Professional Documents
Culture Documents
Date of Activity Activity at Location No./ Section Hindrance at Location No./ Section Resource Idle
Date of Effect on
Date of TNEB client Date of Type of Vehicle (Car / Total No. Name of the Purchaser's Representative to
SL.NO occurance Type of Hindrance Executioin i.e. No.of Mans No. Of Total No. Of
Start End Survey Loc No Foundation Date Erection date Stringing Date Survey Foundation Erection Stringing visit Removal Tractor / Truck / JMC of Man whom hindrances are informed
Hindrance delay in days Idle Per Day Vehicle Vehicle Idle
/ TSE) Days Idle
11 25-05-18 01-06-18 Detail Survey Start-A60 TO AP 80 27-05-18 63/0,64/0,65/0,66/0 Land owner objection land owner requests for re-routing of line 30-05-18 11-06-18 15 3 1 45 15 Executive Engineer,Dharmapuri
105 12-09-18 12-09-18 169/1 12-09-18 23-11-18 10-09-18 53/1 Land owner objection land owner requests for re-routing of line 12-09-18 08-08-19 332 15 2 1 4980 996 Executive Engineer,Dharmapuri
106 12-09-18 12-09-18 169/2 12-09-18 26-11-18
107 12-09-18 13-09-18 41/1 13-09-18 26-10-18 12-09-18 164/0 Land owner objection 02-07-19 28-08-19 350 15 2 1 5250 1050 Executive Engineer,Tirupattur
108 12-09-18 14-09-18 AP86 14-09-18 27-11-18
109 13-09-18 15-09-18 AP41 15-09-18 23-04-19 19-09-20
110 13-09-18 17-09-18 AP171 17-09-18 20-12-18 14-06-19
111 14-09-18 16-09-18 86/1 16-09-18 28-11-18
112 14-09-18 16-09-18 AP179 16-09-18 29-12-18 17-05-19
113 14-09-18 18-09-18 178/1 18-09-18 29-01-19
114 15-09-18 17-09-18 41/2 17-09-18 01-10-19
Land owner objection
115 15-09-18 18-09-18 84/1 18-09-18 02-10-18 84/1 land owners demanding for high crop compensation yet to pay 05-10-18 13-03-23 1,623 25 3 1 40575 6492 Executive Engineer,Dharmapuri
by Tantransco
116 16-09-18 19-09-18 AP40 19-09-18 25-04-19 13-09-20
117 16-09-18 20-09-18 AP169 20-09-18 21-06-19 28-06-19
118 16-09-18 20-09-18 AP54 20-09-18 08-05-19
119 16-09-18 29-09-18 AP183 29-09-18 11-12-18 28-05-19
120 16-09-18 29-09-18 152/1 29-09-18 02-12-18 16-09-18 158/1 Land owner objection 21-09-18 25-10-18 39 15 2 1 585 117 Executive Engineer,Tirupattur
157/0
121 19-09-18 24-09-18 AP69 24-09-18 04-10-19 18-09-18 Land owner objection 23-09-18 07-10-18 19 15 2 1 285 57 Executive Engineer,Tirupattur
122 20-09-18 23-09-18 AP167 23-09-18 11-06-19 18-09-18 157/1 Land owner objection 23-09-18 10-10-18 22 15 2 1 330 66 Executive Engineer,Tirupattur
123 21-09-18 24-09-18 AP59 24-09-18 01-05-19
124 22-09-18 25-09-18 AP58 25-09-18 15-04-19
