Professional Documents
Culture Documents
Authuvdty
Volume VII
January 1986
Sponsored by
International Development
Prepared b,
VOLUME VII
Submitted to
and
DEVELOPMENT AUTHORITY
By
R-2748
January, 1986
TABLE OF CONTENTS
Page
VOLUME I
EXECUTIVE SUMMARY
1.0 INTRODUCTION
1-1
3.0
SYSTEM PLANNING AND COST ANALYSIS 3-1
LPS/D11
TABLE OF CONTENTS
(Continued)
Page
ASH COAL
4-47
5.1 GENERAL
5-I
Requirements 5-80
5.5.7 Availability
5-97
LPS/DI1
TABLE OF CONTENTS
(Continued)
Page
VOLUME II
6.1 INTRODUCTION
6-1
MAINTENANCE)
6-71
Maintenance Activities
6-187
7.0 TRAINING
7-1
7.1 INTRODUCTION
7-1
7.3.1 Approach
7-6
LPS/D11
TABLE OF CONTENTS
(Continued)
Page
VOLUME II CONT'D
7.4.1 Organization
7-11
7.4.2 Plan
7-15
VOLUME III
8.2 EXCLUSIONS
8-7
9.0 CONCLUSIONS
9-1
10.0 RECOMMENDATIONS
10-1
LPS/D11
TABLE OF CONTENTS
(Continued)
VOLUME IV
APPENDIX A - SPECIFICATIONS
MATERIAL SPECIFICATIONS
Chemicals
Limestone
MECHANICAL SPECIFICATIONS
VOLUME V
APPENDIX A - SPECIFICATIONS
MECHANICAL SPECIFICATIONS
M-6 Deaerator
M-16A Diesel Engine and Electric Motor Driven Fire Pump and
Accessories
LPS/DI1
TABLE OF CONTENTS
(Continued)
VOLUME VI
APPENDIX A - SPECIFICATIONS
MECHANICAL SPECIFICATIONS
CIVIL/STRUCTURAL SPECIFICATIONS
ELECTRICAL SPECIFICATIONS
VOLUME VII
APPENDIX B - DRAWINGS
SITE ARRANGEMENTS
Figure 5.3-1
Khanot Site, Plant Site General Arrangement
Figure 5.3-3
Lakhra Site, Plant Site General Arrangement
LPS/D11
-1
LAHKRA POWER FEASIBILITY STUDY
TABLE OF CONTENTS
(Continued)
PLANT ARRANGEMENTS
Figure 5.5.1-1
Ground Floor Plan
Figure 5.5.1-2
Mezzanine Floor and Misc. Floor Plans
Figure 5.5.1-3
Operating Floor Plan
Figure 5.5.1-4
Plant Cross Section
Figure 5.5.1-5
Longitudinal Cross Section
FLOW DIAGRAMS
Figure 5.5.3-1
Water Balance Diagram
Figure 5.5.3-2
Material Balance Diagram
Figure 5.5.41-i
Turbine Heat Balance, SI Units
Figure 5.5.41-2
Turbine Heat Balance, SI Units
Figure 5.5.41-3
Turbine Heat Balance, English Units
Figure 5.5.41-4
Turbine Heat Balance, English Units
Figure 5.5.41X-1
Water Treatment Diagram
Figure 5.5.4XI-I
Auxiliary Steam Diagram
Figure 5.5.4XII-1
Compressed Air Diagram
Figure 5.5.4XVI-1
Fire Protection System Diagram
Figure 5.5.4XX-1
Coal Flow Diagram
Figure 5.5.4XX-la
Inplant Coal Flow Diagram
Figure 5.5.4XXI-I
Generator and Station Power
Figure 5.5.4XXII-I
Emergency Power System
VOLUME VIII
VOLUME IX
LPS/D11
LIST OF TABLES
Number
Page
Characteristics
4-88
LPS/1/B4233/1.1
LIST OF TABLES
Number Page
4.4-5 Preliminary FPTF Results 4-91
4.4-6 Lakhra Baseline Coal Furnace Slagging Results 4-92
4.4-7 Preliminary FPTF Results - Convective Pass
Fouling Characteristics 4-93
4.4-8 Preliminary FPTF Results - In-Site Fly Ash
Resistivity Measurement 4-94
4.4-9 Preliminary FPTF Results - Ash Loading, Gas
Velocity, Erosion Rate 4-95
4.4-10 Lahkra Coal Corrosion Probe Results 4-96
4.5-1 Test Fuel Analysis for Lakhra Washed and
Baseline Coal 4-97
4.5-2 Preliminary FPTF Pulverization Results 4-98
4.5-3 Lakhra Washed Test Matrix 4-99
