Professional Documents
Culture Documents
fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
1
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
2
𝑐sum,𝑗 Total weighting factor of load zones in load group 𝑗. crogrids, such as fuels for generators and electric energy in
𝑃sum,𝑗 Total amount of load (kW) at load zones in load storage devices, can be limited and hard to get supplemented. A
group 𝑗. practical service restoration plan should also take into account
𝜏𝑗 Time duration (hours) in which load zones in load the scarcity of generation resources.
group 𝑗 are served by the corresponding microgrid if Studies on distribution system service restoration include the
load group 𝑗 is selected. development of reconfiguration algorithms, optimal energizing
Notation associated with switching operations: strategies, and approaches to enhancement of restoration ca-
m
𝑡swi Mean time to operate a manual switch. pability [4]-[10]. Some recent studies have considered utiliza-
r
𝑡swi Mean time to operate a remote-controlled switch tion of DGs, energy storages, electric vehicles (EVs), and mi-
(RCS). crogrids for service restoration [11]-[15]. In [11], a multi-stage
𝑡int Lower limit on the length of time interval between restoration procedure is proposed to maximize the amount of
two consecutive restorative actions. load restored by DGs. The upper limit on the amount of load
𝑁fc Number of field crews. that can be picked up by a DG at the same time is a dynamic
𝑺m fi Set of manual switches adjacent to faulted zones. constraint of the DG. The limits on frequency deviation are also
𝑺rfi Set of RCSs adjacent to faulted zones. considered. In [12], a decentralized multi-agent system (MAS)
𝑺mrpi Set of manual switches for restoration path isolation.
is proposed to restore interrupted loads using DGs and EVs.
r
𝑺rpi Set of RCSs for restoration path isolation. The impact of vehicle-to-grid (V2G) facility on service resto-
𝑺msr,𝑗 Set of manual switches for restorative actions of load ration is investigated. In the authors' prior work [15], a
group 𝑗. graph-theoretic restoration algorithm is designed to find the
𝑺rsr,𝑗 Set of RCSs for restorative actions of load group 𝑗. optimal post-outage network configuration for distribution
ceil(⋅) Function that rounds the input number to the nearest systems with microgrids. It is shown that microgrids improve
integer greater than or equal to that number. the restoration capability of a distribution system. A method for
enhancement of restoration capability by adding re-
II. INTRODUCTION mote-controlled switches (RCSs) is proposed [16].
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
3
for basic societal needs. Priority levels of critical loads feeders weighted by the priority. Dynamic, generation-resource,
are considered. operational, and topological constraints are considered. The
3) The stability of microgrids and dynamic performance of critical load restoration problem is formulated as follows.
DGs during the restoration process are incorporated. A. Objective
Dynamic simulations are performed to evaluate the
feasibility of restoration schemes. Maximizing the cumulative service time of microgrids
to loads on the distribution feeders weighted by their
4) Limits on the amount of available generation resources
priority, i.e.,
within microgrids are considered.
Some recent studies [13], [15] also use microgrids for service max ∑ 𝑡𝑖 𝑐𝑖 (1)
restoration. In [13], a black-start restoration procedure is pro- 𝑖∈𝒁uni
posed, which uses micro-sources to energize load within a In general, the weighting factor should be greater than or
microgrid when a blackout occurs. In contrast, this paper is equal to zero, i.e., 𝑐𝑖 ≥ 0. To ensure that the limited capacity of
focused on using the available generation capacity of a mi- DGs and generation resources are first used to serve critical
crogrid to serve critical load outside the microgrid. The authors’ loads, the weighting factor of a critical load zone should be
prior work [15] explores the feasibility of using microgrids to sufficiently greater than that of a non-critical one. For example,
support the local distribution system. It considers only sin- one can let 𝑐𝑖 ≥ 1 and 𝑐𝑖 ≤ 0.05 for critical and non-critical
gle-fault scenarios. Microgrids are modeled as a voltage source load zones, respectively. Sometimes, using microgrids to serve
non-critical loads on distribution feeders may be too costly
and power flow calculations are performed to evaluate restora-
from the utility viewpoint, since DGs within microgrids may
tion strategies. In this paper, the authors extend their work to
not belong to the utility. In this case, let 𝑐𝑖 < 0 to avoid unde-
multiple-fault scenarios. Dynamic characteristics of DGs and
sired energization of non-critical loads. By allowing the
limits on generation resources are incorporated. weighting factors to be assigned positive to negative values,
The remainder of this paper is organized as follows. Section more flexibility is provided.
III formulates the critical load restoration problem. Section IV
describes the proposed method. In Section V, numerical simu- B. Constraints
lation results for a 1069-bus test system are presented. Section 1) Dynamic Constraints: Assume that the restoration process
VI describes the application of the proposed method to a real starts at time 𝑡 = 0 and the system reaches a steady state at time
distribution system. The conclusion is given in Section VII. 𝑡 = 𝑇 > 0 (if it is stable).
Each microgrid must be stable during the restoration
III. PROBLEM FORMULATION process. That is, after the restorative actions are per-
formed, the microgrid should reach a steady state with
A major disaster, such as an earthquake, can damage trans-
an acceptable frequency. Limits on the steady-state
mission and/or distribution lines serving substations in a region.
As a result, the electric power from the transmission or distri- frequency are defined by
s
bution system cannot reach the loads in the region. However, 𝑓min ≤ 𝑓𝑘s ≤ 𝑓max s
,𝑘∈𝑴 (2)
s s
local generators in the regional distribution system, such as In this paper, 𝑓min = 59.5 Hz and 𝑓max = 60.5 Hz.