125 22-09-18 25-09-18 AP166 25-09-18 23-02-19 06-07-19
126 24-09-18 26-09-18 166/1 26-09-18 28-06-19
127 25-09-18 28-09-18 59/1 28-09-18 01-11-18
128 25-09-18 28-09-18 AP156 28-09-18 28-11-18
129 26-09-18 28-09-18 167/1 28-09-18 19-11-18
130 26-09-18 29-09-18 AP65 29-09-18 02-10-19
131 26-09-18 29-09-18 AP60 29-09-18 13-04-19
132 26-09-18 30-09-18 AP70 30-09-18 06-10-19
133 26-09-18 30-09-18 AP61 30-09-18 20-09-19
134 26-09-18 02-10-18 AP64 02-10-18 11-09-19 28-09-18 7/0 Land owner objection 08-10-18 11-03-19 164 15 2 1 2460 492 Executive Engineer,Dharmapuri
135 28-09-18 02-10-18 AP153 02-10-18 02-12-18
136 28-09-18 02-10-18 AP190 02-10-18 18-11-18 26-11-19
137 29-09-18 03-10-18 154/1 03-10-18 30-11-18
138 01-10-18 04-10-18 AP62 04-10-18 23-09-19
139 03-10-18 05-10-18 AP63 05-10-18 17-09-19
140 04-10-18 07-10-18 AP157 07-10-18 19-11-18
141 07-10-18 10-10-18 157/1 10-10-18 18-11-18
142 08-10-18 12-10-18 AP189 12-10-18 21-11-18 29-11-19
143 10-10-18 12-10-18 AP158 12-10-18 07-02-20
144 11-10-18 15-10-18 AP188 15-10-18 19-02-19 02-12-19
145 12-10-18 16-10-18 AP154 16-10-18 01-12-18
146 14-10-18 17-10-18 AP168 17-10-18 22-11-18 02-07-19
147 15-10-18 18-10-18 AP152 18-10-18 03-12-18
148 15-10-18 18-10-18 AP77 18-10-18 02-09-19
149 16-10-18 19-10-18 74/1 19-10-18 20-11-18
150 18-10-18 21-10-18 AP74 21-10-18 17-11-18
151 19-10-18 22-10-18 AP151 22-10-18 04-12-18
152 20-10-18 23-10-18 153/1 23-10-18 01-12-18
153 22-10-18 24-10-18 AP88 24-10-18 20-10-19
154 23-10-18 25-10-18 158/1 25-10-18 23-11-18
155 23-10-18 26-10-18 AP145 26-10-18 21-12-18 13-11-19
156 24-10-18 26-10-18 AP87 26-10-18 25-10-19
157 25-10-18 27-10-18 144/2 27-10-18 10-12-18
158 26-10-18 28-10-18 AP146 28-10-18 08-12-18 15-11-19
159 26-10-18 28-10-18 AP155 28-10-18 27-11-18
160 26-10-18 31-10-18 AP16 31-10-18 13-10-19
161 26-10-18 31-10-18 AP17 31-10-18 20-10-19
162 27-10-18 29-10-18 146/1 29-10-18 21-12-18
163 28-10-18 30-10-18 145/2 30-10-18 09-12-18 28-10-18 151/1 Land owner objection 12-11-18 07-08-19 283 15 2 1 4245 849 Executive Engineer,Tirupattur
164 29-10-18 31-10-18 145/1 31-10-18 07-12-18 30-10-18 144/1 Land owner objection 14-11-18 17-08-19 291 15 2 1 4365 873 Executive Engineer,Tirupattur
165 29-10-18 01-11-18 AP18 01-11-18 02-10-19
166 30-10-18 01-11-18 142/1 01-11-18 25-07-19
167 31-10-18 02-11-18 AP142 02-11-18 06-12-18
168 01-11-18 03-11-18 44/2 03-11-18 14-11-18
169 01-11-18 03-11-18 AP57 03-11-18 10-07-19
land owner demands for re-routing of line as he is planning to
construct college.