4.5-4 Preliminary FPTF Results - Relative
Combustion Characteristics 4-100
4.5-5 Preliminary FPTF Results - Furnace Slagging
Characteristics 4-101
4.5-6 Lakhra Washed Coal Characterization, FPTF
Slagging Results 4-102
4.5-7 Preliminary FPTF Results - Convective Pass
Fouling Characteristics 4-103
4.5-8 Preliminary FPTF Results - In-Site Fly Ash
Resistivity Measurement 4-104
4.6-1 Lakhra Coal Performance Characteristics 4-105
4.6-2 Lakhra Coal Sample Analyses 4-106
4.7-1 Similar Ash Coal Comparison 4-107
5.4-1 World Bank SO2 Emissions Criteria 5-43
5.4-2 Threshold Limit Values (TLV) for Dusts 5-44
5.4-3 Summary of Major Power Plant Wastewater Discharges 5-46
LPS/2/B4233/DlI
Number
Page
in U.S. Dollars
8-11
in Rupees 8-12
inU.S. Dollars
8-13
in U.S. Dollars
8-16
LPS/3/B4233/DII
Number Page
Emission Limit
8-29
LPS/4/B4233/D11
LIST OF FIGURES
Number Page
LPS/5/B4233/O11
LIST OF FIGURES
Number Page
4.5-3 Lakhra Washed Coal Evaluation 4-134
4.5-4 Lakhra Washed Coal Evaluation 4-135
4.5-5 Lakhra Washed Coal Evaluation 4-136
4.5-6 Lakhra Washed Coal Evaluation 4-137
4.7-1 Site Elevation B&W Boiler 4-138
4.7-2 Design Information B&W Boiler 4-139
4.7-3 Design Information CE Boiler 4-140
4.7-4 Coal Analysis CE Boiler 4-141
4.7--5 Design Information FW Boiler 4-142
4.7-6 Side Elevation FW Boiler 4-143
4.7-7 Coal Analysis FW Boiler 4-144
4.7-8 Ash Analysis FW Boiler 4-145
5.2.1 Lakhra Area Map 5-2
5.5.1.6-1 Coal Laboratory and Sample Preparation Area 5-64
5.6.2 Master Project Schedule 5-111
5.6.3 Progressive Manufacture of Boilers and
Turbines in Pakistan 5-117
5.6.4 Letter in Reference to Progressive Manu
facture of Boilers and Turbines in Pakistan 5-126
5.6.5 Letter in Reference to Local Manufacturing
of Boilers/Turbine 5-129
5.6.6 Letter in Reference to Progress in Manu
facture of Boilers in Pakistan 5-132
5.6.7 Letter in Peference to Progressive Manu
facture of Boilers and Turbines in Pakistan 5-134
LPS/6/B4233/D11
Number Page
6.2.1 CPPD Responsibilities Throughout Project Phases 6-32
6.2.2 Recommended CPPD Head Office Staff Activities 6-33
6.2.3 Recommended Coal Power Projects Department
Organization 6-51
6.2.4 Coal Power Projects Department; WAPDA Staffing
Plan for Key Personnel 6-54
6.2.5 Summary of Base Salary Costs (Rupees) 6-55
6.3.2(a) Lakhra Project Organization (Design and Construction) 6-57
6.3.2(b) Lakhra Construction Management Organization 6-58
6.3.3 Construction Management Manual; Table of Contents 6-63
6.3.4 Project Organization (Design and Construction);
WAPDA Staffing Plan for Key Personnel 6-64
6.4.2 Lakhra Project Organization (Start-up and Test) 6-66
6.4.3 Start-up Manual; Table of Contents 6-68
6.4.4 Project Organization (Start-up and Test);
WAPDA Staffing Plan for Key Personnel 6-70
7.4.2(a) Coal Power Projects Department;
Preliminary Training Plan 7-16
7.4.2(b) Project Organization (Design and Construction);
Preliminary Training Plan 7-17
LPS/7/B4233/DI
LIST OF EXHIBITS
No.
