
It shall be measure in square meter by multiplying length and width of actual covered area. Rate shall
include all materials, tools, labour as well as scaffolding all complete. It shall be paid in sq. m.
11.3.1 Materials
Water proofing cement shall be of (Berger, Nerolac, Birla, KNP, Asian or Equivalent Brand) as per BOQ
and approved by the Engineer in sealed tins.
11.3.2 Application
Before painting is commenced on surface, all dirt and foreign matter shall be completely removed. The
surface shall be wetted by sprinkling water with a fine spray. The surface shall be sprayed several times
with a few minutes intervals between each spraying to allow the moisture to soak into the surface. A
vertical stroke with another horizontal stroke shall be termed one coat. Paint solution to be applied to the
surface with hair brushes in a number of coats to get uniform finish. After the first coat of the paint has
hardened, It shall be cured with water at least for 24 hours before the second coat is applied. Similarly
MCICDC
Technical Specification- Civil 50
required number of coats shall be given to get an even and uniform shade. It shall be kept damp at least for
seven days.
11.3.3 Measurement
It shall be measure in square meter by multiplying length and width of actual covered area. Measurement
shall also be done as per 12.1.3. Nothing extra shall be allowed for painting any rough surface e.g. external
sand - faced plaster or work in short width or surfaces in any shape. Rate shall include all materials, tools,
labour as well as scaffolding all complete. It shall be paid in sq. m.
11.4.1 Materials
Acrylic coat plastic emulsion shall be of Nerolac, Burger, Asian Paints, Birla, KNP or any other equivalent
brand as per BOQ and approved by the Engineer in sealed tins.
11.4.2 Application
All surfaces shall be thoroughly planed and sand papered. Knotting and stopping as required shall be
attended.
11.4.3 Measurement
It shall be measure in square meter by multiplying length and width of actual covered area. Measurement
shall also be done as per 12.1.3. Nothing extra shall be allowed for painting any rough surface e.g. external
sand - faced plaster or work in short width or surfaces in any shape. Rate shall include all materials, tools,
labour as well as scaffolding all complete. It shall be paid in sq. m.
11.5.1 Materials
The paints shall be of Nerolac, Burger, Asian Paints, KNP or any other equivalent brand as per BOQ and
approved by the Engineer, in sealed tins.
11.5.3 Application
After preparing the surface and after the priming coat has been applied a top coat shall be applied. Another
coat shall be applied after the previous coat is dry. Care should be taken that dust or other foreign materials
do not settle; they will disfigure the various coats.
The same brand of materials will be used for various coats. The paints shall be used and applied as per
manufacturer's printed instruction. The paint shall be applied with bristle brushes and not horse hair ones.
MCICDC
Technical Specification- Civil 51
The paints shall be applied in the thinnest possible layers with parallel drawings. No flowing down shall be
allowed. Painting to false ceiling and acoustic tile, soft board etc. shall be done by spray painting only.
11.5.4 Measurement
It shall be measure in square meter by multiplying length and width of actual covered area. Measurement
shall also be done as per 18.1.3. The rate shall include for two or more coats inclusive of materials, labour,
scaffolding all complete. It shall be paid in sq. m.
11.6.1 Materials
The paint shall be of Nerolac, Burger, Asian Paints, Birla, KNP or equivalent or equivalent brand as per
BOQ and approved by the Engineer in sealed tins.
11.6.2 Application
Before painting is commenced on surface, all dirt and foreign matter shall be completely removed. The
surface shall be wetted by sprinkling water with a fine spray. The surface shall be sprayed several times
with a few minutes intervals between each spraying to allow the moisture to soak into the surface. A
vertical stroke with another horizontal stroke shall be termed one coat. Paint solution to be applied to the
surface with hair brushes in a number of coats to get uniform finish. After the first coat of the paint has
hardened, It shall be cured with water at least for 24 hours before the second coat is applied. Similarly
required number of coats shall be given to get an even and uniform shade. It shall be kept damp at least for
seven days.
11.6.3 Measurement
It shall be measure in square meter by multiplying length and width of actual covered area. Measurement
shall also be done as per 12.1.3. Nothing extra shall be allowed for painting any rough surface e.g. external
sand - faced plaster or work in short width or surfaces in any shape. Rate shall include all materials, tools,
labour as well as scaffolding all complete. It shall be paid in sq. m.
11.7.1 Materials
The material required for French polish shall be Chapra, Ramtilak, Sprit, Geru, sand paper, colour, shining
polish, etc.
11.7.3 Application
After preparing the surface and after the priming coat has been applied a topcoat shall be applied. Another
coat shall be applied after the previous coat is dry. Care should be taken that dust or other foreign materials
MCICDC
Technical Specification- Civil 52
do not settle, they will disfigure the various coats. A number of coats of French polish shall be applied till
the surface gives a shining appearance. Finally, shining coat shall be approved.