170 03-11-18 05-11-18 AP43 05-11-18 19-05-19 26-09-20 03-11-18 56/0 30-04-19 13-03-23 1,591 15 2 1 23865 4773 Executive Engineer,Dharmapuri
( K .P. ANBALAGAN - Ex Minister of higher eduaction)
Crop 13.63 Lakhs have to pay by Tantransco
25/0,
25/1, 25/2,
171 05-11-18 08-11-18 AP44 08-11-18 17-06-19 03-11-18 Land owner objection 08-11-18 10-03-19 127 25 3 1 3175 508 Executive Engineer,Dharmapuri
25/3,27/0,
34/0 = 7 nos
172 08-11-18 10-11-18 AP15 10-11-18 11/1019 2 OF 4
Date of Activity Activity at Location No./ Section Hindrance at Location No./ Section Resource Idle
Date of Effect on
Date of TNEB client Date of Type of Vehicle (Car / Total No. Name of the Purchaser's Representative to
SL.NO occurance Type of Hindrance Executioin i.e. No.of Mans No. Of Total No. Of
Start End Survey Loc No Foundation Date Erection date Stringing Date Survey Foundation Erection Stringing visit Removal Tractor / Truck / JMC of Man whom hindrances are informed
Hindrance delay in days Idle Per Day Vehicle Vehicle Idle
/ TSE) Days Idle
173 15-11-18 18-11-18 AP139 18-11-18 13-12-18
35/0,35/1,
174 16-11-18 18-11-18 57/1 18-11-18 26-04-19 16-11-18 Land owner objection 21-11-18 27-03-19 131 25 3 1 3275 524 Executive Engineer,Tirupattur
36/1,40/0
175 18-11-18 20-11-18 139/1 20-11-18 16-12-18
176 20-11-18 22-11-18 AP147 22-11-18 11-12-18
177 21-11-18 23-11-18 AP67 23-11-18 10-10-19
178 22-11-18 24-11-18 AP66 24-11-18 29-09-19
179 22-11-18 25-11-18 AP136 25-11-18 14-12-18
180 23-11-18 24-11-18 130/2 24-11-18 20-02-19
181 24-11-18 26-11-18 130/1 26-11-18 28-02-19
182 24-11-18 26-11-18 44/1 26-11-18 25-09-19
183 25-11-18 27-11-18 129/1 27-11-18 24-02-19
184 25-11-18 27-11-18 AP137 27-11-18 26-12-18
185 25-11-18 27-11-18 AP120 27-11-18 20-12-19
186 26-11-18 28-11-18 131/1 28-11-18 08-01-19
187 26-11-18 28-11-18 AP55 28-11-18 05-05-19
188 26-11-18 28-11-18 119/2 28-11-18 17-12-19
189 27-11-18 29-11-18 AP135 29-11-18 19-12-18
190 28-11-18 30-11-18 AP129 30-11-18 17-02-19 23-10-20
191 28-11-18 30-11-18 119/1 30-11-18 16-12-19
192 29-11-18 01-12-18 AP140 01-12-18 31-07-19
193 01-12-18 03-12-18 AP141 03-12-18 22-08-19
194 02-12-18 04-12-18 AP119 04-12-18 15-12-19
195 03-12-18 05-12-18 118/1 05-12-18 14-12-19
196 04-12-18 06-12-18 AP131 06-12-18 22-01-19 30-10-20
197 04-12-18 06-12-18 AP138 06-12-18 13-12-18
198 04-12-18 06-12-18 AP117 06-12-18 10-11-19
199 05-12-18 07-12-18 116/1 07-12-18 08-12-19
200 05-12-18 07-12-18 AP132 07-12-18 02-01-19 02-11-20 06-12-18 171/0 Land owner objection 11-12-18 16-12-18 10 25 3 1 250 40 Executive Engineer,Tirupattur
201 07-12-18 09-12-18 AP118 09-12-18 11-12-19 06-12-18 170/1,171/1 Land owner objection 11-12-18 25-05-19 170 25 3 1 4250 680 Executive Engineer,Tirupattur
202 07-12-18 09-12-18 120/2 09-12-18 12-01-19
203 08-12-18 10-12-18 141/1 10-12-18 14-12-18
204 08-12-18 10-12-18 120/1 10-12-18 10-01-19
205 08-12-18 10-12-18 AP116 10-12-18 02-12-19
206 09-12-18 11-12-18 AP133 11-12-18 22-12-18 05-11-20
207 10-12-18 12-12-18 128/1 12-12-18 19-02-19
208 10-12-18 12-12-18 AP33 12-12-18 27-12-18 29-08-20
209 10-12-18 12-12-18 115/2 12-12-18 28-11-19
210 11-12-18 13-12-18 27/1 13-12-18 27-12-18
