Professional Documents
Culture Documents
Country: Chile
Project: Santa Isabel Photovoltaic Project
Description: Load Flow (reactive power analysis)
25 Nov. 19
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
This document EE-ES-2019-1015-R0 was prepared for Sterling & Wilson Solar Ltd. by Estudios Eléctricos.
For technical questions regarding the content of this, contact:
This document contains 62 pages and was last saved on 25/11/2019 by Gustavo Alvarado; its versions and
digital signers are indicated below:
All digital signatures can be validated and authenticated through the Electrical Studies website;
http://www.estudios-electricos.com/certificados.
2 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Index
1 EXECUTIVE SUMMARY ............................................................................................................................. 5
2 PROJECT DESCRIPTION............................................................................................................................. 7
2.1 General description .......................................................................................................................... 9
Conductors ............................................................................................................................................... 16
Conductor thermal rating ......................................................................................................................... 16
3 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
5 CONCLUSIONS ........................................................................................................................................59
6 REFERENCES ...........................................................................................................................................61
6.1 General use documentation...........................................................................................................61
6.2 Project documentation ..................................................................................................................61
4 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
1 EXECUTIVE SUMMARY
TSGF SpA are developing 190.0152MWPeak/158.75MWAC Solar Photovoltaic Power Plant Project called
"Parque Fotovoltaico Santa Isabel"(Santa Isabel Photovoltaic Pharm). Sterling & Wilson solar Limited are
awarded Engineering, Procurement, Construction (EPC) Contract to build this Project by TSGF. This project will
be located at Antofagasta Region (Chile), 30km north of Maria Elena Village. The foreseen commercial operation
date is October 2020 and will have a dc installed power of 190MW and 158,75MW of full capacity delivered at
the point of interconnection with the Chilean “National Electric System” (referred to by Spanish acronym SEN).
Additionally, this project contemplates the building of a new substation one and a half breaker scheme named
“Ana María” which will split the existing transmission line 2x220kV Lagunas – Encuentro. That way, the energy
generated by photovoltaic plant will be evacuated through a single circuit 220kV line which will be connected
to the elevating substation (“Don Antonio” substation) and the sectioning substation “Ana Maria”.
In this context, Estudios Eléctricos is carrying out the design studies related with the Detailed Engineering
stage of the project. The main objective is to determine the requirements needed for the specification or
dimensioning of the equipment to be installed in Ana María and Don Antonio substation, and those in the
internal grid of the PV plant as well. Also, these studies aim to assess the compliance with the Chilean grid code
(NTSyCS) [1]. These studies are conducted in accordance with the scope letter “EE-VE-2019-0836-RD_Technical
Proposal - Interconnection Studies - Field Testing & Model Validation” [2] Considering the previous, the studies
that currently are being executed are (Stage 1 – Internal PV Plant Studies):
This document corresponds to the technical report EE-ES-2019-1015 DIgSILENT Load Flow Study (reactive
power capability analysis) corresponding to the analysis of injection/absorption of reactive power and the
assessment of the need to incorporate a capacitor bank in the internal grid of the PV plant. The analyses are
made considering the maximum admissible voltage at the point of connection (S/E Ana María), which
correspond to Emergency State in the utility (±10% from nominal voltage, i.e. 198kV y 242kV) and the reactive
power requirements stated in Article 3-8 of the Chilean Grid Code (NTSyCS). Additionally, the medium and low
voltage busbars voltages are monitored considering the internal grid requirements (tolerance in voltage of ±10%
from nominal voltage for low and medium voltage busbars) and the operation of each inverter in feasible points
considering its PQ curve, informed by the manufacturer.
The analyses are carried out considering the 220/23kV 176.25MVA power transformer on-load tap
changer of the PV Plant and the possibility to change the tap of the inverter transformers (no -load tap changer)
in order to find out which tap position results in the best performance of the inverters.