DGs in a microgrid, may be able to serve the critical loads on During the restoration process, the frequency of each
the distribution feeders by reconfiguration of the distribution microgrid should be within an acceptable range, i.e.,
tr tr
lines that survive the extreme event. 𝑓min ≤ 𝑓𝑘 (𝑡) ≤ 𝑓max , 𝑘 ∈ 𝑴, 𝑡 ∈ [0, 𝑇] (3)
tr
Assume that, after a major disaster, faulted zones are isolated In this paper, the nominal frequency is 60 Hz, 𝑓min = 54
tr
and microgrids are operated in an islanded mode. As a result, Hz, and 𝑓max = 62 Hz.
interrupted islands are formed. An interrupted island is a con- The transient voltage at the terminal of generators
nected portion of a distribution feeder that has no connection should not exceed the preset limits, i.e.,
tr
(except open switches) to other portions of the system and has 𝑉min ≤ 𝑉𝑔tr (𝑡) ≤ 𝑉max tr
, 𝑔 ∈ 𝑮, 𝑡 ∈ [0, 𝑇] (4)
no power source within it. Microgrids and interrupted islands tr tr
In this paper, 𝑉𝑚𝑖𝑛 = 0.9 p.u. and 𝑉max = 1.1 p.u.
are linked by tie switches or microgrid switches. A microgrid The transient current output by a generator should not
would first serve its own critical loads. If the microgrid has exceed the preset limits, i.e.,
spare power capacity and generation resources, it becomes an 𝐼𝑔tr (𝑡) ≤ 𝐼max,𝑔
tr
, 𝑔 ∈ 𝑮, 𝑡 ∈ [0, 𝑇] (5)
available resource for service restoration of critical loads on the tr
In this paper, 𝐼max,𝑔 is 1.1 times of the nominal current.
distribution feeders.
A weighting factor is assigned to each load zone to represent 2) Generation-Resource Constraints:
the priority level. Regard a load zone with/without critical loads The amount of energy that a microgrid can provide to
as a critical/non-critical load zone, which is indicated by a external loads is limited, i.e.,
large/small value of the weighting factor. Due to the scarcity of ∑𝑖∈𝑹𝑘 𝑡𝑖 𝑃𝑖 ≤ 𝐸𝑘ex , 𝑘 ∈ 𝑴 (6)
DG power capacity and generation resources within microgrids The left-hand side of (6) is the total amount of energy served
after a major disaster, microgrids should first be used to serve to external (critical and non-critical) loads by microgrid 𝑘. On
critical loads rather than non-critical ones. With limited gener- the right-hand side, 𝐸𝑘ex = 𝐸𝑘total − 𝐸𝑘in − 𝐸𝑘loss is the upper
ation resource, a microgrid can only serve the loads restored by limit on the amount of energy that microgrid 𝑘 can provide to
it for a limited period of time. The objective is to maximize the its external loads. The total amount of energy, 𝐸𝑘total , depends
cumulative service time of microgrids to loads on distribution on the amount of generation resources within microgrid 𝑘 ,
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
4
including fuel for generators, such as diesel and natural gas, and feasible path between them. All paths that start from a mi-
electric energy stored in storage devices. 𝐸𝑘in is the amount of crogrid form a graph-theoretic tree rooted at the microgrid,
energy served to internal critical loads of microgrid 𝑘. 𝐸𝑘loss is referred to as a restoration tree. The number of restoration trees
the energy loss associated with microgrid 𝑘 , which can be equals that of microgrids.
derived from power flow calculations. For convenience, these The second step is aimed at forming load groups. A load
energy terms are all measured by equivalent electric energy in group is a subset of load zones that can be restored together as a
kWh. The conversion rate from the amount of fuel to electric group by a microgrid through their restoration paths. For each
energy varies with machines and should be determined case by microgrid, a set of load groups can be determined from its
case. As an example, for the diesel generator on Washington restoration tree. If a load zone belongs to a load group, it is
State University (WSU) campus, generating 1-kWh electric covered by the load group.
energy consumes about 0.086 gallons of diesel. The third step formulates the critical load restoration prob-
3) Operational Constraints: lem as a maximum coverage problem. By solving the maxi-
Unbalanced three-phase power flow equations [18] must mum coverage problem, the set of critical load zones restored
be satisfied. and the set of load groups covering these critical load zones are
determined. The corresponding restoration paths are identified
𝑃𝑢𝑠 − 𝑗𝑄𝑢𝑠 = (𝑉̅𝑢𝑠 )∗ ∑ ∑ 𝑌𝑢𝑣 𝑠𝑡 ̅ 𝑡
𝑉𝑣 , from the restoration trees.
𝑣∈𝛀𝑢 𝑡 (7)
The last step determines the restorative actions, i.e., switch-
𝑢 ∈ 𝛀, 𝑠, 𝑡 ∈ {𝑎, 𝑏, 𝑐} ing operations, to restore the critical loads. Dynamic simula-
Steady-state bus voltages should be maintained within tions are performed to evaluate the technical feasibility of the
acceptable operating limits. actions.
𝑉min ≤ 𝑉𝑢 ≤ 𝑉max , 𝑢 ∈ 𝛀 (8)
B. Construct Restoration Trees
In this paper, 𝑉min = 0.95 p.u. and 𝑉max = 1.05 p.u.
Steady-state line currents should not exceed their limits. Model the distribution system as an undirected graph 𝐺 =
𝐼𝑙 ≤ 𝐼max,𝑙 , 𝑙 ∈ 𝑳 (9) (𝑽, 𝑬), where 𝑽 and 𝑬 are the set of nodes and arcs, respec-
The steady-state output power of each microgrid should tively [15]. Nodes in 𝑽 represent load zones and microgrids,
not exceed the maximum amount of power that it is able while arcs in 𝑬 represent switches. Furthermore, a node rep-
to provide, i.e., the total generation capacity of DGs resenting a load zone or microgrid is called a load node or
minus the amount of critical load within the microgrid. source node, respectively. Particularly, a node representing a
𝑃𝑘 ≤ 𝑃max,𝑘 critical load zone is called a critical load node. A weight 𝑤 is
{ ,𝑘∈𝑴 (10) set for each load node, whose value equals the amount of load
𝑄𝑘 ≤ 𝑄max,𝑘
at the corresponding load zone.