211 11-12-18 13-12-18 115/1 13-12-18 26-11-19 12-12-18 150/1 Land owner objection 17-12-18 22-04-19 131 15 2 1 1965 393 Executive Engineer,Tirupattur
212 14-12-18 16-12-18 AP127 16-12-18 04-01-19 16-10-20 12-12-18 97/0 Land owner objection 16-01-19 08-07-19 208 15 2 1 3120 624 Executive Engineer,Dharmapuri
Land owner objection
213 14-12-18 16-12-18 AP114 16-12-18 30-12-18 AP114 land owners demanding for high crop compensation yet to pay 02-01-19 13-03-23 1,534 25 3 1 38350 6136 Executive Engineer,Dharmapuri
by Tantransco
214 14-12-18 16-12-18 AP115 16-12-18 25-11-19
Land owner objection
215 15-12-18 17-12-18 AP113 17-12-18 31-12-18 AP113 land owners demanding for high crop compensation yet to pay 03-01-19 13-03-23 1,533 25 3 1 38325 6132 Executive Engineer,Dharmapuri
by Tantransco
216 15-12-18 17-12-18 AP130 17-12-18 21-02-19 27-10-20
217 16-12-18 18-12-18 AP125 18-12-18 03-02-19 12-10-20
218 17-12-18 19-12-18 AP126 19-12-18 13-01-19 14-10-20
219 17-12-18 19-12-18 132/1 19-12-18 30-12-18
220 17-12-18 19-12-18 AP28 19-12-18 25-02-20 21-08-20
221 17-12-18 19-12-18 114/1 19-12-18 08-11-19
222 18-12-18 20-12-18 132/2 20-12-18 27-12-18
223 19-12-18 21-12-18 AP124 21-12-18 06-02-19
224 24-12-18 27-12-18 28/1 27-12-18 25-02-20
225 25-12-18 27-12-18 AP134 27-12-18 01-02-19
226 25-12-18 27-12-18 AP21 27-12-18 22-07-20
Land owner objection
227 28-12-18 01-01-19 123/1 01-01-19 14-02-19 31-12-18 148/0 10-01-19 01-04-19 91 15 2 1 1365 273 Executive Engineer,Tirupattur
land owners demanding for high crop compensation
228 01-01-19 04-01-19 AP149 04-01-19 19-09-19
229 02-01-19 06-01-19 AP150 06-01-19 01-09-19
230 03-01-19 05-01-19 AP49 05-01-19 20-11-19
231 03-01-19 05-01-19 AP50 05-01-19 09-09-19
232 04-01-19 06-01-19 49/1 06-01-19 18-11-19
233 05-01-19 07-01-19 AP98 07-01-19 23-11-19
Land owner objection
234 05-01-19 07-01-19 54/1 07-01-19 21-01-19 54/1 land owners demanding for high crop compensation yet to pay 24-01-19 13-03-23 1,512 25 3 1 37800 6048 Executive Engineer,Dharmapuri
by Tantransco
235 05-01-19 08-01-19 AP37 08-01-19 15-11-19 10-09-20
Land owner objection
236 06-01-19 11-01-19 19/1 11-01-19 25-01-19 19/1 land owners demanding for high crop compensation yet to pay 28-01-19 13-03-23 1,508 25 3 1 37700 6032 Executive Engineer,Dharmapuri
by Tantransco
237 07-01-19 09-01-19 37/2 09-01-19 18-11-19
238 07-01-19 09-01-19 AP20 09-01-19 18-10-19 D-3 D-3 TOWER GIVEN TO TANTRANSCO YET TO RECEIVE 18-10-19 13-03-23 1,242 25 3 1 31050 4968 Executive Engineer,Tirupattur
Land owner objection
239 08-01-19 12-01-19 AP19 12-01-19 26-01-19 AP19 land owners demanding for high crop compensation yet to pay 29-01-19 13-03-23 1,507 25 3 1 37675 6028 Executive Engineer,Dharmapuri
by Tantransco
240 26-01-19 28-01-19 27/2 28-01-19 18-02-19
Land owner objection
241 28-01-19 30-01-19 AP29 30-01-19 24-03-19 24-08-20 15-01-19 22/0 25-01-19 02-08-19 199 15 2 1 2985 597 Executive Engineer,Dharmapuri
land owners demanding for high crop compensation
Land owner objection
242 30-01-19 01-02-19 AP38 01-02-19 01-05-19 04-02-19 140/0,141/0 14-02-19 21-06-19 137 25 3 1 3425 548 Executive Engineer,Tirupattur