Page
Planning Studies
3.14
Data for Alternate 300 MW Unit Additions 3-63
LPS/I./DlI
LIST OF EXHIBITS
(Continued)
No. Page
3.17 First Series of WASP-3 Computer Studies, 3-67
Cumulative Present Worth Through the
Year 2005 vs. Coal Cost
3.18 Power Cost as a Function of Capacity Factor 3-68
3.19 Second Series of WASP-3 Computer Studies, 3-69
Optimum Generator Expansion Program for
the WAPDA System
3.20 Second Series of WASP-3 Computer Studies, 3-71
Capacity Factors in Percent for Various
Periods for the First Domestic Coal
Unit (300 MW) (1990-1991)
LPS/2/D11
LIST OF EXHIBITS
(Continued)
No.
Page
Station Equipment
to Jamshoro
3.39 1991 Plans 2 and 2A, I X 600 MW Imported Coal Unit 3-92
LPS/3/DII
LIST OF EXHIBITS
(Continued)
No. Page
3.53 Jamshoro 500/220 kV Substation, Plan 4 3-106
3.54 Capital Costs of Imported Coal Alternative 3-107
Transmission Plans
3.55 Economic Comparison of Imported Coal Transmission 3-108
Alternatives
3.56 Computation of Transmission Losses From Import Coal 3-109
Plant to Jamshoro
3.57 Plant and Transmission Capital Costs, Comparison of 3-110
Lakhra Alternatives
3.58 Plant and Transmission Capital Cost, Comparison of 3-111
Lakhra Alternative, First Unit Only
3.59 Lakhra and Imported Coal Project Comparisons 3-112
3.60 Lakhra and Imported Coal Comparative Parameters, 3-113
July 1985 Dollars
3.61 Diversified Maximum Demand at Generation Level (M) 3-114
3.62 Energy Requirement at Generation Level (GWH) 3-115
3.63 System Load Factor 3-116
3.64 Second Series of WASP-3 Computer Studies Generation 3-117
Expansion Program with the Cost of 5100 Btu/Ib Lakhra
Coal Equal to $30.50/MT (1081 ¢/KCAL X 106)
3.65 Lakhra or Khanot 500 kV Substation for Two 350 MW 3-119
Units
3.66 Capital Costs of Lakhra Alternative Transmission 3-120
Plans for Two 350 MW Units
3.67 Plant and Transmission Capital Cost Comparison of 3-121
Lakhra Alternatives for Two 350 MW Units Year of
Expenditure Dollars
LPS/4/D11
I_ i I 1 , 1s,
2 ,,, i
I - --
SIM ----
c
u1 MI.
- - . / . - _ .
- '- " :ri
V-..
-- COM I I
Y
- ' °
I '3 '
.,.;;
...
. __ , "------.-------_ Lii -
- -,. ". : .
"- ' *,Ljs' -- .7p,[.
T
---------------------------
SFIGURE
5.3-1
1
T IE
-7 SITEI N1 M
II I
I fl
* ,,f ,,* 0e a a
10 1' 5 '-
/ .
e* .. MtWU.
c|
I ---- ------------ \c
,.. 4- _ _
- l,iliIi(41 roow
an tat.o- . ... .
-+ - +FIGURE 5.3-2
. iaIM I II UTUn
M.j C KX? RWMIT'
41 -S TI
.1< -AWT W-PA
(1 zI ,,sI
llnl
- ,L
L-- ---------- l-
LII, MIEMT
&
IiLO
Ao
PL(ACAWE3GEWl AWMEWD1
G
SA~l \'
0 - -7+2;Ll fA9iw
i i
MINE FACILITIES
E1 -
To r,.
C
, /
-,
-!
- -,-
.--..
-
--
-_______
-
-
_
/>4__ _
__
"' ' q
' I
FF"Y-,r--
B
to1 w 0900 59rVn5.3-4
FIGLURE 01
W
--... I _
-.
l or="
" ;"
0 -- '
,I
, l , lE , l
' Li
STS
" R ,
LIE Oi CpCI;I(MWA
O .. A'." " ! '."
EMI _ _W 'Iv.O
n HID&
CM.l
AER CO- . ~~~FD
- *
AN --- - -
IL I IR P lAk.l
• -..
L t 1 I t
u uf .. . . . FA . . . .,,,
-" DIKE C
" agoA
agA [ I[
fJ OlLDVI I~ L rM;0FhIA
i
,,I .-- . . . . . . . . . . ..
c ~~SAT
Y---I !
