Bill of Quantities

FOR

CONSTRUCTION OF

WATER SUPPLY SCHEME

For

KARUWALAGASWEWA PRADESHIYA SABHA

Package No. NWP - AF - WS -CKD- 15


CONSULTANT
PURANEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT (LGESP) - Resources Development
(ADDITIONAL FINANCING) Consultants (Pvt) Ltd.
Sanken
CONSTRUCTION
(Pvt) Ltd. CONSRTUCTION OF WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA CLIENT
Sky's the limit SABHA PURANAGUMA
CONTRACT NO: NWP-AF-WS-CKD-15

Interim Payment Application No. 18 Date of Service


30th April 2022

MONTHLY PAYMENT - IPC - 18


Contract Information SLR
01 Gross Tender Value (Excluding Vat) 300,716,571.32
02 Mobilization Advance (Excluding Vat) 53,545,263.29
03 Balance Advance to be Recovered 53,545,263.29
04 Limit of retention 15,035,828.57
05 Balance Retention to be Released Err:509
06 Limit of Maximum Discount -
07 Date of Project Commencement 06th January, 2020
08 Original date of project completion 29th March, 2021
TOTAL VALUATION TO
NO DESCRIPTION DATE
SLR
1.1 VALUE OF WORKS EXECUTED ( Excluding Provisional Sum & Extra Works ) Err:509
1.2 PROVISIONAL SUM ITEMS(Excluding Price Escalation) -
1.3 EXTRA WORKS 901,139.16
1.4 VARIATION ORDERS 12,064,888.63
1.5 DAY WORKS 337,129.60
1.6 PRICE REVISION (ESCALATION) -
1.7 MATERIAL PURCHASED LOCALLY -
1 SUB TOTAL (1.1+1.2+1.3+1.4+1.5+1.6+1.7) Err:509
ADDITIONS
2.1 Mobilization Advance (Excluding Vat)
2.2 Material at site 49,466,335.85
2.3 Release of Retention -
2.4 Other Payments -
2 SUB TOTAL FOR ADDITIONS (2.1+2.2+2.3+2.4) 49,466,335.85
DEDUCTIONS
3.1 Retention ( 10 % Gross Amount Less P/Sums) Err:509
3.2 Recovery of Advance
3.3 Other Deductions -
3 SUB TOTAL FOR DEDUCTIONS (3.1+3.2+3.3) Err:509
4 NET CUMULATIVE AMOUNT DUE (1+2-3) Err:509
5 DEDUCT ; PREVIOUS CERTIFIED AMOUNT 136,360,784.48
6 NET AMOUNT (4-5) Err:509
7 VAT 8% Err:509
8 Bank Commitment Fee (Net Amount x 1%)
9 TOTAL STATEMENT AMOUNT (6+7+8) Err:509

Prepared Checked & Recommende Checked & Certified as per the


as per the contract contract
………………………….. ………………………….. …………………………
Contractor (PM) Consultant QS/ Engineer Engineer (SPCU)
PURANEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT (LGESP) - (ADDITIONAL FINANCING)

SANKEN CONSTRUCTION (PVT) LTD.


CONSRTUCTION OF WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA PROGRESS CLAIM NO: 18
CONTRACT NO: NWP-AF-WS-CKD-15
DATE OF SERVICE : 30th APRIL 2022
GRAND SUMMARY
BOQ BILL PREVIOUS WORK CURRENT WORK CUMULATIVE
BILL DESCRIPTION CONTRACT AMOUNT(Rs)
NO DONE DONE WORK DONE
1 Preliminaries 5,012,400.00 2,076,793.93 71,200.00 2,147,993.93
2 Renovation of Intake Structure. 846,775.00 89,966.05 89,966.05
3 Construction of Aerator 1,047,407.65 411,834.23 157,942.00 569,776.23
4 Construction of Chemical Adding Chamber,Chemical House & Chlorine Bath 3,281,795.10 2,145,878.92 227,073.53 2,372,952.45
5 Construction of Flocculator & Sedimentation Tank 6,037,914.00 2,399,944.80 383,444.87 2,783,389.67
6 Construction of Rapid Sand Filter 3,119,105.00 837,100.16 - 837,100.16
7 Construction of 450m3 Treated Water Sump 15,005,270.50 11,369,543.15 11,369,543.15
8 Construction of High Lift Pump House. 3,733,684.00 1,933,012.51 1,933,012.51
9 Construction of 13m high 175m3 Capacity Overhead Tank. 11,708,197.00 6,343,579.97 93,456.25 6,437,036.22
10 Renovation of Existing Water Tower 2,324,449.00 758,370.09 758,370.09
11 Supply & Laying Of uPVC and DI Pipes,Fittings Specials and Valves 183,001,639.00 53,055,534.54 Err:509 Err:509
12 Supply & Installation of Mechanical & Electrical Equipment 33,773,873.00 - - -
13 Miscellaneous Work. 3,646,125.00 983,265.86 983,265.86
Sub Total 01 272,538,634.25 82,404,824.22 Err:509 Err:509
BOQ Excess Qty 2,282,547.15 198,267.81 2,480,814.96
Deduct Provisional Sums Amount (6,340,500.00) - -
Sub Total 02 266,198,134.25 84,687,371.37 Err:509 Err:509
Deduct Discount ………..% (If Any) - -
Sub Total 03 266,198,134.25 84,687,371.37 Err:509 Err:509
Add Contingencies 10 % 26,619,813.43
Add Variation Oder No.03 (NEELAMALAPURA) 34,587,899.00 9,506,293.20 2,558,595.43 12,064,888.63
Add EXTRA WORK 03.01 144,524.38 144,524.38
Add EXTRA WORK 03.02 141,350.50 141,350.50
Add EXTRA WORK 04 33,803.50 33,803.50
Add EXTRA WORK 06 581,460.78 581,460.78
14 Allow for Day Work (Labour, Material & Plant) 1,228,767.63 309,580.10 27,549.50 337,129.60
Sub Total 04 327,405,846.68 94,647,769.05 Err:509 Err:509
Add Provisional Sums Amount 6,340,500.00 - -
Grand Total 333,746,346.68 94,647,769.05 Err:509 Err:509

Prepared Checked & Recommended as per the contract Checked & Recommended as per the contract Checked & Certified as per the contract
…………………………..,……….. …………….……………………………………………… ………………………………………………………….. ………………...…………………………………………
Contractor Consultant QS/ Engineer Assistant QS (SPCU) Senior Engineer
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

BILL NO 03 ; CONSTRUCTION Of AERATOR

CLASS E - EARTHWORKS
Rate shall include for compacting dewatering,
upholding sides of excavation where necessary

Excavation for foundation base, Trenches and the like


commencing from the existing ground level, in any material
other than rock including compacting bottom of excavation

2.1 Depth not exceeding 1.0 m m3 1,066.00 0.76 810.16 0.76 810.16

Bituminous Painting
Apply two coats of Bituminous Paint on the four sides of
27 the base , Upper surface of base and for sides of column m2 2,100.00 6.89 14,469.00 6.89 14,469.00
up to floor level.

TOTAL CARRIED FORWARD 15,279.16 - 15,279.16

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 15,279.16 - 15,279.16
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING
CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
2.00 CONSTRUCTION OF CHEMICAL HOUSE

CLASS E - EARTHWORKS
Rate to include for removing surplus excavated earth and
deposited at the direction of Engineer with in the site
boundaries at suitable places not disturbing to surface
1.1 Depth not exceeding
drainage and cost of1.0 m
dewatering, Planking & Strutting, if m3 1,065.00 15.38 16,379.70 15.38 16,379.70
1.2 necessary.
Depth exceeding 1.0 m but not exceeding 2.0 m m3 1,145.00 17.38 19,900.10 17.38 19,900.10

CONCRETE WORK

Concrete in Grade 15
2.5 In 50 mm thick blinding concrete for foundations m2 737.00 0.56 412.72 0.56 412.72

Concrete in Grade 20
2.8 In 75 mm thick mass concrete base for 1,000 liters tank in
ground floor m2 1,385.00 0.97 1,343.45 0.97 1,343.45
- - - -
Reinforced Concrete in Grade 20 (Formwork measured
separately) - - - -
2.9 In 225x150 mm Plinth Beam m3 18,991.00 0.53 10,065.23 0.53 10,065.23
2.11 In Lintols m3 18,991.00 1.61 30,575.51 1.61 30,575.51
- - - -
FORMWORK - - - -
Rate to include for Splayed Edges, Battens, Strutting,
Bolting, Wedging, Easing, Striking and Removal . -
- - -
2.13 In Columns m2 1,295.00 0.47 608.65 0.47 608.65
2.14 In Lintols m2 1,295.00 13.89 17,987.55 13.89 17,987.55
TOTAL CARRIED FORWARD 76,272.27 36,279.80 112,552.07

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

the Contract the Contract

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 76,272.27 36,279.80 112,552.07

REINFORCEMENTS
Rate to include for supply and delivery to the yard, storing,
cutting and bending, transport to the site, cleaning as
specified and to the approval of the Engineer, placing in
position and tied with GI binding wire, complete as
depicted in drawing

2.15 Tor Steel kg 169.00 117.51 19,859.19 117.51 19,859.19

MASONARY WORKS

2.18 Random Rubble Masonry in 1:5 cement sand mortar in m3 13,182.00 0.97 12,786.54 0.97 12,786.54
foundation

SURFACE FINISHES

Internal Plastering 16 mm thick in 1:1:5 cement lime sand


2.24 to Internal walls, columns, beams finished smooth with m2 752.00 15.99 12,024.48 15.99 12,024.48
lime putty. Rate to include for door and window reveals

3.00 CONSTRUCTION OF CHLORINE BATH

Concrete Grade 25
Reinforced Concrete
3.5 In 200 mm thick Base & walls of pond m3 17,416.00 0.30 5,224.80 0.30 5,224.80
Miscellaneous
Cement, Sand 1:3 plastering finished semi rough of
3.12 concrete work m3 705.00 2.62 1,847.10 2.62 1,847.10
TOTAL CARRIED FORWARD 128,014.38 36,279.80 164,294.18
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 128,014.38 36,279.80 164,294.18
REINFORCEMENTS
3.9 10 mm dia. kg 169.00 31.61 5,342.09 31.61 5,342.09

BILL NO.05: CONSTRUCTION OF FLOCCULATOR &


SEDIMENTATION TANK
CLASS E - EXCAVATION & EARTHWORKS
2.2 Depth exceeding 1.0 m but not exceeding 2.0 m m3 1,145.00 0.22 251.90 0.22 251.90
2.4 Depth exceeding 3.0 m but not exceeding 5.0 m m 3 1,260.00 12.40 15,624.00 12.40 15,624.00

4 mm dia. GI wire in tank walls & Ferro cement walls tied


18 with GI binding wire (40 mm spacing shall be kept as
shown in the drawing) Kg 169.00 8.54 1,443.00 8.54 1,443.00
Supplying & fixing of SWG 18 No. 04 GI wire mesh, cut to
19 length, bent to shape, laid in position in Ferro cement walls
& tank walls (Rate to include for lap length) m2 788.00 91.55 72,143.65 91.55 72,143.65

Reinforced Concrete - Grade 25


12 In Base Slab for Flocculator m3 18,466.00 0.40 7,386.40 0.40 7,386.40

BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER

Earth Works
2.3 Depth exceeding 2.0 m but not exceeding 3.0 m m3 1,145.00 4.60 5,267.00 4.60 5,267.00
-
Supply & fixing of SWG 18 No. 04 GI wire mesh, Supplied,
cut to length, bent to shape, laid in position in vertical
Ferro cement tank walls and at places where it is
11 connecting the base slab and walls (Rate to include for lap m2 788.00 28.80 22,690.46 28.80 22,690.46
TOTAL CARRIED FORWARD
length) 184,576.23 109,866.45 294,442.68
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 184,576.23 109,866.45 294,442.68

BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY


GROUND RESERVOIR AT WATER TRATMENT PLANT AT
KARUWALAGASWEWA

Excavation & Earth Work

2.4 Depth exceeding 3.0 m but not exceeding 4.0 m m3 1,260.00 14.12 17,791.20 14.12 17,791.20

Earth Filling
5 Back filling around the structure with selected excavated
material (other than top soil or rock) to 95% compaction
as directed by the Engineer (Compaction reports should be
provided)
m3 830.00 53.15 44,114.50 53.15 44,114.50
- - - -
In Upstanding Projections on cover slab & manhole
openings with thickness not exceeding 100 mm (Kerb
13 Wall) m3 23,993.00 0.69 16,555.17 0.69 16,555.17

Formwork
26 For sides of slab projections for manhole opening m2 1,295.00 16.38 21,212.10 16.38 21,212.10

40 10 mm thick Bitumen layer between roof slab and wall and


blinded with sand m2 3,150.00 0.66 2,079.00 0.66 2,079.00
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

41 Applying non toxic water proofing (Approved by the


Engineer) on internal wall including bottom of ground
reservoir
m2 1,575.00 140.14 220,720.50 140.14 220,720.50

TOTAL CARRIED FORWARD 507,048.70 109,866.45 616,915.15

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 507,048.70 109,866.45 616,915.15

BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP


HOUSE

4 Excavation for rubble strip foundation in any material


other than top soil, rock or artificial hard material with
maximum depth not exceeding 1.5m from existing ground
level.
m3 1,065.00 1.04 1,111.59 1.04 1,111.59

CLASS F - IN SITU CONCRETE

10 Grade 25 Reinforced Concrete m3 19,440.00 6.25 121,500.00 6.25 121,500.00


- - - -
CLASS G - CONCRETE ANCILLARIES - - - -
Formwork - - - -
(Plane Vertical) - - - -
11 Masonry Work m2 1,295.00 62.25 80,613.75 62.25 80,613.75
12 To sides of column shafts, with width exceeding 0.2 m but
not exceeding 0.4 m. 19,748.75
m2 1,295.00 15.25 15.25 19,748.75
- - - -
Reinforcement - - - -
Mild steel bar reinforcement cut to length, bent to - - - -
16 shape, placed in position and tied with GI wire
6 mm dia kg 169.00 187.85 31,746.65 187.85 31,746.65
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

- - - -
Tor steel bar reinforcement cut to length, bent to - - - -
17 shape,
12 mm placed
dia. in position and tied with GI wire kg 169.00 196.40 33,191.60 196.40 33,191.60
18 16 mm dia. kg 169.00 248.66 42,023.54 248.66 42,023.54

TOTAL CARRIED FORWARD 836,984.58 109,866.45 946,851.03

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 836,984.58 109,866.45 946,851.03

CLASS U – BRICK WORK, BLOCK WORK AND MASONRY

Brick Work
19 225 mm thick vertical straight, common brick walls in 1:6
cement and sand mortar m2 3,922.00 37.65 147,663.30 37.65 147,663.30
- - - -
Rubble work - - - -
21 450 mm thick vertical straight, rubble masonry walls of
foundation, in cement and sand 1:5 mortar m2 5,932.00 19.57 116,089.24 19.57 116,089.24
- - - -
Wall Finishes - - - -
34 16 mm thick internal wall plastering in 1:1:5 cement, lime
and sand mortar finished smooth with lime putty on brick
walls and concrete columns. Rate to include for door and
window reveals
m2 752.00 55.48 41,720.96 55.48 41,720.96
35 20 mm thick external wall plastering in 1:1:5 cement, lime
and sand mortar finished semi-rough on brick walls and
concrete columns. Rate to include for door and window
reveals
m2 731.00 48.00 35,088.00 48.00 35,088.00
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

- -
-

TOTAL CARRIED FORWARD 1,177,546.08 109,866.45 1,287,412.53

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 1,177,546.08 109,866.45 1,287,412.53
Roof Work and Ceiling
36 Supply, Fabricate & fixing of Zinc Aluminium coated
colour bonded profile sheet roof on Category "A " timber
frame including 50 X 175 mm Ridge plate , 50 X100 mm
Rafters, 50 X 50 mm reepers, 75 X 100 mm Wall plate
etc. All timber works to be treated with two coats of good
quality wood preservative approved by the Engineer. Rate
to be include for Ridging with Zink Alumn Colour bonded
ridge caps.
m2 5,775.00 13.15 75,941.25 13.15 75,941.25
- - - - -
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3
CAPACITY OVERHEAD TANK - - - - -
- - - - -
Site Clearing and Anchoring - - - - -
1 General clearing of the site (premises of 175 m3 Water
Tower) including removal of hedges, bushes, etc.
m2 73.00 6.00 438.00 6.00 438.00
- - - - -
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

2 Excavation for base, trenches and the like, commencing


from existing ground level, in any material other than rock,
including compacting bottom of excavation
- - - - -
Rate to include for removing surplus excavated earth and
deposited at the direction of Engineer within the site
boundaries at suitable places not disturbing the surface
drainage; Rate to include cost of dewatering, Planking &
Strutting, if necessary. - - - - -
- - - - -
2.2 Depth exceeding 1.0 m but not exceeding 2.0 m m3 1,145.00 0.11 125.95 0.11 125.95

TOTAL CARRIED FORWARD 1,254,051.28 109,866.45 1,363,917.73

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 1,254,051.28 109,866.45 1,363,917.73

Excavation in Rock
Extra-over for above item no. 2 for excavation of soft rock,
3 (Provisional Quantity)(No blasting required) m3 4,725.00 101.67 480,390.75 101.67 480,390.75
Extra-over for above items no. 2 & 3 for excavation in hard
4 rock (Provisional Quantity)(Controlled blasting) m3 13,125.00 14.69 192,806.25 14.69 192,806.25
- - - -
Earth Filling - - - -

Back filling around the structure with selected excavated


material (other than top soil or rock) to 95% compaction
as directed by the Engineer (Compaction reports should be
6 provided) m3 830.00 18.06 14,989.80 18.06 14,989.80
- - - -
RCC Concrete - - - -
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

Providing and placing of G25 concrete in base at all levels


where specified, including Scaffolding, proper compaction,
curing, etc., but excluding form work & reinforcement as
10 per the direction of Engineer (Ready Mixed Concrete) m3 19,965.00 8.26 164,910.90 8.26 164,910.90

- - -
TOTAL CARRIED FORWARD 2,107,148.98 109,866.45 2,217,015.43

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 2,107,148.98 109,866.45 2,217,015.43

Form work - - -

Providing, fabrication and fixing to correct levels, line and


plumb, plain form work made up of 12 mm plywood for all
types of RCC works at all levels including necessary
strutting, scaffolding, access and working platforms,
15 bracings, leaving necessary openings, etc. m2 1,295.00 119.11 154,247.45 68.26 88,401.36 187.37 242,648.81

BILL NO. 10: RENOVATION OF EXISTING WATER


TOWER AT KARUWALAGASWEWA PS AREA (60m3) &
NEELAMALAPURA (30m3).
Pura Neguma - Local Government Enhancement Sector Project
Excess Quantity BOQ Summary

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

EXCESS
ITEM DESCRIPTION AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
UNIT RATE QTY AMOUNT QTY AMOUNT QTY AMOUNT

14 Applying two coats of Reflective type Paint of approved


colour to outer surface of the Tank, approved by the
Engineer. Rate to include cleaning the outer surface of the
tank & finish smooth.
a. Karuwalagaswewa PS m2 1,890.00 9.18 17,350.20 - 9.18 17,350.20

16 Applying two coats of Weather Shield Paint in approved


colour including one coat primer outside the tank support
structure (Columns, Beams & Tank Base)
b. Neelamalapura m2 612.00 6.21 3,800.52 - 6.21 3,800.52

Total Carried Over to Summary … 2,282,547.15 198,267.81 2,480,814.96

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . …………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
PURANEGUMA - LOCAL GOVERNMENT ENHANCEMENT SECTOR PROJECT
(LGESP) - (ADDITIONAL FINANCING)

SANKEN CONSTRUCTION (PVT) LTD.


CONSRTUCTION OF WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
CONTRACT NO: NWP-AF-WS-CKD-15 PROGRESS CLAIM NO: 02

DATE OF SERVICE : 30th SEPTEMBER 2020

Advance Recovery Summary

Advance Recovery = Current Work Done(Excluding PS & Contingencies) x Advance Payment Received
90% of BOQ

= Err:509 x 53,545,263.29
90% 300,716,571.32

= Err:509
270,644,914.19

= Err:509

Prepared Checked as per the contract


Checked & Recommended as per the
contract

……………………………. ………………………………………….. ………………………………………


Contractor Consultant TO/QS Consultant ARE/Engineer

Checked as per the Checked & Certified as per the contract


contract

……………………………….. ……………………………………………..
Assistant QS(SPCU) Senior Engineer/Compliance Officer SPCU
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 01 : PRELIMINARIES

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Contractual Requirements

For payment of actual charges incurred to obtain


and maintain Insurance Policies issued by an
Insurance organization in Sri Lanka acceptable to
1 the Employer conforming to the requirements Item Lump Sum 1,000,000.00 1.00 819,698.20 1.00 819,698.20
stipulated in the Conditions of Contract. The
Insurance Policies shall be valid up to the period
as stipulated in the Conditions of Contract.

