Professional Documents
Culture Documents
OPERATIONS RESEARCH
TIE 5208
July/August 2015
Special Requirements:
INSTRUCTIONS
Warehouse Product
Available
1 2 3 4
units
A 12 23 43 3 6
Factory
B 63 23 33 53 8
C 33 1 63 13 17
Required units 4 7 6 14 31
a) You are required to determine the minimum cost transportation plan, [14]
b) Calculate the cost of this plan, [2]
c) Explain the difference between solving a transportation maximization and minimization
problem. [4]
Question 2
a) Explain the meaning of the following terms , when applied to the planning and control of inventory:.
b) The forecast annual demand for a particular product sold by a retail store is 600 units; the cost is
$60 per unit. The cost of ordering and receiving delivery is $15 on each occasion. Stockholding costs
are 20% per annum of stock value.
i. Derive the basic economic batch quantity (EBQ) formula defining any symbols used and
stating clearly the assumptions you have made. [6]
ii. Calculate the optimum order quantity if there is to be instantaneous delivery of an
order. [3]
iii. Explain how the various stock related costs balance up to be economic. [5]
(a) Your Company manufactures three products. You try to follow a policy of producing those which
contribute most to fixed costs and profit. However, there is also a policy of recognizing certain
minimum sales requirements: Currently these are as shown in Table Qu3.1. these are as shown in
Table 3.1. :
You have three producing departments. The product times in hours per unit in each department and the
total times available each week in each department are as in the Table Qu 3.2 below.
The contributions per unit of products X, Y, Z are $10.50, $9.00 and $8.00 respectively. Your Company
has scheduled 1558 units of X, 30 units of Y and 60 units of Z for production in the following week.
You are required to state whether the present schedule is an optimum one from a profit point of view
and, if it is not, what it should be. [15]
(b) In Linear programming, what are the differences in dealing with minimization and maximization
problems by graphical means? [4]
(c) How many constraints can be handled by graphical methods? [1]
Question 4
a) Discuss what transpires in each of the five (5) phases on Project Management. [15]
b) Explain how the Critical Path Method (CPM) is used in Project Management. [5]
Question 6
Table Qu.6 below defines the various activities of a small project.
Table Qu 6.1. Project Activity Durations
Activity Duration (Weeks)
A 3
B 2
C 5
D 4
E 3
F 6
G 1
H 2
I 4
J 5
Question 7
a) In the phases of Operation Research, explain what transpires in the Problem Identification stage and
discuss any four tools that can be used during this stage. [10]
b) What are the pros and cons of using the Team Concept approach in solving Operations Research
problems? [5]
c) Explain the main considerations in the Bayesian Probability when using it as an Operations Research
Method. [5]
End of Examination