11.7.4 Measurement
It shall be measure in square meter by multiplying length and width of actual covered area. Measurement
shall also be done as per 12.1.3.The rate shall include for five or more coats inclusive of materials, labour,
scaffolding all complete. It shall be paid in sq. m.
16. I.S. 875 : Code of practice for structural safety of building : Loading
standards.
17. I.S. 1893 : Recommendations for earthquake resistant design of
structures.
18. B.S. 449 : The use of structural steel in building.
19. I.S. 816 : Code of practice for use of metal arc welding for general
construction.
20. I.S. 4353 : Recommendations for submerged arc welding of mild
steel and low alloy steel.
21. I.S. 823 : Code of procedure for manual metal arc welding of mild
steel.
22. I.S. 817 : Codes of practice for training and welding of metal arc
welders.
24. I.S. 1182 : Recommended practice for radiographic examination of
fusion-welded butt joints in steel plates
25. I.S. 5334 : Codes of practice for magnetic particle flaw detection of
welds
26. ASTM E. 94 : Recommended practice for radiographic testing.
27. ASTME. 109 : Dry powder magnetic particle inspection.
28. ASTME. 130 : Wet magnetic particle inspection.
29. ASTME. 165 : Liquid penetrant inspection.
30. I.S. 1477 : Code of practice for painting of ferrous metals in building
all allied finishes.
31. I.S. 1161 : Steel Tubes for structural purposes
32. IS:1363 : Hexagon Head Bolts, Screws and Nuts of product (Part I
to III)
33. I.S. 1852 : Rolling and Cutting Tolerances for Hot Rolled Steel
Products
34. I.S. 3502 : Steel Chequered Plate
I.S. 3757 :
35. High Strength Structural Bolts
36. I.S. 1200 : Method of Measurement
Contractor’s stock material may be used provided the mill test reports identified with the materials,
satisfactorily demonstrate specified grade and quality. Also all such materials supplied by
contractor shall be in a sound condition of recent manufacture, in full length, free from defects,
loose mill scale, slag intrusions, laminations, pitting, flaky crust etc. and be of full weight of
thickness specified.
Unidentified steel material may be used only with prior permission from Engineer-in- charge, in
writing, for short sections of minor importance or for small unimportant welds and connections
MCICDC
Technical Specification- Civil 54
where in the opinion of the Engineer-in-charge the quality of such material would not adversely
affect the strength and / or durability of the structure. Engineer-in-charge may also permit use of
such material for other work if adequate and random samples taken out and tested to demonstrate
conformity with specification & requirement for work in view.
Contractor shall submit the fabrication drawing for the Engineer-in-charge’s approval before
fabrication commences and make any modification therein as directed by the Engineer-in-charge.
Approval by the Engineer-in-charge of any of the drawings shall not relieve the Contractor from
the responsibility for correctness of engineering & design of connections, workmanship, fit of
parts, details, material, errors or omissions of any and all work shown thereon. The Engineer-in-
charge’s approval shall constitute approval of the size of members, dimensions and general
arrangement but shall not constitute approval of the connections between members and other
details.
Approved design drawings will be furnished to the contractor and all drawings so furnished shall
form a part of this specification. Contractor shall consult these in detail for all the information
contained therein; which pertains to and is required for his work.
The Engineer-in-Charge reserve the right to make changes, revisions to drawings even after release
for preparation of shop drawings are very likely to be made to reflect additional data/details
received and more updated requirements.
Revisions in drawings and any new drawings made to include additional work by the Engineer-in-
charge shall be considered a part of this specification and contract and the contractor shall have no
extra claims on this account.
Unless otherwise specified, the drawings and specifications are intended to include everything
obviously requisite and necessary for the proper and entire completion of the work and job shall
be carried out accordingly for the completeness as required.
Design drawings prepared by the Engineer-in-Charge will show all the dimensions and if
necessary clearance of structure, landings where necessary, size of each member, definite location
of openings at various levels and all other information necessary to enable the contractor in
prepare drawings for fabrication and erection.
It shall be clearly understood that the Engineer-in-charge’s drawings are design drawing and are
not intended to show connection details, thickness of members, cuts, notches, bends and such other
details.
In the case of variation in drawings and specifications the decision of the Engineer-in- Charge
shall be final.
Should contractor in the execution of his work, find discrepancies in the information furnished by
the Engineer-in-charge he shall refer such discrepancies to the Engineer-in-Charge before
proceeding with the work.
12.1.3 . FABRICATION:
All workmanship and finish shall be of the best quality and shall conform to the best- approved
method of fabrication. All materials shall be finished straight and shall be machined true and
square where so specified. All holes and edges shall be free of burrs. Shearing and chipping shall
be neatly and accurately done and all portions of work exposed to view shall be neatly finished.
Standard fabrication clearance as detailed in American Institute of steel construction manuals shall
generally be followed unless otherwise directed approved.