Specified Requirements:
Provide original (01 set) "As Built Drawings" in
A1 papers and 03 sets of copies in A3 size paper
2 including 4 sets of electronic files (editable) in Item Lump Sum 20,000.00
CDs as specified in General Requirements

Engineer's Facilities - - - -
Provision for establishment, maintenance and
3 removal at completion of Engineers office as Months 15 53,793.33 806,900.00 15th Months 806,900.00 - - 806,900.00
specified in the Specifications 6.2a Para 8.
Provide for the sole use of the Engineer and his
4 staff, safety shoes, protective clothing, helmet Item Lump Sum 30,000.00 15th Months 25,846.20 15th Months 25,846.20
and equipment, etc.
Supply and erection
Temporary Works :of Project Name Boards (Size
not less than 2.4 m x 3.0 m) to be displayed at
sites and offices as directed by the Engineer.
5 Script shall be approved by the Engineer. Rate to nr 2 25,000.00 50,000.00 2.00 50,000.00 2.00 50,000.00
include for fixing of 2 posts (GI Pipes) at a height
of 2 m above ground level and both posts
TOTAL CARRIED
supported FORWARD
with concrete foundations. 1,906,900.00 1,652,444.40 50,000.00 1,702,444.40

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 01 : PRELIMINARIES

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)


Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 01 : PRELIMINARIES

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

BROUGHT FORWARD 1,906,900.00 1,652,444.40 50,000.00 1,702,444.40


Miscellaneous - -
Training of Operation & Maintenance staff and
6 Handing over the operation manuals and parts Item Lump Sum 5,000.00 - -
manual of all pumps & accessories
Other Provisional Sums - -
For payment of actual charges incurred for
Inspection, testing of materials and other
7 required laboratory tests as directed by the PS 250,000.00 - -
Engineer. (for Testing not covered by the BOQ
Item description.)

For payment of actual charges incurred for Soil


8 testing , Geotechnical investigation where PS 150,000.00 1.00 16,520.00 1.00 16,520.00
necessary as directed by the Engineer. (for
Testing not covered by the BOQ Item description.)

For payment of actual charges incurred for


9 Demolition and reinstatement of private PS 425,000.00 - 1.00 20,000.00 1.00 20,000.00
properties as directed by the Engineer.
For payment of actual charges incurred for
10 Payment to RDA/PRDA/PS/LA and other PS 2,000,000.00 1.00 384,017.37 1.00 384,017.37
authorities for Supervision.
For payment of actual charges incurred for
11 removing & relocating of existing electrical posts, PS 100,000.00
Telephone posts as per the specifications given
by relevant Government Authorities.
12 Percentage adjustment to Provisional Sums for Item Lump Sum 175,500.00 1.00 23,812.16 1.00 1,200.00 1.00 25,012.16
above items 7 to 11 (6%)
TOTAL CARRIED FORWARD 5,012,400.00 2,076,793.93 71,200.00 2,147,993.93

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
PRELIMINARIES
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
Description Unit Nos Qty up to Qty for This
No Length Breath Depth Previous Bill Quantity
Bill

Contractual Requirements

For payment of actual charges incurred to


obtain and maintain Insurance Policies issued
by an Insurance organization in Sri Lanka
1 acceptable to the Employer conforming to the
requirements stipulated in the Conditions of
Contract. The Insurance Policies shall be valid
up to the period as stipulated in the
Conditions of Contract. Item 1 819,698.20 819,698.20

Engineer's Facilities

Provision for establishment, maintenance and


3 removal at completion of Engineers office as
specified in the Specifications 6.2a Para 8.
months 6.00
months 3.00
months 1.00
months 1.00
months 1.00
months 1.00
months 2.00
15.00 - 15.00

Provide for the sole use of the Engineer and


4 his staff, safety shoes, protective clothing,
helmet and equipment, etc.
Item 21,230.80 70.8%
Item 1,153.85 3.85%
Item 1,153.85 3.85%
Item 1,153.85 3.85%
Item 1,153.85 3.85%
25,846.20 - 25,846.20
Temporary Works :
Supply and erection of Project Name Boards
(Size not less than 2.4 m x 3.0 m) to be
displayed at sites and offices as directed by the
5 Engineer. Script shall be approved by the
Engineer. Rate to include for fixing of 2 posts
(GI Pipes) at a height of 2 m above ground
level and both posts supported with concrete
foundations. nr 2.00 2.00
- 2.00 2.00

For payment of actual charges incurred for


Soil testing , Geotechnical investigation where
8 necessary as directed by the Engineer. (for
Testing not covered by the BOQ Item
description.)
Paid of Inspection Charges on Geological
Survev & Mines Bureau PS 5,000.00
Royalty on aggregate Charges on Geological
Survev & Mines Bureau PS 11,520.00
16,520.00 - 16,520.00

Prepared Checked as per the Contract Checked & Recommanded as per Checked & Certified as per the Contract
the Contract
Pura Neguma - Local Government Enhancement Sector Project
PRELIMINARIES
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
Description Unit Nos Qty up to Qty for This
No Length Breath Depth Previous Bill Quantity
Bill

…………………………… ………………………………………………… ……………………………………………………………………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

For payment of actual charges incurred for


9 Demolition and reinstatement of private
properties as directed by the Engineer. PS 20,000.00
- 20,000.00 20,000.00

For payment of actual charges incurred for


10 Payment to RDA/PRDA/PS/LA and other
authorities for Supervision. PS 264,017.37
PS 120,000.00
384,017.37 - 384,017.37
Other Provisional Sums
Percentage adjustment to Provisional Sums
12 for item 10 (6%) Lump
15,841.04
7,200.00
From Item No.09 (6%) 1,200.00
23,041.04 1,200.00 24,241.04

Prepared Checked & Certified as per the Contract Checked & Certified as
Checked & Certified as per the Contract
per the Contract
Pura Neguma - Local Government Enhancement Sector Project
PRELIMINARIES
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
Description Unit Nos Qty up to Qty for This
No Length Breath Depth Previous Bill Quantity
Bill

……………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Technical officer of Consultant/RDC Asst . QS RDC Eng. Water Supply (RDC)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 02 : RENOVATION WORK OF INTAKE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Note :

Quantities given in the Bill Of Quantities are


nominal, Bidder shall visit the site and take
necessary information before submitting the offer.

All payments will be based on actual site


measurements.

Any tax/duty levied on material shall be


incorporated in the rates submitted. Such
taxes/duties, other than VAT payable on this
contract, shall not be reimbursed separately by the
Chief Secretary, North Western Province.

The present system of pumping water to


Karuwalagaswewa shall not be disturbed during the
construction period and the method statement for
construction is to be approved by the Engineer.

Penstocks
Supplying & Installation of 300 mm dia. Penstock to
existing Brick wall. Rate to include for the cost of
1 preparing the wall for fixing the Penstock housing. nr 4 5,250.00 21,000.00 - -
According to the Section 06-Employer’s
Requirements -Specifications 6.2s

TOTAL CARRIED FORWARD 21,000.00 - - - - - -

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 02 : RENOVATION WORK OF INTAKE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 21,000.00 - - - - - -
Headstocks -
Supplying & fixing of Rising Spindle Style
Horizontal wheel operated Headstock. According to
2 the Section 06-Employer’s Requirements - nr 4 5,250.00 21,000.00 - -
Specifications 6.2s
Internal Plaster - - -

16 mm thick plastering to wall in cement and sand


3 m2 100.00 667.00 66,700.00 0.47 313.49 - 0.47 313.49
mortar 1:5 finished smooth with Wall Putty.

External Plaster - - -

4 16 mm thick plastering to wall in cement and sand m2 100.00 680.00 68,000.00 - -


mortar 1:5 finished semi-rough with wooden float.

For Payment of actual charges incurred for


5 Providing Foot Bridge access to the Grid Chamber PS 80,000.00 - -

Percentage adjustment to provisional Sum for ,


5.1 Item Lump Sum 20,000.00 - -
Item 5(…25%...)
TOTAL CARRIED FORWARD 276,700.00 313.49 - 313.49

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 02 : RENOVATION WORK OF INTAKE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 276,700.00 - 313.49 - - 313.49

900 mm wide Pavement without drain in 1:3:6 (40


mm) concrete, 75 mm thick with 700 gauge
polythene layer on earth surface after compaction
6 including expansion joint at every 3,000 mm m 15.00 3,853.00 57,795.00 6.80 26,200.40 - 6.80 26,200.40
interval laterally and along the plinth using 6 mm
thick regiform and finished smooth with 12 mm
thick rendering 1:3 cement and sand around the
Intake Pump House.

Floor rendering at the Intake Pump House by


applying 20 mm thick rendering in cement and
7 sand 1:3 finished smooth with neat cement float up m2 2.50 906.00 2,265.00 1.82 1,648.92 - 1.82 1,648.92
to the level equal to the existing floor. (Rate to
include any demolishing work of existing floor
rendering)

External Painting -

Prepare the surfaces and apply one coat of wall


8 primer and two coats of Weather shield Emulsion m2 35.00 613.00 21,455.00 34.69 21,264.97 - 34.69 21,264.97
Paint in external surfaces of Pump House.

Internal Painting -
Prepare the surfaces and apply one coat of wall
9 primer and two coats of emulsion paint in Pump m2 40.00 542.00 21,680.00 31.06 16,834.52 - 31.06 16,834.52
House Internal wall surfaces & soffit of roof slab.
TOTAL CARRIED FORWARD 379,895.00 66,262.30 - 66,262.30

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 02 : RENOVATION WORK OF INTAKE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 379,895.00 - 66,262.30 - 66,262.30


Water Proofing Painting - - -

Applying water proofing paint (Approved by the


10 Engineer) on top of the Roof slab of Pump House. m2 18.00 1,575.00 28,350.00 15.05 23,703.75 - 15.05 23,703.75

Replace the existing panelled Door (750 x2,100


mm) sash only with 28 mm thick (Jak, Satin,
Halmilla, Milla ) with Brass hinges 4 Nos 125x125
11 mm, best quality Union mortise lock, two coats of nr 1 61,950.00 61,950.00 - -
wood preservative, aluminium primer under coat
and two coats of enamel paint.

Supplying & Fabrication of Chequered plate/Steel


Flat Form in side of the Dry well as per the Detail
12 Drawing No. NWP/AF/WS/CKD-15 / KGW/ RWT - Item Lump Sum 180,180.00 - -
01 and the instructions given by the Engineer. Rate
to include to provide Hand Rails as per the Drawing.

Supplying & Fixing of PVC coated Net to existing


13 roof covering GI frame for Dry Well. Item Lump Sum 75,075.00 - -

14 Allow Provisional Sum for Payment of actual PS 105,500.00 - -


charges incurred for Electrical wiring System.
Percentage adjustment to Provisional Sum for, Item
14.1 Item Lump Sum 15,825.00 - -
14 (…15……%)
Total Carried Over to Summary … 846,775.00 89,966.05 - 89,966.05

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 02 : RENOVATION WORK OF INTAKE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BILL NO. 02 : RENOVATION WORK OF INTAKE.
1 Penstock
Supply Cost 272,600.00
According to CIF Value 237,823.00
NWSDB Circular
Custom Duty 17,837.00
Add 13.80% 255,660.00 35,281.08
New Supply Cost 307,881.08
Add CIF Value 237,823.00
20% 237,823.00 47,564.60
Total Supply Cost including O & P 355,445.68
Laying 17,700.00
Other cost (Masonry works) 7,500.00
25,200.00
Add Overhead & Profits 25,200.00
27% 25,200.00 6,804.00
Total Laying Cost including O & P 32,004.00
Rate Per 1nr 387,450.00

2 Headstock
Supply Cost 198,200.00
According to CIF Value 172,880.00
NWSDB Circular
Custom Duty 12,966.00
Add 13.80% 185,846.00 25,646.75
New Supply Cost 223,846.75
Add CIF Value 172,880.00
20% 172,880.00 34,576.00
Total Supply Cost including O & P 258,422.75
Laying 5,100.00
Other cost (Masonry works) 5,000.00
10,100.00
Add Overhead & Profits 10,100.00
27% 10,100.00 2,727.00
Total Laying Cost including O & P 12,827.00
Rate Per 1nr 271,250.00

3 Internal Plastering T2.1.1.1


Plastering 773.00
Add Overhead & Profits
27% 208.71
Total Cost 981.71
Rate Per m2 982.00

4 External Plastering T2.1.2.1


Plastering 669.00
Add Overhead & Profits
27% 180.63
Total Cost 849.63
Rate Per m2 850.00

900 mm wide pavement


6 NWP ENG. J-31 2,517.00
Add Overhead & Profits
12% 302.04
Total Cost 2,819.04
Rate Per m 2,819.00
BILL NO. 02 : RENOVATION WORK OF INTAKE.

7 Floor Rendering T1.1.1.1


Rendering 703.00
Demolishing (NWP) 271.00
974.00
Add Overhead & Profits
27% 262.98
Total Cost 1,236.98
Rate Per m2 1,237.00

8 External Painting V1.1.1.1.


Ex. Painting 496.00
Add Overhead & Profits
27% 133.92
Total Cost 629.92
Rate Per m2 630.00

9 Internal Painting V1.1.1.1.


In. Painting 412.00
Soffit Painting 497.00
909.00
Average 454.50
Add Overhead & Profits
27% 122.72
Total Cost 577.22
Rate Per m2 577.00

10 Water Proofing Painting H1.2.1.1.


Roof top 1,475.00
Add Overhead & Profits
27% 398.25
Total Cost 1,873.25
Rate Per m2 1,873.00

11 Panelled Door (Sash)


NWP ENG. Q-10 13,020.00 m2
Add Overhead & Profits
12% 1,562.40
Total Cost 14,582.40 m2

Rate per door Sash 750*2100 mm 22,967.28


Rate Per nr 22,967.00

12 Chequered Plate
Plate 118,000.00
Hand Rail 21,000.00
for frame work 5,000.00
144,000.00
Add Overhead & Profits
27% 38,880.00
Total Cost 182,880.00
Rate Per m2 182,880.00
Pura Neguma - Local Government Enhancement Sector Project
RENOVATION WORK OF INTAKE
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Quantity
Length Breath Depth Previous Bill Bill

Internal Plaster
16 mm thick plastering to wall in cement and
3 sand mortar 1:5 finished smooth with Wall m2
Putty.
Window Reveals m2 1.00 4.70 0.10 0.47
0.47 - 0.47

900 mm wide Pavement without drain in 1:3:6


(40 mm) concrete, 75 mm thick with 700
gauge polythene layer on earth surface after
compaction including expansion joint at every
6 3,000 mm interval laterally and along the
plinth using 6 mm thick regiform and finished
smooth with 12 mm thick rendering 1:3
cement and sand around the Intake Pump
House.
m 1 5.35 5.35
m 1 1.45 1.45

6.80 - 6.80

Floor rendering at the Intake Pump House by


applying 20 mm thick rendering in cement and
sand 1:3 finished smooth with neat cement
7 float up to the level equal to the existing floor.
(Rate to include any demolishing work of
existing floor rendering)
m2 1 1.1 1.65 1.82
1.82 - 1.82

External Painting

Prepare the surfaces and apply one coat of


wall primer and two coats of Weather shield
8 Emulsion Paint in external surfaces of Pump
House.

External Area m2 2.00 2.95 2.36 13.92


m2 2.00 3.52 2.36 16.61
m2 1.00 1.93 0.84 (1.62)
m2 1.00 1.03 1.32 (1.36)
m2 1.00 0.67 0.90 (0.60)
External Slab Bottom m2 1.00 14.25 0.33 4.63
Side of Slab m2 1.00 0.20 15.56 3.10

34.69 - 34.69

Prepared Checked as per the Contract Checked & Recommanded as per Checked & Certified as per the Contract
the Contract
Pura Neguma - Local Government Enhancement Sector Project
RENOVATION WORK OF INTAKE
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Quantity
Length Breath Depth Previous Bill Bill

…………………………… ………………………………………………… ……………………………………………………………………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Internal Painting
Prepare the surfaces and apply one coat of wall
9 primer and two coats of emulsion paint in
Pump House Internal wall surfaces & soffit of
roof slab.
Internal Area m2 2.00 3.08 2.36 14.54
1.00 1.93 0.84 (1.62)
1.00 1.03 1.32 (1.36)
2.00 2.50 2.36 11.80
Internal Top Of the Ceiling m2 1.00 3.08 2.50 7.70
31.06 - 31.06

Water Proofing Painting

Applying water proofing paint (Approved by


the Engineer) on top of the Roof slab of Pump
10 House. m2 1.00 3.60 4.18 15.05
15.05 - 15.05

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per
the Contract
Pura Neguma - Local Government Enhancement Sector Project
RENOVATION WORK OF INTAKE
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Quantity
Length Breath Depth Previous Bill Bill
Checked & Certified as per the Contract
Checked & Recommanded as per
the Contract

…………………………… ………………………………………………… ……………………………………………………………………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 03 : CONSTRUCTION OF AERATOR

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
CLASS D - DEMOLITION AND SITE CLEARANCE
General Clearance shall be measured in square
meters

General clearing site vegetation of bushes, shrub,


1 undergrowth, hedges and tree stumps ≤ 500 mm m2 30.00 73.00 2,190.00 30.00 2,190.00 - 30.00 2,190.00
girth.( premises of Aerator)

Refer Drawing No.


NWP-AF-WS-CKD-15/KGW/WTP/3,4,5 - - - - -

CLASS E - EARTHWORKS - - - - -

Rate shall include for compacting dewatering,


upholding sides of excavation where necessary - - - - -

Excavation for foundation base, Trenches and the


like commencing from the existing ground level, in
2 any material other than rock including compacting - - - - -
bottom of excavation
2.1 Depth not exceeding 1.0 m m3 6.00 1,066.00 6,396.00 6.00 6,396.00 - 6.00 6,396.00

2.2 Depth exceeding 1.0 m but not exceeding 2.0 m m3 4.00 1,146.00 4,584.00 2.03 2,326.38 - 2.03 2,326.38

TOTAL CARRIED FORWARD 13,170.00 10,912.38 - 10,912.38

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 03 : CONSTRUCTION OF AERATOR

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 13,170.00 10,912.38 - 10,912.38


Excavation in Rock - - -
Extra-over excavation for above item nos. 2 .1 &
3 2.2 for soft rock, (Provisional Quantity)(Not m3 1.00 4,725.00 4,725.00 - -
requiring blasting)
Extra-over excavation for above item nos. 2.1, 2.2
4 & 3 for hard rock (Provisional Quantity) m3 1.00 13,125.00 13,125.00 - -
(Controlled blasting)

Back filling around the structure with selected


5 excavated materials (other than top soil or rock) to m3 5.40 830.00 4,482.00 4.71 3,909.30 - 4.71 3,909.30
95% of compaction as directed by the Engineer.
(Compaction reports should be provided)

CLASS F - INSITU CONCRETE -


Reinforcement and formwork to be measured
separately unless otherwise stated. -
Provision and Placing of Concrete. -
Concrete Grade 15 -
Mass Concrete -
6 75mm thick screed under the base of Aerator m2 8.00 1,106.00 8,848.00 6.76 7,476.56 - 6.76 7,476.56
Provision and Placing of Concrete. - -
Concrete Grade 25 - -
Reinforced Concrete - -
7 In 225 mm thick base slab of Aerator. m3 1.70 22,494.00 38,239.80 1.52 34,190.88 - 1.52 34,190.88
8 In 450 mm diameter of supporting Column m3 0.90 22,494.00 20,244.60 1.04 23,393.76 - 1.04 23,393.76
TOTAL CARRIED FORWARD 102,834.40 79,882.88 - 79,882.88

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 03 : CONSTRUCTION OF AERATOR

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 102,834.40 79,882.88 - 79,882.88


In 150 mm thick tray no. 4 with conical edge
9 (Rate to include for forming a bell form at top of m3 0.20 24,594.00 4,918.80 0.10 2,459.40 - 0.10 2,459.40
the tray)
In 150 mm thick tray no. 3 with conical edge
10 (Rate to include for forming a bell form at top of m3 0.60 24,594.00 14,756.40 0.48 11,805.12 - 0.48 11,805.12
the tray)
In 150 mm thick tray no. 2 with conical edge
11 (Rate to include for forming a bell form at top of m3 1.00 24,594.00 24,594.00 0.91 22,380.54 - 0.91 22,380.54
the tray)
In 150 mm thick tray no. 1 with conical edge
12 (Rate to include for forming a bell form at top of m3 1.70 24,594.00 41,809.80 1.51 37,136.94 - 1.51 37,136.94
the tray)
FORMWORK - - -
Formwork in approved timber. Rate to include
for supply of formwork, splayed edges, battens,
strutting, bolting, wedging, easing, striking - - -
and removal.
Rough Finished Formwork - - -
(Plane Vertical.) - - -

13 To sides of Screed of Aerator Base. (75 mm thick) m 10.50 131.00 1,375.50 10.40 1,362.40 - 10.40 1,362.40

14 To sides of Base of Aerator. m2 2.60 1,295.00 3,367.00 2.34 3,030.30 - 2.34 3,030.30

TOTAL CARRIED FORWARD 193,655.90 158,057.58 - 158,057.58

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 03 : CONSTRUCTION OF AERATOR

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 193,655.90 158,057.58 - 158,057.58


Fair Finish Formwork -
(Plain Horizontal) -
15 To Soffit of tray no.04 m2 0.25 1,295.00 323.75 0.08 103.60 - 0.08 103.60
16 To Soffit of tray no.03 m2 2.10 1,295.00 2,719.50 1.85 2,395.75 - 1.85 2,395.75
17 To Soffit of tray no.02 m2 4.50 1,295.00 5,827.50 4.18 5,413.10 - 4.18 5,413.10
18 To Soffit of tray no.01 m2 8.20 1,295.00 10,619.00 7.63 9,880.85 - 7.63 9,880.85
(Plain Sloping)
19 To Sloping sides of tray no.04 m2 1.20 1,295.00 1,554.00 1.06 1,372.70 - 1.06 1,372.70
20 To Sloping sides of tray no.03 m2 3.30 1,295.00 4,273.50 2.98 3,859.10 - 2.98 3,859.10
21 To Sloping sides of tray no.02 m2 4.90 1,295.00 6,345.50 4.36 5,646.20 - 4.36 5,646.20
22 To Sloping sides of tray no.01 m2 6.50 1,295.00 8,417.50 5.83 7,549.85 - 5.83 7,549.85
(For Concrete Components of Constant Cross-
Section)
23 To sides of 450 mm dia. Supporting column. m2 7.90 1,295.00 10,230.50 6.92 8,961.40 - 6.92 8,961.40
REINFORCEMENTS - - - - - -
Tor/ Mild steel bar reinforcement cut to
length, bent to shape, placed in position and - - - - - -
tied with GI wire.
24 6 mm dia. kg 10.00 170.00 1,700.00 7.95 1,351.50 - 7.95 1,351.50
25 10 mm dia. kg 250.00 170.00 42,500.00 232.26 39,484.20 - 232.26 39,484.20
26 16 mm dia. kg 200.00 170.00 34,000.00 185.22 31,487.40 - 185.22 31,487.40
TOTAL CARRIED FORWARD 322,166.65 275,563.23 - 275,563.23

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 03 : CONSTRUCTION OF AERATOR

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 322,166.65 275,563.23 - 275,563.23


Bituminous Painting -
Apply two coats of Bituminous Paint on the four
27 sides of the base , Upper surface of base and for m2 5.00 2,100.00 10,500.00 5.00 10,500.00 - 5.00 24,969.00
sides of column up to floor level.

