Professional Documents
Culture Documents
Item
Description of Works Unit Nos Quantity Rate Amount (NPR) Remarks
No.
A. SANITARY INSTALLATION
Stainless Steel Kitchen Sink 37" long 8" deep with sink
3 Set 2 2 9623.20 19246.40
cock, bottle trap all complete set.
SANITARY ESTIMATE
Item
Description of Works Unit Nos Length Breadth Height Quantity Rate Amount (NPR) Remarks
No.
A. SANITARY INSTALLATION
Ground Floor
Normal Toilet 10 10
Disable Toilet 3 3
First Floor 0
Normal Toilet 4 4
Disable Toilet 3 3
Canteen Block 4 4
Set Total 24 9326.50 223836.00
Stainless Steel Kitchen Sink 37" long 8" deep with sink
3 Set 2 2 9623.20 19246.40
cock, bottle trap all complete set.
Ground Floor
Normal Toilet Set 15 15
Total 15 7613.00 114195.00
12 Grad bar American standard No. 12 12 5759.55 69114.54 2 nos per disable toilet
13 CP Soap tray Set 24 24 436.43 10474.20 as per no of basin
14 Stainless steel towel rod 1.5*45cm (1/2"*18") Set 10 10 1834.25 18342.50 for first floor -bath room /wash basin
15 Looking mirror Modi guard 450*600mm (18"*24") Nos 24 24 2650.18 63604.20 as per no of basin
34 50 mm dia CPVC Ball Valve, CTS Socket all complete. Nos 12 12 2785.53 33426.36
EXTERNAL WORKS
59 SEPTIC TANK
60 SOAK PIT
#REF!
Item No. Description of Works Unit Nos Total Quantity Rate Amount (NPR) Remarks
16 Amps SP MCB Geco, North west, ISI or eqvt. For light and
1.2 Nos 342.00 342.00 165.60 56,635.20
power supply.
6 Amps SP MCB Geco, North west, ISI or eqvt. For light and
1.3 Nos 162.00 162.00 165.60 26,827.20
power supply.
1.4 40 Amps TP MCB Siemens, Geco,Legrend or eqvt. For main. Nos 18.00 18.00 688.00 12,384.00
-
2 Power Socket Point Wiring -
1 1 gang 1 way switch or North west type eqvt.etc all complete. Nos 10.00 10.00 434.30 4,343.00
2 2 gang 1 way switch or North west type eqvt.etc all complete. Nos 11.00 11.00 478.32 5,261.52
3 3 gang 1 way switch or North west type eqvt.etc all complete. Nos 41.00 41.00 478.32 19,611.12
4 4 gang 1 way switch or North west type eqvt.etc all complete. Nos 38.00 38.00 608.62 23,127.56
5 6 gang 1 way switch or North west type eqvt.etc all complete. Nos 3.00 3.00 716.65 2,149.95
6 8 gang 1 way switch or North west type eqvt.etc all complete. Nos 4.00 4.00 1,139.49 4,557.96
488673245.xlsx Page 6
Item No. Description of Works Unit Nos Total Quantity Rate Amount (NPR) Remarks
1 External Work -
1 CABLES & WIRES - - -
Supply, installation, testing & commissioning of following sizes
of PVC insulated multistranded Copper/Aluminium conductor
cables/wires of 1.1 KV grade to be lay below ground level - - -
through HDPE conduit as required all complete.
-
Supply,Installation and
assembling,erection,connecting,testing and
J -
commissioning of the following External light fixtures
complete with all accessories as required.
1.1 3 mtrs Street light pole Nos 8.00 8.00 4,500.00 36,000.00
1.2 Gate post light Nos 2.00 2.00 4,500.00 9,000.00
K Main Distribution panels/Sub Panel Board -
i Main Distribution panels -
60/100 Sub Panel board made of mild steel sheet double cover
floor mount suitable color push type lock suitable size for
1.1 set 6.00 6.00 34,664.34 207,986.01
housing the following items, all complete.12''*36"*48"
size(space for 5 no MCB)
80A TP MCB Siemens,Ge,Legrand or eqvt. for incoming for
1.2 set 6.00 6.00 6,514.75 39,088.50
panel board.
40A TP MCB Siemens,Ge,Legrand or eqvt. for outgoing DB
1.3 set 18.00 18.00 6,514.75 117,265.50
box.
30A TP MCB Siemens,Ge,Legrand or eqvt. for outgoing DB
1.4 set 6.00 6.00 5,750.00 34,500.00
box.