4) Topological Constraint:
Define the weight of a path as the total amount of load on the
A radial network structure should be maintained, i.e., a path. For a given “microgrid – critical load zone” pair, the
critical load is served by only one microgrid through one restoration path between the corresponding source and critical
path and the paths for different critical loads do not load nodes is defined as any path whose weight is minimum
overlap. Maintaining a radial structure helps to simplify among all paths between them. The modified Dijkstra’s algo-
some operational issues, such as synchronization and rithm [17] is used to determine the restoration paths from a
load sharing among microgrids. Moreover, in a radial given microgrid to all critical load zones. Validate the restora-
network, the relay settings can be easily adjusted to tion paths by power flow calculations and dynamic simulations
protect the system from potential subsequent faults. and remove unfeasible ones. Then a feasible restoration tree is
found.
IV. THE PROPOSED METHOD The pseudo code for the restoration tree construction algo-
In this section, a graph-theoretic algorithm for the critical rithm is shown below. It returns the restoration tree of a given
load restoration problem is proposed. Subsection IV-A intro- source node (microgrid), denoted by 𝑠. For a node 𝑣 ∈ 𝑽, the
duces the overall procedure to generate the restoration strategy, attribute 𝑣. 𝑑 is an upper bound on the amount of load on the
which consists of four steps. Subsections IV-B to IV-E illus- restoration path from 𝑠 to 𝑣. When a restoration path is found,
trate the four steps in detail, respectively. Subsection IV-F 𝑣. 𝑑 equals the amount of load on the restoration path. The
discusses time associated with fault management activities. attribute 𝑣. 𝜋 is the predecessor of 𝑣. A min-priority queue 𝑸 is
Subsection IV-G describes the software implementation of the used to manage the nodes, keyed by the 𝑑 values. Nodes that
proposed method. have not been explored by the algorithm are stored in 𝑸. Here,
A. Critical Load Restoration Procedure exploring a node means discovering its neighboring nodes and
updating their attributes. Function EXTRACT-MIN (𝑸) extracts
A four-step procedure is proposed to determine the critical and removes the node with the minimum value of 𝑑 from 𝑸.
load restoration strategy: 1) construct restoration trees, 2) form
The graph 𝑇 = (𝑽𝑡 , 𝑬𝑡 ) represents the restoration tree. 𝑽𝑡 and
load groups, 3) formulate and solve the critical load restoration
𝑬𝑡 are its node set and arc set, respectively.
problem as a maximum coverage problem, and 4) determine
restorative actions.
The first step identifies the paths from microgrids to critical
loads. For each “microgrid – critical load zone” pair, a unique
path is determined, called a restoration path, or there is no
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
5
Algorithm: Construct Restoration Tree for a Microgrid Note that the algorithm returns only one restoration tree for
⊳ Initialization each microgrid. The uniqueness of the restoration tree is
1 for each node 𝑣 ∈ 𝑽 guaranteed by the restoration path search process in Lines 8-19,
2 𝑣. 𝑑 ← ∞ which is based on Dijkstra’s algorithm. Dijkstra’s algorithm
3 𝑣. 𝜋 ← 𝑁𝑈𝐿𝐿 identifies a unique path, which is the shortest path, from the
4 end for source to each node [19].
5 𝑠. 𝑑 ← 0 The feasibility of each restoration path is evaluated by power
6 𝑸←𝑽 flow calculation and dynamic simulation with GridLAB-D [20]
7 𝑪 ← Set of critical load nodes (Line 23). Power flow is calculated with load zones that are not
⊳ Identify restoration paths on the restoration path disconnected. Operational constraints,
8 while 𝑸 ≠ ∅ && 𝑪 ≠ ∅
i.e., (7)-(10), are examined. In the dynamic simulation, load
9 𝑢 ← EXTRACT-MIN (𝑸)
zones on the restoration path are picked up one by one with a
10 for each node 𝑣 adjacent to 𝑢
⊳ Relaxation operation preset time interval, say one minute, between two consecutive
11 if 𝑣. 𝑑 > 𝑢. 𝑑 + 𝑤(𝑣) restorative actions, which allows the dynamics induced by an
12 𝑣. 𝑑 ← 𝑢. 𝑑 + 𝑤(𝑣) action to damp out before the next action is performed. Stability
13 𝑣. 𝜋 ← 𝑢 of microgrids and other dynamic constraints, i.e., (2)-(5), are
14 end if examined. If all constraints in Section III-B are satisfied, nodes
15 end for and arcs on the restoration path are added to the node set and
16 if 𝑢 ∈ 𝑪 arc set of the restoration tree, respectively (Lines 24-31). In-
17 𝑪 ← 𝑪 − {𝑢} feasible restoration paths will not be included in the restoration
18 end if tree.
19 end while
In order to reduce the number of power flow calculations and
⊳ Construct restoration tree
20 𝑽𝑡 ← {𝑠} dynamic simulations, the program will first check if the total
21 𝑬𝑡 ← ∅ amount of load on the restoration path exceeds the maximum
22 for each critical load node 𝑣 ∉ 𝑪 power that can be provided by the corresponding microgrid. If
23 Evaluate the feasibility of the restoration path from 𝑠 to yes, the restoration path is considered infeasible without per-
𝑣 by performing a power flow calculation and a dy- forming a power flow calculation or a dynamic simulation;
namic simulation otherwise, a power flow calculation will be performed. If any of
24 if the restoration path from 𝑠 to 𝑣 is feasible the operational constraints is violated, the restoration path is
⊳ Add the nodes and arcs on the restoration path determined to be infeasible without performing a dynamic
to 𝑽𝑡 and 𝑬𝑡 , respectively. simulation; otherwise, a dynamic simulation will be conducted
25 𝑢←𝑣 to examine the dynamic constraints.