5 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Considering the mentioned above, load flow analyses are carried out for two cases: i) Compliance of
Article 3-8 and ii) analyses to determine the size of a capacitor bank which may allow compliance of Article 3-8
without reduction of the active power injection (i.e. maximum active power of the PV Plant with a reactive
power injection corresponding to a power factor of 0.95). In both cases it is considered a ±10% of variation in
the voltage at the point of interconnection (S/E Ana Maria), i.e. 220kV ±22kV, being the voltage at the23kV side
of the power transformer controlled by the on-load tap changer.
o The higher reactive losses are in the power transformer (about 30Mvar) and in the
inverter transformers (about 9Mvar in total).
o With the recommendations mentioned above it is possible to comply with Article 3-8,
keeping the medium and low voltage buses voltages within a safe range for the plant
equipment for every operating state of the utility (Normal, Alert and Emergency States).
o This allows, also, more flexibility to manage the internal grid voltages, giving more
security to the equipment and facilities of the internal grid for each condition in the utility.
o Finally, it is mentioned that according with the scope of this study, the resonance
phenomena is not considered here, but it will be analysed in the Stage II of the
Interconnection Studies contracted in the offer.
• Additionally, the internal grid is simulated in night conditions (without active power injection) and
with nominal voltage at the 23kV Don Antonio bus (1pu), with the objective of determining the
maximum voltages at the medium voltage buses. From this analysis, the following is found:
6 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
2 PROJECT DESCRIPTION
TSGF SpA are developing 190.0152MWPeak/158.75MWAC Solar Photovoltaic Power Plant Project called
"Parque Fotovoltaico Santa Isabel"(Santa Isabel Photovoltaic Farm). Sterling & Wilson solar Limited are awarded
Engineering, Procurement, Construction (EPC) Contract to build this Project by TSGF. This project will be located
at Antofagasta Region (Chile), 30km north of Maria Elena Village. The foreseen commercial operation date is
October 2020 and will have a dc installed power of 190MW and 158,75MW of full capacity delivered at the point
of interconnection with the Chilean “National Electric System” (referred to by Spanish acronym SEN).
Additionally, this project contemplates the building of a new substation one and a half breaker scheme named
“Ana María” which will split the existing transmission line 2x220kV Lagunas – Encuentro. Energy generated by
Photovoltaic Plant at 23kV will be evacuated through an 23/220kV Elevating Substation at Plant to the 220kV
Sectioning Substation at Ana Maria. A Single Circuit 220kV Line with approximately 750m length will
interconnect 23/220kV Elevating Substation at Plant and 220kV Sectioning Substation at Ana Maria.
PV Santa Isabel
7 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
The sectioning of the line Lagunas – Encuentro 2x220kV will be from the structure T071-1 through the
structure T070-1, as can be seen in the following figure.
8 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
PLOT 2:
88,75MW
PLOT 1:
70MW
9 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
• One sectioning substation 220kV one and a half scheme, that will section the 2x220kV Lagunas –
Encuentro line.
• One 220kV overhead line single circuit, 750m long that will evacuate the energy generated and
will connect Santa Isabel PV plant to the SEN.
• Zig-Zag Transformer connected to the medium voltage side of the power transformer.
• 23kV internal collector system, consisting in both underground cable and overhead lines.
10 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
3 PROJECT MODELLING
3.1 Internal grid
In the following figure can be seen the internal grid of the PV Santa Isabel project and the sectioning
substation Ana Maria 220kV.
5
10
8 7
7
10
11 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
2. 1x220kV S/E Ana María – S/E Don Antonio overhead line, 750m
3. Lagunas – Encuentro 2x220kV overhead line extension (250m)
4. 220/23kV Transformer (Don Antonio substation)
5. Zig-zag transformer
6. 2x23kV overhead line
7. Cable system made of 240mm2, 400mm2 and 630mm2 cables.
8. Inverter step-up transformer
9. Inverters
10. Auxiliary service transformer
12 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
PAÑO DESCRIPCIÓN
J1-J2 Ana María - Lagunas 2x220kV C1
J2-J3 Ana María - Encuntro 2x220kV C1
J4-J5 Ana María - Lagunas 2x220kV C2
J5-J6 Ana María - Encuentro 2x220kV C2
J7-J8 Ana María - Don Antonio 1x220kV
Table 3-1: Ana Maria 220kV substation bays
The next figure shows the detailed model of Ana Maria substation in DIgSILENT PowerFactory, which
present the same order as in the substation single line diagram [12].