Material at the shops shall be kept clean and protected from weather.
Shop connections shall be effected by welding as specified on the Engineer-in- Charge’s design
drawings.
Rolled materials before being worked shall be straightened unless otherwise required/specified.
If straightening or flattening is necessary, it shall be done by methods that will not injure the
MCICDC
Technical Specification- Civil 55
material. Long plates shall be straightened by passing through a mangle or levelling rolls and
structural shapes by the use of mechanical or hydraulic bar straightening machines.
Heating or forging shall not be resorted to without the prior approval of the Engineer- in-charge in
writing.
Cutting may be by shearing, cropping, sawing or machine flame cutting. All re- entrant corners
shall be shaped notch-free to a radius of at least 12 mm. Sheared or cropped edges shall be
dressed to a neat workmanlike finish and shall be free from distortion and burrs.
The korf on machine flame cut edges shall be removed. Where machine flame cutting is permitted
for high tensile steel, special care shall be taken to leave sufficient metal and all flame hardened
material shall be removed by machining/edge planning.
Hand flame cutting shall be undertaken only if so permitted by Engineer-in-charge and only be
carried out by an expert in such work. Hand flame cut edges shall be ground smooth and straight.
Edge planning of sheared, chopped or gas cut edges is not intended unless the sheared, chopped or
gas cut edges are such as to warrant it or specifically called for.
12.1.4 WELDING:
MCICDC
Technical Specification- Civil 56
applicable standards.
All welds shall be free from defects like blowholes, slag inclusions, lack of penetration, under
cutting, cracks etc. All welds shall be cleaned of slag or flux and show uniform sections,
smoothness of weld metal, featheredges without overlap and freedom from porosity.
Fusion faces and surfaces adjacent to the joint for a distance of at least 50 mm on either side shall
be absolutely free from grease, paint, loose scales, moisture or any other substance which might
interfere with welding or adversely affect the quality of the weld.
Joint surfaces shall be smooth, uniform and free from fins, tears, laminations etc.
Preparation of fusion faces shall be done in accordance with the approved fabrication drawings by
shearing, chipping, achining or machine flame cutting except that shearing shall not be used for
thickness over 8 mm.
In the fabrication of cover plated beams and built up members all shop splices in each component
part shall be made before such component part is welded to other parts of the member. Wherever
weld reinforcement interiors with proper fit-up between components to be assembled for welding,
these welds shall be ground flush prior to assembly.
The members to be joined by fillet welding shall be brought and held as close together as possible
and in no event shall be separated by more than 3 mm. If the separation is 1.5 mm or greater the
fillet weld size shall be increased by the amount of separation. This shall only apply if the surfaces
are completely sealed by welds. In all other cases the fit-up shall be close enough to exclude water
after painting.
The separation between faying surfaces of lap joints and butt joints with backing plate shall not
exceed 1.5 mm. A butting part to be butt-welded shall be carefully aligned and the correct root gap
maintained throughout the welding operation.
Misalignments greater than 25 percent of the thickness of the thinner plate or 3 mm whichever is
smaller shall be corrected and in making the correction the parts shall not be drawn into a shape
sharper than 2 degrees (1 in 27.5).
Pre-qualified procedures recommended for appropriate welding standards and known to provide
satisfactory welds shall be followed. For non-standard procedures, qualification testes are
prescribed in IS: 823 shall be made to verify the adequacy of the procedures. A welding procedure
shall be prepared by the contractor and submitted to the Engineer-in-charge for approval before
the welding starts. This shall include all the details of welding procedures with reference to the
provisions of IS: 823 and IS: 4353. Approval of the welding procedure by the Engineer-in-charge
shall not relieve the contractor from his responsibility for correct & sound fabrication without
distortion to the finished structure.
Submerged arc automatic or semi-automatic welding shall generally be employed. Only where it is
not practicable to use submerged arc welding manual arc welding may be resorted. Voltage and
current (and polarity if direct current is used) shall be set according to the recommendations of the
manufacturer of the electrode being used and suitability to thickness of material, joint form etc.
The work shall be positioned for flat welding wherever practicable and overhead weld shall be
avoided.
No welding shall be done when the surface of the member is wet nor during periods of high wind
unless the welding operator and the work are properly protected.
In joints connected by fillet welds the minimum sizes of single run fillet welding or first runs and
minimum full sizes of fillet welds shall conform to the requirement of IS: 816 and IS: 823.
All complete penetration butt welds made by manual arc welding except when produced with the
aid of backing material or welded in flat position from both sides in square-edge material not over
8 mm thick with root opening not less than one-half the thickness of the thinner part joined shall
have the root of the initial layer gouged and on the back side before welding is started from that
side and shall be so welded as to secure sound metal and complete fusion throughout the entire
MCICDC
Technical Specification- Civil 57
core section.