26 while 𝑢 ∉ 𝑽𝑡
27 𝑽𝑡 ← 𝑽𝑡 ∪ {𝑢} C. Form Load Groups
28 𝑬𝑡 ← 𝑬𝑡 ∪ {(𝑢. 𝜋, 𝑢)}
Given a microgrid, a set of load groups can be found by ex-
29 𝑢 ← 𝑢. 𝜋
30 end while
ploring all possible combinations of critical load zones on its
31 end if restoration tree. For each combination, a load group is formed,
32 end for which consists of load zones on the restoration paths from the
33 𝑇 ← (𝑽𝑡 , 𝑬𝑡 ) microgrid to critical load zones in the combination. The feasi-
bility of load groups with two or more critical load zones will
Lines 1-5 initialize attributes of nodes. The predecessor of be evaluated by power flow calculations and dynamic simula-
nodes are set to 𝑁𝑈𝐿𝐿 (Line 3). The 𝑑 value of node 𝑠 is set to tions. Infeasible load groups are removed from the set.
0 (Line 5) while that of other nodes are set to infinity (Line 2). For each feasible load group, indexed by 𝑗, the microgrid
Line 6 inserts all nodes into 𝑸. A universal set of critical load service time 𝜏𝑗 is calculated. Suppose that load group 𝑗 is as-
nodes, i.e., 𝑪, is defined in Line 7. The while loop of Lines 8-19 sociated with microgrid 𝑘. Then, 𝜏𝑗 = 𝐸𝑘ex /𝑃sum,𝑗 .
searches for the restoration paths from 𝑠 to critical load nodes.
D. Maximum Coverage Problem Formulation
In each iteration, the node with minimum 𝑑 value, denoted by
𝑢, is extracted from 𝑸 (Line 9). Node 𝑢 will be explored in this A load group indicates a feasible restoration scheme. Sup-
iteration and removed from 𝑸. The technique of relaxation [19] pose load group 𝑗 corresponds to microgrid 𝑘 and covers crit-
is applied to nodes adjacent to 𝑢 (Lines 10-15). If 𝑢 is a critical ical load zones 𝑖1 , 𝑖2 , … , 𝑖𝑝 (𝑝 ≥ 1). Then zones 𝑖1 , 𝑖2 , … , 𝑖𝑝 can
load node, it is removed from 𝑪 (Lines 16-18). It means that the be restored by microgrid 𝑘 through their restoration paths
restoration path from 𝑠 to 𝑢 is found. The search ends when without violating any constraint.
one of the two conditions is met: 𝑪 = ∅ (the restoration paths Select a set of disjoint load groups. Any two distinct load
from 𝑠 to all critical load nodes are found) or 𝑸 = ∅ (all nodes groups in the set correspond to different microgrids. Then the
connected to 𝑠, directly or indirectly, have been explored). In critical load zones covered by the selected load groups can be
the latter case, 𝑪 may not be empty, which indicates that no restored without violating any constraint. Therefore, the critical
path exists between 𝑠 and critical load nodes remaining in 𝑪. load restoration problem can be formulated as a maximum
Lines 20-33 form the restoration tree rooted at 𝑠. coverage problem as follows:
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
6
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
7
The electromechanical simulation method for unbalanced ical loads are connected at the bus. The microgrid is connected
power systems proposed in [23] is used in this study to simulate to the distribution system through a transformer at the point of
system dynamics. The electromechanical simulation method common coupling (PCC). The generation and load information
includes a synchronous machine dynamic model, a network for the four microgrids in the test system are given in Table I.
solver, an interface, and an initialization program. More details Parameters for generators and transformers are given in the
can be found in [23]. Appendix.
Power flow calculation and dynamic simulation results are Power flow calculations and dynamic simulations of the test
written into comma-separated values (CSV) files by system are performed using GridLAB-D. For power flow cal-
GridLAB-D. The MATLAB program reads data from the CSV culations, the generator bus in a microgrid is modeled as a slack
files, calculates variables in (2)-(10), and evaluates the opera- bus (constant voltage). For dynamic simulations, a generator
tional and dynamic constraints. Then the feasibility of restora- model applicable for unbalanced simulation [23] is adopted. A
tion paths and load groups is determined. Woodward diesel governor model (DEGOV) is used to main-
tain a constant frequency, i.e., 60 Hz, in the steady state. A
V. CASE STUDY simplified exciter system model (SEXS) is used to regulate the
generator’s terminal voltage (average magnitude of phase
A. System Information voltages). The diagrams and parameters for DEGOV and SEXS
A 4-feeder 1069-bus test system [16] with four microgrids are given in the Appendix. More details on the models of gen-
and five critical loads is used to validate the effectiveness of the erator and controllers can be found in [23].