13 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
In Table 3-2 are detailed each busbar stretch as can be seen also in Figure 3-2.
Longitud
Barra Tramo Terminal i Terminal j
[m]
B1-J1_B1-J4 J1 J4 18
Barra 1
B1-J4_B1-J8 J4 J8 18
B2_J3-B2_J6 J3 J6 18
Barra 2
B2-J6_B2-J9 J6 J9 18
Table 3-2: Ana Maria 220kV busbar stretches*.
Environmental data
Ana Maria substation will be built in Maria Elena substation, Tocopilla village, Antofagasta region. Figure
3-3 show the approximate georeference of the location of the substation.
Based on the above, Table 3-3 shows the environmental data considered. Some of them are obtained
from [9] other data is obtained from Google Earth using the SEN georeferences 1.
14 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
15 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Conductors
According with the collected information [12] three conductors per phase will be used for the busbar
modelling and two conductors per phase for the connection to the bay and diagonals. Any case, a AAAC
COWSLIP 2000MCM conductor type will be used, whose main characteristics are presented in the following
table.
Conductor
Parámetro Unidad
AAC COWSLIP 2000MCM
Diameter 41,41 [mm]
GMR 16,125 [mm]
DC resistance at 20°C 0,02784 [ohm/km]
AC resistance at 25°C 0,0312 [ohm/km]
AC resistance at 75°C 0,0373 [ohm/km]
Mass per unit of length 2,791 [kg/m]
Calorific Capacity 2665,4 [J/(m*°C)]
Maximum Temperature 75 (*) [°C]
Emissivity Factor 0,5 [9] -
Absorption Factor 0,5 [9] -
Table 3-4: AAAC COWSLIP 2000MCM parameters.
𝑞𝑐 + 𝑞𝑟 = 𝑞𝑠 + 𝐼 2 𝑅(𝑇𝑐 )
𝑞𝑐 + 𝑞𝑟 − 𝑞𝑠
𝐼=√
𝑅(𝑇𝑐 )
Where:
𝑞𝑐 : convection losses
𝑞𝑟 : radiation losses
𝑞𝑠 : solar contribution in heat increase
16 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
The parameters 𝑞𝑐 , 𝑞𝑟 𝑎𝑛𝑑 𝑞𝑠 are determined according the technical information of the conductor and
environmental data associated to the location of the substation (Table 3-3).
Finally, using the previous equation, the relationship between permissible current flowing through the
conductor and the ambient temperate can be found.
I adm[A]
T amb [ºC]
CON SOL SIN SOL
0 1796,0 1975,0
5 1727,2 1912,7
10 1654,9 1847,7
15 1578,7 1779,7
20 1497,7 1708,3
25 1411,3 1633,1
30 1318,3 1553,4
35 1217,2 1468,6
40 1105,7 1377,5
45 980,1 1278,9
Table 3-5: Conductor rating as function of ambient temperature.
Figure 3-4: Current vs ambient temperature curve for AAAC COWSLIP 2000MCM.
17 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
From the calculated values, 30ºC for ambient temperature with presence of sun is considered for Ana
Maria busbar conductor capacity. Thus, for the diagonals (2 conductors per phase) it is 2x1.318,3A = 2.636,6A
(~1.000MVA), while for each bar (3 conductors per phase) it is 3x1.318,3A = 3.955A (~1.500MVA).
Conductor Model
For conductor modelling of the busbar stretches (AIS) those parameter of [9] are used and for its thermal
rating the analysis of the previous section are used.
In the following figure, it can be seen the DIgSILENT model typo of AAAC COWSLIP 2000MCM conductor
18 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
19 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
For this tower, the basic height measured with a 3m foot, is considered H=25,5m.
Also, to improve the line representation, the conductor sag and length of insulators chain is considered
2
to better estimates the altitude of each conductor. For this, the following equation is used: ℎ𝑚𝑒𝑑𝑖𝑎 = ℎ𝑠 − 3 𝐹 .