1.6 Voltmeter 0-500 v with selector switch set 6.00 6.00 1,391.50 8,349.00
1.7 Indicator lamp with fuse. set 18.00 18.00 299.81 5,396.49
1.8 Ammeter 0-500 A with selector switch set 6.00 6.00 1,238.44 7,430.61
1.9 Selector switch set 6.00 6.00 899.42 5,396.49
2 CT coil of suitable ratio set 24.00 24.00 1,811.48 43,475.52
-
L NEA SUPPLY -
Supply, installation, testing and commissioning of Energy
i Meter ( 20-80 A, Three Ph, 3x380 v, 50 Hz ) as per NEA rules Set 1.00 1.00 28,500.00 28,500.00
and regulation .
488673245.xlsx Page 7
Item No. Description of Works Unit Nos Total Quantity Rate Amount (NPR) Remarks
L 150A 4 pole pannel mounting changeover switch Set 1.00 1.00 14,932.75 14,932.75
M Earthing & Lighting Protection -
Earthing with cu plate size 65 cm x 65 cm x3.15 mm with G.N.
8 cu wire for earth continuity from panel board to earthing site
1 all complete with necessary accessories: salt,coal,cu Set 1.00 1.00 10,085.50 10,085.50
plate,HDEP polythene pipe etc) as per specification and
instruction of site engineer.
Supply , installation & testing of Air Termination Unit of 2m
2 long solid copper rod of 16mm dia. to be mount on the roof of Set 1.00 1.00 5,500.00 5,500.00
the building.
Supply , installation & testing of 25mmx3.15 mm copper strip
3 for horizontal conductor ,duly brazed to lightning arrester & to Rm. 8.00 8.00 1,350.00 10,800.00
be laid on roof of the building .
Supply , installation & testing of 25x3.15 Sq. mm copper strip
for down conductor ,duly brazed to horizontal conductor & to
4 Rm. 15.00 15.00 1,450.00 21,750.00
be clamp from horizontal conductor to the test point of the
earthing.
Total 4,912,666.51
488673245.xlsx Page 8
ELECTRICAL ESTIMATE
Item
Description of Works Unit length Breadth Height Total Quantity Rate Amount (NPR) Remarks
No.
16 Amps SP MCB Geco, North west, ISI or eqvt. For light and
1.2 Nos 342.00 342.00 165.60 56,635.20
power supply.
6 Amps SP MCB Geco, North west, ISI or eqvt. For light and
1.3 Nos 162.00 162.00 165.60 26,827.20
power supply.
1.4 40 Amps TP MCB Siemens, Geco,Legrend or eqvt. For main. Nos 18.00 18.00 688.00 12,384.00
Main Building
2x18 watt CFL light Fixture with mirror optic point 207.00 207.00
12 watt lpannel led light point 183.00 183.00
42" Ceiling Fan point 138.00 138.00
Canteen -
2x18 watt CFL light Fixture with mirror optic point 24.00 24.00
12 watt lpannel led light point 4.00 4.00
42" Ceiling Fan point - -
Total 556.00 843.25 468,847.00
Main Building
15 amp 3 pin power socket point 100.00 100.00
Canteen -
15 amp 3 pin power socket point 3.00 3.00
Total 103.00 1,186.13 122,170.88
D Switch Socket Outlets
6 8 gang 1 way switch or North west type eqvt.etc all complete. Nos
1.1 42'' ceiling fan Almonard/Bajaj or eqvt.etc all complete. Set 138.00 138.00 5,235.95 722,561.10
1.2 9"exhaust fan Almonard /Bajaj or eqvt.etc all complete. Set - -
G Telephone, telephone and Network Point Wiring:
1 Telephone system
Supply and installation of telephone point wiring from
telephone junction box to individual apartment point with 2-
1.1 Pair jelly filled pvc insulated telephone cable through 16 mm Point 2.00 2.00 850.00 1,700.00
internal dia HDPE conduit concealed as per drawing and
specification.
2 Network Point Wiring:
Supply and installation of Network point wiring with 1 no of
CAT-5E UTP cable wires through PVC conduit from TJB to
Point 6.00 6.00 1,550.00 9,300.00
various points excluding router, socket as per drawing and
specification.
3 Telephone and Network socket
1.1 Computer socket( RJ-45) Nos 4.00 4.00 632.40 2,529.60
1.2 Telephone (RJ-11) set 2.00 2.00 610.39 1,220.78
H Power Back up system( Solar back up System)
250 Wp PV Module 24V - 4 NOS Nos 4.00 4.00 25,875.00 103,500.00 90 rs per watt of module
200AH solar Tubular plate battery- 4 Nos 4.00 4.00 36,915.00 147,660.00
3KVA 24V Hybride inverter Nos 1.00 1.00 71,500.00 71,500.00
Mounting Frame Nos 1.00 1.00 5,800.00 5,800.00
Battery Rack Nos 1.00 1.00 4,500.00 4,500.00
I External Works
1 External Work
1 CABLES & WIRES -
Supply, installation, testing & commissioning of following sizes
of PVC insulated multistranded Copper/Aluminium conductor
cables/wires of 1.1 KV grade to be lay below ground level -
through HDPE conduit as required all complete.