CLASS J: PIPE WORK - FITTINGS AND VALVES


Rate shall include bolts and other fixing
accessories where necessary.
Inlet Pipe

28 150 mm dia. DI Flanged and Plain ended nr 1 56,112.00 56,112.00 1.00 56,112.00 - 1.00 56,112.00
approximately 3,787 mm long pipe piece.
29 150 mm dia. DI D/F 900 Long Radius Bend. nr 1 25,517.00 25,517.00 1.00 25,517.00 - 1.00 25,517.00
30 150 mm dia. DI D/F 2,250 mm long pipe nr 1 42,601.00 42,601.00 - - 1.00 42,601.00 1.00 42,601.00
Outlet Pipes. - - - - - -
250 mm dia. DI Flanged and Plain ended pipe,
31 (300 mm long) with Puddle. nr 1 44,142.00 44,142.00 1.00 44,142.00 - 1.00 44,142.00

32 250 mm dia. DI, D/F 90 Long Radius Bend


0
nr 1 60,651.00 60,651.00 1.00 60,651.00 1.00 60,651.00

33 250 mm dia. DI Flange and Plain Ended nr 1 54,690.00 54,690.00 1.00 54,690.00 1.00 54,690.00
approximately 1,000 mm long pipe with Puddle.

Supply & Fixing of 150 mm dia. Section valves


complete including construction of Valve Chamber
34 as shown in detail on drawing no. nr 2 215,514.00 431,028.00 - - -
NWP/AF/WS/CKD-15 / KGW/ TP- 05.
Total Carried Over to Summary … 1,047,407.65 411,834.23 157,942.00 584,245.23

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 03 : CONSTRUCTION OF AERATOR

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
AERATOR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Total
No Qty up to Qty for This Quantity
Previous Bill Bill
Length Constant Depth

CLASS D - DEMOLITION AND SITE CLEARANCE


General clearing site vegetation of bushes,
1 shrub, undergrowth, hedges and tree stumps ≤
500 mm girth.( premises of Aerator) m2 5.00 6.00 30.00
30.00 - 30.00

CLASS E - EARTHWORKS

Excavation for foundation base, Trenches and


2 the like commencing from the existing ground
level, in any material other than rock including
compacting bottom of excavation

2.1 Depth not exceeding 1.0 m m3 1 2.60 2.60 1.00 6.76


CUMULATIVE QTY 6.76 6.76
BOQ QTY 6.00 - 6.00
EXCESS QTY 0.76 0.76

2.2 Depth exceeding 1.0 m but not exceeding 2.0 m


m3 1 2.60 2.60 0.30 2.03
2.03 - 2.03

CLASS E - EARTHWORKS

Back filling around the structure with selected


excavated materials (other than top soil or rock)
5 to 95% of compaction as directed by the
Engineer. (Compaction reports should be
provided)
m3 1.00 2.60 2.60 1.075 7.27
m3 1.00 0.76 0.88 0.80 (0.54)
6.73 - 6.73
Paid 70% 4.71 4.71
CLASS F - INSITU CONCRETE
Concrete Grade 15
6 75mm thick screed under the base of Aerator m2 1 2.60 2.60 6.76
6.76 - 6.76

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
AERATOR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Total
No Qty up to Qty for This Quantity
Previous Bill Bill
Length Constant Depth

…………………………… ………………………………………………… ……………………………………………………………………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Concrete Grade 25
Reinforced Concrete
7 In 225 mm thick base slab of Aerator. m3 1 0.23 2.60 2.60 1.52
1.52 - 1.52

8 In 450 mm diameter of supporting Column m3 1.00 0.80 0.80 0.87 0.56


1.00 0.75 3.14 0.20 0.48
1.04 - 1.04

9 In 150 mm thick tray no. 4 with conical edge m3 1.00 0.10 3.14 0.33 0.10
0.10 - 0.10

10 In 150 mm thick tray no. 3 with conical edge m3 1.00 0.46 3.14 0.33 0.48
0.48 - 0.48

11 In 150 mm thick tray no. 2 with conical edge m3 1.00 0.88 3.14 0.33 0.91
0.91 - 0.91

12 In 150 mm thick tray no. 1 with conical edge m3 1.00 1.46 3.14 0.33 1.51
1.51 - 1.51

FORMWORK
Rough Finished Formwork
(Plane Vertical.)

13 To sides of Screed of Aerator Base. (75 mm m


thick) 4.00 2.60 10.40
10.40 - 10.40

14 To sides of Base of Aerator. m2 4.00 0.23 2.60 2.34


2.34 - 2.34

Fair Finish Formwork


(Plain Horizontal)
15 To Soffit of tray no.04 m2 1.00 0.30 3.14 0.25 0.24
m2 1.00 0.20 3.14 0.25 (0.16)
0.08 - 0.08

16 To Soffit of tray no.03 m2 1.00 0.64 3.14 2.01


1.00 0.05 3.14 (0.16)
1.85 - 1.85

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
AERATOR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Total
No Qty up to Qty for This Quantity
Previous Bill Bill
Length Constant Depth

…………………………… ………………………………………………… ……………………………………………………………………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

17 To Soffit of tray no.02 m2 1.00 1.38 3.14 4.33


1.00 0.05 3.14 (0.16)
4.18 - 4.18

18 To Soffit of tray no.01 m2 1.00 2.48 3.14 7.79


1.00 0.05 3.14 (0.16)
7.63 - 7.63

(Plain Sloping)
19 To Sloping sides of tray no.04 m2 1.00 0.25 3.14 0.79
m2 1.00 0.09 3.14 0.27
1.06 - 1.06

20 To Sloping sides of tray no.03 m2 1.00 0.64 3.14 2.01


1.00 0.31 3.14 0.97
2.98 - 2.98

21 To Sloping sides of tray no.02 m2 1.00 0.92 3.14 2.89


m2 1.00 0.47 3.14 1.47
4.36 - 4.36

22 To Sloping sides of tray no.01 m2 1.00 1.22 3.14 3.82


m2 1.00 0.64 3.14 2.00
5.83 - 5.83

23 To sides of 450 mm dia. Supporting column. m2 2.00 0.80 0.87 1.39


2.00 0.80 0.80 1.28
m2 1.00 0.45 3.14 3.01 4.25
6.92 - 6.92

REINFORCEMENTS
24 6 mm dia. kg 2.27
5.68
7.95 - 7.95

25 10 mm dia. kg 55.98
176.27
232.25 - 232.25

26 16 mm dia. kg 185.22
185.22 - 185.22

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
AERATOR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Total
No Qty up to Qty for This Quantity
Previous Bill Bill
Length Constant Depth
Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ……………………………………………………………………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Bituminous Painting
Apply two coats of Bituminous Paint on the
27 four sides of the base , Upper surface of base m2
and for sides of column up to floor level. 4.00 0.23 2.60 2.34
1.00 3.36 0.76 2.55
1.00 2.60 2.60 6.76
1.00 0.80 0.88 0.70
1.00 0.80 0.88 (0.70)
1.00 0.075 3.14 0.24
CUMULATIVE QTY 11.89 11.89
BOQ QTY 5.00 - 5.00
EXCESS QTY 6.89 6.89

CLASS J: PIPE WORK - FITTINGS AND VALVES

Inlet Pipe
150 mm dia. DI Flanged and Plain ended
28 nr 1 1.00
approximately 3,787 mm long pipe piece.
1.00 - 1.00

29 150 mm dia. DI D/F 900 Long Radius Bend. nr 1 1.00


1.00 - 1.00

30 150 mm dia. DI D/F 2,250 mm long pipe nr 1 1.00


- 1.00 1.00

Outlet Pipes

31 250 mm dia. DI Flanged and Plain ended pipe, nr 1 1.00


(300 mm long) with Puddle.
1.00 - 1.00

32 250 mm dia. DI, D/F 900 Long Radius Bend nr 1 1.00


- 1.00 1.00

250 mm dia. DI Flange and Plain Ended


approximately 1,000 mm long pipe with
33 Puddle. nr 1 1.00
- 1.00 1.00
Pura Neguma - Local Government Enhancement Sector Project
AERATOR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Total
No Qty up to Qty for This Quantity
Previous Bill Bill
Length Constant Depth
Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ……………………………………………………………………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
1 CONSTRUCTION OF CHEMICAL ADDING CHAMBER
CLASS E - EARTHWORKS

Rate shall include for compacting dewatering,


upholding sides of excavation where
necessary
Rate to include for removing surplus excavated
earth and deposited at the direction of Engineer
with in the site boundaries at suitable places not
disturbing to surface drainage and cost of
dewatering, Planking & Strutting, if necessary.

1.1 Depth not exceeding 1.0 m m3 2.75 1,065.00 2,928.75 2.75 2,928.75 2.75 2,928.75
1.2 Depth exceeding 1.0 m but not exceeding 2.0 m m3 0.75 1,145.00 858.75 0.75 858.75 0.75 858.75
Excavation in Rock -
1.3 Extra-over excavation for above item no. 2 .1 &
2.2 for soft rock, (Provisional Quantity)(Not
requiring blasting)
m3 1.00 4,725.00 4,725.00
1.4 Extra-over excavation for above item no. 2.1, 2.2
& 3 for hard rock, (Provisional Quantity)
(Controlled blasting)
m3 1.00 13,125.00 13,125.00
1.5 Back filling around the structure with selected
excavated materials (other than top soil or rock)
to 95% of compaction as directed by the
Engineer. (Compaction reports should be
provided)
m3 2.00 830.00 1,660.00
TOTAL CARRIED FORWARD 23,297.50 - 3,787.50 3,787.50

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 23,297.50 - 3,787.50 3,787.50


CLASS F - INSITU CONCRETE -

Reinforcement and formwork to be measured


separately unless otherwise stated. -
Provision and Placing of Concrete. -
Concrete Grade 15 -
Mass Concrete -
1.6 75 mm thick screed under the base of Column
Footing
m2 2.60 1,105.00 2,873.00 2.52 2,784.60 2.52 2,784.60
Provision and Placing of Concrete. -
Concrete Grade 25 -
Reinforced Concrete -
1.7 In 200 mm thick Base of Column m3 0.60 22,494.00 13,496.40 0.50 11,336.98 0.50 11,336.98
1.8 In 225 x 225 mm Columns m3 0.25 22,494.00 5,623.50 0.25 5,579.92 0.25 5,579.92
1.9 In 225 x 225 mm Beam m3 0.10 22,494.00 2,249.40 0.06 1,366.51 0.06 1,366.51
1.10 In Chamber m3 0.60 22,494.00 13,496.40 0.53 11,876.83 0.53 11,876.83
Formwork
FORMWORKin approved timber. Rate to
include for supply of formwork, splayed
edges, battens, strutting, bolting, wedging,
Rough
easing,Finished Formwork
striking and removal.
1.11 To sides of Base m2 1.30 1,295.00 1,683.50 1.28 1,657.60 1.28 1,657.60
1.12 To sides of column. m2 4.25 1,295.00 5,503.75 4.14 5,361.30 4.14 5,361.30
1.13 To sides & soffit of Beam m2 0.40 1,295.00 518.00 0.40 518.00 0.40 518.00
1.14 To sides & soffit of Chamber m2 8.50 1,295.00 11,007.50 7.32 9,479.40 7.32 9,479.40
TOTAL CARRIED FORWARD 79,748.95 - 53,748.64 53,748.64

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 79,748.95 - 53,748.64 53,748.64
Extra over Formwork for forming openings for
the following -
1.15 For passing 250 mm dia. Pipe through 100 mm
thick wall nr 1 525.00 525.00 1.00 525.00 1.00 525.00
1.16 For passing 250 mm dia. Pipe through 150 mm
thick wall nr 1 525.00 525.00 1.00 525.00 1.00 525.00
REINFORCEMENTS - - - - -
Tor/ Mild steel bar reinforcement cut to
length, bent to shape, placed in position and
tied with GI wire.
- - - - -
1.17 6 mm dia. kg 20.00 169.00 3,380.00 4.88 824.72 4.88 824.72
1.18 10 mm dia. kg 15.00 169.00 2,535.00 14.99 2,533.31 14.99 2,533.31
1.19 12 mm dia. kg 85.00 169.00 14,365.00 65.87 11,132.03 65.87 11,132.03
1.20 16 mm dia. kg 50.00 169.00 8,450.00 46.07 7,785.83 46.07 7,785.83
Bituminous Painting -
1.21 Apply two coats of Bituminous Paint on the four
sides of the base, Upper surface of base and sides
of column up to floor level.
m2 6.00 1,575.00 9,450.00
1.22 Applying non toxic water proofing paint
(Approved by the Engineer) on Chamber Internal
wall including bottom.
m2 3.50 2,730.00 9,555.00

TOTAL CARRIED FORWARD 128,533.95 - 77,074.53 77,074.53

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 128,533.95 - 77,074.53 77,074.53

CLASS J: PIPE WORK - FITTINGS AND VALVES -


Supplying, laying and jointing or fixing in
position DI pipes, fittings and specials,
complete as shown in drawings and as
directed by the Engineer.
-
Inlet Pipe -
1.23 250 mm dia. DI Flanged and Plain ended
approximately 1,000 mm long pipe piece with
Puddle Flange .
nr 1 55,740.00 55,740.00 1.00 55,740.00 1.00 55,740.00
Outlet Pipes. -
1.24 250 mm dia. DI Double Flanged pipe, (2,500 mm
long) with Puddle.
nr 1 94,259.00 94,259.00 1.00 94,259.00 1.00 94,259.00
1.25 250 mm dia. DI, D/F 900 Long Radius Bend nr 1 60,230.00 60,230.00
1.26 250 mm dia. DI Flange and Plain Ended
approximately 1,000 mm long pipe with Puddle.
nr 1 54,690.00 54,690.00
Miscellaneous -
1.27 16 mm thick plastering to concrete surfaces in
Cement, Sand mortar 1:3 finished semi rough
with wooden float.
m2 9.00 705.00 6,345.00
1.28 Prepare and apply approved type one coat of filler
and two coats of weather proof emulsion paint to
specified colour in external walls
m2 9.00 612.00 5,508.00
TOTAL CARRIED FORWARD 405,305.95 - 227,073.53 227,073.53

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 405,305.95 - 227,073.53 227,073.53
1.29 Supplying, Fabrication & Fixing of GI Ladder
consisting of 50 x 100 mm GI Box Bar stringers
500 mm apart and 400x200 mm Chequered plate
steps with 25 x 25 mm Box Bar frame fixed to
200 mm centers and fixed to concrete floor with
Grade 20 concrete pad. Rate to include for
applying two coats of Zinc Phosphate paint to all
GI Surfaces

Item Lump Sum 68,250.00


1.30 Supplying, Fabrication & Fixing of GI Hand rail
consisting of 50 x 50 mm GI Box Bar (Vertical &
Horizontal members) at both sides of ladder. Rate
to include for applying two coats of Zinc
Phosphate paint to all GI Surfaces as per given
detail drawing No.
NWP-AF-WS-CKD-15/KGW/WTP 6 and per the
instructions given by the Engineer

Item Lump Sum 37,537.50

TOTAL CARRIED FORWARD 511,093.45 - 227,073.53 227,073.53

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 511,093.45 - 227,073.53 227,073.53
2 CONSTRUCTION OF CHEMICAL HOUSE
EARTH WORK
2.1 Removing top soil to a depth up to 150 mm &
depositing excavated materials at site .Rate to
include for removing surplus excavated earth and
deposited at the direction of Engineer with in the
site boundaries at suitable places not disturbing
to surface drainage system.
m2 80.00 249.00 19,920.00 71.20 17,728.80 - 71.20 17,728.80
2.2 Excavation in foundation in any material other
than rock. Depth not exceeding 1.0 m m3 7.00 1,065.00 7,455.00 6.05 6,443.25 - 6.05 6,443.25
2.3 Filling under floors with selected gravel material,
watered and well rammed in layers of 200 mm
thick
m3 17.00 830.00 14,110.00 5.53 4,589.90 - 5.53 4,589.90
2.4 Anti termite treatment prior to the floor
concreting for new construction in Bifenthrin or
approved equivalent chemical in accordance with
manufactured specifications by an approved
specialist pest control contractor. Pest control
contractor shall submit a guarantee for a
minimum of 10 years for new construction works
from the date of application

m2 75.00 137.00 10,275.00 - - -

TOTAL CARRIED FORWARD 562,853.45 28,761.95 227,073.53 255,835.48

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 562,853.45 28,761.95 227,073.53 255,835.48
CONCRETE WORK
Concrete in Grade 15
2.5 In 50 mm thick blinding concrete for foundations
m2 12.00 737.00 8,844.00 12.00 8,844.00 - 12.00 8,844.00
- -

2.6 In 75 mm thick blinding concrete for column


footing
m2 1.00 1,105.00 1,105.00 0.81 895.05 - 0.81 895.05
Concrete in Grade 20 - -
2.7 In 75 mm thick mass concrete in ground floor m2 40.00 1,385.00 55,400.00 37.07 51,341.95 - 37.07 51,341.95
2.8 In 75 mm thick mass concrete base for 1,000
liters tank in ground floor m2 4.00 1,385.00 5,540.00 4.00 5,540.00 - 4.00 5,540.00
- -

Reinforced Concrete in Grade 20 (Formwork


measured separately) - -
2.9 In 225x150 mm Plinth Beam m3 0.50 18,991.00 9,495.50 0.50 9,495.50 - 0.50 9,495.50

2.10 In Columns including column footing m3 0.40 18,991.00 7,596.40 0.40 7,596.40 - 0.40 7,596.40
2.11 In Lintols m3 0.25 18,991.00 4,747.75 0.25 4,747.75 - 0.25 4,747.75

FORMWORK - - -
Rate to include for Splayed Edges, Battens,
Strutting, Bolting, Wedging, Easing, Striking and
Removal . - - -
2.12 In 225x150 mm Plinth Beam m2 10.25 1,295.00 13,273.75 9.13 11,823.35 - 9.13 11,823.35
2.13 In Columns m2 4.20 1,295.00 5,439.00 4.20 5,439.00 - 4.20 5,439.00

2.14 In Lintols m2 4.00 1,295.00 5,180.00 4.00 5,180.00 - 4.00 5,180.00

TOTAL CARRIED FORWARD 679,474.85 139,664.95 227,073.53 366,738.48

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 679,474.85 139,664.95 227,073.53 366,738.48
REINFORCEMENTS -
2.15 Tor Steel kg 100.00 169.00 16,900.00 100.00 16,900.00 100.00 16,900.00
- -
2.16 Mild Steel kg 50.00 169.00 8,450.00 45.09 7,620.21 45.09 7,620.21
BRICK WORK, BLOCK WORK & MASONRY - - - - -
BRICK WORK - - - - -
2.17 225 mm thick brick work in 1:5 cement sand
mortar m2 130.00 3,922.00 509,860.00 86.77 340,311.94 86.77 340,311.94
MASONARY WORKS - - - - -
2.18 Random Rubble Masonry in 1:5 cement sand
mortar in foundation m3 8.00 13,182.00 105,456.00 8.00 105,456.00 8.00 105,456.00
- -
ROOF WORK & CEILING - - -
All timber work in roof and ceiling Category "A"
timber which should be treated with two coats of
good quality wood preservative approved by the
Engineer - - - -
2.19 Supply, Fabricate & fixing of Zinc Aluminium
coated colour bonded profile sheet roof on
Category "A " timber frame including 50 X 175
mm Ridge plate , 50 X100 mm Rafters, 50 X 50
mm reepers, 75 X 100 mm Wall plate etc. All
timber works to be treated with two coats of
good quality wood preservative approved by the
Engineer. Rate to be include for Ridging with
Zink Alumn Colour bonded ridge caps.

