You are on page 1of 1

PROYECTO A

INVERCION 5.000.000
TIR 14,9795%
VPN 10,01
Nº 1 2 3 4 5 6 7 8 9 10
FLUJO DE
EFECTIVO 514.083 668.308 768.555 883.838 1.016.413 1.168.875 1.344.207 1.545.838 1.777.713 2.044.370
R 447.108,40 505.517,07 505.607,73 505.697,73 505.787,55 505.877,75 505.968,22 506.058,42 506.148,44 506.238,70
∑ 5.000.010,01

PROYECTO B

INVERCION 5.000.000
TIR 2,3019%
VPN 97,48
Nº 1 2 3 4 5 6 7 8 9 10
FLUJO DE
EFECTIVO 1.584.874 1.325.680 1.020.452 840.100 520.014 320.147 102.541 54.785 41.254 109.656
R 1.549.212,67 1.266.692,81 953.106,61 767.001,45 464.083,94 279.284,76 87.440,30 45.665,90 33.613,43 87.336,42
∑ 5.000.097,48