Supply,Installation and
assembling,erection,connecting,testing and
J
commissioning of the following External light fixtures
complete with all accessories as required.
1.1 3 mtrs Street light pole Nos 8.00 8.00 4,500.00 36,000.00
1.2 Gate post light Nos 2.00 2.00 4,500.00 9,000.00
K Main Distribution panels/Sub Panel Board
i Main Distribution panels
60/100 Sub Panel board made of mild steel sheet double cover
floor mount suitable color push type lock suitable size for
1.1 set 6.00 6.00 34,664.34 207,986.01
housing the following items, all complete.12''*36"*48"
size(space for 5 no MCB)
80A TP MCB Siemens,Ge,Legrand or eqvt. for incoming for
1.2 set 6.00 6.00 6,514.75 39,088.50
panel board.
40A TP MCB Siemens,Ge,Legrand or eqvt. for outgoing DB
1.3 set 18.00 18.00 6,514.75 117,265.50
box.
30A TP MCB Siemens,Ge,Legrand or eqvt. for outgoing DB
1.4 set 6.00 6.00 5,750.00 34,500.00
box.
1.6 Voltmeter 0-500 v with selector switch set 6.00 6.00 1,391.50 8,349.00
1.7 Indicator lamp with fuse. set 18.00 18.00 299.81 5,396.49
1.8 Ammeter 0-500 A with selector switch set 6.00 6.00 1,238.44 7,430.61
1.9 Selector switch set 6.00 6.00 899.42 5,396.49
2 CT coil of suitable ratio set 24.00 24.00 1,811.48 43,475.52
L NEA SUPPLY
Supply, installation, testing and commissioning of Energy
i Meter ( 20-80 A, Three Ph, 3x380 v, 50 Hz ) as per NEA rules Set 1.00 1.00 28,500.00 28,500.00
and regulation .
L 150A 4 pole pannel mounting changeover switch Set 1.00 1.00 14,932.75 14,932.75
M Earthing & Lighting Protection
Earthing with cu plate size 65 cm x 65 cm x3.15 mm with G.N.
8 cu wire for earth continuity from panel board to earthing site
1 all complete with necessary accessories: salt,coal,cu Set 1.00 1.00 10,085.50 10,085.50
plate,HDEP polythene pipe etc) as per specification and
instruction of site engineer.
Supply , installation & testing of Air Termination Unit of 2m
2 long solid copper rod of 16mm dia. to be mount on the roof of Set 1.00 1.00 5,500.00 5,500.00
the building.
Supply , installation & testing of 25mmx3.15 mm copper strip
3 for horizontal conductor ,duly brazed to lightning arrester & to Rm. 8.00 8.00 1,350.00 10,800.00
be laid on roof of the building .
Supply , installation & testing of 25x3.15 Sq. mm copper strip
for down conductor ,duly brazed to horizontal conductor & to
4 Rm. 15.00 15.00 1,450.00 21,750.00
be clamp from horizontal conductor to the test point of the
earthing.
Total 4,912,666.51
1
I.P W C. COMODE with low level cistern complete set.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 850.00 2,550.00
un skilled 3 nos 520.00 1,560.00 4,110.00
a. Porcelain clay white glaze
3
50x40cm OVAL WASH BASIN with mixer COMPLETE SET
c. 15 mm CP basin mixer
jaquar,Parrtware or equivalent 1 nos 2,500.00 2,500.00
d. screw etc Ls 40.00 5,370.00
Total Rate 8,110.00
Extra 10% -
Actual rate 8,110.00
15% contractor overhead 1,216.50
4
Kitchen Sink 37" long stainless steel
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 2 nos 850.00 1,700.00
un skilled 1 nos 520.00 520.00 2,220.00
a. Stainless steel, 19"x16" size
materials Bowl with drain board. Heavy
type 1 sets 2,958.00 2,958.00
b. Pvc bottle trap with 32mm Dia
5
61x41x38 cm. Large flat back white glazed urinal with bracket (Hindware,Parryware,clasica,cera or equivalent)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 850.00 1,700.00
un skilled 1 nos 520.00 520.00 2,220.00
6
15mm CP Bib Cock
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
materials 15mm CP bib cock 1 nos 1,037.04 1,037.04 1,037.04
Total rate 1,130.54
Extra 10% 103.70
Actual rate 1,234.24
15% contractor overhead 185.14
Rate per nos Rs. 1419.38 Total (Rs.) 1,419.38
8
15mm Auto closing Bib Cock with aerator
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