Then, for this line modelling is considered 7m for sag distance and 3,4m for the insulators chain, getting this way
the mean height for each conductor as shown in table below.
Altura de
Altura altura media
Ítem suspensión del
Cruceta del conductor
conductor
Cruceta inferior [m] 25,5 22,1 19,8
Cruceta media [m] 31,5 28,1 25,8
Cruceta superior [m] 37,5 34,1 31,8
Canastillo [m] 40,5 40,5 40,5
Figure 3-7: Conductor positions.
Conductor
Parámetro Unidad
FLINT 740,8MCM
Diámetro 25,16 [mm]
GMR 9,80 [mm]
Resistencia DC a 20°C 0,0892 [ohm/km]
Resistencia AC a 25°C 0,0921 [ohm/km]
Resistencia AC a 75°C 0,1074 [ohm/km]
Masa por unidad de longitud 1,028 [kg/m]
Capacidad Calorífica 914,92 [J/(m*°C)]
Temperatura máxima 75 (*) [°C]
Factor de Emisividad 0,5 [9] -
Factor de Absorción 0,5 [9] -
Table 3-6: Phase conductor characteristics.
For ground wire modelling, typical parameter data is used knowing the diameter of the wire chosen. The
main information is shown in the table below.
20 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
DIgSILENT model
The following figure shows the equivalent circuit of a three-phase line used in DIgSILENT for static and
rms analysis, where the self-impedances and mutual impedances can be seen.
The following figures shows the parametrization used to represent the main characteristics of the project
transmission line.
21 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
The tower modelling was made from a generic reference double circuit 220kV structure. In the following
figure the tower DIgSILENT model is presented.
As it is projected to lay one line-circuit at the date of connection, for modelling purposes the tower model
has just one circuit. This have no implications in the resulting parameters.
22 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
23 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Conductor
Parámetro Unidad
FLINT 740,8MCM
Diámetro 25,16 [mm]
GMR 9,80 [mm]
Resistencia DC a 20°C 0,0892 [ohm/km]
Resistencia AC a 25°C 0,0921 [ohm/km]
Resistencia AC a 75°C 0,1074 [ohm/km]
Masa por unidad de longitud 1,028 [kg/m]
Capacidad Calorífica 914,92 [J/(m*°C)]
Temperatura máxima 75 (*) [°C]
Factor de Emisividad 0,5 [9] -
Factor de Absorción 0,5 [9] -
Table 3-7: Phase conductor characteristics.
For ground wire modelling, information has been gotten from Chilean National Coordinator website [10].
The main information is shown in the table below.
24 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
DIgSILENT model
The following figures show the model of both conductors in DIgSILENT.
25 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
26 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Figure 3-16: Nameplate extract. Don Antonio Step-up transformer 220/23kV 140MVA.
27 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
In the next sections are presented the main characteristics of the on-load tap changer and the DIgSILENT
model.
It is foreseeing the automatic operation of the tap change, controlling the medium voltage busbar.
28 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
DIgSILENT model
The following figure shows the model used to represent the transformer.
In the following figure is shown the parametrization used in the model, according with the information
provided [13].
The impedance dependence with tap position has been modelled using as reference standard values.
Nevertheless, this is relevant for the load flow study (PQ capability) where the influence in tap change is
considered. In this sense, this model must be updated when the FAT documentation is available.
29 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
30 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Preliminarily, the zig-zag transformer is modelled in such a way that after a single phase to ground fault
the residual current is 3𝐼0 = 750𝐴 as is informed by S&W [13]. Then, the zero-sequence impedance is calculated
𝑈𝑙−𝑙
as: 𝑍0 = 3 ∗
√3∗3𝐼0
31 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Structure
0, m
0, m
0, m
0m , m
32 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Phase conductor
Each circuit will have two conductor per phase. The conductor type is DARIEN 559,5MCM whose main
characteristics are presented in the table.