land owners demanding for high crop compensation
243 31-01-19 03-02-19 AP39 03-02-19 04-05-19 12-09-20 08-02-19 186/0 Land owner objection 18-02-19 22-06-19 134 15 2 1 2010 402 Executive Engineer,Tirupattur
244 01-02-19 02-02-19 33/1 02-02-19 01-03-19 09-02-19 123/1 Land owner objection 11-02-19 14-02-19 5 25 3 1 125 20 Executive Engineer,Tirupattur
The land comes under Public works department which is found
to be water lake area and letter has been issued by EE to PWD
245 04-02-19 06-02-19 AP83 06-02-19 02-02-19 104/0-112/0 for JOINT INSPECTION on 02.05.19 02.05.19 13-03-23 1,500 15 2 1 22500 4500 Executive Engineer,Dharmapuri
GO issued on 06.07.21, Lease Amount DD deposit on
04.04.22,GST paid on 03.03.23
Land owner objection
246 05-02-19 07-02-19 AP84 07-02-19 21-02-19 AP84 land owners demanding for high crop compensation yet to pay 21-02-19 13-03-23 1,481 25 3 1 37025 5924 Executive Engineer,Dharmapuri
by Tantransco
247 06-02-19 08-02-19 AP30 08-02-19 25-02-20 25-08-20
Land owner objection
248 07-02-19 09-02-19 AP82 09-02-19 23-02-19 AP82 land owners demanding for high crop compensation yet to pay 23-02-19 13-03-23 1,479 25 3 1 36975 5916 Executive Engineer,Dharmapuri
by Tantransco
Land owner objection
249 08-02-19 10-02-19 AP81 10-02-19 24-02-19 AP81 land owners demanding for high crop compensation yet to pay 24-02-19 13-03-23 1,478 25 3 1 36950 5912 Executive Engineer,Dharmapuri
by Tantransco
250 10-02-19 12-02-19 AP76 12-02-19 18-10-19 D-3 D-3 TOWER GIVEN TO TANTRANSCO YET TO RECEIVE 18-10-19 13-03-23 1,242 25 3 1 31050 4968 Executive Engineer,Tirupattur
251 11-02-19 13-02-19 AP75 13-02-19 18-10-19 D-3 D-3 TOWER GIVEN TO TANTRANSCO YET TO RECEIVE 18-10-19 13-03-23 1,242 25 3 1 31050 4968 Executive Engineer,Tirupattur
Land owner objection
252 14-02-19 16-02-19 AP80 16-02-19 02-03-19 AP80 land owners demanding for high crop compensation yet to pay 02-03-19 13-03-23 1,472 25 3 1 36800 5888 Executive Engineer,Dharmapuri
by Tantransco
253 16-02-19 18-02-19 AP4 18-02-19 18-10-19 D-3 D-3 TOWER GIVEN TO TANTRANSCO YET TO RECEIVE 18-10-19 13-03-23 1,242 25 3 1 31050 4968 Executive Engineer,Tirupattur
254 16-02-19 24-02-19 AP32 24-02-19 25-06-20 27-08-20
255 26-02-19 28-02-19 AP31 28-02-19 24-06-20 26-08-20
256 28-02-19 02-03-19 AP2 02-03-19 18-10-19 D-3 D-3 TOWER GIVEN TO TANTRANSCO YET TO RECEIVE 18-10-19 13-03-23 1,242 25 3 1 31050 4968 Executive Engineer,Tirupattur
257 01-03-19 04-03-19 AP3 04-03-19 18-10-19 D-3 D-3 TOWER GIVEN TO TANTRANSCO YET TO RECEIVE 18-10-19 13-03-23 1,242 25 3 1 31050 4968 Executive Engineer,Tirupattur
258 07-03-19 10-03-19 AP8 10-03-19 20-07-20
3 OF 4
Date of Activity Activity at Location No./ Section Hindrance at Location No./ Section Resource Idle
Date of Effect on
Date of TNEB client Date of Type of Vehicle (Car / Total No. Name of the Purchaser's Representative to
SL.NO occurance Type of Hindrance Executioin i.e. No.of Mans No. Of Total No. Of
Start End Survey Loc No Foundation Date Erection date Stringing Date Survey Foundation Erection Stringing visit Removal Tractor / Truck / JMC of Man whom hindrances are informed
Hindrance delay in days Idle Per Day Vehicle Vehicle Idle