materials a. 15mm Auto closing bib cock wi 1 nos - - -
Total rate 93.50
Extra 10% -
Actual rate 93.50
15% contractor overhead 14.03
Rate per nos Rs. 107.53 Total (Rs.) 107.53
9
15mm Urinal Auto closing Valve with built in control cock
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
materials a. 15mm Urinal Auto closing valve 1 nos 2,300.00 2,300.00 2,300.00
built - in control cock
Total rate 2,393.50
Extra 10% 230.00
Actual rate 2,623.50
15% contractor overhead 393.53
Rate per nos Rs. 3017.03 Total (Rs.) 3,017.03
10
C.P. 15mm Angle valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
materials a. 15mm fancy type angle valve 1 nos 660.00 660.00 660.00
Total rate 753.50
Extra 10% -
Actual rate 753.50
15% contractor overhead 113.03
Rate per nos Rs. 866.53 Total (Rs.) 866.53
12
1.5cm C.P. Water Spray
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 850.00 212.50
un skilled 0.17 nos 600.00 102.00 314.50
a.Water spray (Health faucet)
materials
with 1.2 m. long flexible pipe. 1 sets 1,146.00 1,146.00 1,146.00
Total rate 1,460.50
Extra 10% -
Actual rate 1,460.50
15% contractor overhead 219.08
Rate per No Rs. 1679.58 Total (Rs.) 1,679.58
13
CHROME PLATE TOILET PAPER HOLDER
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
a.Chrome plate toilet paper
14
PVC FLOOR TRAP 11x7.5cm (4" X 2½")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
un skilled 0.10 nos 520.00 52.00 145.50
materials Floor Trap 11x7.5cm (4" X 2½") 1 nos 185.00 185.00 185.00
Total rate 330.50
Extra 10% 18.50
Actual rate 349.00
15% contractor overhead 52.35
Rate per nos Rs. 401.35 Total (Rs.) 401.35
16
CHROME PLATE SOAP DISH.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
a.C.P Soap dish
materials 1 nos 220.00 220.00
b.Zink oxide screw etc. Ls 40.00 260.00
Total rate 353.50
Extra 10% 26.00
Actual rate 379.50
15% contractor overhead 56.93
Rate per nos Rs. 436.43 Total (Rs.) 436.43
17
Stainless Steel towel rod 1.5x45cm (½"x18")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.22 nos 850.00 187.00 187.00
materials a . Stainless Steel Towel rod 1 nos 1,240.00 1,240.00
b. Screws etc. Ls 40.00 1,280.00
Total rate 1,467.00
Extra 10% 128.00
Actual rate 1,595.00
15% contractor overhead 239.25
Rate per nos Rs. 1834.25 Total (Rs.) 1,834.25
18
Looking Mirror Modi guard 450x600mm (18"x 24")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.33 nos 850.00 280.50 280.50
materials a.Bevelled edge looking mirror 5 1 nos 1,800.00 1,800.00
b . Screws Ls 40.00 1,840.00
Total rate 2,120.50
Extra 10% 184.00
Actual rate 2,304.50
15% contractor overhead 345.68
Rate per nos Rs. 2650.18 Total (Rs.) 2,650.18
20
CPVC Pipe SDR 11, 20mm (3/4") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.01 nos 850.00 8.50
un skilled 0.01 nos 520.00 5.20 13.70
21
CPVC Pipe SDR 11, 25mm (1") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.01 nos 850.00 8.50
un skilled 0.01 nos 520.00 5.20 13.70
23
CPVC Pipe SDR 11, 40mm (1 1/2") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.011 nos 850.00 9.35
un skilled 0.019 nos 520.00 9.88 19.23
24
CPVC Pipe SDR 11, 50mm (2") CTS
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.011 nos 850.00 9.35
un skilled 0.019 nos 520.00 9.88 19.23
26
CPVC CTS. 20 mm ball Valve( 3/4")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
materials a. 20 mm CPVC ball valve, CTS so 1 set 486.00 486.00 579.50
Total rate 579.50
Extra 10% 48.60
Actual rate 628.10
15% contractor overhead 94.22
Rate per Rm Rs. 722.32 Total (Rs.) 722.32
27
CPVC CTS. 25 mm ball Valve (1")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
materials a. 25 mm CPVC ball valve, CTS so 1 set 588.00 588.00 681.50
Total rate 681.50
Extra 10% 58.80
Actual rate 740.30
15% contractor overhead 111.05