Conductor
Parámetro Unidad
DARIEN 559,5MCM
Diámetro 21,79 [mm]
GMR 8,251 [mm]
Resistencia DC a 20°C 0,1188 [ohm/km]
Resistencia AC a 25°C 0,1211 [ohm/km]
Resistencia AC a 75°C 0,1417 [ohm/km]
Table 3-9: Phase conductor characteristics.
DIgSILENT model
The following figures show the conductor model in DIgSILENT
The tower geometry shown previously is used to model the tower type as can be seen in the figure below.
33 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
34 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
The following table indicates the relevant distances between converter stations and the main medium
voltage switchgear.
Plot-1
HT CABLE LENGTH
MV Panel -1
CABLE SIZE
FEDDER NO. FROM TO NO OF INV. NO. FO RUN LENGTH
Sq MM
BLOCK-1 MCR 2 1 1CX400 Al 356
1
BLOCK-2 BLOCK-1 2 1 1CX240 Al 380
BLOCK-3 MCR 2 1 1CX400 Al 1065
2
BLOCK-4 BLOCK-3 2 1 1CX240 Al 300
BLOCK-5 MCR 2 1 1CX400 Al 1736
3
BLOCK-6 BLOCK-5 2 1 1CX240 Al 275
BLOCK-8 MCR 2 1 1CX400 Al 2720
4
BLOCK-11 BLOCK-8 2 1 1CX240 Al 835
BLOCK-9 MCR 2 1 1CX400 Al 2965
5
BLOCK-10 BLOCK-9 2 1 1CX240 Al 265
6 BLOCK-7 MCR 2 1 1CX240 Al 2267
Plot -2
HT CABLE LENGTH
MV Panel -5
CABLE SIZE
FEDDER NO. FROM TO NO OF INV. NO. FO RUN LENGTH
Sq MM
BLOCK-13 MCR 2 1 1CX400 Al 280
1
BLOCK-14 BLOCK-13 2 1 1CX240 Al 500
BLOCK-15 MCR 2 1 1CX400 Al 1133
2
BLOCK-16 BLOCK-15 2 1 1CX240 Al 460
BLOCK-18 MCR 2 1 1CX400 Al 1020
3
BLOCK-17 BLOCK-18 2 1 1CX240 Al 460
BLOCK-19 MCR 2 1 1CX400 Al 1026
4
BLOCK-24 BLOCK-19 2 1 1CX240 Al 745
MV Panel -6
BLOCK-20 MCR 2 1 1CX400 Al 1440
5
BLOCK-21 BLOCK-20 2 1 1CX240 Al 460
BLOCK-23 MCR 2 1 1CX400 Al 1350
6
BLOCK-22 BLOCK-23 2 1 1CX240 Al 460
BLOCK-25 MCR 2 1 1CX400 Al 1770
7
BLOCK-26 BLOCK-25 2 1 1CX240 Al 460
8 BLOCK-12 MCR 2 1 1CX240 Al 402
Table 3-10: Cable system detail.
35 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
36 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
37 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
38 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
2750 kVA
39 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
The following table shows the distribution of the inverter transformer by inverter station (Block).
40 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
The following figures show the model of each inverter transformer in DIgSILENT.
41 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
42 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
43 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
3.10 Inverters
50 inverters of 3125kW and one of 2750kW will be used. These equipments will take the energy generated
by the arrays of photovoltaic cells, in the form of direct current and convert it into alternating current for
transport at a voltage level of 23kV to the lifting substation. The main characteristics of investors are:
The following figure shows the capability curves of the inverters, with their temperature dependency.
For the design of the PV plant, an operating temperature of 40ºC is considered in the inverters. Thus,
considering 40°C, these inverters deliver a maximum active output power of 3.437MW (@ 0Mvar) and a
maximum reactive power of ± 2.062Mvar (@2.75MW).
Similarly, for the 2874kVA inverter, an operating temperature of 40ºC is considered. In this way, these
inverters deliver a maximum active output power of 2.874MW (@ 0Mvar) and a maximum reactive power of ±
1.72Mvar (@ 2.3MW).
Regarding the contribution to the short-circuit current, a contribution equal to 1.1 times the nominal
current of the inverter is considered.