Butt welds shall be terminated at the ends of joint in a manner that will ensure their soundness.
Where abutting parts are 20 mm or more in thickness run-on and run-off plates with similar edge
preparation and having a width not less than the thickness of the thicker part joined shall be used.
These extension pieces shall be approved upon completion of the weld and the ends of the weld
made smooth and flush with the abutting parts. Where the abutting parts are thinner than 20 mm
the extension pieces may be omitted but the ends of the butt welds shall then be chipped or gouged
out to sound metal and side welded to fill up the ends to the required reinforcement.
Each layer of a multiple layer weld except root and surface runs may be moderately peened with
light blows from a blunt tool. Care shall be exercised to prevent scaling or flaking of weld and
base metal from over peening.
No welding shall be done on base metal at a temperature below 5 oC. Base metal shall be preheated
as required to the temperature given in the table below prior to tack welding or welding. When
base metal not otherwise required to be preheated is at a temperature below zero degree centigrade
it shall be preheated to at least 20oC prior to tack welding or welding. Preheating shall bring the
surface of the base metal within 75 mm of the point of welding to the specified preheat
temperature and this temperature shall be maintained as minimum inter pass temperature while
welding is in progress.
Minimum preheat for I.S. 226 steel in thickness up to 80 mm shall be 10 degrees centigrade.
Electrodes other than low-hydrogen electrodes shall not be permitted for thickness of 75 mm and
above.
Before commencing fabrication of a member or structure in which welding is likely to result in
distortion and or locked up stresses a complete programme of fabrication, assembly and welding
shall be made and submitted to the Engineer-in-charge for approval. Such a programme shall
include, besides other appropriate details, full particulars in regard to the following:
Proposed preheating in components such as flanges and pre-setting of joints to offset expected
distortion. Make up of sub-assemblies proposed to be welded before incorporation in final
assembly.
Proposed joint forms, classification of wire and flux or covered electrodes, welding process
including fitting and welding sequence with directions in which freedom of movement is to be
allowed.
Proposed number, spacing and type of strong backs and details of jigs and fixtures for maintaining
proper fit-up and alignment during welding.
Any other special features like assembling similar members back to back or stress relief.
If so desired by the Engineer-in-Charge mock-up welding shall be carried out at contractor’s cost
to establish the efficiency of the proposed programme, with any modification suggested by the
Engineer-in-charge in limiting distortion or/ and residual stress to acceptable levels.
All welds shall be inspected for flaws by any of the methods described under the clause of
‘Inspection’ given below in this specification. The choice of the method adopted shall be
determined by Engineer-in-charge.
Contractor shall quote separately for carrying out such tests as called for in the schedule of
quantities. Contractor shall be paid only for tests, which establish soundness of welds. In case the
tests wherever defective work such tests will be at the contractor’s cost and contractor shall correct
such defects at his own cost and prove the soundness of rectified work.
The correction of defective welds shall be carried out as directed by the Engineer-in- charge
without damaging the parent metal. When a crack in weld is removed, magnetic particle inspection
or any other equally positive means as prescribed by the Engineer-in-charge shall be used to
inspect that the whole of the crack and material up to 25 mm beyond each end of the crack has
been removed. Cost of such test & operation incidental to correction shall be on contractor’s
account.
MCICDC
Technical Specification- Civil 58
12.1.5 TOLERANCES:
The dimensional and weight tolerances for rolled shapes shall be in accordance with I.S. 1852 and /
or ASTM A6. No rolled or fabricated member shall deviate from straightness by more than 1/1000th
of the length or 10 mm whichever is smaller. The length of members with both ends finished for
contact shall have a tolerance of (±) 1 mm. Members without ends finished for contact bearing shall
have a tolerance of (±) 1.5 mm for members up to 10 metres long and a tolerance of (±) 3 mm for
members over 10 metres in length.
Lateral deviation between centre line of web plates and Centre line of flange plate at contact
surface in the case of built up sections shall not exceed 6 mm.
The combined warpage and filet of flanges in welded built up sections shall not exceed 1/200th of
the flange width or 3 mm whichever is smaller.
The deviation from flatness of welded plate girder web in the length between stiffeners or a length
equal to the depth of the girder shall not exceed 1/150th of each length.
Deviations from the specified depth of welded girders measured at the Centre line of the web shall
not exceed (±) 3 mm up to a depth of 1000 mm, (±) 5 mm for depths above 1000 mm up to 2000
mm and (+) 0 mm and (-) 5 mm for depths over 2000 mm.
Magnetic Particle Test: Where root and intermediate passes of weld is examined by magnetic
particle testing such testing shall be carried out throughout. Its entire length in accordance with
ASTM specification E-109. In the case of completed welds such tests shall be carried out in
accordance with ASTM specification E-109 0r E-130 as decided by the Engineer-in-charge. If heat
treatment is performed the completed weld shall be examined after the heat treatment. All defects
shall be replaced and retested. Magnetic particle tests shall be carried out using alternating current.