Rate per Rm Rs. 851.35 Total (Rs.) 851.35
28
CPVC CTS. 32 mm ball Valve (1 1/4")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
materials a. 32 mm CPVC ball valve, CTS so 1 set 1,371.00 1,371.00 1,464.50
Total rate 1,464.50
Extra 10% 137.10
Actual rate 1,601.60
15% contractor overhead 240.24
Rate per Rm Rs. 1841.84 Total (Rs.) 1,841.84
30
CPVC CTS. 50 mm ball Valve (2")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
materials a. 50 mm CPVC ball valve, CTS so 1 set 2,117.00 2,117.00 2,210.50
Total rate 2,210.50
Extra 10% 211.70
Actual rate 2,422.20
15% contractor overhead 363.33
Rate per Rm Rs. 2785.53 Total (Rs.) 2,785.53
31
G.M 50mm float valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.44 nos 850.00 374.00 374.00
materials a.50 mm float valve 1 nos 4,599.00 4,599.00 4,599.00
Total rate 4,973.00
Extra 10% 459.90
Actual rate 5,432.90
15% contractor overhead 814.94
Total (Rs.) 6,247.84
32
1000 litre PVC WATER TANK
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 850.00 2,550.00
un skilled 4 nos 520.00 2,080.00 4,630.00
a. 1000 liter PVC water tank
with Inlet, outlet, over flow,
cleanout hole etc. all compete
34
2 H.P. Electrical motor water pump Multi stage, coupled pump (Crompton)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 4 nos 850.00 3,400.00
un skilled 3 nos 520.00 1,560.00 4,960.00
a.2 H P Electricmotor pump with
35
50 mm dia uPVC PIPE 6 KG/CM. SQ.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled(1/18) 0.06 nos 850.00 51.00
un skilled(1/10) 0.10 nos 520.00 52.00 103.00
a.50 mm dia. uPvc pipe
materials 1 RM 99.00 99.00
b. Jointing materialsetc. Ls 99.00
Total rate 202.00
Extra 10% 9.90
Actual rate 211.90
15% contractor overhead 31.79
Rate per Rm Rs. 243.69 Total (Rs.) 243.69
37
110 mm dia UPVC PIPE 6 KG/CM. SQ
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.17 nos 850.00 144.50
un skilled 0.20 nos 520.00 104.00 248.50
a.110 m m dia.UPvc pipe
38
Motor Starter Switch
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 850.00 212.50
un skilled 0.17 nos 520.00 88.40 300.90
a. Motor Starter Switch
39
G.M. 25mm float valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.22 nos 850.00 187.00 187.00
materials G.M. 25mm float valve 1 nos 1,297.00 1,297.00 1,297.00
Actual rate 1,484.00
15% contractor overhead 222.60
Rate per nos Rs. 1706.60 Total (Rs.) 1,706.60
40
41
200 mm RCC hump pipe NP2
For 32m
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 4 nos 850.00 3,400.00
un skilled 20 nos 520.00 10,400.00 13,800.00
materials a.200 mm RCC hump pipe np2 32 Rm 673.00 21,536.00
b.200mm RCC collar 13 nos 170.00 2,210.00
c. cement 0.052 mt - -
d. sand 0.08 cum - -
e. Jute 2.4 kg 50.00 120.00 23,866.00
Total rate 37,666.00
Extra 10% 2,386.60
Actual rate 40,052.60
15% contractor overhead 6,007.89
Rate per Rm Rs. 1439.39 Total (Rs.) 46,060.49
42
Foldable hinge
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 850.00 1,700.00
un skilled 1 nos 520.00 520.00 2,220.00
materials Foldable hinge 1 nos 1,212.00 1,212.00
1,212.00
Total rate 3,432.00
Extra 10% 121.20
Actual rate 3,553.20
15% contractor overhead 532.98
4086.18 Total (Rs.) 4,086.18
44
Pressure Senser Switch
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 850.00 212.50
semi skilled 0.17 nos 520.00 88.40 300.90
a. Pressure Senser Switch
45
C I Tank Cover 24"x24" (50Kg) Square (Locking Type)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.33 nos 850.00 280.50 280.50
C I Tank Cover 24"x24" (50Kg)
materials Square (Locking Type) 1 nos 10,038.00 10,038.00 10,038.00
Total rate 10,318.50
Extra 10% 1,003.80
Actual rate 11,322.30
15% contractor overhead 1,698.34
13020.64 Total (Rs.) 13,020.64
46
5 kg fire extingusher ABC type Minimax, all complete set eversafe or equivalent .