proposed method. The one-line diagram of the test system is
shown in Fig. 1. The test system has a model in a GridLAB-D TABLE I
compatible format, which is based on the taxonomy feeder GENERATION AND LOAD DATA FOR MICROGRIDS
Microgrid ID 1 2 3 4
“R3-12.47-2” model [24] developed by the Pacific Northwest
Generation Real Power (MW) 8.5 4.25 5.95 3.4
National Laboratory (PNNL). Capacity Reactive Power (MVar) 5.27 2.63 3.69 2.11
A simplified microgrid model is used, as shown in Fig. 2. Generation Resource (MWh) 65 30 45 25
Each microgrid is modeled as a grid with a single bus. An Critical Demand (MW) 4.38 2.1 2.95 1.86
aggregated generator whose capacity equals the total capacity Load Power Factor 0.9 0.9 0.9 0.9
of controllable units and an aggregated load representing crit-
Z28 Z15
Z10
F-a Z1 Z24 Z4 Z30 Z8 Z18 Z5 Z23 Z6 Z7 Z19 Z2 Z14 Z16 Z9 Z26 Z27
FB-a Z22
CL1
Z34 Z21 Z36 Z32 Z11
T2 Microgrid 2
Z37 Z68 Z55 M
T1 Z65 Z80 Z73
Z69
Z50
F-b Z41 Z64 Z62 Z44 Z48 Z58 Z45 Z63 Z46 Z47 Z59 Z42 Z54 Z56 Z49 Z66 Z67
FB-b Z70
CL2
T3
Z74 Z61 Z76 Z72 Z51 Z53
T7
Z77 Z108 Z95 T6
Z105 Z113 Microgrid 3
S Z109
M
Sub- Z111 Z115 Z116 Z97 Z100 Z119 Z118 Z83 Z93
CL4
Transmission Z88 Z90
F-c Z81 Z104 Z84 Z110 Z85 Z103 Z86 Z87 Z82 Z94 Z96 Z89 Z106 Z107
Node Z98 Z99
FB-c Z102 Z92
F-d Z121 Z144 Z142 Z124 Z150 Z128 Z138 Z125 Z143 Z126 Z127 Z139 Z122 Z134 Z136 Z130 Z146 Z147
FB-d Z129
Voltage Regulator F-a Feeder Id Load Zone Feeder Breaker Sectionalizing Switch Tie/Microgrid Switch M Microgrid
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
8
TABLE II
RESTORATION TREES
Microgrid ID Restoration Paths
1) M1-Z39-Z7-Z19-Z2
2) M1-Z39-Z7-Z19-Z2-Z14-Z16-Z9-Z78-Z54-Z56-Z49
Fig. 2. A simplified microgrid model. 3) M1-Z39-Z7-Z6-Z23-Z5-Z18-Z8-Z30-Z4-Z21-Z37-Z75
-Z48-Z58-Z45-Z90-Z92
1
4) M1-Z39-Z7-Z6-Z23-Z5-Z18-Z8-Z30-Z4-Z21-Z37-Z75
B. Results -Z48-Z58-Z45-Z90-Z106-Z93
Five zones in the test system are critical load zones, i.e., Z2, 5) M1-Z39-Z7-Z19-Z2-Z14-Z16-Z9-Z10-Z26-Z27-Z146
-Z130-Z132
Z49, Z92, Z93, and Z132. Each of them contains one critical
2 None
load, whose priority levels, 𝑐𝑖 , are 3, 3, 2, 2, and 1, respectively. 1) M3-Z93-Z106-Z90-Z45-Z63-Z46-Z47-Z59-Z42-Z54
The weighting factors for non-critical load zones are 0.05. -Z78-Z9-Z16-Z14-Z2
Assume that a severe event caused an outage of the entire dis- 3 2) M3-Z93-Z106-Z90-Z45-Z63-Z46-Z47-Z59-Z42-Z54
tribution system. Power from the transmission system is una- -Z56-Z49
vailable. Seven faults occurred in the distribution network. The 3) M3-Z93
corresponding faulted zones are Z22, Z60, Z70, Z98, Z99, 4 None
Z102, and Z129, as shown in Fig. 1. The outage duration is TABLE III
estimated to be 10 hours. LOAD GROUPS
The proposed method is used to find a restoration strategy for Index 𝑗 Source Critical Load Zones 𝑐sum,𝑗 𝜏𝑗 (hour)
the critical loads. 1 Microgrid 1 Z2 3.05 10
Step 1: construct restoration trees. Five restoration paths are 2 Microgrid 1 Z92 2.2 9.02
identified for Microgrid 1, three for Microgrid 3, and none for 3 Microgrid 1 Z93 2.2 9.77
Microgrids 2 and 4. Therefore, a restoration tree is constructed 4 Microgrid 1 Z92, Z93 4.2 7.33
for Microgrids 1 and 3, respectively. The results are summa- 5 Microgrid 1 Z2, Z132 4.25 7.35
6 Microgrid 1 Z2, Z93 5.2 9.53
rized in Table II.
7 Microgrid 1 Z2, Z92 5.2 8.83
Step 2: form load groups. Sixteen load groups are formed.
8 Microgrid 1 Z2, Z49 6.2 10
Weighting factors 𝑐sum,𝑗 and service time 𝜏𝑗 are calculated for 9 Microgrid 1 Z2, Z92, Z93 7.2 7.22
each load group, as shown in Table III. Only critical load zones 10 Microgrid 1 Z2, Z49, Z132 7.3 6.97
in each load groups are given. Non-critical load zones in the 11 Microgrid 1 Z2, Z49, Z93 8.35 8.37
load groups can be identified from the restoration paths given in 12 Microgrid 1 Z2, Z49, Z92 8.35 7.82
Table II. Note that dynamic simulation is essential in the fea- 13 Microgrid 1 Z2, Z49, Z92, Z93 10.35 6.52
sibility evaluation of load groups. For example, from Fig. 1, it 14 Microgrid 3 Z93 2 10
can be seen that microgrid 4 is close to critical load CL5. It 15 Microgrid 3 Z49, Z93 5.2 7.98
16 Microgrid 3 Z2, Z93 5.3 7.72
appears to be a good idea to use microgrid 4 to restore critical
load CL5 through path “M4-Z160-Z132.” Indeed, by power
flow calculations, one finds that the path does satisfy all oper-
ational constraints. However, it is not listed as a feasible res-
toration path in Table II. This is because the amount of load on
zone Z160 is large and the generator capacity of microgrid 4 is
relatively small, which causes instability if an attempt is made
to pick up zone Z160 by microgrid 4.
Step 3: formulate and solve maximum coverage problem.
The critical load restoration problem is formulated as a maxi-
mum coverage problem and solved using the MATLAB MILP
Solver intlinprog. Load groups 12 and 14 are selected. Four (a)
out of five critical loads are restored. Specifically, zones Z2,
Z49, and Z92 are restored by microgrid 1 for a time period of
7.82 hours, zone Z93 is restored by microgrid 3 for a time
period of 10 hours, while zone Z132 remains interrupted. The
cumulative service time of microgrids to external loads
weighted by their priority is 85.32 hours.
Step 4: Determine restorative actions. After disconnecting
load zones that are not on the restoration paths, critical load
zones Z2, Z49, and Z92 are restored by microgrid 1 in five
actions, while Z93 is restored by microgrid 3 in one action. The (b)
time interval between two consecutive actions is one minute.
Fig. 3. Frequency variations of (a) microgrid 1 and (b) microgrid 3.
The frequency variations of the two microgrids are shown in
Fig. 3.