Direct current may be used with the permission of the Engineer-in-charge.
Liquid Penetrant Inspection: In the case of welds examined by liquid penetrant inspection such
tests shall be carried out in accordance with ASTM E- 164 or I.S. 3650. All defects shown shall
be repaired and rechecked.
Radiographic Inspection: All full strength butt welds shall be fully radiographed in accordance
with the recommended practice for radiographic testing as per ASTM E-94 and Part U.W. 51
ASME Code Section VIII.
In the event of any failure of structural steel members to meet an inspection or test requirement,
contractor shall notify Engineer-in-charge or his authorized representative. Contractor must obtain
permission from Engineer-in-charge before repair is undertaken.
The quality control procedures to be followed to ensure satisfactory repair shall be subject to
approval by Engineer-in-charge.
Engineer-in-charge has a right to specify additional inspection or testing, as he deems necessary
and the additional cost of such testing will be borne by the department.
Contractor shall maintain records of all inspection and testing which shall be made available to
Engineer-in-charge or his authorized representative.
Some steel work particularly columns along with the tie beams/bracings may have to be shop as-
sembled to ensure satisfactory fabrication, obtaining of adequate bearing areas etc.; if so desired by
Engineer-in-charge at no extra cost to purchaser.
No dragging of steel shall be permitted. All steel shall be stored 300 mm above ground on suitable
packing to avoid damage in the order required for erection and with erection marks visible. All
storage areas shall be prepared and maintained by contractor.
MCICDC
Technical Specification- Civil 60
Steel shall not be stored in the vicinity of area where the excavation or grading will be done and if
stored temporarily, this shall be removed by contractor well before such excavation and /or grading
commence in a safe distance to avoid burial under debris.
Scratched or abraded steel shall be given a coat of the primer specified on drawings for protection
after unloading and handling prior to erection. All milled and machined surfaces shall be properly
protected from rust/corrosion by suitable coating and also from getting damaged.
After checking and inspection, all members shall be marked for identification during erection. This
mark shall correspond to distinguishing marks on approved erection drawings and shall be legibly
painted and stamped on it. The erection mark shall be stamped with a metal dye with figures at
least 20 mm high and to such optimum depth as to be clearly visible.
Structural steel frames shall be erected plumb and true. All steel columns and beams shall be
checked for plumb and level individually before and after connections are made. Temporary
bracings may be introduced wherever necessary to take care of all loads to which the structure may
be subjected including erection equipment and the operation thereof. Such bracings shall be left in
place as long as may be required for safety and stability.
For the purpose of payment, the weight of the actual completed structures shall be calculated
from the approved drawings for different items of work.
The allowances will be permitted for galvanizing, welding or for cutting margins. One Tonne
for the purpose of payment shall mean One Metric Tonne i.e., 1000 Kg.
The weight of member made out of standard rolled section such as beam, channels, angles, etc.
shall be based on the standard IS: 800. The weight of member shall be considered without
deducting for holes, notches, bevels cuts etc. Where a component consists of a cut joist or
channels, the full weight of the rolled section shall be considered only if more than half the depth
of the original section is used. Otherwise, only half the section unit weight shall be considered for
calculation of the weight of plates for skew cuts and notches of 900 square centimetre or larger.
The weight of any built-up member shall be separated into weight of each component.
MCICDC
Technical Specification- Civil 61
13. ROOFING
13.1.1 Material
Steel tubes used in the trusses shall be finished tubes conforming to the requirements specified in IS: 1161
&IS : 806-1968. Materials shall conform to drawings and BOQ.
13.1.2 Fabrication
The fabrication of trusses using steel tubes shall be done in accordance with IS : 800-1962, welding shall be
done with reference to the IS : 820 and IS : 816-1956. The component parts of the structure shall be
assembled in such a manner that they are neither twisted nor damaged. The fabricator shall submit
fabrication shop drawing for approval. The members of the truss shall be assembled and welding done
according to the drawing. All materials before assembly shall be straight end, if necessary, unless required
to be of a curvilinear form and shall be free from twist. All the works shall be carried under the instructions
of Resident engineer.
13.1.3 Bolting
Washers shall be specially shaped where necessary or other means used, to give the nuts and the heads of
bolts a satisfactory bearing. In all cases where the full bearing area of the bolt is to be developed, the
threaded portion of the bolt shall not be within the thickness of the parts bolted together and washers or
appropriate thickness shall be provided to allow the nut to be completely tightened. Edges should be
dressed to a neat workman like finish and be free from distortion where parts are to be in contact with
metal.