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 1.00 nos 850.00 850.00 850.00
5 kg fire extingusher ABC type
Minimax, all complete set
materials eversafe or equivalent . 1 nos 5,500.00 5,500.00 5,500.00
Total rate 6,350.00
Extra 10% 550.00
Actual rate 6,900.00
15% contractor overhead 1,035.00
7935.00 Total (Rs.) 7,935.00
10 LS 11.00 110.00
1569.60
Total rate 3619.60
Extra 10% 156.96
Actual Rate 3776.56
Rate per set Rs. 434.30 15% conctractor overhead 566.48
Total (Rs.) 4343.04
0 LS 11.00 0.00
0.00
Total rate 0.00
Extra 10% 0.00
Actual Rate 0.00
Rate per set Rs. 0.00 15% conctractor overhead 0.00
Total (Rs.) 0.00
10 LS 11.00 110.00
1917.60
Total rate 3967.60
Extra 10% 191.76
Actual Rate 4159.36
Rate per set Rs. 478.32 15% conctractor overhead 623.90
Total (Rs.) 4783.26
10 LS 11.00 110.00
1917.60
Total rate 3967.60
Extra 10% 191.76
Actual Rate 4159.36
Rate per set Rs. 478.32 15% conctractor overhead 623.90
Total (Rs.) 4783.26
10 LS 11.00 110.00
2947.60
Total rate 4997.60
Extra 10% 294.76
Actual Rate 5292.36
Rate per set Rs. 608.62 15% conctractor overhead 793.85
Total (Rs.) 6086.21
10 LS 11.00 110.00
3801.60
Total rate 5851.60
Extra 10% 380.16
Actual Rate 6231.76
Rate per set Rs. 716.65 15% conctractor overhead 934.76
Total (Rs.) 7166.52
10 LS 11.00 110.00
5280.60
Total rate 9380.60
Extra 10% 528.06
Actual Rate 9908.66
Rate per set Rs. 1139.49 15% conctractor overhead 1486.30
Total (Rs.) 11394.96
10 LS 11.00 110.00
4550.00
Total rate 6600.00
Extra 10% 455.00
Actual Rate 7055.00
Rate per set Rs. 811.32 15% conctractor overhead 1058.25
Total (Rs.) 8113.25
LS 25.00
693.00
Tatal rate 1718.00
Extra 10% 69.30
Actual Rate 1787.30
Rate per set Rs. 2055.40 15% conctractor overhead 268.10
Total (Rs.) 2055.40
LS 25.00
12985.00
Tatal rate 12985.00
Extra 10% 0.00
Actual Rate 12985.00
Rate per set Rs. 14932.75 15% conctractor overhead 1947.75
Total (Rs.) 14932.75
Panel Board & Accessaries
LS 46.00
25539.00
Total rate 27589.00
Extra 10% 2553.90
Actual Rate 30142.90
Rate per set Rs. 34664.34 15% conctractor overhead 4521.44
Total (Rs.) 34664.34
MCCB 10KA to 40KA-Siemens,GE, Legrand, C&S or Eqv.
LS 0.00
13390.00
Total rate 13390.00
Extra 10% 0.00
Actual Rate 13390.00
Rate per set Rs. 15398.50 15% conctractor overhead 2008.50
Total (Rs.) 15398.50
LS 0.00
5665.00
Total rate 5665.00
Extra 10% 0.00
Actual Rate 5665.00
Rate per set Rs. 6514.75 15% conctractor overhead 849.75
Total (Rs.) 6514.75
LS 0.00
5665.00
Total rate 5665.00
Extra 10% 0.00
Actual Rate 5665.00
Rate per set Rs. 6514.75 15% conctractor overhead 849.75
Total (Rs.) 6514.75
LS 0.00
5000.00
Total rate 5000.00
Extra 10% 0.00
Actual Rate 5000.00
Rate per set Rs. 5750.00 15% conctractor overhead 750.00
Total (Rs.) 5750.00
13 Voltmeter (0-500)
sources Level Qty Unit Rate/unit cost Total Cost
3013 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 600.00 0.00
un skilled 0 nos 525.00 0.00 0.00
materials a. Voltmeter 1 nos 1100.00 1100.00
c. CM, Screws, Grips etc.
LS 0.00
1100.00
Totaal rate 1100.00
Extra 10% 110.00
Actual Rate 1210.00
Rate per set Rs. 1391.50 15% conctractor overhead 181.50
Total (Rs.) 1391.50
LS 0.00
237.00
Totaal rate 237.00
Extra 10% 23.70
Actual Rate 260.70
Rate per set Rs. 299.81 15% conctractor overhead 39.11
Total (Rs.) 299.81
14 Amp. Meter (0-500)
sources Level Qty Unit Rate/unit cost Total Cost
3014 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 600.00 0.00
un skilled 0 nos 525.00 0.00 0.00
materials a. Amp.Meter 1 nos 979.00 979.00
b. CM, Screws, Grips etc.
LS 0.00
979.00
Total rate 979.00
Extra 10% 97.90
Actual Rate 1076.90
Rate per set Rs. 1238.44 15% conctractor overhead 161.54
Total (Rs.) 1238.44
15 Slector Switch
sources Level Qty Unit Rate/unit cost Total Cost
3015 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 600.00 0.00
un skilled 0 nos 525.00 0.00 0.00
materials a. Selector Switch 1 nos 711.00 711.00
b. CM, Screws, Grips etc.
LS 0.00
711.00
Total rate 711.00
Extra 10% 71.10
Actual rate 782.10
Rate per set Rs. 899.42 15% conctractor overhead 117.32
Total (Rs.) 899.42
LS 0.00
1432.00
Total rate 1432.00
Extra 10% 143.20
Actual Rate 1575.20
Rate per set Rs. 1811.48 15% conctractor overhead 236.28
Total (Rs.) 1811.48
17 32 Amp TP MCB
sources Level Qty Unit Rate/unit cost Total Cost
3119 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 600.00 0.00
un skilled 0 nos 525.00 0.00 0.00
materials a. M.C.B 10 nos 5000.00 50000.00
b. CM, Screws, Grips etc.