m2 83.00 5,775.00 479,325.00 76.86 443,866.50 - 76.86 443,866.50


TOTAL CARRIED FORWARD 1,799,465.85 1,053,819.60 227,073.53 1,280,893.13

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 1,799,465.85 1,053,819.60 227,073.53 1,280,893.13
2.20 Supplying & Fixing of 305 mm gith 0.47 mm
thick Zinc Aluminium colour bond valance board
and barge board fixed with MS 32x5mm brackets
at 900 mm C/c. Rates shall include for
application of one coat of anti corrosive paint and
finishing coat of enamel paint for MS brackets as
per instruction given by the Engineer.

m 37.00 2,100.00 77,700.00 35.12 73,752.00 - 35.12 73,752.00


2.21 Supply & fixing of 15 mm thick Timber ceiling
(Lunumidella) fixed to under side of rafters;
Treated with two coat of good quality wood
preservative approved by the Engineer to all
timber work as per detail drawings
m2 65.00 2,625.00 170,625.00 46.59 122,298.75 - 46.59 122,298.75
SURFACE FINISHES - - - - -
2.22 Supplying and laying 1000 gauge polythene sheet
under side of floor m2 45.00 126.00 5,670.00 37.07 4,670.82 - 37.07 4,670.82
2.23 External Plastering 16 mm thick in 1:1:5 cement
lime sand to external walls, columns, beams
finished semi rough. Rate to include for door and
window reveals
m2 78.00 731.00 57,018.00 71.15 52,010.65 - 71.15 52,010.65
2.24 Internal Plastering 16 mm thick in 1:1:5 cement
lime sand to Internal walls, columns, beams
finished smooth with lime putty. Rate to include
for door and window reveals
m2 103.00 752.00 77,456.00 103.00 77,456.00 - 103.00 77,456.00

TOTAL CARRIED FORWARD 2,187,934.85 1,384,007.82 227,073.53 1,611,081.35

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 2,187,934.85 1,384,007.82 227,073.53 1,611,081.35
2.25 100 mm high skirting in cement sand mortar 1:3
flush with wall, finished with neat red cement
float including forming of the groove
m 38.00 141.00 5,358.00 11.40 1,607.40 - 11.40 1,607.40
2.26 Cement Rendering in floors 20 mm average thick,
1:3 cement sand mortar finished smooth with red
cement float and polished in floor
m2 45.00 905.00 40,725.00 8.74 7,909.70 - 8.74 7,909.70
PAINTING - - - -
2.27 Apply one under coat and two finishing coats of
approved Weather Proof emulsion paint on all
surfaces of External Walls including reveals.
m2 78.00 612.00 47,736.00 71.15 43,546.77 - 71.15 43,546.77
2.28 Apply one under coat and two finishing coats of
approved emulsion paint on all surfaces of
Internal Walls including reveals.
m2 103.00 542.00 55,826.00
2.29 Apply one under coat and two finishing coats of
approved emulsion paint on under side of Ceiling

m2 65.00 590.00 38,350.00

TOTAL CARRIED FORWARD 2,375,929.85 1,437,071.69 227,073.53 1,664,145.22

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 2,375,929.85 1,437,071.69 227,073.53 1,664,145.22
DOORS & WINDOWS
For powder coated Aluminium profiles
(minimum powder coating thickness of 60 to
80 microns)

Roller Door
2.30 Supplying, Fabricating and fixing of a Zn/Al Roller
door size 3,000 x 2,550 mm, having a maximum
clear width of 3.0 m and consisting of 0.6 mm
thick Zn/Al covering sheet, center bar pulleys,
side plates with necessary racers, fabricating
mechanical winding box with m.s square tube and
covering the box with metallic sheets, fixing on
site with bottom bars and G.I u-channels for
vertical guides at two vertical edges, which are
painted with two coats of anticorrosive paint and
two coats of enamel paint to match the colour of
door sheeting, and sound reduction rubber
beading embedded in the guide bars. Pulling rod
and chain to be provided for manual rolling
operation (Additional length of 225 mm to two
sides horizontally and 450 mm to upper end
inside the mechanical box as initial winding
vertically to be added to the clear opening area)

nr 1 240,975.00 240,975.00 1.00 240,975.00 1.00 240,975.00


TOTAL CARRIED FORWARD 2,616,904.85 1,678,046.69 227,073.53 1,905,120.22

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 2,616,904.85 1,678,046.69 227,073.53 1,905,120.22
2.31 Supply, fabricate & fix Powder coated Aluminium
framed composite panel single sash, Swing Door
size 900x2,100 mm, including 1 pair of 25 mm
dia. 450 mm long stainless steel handle, best
quality door lock, 4 nrs Stainless steel hinges and
other accessories to manufacturer's details and to
the Engineer's approval

m2 2 21,000.00 42,000.00 1.92 40,320.00 - 1.92 40,320.00


2.32 Supply, fabricate & fix Powder coated Aluminium
framed single sash glazed window, size 750x1650
mm, with 900 mm sill height and fixed Glass on
top, including best quality aluminium casement
locks and other accessories to manufacturer's
details and to the Engineer's approval

m2 2.5 21,000.00 52,500.00 2.48 52,080.00 - 2.48 52,080.00


GUTTERS AND DOWN PIPES - -
2.33 Zinc Aluminium coated colour bonded plain sheet
eave gutter 470 mm giirth fixed with and
including standard gutter brackets.
m 20.00 1,890.00 37,800.00 18.52 35,002.80 18.52 35,002.80
2.34 100 x 100 mm Square type Zinc Aluminium
coated colour bonded plain sheet down pipe fixed
to column/wall with and including standard
down pipe brackets and necessary fittings, bends,
shoe etc., fixed complete .
m 16.00 1,680.00 26,880.00
TOTAL CARRIED FORWARD 2,776,084.85 1,805,449.49 227,073.53 2,032,523.02

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 2,776,084.85 1,805,449.49 227,073.53 2,032,523.02
ELECTRICAL INSTALLATION
All materials supplied and fixed complete as per
the drawing and as directed by the Engineer. Rate
to include for all PVC conduits and wiring as
specified, fittings and switches of approved make
- approval by the Engineer and testing,
commissioning to working order. Allow for
supply of lighting and small power as per
schedule. Allow for wiring & installation of
lighting & small power as per schedule.

2.35 Pendant lamp with 18 W CFL lamp nr 8 7,875.00 63,000.00


2.36 Ceiling Fan with Regulator nr 1 8,925.00 8,925.00
2.37 13A Socket outlet nr 2 8,925.00 17,850.00
2.38 Earth Electrode -15 mm rod (2,400 mm length)
nr 1 5,250.00 5,250.00
MISCELLANEOUS -
2.39 900 mm wide pavement with 150 x 150 mm
Concrete cut of wall & without drain in 1:3:6 (40
mm) concrete, 100 mm thick with 700 gauge
polythene layer on earth surface after compaction
including expansion joint each at 3,000 mm
intervals laterally and along the plinth using 6
mm thick regiform and cement rendering in
pavement 12 mm average thick rendering 1:3
cement and sand mortar finished smooth with red m 30.00 5,606.00 168,180.00 27.138 152,135.63 27.14 152,135.63
cement
TOTAL float.
CARRIED FORWARD 3,039,289.85 1,957,585.12 227,073.53 2,184,658.65

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 3,039,289.85 1,957,585.12 227,073.53 2,184,658.65
2.40 1,500 mm wide, 5,850 mm long ramp with 150 x
150 mm Concrete cut of wall (ref. Drawing No.
NWP/AF/WS/CKD-15/KGW/WTP-15) in 1:3:6
(40 mm) concrete, 100 mm thick with 700 gauge
polythene layer on earth surface after compaction
including expansion joint each at 3,000 mm
intervals laterally and along the plinth using 6
mm thick regiform and cement rendering in
pavement 12 mm average thick rendering 1:3
cement and sand mortar.

Item Lump Sum 52,809.75 1.00 52,809.75 - 1.00 52,809.75


3.00 CONSTRUCTION OF CHLORINE BATH
Refer Drawing, No.
NWP-AF-WS-CKD-15/KGW/WTP/16
CLASS E - EARTHWORKS
Rate to include for removing surplus excavated
earth and deposited at the direction of Engineer
within the site boundaries at suitable places not
disturbing the surface drainage; Rate to include
cost of dewatering, Planking & Strutting, if
necessary.

3.1 Depth not exceeding 1.0 m m3 4.50 1,065.00 4,792.50 2.71 2,886.15 - 2.71 2,886.15
TOTAL CARRIED FORWARD 3,096,892.10 2,013,281.02 227,073.53 2,240,354.55

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 3,096,892.10 2,013,281.02 227,073.53 2,240,354.55


Excavation in Rock -
3.2 Extra-over excavation for above item no. 3 .1 for
soft rock, (Provisional Quantity)(No blasting
required)
m3 1.00 4,725.00 4,725.00
3.3 Extra-over excavation for above item no. 3.1 & 3.2
for hard rock (Provisional Quantity)(Controlled
blasting)
m3 1.00 13,125.00 13,125.00
CLASS F - INSITU CONCRETE -
Provision and Placing of Concrete. -
Concrete Grade 15 -
Mass Concrete -
3.4 75 mm thick screed m2 5.70 1,105.00 6,298.50 4.54 5,016.70 - 4.54 5,016.70
Provision and Placing of Concrete -
Concrete Grade 25 -
Reinforced Concrete -
3.5 In 200 mm thick Base & walls of pond m3 2.00 17,416.00 34,832.00 2.00 34,832.00 - 2.00 34,832.00
- -
FORMWORK -
Rough Finished Formwork -
3.7 To sides of Pond & Beam m2 18.00 1,295.00 23,310.00 10.76 13,934.20 10.76 13,934.20
REINFORCEMENTS - - - - -
3.8 6 mm dia. kg 15.00 169.00 2,535.00 - - - -
3.9 10 mm dia. kg 50.00 169.00 8,450.00 50.00 8,450.00 50.00 8,450.00
- -
TOTAL CARRIED FORWARD 3,190,167.60 2,075,513.92 227,073.53 2,302,587.45

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


NO. DESCRIPTION UNIT QTY
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 3,190,167.60 2,075,513.92 227,073.53 2,302,587.45


3.10 Applying water proofing (Approved by the
Engineer) on Chlorine bath Internal wall
including bottom
m2 3.50 1,575.00 5,512.50
Miscellaneous -
3.12 Cement, Sand 1:3 plastering finished semi rough
of concrete work
m2 3.00 705.00 2,115.00 3.00 2,115.00 - 3.00 2,115.00
3.13 Supplying, Fabrication & Fixing of Stainless Steel
Hand Rail consisting of 38 mm dia. Vertical bars
fixed to floor using 6 mm thick Stainless steel
Base Plate and 25 mm dia. vertical members as
shown in the drawing. Rate to include for cut and
polish both bars - detail in drawing No. NWP-AF-
WS-CKD-15/KGW/WTP 16 and the instructions
given by the Engineer

Item Lump Sum 68,250.00 1.00 68,250.00 1.00 68,250.00


3.14 Supplying & Fixing of 1,300 x 150x 50 mm thick
Kubuk wood strips in bottom of the pond as given
in detail drawing No.
NWP-AF-WS-CKD-15/KGW/WTP 16 and per the
instructions given by the Engineer
Item Lump Sum 15,750.00
Total Carried Over to Summary … 3,281,795.10 2,145,878.92 227,073.53 2,372,952.45

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

CONSTRUCTION OF CHEMICAL ADDING CHAMBER


CLASS E - EARTHWORKS
Rate to include for removing surplus
excavated earth and deposited at the
direction of Engineer with in the site
boundaries at suitable places not disturbing
to surface drainage and cost of dewatering,
Planking & Strutting, if necessary.

1.1 Depth not exceeding 1.0 m m3 1.00 3.70 4.90 1.00 18.13
CUMULATIVE QTY - 18.13 18.13
BOQ QTY - 2.75 2.75
EXCESS QTY - 15.38 15.38

1.2 Depth exceeding 1.0 m but not exceeding 2.0


m m3 1.00 3.70 4.90 1.00 18.13
CUMULATIVE QTY - 18.13 18.13
BOQ QTY - 0.75 0.75
EXCESS QTY - 17.38 17.38

CLASS F - INSITU CONCRETE


Concrete Grade 15
Mass Concrete
1.6 75 mm thick screed under the base of
Column Footing
m2 1.00 1.40 1.80 2.52
- 2.52 2.52
Concrete Grade 25
Reinforced Concrete
1.7 In 200 mm thick Base of Column m3 1.00 1.40 0.20 1.80 0.50
- 0.50 0.50

1.8 In 225 x 225 mm Columns m3 2.00 0.225 0.225 2.45 0.25


- 0.25 0.25

1.9 In 225 x 225 mm Beam m3 1.00 0.225 0.225 1.20 0.06


- 0.06 0.06

1.10 In Chamber m3 1.00 1.20 1.20 0.15 0.22


1.00 1.20 1.20 0.60 0.86
1.00 1.00 1.00 0.60 (0.60)
1.00 0.10 0.40 1.20 0.05
- 0.53 0.53

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

FORMWORK
Rough Finished Formwork
1.11 To sides of Base m2 2.00 0.20 1.40 0.56
2.00 0.20 1.80 0.72
- 1.28 1.28

1.12 To sides of column. m2 8.00 0.225 2.300 4.14


- 4.14 4.14

1.13 To sides & soffit of Beam m2 1.00 0.750 0.225 0.17


2.00 0.750 0.125 0.19
2.00 0.125 0.225 0.06
- 0.41 0.41

1.14 To sides & soffit of Chamber m2 4.00 0.600 1.20 2.88


4.00 0.600 1.00 2.40
1.00 1.200 1.20 1.44
1.00 0.500 1.20 0.60
7.32 7.32
Extra over Formwork for forming
openings for the following
1.15 For passing 250 mm dia. Pipe through 100
mm thick wall 1.00
nr 1
1.00 1.00

1.16 For passing 250 mm dia. Pipe through 150


mm thick wall 1.00
nr 1
1.00 1.00
REINFORCEMENTS
Tor/ Mild steel bar reinforcement cut to
length, bent to shape, placed in position
and tied with GI wire.
1.17 6 mm dia. kg 4.88
4.88 4.88

1.18 10 mm dia. kg 14.99


14.99 14.99

1.19 12 mm dia. kg 65.87


65.87 65.87

1.20 16 mm dia. kg 46.07


46.07 46.07

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
CLASS J: PIPE WORK - FITTINGS AND
VALVES
Inlet Pipe
1.23 250 mm dia. DI Flanged and Plain ended
approximately 1,000 mm long pipe piece
with Puddle Flange .
nr 1 1.00
Outlet Pipes. 1.00 1.00
1.24 250 mm dia. DI Double Flanged pipe, (2,500
mm long) with Puddle. nr 1 1.00
1.00 1.00
CONSTRUCTION OF CHEMICAL HOUSE
EARTH WORK
2.1 Removing top soil to a depth up to 150 mm &
depositing excavated materials at site .Rate
to include for removing surplus excavated
earth and deposited at the direction of
Engineer with in the site boundaries at
suitable places not disturbing to surface
drainage system.
m2 1.00 9.187 7.750 71.20
71.20 - 71.20

2.2 Excavation in foundation in any material


other than rock. Depth not exceeding 1.0 m 1.00 35.204 0.350 0.450 5.54
m3
m3 4.00 0.500 0.350 0.450 (0.32)
5.23 - 5.23

2.3 Filling under floors with selected gravel


material, watered and well rammed in layers
of 200 mm thick
m3 1.00 4.200 5.770 0.200 4.85
m3 1.00 2.300 3.800 0.200 1.75
m3 1.00 2.250 1.700 0.200 0.77
7.36 - 7.36
Paid 75% 5.53 5.53

CONCRETE WORK
Concrete in Grade 15
2.5 In 50 mm thick blinding concrete for
foundations m2 1.00 34.504 0.36 12.56
CUMULATIVE QTY 12.56 12.56
BOQ QTY 12.00 - 12.00
EXCESS QTY 0.56 0.56

2.6 In 75 mm thick blinding concrete for column


footing m2 1.00 0.900 0.90 0.81
0.81 - 0.81

Concrete in Grade 20
2.7 In 75 mm thick mass concrete in ground
floor m2 1.00 2.350 3.80 8.93
m2 1.00 2.300 1.70 3.91
m2 1.00 4.200 5.77 24.23
37.07 - 37.07
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Concrete in Grade 20
In 75 mm thick mass concrete base for 1,000
2.8 liters tank in ground floor
m2 1.00 1.420 3.500 4.97
CUMULATIVE QTY 4.97 4.97
BOQ QTY 4.00 - 4.00
EXCESS QTY 0.97 0.97

Reinforced Concrete in Grade 20


(Formwork measured separately)
2.9 In 225x150 mm Plinth Beam m3 1.00 32.740 0.225 0.150 1.10
m3 4.00 0.500 0.225 0.150 (0.07)
CUMULATIVE QTY 1.03 1.03
BOQ QTY 0.50 - 0.50
EXCESS QTY 0.53 0.53

2.10 In Columns including column footing m3 1.000 0.900 0.900 0.240 0.19
m3 1.000 0.225 0.225 1.000 0.05
m3 1.000 3.000 0.225 0.225 0.15
0.40 - 0.40

2.11 In Lintols m3 1.00 34.752 0.225 0.150 1.17


Slab & Beam m3 1.00 4.280 0.225 0.225 0.22
1.00 4.280 0.87 0.125 0.47
CUMULATIVE QTY 1.86 1.86
BOQ QTY 0.25 - 0.25
EXCESS QTY 1.61 1.61

FORMWORK
2.12 In 225x150 mm Plinth Beam m2 2.00 32.440 0.150 9.73
m2 2.00 4.000 0.500 0.150 (0.60)
9.13 - 9.13

2.13 In Columns m2 4.00 0.360 0.900 1.30


4.00 0.225 0.750 0.68
m2 4.00 3.000 0.225 2.70
CUMULATIVE QTY 4.67 4.67
BOQ QTY 4.20 - 4.20
EXCESS QTY 0.47 0.47

2.14 In Lintols m2 2.00 34.740 0.150 10.42


Slab & Beam m2 1.00 0.675 4.28 2.89
m2 2.00 0.225 0.225 0.10
m2 1.00 4.280 0.87 3.72
m2 2.00 0.125 0.87 0.22
m2 1.00 4.280 0.125 0.54
CUMULATIVE QTY 17.89 17.89
BOQ QTY 4.00 - 4.00
EXCESS QTY 13.89 13.89
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

REINFORCEMENTS
2.15 Tor Steel kg 57.71
159.80
CUMULATIVE QTY 217.51 217.51
BOQ QTY 100.00 - 100.00
EXCESS QTY 117.51 117.51

2.16 Mild Steel kg 16.78


28.31
45.09 - 45.09

BRICK WORK
2.17 225 mm thick brick work in 1:5 cement sand
mortar m2 3.00 6.33 3.01 57.16
m2 3.00 0.50 6.33 0.95 9.02
m2 2.00 0.75 1.65 (2.48)
m2 1.00 1.75 2.67 (4.67)
m2 2.00 6.68 3.01 40.21
m2 1.00 3.00 2.55 (7.65)
m2 1.00 2.40 2.67 (6.41)
m2 1.00 2.40 3.62 8.69
m2 1.00 0.90 2.10 (1.89)
m2 1.00 34.76 0.15 (5.21)
86.77 - 86.77

MASONARY WORKS
Random Rubble Masonry in 1:5 cement sand
2.18 mortar in foundation m3 1.00 28.910 0.350 0.900 9.11
m3 4.00 0.500 0.350 0.900 (0.63)
m3 0.50 0.870 0.645 1.75 0.49
CUMULATIVE QTY 8.97 8.97
BOQ QTY 8.00 - 8.00
EXCESS QTY 0.97 0.97
ROOF WORK & CEILING
2.19 Supply, Fabricate & fixing of Zinc
Aluminium coated colour bonded profile
sheet roof on Category "A " timber frame
including 50 X 175 mm Ridge plate , 50
X100 mm Rafters, 50 X 50 mm reepers,
75 X 100 mm Wall plate etc. All timber
works to be treated with two coats of good
quality wood preservative approved by the
Engineer. Rate to be include for Ridging
with Zink Alumn Colour bonded ridge caps.

m2 2.00 9.260 4.15 76.86


76.86 - 76.86
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
2.20 Supplying & Fixing of 305 mm gith 0.47 mm
thick Zinc Aluminium colour bond valance
board and barge board fixed with MS
32x5mm brackets at 900 mm C/c. Rates
shall include for application of one coat of
anti corrosive paint and finishing coat of
enamel paint for MS brackets as per
instruction given by the Engineer.

m 4.00 4.150 16.60


m 2.00 9.260 18.52
35.12 - 35.12

2.21 Supply & fixing of 15 mm thick Timber


ceiling (Lunumidella) fixed to under side of
rafters; Treated with two coat of good
quality wood preservative approved by the
Engineer to all timber work as per detail
drawings
m2 1.00 7.360 6.33 46.59
46.59 - 46.59

SURFACE FINISHES
2.22 Supplying and laying 1000 gauge polythene
sheet under side of floor
m2 1.00 2.350 3.80 8.93
m2 1.00 2.300 1.70 3.91
1.00 4.200 5.77 24.23
37.07 - 37.07