/ TSE) Days Idle
259 08-03-19 11-03-19 AP7 11-03-19 24-07-20
260 10-03-19 26-03-19 142/2 26-03-19 29-07-19
261 10-03-19 26-03-19 8/1 26-03-19 26-07-20
262 11-03-19 29-03-19 AP144 29-03-19 12-09-19 10-03-20
263 15-03-19 17-03-19 6/1 17-03-19 15-07-20
264 21-03-19 24-03-19 6/2 24-03-19 17-07-20
265 24-03-19 27-03-19 AP143 27-03-19 11-09-19 12-03-20
266 27-03-19 30-03-19 AP94 30-03-19 25-02-20
267 29-03-19 01-04-19 AP148 01-04-19 23-09-19
Land owner objection
268 29-03-19 01-04-19 94/1 01-04-19 15-04-19 94/1 land owners demanding for high crop compensation yet to pay 15-04-19 13-03-23 1,428 25 3 1 35700 5712 Executive Engineer,Dharmapuri
by Tantransco
269 31-03-19 02-04-19 AP95 02-04-19 23-12-19
270 31-03-19 02-04-19 AP96 02-04-19 25-02-20
Land owner objection
271 02-04-19 04-04-19 96/1 04-04-19 18-04-19 96/1 land owners demanding for high crop compensation yet to pay 18-04-19 13-03-23 1,425 25 3 1 35625 5700 Executive Engineer,Dharmapuri
by Tantransco
Land owner objection
272 12-04-19 15-04-19 9/1 15-04-19 29-04-19 9/1 land owners demanding for high crop compensation yet to pay 29-04-19 13-03-23 1,414 25 3 1 35350 5656 Executive Engineer,Dharmapuri
by Tantransco
Land owner objection
273 17-04-19 21-04-19 AP9 21-04-19 05-05-19 AP9 land owners demanding for high crop compensation yet to pay 05-05-19 13-03-23 1,408 25 3 1 35200 5632 Executive Engineer,Dharmapuri
by Tantransco
274 17-04-19 22-04-19 150/1 22-04-19 15-02-20
275 15-05-19 17-05-19 AP123 17-05-19 16-10-19 08-10-20
276 18-05-19 20-05-19 AP121 20-05-19 15-11-19 04-10-20
Land owner objection
277 18-05-19 20-05-19 AP99 20-05-19 03-06-19 AP99 land owners demanding for high crop compensation yet to pay 03-06-19 13-03-23 1,379 25 3 1 34475 5516 Executive Engineer,Dharmapuri
by Tantransco
278 19-05-19 21-05-19 AP122 21-05-19 21-10-19 06-10-20
Land owner objection
279 19-05-19 21-05-19 AP100 21-05-19 04-06-19 AP100 land owners demanding for high crop compensation yet to pay 04-06-19 13-03-23 1,378 25 3 1 34450 5512 Executive Engineer,Dharmapuri
by Tantransco
280 21-05-19 24-05-19 AP128 24-05-19 11-10-19 19-10-20
Land owner objection
281 23-05-19 25-05-19 100/1 25-05-19 08-06-19 100/1 land owners demanding for high crop compensation yet to pay 08-06-19 13-03-23 1,374 25 3 1 34350 5496 Executive Engineer,Dharmapuri
by Tantransco
Land owner objection
282 24-05-19 26-05-19 AP101 26-05-19 25-05-19 AP 25 - AP26 25-07-19 02-06-19 8 30 3 1 240 32 Executive Engineer,Dharmapuri
land owners demanding for high crop compensation
283 01-06-19 04-06-19 101/1 04-06-19
284 04-06-19 09-06-19 AP102 09-06-19
285 13-06-19 19-06-19 AP193 19-06-19 02-07-19 19-11-19
286 17-06-19 20-06-19 AP192 20-06-19 06-07-19 21-11-19
287 20-06-19 22-06-19 AP186 22-06-19 02-07-19 08-12-19 20-06-19 166/1 Land owner objection 23-06-19 27-06-19 7 25 3 1 175 28 Executive Engineer,Tirupattur
Land owner objection
288 22-06-19 25-06-19 AP191 25-06-19 06-07-19 23-11-19 22-06-19 AP168-AP169 25-06-19 06-07-19 14 30 3 1 420 56 Executive Engineer,Tirupattur
land owners demanding for high crop compensation
Land owner objection
289 25-06-19 28-06-19 101/2 28-06-19 22-06-19 AP 167 - AP 166 25-06-19 07-07-19 15 30 3 1 450 60 Executive Engineer,Tirupattur