LS 0.00
50000.00
Total rate 50000.00
Extra 10% 0.00
Actual Rate 50000.00
Rate per Nos Rs. 5750.00 15% conctractor overhead 7500.00
Total (Rs.) 57500.00
LS 25.00
3480.00
Total rate 4205.00
Extra 10% 348.00
Actual Rate 4553.00
Rate per set Rs. 5235.95 15% conctractor overhead 682.95
Total (Rs.) 5235.95
LS 38.00
1991.00
Total rate 3441.00
Extra 10% 199.10
Actual Rate 3640.10
Rate per set Rs. 4186.12 15% conctractor overhead 546.02
Total (Rs.) 4186.12
21 Musical Bell
sources Level Qty Unit Rate/unit cost Total Cost
3021 labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.5 nos 600.00 300.00
un skilled 0 nos 0.00 0.00 725.00
materials a.M.Bell 1 nos 500.00 500.00
b. CM, Screws,. LS 90.00
590.00
Total rate 1315.00
Extra 10% 59.00
Actual Rate 1374.00
Rate per set Rs. 1580.10 15% conctractor overhead 206.10
Total (Rs.) 1580.10
13910.00
Total rate 13910.00
Extra 10% 1391.00
Actual Rate 15301.00
Rate per Nos. Rs. 1759.61 15% conctractor overhead 2295.15
Total (Rs.) 17596.15
5045.00
Total rate 5920.00
Extra 10% 0.00
Actual Rate 5920.00
Rate per Set. Rs. 6808.00 15% conctractor overhead 888.00
Total (Rs.) 6808.00
1180.00
Total rate 2055.00
Extra 10% 118.00
Actual Rate 2173.00
Rate per Set. Rs. 2498.95 15% conctractor overhead 325.95
Total (Rs.) 2498.95
33 6-32 Amp DP MCB
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 600.00 0.00
un skilled 0 nos 525.00 0.00 0.00
materials a.MCB 10 Nos 618.00 6180.00
b.CM, Screws LS 0.00 0.00
6180.00
Total rate 6180.00
Extra 10% 618.00
Actual Rate 6798.00
Rate per Set. Rs. 781.77 15% conctractor overhead 1019.70
Total (Rs.) 7817.70
kg,sand,soil etc.
7000.00
Total rate 8070.00
Extra 10% 700.00
Actual Rate 8770.00
Rate per set Rs. 10085.50 15% conctractor overhead 1315.50
Total (Rs.) 10085.50
120008.00
Total rate 122058.00
Extra 10% 12000.80
Actual Rate 134058.80
Rate per Rm. Rs. 1541.67 15% conctractor overhead 20108.82
Total (Rs.) 154167.62
37 2 c x 16 Sqmm Cu arm cable & 1 no of 4 Sqmm Cu wire through 40 mmdia. HDPE Conduit ( 4 kgf/cm2 )
110989.00
Total rate 113039.00
Extra 10% 11098.90
Actual Rate 124137.90
Rate per Rm. Rs. 1427.58 15% conctractor overhead 18620.69
Total (Rs.) 142758.59
38 4c x 35 Sqmm Cu arm cable & 1 no of 6 Sqmm Cu wire through 50 mmdia. HDPE Conduit ( 4 kgf/cm2 )
257962.00
Total rate 260012.00
Extra 10% 25796.20
Actual Rate 285808.20
39 4mm2 2 core Armored cable wire through 40mm dia HDPE Conduit(4kgf/cm2)
29400.00
Total rate 30817.50
Extra 10% 2940.00
Actual Rate 33757.50
Rate per Rm. Rs. 388.21 15% conctractor overhead 5063.63
Total (Rs.) 38821.13
Fan regulator(medium)
sources Level Qty Unit Rate/unit cost Total Cost
3000 labour skilled 0.1 nos 850.00 85.00
Semi skilled 0.2 nos 600.00 120.00
un skilled 0 nos 0.00 0.00 205.00
a. Step regulator (Medium)
400.00
Total rate 605.00
Extra 10% 40.00
Actual Rate 645.00
Rate per set Rs. 741.75 15% conctractor overhead 96.75
Total (Rs.) 741.75
A SEPTIC TANK
1 earthwork excavation
1 5.7 3.7 1.8 37.962 Cu.M 492.75 18705.851424
2 Soling work
1 5.7 3.7 0.2 4.218 Cu.M 3887.00 16395.366
3 PCC
1 5.7 3.7 0.1 2.109 Cu.M 9998.56 21086.96304
8 form work
1 5.7 3.7 21.09 Sq.m 664.33 14010.7392029775
Total 262481.71
2 Soakpit
ii Rcc Slab
1 Area 15.20244 0.125 1.900305 Cu.M 13548.04 25745.398650675
Total 83559.14
3 Manhole
1 earthwork excavation
1 1 1 1 1 Cu.M 492.752 492.752
2 Soling work