SURFACE FINISHES
2.23 External Plastering 16 mm thick in 1:1:5
cement lime sand to external walls, columns,
beams finished semi rough. Rate to include
for door and window reveals
m2 2.00 6.330 3.01 38.10
2.00 6.330 0.50 0.95 6.01
1.00 0.750 1.65 (1.23)
1.00 1.750 2.67 (4.67)
2.00 7.130 3.01 42.92
1.00 3.000 2.55 (7.65)
1.00 2.400 2.64 (6.33)
1.00 0.750 1.65 (1.23)
2.00 0.225 4.80 2.16
1.00 0.225 8.55 1.92
1.00 5.100 0.23 1.15
71.15 - 71.15
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
2.24 Internal Plastering 16 mm thick in 1:1:5
cement lime sand to Internal walls, columns,
beams finished smooth with lime putty. Rate
to include for door and window reveals

m2 2.00 5.880 3.01 35.39


2.00 5.880 0.95 0.50 5.58
1.00 4.280 3.01 12.88
1.00 0.750 1.65 (1.23)
1.00 4.280 3.01 12.88
1.00 3.000 2.55 (7.65)
2.00 2.400 3.62 17.37
1.00 0.900 2.10 (1.89)
1.00 5.880 3.01 17.69
1.00 5.880 0.50 0.95 2.79
1.00 5.880 3.01 17.69
1.00 6.330 0.50 0.95 3.01
1.00 0.750 1.65 (1.23)
1.00 1.750 2.67 (4.67)
2.00 2.400 3.01 14.45
1.00 2.400 2.67 (6.40)
m2 1.00 0.400 2.40 0.96
1.00 0.520 2.65 1.38
CUMULATIVE QTY 118.99 118.99
BOQ QTY 103.00 - 103.00
EXCESS QTY 15.99 15.99

2.25 100 mm high skirting in cement sand mortar


1:3 flush with wall, finished with neat red
cement float including forming of the groove
m 11.40
11.40 - 11.40
2.26 Cement Rendering in floors 20 mm average
thick, 1:3 cement sand mortar finished
smooth with red cement float and polished
in floor
m2 1.00 3.800 2.30 8.74
8.74 - 8.74

2.27 Apply one under coat and two finishing coats


of approved Weather Proof emulsion paint
on all surfaces of External Walls including
reveals.
m2 2.00 6.330 3.01 38.10
2.00 6.330 0.50 0.95 6.01
1.00 0.750 1.65 (1.23)
1.00 1.750 2.67 (4.67)
2.00 7.130 3.01 42.92
1.00 3.000 2.55 (7.65)
1.00 2.400 2.64 (6.33)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

1.00 0.750 1.65 (1.23)


2.00 0.225 4.80 2.16
1.00 0.225 8.55 1.92
1.00 5.100 0.23 1.15
71.15 - 71.15

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Roller Door
Supplying, Fabricating and fixing of a Zn/Al
2.30 Roller door nr 1.00 1.00

1.00 - 1.00
CONSTRUCTION OF CHEMICAL HOUSE
DOORS & WINDOWS
2.31 Supply, fabricate & fix Powder coated
Aluminium framed composite panel single
sash, Swing Door size 900x2,100 mm,
including 1 pair of 25 mm dia. 450 mm long
stainless steel handle, best quality door lock,
4 nrs Stainless steel hinges and other
accessories to manufacturer's details and to
the Engineer's approval
m2 1.00 0.900 2.13 1.92
1.92 - 1.92

2.32 Supply, fabricate & fix Powder coated


Aluminium framed single sash glazed
window, size 750x1650 mm, with 900 mm
sill height and fixed Glass on top, including
best quality aluminium casement locks and
other accessories to manufacturer's details
and to the Engineer's approval
m2 2.00 0.750 1.65 2.48
2.48 - 2.48

GUTTERS AND DOWN PIPES


2.33 Zinc Aluminium coated colour bonded plain
sheet eave gutter 470 mm giirth fixed with
and including standard gutter brackets.
m 2.00 9.260 18.52
18.52 - 18.52

MISCELLANEOUS
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

2.39 900 mm wide pavement with 150 x 150 mm


Concrete cut of wall & without drain in 1:3:6
(40 mm) concrete, 100 mm thick with 700
gauge polythene layer on earth surface after
compaction including expansion joint each at
3,000 mm intervals laterally and along the
plinth using 6 mm thick regiform and cement
rendering in pavement 12 mm average thick
rendering 1:3 cement and sand mortar
finished smooth with red cement float.

m 1.00 2.500 2.500


8.127 8.127
1.127 1.127
8.457 8.457
5.127 5.127
0.900 0.900
0.900 0.900
27.14 - 27.14

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

2.40 1,500 mm wide, 5,850 mm long ramp with


150 x 150 mm Concrete cut of wall (ref.
Drawing No.
NWP/AF/WS/CKD-15/KGW/WTP-15) in
1:3:6 (40 mm) concrete, 100 mm thick with
700 gauge polythene layer on earth surface
after compaction including expansion joint
each at 3,000 mm intervals laterally and
along the plinth using 6 mm thick regiform
and cement rendering in pavement 12 mm
average thick rendering 1:3 cement and sand
mortar.

Item Lump Sum 1.00


1.00 - 1.00
3.00 CONSTRUCTION OF CHLORINE BATH

3.1 Depth not exceeding 1.0 m m3 1.00 0.700 1.80 2.15 2.71
2.71 - 2.71

Concrete Grade 15
Mass Concrete
3.4 75 mm thick screed m2 1.00 2.110 2.15 4.54
4.54 - 4.54
Concrete Grade 25
Reinforced Concrete
3.5 In 200 mm thick Base & walls of pond m3 1.00 1.100 0.20 2.15 0.47
1.00 0.630 0.20 2.15 0.27
1.00 1.150 0.20 2.15 0.49
1.00 1.650 0.20 2.15 0.71
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

1.00 0.920 0.20 1.93 0.36


CUMULATIVE QTY 2.30 2.30
BOQ QTY 2.00 - 2.00
EXCESS QTY 0.30 0.30
FORMWORK
Rough Finished Formwork
3.7 To sides of Pond & Beam m2 1.00 1.130 2.15 2.43
1.00 0.930 2.15 1.99
2.00 0.500 2.13 0.930 1.98
2.00 1.245 1.50 3.72
1.00 2.150 0.30 0.64
10.76 - 10.76

REINFORCEMENTS
3.9 10 mm dia. kg 81.61
CUMULATIVE QTY 81.61 81.61
BOQ QTY 50.00 - 50.00
EXCESS QTY 31.61 31.61

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Miscellaneous
Cement, Sand 1:3 plastering finished semi
3.12 rough of concrete work m2
1.00 5.600 0.50 2.80
1.00 1.100 1.00 1.10
1.00 1.720 1.00 1.72
CUMULATIVE QTY 5.62 5.62
BOQ QTY 3.00 - 3.00
EXCESS QTY 2.62 - 2.62
CONSTRUCTION OF CHLORINE BATH
3.13 Supplying, Fabrication & Fixing of Stainless
Steel Hand Rail consisting of 38 mm dia.
Vertical bars fixed to floor using 6 mm thick
Stainless steel Base Plate and 25 mm dia.
vertical members as shown in the drawing.
Rate to include for cut and polish both bars -
detail in drawing No.
NWP-AF-WS-CKD-15/KGW/WTP 16 and the
instructions given by the Engineer
Lump 1.00
1.00 - 1.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

Prepared Checked as per the Contract Checked & Recommanded as Checked & Certified as per the Contract
per the Contract

……………………………… ……………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
BAR SCHEDULE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No.Of Length of
Item Bar Type & Size Space No.Of bars in Total Length of each mm each Total length Weight per Weight (kg)
Mark mem: each No. m
A B C mm m

Base 1 T 12 1.0 9.0 9.0 1700.0 1700.0 15.30 0.889 13.60


2 T 12 1.0 12.0 12.0 1300.0 1300.0 15.60 0.889 13.87

3 T 6 1.0 20.0 20.0 800.0 800.0 16.00 0.222 3.46

Columns 4 T 16 1.0 8.0 8.0 3100.0 3100.0 24.80 1.578 39.13

Slab & Wall 5 T 12 1.0 16.0 16.0 2400.0 2400.0 38.40 0.889 34.14
6 T 12 1.0 8.0 8.0 600.0 600.0 4.80 0.889 4.27

7 T 10 1.0 5.0 5.0 4200.0 4200.0 21.00 0.617 12.96


8 T 10 1.0 3.0 3.0 1100.0 1100.0 3.30 0.617 2.04

9 T 16 1.0 4.0 4.0 1100.0 1100.0 4.40 1.578 6.94

10 T 6 1.0 8.0 8.0 800.0 800.0 6.40 0.222 1.42

Total Carried To Summary 131.82

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the Contract Certified & Recommanded as per
the Contractor

………………….………………… …………………………………………………. ………………………………………………… ...…….…………………………………………. ……………………………………………….


Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 04: CONSTRUCTION OF CHEMICAL ADDING CHAMBER, CHEMICAL HOUSE & CHLORINE BATH
BAR SCHEDULE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No.Of Length of
Item Bar Type & Size Space No.Of bars in Total Length of each mm each Total length Weight per Weight (kg)
Mark mem: each No. m
A B C mm m
Contractor Technical officer of Consultant/RDC Asst . QS RDC Asst . QS SPCU Senior Engineer
Pura Neguma - Local Government Enhancement Sector Project
BILL NO.05: CONSTRUCTION OF FLOCCULATOR & SEDIMENTATION TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Refer Drawings No.
NWP-AF-WS-CKD-15/KGW/WTP/17,18,19,20
CLASS D - DEMOLITION AND SITE CLEARANCE
Site Preparation
1 Clearing site including removal of bushes, scrub,
shrubs and under growth and grubbing up roots.
Rate to include for removing debris and
deposited at the direction of Engineer with in the m2 200.00 73.00 14,600.00 200.00 14,600.00 - 200.00 14,600.00
site boundaries at suitable places not disturbing
to surface drainage.

CLASS E - EXCAVATION & EARTHWORKS -


2 Excavation for Base, Trenches and the like, in
any material other than rock including
compacting bottom of excavation to form earth
steps as shown on drawing. Excavation to be
carried out with net dimensions keeping sides
plumbed and forming steps.
-
2.1 Depth not exceeding 1.0 m m 3
70.00 1,065.00 74,550.00 54.07 57,584.55 - 54.07 57,584.55
2.2 Depth exceeding 1.0 m but not exceeding 2.0 m
m3 55.00 1,145.00 62,975.00 55.00 62,975.00 - 55.00 62,975.00
- -
2.3 Depth exceeding 2.0 m but not exceeding 3.0 m
m3 38.00 1,260.00 47,880.00 36.75 46,305.00 - 36.75 46,305.00
2.4 Depth exceeding 3.0 m but not exceeding 5.0 m
m3 22.00 1,260.00 27,720.00 22.00 27,720.00 - 22.00 27,720.00
- -
TOTAL CARRIED FORWARD 227,725.00 209,184.55 - 209,184.55

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO.05: CONSTRUCTION OF FLOCCULATOR & SEDIMENTATION TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 227,725.00 209,184.55 - 209,184.55
Excavation in Rock
3 Extra-over item for above item no. 2 for
excavation in soft rock (Provisional Quantity)
(No blasting required)
m3 30.00 4,725.00 141,750.00
4 Extra-over item for above items no. 2 & 3 for
hard rock (Provisional Quantity)(Controlled
blasting)
m3 10.00 13,125.00 131,250.00
Earthwork Support -
5 In moderately firm ground, total depth not
exceeding 2.0 m m2 10.00 4,515.00 45,150.00
Earth Filling -
6 Earth filling around the structure to make up
levels with imported earth (other than top soil or
rock) to 98% compaction, as directed by the
Engineer (Compaction reports should be
provided)
m3 100.00 2,474.00 247,400.00 - -
7 Concrete Works -
Mass Concrete - Grade 15 -
8 75 mm thick screed in Base Slab m2 16.00 1,105.00 17,680.00 13.84 15,293.20 - 13.84 15,293.20
9 75 mm thick screed in Steps m2 60.00 1,105.00 66,300.00 47.92 52,951.60 - 47.92 52,951.60
Reinforced Concrete - Grade 25
10 In base Slab m3 6.00 17,416.00 104,496.00 4.15 72,276.40 - 4.15 72,276.40
11 In Ring Beam m3 2.50 18,466.00 46,165.00 1.53 28,252.98 - 1.53 28,252.98
TOTAL CARRIED FORWARD 1,027,916.00 377,958.73 - 377,958.73

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO.05: CONSTRUCTION OF FLOCCULATOR & SEDIMENTATION TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 1,027,916.00 377,958.73 - 377,958.73
12 In Base Slab for Flocculator m3 7.00 18,466.00 129,262.00 70.00 129,262.00 - 70.00 129,262.00
- -
13 in Column Supports for Decanting Trough m3 2.50 18,466.00 1.03 19,019.98 - 1.03 19,019.98

14 In Beams m3 2.00 18,466.00 36,932.00 0.28 5,170.48 - 0.28 5,170.48


15 In Decanting Trough m3 2.00 18,466.00 36,932.00 0.43 7,940.38 - 0.43 7,940.38
Reinforcement - -
Mild steel bars in brick Wall, Beams, Ferro
16 cement walls & columns. Kg 300.00 169.00 50,700.00 254.11 42,944.59 11.00 1,859.00 265.11 44,803.59

Tor steel bars in base Slab, Tank Wall, Beams, &


Base slab of Flocculator, Ferro cement wall,
Decanting Trough, Manholes & Column Supports
17 for Decanting Trough. Kg 2175.00 169.00 367,575.00 1,433.47 242,256.43 69.48 11,742.12 1,502.95 253,998.55
4 mm dia. GI wire in tank walls & Ferro cement
18 walls tied with GI binding wire (40 mm spacing
shall be kept as shown in the drawing)
Kg 300.00 169.00 50,700.00 140.02 23,663.38 159.98 27,036.62 300.00 50,700.00
Supplying & fixing of SWG 18 No. 04 GI wire
mesh, cut to length, bent to shape, laid in
19 position in Ferro cement walls & tank walls
(Rate to include for lap length)
m2 190.00 788.00 149,720.00 145.62 114,748.56 44.38 34,968.09 190.00 149,716.65
Formwork -
20 To sides of screed (75mm thick) m 75.00 130.00 9,750.00 72.83 9,467.90 72.83 9,467.90
TOTAL CARRIED FORWARD 1,859,487.00 972,432.43 75,605.83 1,048,038.26

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO.05: CONSTRUCTION OF FLOCCULATOR & SEDIMENTATION TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 1,859,487.00 972,432.43 75,605.83 1,048,038.26
Slab & Beam -
21 To sides & soffit of Slab m2 45.00 1,295.00 58,275.00 12.79 16,563.05 - 12.79 16,563.05

22 To sides of beam m2 10.00 1,295.00 12,950.00 8.28 10,722.60 - 8.28 10,722.60


Column Supports - -
23 To sides of Columns m2 22.00 1,295.00 28,490.00 18.36 23,776.20 - 18.36 23,776.20

24 To sides of Beams m2 8.00 1,295.00 10,360.00 3.70 4,791.50 - 3.70 4,791.50


Random Rubble Masonry in 150-225 mm
Rubble -
25 Random Rubble masonry in 1:5 cement, sand
mortar in Sedimentation Tank Wall
m3 100.00 13,182.00 1,318,200.00 90.69 1,195,475.58 - 90.69 1,195,475.58
Plastering - - - -
26 In Flocculator m2 142.00 1,412.00 200,504.00 135.92 191,919.04 135.92 191,919.04
27 In Sedimentation Tank (Inner and Outer) m2 202.00 1,412.00 285,224.00 66.61 94,049.44 - 66.61 94,049.44
28 In Ferocement Mounts for Decanting Pipes as
shown in the Drawing No. NWP-AF-WS-CKD15-
KGW/WTP18 (i),(ii)
nr 8.00 14,490.00 115,920.00 8.00 115,920.00 8.00 115,920.00
TOTAL CARRIED FORWARD 3,889,410.00 2,317,810.80 383,444.87 2,701,255.67

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO.05: CONSTRUCTION OF FLOCCULATOR & SEDIMENTATION TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 3,889,410.00 2,317,810.80 383,444.87 2,701,255.67
Pipe Work -
All Pipes and Specials, Supplying, Laying and
Jointing or fixing in position, DI/PVC pipes,
fittings an specials complete as shown in detail
on drawings and as directed. Rate to include for
Perforating Pipes.
-
Inlet -
29 280 mm dia. T-600 PVC Pipes m 26.00 3,744.00 97,344.00 2.25 8,424.00 - 2.25 8,424.00
30 280 mm dia. PVC 900 Bends nr 3.00 24,570.00 73,710.00 3.00 73,710.00 - 3.00 73,710.00
Outlet -
31 280 mm dia. PVC 900 Bends nr 2.00 24,570.00 49,140.00
32 280 mm dia. T-1000 PVC Pipes for outlet m 30.00 5,534.00 166,020.00
Decanting Pipe -
33 225 mm dia. T-1000 PVC perforated decanting nr 7.00 12,112.00 84,784.00
pipe 3,325 mm long (Pipes to rest on supports
34 280 mm dia.
and beams T-1000inPVC
as shown perforated
the drawing decanting
No.NWP-AF-
pipe 3,800 mm long (Pipe(i),(ii)
WS-CKD15-KGW/WTP18 to be rest on supports
and beams as shown in the drawing No. NWP-
AF-WS-CKD15-KGW/WTP18 (i),(ii) nr 1.00 18,571.00 18,571.00
Sludge Removal System -
35 110 mm dia. T-1000 PVC Pipes m 15.00 1,035.00 15,525.00
36 110 mm dia. PVC Equal socketed Tee nr 1.00 12,711.00 12,711.00
37 110 mm dia. PVC 450 Bends nr 2.00 2,070.00 4,140.00
38 100 mm dia. Scour Valve- Quick Opening type nr 1.00 27,825.00 27,825.00
TOTAL CARRIED FORWARD 4,439,180.00 2,399,944.80 383,444.87 2,783,389.67

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO.05: CONSTRUCTION OF FLOCCULATOR & SEDIMENTATION TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 4,439,180.00 2,399,944.80 383,444.87 2,783,389.67


39 100 mm dia. VJFA nr 2 12,898.00 25,796.00
40 110 mm dia. PVC 900 Bends nr 1 2,757.00 2,757.00
41 Supply & fix 90 mm dia. Armoured Flexible Hose
6.0 m long including necessary Hose clips etc.
nr 1 31,500.00 31,500.00
42 Supply & fix 90 mm dia. Heavily Galvanized
tapered flange & PVC tapered core, prepared
suitable for tightly connecting the 80 mm dia.
Flexible Hose, inclusive of 04 nos. 12 x 50 mm
Stainless Steel bolts & nuts and rubber packing nr 1 9,608.00 9,608.00
etc.
43 90mm dia. T-1000 PVC Pipes m 10.00 950.00 9,500.00
44 80 mm dia. VJFA nr 2 10,678.00 21,356.00
45 90 mm dia. PVC 900 Bends nr 1 1,857.00 1,857.00
46 80mm dia. DI, D/F Sluice valve nr 1 28,046.00 28,046.00
Baffle Boards
Supply & fixing of 10 mm thick PVC/ Plastic
laminated baffles (similar to DAMRO Ceiling
Sheets) framed with PVC beading fixed to
Aluminium "L" with Stainless Steel nuts & bolts
@ 150mm c/c as per Drawing No. NWP-AF-WS-
47 CKD15-KGW/WTP17(ii)
Baffle Board of overall dimension 850 x 1,000
mm nr 30 3,927.00 117,810.00
48 Baffle Board of overall dimension 825 x 1,000
mm nr 16 3,822.00 61,152.00
TOTAL CARRIED FORWARD 4,748,562.00 2,399,944.80 383,444.87 2,783,389.67

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO.05: CONSTRUCTION OF FLOCCULATOR & SEDIMENTATION TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 4,748,562.00 2,399,944.80 383,444.87 2,783,389.67


49 Baffle Board of overall dimension 800x 1,000
mm nr 12 3,717.00 44,604.00
50 Baffle Board of overall dimension 775 x 1,000 nr 8 3,612.00 28,896.00
mm
51 Baffle Board of overall dimension 750 x 1,000 nr 8 3,507.00 28,056.00
mm
52 Baffle Board of overall dimension 725 x 1,000 nr 12 3,402.00 40,824.00
53 mm
Baffle Board of overall dimension 700 x 1,000 nr 8 3,297.00 26,376.00
54 mm
Baffle Board of overall dimension 600 x 1,000 nr 3 2,877.00 8,631.00
mm
55 Supply, fabricate & fix Stainless Steel Sludge
Bucket including cable, pulleys & all accessories
as shown in detail drawing No. NWP-AF-WS- nr 1 42,000.00 42,000.00
Miscellaneous
CKD-15/KGW/WTP 17(iii) -
56 Applying non toxic water proofing paint
(Approved by the Engineer) on tank internal m2 400.00 2,100.00 840,000.00
wall including bottom
57 Prepare and apply approved type one coat of
filler and two coats of weather proof emulsion
paint to specified colour in external walls
m2 150 612.00 91,800.00
58 For Payment of actual charges incurred for
Supply, fabrication & Installation of suitable
access to centre of the Sedimentation Tank PS 80,000.00
59 Percentage adjustment to Provisional Sum for
above Item No. 58(…15….%)
Item Lump Sum 12,000.00
Total Carried Over to Summary … 5,991,749.00 2,399,944.80 383,444.87 2,783,389.67

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
FLOCCULATOR & SEDIMENTATION TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
Description Unit Nos Qty up to Qty for This
No Previous Bill Bill Quantity
Length Constant Depth