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
9
C. Discussions
1) Time Associated with Fault Management Activities Note that microgrid 1 restores the corresponding load zones
Assume that all switches in the test system are manual and by five switching operations. The time interval between two
there are 𝑁fc = 10 field crews. Suppose that the mean time to consecutive switching operations should be long enough to
operate a manual switch and a RCS are 𝑡swi m
= 30 minutes and allow the dynamics induced by an action to damp out before the
r
𝑡swi = 20 seconds, respectively. The implementation time (in next action is performed. It depends on the amount of load to be
the sense of average) for fault isolation, restoration path isola- picked up in each action, as well as the capacity of generators
tion, and service restoration can be estimated using (14)-(16) and controller settings. In the above case, an interval of one
proposed in Section IV-F. The results are as follows. minute is used, i.e., 𝑡𝑖𝑛𝑡 = 1 minute , which is determined
i) Fault isolation: In the above scenario, there are seven empirically. When applying the proposed method to other
faults. Fourteen switches should be opened to isolate the distribution systems, the proper time interval should be deter-
faulted zones, which takes 1 hour. mined case by case.
ii) Restoration path isolation: The selected restoration
paths are indicated by green color in Fig. 1. Eight 2) Computational Burden
switches should be opened for load group 12, including The proposed algorithm is implemented in MATLAB and
Z9-Z10, Z45-Z63, Z42-Z54, Z49-Z50, Z89-Z90, GridLAB-D on a PC with an Intel(R) Core(TM) i7-3770 CPU
Z83-Z90, Z90-Z91, and Z90-92, while one switch, i.e., and 12 GB RAM. The total running time for this case is 296.14
Z93-Z106, for load group 14. Note that some zones not s. Specifically, gathering case information takes 20.79 s, con-
on the restoration paths are not disconnected, e.g., zone structing restoration trees 106.52 s, forming load groups 123.95
Z38, because these zones serve no load. Assuming that s, solving the maximum coverage problem 0.27 s, and deter-
each switch is operated by a field crew, the process takes mining restorative actions 44.61 s. It can be seen that most of
30 minutes. the computation time is spent on constructing restoration trees
iii) Service restoration: By closing switch M3-Z93, zone and forming load groups. This is because dynamic simulation is
Z93 (with critical load CL4) is restored by microgrid 3, used to evaluate the feasibility of restoration paths and load
which takes 30 minutes. Microgrid 1 will pick up the groups. In this case, GridLAB-D dynamic simulation is per-
corresponding load zones by closing switches M1-Z39, formed 35 times with an execution time of 253.3 s, 85.5% of
T2, T1, T3, and Z90-92 in sequence. Each switching the total computation time. Note that, for the feasibility evalu-
operation takes 30 minutes. ation of a restoration path or load group, dynamic simulation is
The above results are summarized in the second row of Table performed on the corresponding portion of the distribution
IV. system but not the entire system, which significantly reduces
According to the authors’ prior research [16], upgrading a the simulation time.
small portion of manual switches to RCSs can significantly The proposed method is intended for online use. When a
reduce the implementation time of restoration plans. Suppose major disaster strikes a distribution system, the proposed
that the four microgrid switches, seven tie switches, and ten method will be used to determine the service restoration strat-
sectionalizing switches adjacent to critical load zones are up- egy after faults are located. To avoid unacceptably long com-
graded to RCSs. Since the switches adjacent to faulted zones putational time, especially for large distribution systems with
are not upgraded, the time for fault isolation does not change. multiple microgrids and critical loads, parallel computing can
The restoration path isolation and service restoration processes be used to accelerate the computation, based on the fact that
become more efficient due to RCSs. For example, zone Z93 restoration paths and load groups associated with different
(with CL4) can be isolated from the rest of the distribution microgrids are independent and can be evaluated separately.
network by opening a RCS, Z93-Z106, and restored by mi-
crogrid 3 by closing another RCS, M3-Z93. Each switching VI. APPLICATION
operation is assumed to take 20 seconds. Similarly, the time The proposed method is applied to the Avista distribution
elements associated with microgrid 1 and critical loads CL1, system that serves Pullman, including Washington State Uni-
CL2, and CL3 can be estimated. The results are given in the versity [25]. There are two critical loads on the distribution
third row of Table IV. feeders, i.e., the Pullman Regional Hospital and Pullman City
Hall (acting as a local emergency response center). Three
TABLE IV
generators, one 1.75 MW diesel generator and two 1.1 MW
IMPLEMENTATION TIME
Fault Restoration Service
natural gas generators, are available at the WSU power plant
Activity providing backup power for the campus. These generators and
Isolation Path Isolation Restoration
CL1: 30 minutes the control capability as a microgrid provide potential sources
Microgrid 1:
Time CL2: 1 hour for service restoration when power from Avista is unavailable.
30 minutes
without 1 hour CL3: 2.5 hours By applying the proposed method, the restoration paths for
RCSs Microgrid 3: critical loads are obtained, as shown in Fig. 4. The City Hall
CL4: 30 minutes
30 minutes and Hospital are restored through a restoration path with one
CL1: 20 seconds transformer and nine zones. Without considering dynamic
Microgrid 1:
Time CL2: 80 seconds
30 minutes constraints, critical loads, on and off campus, can be restored at
with 1 hour CL3: 260 seconds
RCSs Microgrid 3:
the same time, which can be validated by power flow calcula-
CL4: 20 seconds tions. However, the results of dynamic simulation indicate that
20 seconds
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
10
the system will become unstable. Another intuitive choice is to them in order to maintain the function of the hospital. Further
restore critical loads on campus first (with one action) and then studies should consider the interdependency of critical loads.
energize the City Hall and Hospital by closing the four tie
switches on the restoration path. The dynamic simulation re-
sults are shown in Fig. 5. A significant fluctuation in system
frequency and generator voltage is observed. The minimum
transient frequency is 47.41 Hz, which falls outside the ac-
ceptable range defined by constraint (4).
Proper switching actions are then determined by the method
proposed in Section IV-E. The restoration plan is implemented
in seven steps. The time interval between two restorative ac-
tions is one minute. In steps 1-3, critical loads within WSU are
restored. Steps 4-7 restore the loads on the restoration path. The
City Hall and Hospital are restored in step 5 and 7, respectively.