SERJICI!PLL i:[,,
t,t ''" -L.-i ~aranj.,
ut m_
PIALSI.ER
PC i
AF
CD~ ~ ~ ~ " FEER-
P
2 1 I
M ATE
- L PUS
C~ ERSC
~
A ~ DC 02 0405~ 0l-2~~O
MWIS IIAIR
TRANS. [w]
so mA
AREA "\ASFTI
21/
h~1Lp -i
-I iu I
I iii---* 1S'1VEL
HEATER BAY PLANS --
2ND
LEVELS ABOVE OPERATIlNG
LEVE
FLOOR
I
--.71A
o~ oA-t--,--.
~
. . ... LI
cQ
-- G D
TR Is NS a DC
.o H ~p ,,iGUR ~ ![
5.5.1-2 LL_
F COALTIMERS ~ a
LL OILRESOIR
F U U
VEIILATI O &,
[I
TLIREI 14FUNERAAO
SIEAAI.
AL E A;
1HI 4A- I TaI(Vk
?LALIPI
HEATERS
r EEDIATER CF
1 ----- ~CI
- LINIT I
(AA I F EECAE
A. /ICCIGM
I 000
/3L'uAAF A(A
ACCESS,' PAOI
A .
LOWPRESSLK iiI
FEEIATER (IfAPEK
a LI
CC4ONsT
m
II[7
,.;T 2
FI UR 5..
N.
14bG - Lr - ;; -p Z
.4'
i's F P[FhV.AT\L
BOILEFR
S(nIEL,
To Lp4,1 2
TL
CODE1IR RE-TLIGW
?LPLAN[em W .0..0,1.rJ. IOl
SPACE -LBICR
RikliflYA AREA
AA AOCSAREA AOL~
II
PLL4T1CROSSSEC71IO
4I~I*A 3
'I'VA
30p I I 4 2
EIVIATiOR
STM STTL~m
OKU CA
R I
LNt 2
CCA,
$ ORACE
03W-P
AIOI51110 -
STATION~A8-4 ,].JP'N
I ROOMPL
ACCESS
FIUR 55.-
SIIICIGSILO £ .0334.P
t= 74-';I
BOLE I LXI
TI
STATO MEL
ATtV T O COALTSILOSM a , N XSS SC
TO I I ,opoo ,-- = / . 1
BEL f
sI, : * I,,
21N5&3
rL-E
fla S IB..TTSII1
IATER
BALANIDIAGRAM
-,M~UJYin.~
ACOL
7 -
MTRIAL UTTER.
DIL
NX -E-7;D - -
9 6 41 1 111 1 1 11 1 1 1 j
1131 am
3477 9H
•i026 SP
10 7 jr.1
5000 391 )t
2370211
2 WU
9A I O
g94 HP
P1060 12L F7 00
43 F A BTl TUYP
2 HMM
301
0 9h G 3172 5. 58 71
2965 611 14 bT cr2
1851 2P
b 1,4A¥[-UP
205 1
3163911
211
3120
. 601 1l4t
1 3120 211
32612P 1?9 I
I6ti,tA
128
;"1" bp I2 162P, , I b9P 31OP o .
1287IP
11 9T|11
1iI
t34¢ 116
28b
010~ ~ ~
0=1 ~ ~~r 20 t)u41 b5r2 1
B1619-4/GF#7 3 " I- ID IT
VWO - NP 8.47 kPa, 0.5% MU, TC2F
P .Ift
118461.13411 2h
3178P
1090 911
510T 31818 0
1312 OtM 5i0I
12514P 3170 2H J 34;77~ 2i1
1 is? 21.1
21.
O2 4330230
2 511
0 b .lG
A I 5POWffhtALI(
3 7 2H1
3370
46 9P
0 hI
3 11.1 ----------- Id J4 4P
3062" HHPP 1130 7P
21 9 P.1
32b(141 ul.1 9
f , U1. IO
CR 3 f12786 411 L8U4 I11 1LLt = 23b64tl
CR2 m4 / k
3062.t 4b(t
31161102 RA
31 1o431 '4 .
131S SM
109"
144
IT3I 1
I 1101 A J '1 Il.
dUi tH fE
iL PUMP
1558 P
POWER
1491 3"
22186770.1
120MAl 01 0111P0J
k I ON
2 / LP389.300
14-39H 5260M kW
*AlbtPOWLHIACIUH
31001941.