Site Preparation

Clearing site including removal of bushes,


scrub, shrubs and under growth and
grubbing up roots. Rate to include for
1 removing debris and deposited at the m2
direction of Engineer with in the site
boundaries at suitable places not disturbing
to surface drainage.
20.00 10.00 200.00
200.00 - 200.00

CLASS E - EXCAVATION & EARTHWORKS

2.1 Depth not exceeding 1.0 m m3 17.22 3.14 1.00 54.07


54.07 - 54.07

2.2 Depth exceeding 1.0 m but not exceeding


2.0 m m3 19.36 3.14 0.67 40.72
14.44 3.14 0.32 14.50
CUMULATIVE QTY 55.22 55.22
BOQ QTY 55.00 - 55.00
EXCESS QTY 0.22 0.22

2.3 Depth exceeding 2.0 m but not exceeding 3.0


m m3 14.44 3.14 0.35 15.86
10.24 3.14 0.65 20.89
36.75 - 36.75

2.4 Depth exceeding 3.0 m but not exceeding 5.0


m m3 10.24 3.14 0.07 2.25
6.76 3.14 0.67 14.22
4.00 3.14 1.02 12.81
4.41 3.14 0.37 5.12
CUMULATIVE QTY 34.40 34.40
BOQ QTY 22.00 - 22.00
EXCESS QTY 12.40 12.40
Concrete Works
7 Rate to include for mixing, placing,
compacting, curing and testing to the
standards and instructions given by the
Engineer

Mass Concrete - Grade 15


8 75 mm thick screed in Base Slab m2 3.14 4.41 13.84
13.84 - 13.84

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Pura Neguma - Local Government Enhancement Sector Project
FLOCCULATOR & SEDIMENTATION TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
Description Unit Nos Qty up to Qty for This
No Previous Bill Bill Quantity
Length Constant Depth

Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

9 75 mm thick screed in Steps m2 61.44 0.78 47.92


47.92 - 47.92

Reinforced Concrete - Grade 25


10 In base Slab m3 1.00 (2.1)2 3.14 0.30 4.15
4.15 - 4.15

11 In Ring Beam m3 1.00 22.67 0.30 0.23 1.53


1.53 - 1.53

12 In Base Slab for Flocculator m3 1.00 25.56 1.03 0.30 7.91


m3 1.00 0.80 1.50 1.50 1.80
m3 1.00 0.20 0.40 2.00 0.16
9.87 - 9.87
Paid 75% 7.40 7.40
CUMULATIVE QTY 7.40 7.40
BOQ QTY 7.00 - 7.00
EXCESS QTY 0.40 0.40

13 in Column Supports for Decanting Trough m3 4.00 0.225 0.225 5.100 1.03
1.03 - 1.03

14 In Beams m3 2.00 0.48 0.225 0.225 0.05


m3 2.00 1.58 0.225 0.225 0.16
m3 2.00 1.580 0.225 0.075 0.05
m3 2.00 0.475 0.225 0.075 0.02
0.28 - 0.28

15 In Decanting Trough m3 1.00 1.425 2.030 0.150 0.43


0.43 - 0.43

Reinforcement

16 Mild steel bars in brick Wall, Beams, Ferro


cement walls & columns. Kg 153.37
100.74
11.00
254.11 11.00 265.11

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Pura Neguma - Local Government Enhancement Sector Project
FLOCCULATOR & SEDIMENTATION TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
Description Unit Nos Qty up to Qty for This
No Previous Bill Bill Quantity
Length Constant Depth

Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)


Tor steel bars in base Slab, Tank Wall,
17 Beams, & Base slab of Flocculator, Ferro
cement wall, Decanting Trough, Manholes &
Column Supports for Decanting Trough.
Kg 426.89
Kg 40.28
Kg 58.17
Kg 908.13
Kg 69.48
1,433.47 69.48 1,502.95

18 4 mm dia. GI wire in tank walls & Ferro


cement walls tied with GI binding wire (40
mm spacing shall be kept as shown in the Kg
drawing)
56.00 13.350 0.104 77.75
15.00 4.720 0.104 7.36
24.00 22.000 0.104 54.91
31.00 22.760 0.104 73.38
31.00 29.510 0.104 95.14
CUMULATIVE QTY 140.02 168.52 308.54
BOQ QTY 300.00 300.00
EXCESS QTY 8.54

Supplying & fixing of SWG 18 No. 04 GI wire


19 mesh, cut to length, bent to shape, laid in
position in Ferro cement walls & tank walls
(Rate to include for lap length)
m2 1.00 1.50 3.14 0.75 3.53
m2 1.00 30.020 0.90 27.02
m2 2.00 22.480 0.90 40.46
m2 0.50 26.69 2.75 36.70
m2 2.00 3.140 3.50 1.50 32.97
m2 2.00 3.140 0.75 1.05 4.95
m2 4.00 3.140 3.625 1.30 59.19
m2 4.00 3.140 4.70 1.30 76.74
CUMULATIVE QTY 145.62 135.93 281.55
BOQ QTY 190.00 190.00
EXCESS QTY 91.55

Formwork
Rate to include for supplying & fixing to
shape
20 To sides of screed (75mm thick) m 7.60 3.14 23.86
6.40 3.14 20.09
5.20 3.14 16.32
4.00 3.14 12.56
72.83 - 72.83

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
FLOCCULATOR & SEDIMENTATION TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
Description Unit Nos Qty up to Qty for This
No Previous Bill Bill Quantity
Length Constant Depth

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Slab & Beam m2 2.00 2.030 0.150 0.61
21 To sides & soffit of Slab m2 2.00 1.410 0.150 0.42
m2 1.00 2.030 1.410 2.86
m2 (4.00) 0.225 0.225 (0.20)
m2 1.00 30.330 0.30 9.10
12.79 - 12.79

22 To sides of beam m2 4 1.580 0.075 0.47


m2 2 1.580 0.225 0.71
m2 4 0.475 0.075 0.14
m2 2 0.225 0.475 0.21
m2 1.00 22.480 0.30 6.74
8.28 - 8.28
Column Supports
23 To sides of Columns m2 16 0.23 5.10 18.36
18.36 - 18.36

24 To sides of Beams m2 8 0.23 0.48 0.86


m2 8 0.23 1.58 2.84
3.70 3.70

Random Rubble Masonry in 150-225 mm


Rubble

25 Random Rubble masonry in 1:5 cement, m3 1.00 4.41 3.14 0.75 10.39
sand mortar in Sedimentation Tank Wall
1.00 4.41 3.14 0.28 3.88
1.00 7.29 3.14 0.63 14.42
1.00 10.89 3.14 0.63 21.54
1.00 15.21 3.14 0.63 30.09
1.00 20.25 3.14 0.63 40.06
1.00 17.22 3.14 1.00 54.07
1.00 0.56 3.14 0.75 (1.32)
0.33 15.43 3.14 2.75 (43.97)
1.00 12.25 3.14 1.00 (38.47)
90.69 - 90.69
Plastering
26 In Flocculator m2 4.00 3.140 3.625 1.30 59.19
4.00 3.140 4.70 1.30 76.74
- 135.93 135.93

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
FLOCCULATOR & SEDIMENTATION TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
Description Unit Nos Qty up to Qty for This
No Previous Bill Bill Quantity
Length Constant Depth

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

27 In Sedimentation Tank (Inner and Outer) m2 0.50 26.69 2.75 36.70


2.00 3.140 3.50 1.20 26.38
2.00 3.140 0.75 0.75 3.53
66.61 - 66.61

In Ferocement Mounts for Decanting Pipes


as shown in the Drawing No. NWP-AF-WS-
28 CKD15-KGW/WTP18 (i),(ii) nr 8.00
8.00 8.00

Pipe Work - -
Inlet
29 280 mm dia. T-600 PVC Pipes m 1.00 2.25 2.25
2.25 - 2.25

30 280 mm dia. PVC 900 Bends nr 3.00 3.00


3.00 - 3.00

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
FLOCCULATOR & SEDIMENTATION TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
Description Unit Nos Qty up to Qty for This
No Previous Bill Bill Quantity
Length Constant Depth

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO.05: CONSTRUCTION OF FLOCCULATOR & SEDIMENTATION TANK
BAR SCHEDULE
Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No.Of Total Length of


Item Bar Type & Size Space No.Of bars in Weight Weight (kg) Shape &
Mark mem: Length of each mm each Total length per m Demension
each No. A B C D E F mm m

FERROCEMENT
WALL 31 T 10 1.0 2.0 2.0 6000.0 6000.0 6000.0 6000.0 6000.0 1850.0 31850.00 63.70 0.617 39.30

32 T 10 1.0 2.0 2.0 6000.0 6000.0 6000.0 6000.0 460.0 24460.00 48.92 0.617 30.18

4mm
Dia GI
Inner Wall 34 Wire 1.0 31.0 31.0 22760.0 22760.00 705.56 0.104 73.38

4mm
Dia GI
Wire
Outer Wall 34 1.0 31.0 31.0 29510.0 29510.00 914.81 0.104 95.14

35 R 6 1.0 35.0 35.0 300.0 300.0 516.0 300.0 1416.00 49.56 0.222 11.00

Total Carried To Summary 249.00

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the Contract Certified & Recommanded as per
the Contractor

………………….………………… …………………………………………………. ………………………………………………… ...…….…………………………………………. ……………………………………………….


Pura Neguma - Local Government Enhancement Sector Project
BILL NO.05: CONSTRUCTION OF FLOCCULATOR & SEDIMENTATION TANK
BAR SCHEDULE
Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No.Of Total Length of


Item Bar Type & Size Space No.Of bars in Weight Weight (kg) Shape &
Mark mem: Length of each mm each Total length per m Demension
each No. A B C D E F mm m
Contractor Technical officer of Consultant/RDC Asst . QS RDC Asst . QS SPCU Senior Engineer/Compliance Officer SPCU
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Refer Drawings No.
NWP-AF-WS-CKD-15/KGW/WTP/12,13,14
Note:
All Payments will be based on actual site measurements.
Cost of Excavation for working space & Backfilling will
not paid for, separately

Site Clearance
1 Clearing site, including removal of bushes, scrub, shrubs
and under growth Hedges. Rate to include for removing
debris from site
m2 100.00 73.00 7,300.00 100.00 7,300.00 - 100.00 7,300.00
Earth Works -
2 Excavation for Basement, Trenches and the like
commencing from existing ground level, in any material
other than rock including compacting bottom of
excavation
-
Rate to include for removing surplus excavated earth and
deposited at the direction of Engineer within the site
boundaries at suitable places not disturbing the surface
drainage; Rate to include cost of dewatering, Planking &
Strutting, if necessary.
-
2.1 Depth not exceeding 1.0 m m3 22.00 1,065.00 23,430.00 19.63 20,905.95 - 19.63 20,905.95
2.2 Depth exceeding 1.0 m but not exceeding 2.0 m m3 20.00 1,145.00 22,900.00 13.19 15,102.55 - 13.19 15,102.55
2.3 Depth exceeding 2.0 m but not exceeding 3.0 m m3 2.00 1,145.00 2,290.00 6.60 7,557.00 - 6.60 7,557.00
TOTAL CARRIED FORWARD 55,920.00 50,865.50 - 50,865.50

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 55,920.00 50,865.50 - 50,865.50


Excavation in Rock -
3 Extra-over excavation for above item no. 2 for soft rock,
(Provisional Quantity)(No blasting required)
m3 5.00 4,725.00 23,625.00
4 Extra-over excavation for above item no. 2 & 3 for hard
rock, (Provisional Quantity) (Controlled blasting)
m3 5.00 13,125.00 65,625.00
Concrete Woks (Formwork and Reinforcement
Measured separately) -
5 50 mm thick Grade 15 screed Concrete under the Filter
and the Filter Channel
m2 22.00 737.00 16,214.00 20.02 14,754.74 - 20.02 14,754.74
6 Grade 25 reinforced concrete in filter base, base slab of
channel, ring beam and manifold
m3 6.00 19,965.00 119,790.00 5.81 115,996.65 - 5.81 115,996.65
Formwork - - -
7
Rough finished Formwork in filter base, channel base,
manifold and ring beam m2 17.00 1,295.00 22,015.00 11.36 14,711.20 - 11.36 14,711.20
Reinforcement - - - -
8 Tor Steel bars, supplied, cut to length, bent to shape, laid
in position and tied with GI wire Kg 680.00 169.00 114,920.00 499.70 84,449.30 - 499.70 84,449.30
9 6 mm dia, Mild steel bars, Supplied, cut to length, bent to
shape, laid in position and tied with GI wire in filter tank
walls and in the ring beam
Kg 75.00 169.00 12,675.00 62.30 10,528.70 - 62.30 10,528.70
TOTAL CARRIED FORWARD 430,784.00 291,306.09 - 291,306.09

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 430,784.00 291,306.09 - 291,306.09


10 4 mm dia. GI wire in filter tank walls tied with GI binding
wire (40 mm spacing shall be kept as per the drawing)
Kg 85.00 169.00 14,365.00 85.00 14,365.00 - 85.00 14,365.00
11 Supply & fixing of SWG 18 No. 04 GI wire mesh, Supplied,
cut to length, bent to shape, laid in position in vertical
Ferro cement tank walls and at places where it is
connecting the base slab and walls (Rate to include for lap
length)
m2 80.00 788.00 63,040.00 108.80 85,734.40 - 108.80 85,734.40
12 Supplying & fixing of Chicken mesh in 225 mm walls and
bottom of the channel (embedded in the concrete) for
Ferro Cement plaster (Rate to include for lap length)
m2 65.00 368.00 23,920.00 14.37 5,288.16 14.37 5,288.16
Pre Cast Blocks (Formwork Included) - - - -
13 Casting and Placing 150 x 75x 130 mm Grade 25 concrete
Pre Cast Support Blocks including 25 x 1 mm S/S Straps &
Screws as per the drawing Nos.
NWP-AF-WS-CKD-15/KGW/WTP-12(i) and NWP-AF-WS-
CKD-15/KGW/WTP-12(ii)
nr 60 281.00 16,860.00 - - -
Masonry Work/ Ferro Cement Works - - - -
14 225 mm thick Brick Work in 1:5 Cement Sand mortar for
Walls m2 18.00 3,922.00 70,596.00 16.88 66,203.36 - 16.88 66,203.36
15 25 mm thick Ferro cement plastering in 1:3 Cement Sand
mortar, finished smooth with cement float (1:16 cement &
Pudlo cement shall be used) in Internal & External Brick
walls of filters. All as per the drawing no. NWP-AF-WS-
CKD-15/KGW/WTP-12(ii)
m2 55.00 847.00 46,585.00 37.82 32,033.54 - 37.82 32,033.54
TOTAL CARRIED FORWARD 666,150.00 494,930.55 - 494,930.55

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 666,150.00 494,930.55 - 494,930.55


16 25 mm thick Ferro Cement Plastering in 1:3 Cement Sand
mortar, finished smooth with cement float in Internal &
External walls and bottom of the channel (1:16 cement &
Pudlo cement shall be used. Additional quantity to be
considered for forming up the 75 mm thick top edge)

m2 80.00 847.00 67,760.00 58.78 49,786.66 - 58.78 49,786.66


17 12 mm thick rendering in 1:3 cement sand mortar (1:16
cement and Pudlo cement shall be used) finished smooth
with cement float at filter bottom.
m2 9.00 660.00 5,940.00
18 Forming up 150 x 150 mm chamfer in 1:3 cement mortar
(1:16 Cement & Pudlo cement shall be used and finished
smooth with cement float)
m 28.00 368.00 10,304.00
19 Applying non toxic water proofing coating on filter
internal wall including bottom m2 75.00 2,100.00 157,500.00
20 Apply two coats of Bituminous Paint on the external faces
up to ground level m2 35.00 1,575.00 55,125.00 14.37 22,632.75 - 14.37 22,632.75
21 Applying two coats of Weather Shield Paint in approved
colour including one coat of primer on external faces of
the structure above ground level
m2 75.00 612.00 45,900.00

TOTAL CARRIED FORWARD 1,008,679.00 567,349.96 - 567,349.96

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 1,008,679.00 567,349.96 - 567,349.96


PIPE WORKS
Supplying & Fixing of Pipes & Specials
Rate to include for Thrust Blocks and fixing of
Brackets, bolts & nuts, screws as per Drawings no.
NWP-AF-WS-CKD-15/KGW/WTP-12(i) & NWP-AF-WS-
Inlet Pipe
CKD-15/KGW/WTP-12(ii)
22 280 mm Dia. PVC (PNT11) Socket & Spigot Pipe m 10.00 5,533.00 55,330.00 0.40 2,213.20 - 0.40 2,213.20
23 160 mm Dia. PVC (PNT11) Socket & Spigot Pipe m 10.00 2,142.00 21,420.00
24 280 x 160 mm dia. PVC Socket Reducing Tee nr 1.00 107,310.00 107,310.00
25 280 mm dia. PVC Socketed Bend nr 1.00 24,570.00 24,570.00
Under Drain System -
26 63 mm Dia. PVC ( PNT11) Socket & Spigot perforated Pipe,
approximately 1,450 mm long
nr 20.00 885.00 17,700.00
27 63 mm Dia. PVC End cap nr 20.00 588.00 11,760.00
Filtered Water Outlet Pipes & Back Wash pipes -
28 250 mm dia. DI Flanged & Plain Ended Pipe 350 mm long
with Puddle Flange 150 mm away from Plain End nr 1.00 44,809.00 44,809.00 1.00 44,809.00 1.00 44,809.00
29 250 mm dia. DI 900 Short Radius Flanged Bend nr 2.00 49,105.00 98,210.00 1.00 49,105.00 1.00 49,105.00
30 250 mm dia. DI Flanged Pipe 3,000 mm long nr 1.00 88,718.00 88,718.00 1.00 88,718.00 1.00 88,718.00
31 250 x 250 mm DI All Flanged Tee nr 1.00 67,594.00 67,594.00
32 250 mm dia. DI Flanged Pipe approximately 2,100 mm
long . nr 1.00 74,592.00 74,592.00
33 250 x 150 mm DI All Flanged Tee nr 1.00 63,388.00 63,388.00
34 280 mm Dia. PVC ( PNT11) Socket & Spigot Pipe m 40.00 5,533.00 221,320.00
TOTAL CARRIED FORWARD 1,905,400.00 752,195.16 - 752,195.16
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 1,905,400.00 752,195.16 - 752,195.16


35 160 mm Dia. PVC ( PNT11) Socket & Spigot Pipe m 20 2,142.00 42,840.00
36 160 mm dia. PVC 900 Socketed Bend nr 2 5,584.00 11,168.00
37 160 mm dia. PVC 450 Socketed Bend nr 2 4,674.00 9,348.00
38 280 mm dia. PVC 900 Socketed Bend nr 2 11,445.00 22,890.00 1.00 11,445.00 - 1.00 11,445.00
39 280 mm dia. PVC 450 Socketed Bend nr 2 7,434.00 14,868.00 - -
40 250 mm dia. DI Flanged Adaptor nr 4 37,938.00 151,752.00 - -
41 150 mm dia. DI Flanged Adaptor nr 2 16,672.00 33,344.00 - -
Overflow Pipe - - -
42 225 mm dia. PVC PNT11 Spigot pipe, approximately 400
mm long
nr 1 1,932.00 1,932.00 - -
43 225 mm dia. PVC PNT11 Spigot pipe, approximately 1,200
mm long
nr 1 4,912.00 4,912.00 - -
44 225 mm dia. PVC PNT11 Spigot pipe, approximately 5,000
mm long
nr 1 20,205.00 20,205.00 - -
45 225 mm dia. PVC 900 Socketed Bend nr 2 15,538.00 31,076.00 - -
Air Pipe - -
46 80 mm dia. DI Flanged & Plain ended Pipe 1,350 mm long
with Puddle Flange 150 mm away from Plain end nr 1 43,403.00 43,403.00 - -
47 80 mm dia. DI Double Flanged Pipe approximately 4,000
mm long nr 1 73,460.00 73,460.00 1.00 73,460.00 1.00 73,460.00
48 80 mm dia. DI 900 short radius Flanged Bend nr 1 15,532.00 15,532.00 - -
49 80 mm dia. Flanged Sluice Valve (Wheel Operated) nr 1 31,433.00 31,433.00 -
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
TOTAL CARRIED FORWARD 2,413,563.00 837,100.16 - 837,100.16

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 2,413,563.00 837,100.16 - 837,100.16


50 80 mm dia. DI Flanged Adaptor nr 2 10,276.00 20,552.00
51 90 mm Dia. PVC ( PNT11) Socket & Spigot Pipe m 20 930.00 18,600.00
Washout Mains -
52 280 mm dia. PVC PNT11 pipe . m 45.00 4,694.00 211,230.00
FILTER MEDIA -
Supply and Place graded filter media in layers, of
Specified thickness complete as shown on the Drawing
-
53 Filter sand up to thickness of 600 mm (Uniformity
Coefficient of Filter media 1.5 -1.75, Effective size -
0.60mm)
m3 7.00 22,745.00 159,215.00
53.1 Filter Gravel Size of 2.5 mm -5.0 mm m3 1.50 22,745.00 34,117.50
53.2 Filter Gravel Size of 5.0 mm -10.0 mm m3 1.50 31,290.00 46,935.00
53.3 Filter Gravel Size of 10.0 mm -20.0 mm m3 2.00 31,290.00 62,580.00
53.4 Filter Gravel Size of 20.0 mm - 40.0 mm m3 2.00 31,290.00 62,580.00
53.5 Filter Gravel Size of 40.0 mm - 60.0 mm m3 2.50 35,893.00 89,732.50
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


DESCRIPTION UNIT QTY
NO. RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

TOTAL CARRIED FORWARD 3,119,105.00 837,100.16 - 837,100.16

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER .
Mass Concrete
Grade 15
5 50mm thick 12,400.00
2,535.00
14,935.00
Add 27%. 4,032.45
Total Cost 18,967.45
6.00% 1,138.05
New Rate 20,105.00 1,005.25

5 50mm thick 13,600.00


4,527.00
18,127.00
Add 27%. 4,894.29
Total Cost 23,021.29
6.00% 1,381.28
New Rate 24,403.00

Pre Cast Blocks


(Formwork
5 Included) 13,600.00
4,527.00 160.00
18,127.00 110.00
Add 27%. 4,894.29 90.00
Total Cost 23,021.29 63
6.00% 1,381.28
New Rate 24,403.00

17 893.00
Allow 500.00
-
1,393.00
Add 27%. 376.11
Total Cost 1,769.11
6.00% 106.15
New Rate 1,875.00

FILTTER MEDIA
53 Filter sand up to thickness
of 600 mm
( Uniformity Coefficient of
Filter media 1.5 -1.75
Effective size -0.60mm)
11,150.00 27% 3,010.50
53.1 Filter Gravel Size of 2.5
mm -5.0 mm 12,100.00 27% 3,267.00
53.2 Filter Gravel Size of 5.0
mm -10.0 mm 12,125.00 27% 3,273.75
53.3 Filter Gravel Size of 10.0
mm -20.0 mm 13,900.00 27% 3,753.00
53.4 Filter Gravel Size of 20.0
mm -40.0 mm 15,450.00 27% 4,171.50
53.5 Filter Gravel Size of 40.0
mm -60.0 mm 15,450.00 27% 4,171.50

Item 01 - PNT11
( Consider 1m ) 225mm 110mm
Supply Cost 4,304.35 1,052.17
15% 645.65 157.83
Total Supply Cost 4,950.00 1,210.00
Rubber Rings 56.17 15.67
General Clearance
Excavation - 242.00
Disposal Excavated Material -
Laying 347.00 269.00
Flushing & Disinfection 27.00 17.00
Pressure Testing. 39.00 24.00
Backfilling (Selected Excavated Material) -
Dewatering - 140.00
Earth Work Support - 500.00
Trial Holes
Total Cost 413.00 1,192.00
Add 27% Overheads & Profits 111.51 321.84
524.51 1,513.84
Add 6% for 2019
Supplying & Laying Cost5,475.00 2,724.00

5506 0.40 2202


5506 1.20 6607
5506 5.00 27530

80 mm dia. DI Flanged & Plain ended Pipe 1350 mm


6,750.00

1,000.00
800.00
216.00
8,766.00
-

80 mm dia. DI Doub 2,850.00


769.50
17,000.00
2,600.00
23,219.50
-

80mm dia. DI 900 short radius Flanged Bend. 80mm dia.