13.1.6 Erection
The contractor must see to it that the base plates are in one level as shown in drawing. The truss shall be
erected only after the walls and columns have been constructed to the full height. The bolts shall be fitted
loosely at first. The bolts shall be tightened hard only after two pieces of the truss have been closely fitted
till then the truss should be supported fully from underneath by means of props. All the bolts in the truss for
the whole building shall be tightened at one time. The contractor is to pay special attention so that bolts are
not bent due to mishandling of the truss.
13.1.7 Painting
All tubes shall unless specified otherwise shall be painted with one coat of red oxide paint before erection at
site and one coat of red oxide paint after erection.
MCICDC
Technical Specification- Civil 62
13.1.8 Measurement
It shall be measured in weight and shall be paid in Kg. Rate shall include the strut, purlin, base plate, gusset
plate, nut & bolts and other accessories, materials and labour all complete.
13.2.1 Quality
The surfaces of the sheets must be clean, bright and free from rust; any sheet showing a white powdery
deposit should be rejected. Iron galvanized after and not before the process of corrugations should be used.
0.55mm thick, 120 GDM Zinc Coating Coloured CGI sheet of varying width and plain GI ridge of
approved brand and colour as per drawing and BOQ approved by Resident Engineer shall be used.
All rivets will be G.I. and will be passed from below with a lead washer on the top extending 12 mm round
beyond the edge of the hole. Care should be taken that the sheet is well supported underneath and no
inundations are made on the upper surface. The sheets are secured to the iron purlins by means of 10 mm
dia. hooks or bolts passing through the sheets and 75 mm screws to the wooden purlins.
The bolt holes should be slightly larger than the diameter of the bolts and covered with a limpet or leaden
washer. All rivets, bolts etc. should be set in white lead.
The ridges and hips are covered by plain G.I. riveted sheets and fastened with limpet washers to Plain GI
sheets and overlap of 300 mm on each side and joint set in white lead.
The sheets should be fastened at eaves and ends, by continuous length of flat steel bars called "Wind Ties"
which are usually 40 mm x 6 mm with slotted holes bolted down to the bressummer or rafter at about 100
mm intervals. These bolts should not be less than 45 mm in length with 150 mm square plates over pillars
or walls. The projection at eaves is generally 32 mm to 50 mm.
The pitch is sloped up to 25 to 40 degree. The finished surface shall be uniform and the lines of
corrugations shall be uniform and the lines of corrugations shall be straight and parallel.
13.2.4 Measurement
The CGI sheet roofing shall be measured in Sqm. and plain GI sheet ridge shall be in Rm. Rate shall
include the Hilti screw/self-tapping screw and bolts, limpit, washer, bitumen washer, and other accessories,
materials and labour all complete.
13.3.1 Quality
Providing and installation of 1mm thick,120 GDM Zinc Coating, Coloured CGI plain sheet 150mm-
450mm wide colour G.I. The surfaces of the sheets must be clean, bright and free from rust; any sheet
showing a white powdery deposit should be rejected. Iron galvanized after and not before the process of
corrugations should be used.
MCICDC
Technical Specification- Civil 63
13.3.2 Measurement
The MS rain water gutter shall be measured in running meter. Rate shall include the manufacturing,
installation and other accessories, materials and labour all complete.
Providing and laying of 50mm Stone dust bed as specified in the design drawings over prepared base
course. The stone dust bed shall be well compacted by sprinkling water.
Providing and laying pre-cast interlocking concrete paving blocks 60 mm thick as specified in the designed
drawings over stone dust bed. Interlocking units shall be laid in running or stretcher bond as their
interlocking design resists the forces that cause creep. Each block is place against the adjacent units without
disturbing the other units, developments are taking place at this time relative to mechanized placement of
individual units or clusters of block that are tied together with break-away webs. The order of laying should
be such that it is never necessary to force a block between those already laid.
Where whole units do not fit at the edges of a pavement, cut block are used to fill the spaces. Spaces left
around manholes and drainage inlets are treated in the same manner. This is readily accomplished with a
small hydraulic block splitter. Spaces less than about 40mm can be filled with sand.
Concrete or masonry sand should be spread over the installed paving blocks so that it may be vibrated into
the joints. After enough area is laid to make vibration worthwhile, the blocks are vibrated to their final level
to their final level with a plate vibrator. The vibrating action compact the sand and also forces some sand
up between the joints. After the initial vibration, sand is brushed over the surface and is vibrated into the
joints by additional two passes of the vibrator. This locks the block together so that they no longer act as
individual units but as a group in distributing loads. Vibration also evens out any minor variations in level
between units. The vibrator should not be passed closer than about one yard from and unrestrained edge.
After surplus sand is removed the pavement is completed and ready for traffic. If heavy trucks are used to
deliver materials close to the work, the sanding and vibrations should be done before the trucks are
permitted to enter that section of the pavement.
Paving blocks should be installed hand tight and level on the undisturbed stone dust bed.
Concrete or masonry sand should be spread over the installed paving blocks so that it may be vibrated
into the joints.