land owners demanding for high crop compensation
Land owner objection
290 05-07-19 08-07-19 AP97 08-07-19 06-07-19 AP 161-163 09-07-19 16-07-19 10 30 3 1 300 40 Executive Engineer,Tirupattur
land owners demanding for high crop compensation
Land owner objection
291 12-07-19 15-07-19 AP103 15-07-19 06-07-19 AP 158 09-07-19 07-02-20 216 25 3 1 5400 864 Executive Engineer,Tirupattur
land owners demanding for high crop compensation
Land owner objection
292 29-07-19 02-08-19 AP22 02-08-19 16-08-19 AP22 land owners demanding for high crop compensation yet to pay 26-08-19 13-03-23 1,305 25 3 1 32625 5220 Executive Engineer,Dharmapuri
by Tantransco
293 04-08-19 06-08-19 AP52 06-08-19 04-09-19
294 05-08-19 07-08-19 151/1 07-08-19 14-08-19
295 06-08-19 08-08-19 53/1 08-08-19 01-09-19
Land owner objection
296 07-08-19 09-08-19 48/1 09-08-19 23-08-19 48/1 land owners demanding for high crop compensation yet to pay 02-09-19 13-03-23 1,298 25 3 1 32450 5192 Executive Engineer,Dharmapuri
by Tantransco
297 07-08-19 10-08-19 AP53 10-08-19 24-08-19
298 12-08-19 17-08-19 144/1 17-08-19 26-08-19 09-11-19
299 18-08-19 22-08-19 AP164 22-08-19 29-08-19
Land owner objection
300 30-09-19 03-10-19 AP11 03-10-19 17-10-19 AP11 land owners demanding for high crop compensation yet to pay 27-10-19 13-03-23 1,243 25 3 1 31075 4972 Executive Engineer,Dharmapuri
by Tantransco
301 15-11-19 18-11-19 AP1 18-11-19 18-10-19 LSR+0 LSR+0 TOWER GIVEN TO TANTRANSCO YET TO RECEIVE 18-10-19 13-03-23 1,242 25 3 1 31050 4968 Executive Engineer,Tirupattur
Land owner objection
302 20-11-19 22-11-19 AP12 22-11-19 06-12-19 AP12 land owners demanding for high crop compensation yet to pay 16-12-19 13-03-23 1,193 25 3 1 29825 4772 Executive Engineer,Dharmapuri
by Tantransco
Land owner objection
303 22-11-19 25-11-19 18/1 25-11-19 09-12-19 18/1 land owners demanding for high crop compensation yet to pay 19-12-19 13-03-23 1,190 25 3 1 29750 4760 Executive Engineer,Dharmapuri
by Tantransco
304 29-11-19 02-12-19 AP13 02-12-19 18-10-19 D-3 D-3 TOWER GIVEN TO TANTRANSCO YET TO RECEIVE 18-10-19 13-03-23 1,242 25 3 1 31050 4968 Executive Engineer,Tirupattur
305 02-12-19 05-12-19 AP14 05-12-19 18-10-19 D-3 D-3 TOWER GIVEN TO TANTRANSCO YET TO RECEIVE 18-10-19 13-03-23 1,242 25 3 1 31050 4968 Executive Engineer,Tirupattur
Land owner objection
306 10-02-20 14-02-20 AP10 14-02-20 28-02-20 AP10 land owners demanding for high crop compensation yet to pay 09-03-20 13-03-23 1,109 25 3 1 27725 4436 Executive Engineer,Dharmapuri
by Tantransco
Land owner objection
307 13-02-20 15-02-20 10/1 15-02-20 29-02-20 10/1 land owners demanding for high crop compensation yet to pay 10-03-20 13-03-23 1,108 25 3 1 27700 4432 Executive Engineer,Dharmapuri
by Tantransco
308 23-07-20 23-07-20 37/1 23-07-20 26-07-20
09-07-19 Delays due to order value amendment Approval From HO Chennai 09-07-19 22-06-22 1,079
Foundation Erection Stringing TOTAL Mans / Man Days Idle 58,803 1686 204 86 1313967 215730
WITHIN 15 MONTHS COMPLETION PERIOD WORKS COMPLETED 266 NOS 156 NOS 8.975 KM DELAY DUE TO HINDRANCE (DAYS) 58,353
4 OF 4