4,635.00 Flanged
727.00 Sluice Valve
389.00 ( Whe
105.03
5,856.03
-

( Consider 1m ) 280 mmPipes.


dia. T-600 PVC
Supply Cost 6,695.65
15% 1,004.35
Total Supply Cost 7,700.00
Rubber Rings 86.83
General Clearance
Excavation -
Disposal Excavated Material
Laying 652.00
Flushing & Disinfection 83.00
Pressure Testing. 56.00
Backfilling (Selected Excavated Material)
Dewatering -
Earth Work Support -
Trial Holes
Total Cost 791.00
Add 27% Overheads & Profits 213.57
1,004.57
Add 6% for 2019 60.27
Supplying & Laying Cost8,765.00
Tees 31

From NWSDB Book 280x160 (300x150)


Supply 29,104.08
20% 5,820.82
Total Supply Cost 34,924.90
Laying 1,900.00
Rubber rings 963.88
thrust block 2,050.00
lubricants 50.00
Total 4,963.88
27% 1,340.25
6,304.13

41,229.00
41,230.00

27,569.01 23,973.05 3,904.41 2,342.64 26


13,243.01 11,515.66 1,872.47 1,123.48
8,916.01 7,753.05 1,266.84 760.10
2968 2,580.87 421.71 253.03

14,160.50 14,160.50

15,367.00 15,367.00

15,398.75 15,398.75

17,653.00 17,653.00

19,621.50 19,621.50
19,621.50 19,621.50

63mm
471.39
70.71
542.10
8.50
-
206.00
-
165.00
12.00
16.00

6.00
92.85
-
506.35
136.71
643.06

1,185.00

46

20,000.00
2,378.40
1,300.00
351.00
24,029.40
-
250x250 mm All Flanged Tee
Supply Cost 33,934.00
CIF Value 26,615.00
Custom Duty 5,988.00
32,603.00
13.80% 4,499.21
New Supply Cost 38,433.21
CIF Value 26,615.00
20% 26,615.00 5,323.00
Total Supply Cost including O & P 43,756.21
Laying 2,264.00 2,875.28
others 514.45 1,543.36
5,419.44 16,258.33
2,500.00 7,500.00
71,933.19

250x150 mm All Flanged Tee


Supply Cost 25,744.00
CIF Value 20,191.00
Custom Duty 4,543.00
24,734.00
13.80% 3,413.29
New Supply Cost 29,157.29
CIF Value 20,191.00
20% 20,191.00 4,038.20
Total Supply Cost including O & P 33,195.49
Laying 2,031.00 2,579.37
others 514.45 1,028.91
5,419.44 10,838.89
2,500.00 7,500.00
362.26 362.26
2,537.76 2,537.76
58,042.68

250 mm Dia. D/ F Pipe 3000 mm long


Supply Cost 44,500.00
CIF Value 34,000.00
Custom Duty 7,500.00
41,500.00
13.80% 5,727.00
New Supply Cost 50,227.00
CIF Value 34,000.00
20% 34,000.00 6,800.00
Total Supply Cost including O & P 57,027.00

Laying 2,850.00
2,850.00 2,850.00
27% 769.50
Total Laying Cost including O & P 3,619.50
Rate Per 1nr 60,647.00
3000 mm long 60,647.00

2100 mm long 42,452.90


250 x 250 mm DI All Flanged Tee. 33

From NWSDB Book 250x250


Supply 79,140.00
20% 5,323.00
Total Supply Cost 84,463.00 Total Supply Cost
Laying 1,900.00
Rubber rings 963.88
thrust block 2,050.00
lubricants 50.00
Total 4,963.88
27% 1,340.25
6,304.13

90,767.00

PVC Pipe Laying


Item 02 - PNT7
( Consider 1m ) 63mm
Supply Cost 253.03
20% 50.61
Total Supply Cost 303.64

Rubber Rings 9.27


Excavation 206.00
Disposal Excavated Material
Laying 165.00
Flushing & Disinfection 12.00
Pressure Testing. 16.00
Backfilling (Selected Excavated Material)
Dewatering 6.00
Earth Work Support 92.85
Trial Holes

Total Cost 507.12

Add 27% Overheads & Profits 136.92


644.04

Supplying & Laying Cost 948.00


1450mm 1,374.60
add 1000
2,374.60
2,375.00

250mm dia. DI 900 Short Radius Flanged Bend.


( Consider 1m ) 250
Supply Cost 24,724.41
20% of CIF 3,424.40
Total Supply Cost 28,148.81
Rubber Rings 596.83
20% of CIF 119.40
Gasket 600.00
20% 120.00
Nut & Bolts 2,760.00
20% 552.00
4,748.23

32,897.04
Laying 1,937.00
Trust Blocks 2,609.00
Polythene Sleeving 173.00
Lubricants -
Total Cost 4,719.00
Add 27% Overheads & Profits 1,274.13
5,993.13

861.88
Supplying & Laying Cost 33,759.00

80 mm dia. DI Flanged & Plain ended Pipe 1350 mm long


with Puddle Flanged 150 mm away from Plain end.
Item 07 - DI D/F Pipes 20,000.00
( Consider 1m ) 80mm
Supply Cost 20,000.00
20% 4,000.00
Total Supply Cost 24,000.00
Rubber Rings 489.27
20% of CIF 67.80
Gasket 142.70
20% of CIF 19.80
Nut & Bolts 661.42
20% of CIF 91.60
1,472.59
Laying 625.00
Flushing & Disinfection 14.00
Pressure Testing. 18.00
Polythene Sleeving 32.40
Lubricants 100.00
Total Cost 789.40
Add 27% Overheads & Profits 213.14
1,791.94
Supplying & Laying Cost 27,265.00

80 mm dia. DI Flanged & Plain ended Pipe 1350 mm long


with Puddle Flanged 150 mm away from Plain end.
Item 07 - DI D/F Pipes
( Consider 1m ) 80mm
Supply Cost 48,500.00
20% 9,700.00
Total Supply Cost 58,200.00
Rubber Rings 489.27
20% of CIF 67.80
Gasket 142.70
20% of CIF 19.80
Nut & Bolts 661.42
20% of CIF 91.60
1,472.59
Laying 625.00
Flushing & Disinfection 14.00
Pressure Testing. 18.00
Polythene Sleeving 32.40
Lubricants 100.00
Total Cost 789.40
Add 27% Overheads & Profits 213.14
1,791.94
Supplying & Laying Cost 61,465.00

80 mm Dia. D/ F Pipe 4000 mm long


Supply Cost 17,000.00
CIF Value 13,000.00
Custom Duty 3,000.00
16,000.00
13.80% 2,208.00
New Supply Cost 19,208.00
CIF Value 13,000.00
20% 13,000.00 2,600.00
Total Supply Cost including O & P 21,808.00

Laying 2,000.00
2,000.00 2,000.00
27% 540.00
Total Laying Cost including O & P 2,540.00
Rate Per 1nr 24,348.00
80 mm Dia. F/ plain ended Pipe 1350 mm long with puddle
Supply Cost 6,000.00
CIF Value 4,500.00
Custom Duty 1,000.00
5,500.00
13.80% 759.00
New Supply Cost 6,759.00
CIF Value 4,500.00
20% 4,500.00 900.00
Total Supply Cost including O & P 7,659.00

Laying 2,000.00
Allow for puddle 3,000.00
5,000.00 5,000.00
27% 1,350.00
Total Laying Cost including O & P 6,350.00
Rate Per 1nr 14,009.00
250 x 150 mm DI All Flanged Tee. 39 280mm dia. PVC 450 Socketed Bend.
PVC 450
From NWSDB Boo250x150 Supply 14,332.41
Supply 29,157.29 20% 2,866.48
20% 4,038.20 Total Supply Cost 17,198.89
Total Supply Cost 33,195.49 Laying 627.00
Laying 1,900.00 Rubber rings 521.00
Rubber rings 963.88 thrust block 2,609.00
thrust block 2,050.00 lubricants -
lubricants 50.00 Total 3,757.00
Total 4,963.88 27% 1,014.39
27% 1,340.25 4,771.39
6,304.13 4,771.39
21,970.00
39,500.00
PVC Pipe Laying
PNT11 PNT7
( Consider 1m ) 160mm 280mm 280mm
Table B- PVC/1 Supply Cost 1,315.00 3,872.00 2,506.00
Add 9% of supply cost
According to 9% 118.35 348.48 225.54
NWSDB Circular New Supply Cost 1,433.35 4,220.48 2,731.54
Add 20% of new supply cost as handling, O&P
20% 286.67 844.10 546.31
Total Supply Cost including O. & P. 1,720.02 5,064.58 3,277.85

Table B- PVC/4 Excavation 333.00 592.00 592.00


Table B- PVC/1 Laying 269.00 478.00 478.00
Table B- PVC/7 Flushing & Disinfection 27.00 56.00 56.00
Table B- PVC/7 Pressure Testing. 39.00 83.00 83.00
Table B- PVC/6 Dewatering(Allow 5%) 9.35 15.30 15.30
Table B- PVC/5 Earth Work Support(Allow 5%) 89.65 97.15 97.15
Total Cost 767.00 1,321.45 1,321.45
Add 27% Overheads & Profits 207.09 356.79 356.79
974.09 1,678.24 1,678.24

Supplying & Laying Cost 2,694.00 6,743.00 4,956.00

24 DI Tees
( Consider 1nr ) 280x160
Table B- PVC/2 250X150 Soakted T 21,413.93 21,413.93 2,045.97
250mm Flange Adaptor 2nrs 18,020.13 36,040.25 1,554.48
150mm Flange Adaptor 1nrs 9,679.99 9,679.99 523.24

Total Supply Cost including O. & P. -

Table B- PVC/2 Laying 723.00


Table B- COM/4 Thrust block 5,050.00
Lubricants 50.00
Total 5,823.00
27% #VALUE!
#VALUE!
#VALUE!

4 PVC Bends 280 mm Dia.


( Consider 1nr ) 90 0 45 0
Table B- PVC/2 Supply Cost 13,149.00 13,149.00
Add 9% of supply cost
According to 9% 1,183.41 1,183.41
NWSDB Circular New Supply Cost 14,332.41 14,332.41
Add 20% of new supply cost as handling, O&P
20% 2,866.48 2,866.48
Total Supply Cost including O. & P. 17,198.89 17,198.89

Table B- PVC/2 Laying 627.00 627.00


Table B- COM/4 Thrust block 4,659.00 4,659.00
Lubricants 50.00 50.00
Total 5,336.00 5,336.00
27% 1,440.72 1,440.72
6,776.72 6,776.72
23,976.00 23,976.00

1 PNT11
( Consider 1m ) 225mm
Table B- PVC/1 Supply Cost 2,587.00
Add 9% of supply cost
According to 9% 232.83
NWSDB Circular New Supply Cost 2,819.83
Add 20% of new supply cost as handling, O&P
20% 563.97
Total Supply Cost including O. & P. 3,383.80

Table B- PVC/4 Excavation 430.00


Table B- PVC/1 Laying 347.00
Table B- PVC/7 Flushing & Disinfection 41.00
Table B- PVC/7 Pressure Testing. 60.00
Table B- PVC/6 Dewatering(Allow 5%) 11.70
Table B- PVC/5 Earth Work Support(Allow 5%) 97.15
Total Cost 986.85
Add 27% Overheads & Profits 266.45
1,253.30

Supplying & Laying Cost 4,637.00

46 80mm dia. Flanged Sluice Valve


Supply Cost 13,700.00
CIF Value 11,892.00
Custom Duty 892.00
12,784.00
13.80% 1,764.19
New Supply Cost 15,464.19
CIF Value 11,892.00
20% 11,892.00 2,378.40
Total Supply Cost including O & P 17,842.59
Laying 1300 1651
2/Flange adaptor -
Denso 5000
22,843.00
23,459.90
37,594.73
10,203.23
71,257.86
71,258.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Length Constant Depth Previous Bill Bill Quantity

Site Clearance
Clearing site, including removal of bushes,
1 scrub, shrubs and under growth Hedges.
Rate to include for removing debris from
site m2 1.00 10.00 10.00 100.00
100.00 - 100.00

Earth Works
2 Excavation for Basement, Trenches and the
like commencing from existing ground level,
in any material other than rock including
compacting bottom of excavation

2.1 Depth not exceeding 1.0 m m3 1.00 3.140 6.250 1.000 19.63
19.63 - 19.63

2.2 Depth exceeding 1.0 m but not exceeding


2.0 m
m3 1.00 3.140 4.200 1.000 13.19
13.19 - 13.19

2.3 Depth exceeding 2.0 m but not exceeding 3.0


m
m3 1.00 3.140 4.200 0.500 6.60
CUMULATIVE QTY 6.60 6.60
BOQ QTY 2.00 - 2.00
EXCESS QTY 4.60 4.60

Concrete Woks (Formwork and


Reinforcement Measured separately)
5 50 mm thick Grade 15 screed Concrete
under the Filter and the Filter Channel m2 1.00 3.14 2.05 2.05 13.19
m2 1.00 13.66 0.50 6.83
20.02 - 20.02

Grade 25 reinforced concrete in filter base,


base slab of channel, ring beam and
6 manifold m3 1.00 4.20 3.14 0.25 3.30
m3 1.00 13.56 0.82 0.30 2.51 75%
5.81 - 5.81

Formwork
7
Rough finished Formwork in filter base,
channel base, manifold and ring beam m2 1.00 12.87 0.25 3.22
m2 1.00 16.13 0.30 4.85
1.00 10.99 0.30 3.30
11.36 - 11.36

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Length Constant Depth Previous Bill Bill Quantity

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Reinforcement
8 Tor Steel bars, supplied, cut to length, bent
to shape, laid in position and tied with GI
wire
Kg 187.32
256.70
55.68
499.70 - 499.70

9 6 mm dia, Mild steel bars, Supplied, cut to


length, bent to shape, laid in position and
tied with GI wire in filter tank walls and in
the ring beam
Kg 16.45
45.85
62.30 - 62.30

10 4 mm dia. GI wire in filter tank walls tied


with GI binding wire (40 mm spacing shall
be kept as per the drawing)
Kg 85.00
85.00 - 85.00

Supply & fixing of SWG 18 No. 04 GI wire


mesh, Supplied, cut to length, bent to shape,
laid in position in vertical Ferro cement
tank walls and at places where it is
connecting the base slab and walls (Rate to
include for lap length)
11 m2 1.00 16.14 0.90 14.53
m2 1.00 12.56 0.90 11.31
m2 1.00 10.99 0.90 9.89
m2 2.00 16.33 1.80 58.78
m2 1.00 10.99 1.30 14.29
CUMULATIVE QTY 108.80 108.80
BOQ QTY 80.00 - 80.00
EXCESS QTY 28.80 28.80

12 Supplying & fixing of Chicken mesh in 225


mm walls and bottom of the channel
(embedded in the concrete) for Ferro
Cement plaster (Rate to include for lap
length)
m2 1.00 12.49 1.15 14.37
14.37 - 14.37

Masonry Work/ Ferro Cement Works

225 mm thick Brick Work in 1:5 Cement


14 Sand mortar for Walls m2 2.00 1.85 3.14 1.15 13.32
m2 1.00 11.87 0.30 3.56
16.88 - 16.88

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Length Constant Depth Previous Bill Bill Quantity

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

25 mm thick Ferro cement plastering in 1:3


Cement Sand mortar, finished smooth with
cement float (1:16 cement & Pudlo cement
shall be used) in Internal & External Brick
walls of filters. All as per the drawing no.
15 NWP-AF-WS-CKD-15/KGW/WTP-12(ii) m2 2.00 1.99 3.14 1.15 14.37
m2 1.00 6.28 1.75 2.13 23.45
37.82 - 37.82

16 25 mm thick Ferro Cement Plastering in 1:3


Cement Sand mortar, finished smooth with
cement float in Internal & External walls and
bottom of the channel (1:16 cement & Pudlo
cement shall be used. Additional quantity to
be considered for forming up the 75 mm
thick top edge)
m2 2.00 16.33 1.80 58.78
58.78 - 58.78

20 Apply two coats of Bituminous Paint on the


external faces up to ground level
m2 2.00 1.99 3.14 1.15 14.37
14.37 - 14.37
PIPE WORKS
Inlet Pipe

280 mm Dia. PVC (PNT11) Socket & Spigot


22 Pipe m 0.40
0.40 - 0.40

Filtered Water Outlet Pipes & Back Wash


pipes
28 250 mm dia. DI Flanged & Plain Ended Pipe
350 mm long with Puddle Flange 150 mm
away from Plain End
nos 1.00
1.00 - 1.00

29 250 mm dia. DI 900 Short Radius Flanged


Bend
nos 1.00
1.00 - 1.00

30 250 mm dia. DI Flanged Pipe 3,000 mm long


nos 1.00
1.00 - 1.00

Filtered Water Outlet Pipes & Back Wash


pipes
38 280 mm dia. PVC 900 Socketed Bend
nr 1.00
1.00 - 1.00
Air Pipe
47 80 mm dia. DI Double Flanged Pipe
approximately 4,000 mm long nr 1.00
1.00 - 1.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 06: CONSTRUCTION OF RAPID SAND FILTER
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Length Constant Depth Previous Bill Bill Quantity

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
CONSTRUCTION OF RAPID SAND FILTER
BAR SCHEDULE
Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 10
Period Up to :- 31st July 2021
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 10th August 2021

No.Of Total Length of


Item Bar Type & Size Space No.Of Length of each mm each Total length Weight per Weight (kg) Shape & Demension
Mark mem: bars in No. m
each A B C mm m

FILTER WALL
(BRICK)
17 T 10 1.0 38.0 38.0 2375.0 2375.0 90.25 0.617 55.68

FERRO CEMENT
WALL
29 R 6 1.0 81.0 81.0 2550.0 2550.0 206.55 0.222 45.85

31 4mm Dia
GI Wire
1.0 50.0 50.0 16328.0 16328.0 816.40 0.104 85.00

Total Carried To Summary 186.53

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the Contract Certified & Recommanded as per
the Contractor
Pura Neguma - Local Government Enhancement Sector Project
CONSTRUCTION OF RAPID SAND FILTER
BAR SCHEDULE
Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 10
Period Up to :- 31st July 2021
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 10th August 2021