Roller or plate vibratos should be used to compact the base course and stone dust and to vibrate the
sand into the stone joints.
Excess sand should be swept into the joints or disposed of from surface area.
The completed paving stone installation should be washed down and cleaned to provide a clean
finished workmanlike installation.
14.1.5 Measurement
Measurement shall be in square metre of the actual covered area. Nothing extra shall be allowed for sand
blending, small hydraulic block splitter, etc. Rate shall include all materials, tools, labour, etc., including
50 mm thick stone dust bed all complete. It shall be paid in sq.m. The crushed aggregate base course shall
be paid separately in cum.
Turfs shall be interpreted as grass carpet of size 30cmx 30 cm slip that is seasonally dormant during cold or
dry seasons and is capable of renewing growth after the dormant period. The turfs shall be brought by the
Contractor from areas where the top soil is reasonably fertile and contain a high percentage of loamy
topsoil. Turfs shall be cut or stripped from living, thickly matted turf relatively free from weeds or other
undesirable foreign plants, large stones, roots or other materials which might be detrimental to the
development of the turf or to future maintenance. Turf including the soil containing the roots shall be
planted in a neat and systematic way.
The top soil on which Turfing is to be done shall be free of admixture of sub-soil, stone, gravel, clay lumps,
plants or their roots, sticks or other extraneous material exceeding 50 mm. diameter. It shall be clay loam.
The top soil shall be approved by the Engineer before being placed.
The strips of turf shall be in uniform widths not less than 230 mm. and length not more than 460 mm. and
such lengths should be readily lifted without breaking, tearing or loss of soil. The turfs shall be transplanted
within 24 hours from the time it is stripped unless storing is necessary. If stored, turfs shall be stacked, kept
moist and protected from exposure to sun. Turfs shall be cut and moved only when the soil mixture
conditions are such that favorable results can be expected. Turfing shall be performed only during the
seasons when satisfactory results can be expected. Turfing may be transplanted during drought free periods
with the approval of the Engineer provided the turf bed is watered to moisten the soil to a depth of at least
100 mm immediately prior to laying the turf.
The turf shall be carefully placed by hand, edge to edge with staggered joints, in rows at right angle to the
slopes, commencing at the base of the area to be turfed and working upward. The turf shall immediately be
pressed firmly into contact with bed by tamping to provide a true and even surface. Screened soil of good
quality shall be used to fill all cracks between turfs. The quality of fill soil shall not cause smothering of the
grass.
The Contractor shall provide general care for the turfed area, protect against traffic and shall continue care
until final inspection and acceptance of the work. If the surface become gullied or otherwise damaged
during the period the affected area shall be repaved to stabilise grade and condition as directed.
14.2.1 Measurement
It shall be measured in square meter on the ground surface including materials and labour.
MCICDC
Technical Specification- Civil 65
14.3.1 Materials
The size and type of flowers to be planted shall be approved by Engineer prior to supply and plantation.
14.3.2 Measurement
It shall be measured in Numbers of flower planted and running meter as per BOQ.
14.4.1 Materials
The variety and size of tree plant shall be as per approval of Resident Engineer. The plant shall not have the
dead branches and shall have fresh full roots. The Guard post of specified size and shape shall be fixed
around the plant by fixing over concrete ring base of minimum 150mm thickness.
14.4.2 Measurement
It shall be measured in Numbers of Tree planted with tree guard.
14.5 KERBSTONE
14.5.1 General
providing and laying M20 precast in situ concrete in kerbs with 12 mm thick 1:3 cement sand mortar
bedding and joints including foundation excavation, levelling, Flat Brick Soling and 75mm thick/30cm
wide 1:2:4 PCC works (kerb stone size 150*200*350) all complete
14.5.2 Measurement
It shall be measured in Running meter of Kerb Stone so laid. No extra payment shall be done for stone
soling and PCC works.
15. MISCELLANEOUS
15.1.1 Measurement
It shall be measured in Kg. Rate shall be inclusive of all materials and labour complete.
MCICDC
Technical Specification- Civil 66
15.2.1 Materials
The Mild Steel pipe of 20x20mm square and 2mm wall thickness shall be cut to shape, and size, properly
welded to fill the gaps in every joint. The Pipe shall confirm the IS 4923:1997 Specification for structural
Steels
15.2.2 Installation
The end of Hollow square pipe along the face of concrete Member shall be embedded for minimum of 6"
inside the concrete or properly welded in structural steels or frames for firm finishing. Not any slots or
holes in welded joints are permitted while preparing the grill of square pipe. Spacing, Size and Shape of the
finished grill shall be as per the drawing or as instruction of Engineer. The top end of Vertical pipe shall be
finished with minimum 50mm high pyramid of 20x20mm base. 100x100x5mm MS hollow pipe shall be
erected at every 2 m interval between Concrete Pillars for framing the Grill from either Side. The Post shall
be properly erected over the concrete block of 1:1.5:3 Cement concrete foundation. The cost of Concrete
foundation shall be paid as separate item.