245 1J lI 4 liP
S 1 rOt 276P
1340.
---
- "
129470.1
1164d
fiG4 0P 1275i 54 5 or.1
CH66
1b 1 5P 21,
4 P13630M 152240MI 1090
1364 0ti b9 940 1.1I o1,,.
C h O B O M1 19 6 ti 15 I1ISOM
:U Lti P 1042
165100M.
140420t.1li 1101k-U
I
He
41411 374it
44lH.Ri8i
0DM227011 28
29/0.129410. , lbl.
lillIk3. /k 11
At II 88
2300d0
7800kw
26 1223 5M
1495 14
9501 1368H
514971H
28930001.1
2 1ION9501
149SH
1449Hi
II 1 ,,0 414.000 kW
14491- AT 8
a3.2 50119
2 11
2?81
33
lop.,,,o
POWER
5 IACTOR
1315P114491
3000 RPt,
26
__), __b__8_21 _ 21I
,35102' 9109.
16" I
ooo
136611
.
./
121811
8191
173M
431 597.
273 51'
2314M , POE1L
105032M
''
N
=ODUERO
92 109
Hh119p u 1154H ELEP
5 1 1I 2 5 " 1026t
lA
1200t.1 I A A
13167134111
2430712PA 14465
fM
AKE-UP
169407176
205429.1 1365 911
30136r CIt E"
0 103L°°,.,I
I()~2
280
,ur.1
l.Ol d.[
12 12 1 I 61
201091641X
311 L380111. 200 26.9
0 -,Ll~I
is(~~~
'~~
_
1
8.b3''
159 815
2b41
8 4911
316f81.
1l
" 40 0M5
tea~~9745'
4,0t!0'I
°
_____8
40t,
1341 511
20-150 4 61 1 2(S
33
1 9 4F1 24
82I
1~b
li 11S
/11 51
13814 Si~~
4 4 9 GRO55
8RAT t ~ 81 ~1
~~~. 10~~~~~LK
(HeatHO
Ra e mDID HEAT
yv r D eD8Be uk hM
1 2 0 hi 17 ,1 - L 2 t
d n 00P - F o5 O I-bsh SOOCDO,
O $DI
0
r u1E 1 D
ue4 - psaT R POWE PLANT0bc1
8°32 11
P C LP EL M S B L T
U ,81
HQ;
f E nh l y T D
B u b NR1U B NE H A A A C
ENG IS UNITS
on the T/G Vendor
Selected)
619
T - Temperature-*F
/G F #72
-1
G C I111/12/85 HB-2
ET 'I C I 'T /
I. *I a 4$;
2q
rN\
--
aE
-~~~~~~~~FG -L -I -
I Jil
FEASIIIT SUT
- TREATNET
WATER 011wM
toa -~h
a
34
PON;mm R vv
f M U" PUW -A
FEASIIUUTTSTWV
AWLIUM SnO DIUM
-04-T
I
I IMS'-MV
I II 1I'i11
ff MW
-. 4.--RMM
MSM~lT
ST S
C29SE A IM
a.CIO
3.5 .- I m
~ - - VI SILS.&4 Sal-
FIR ROC rCIIrM
S tAU
a 4-9- S
42 ~
1
C-
- - - - - - - - - - - -- -- -
240Ire.E
O~~~~~OA _ KaO\lv
FIGRE5.54 X-
LMUA"'J
COXaFLOND"
f
to140OWICMI-%
I. I I I I 4 5
{...)5I NET .
62 4
B -.
pansa mu
Pamm min.u
LAA ,,"..OCAC
w FL~f WIAO
IOB COAL
16-9- m
a. I a I 3 ,N
a SL STATIO
MVOI,,0
C...
C. A. ~A fSC C 541
T T NOM CI
ctI l.S .. U
Af A I- -" kT)T kT k
T kT "T )T T T 1 T
)9 k
M"-N
SI SN TATL.LII
400V VITAL BUS
£ ) ) I) ) £
I---
rtltaS
---
... . . Ia ;.tn
a.....
-
.... ..
llttllv S
Ill." Inla
as.oast,.aa a
Is
ICEI I-
I SCfl
, , IoI a
h *ah D lI '
arC.Ma
? a, K I I II I II I II
I