The dynamics of system frequency and generator voltages are
shown in Fig. 6. Note that a Woodward diesel governor model Fig. 4. Critical load restoration strategy for Pullman-WSU system.
with a droop speed control (DEGOV1) is applied to allow
proper load sharing among the three generators and the sec-
ondary frequency control is not considered. Therefore, the
steady-state frequency is a bit lower than 60 Hz but acceptable.
Natural gas and diesel are fuels for WSU generators. Natural
gas is served to WSU through a pipeline from British Columbia,
Canada. Another route coming out of Albert, Canada, and
down into Colorado provides back-up service. As long as one
of the two paralleling pipelines remains working, one can as-
sume that an infinite amount of natural gas is available for
(a)
WSU generators. Diesel is delivered to WSU by trucks and
stored in a 250,000-gallon fuel tank. WSU receives 10,000
gallons of diesel per delivery and 8 deliveries per year. For the
diesel generator on WSU campus, generating 1-kWh electric
energy consumes about 0.086 gallons of diesel. Therefore, after
a major disaster, if the natural gas pipeline is not damaged and
the diesel tank is not empty, the WSU generators can serve
critical loads on and off campus. If the two pipelines are
damaged and the roads entering Pullman are blocked, one can
only rely on the diesel generator. In this case, the diesel gener- (b)
ator will serve only the critical loads on campus and the service Fig. 5. Curves of (a) system frequency and (b) generator voltages. Critical loads
on campus are restored in one step.
time depends on the amount of diesel left in the tank. Note that
the WSU steam plant (one of the critical load on campus, which
is used for heating in winter) also consumes diesel. When the
steam plant and diesel generator are both operated at full ca-
pacity, a full tank of diesel can supply them for about 5-7 days.
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
11
In this paper, DGs are modeled as synchronous machines. [4] C.-C. Liu, S.-J. Lee, and S. S. Venkata, "An expert system operational aid
for restoration and loss reduction of distribution systems," IEEE Trans.
Different types of DGs should be considered in the future work.
Power Syst., vol. 3, no. 2, pp. 619-626, May 1988.
An important feature is whether a unit is controllable or [5] I.-H. Lim, T. S. Sidhu, M.-S. Choi, S.-J. Lee, S. Hong, S.-I. Lim, and
non-controllable. Other features that affect service restoration S.-W. Lee, "Design and implementation of multiagent-based distributed
include intermittency, interface to the grid, and dynamic char- restoration system in DAS," IEEE Trans. Power Del., vol. 28, no. 2, pp.
585-593, Apr. 2013.
acteristics. In addition, distribution automation also plays an
[6] W.-H. Chen, "Quantitative decision-making model for distribution system
important role. Remote monitoring and control of DGs can restoration," IEEE Trans. Power Syst., vol. 25, no. 1, pp. 313-321, Feb.
facilitate the decision-making process and implementation of 2010.
restoration plans. [7] R. E. Perez-Guerrero and G. T. Heydt, "Distribution system restoration
via subgradient-based Lagrangian relaxation," IEEE Trans. Power Syst.,
vol. 23, no. 3, pp. 1162-1169, Aug. 2008.
VIII. ACKNOWLEDGEMENT [8] S. Dimitrijevic and N. Rajakovic, "Service restoration of distribution
networks considering switching operation costs and actual status of the
The authors would like to thank the WSU Facilities and
switching equipment," IEEE Trans. Smart Grid, vol. 6, no. 3, pp.
Avista Utility Company for their support in this research. 1227-1232, May 2015.
[9] Y. Kumar, B. Das, and J. Sharma, "Multiobjective, multiconstraint
APPENDIX restoration of electric power distribution system with priority customers,"
IEEE Trans. Power Del., vol. 23, no. 1. Jan. 2008.
A. Parameters of generator [27] [10] M.-S. Tsai, "Development of an object-oriented service restoration expert
system with load variations," IEEE Trans. Power Syst., vol. 23, no. 1, pp.
𝐻 = 0.7 s, 𝐷 = 0.0 p.u., number of poles = 2, 𝑟𝑎 = 0.00625 p.u., 𝑥𝑑 =
219-225, Feb. 2008.
2.06 p.u., 𝑥𝑞 = 2.5 p.u., 𝑥𝑑′ = 0.398 p.u., 𝑥𝑞′ = 0.3 p.u., 𝑥𝑑′′ = 0.254 p.u., [11] T. T. H. Pham, Y. Besanger, and N. Hadjsaid, "New challenges in power
𝑥𝑞′′ = 0.254 p.u., 𝑥𝑙 = 0.1 p.u., 𝑇𝑑′ = 0.31737 s, 𝑇𝑑0
′
= 4.45075 s, 𝑇𝑞0 ′
= system restoration with large scale of dispersed generation insertion,"
′′ ′′
3.0 s, 𝑇𝑑0 = 0.066 s, 𝑇𝑞0 = 0.075 s, 𝑇𝑎 = 0.03202 s, 𝑟2 = 0.0072 p.u., IEEE Trans. Power Syst., vol. 24, no. 1, pp. 398-405, Feb. 2009.
𝑥2 = 0.254 p.u., 𝑟0 = 0.005 p.u., 𝑥0 = 0.05 p.u. [12] A. Sharma, D. Srinivasan, and A. Trivedi, "A decentralized multiagent
system approach for service restoration using DG islanding," IEEE Trans.
B. Diagram and parameters of governor (DEGOV/DEGOV1) Smart Grid, vol. 6, no. 6, pp. 2784-2793, Nov. 2015.
[13] C. L. Moreira, F. O. Resende, and J. A. Pecas Lopes, "Using low voltage
microgrids for service restoration," IEEE Trans. Power Syst., vol. 22, no.
1, pp. 395-403, Feb. 2007.
[14] I.-K. Song, W.-W. Jung, J.-Y. Kim, S.-Y. Yun, J.-H. Choi, and S.-J. Ahn,
"Operation schemes of smart distribution networks with distributed
energy resources for loss reduction and service restoration," IEEE Trans.