15.2.3 Measurement
The measurement shall be done in square meter (m2) of finished grill by multiplying the clear spacing
between two concrete pillars with total height of grill from base of vertical 20x20x2mm square pipe with tip
of square pyramid (20x20mm base). The rate shall include the vertical post from foundation to top,
horizontal pipes, vertical pipes, semi-circular design pipes, welding, joining, fixing, finishing and one coat
of primer all complete.
15.3 BOUNDARY WALL USING MS ANGLE, POST, GI MESH AND FENCE WIRE
Providing, Fabrication, Fixing and Primer Painting of Boundary wall with 40*40*5 mm MS Post @ 2m c/c,
frame of 25x25x5 and 25x25x5mm MS angle and 10SWG GI chain link of mesh size 50x50mm at Angle
Frames with 10mm dia hook for chain-link anchorage and 12mm dia anchor Holdfast jammed and
25*25*5mm angle bracing at Every 15m length and change in direction/bend all complete as per Drawing
and Technical Specifications and Engineer’s Instruction
15.3.1 Installation
The 40*40* 5mm MS Post shall be erected at every 2m spacing c/c. embedded in the concrete Block
(1:1.5:3) from beneath the foundation. The top 70cm length of Post shall be bend 45 degree for fencing
works. Fencing shall be properly hooked in the post. The MS angles of specified size in BoQ shall be used
as a frame for GI chain link mesh. Horizontal top of the Angle frame shall be welded with the 150mm
height 3*20mm MS Strip with hook type design at top . The spacing of the strip shall not be more than
120mm c/c. Three layer of barbed wire fence shall be fixed in the angled portion of post. The angle frame
shall be properly welded in the Metal post or fixed with bolt in post as per instruction of Engineer. The MS
frame and post shall be painted with aluminium paint all complete after installation.
15.3.2 Measurement
The measurement shall be done in square meter (m2) of finished grill by multiplying the C/C spacing
between two Posts with total height of grill from Lower angle to upper angle. i.e. height of the vertical
strips shall be excluded in measurement. The total length of Metal post from the foundation to the top end
including the bend portion has been included in this item and no extra payment shall be done for this.
15.3.3 Payment
Payment of finished works shall be done in square meter of the above measured quantity. The Cost of
Supplying, fabrication, fixing, painting all complete has been included. However in case of fencing, the
payment shall be done as separate item in Running meter basis for a group of 3 rows of wire supplying and
fixing all complete.
MCICDC
Technical Specification- Civil 67
16.1 GENERAL
b. Contractor shall be responsible for checking field dimensions and site conditions.
c. Unless otherwise indicated all construction joints shall be roughened joints with 5 mm minimum
Amplitude.
a. No measurement shall be directly taken from the print only written dimensions shall be followed.
16.2 FOUNDATION
a. Foundations shall be on undisturbed soil.
b. Soil bearing capacities shall be verified in the field. Notify Engineer immediately of any soft
pockets or other adverse soil conditions encountered.
c. The line of slope between adjacent excavations for footings or along stepped footing shall not
exceed a rise of 1 in a run of 2.
d. Placing of foundation concrete shall be done as soon as excavations have been completed and
approved by the Engineer.
16.3 BACKFILLING
a. Backfilling to foundation wall shall be done simultaneously on both sides.
b. Backfilling shall be done in layers of not more than 150 mm, each layer being properly compacted
to at least 95 % modified protector density.
b. Reinforcing steel shall be new hot rolled deformed bars having a minimum yield strength of 415
N/mm2 and conforming to is 1786;1979 or is 1139 ; 1966 marked.
c. Minimum reinforcing laps shall be in accordance with IS - 456;1978 and as specified on structural
drawings.
d. Cover to reinforcing steel shall be in accordance with IS - 456;1978 and as specified in structural
drawings.
f. Provide corner bars to match horizontal reinforcing steel in walls and footings.
MCICDC
Technical Specification- Civil 68
g. Provide dowels to walls and piers, to match vertical bars in walls and piers, unless otherwise
indicated.
h. Plumbing slots, holes around pipes, ducts or other items which pass through concrete slab or wall
shall be filled and patched to the same depths as the slab or wall.
i. Unless otherwise indicated, all horizontal and vertical construction joints shall be roughened joints
with 5 mm. minimum Amplitude.
j. Slabs on grade shall be cast in panels bounded by column guidelines in a checkered board pattern
allow at least 48 hours between casting of adjacent panels.
k. In the slabs on grade, welded wire fabric of equivalent area may be used in lieu of reinforcing bars,
reinforcing steel shall be 35 mm. clear from the top of slab.
l. Hanging devices for piping shall be provided at the time of casting, breaking out concrete for
hanging from reinforcing bars will not be permitted.
MCICDC