44 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Figure 3-32: Power derating dependence with (above) ambient temperature and (below) ac grid voltage.
45 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
46 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
47 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Figure 3-35: Main characteristics – Auxiliary service Transformers – Santa Isabel PV plant.
Following figure shows the principal parameters in the DIgSILENT Power Factory representation:
48 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
4.1 Methodology
The PV Plant performance related to its capability to inject and absorb reactive power is assessed for the
condition of Emergency State in the utility and, as a result, the need of incorporate capacitor bank in the internal
grid is determined. The analyses are made considering the maximum and minimum admissible voltages at the
point of interconnection for Emergency State (±10% from nominal voltage, i.e. 198kV and 242kV) and the
requirements stated in Article 3-8 of the NTSyCS. Additionally, the low and medium voltage buses voltages are
monitored considering the internal grid’s own requirements (voltage tolerance of ±10% from nominal voltage)
and the operation in admissible points of the inverters is verified, according with the PQ curve informed by
manufacturer.
The analyses are carried out considering the operation of the on-load tap changer of the power
transformer and the possibility to change the no-load tap of the inverter transformers.
49 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
4.2 Analysis
From the analyses carried out it is found that the most severe condition correspond to those in which the
voltage at the point of connection is 1.1pu and the inverters are injecting about 95% of rated power with a
reactive power corresponding with a power factor of 0.95 in order to achieve the highest injection of active and
reactive power requested in Article 3-8 (about 150MW and 49Mvar). In this scenario, the voltage at the inverter
terminals may be higher than 1.1pu, that is why is made the recommendation of use the tap position of the
inverter transformer in that corresponding to 23kV+5% (2 steps from nominal).
The following figures show the results of the simulations for the operating conditions with voltage of
1.1pu and 0.9pu at the interconnection point, considering the tap position recommended for the inverter
transformers. The yellow surface indicates the no-compliance area.
160
No-compliance
140
120
100
MW
80
60
40
20
0
-150 -100 -50 0 50 100 150
MVAr
Figure 4-1: Operating points with OLTC an v=1,1pu at PCC.
50 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
160
No-compliance
140
120
100
MW
80
60
40
20
0
-150 -100 -50 0 50 100 150
MVAr
Figure 4-2: Operating points with OLTC an v=0,9pu at PCC.
As can be seen from the above figures, the OLTC with 17 steps plus the recommendation are not enough.
Based on the above, it is recommended a capacitor bank of 13Mvar. The following figure shows the load flow
with capacitor bank of 13Mvar, OLTC 220kV±8x1.25% and tap position of the inverter transformer in +5% (2
steps) for the condition with voltage at the point of interconnection of 1.1pu and generation of 95% of maximum
active power with reactive power corresponding to a power factor of 0.95% (related to maximum active power).
51 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Figure 4-3: Verification with capacitor bank of 13Mvar and OLTC 220kV±8% in steps of 1.25%.
As can be seen from the above figure, even though the active and reactive power are in accordance with
Article 3-8, there are 23kV buses with overvoltage (over 1.1pu). To counter this 33kV switchgear shall be
considered and for inverter transformer 23kV±11% variation shall be considered on the MV side. The following
sections shows the validations of all the recommendations made.
52 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
4.3 Recommendations
Based on the results pointed out previously, the following recommendations are made to comply with
Article 3-8:
53 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
160
140
120
100
MW
80
60
40
20
0
-150 -100 -50 0 50 100 150
MVAr
Figure 4-4: Operating points with capacitor bank of 13Mvar, OLTC 220kV ±10% in steps of 1.25% and v=1,1pu at PCC.
54 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
160
140
120
100
MW
80
60
40
20
0
-150 -100 -50 0 50 100 150
MVAr
160
140
120
100
MW
80
60
40
20
0
-150 -100 -50 0 50 100 150
MVAr
Figure 4-5: Operating points with capacitor bank of 13Mvar, OLTC 220kV ±10% in steps of 1.25% and v=0,9pu at PCC.