Smart Grid, vol. 4, no. 1, pp. 367-374, Mar. 2013.
[15] J. Li, X.-Y. Ma, C.-C. Liu, and K. P. Schneider, "Distribution system
restoration with microgrids using spanning tree search," IEEE Trans.
Power Syst., vol. 29, no. 6, pp. 3021–3029, Nov. 2014.
[16] Y. Xu, C.-C. Liu, K. P. Schneider, and D. T. Ton, "Placement of
The model DEGOV does not include the droop speed control. remote-controlled switches to enhance distribution system restoration
𝐾 = 1.2 p.u., 𝑇1 = 0.2 s, 𝑇2 = 0.3 s, 𝑇3 = 0.5 s, 𝑇4 = 1.0 s, 𝑇5 = capability," IEEE Trans. Power Syst., vol. 31, no. 2, pp. 1139-1150, Mar.
0.1 s, 𝑇6 = 0.2 s, 𝑇max = 1.0 p.u., 𝑇min = 0.0 p.u., 𝑅 = 1 % 2016.
(DEGOV1 only), 𝑇𝐷 = 0.01 s [17] Y. Xu, C.-C. Liu, K. P. Schneider, and D. T. Ton, "Toward a resilient
distribution system," in Proc. IEEE PES General Meeting, Denver, CO,
C. Diagram and parameters of exciter (SEXS) 2015, pp. 1-5.
[18] P. A. N. Garcia, J. L. R. Pereira, S. Carneiro, V. M. da Costa, and N.
Martins, "Three-phase power flow calculations using the current injection
method," IEEE Trans. Power Syst., vol. 15, no. 2, pp. 508-514, May 2000.
[19] T. H. Cormen, C. E. Leiserson, R. L. Rivest, and C. Stein, "Single-source
shortest paths," in Introduction to Algorithm, 3rd ed. Cambridge, MA: The
MIT Press, 2009, pp. 643-683.
[20] U.S. Department of Energy at Pacific Northwest National Laboratory,
GridLAB-D, Power Distribution Simulation Software, 2015 [Online].
𝑇𝐵 = 2.0 s, 𝑇𝐶 = 10 s, 𝐾𝐴 = 50 p.u., 𝑇𝐴 = 0.01 s, 𝐸max = 3.0 p.u., Available: http://www.gridlabd.org/
[21] The MathWorks, Inc., MATLAB Software, 2015 [Online]. Available:
𝐸min = −3.0 p.u.
http://www.mathworks.com/products/matlab/
D. Parameters of transformer [22] Y. Jiang, C.-C. Liu, M. Diedesch, E. Lee, and A. K. Srivastava, "Outage
management of distribution systems incorporating information from
𝑆𝑏𝑎𝑠𝑒 = 15 MVA, 𝑉1 /𝑉2 = 12.47/4.16 kV, 𝑟𝑡 = 0.007636 p.u., smart meters," IEEE Trans. Power Syst., DOI:
𝑥𝑡 = 0.053457 p.u. 10.1109/TPWRS.2015.2503341.
[23] M. A. Elizondo, F. K. Tuffner, and K. P. Schneider, "Three-phase
unbalanced transient dynamics and powerflow for modeling distribution
REFERENCES
systems with synchronous machines," IEEE Trans. Power Syst., vol. 31,
[1] U.S. Department of Energy and National Energy Technology Laboratory, no. 1, pp. 105-115, Jan. 2016.
Operates Resiliently Against Attack and Natural Disaster [Online]. [24] K. P. Schneider, Y. Chen, D. Engle, and D. Chassin, "A taxonomy of
Available: http://www.smartgridinformation.info/pdf/1438_doc_1.pdf North American radial distribution feeders," in Proc. IEEE PES General
[2] Office of the Press Secretary of the White House, Presidential Policy Meeting, Calgary, AB, 2009, pp. 1-6.
Directive – Critical Infrastructure Security and Resilience [Online]. [25] K. P. Schneider, F. K. Tuffner, M. A. Elizondo, C. C. Liu, Y. Xu, and D.
Available:http://www.whitehouse.gov/the-press-office/2013/02/12/presi T. Ton, "Evaluating the feasibility to use microgrids as a resiliency
dential-policy-directive-critical-infrastructure-security-and-resil resource," IEEE Trans. Smart Grid, DOI: 10.1109/TSG.2015.2494867.
[3] D. T. Ton and W-T. P. Wang, "A more resilient grid," IEEE Power [26] J. R. Marti, J. A. Hollman, C. Ventura, and J. Jatskevich, “Dynamic
Energy Mag., vol. 13, no. 3, pp. 26-34, May/Jun. 2015. recovery of critical infrastructures: real-time temporal coordination,” Int.
J. Critical Infrastructures, vol. 4, nos. ½, pp. 17-31, 2008.
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2016.2591531, IEEE
Transactions on Smart Grid
12
Yin Xu (S’12–M’14) received his B.E. and Ph.D. degrees in electrical engi-
neering from Tsinghua University, Beijing, China, in 2008 and 2013, respec-
tively.
He is currently an Assistant Research Professor at the School of Electrical
Engineering and Computer Science, Washington State University, Pullman,
WA, USA. His research interests include distribution system restoration,
microgrid, power system resilience, power system electromagnetic transients
simulation, and high-performance computing in power systems.
Dr. Xu is currently serving as Secretary of the Distribution Test Feeder
Working Group under the IEEE PES Distribution System Analysis Subcom-
mittee.
Dan T. Ton received his B.S. degree is in electrical engineering and M.S.
degree in business management from the University of Maryland, Baltimore,
MD, USA.
He is a Program Manager of Smart Grid R&D within the U.S. Department of
Energy (DOE) Office of Electricity Delivery and Energy Reliability (OE). He
is responsible for developing and implementing a multi-year R&D program
plan for next-generation smart grid technologies to transform the electric grid in
the United States through public/private partnerships. Previously, he managed
the Renewable Systems Integration program within the DOE Solar Energy
Technologies Program.
1949-3053 (c) 2016 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.