1 1 1 0.1 0.1 Cu.M 3887 388.7
3 PCC
1 1 1 0.1 0.1 Cu.M 9998.56 999.856
8 form work
1 1 1 1 Sq.m 664.3309 664.33092475
Total 10212.66
A Labour
Unskilled MD 0.8 520.00 416.00
B Material
Nil
C Equipment
@ 3% of (A) LS 1 12.48
D Subtotal (A+B+C) 428.48
E Contractor's Overhead@ 15% 0f(D) 64.27
Total(D+E) 492.75
Dry stone soling with sand foundation/floor including sand filling in joint levelling ramming to level including sand
2 Unit: 1 m3
filling joints.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.) Remarks
A Labour
Skilled MD
Unskilled MD 1.5 520.00 780.00
B Material
2200.00
Stone m3 1 2200.00
P.C.C. in 1:3:6 (M10)work for levelling in ground with approved quality of cement and sand and crushed stone
3 Unit: 1 m3
aggregate including mixing,laying,curing etc all as per instruction and specification all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.) Remarks
A Labour
Skilled MD 1 850.00 850.00
Unskilled MD 4 520.00 2080.00
B Material
Cement MT 0.22 13620.00 2996.40
A Labour
Skilled MD 1.5 850.00 1275.00
Unskilled MD 2.2 520.00 1144.00
Unskilled MD 0.2 520.00 104.00
B Material
Cement MT 0.07 13620.00 953.40
3
Sand m 0.3 2000.00 600.00
4704.00
Brick Nos 560 8.40
30.00
water ltr 100 0.30
C Equipment
3% of A LS 1 3.12
D Subtotal (A+B+C) 8813.52
E Contractor's Overhead @15% of (D) 1322.03
Total(D+E) 10135.55
A Labour
Skilled MD 10 850.00 8500.00
Unskilled MD 10 520.00 5200.00
B Material
Cement MT 0.53 13620.00 7218.60
3
Sand m 0.23 2000.00 460.00
C Equipment
Nil
D Subtotal (A+B+C) 21378.60
E Contractor's Overhead @15% of (D) 3206.79
Total(D+E) 24585.39
2
Rate per 1 m 245.85
P.C.C. in 1:1.5:3 (M20) work for levelling in ground with approved quality of cement and sand and crushed stone
6 Unit: 1 m3
aggregate including mixing,laying,curing etc all as per instruction and specification all complete.
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.) Remarks
A Labour
Skilled MD 0.5 850.00 425.00
Unskilled MD 3.5 520.00 1820.00
B Material
Cement MT 0.4 13620.00 5448.00
3
River Sand m 0.425 2000.00 850.00
3
Crushed agg.20mm down m 0.57 2050.00 1168.50
3
Crushed agg.10mm down m 0.29 2100.00 609.00
Water ltr 200 0.30 60.00
Diesel ltr 3.1 77.50 240.25
Petrol ltr 0.1 101.50 10.15
C Equipment
Vibrator Hrs 0.25 100.00 25.00
Mixer Hrs 0.6 1875.00 1125.00
D Subtotal (A+B+C) 11780.90
8 Plywood formworks with steel adjustable pipe props for floor and slab Unit: 100 m2
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.) Remarks
A. Labour:
md 17.200 14620.00
Skilled 850.00
md 25.700 13364.00
Unskilled 520.00
B. Material:
19mm board m2 16.50 1150.00 18975.00 use for 6 times
9 12.5 mm thick plastering for levelling surface,1:6 cement sand mortar other than ceiling Unit:100 m2
S. N. Description Unit Quantity Rate (NRs.) Amount (NRs.) Remarks
A Labour
Skilled MD 12 850.0 10200.00
Unskilled MD 16 520.0 8320.00
B Material
Cement MT 0.382 13620.0 5202.84
Sand m 3
1.57 2000.0 3140.00
C Equipment
Nil
D Subtotal (A+B+C) 26862.84
E Contractor's Overhead @15% of (D) 4029.43
Total(D+E) 30892.27
Rate per 1 m2 308.92
A Labour
skilled MD 2.2 850 1870.00
Unskilled MD 2.2 520 1144.00
B Const.material
Bricks NO 377 8.6 3242.20
Cement MT 0.1465 13620.0 1995.33
Sand CUM 0.3 2000 600.00
Water Charge LS 60.00
C Subtotal (A+B) 8911.53
D Contractor's Overhead@ 15% 0f(C) 1336.73
Total(C+D) 10248.26
Rate per 1 m2 1024.83