55 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
In the following figures are shown the load flows for the most demanding conditions regarding the voltage
level at the interconnection point (1,1pu and 0,9pu) and active power injection of 95% with reactive power
corresponding to a power factor of 0.95.
Figure 4-6: Load flow with capacitor bank of 13Mvar, OLTC 220kV ±8% in steps of 1.25% and v=1,1pu at PCC.
56 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
Figure 4-7: Load flow with capacitor bank of 13Mvar, OLTC 220kV ±10% in steps of 1.25% and v=0,9pu at PCC.
57 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
The following figure shows the load flow for the condition with voltage level at the interconnection point
of 0,9pu, no active power injection and with reactive power corresponding to a power factor of 0.95 (absorbing).
Figure 4-8: Load flow without capacitor bank of 13Mvar, OLTC 220kV ±8% in steps of 1.25% and v=0,9pu at PCC.
58 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
5 CONCLUSIONS
The PV Plant performance related to its capability to inject and absorb reactive power is assessed for the
condition of Emergency State in the utility and, as a result, the need of incorporate capacitor bank in the internal
grid is determined. The analyses are made considering the maximum and minimum admissible voltages at the
point of interconnection for Emergency State (±10% from nominal voltage, i.e. 198kV and 242kV) and the
requirements stated in Article 3-8 of the NTSyCS. Additionally, the low and medium voltage buses voltages are
monitored considering the internal grid’s own requirements (voltage tolerance of ±10% from nominal voltage)
and the operation in admissible points of the inverters is verified, according with the PQ curve informed by
manufacturer. The analyses are carried out considering the operation of the on-load tap changer of the power
transformer and the possibility to change the no-load tap of the inverter transformers.
o The higher reactive losses are in the power transformer (about 30Mvar) and in the
inverter transformers (about 9Mvar in total).
o With the recommendations mentioned above it is possible to comply with Article 3-8,
keeping the medium and low voltage buses voltages within a safe range for the plant
equipment for every operating state of the utility (Normal, Alert and Emergency States).
o This allows, also, more flexibility to manage the internal grid voltages, giving more
security to the equipment and facilities of the internal grid for each condition in the utility.
o Finally, it is mentioned that according with the scope of this study, the resonance
phenomena is not considered here, but it will be analysed in the Stage II of the
Interconnection Studies contracted in the offer.
59 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
• Additionally, the internal grid is simulated in night conditions (without active power injection) and
with nominal voltage at the 23kV Don Antonio bus (1pu), with the objective of determining the
maximum voltages at the medium voltage buses. From this analysis, the following is found:
60 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
6 REFERENCES
6.1 General use documentation
[1] NORMA TÉCNICA DE SEGURIDAD Y CALIDAD DE SERVICIO. Comisión Nacional de Energía. Mayo
2018.
[2] EE-VE-2019-0836-RD_Technical Proposal - Interconnection Studies - Field Testing & Model
Validation.
[3] FIJACIÓN DE PRECIOS DE NUDO DE CORTO PLAZO. INFORME TÉCNICO DEFINITIVO ENERO 2019.
Comisión Nacional de Energía.
[4] Cuadros-ITD-Enero.xlsx
[5] Informe-Catastro-de-Proyectos-CNE-2019.07.xlsx
[6] DU SEN 2018.06.22_RA.dwg Diagrama unilineal General del Sistema Eléctrico Nacional.
Coordinador Independiente del Sistema Eléctrico Nacional. 22/06/2018.
[7] Base de datos del SEN: https://www.coordinador.cl/operacion/documentos/modelacion-del-
sen/modelos-digsilent/base-de-datos-digsilent/
[8] Mapa SEN: Mapa_Sistema_Electrico_Nacional_mayo_2019.pdf. Coordinador Independiente del
Sistema Eléctrico Nacional.
[9] IEEE 738-2012 - IEEE Standard for Calculating the Current-Temperature Relationship of Bare
Overhead Conductors.
[10] https://infotecnica.coordinador.cl/instalaciones/secciones-tramos
61 / 62
Santa Isabel Photovoltaic Project
Load Flow (reactive power analysis)
62 / 62