No.Of Total Length of


Item Bar Type & Size Space No.Of Length of each mm each Total length Weight per Weight (kg) Shape & Demension
Mark mem: bars in No. m
each A B C mm m
………………….………………… …………………………………………………. ………………………………………………… ...…….…………………………………………. ……………………………………………….
Contractor Technical officer of Consultant/RDC Asst . QS RDC Asst . QS SPCU Senior Engineer/Compliance Officer SPCU
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Site Clearance
1 Clearing site, including removal of bushes,
scrub, shrubs and under growth hedges. Rate to
include removal of debris from site and
deposited at the direction of Engineer with in
the site boundaries at suitable places not
disturbing to surface drainage.
m2 400.00 73.00 29,200.00 400.00 29,200.00 - 400.00 29,200.00
Excavation & Earth Work - - - -
2 Excavation for Base, Trenches and the like,
commencing from existing ground level, in any
material other than rock including compacting
bottom of excavation
- - - -
2.1 Depth not exceeding 1.0 m m3 230.00 1,065.00 244,950.00 221.94 236,366.10 - 221.94 236,366.10
2.2 Depth exceeding 1.0 m but not exceeding 2.0 m m3 230.00 1,145.00 263,350.00 221.94 254,121.30 - 221.94 254,121.30
2.3 Depth exceeding 2.0 m but not exceeding 3.0 m m3 230.00 1,260.00 289,800.00 221.94 279,644.40 - 221.94 279,644.40
2.4 Depth exceeding 3.0 m but not exceeding 4.0 m m3 50.00 1,260.00 63,000.00 50.00 63,000.00 - 50.00 63,000.00
- -
Excavation in Rock -
3 Extra-over excavation for above item no. 2 for
soft rock (Provisional Quantity)(No blasting
required) m3 15.00 4,725.00 70,875.00
4 Extra-over excavation for above items no. 2 & 3
for hard rock, (Provisional Quantity)
(Controlled blasting) m3 5.00 18,900.00 94,500.00
TOTAL CARRIED FORWARD 1,055,675.00 862,331.80 - 862,331.80

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 1,055,675.00 862,331.80 862,331.80
Earth Filling - - - -
5 Back filling around the structure with selected
excavated material (other than top soil or rock)
to 95% compaction as directed by the Engineer
(Compaction reports should be provided)

m3 85.00 830.00 70,550.00 85.00 70,550.00 - 85.00 70,550.00


- -
Concrete Work - - - -
Provision and Placing of Concrete Grade 20 - - - -
6 In screed for Bed of Sump & Chamber with
thickness not exceeding 100 mm m3 18.00 17,941.00 322,938.00 18.00 322,938.00 - 18.00 322,938.00
Provision and Placing of Concrete Grade 25
7 In Base of Chambers with thickness exceeding
150 mm but not exceeding 300 mm
m3 1.00 19,469.00 19,469.00 -
8 In Walls of Valve Chambers with thickness not
exceeding 150 mm and height not exceeding 3.0
m m3 2.00 19,994.00 39,988.00
9 Reinforced Concrete Column 150x 150 mm
in section to fix water level indicator as per the
drawing. Rate to include for reinforcing with 4
nos 12 mm dia. Tor steel bars and 6 mm MS
stirrups at 150 mm centers and necessary
formwork
m3 0.10 84,000.00 8,400.00
TOTAL CARRIED FORWARD 1,517,020.00 1,255,819.80 - 1,255,819.80

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 1,517,020.00 1,255,819.80 - 1,255,819.80


Provision and Placing of Concrete Grade 35
A (Ready-mix Concrete)
10 In Base of Sump with thickness exceeding 150
mm but not exceeding 300 mm m3 68.00 21,893.00 1,488,724.00 67.61 1,480,185.73 - 67.61 1,480,185.73
11 In Walls of Main Structure with thickness
exceeding 150 mm but not exceeding 300 mm
and maximum height not exceeding 4.0 m
m3 97.00 21,893.00 2,123,621.00 84.54 1,850,834.22 - 84.54 1,850,834.22
12 In Roof Slab of Main Structure Opening with
thickness not exceeding 150 mm m3 33.00 21,893.00 722,469.00 30.28 662,920.04 - 30.28 662,920.04
13 In Upstanding Projections on cover slab &
manhole openings with thickness not
exceeding 100 mm (Kerb Wall)
m3 0.50 23,993.00 11,996.50 0.50 11,996.50 - 0.50 11,996.50
- -
Masonry Work/ Ferro Cement Works - -
14 1400 x 350 x100 mm Pre-Cast Cover Slab
reinforced with 10 mm dia. Tor steel rods at
200 mm centers both way, 2 nos 12 mm dia.
Mild steel lifting handles shall be provided as
per given in detail drawings
nr 4 2,753.00 11,012.00 -
Reinforcement - -
15 10 mm dia, 12 mm dia, 16 mm dia. (including in
Valve Chambers) mt 22.0 168,587.00 3,708,914.00 21.78 3,671,824.86 - 21.78 3,671,824.86
TOTAL CARRIED FORWARD 9,583,756.50 8,933,581.15 - 8,933,581.15

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 9,583,756.50 8,933,581.15 - 8,933,581.15


Formwork -
16 Screed concrete for Valve Chamber & Reservoir
with height not exceeding 100 mm m2 6.00 1,295.00 7,770.00 4.82 6,241.90 - 4.82 6,241.90
17 For sides of Main Structure Base & Valve
Chamber with height not exceeding 300 mm m2 20.00 1,295.00 25,900.00 18.07 23,400.65 - 18.07 23,400.65
18 For sides of external faces of valve chamber
walls m2 15.00 1,295.00 19,425.00
19 For 100 mm high wall kickers of main
structures(External) m2 65.00 1,295.00 84,175.00 20.04 25,951.80 - 20.04 25,951.80
20 For 100 mm high wall kickers of Valve
Chambers (External) m2 7.00 1,295.00 9,065.00
Wrought
21 For sides of main structure walls (both sides)
up to soffit of Roof slab, including Baffle walls m2 750.00 1,295.00 971,250.00 636.26 823,956.70 - 636.26 823,956.70
22 For sides of internal faces of valve chamber
walls m2 12.00 1,295.00 15,540.00 - -
23 For soffit of 150 mm thick roof slab; maximum
height of 3.1 m from the base slab level
m2 225.00 1,295.00 291,375.00 195.12 252,680.40 - 195.12 252,680.40
24 For sides of roof slab edges with height not
exceeding 250 mm m2 20.00 1,295.00 25,900.00 8.61 11,149.95 - 8.61 11,149.95
TOTAL CARRIED FORWARD 11,034,156.50 10,076,962.55 - 10,076,962.55

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 11,034,156.50 10,076,962.55 - 10,076,962.55


25 For 150 mm wide sides of column on top of
reservoir m2 6.00 1,295.00 7,770.00
26 For sides of slab projections for manhole
opening m2 6.00 1,295.00 7,770.00 6.00 7,770.00 - 6.00 7,770.00
- -
27 Forming 50 x 75 mm rebate on chamber walls
to receive cover slabs m 6.00 130.00 780.00
28 Forming 75 mm high internal sides of
upstanding on cover slab m 60.00 130.00 7,800.00
Extra over Formwork for forming openings
for the following -
29 For passing 200 mm dia. Pipe through 300 mm
thick wall nr 1 4,200.00 4,200.00
30 For passing 150 mm dia. Pipe through 300 mm
thick wall nr 5 3,675.00 18,375.00
31 For passing 100 mm dia. Pipe through 300 mm
thick wall nr 2 3,150.00 6,300.00
32 For passing 150 mm dia. Pipe through 150 mm
thick wall (In Valve Chamber) nr 1 3,150.00 3,150.00
Miscellaneous -
PVC Coated Rungs -
33 Supply & fixing of 16 mm dia. non slip PVC
coated (MS rung Steps) at 325 mm centers.
Rungs shall be fixed to concrete wall as shown
in detail drawing
nr 20 2,625.00 52,500.00 10.00 26,250.00 - 10.00 26,250.00
TOTAL CARRIED FORWARD 11,142,801.50 10,110,982.55 - 10,110,982.55

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 11,142,801.50 10,110,982.55 - 10,110,982.55


GI Ventilator -
34
Ventilator assembled out of 50 mm dia. Heavy
Duty GI pipes and fittings having 200 mm long
GI pipe jointed to 900 mm Long radius bend with
GI socket and with GI fine mesh fixed at outer
end between 2 nrs, Screwed flanges bolted
together. This assembly shall be embedded in
concrete cover slab with GI welded Puddle
flange all complete as shown in detail on
drawing
nr 4 15,750.00 63,000.00 4.00 63,000.00 4.00 63,000.00
Manhole Cover
35 Supply & fixing of 750 x 750 x 6 mm thick
Aluminium Chequered Plate including 75 x 75x
6 mm Heavily Galvanized Angle Frame, fixed to
concrete using Rag Bolts. Rate to include for
locking arrangement & lifting handles as shown
in the drawing No. NWP-AF-WS-CKD-15/KGW- nr 3 15,750.00 47,250.00
36 WTP-9
Supply (V)
& fixing of 1150 x 900 x 6 mm thick
Aluminium Chequered Plate including 75 x 75x
6 mm Heavily Galvanized Angle Frame, fixed to
concrete using Rag Bolts. Rate to include for
locking arrangement & lifting handles as shown
in the drawing No. NWP-AF-WS-CKD-15/KGW- nr 2 18,900.00 37,800.00
WTP-9 (V)
TOTAL CARRIED FORWARD 11,290,851.50 10,173,982.55 - 10,173,982.55

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 11,290,851.50 10,173,982.55 - 10,173,982.55


Pipe Bracket -
37 75 x 75 mm angle iron pipe bracket including
50 x 6 mm strap, bent to suit for pipe and fix "L"
iron with 20 mm dia. Nuts and bolts nr 6 1,575.00 9,450.00
38 1:5 Cement mortar on top of cover slab sloped
from center as directed m2 220.00 905.00 199,100.00
39 Applying two coats of bitumen layer and filling
20-40 mm size white pebbles on cover slab
m3 88.00 9,216.00 811,008.00
40 10 mm thick Bitumen layer between roof slab
and wall and blinded with sand m2 25.00 3,150.00 78,750.00 25.00 78,750.00 25.00 78,750.00
- -
41 Applying non toxic water proofing (Approved
by the Engineer) on internal wall including m2 485.00 1,575.00 763,875.00 485.00 763,875.00 485.00 763,875.00
bottom of ground reservoir
- -
42 Apply two coats of Bituminous Paint on the
external surfaces of ground reservoir &
Chamber including base, up to floor level
m2 245.00 1,260.00 308,700.00 213.14 268,556.40 213.14 268,556.40
Pipe Work -
Outlet -
43
150 mm dia. DI Double Flanged approximately
500 mm long pipe with Puddle Flange at center
nr 4 30,765.00 123,060.00
44 150 mm dia. DI Double Flanged long Radius
Bend nr 4 25,469.00 101,876.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
45 150 mm dia. DI Double Flanged approximately
1,500 mm long pipe with Puddle Flange at
center nr 4 40,782.00 163,128.00
TOTAL CARRIED FORWARD 13,849,798.50 - 11,285,163.95

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 13,849,798.50 - 11,285,163.95
46 150 mm dia. Foot Valve nr 4 75,759.00 303,036.00
47 100 mm dia. DI Double Flanged approximately
500 mm long pipe with Puddle Flange at center nr 2 23,497.00 46,994.00
48 100 mm dia. DI Double Flanged long Radius
Bend nr 2 28,762.00 57,524.00
49 150 mm dia. DI Double Flanged approximately
1,500 mm long pipe with Puddle Flange at
center nr 2 40,311.00 80,622.00
50 100 mm dia. Foot Valve nr 2 109,162.00 218,324.00
Inlet -
51 200 mm dia. DI Double Flanged pipe
approximately 600 mm long with Puddle Flange
nr 1 42,868.00 42,868.00 1.00 42,868.00 - 1.00 42,868.00
52 200 mm dia. DI Double Flanged 900 Long Radius
Bend
nr 2 74,267.00 148,534.00
53 200 mm dia. DI Double Flanged approximately
500 mm long pipe nr 1 34,208.00 34,208.00
54 200 mm dia. VJFA nr 1 22,907.00 22,907.00
55 200 mm dia. DI Flange & Plain Ended pipe 1,750
mm long nr 1 39,690.00 39,690.00
56 200 mm dia. DI Flange & Plain Ended pipe 1,000
mm long nr 1 29,435.00 29,435.00
TOTAL CARRIED FORWARD 14,873,940.50 42,868.00 - 11,328,031.95

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… . ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 07: CONSTRUCTION OF 450m3 CAPACITY GROUND RESERVOIR AT WATER TRATMENT PLANT AT KARUWALAGASWEWA

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 14,873,940.50 42,868.00 - 11,328,031.95


Overflow -
57 150 mm dia. DI D/F 900 Short Radius Bend
nr 2 28,169.00 56,338.00
58 150 mm dia. DI D/F Pipe (500 mm long)
nr 1 25,830.00 25,830.00
59 150 mm dia. DI Flange & Plain Ended 600 mm
long pipe with puddle Flange at 150 mm from
Plain End
nr 1 23,720.00 23,720.00 1.00 23,720.00 - 1.00 23,720.00
60 150 mm dia. DI Flange & Plain Ended 800 mm
long pipe with puddle Flange at 100 mm from
Plain End
nr 1 25,442.00 25,442.00

Total Carried Over to Summary … 15,005,270.50 66,588.00 - 11,351,751.95

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
450m3 CAPACITY GROUND RESERVOIR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Qty up to Qty for Total
No Previous Bill This Bill Quantity
Length Width Depth

Site Clearance

Clearing site, including removal of bushes,


scrub, shrubs and under growth hedges. Rate to
include removal of debris from site and
deposited at the direction of Engineer with in
the site boundaries at suitable places not
1 disturbing to surface drainage. m2 20.00 20.00 400.00
400.00 - 400.00
Excavation & Earth Work
2 Excavation for Base, Trenches and the like,
commencing from existing ground level, in any
material other than rock including compacting
bottom of excavation

2.1 Depth not exceeding 1.0 m m3 16.20 13.70 1.00 221.94


221.94 - 221.94

2.2 Depth exceeding 1.0 m but not exceeding 2.0 m m3 16.20 13.70 1.00 221.94
221.94 - 221.94

2.3 Depth exceeding 2.0 m but not exceeding 3.0 m m3 16.20 13.70 1.00 221.94
221.94 - 221.94

2.4 Depth exceeding 3.0 m but not exceeding 4.0 m


m3 16.20 13.70 0.20 44.39
m3 2.40 13.70 0.60 19.73
CUMULATIVE QTY 64.12 64.12
BOQ QTY 50.00 - 50.00
EXCESS QTY 14.12 14.12
Earth Filling
5 Back filling around the structure with selected
excavated material (other than top soil or rock)
to 95% compaction as directed by the Engineer
(Compaction reports should be provided)

m3 1.00 61.40 1.00 3.00 138.15 75%


CUMULATIVE QTY 138.15 138.15
BOQ QTY 85.00 - 85.00
EXCESS QTY 53.15 53.15
Concrete Work
Provision and Placing of Concrete Grade 20
In screed for Bed of Sump & Chamber with
6 thickness not exceeding 100 mm m3 16.42 13.70 0.08 18.00
18.00 - 18.00

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
450m3 CAPACITY GROUND RESERVOIR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Qty up to Qty for Total
No Previous Bill This Bill Quantity
Length Width Depth
…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Provision and Placing of Concrete Grade 35
A (Ready-mix Concrete)

10 In Base of Sump with thickness exceeding 150


mm but not exceeding 300 mm m3 13.70 2.10 0.30 8.63
13.70 0.85 0.30 3.49
13.70 13.50 0.30 55.49
67.61 - 67.61
In Walls of Main Structure with thickness
11 exceeding 150 mm but not exceeding 300 mm
and maximum height not exceeding 4.0 m
m3 4.00 11.00 0.20 0.10 0.88
4.00 11.00 0.45 0.30 5.94
4.00 0.16 0.10 0.06
4.00 0.20 0.30 0.24
2.00 0.20 0.22 12.90 1.15
0.20 0.22 12.20 0.54
2.00 0.40 0.30 13.20 3.17
0.40 0.30 12.80 1.50
2.00 0.20 0.22 1.50 0.13
0.20 0.22 12.50 0.56
2.00 0.30 1.50 1.10 0.99
1.10 0.30 0.60 0.20
0.30 1.10 13.10 4.32
2.00 0.750 0.225 0.200 0.07
4.00 11.00 0.20 2.20 19.36
1.00 56.20 0.30 2.20 37.09
4.0 11.00 0.20 0.33 2.86
1.0 56.20 0.30 0.33 5.48
84.54 - 84.54

Concrete Work
Provision and Placing of Concrete Grade 35
A (Ready-mix Concrete)
12 In Roof Slab of Main Structure Opening with
thickness not exceeding 150 mm m3 1.00 15.60 13.10 0.15 30.65
m3 1.00 1.00 1.20 0.15 (0.18)
m3 8.00 0.40 0.40 0.15 (0.19)
30.28 - 30.28

Provision and Placing of Concrete Grade 35


A (Ready-mix Concrete)
13 In Upstanding Projections on cover slab &
manhole openings with thickness not
exceeding 100 mm (Kerb Wall)
m3 1.00 79.00 0.15 0.10 1.19
CUMULATIVE QTY 1.19 1.19
BOQ QTY 0.50 - 0.50
EXCESS QTY 0.69 0.69

Reinforcement
Tor steel Reinforcement cut to length, bent
to shape, placed in position and tied with GI
15 wire.
10 mm dia, 12 mm dia, 16 mm dia. (including in
Valve Chambers) mt 15.020
mt 4.220
mt 2.400
mt 0.140
21.780 - 21.78

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
450m3 CAPACITY GROUND RESERVOIR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Qty up to Qty for Total
No Previous Bill This Bill Quantity
Length Width Depth

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Formwork
Screed concrete for Valve Chamber & Reservoir 2 16.42 0.08 2.63
16 m2
with height not exceeding 100 mm 2 13.70 0.08 2.19
4.82 - 4.82

For sides of Main Structure Base & Valve 2 16.42 0.30 9.85
17 Chamber with height not exceeding 300 mm m2
2 13.70 0.30 8.22
18.07 - 18.07

19 For 100 mm high wall kickers of main


structures(External) m2 1.00 57.40 0.10 5.74
m2
1.00 55.00 0.10 5.50
m2 8.00 11.00 0.10 8.80
20.04 - 20.04

Wrought
21 For sides of main structure walls (both sides)
up to soffit of Roof slab, including Baffle walls
m2 8.00 11.00 0.10 8.80
m2 8.00 11.00 0.40 35.20
m2 4.00 0.40 0.22 0.36
m2 4.00 0.20 0.50 0.40
m2 4.00 0.30 0.40 4.00 0.48
m2 0.90 13.10 11.79
m2 2.00 0.40 13.20 10.56
m2 0.40 13.10 5.24
m2 4.00 0.20 0.10 (0.08)
m2 4.00 0.95 0.30 0.50 (0.57)
m2 2.00 12.60 0.50 12.60
m2 0.50 12.50 6.25
m2 1.10 13.10 14.41
m2 12.50 0.80 10.00
m2 2.00 0.50 1.10 0.30 0.66
m2 2.00 2.08 1.10 4.56
m2 2.00 0.50 1.10 0.30 0.66
m2 2.00 1.78 0.80 2.85
m2 2.40 0.40 0.96
m2 24.40 0.40 0.50 4.88
m2 1.00 57.40 2.20 126.28
m2 1.00 55.00 2.20 121.00
m2 8.00 11.00 2.20 193.60
m2 1.00 57.40 0.33 18.66
m2 1.00 55.00 0.33 17.88
m2 8.00 11.00 0.33 28.60
m2 4.00 0.20 0.33 0.26
636.26 - 636.26

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
450m3 CAPACITY GROUND RESERVOIR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Qty up to Qty for Total
No Previous Bill This Bill Quantity
Length Width Depth Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Formwork
23 For soffit of 150 mm thick roof slab; maximum
height of 3.1 m from the base slab level
m2 1.00 15.60 13.10 204.36
m2 2.00 1.00 1.20 (2.40)
m2 8.00 0.40 0.40 (1.28)
m2 4.00 0.20 11.00 (8.80)
m2 8.00 1.60 0.15 1.92
m2 2.00 4.40 0.15 1.32
195.12 - 195.12

For sides of roof slab edges with height not


24 exceeding 250 mm m2 1.00 57.40 0.150 8.61
8.61 - 8.61

26 For sides of slab projections for manhole


opening m2 1.00 149.20 0.15 22.38
CUMULATIVE QTY 22.38 22.38
BOQ QTY 6.00 - 6.00
EXCESS QTY 16.38 16.38

PVC Coated Rungs


Supply & fixing of 16 mm dia. non slip PVC
33 coated (MS rung Steps) at 325 mm centers.
Rungs shall be fixed to concrete wall as shown
in detail drawing nr 3.00 3.00
nr 5.00 5.00
nr 2.00 2.00
10.00 - 10.00
GI Ventilator
34
Ventilator assembled out of 50 mm dia. Heavy
Duty GI pipes and fittings having 200 mm long
GI pipe jointed to 900 mm Long radius bend with
GI socket and with GI fine mesh fixed at outer
end between 2 nrs, Screwed flanges bolted
together. This assembly shall be embedded in
concrete cover slab with GI welded Puddle
flange all complete as shown in detail on
drawing
nr 4.00 4.00
4.00 - 4.00

40 10 mm thick Bitumen layer between roof slab


and wall and blinded with sand m2 1.00 56.20 0.30 16.86
m2 1.00 44.00 0.20 8.80
CUMULATIVE QTY 25.66 25.66
BOQ QTY 25.00 - 25.00
EXCESS QTY 0.66 0.66
Pura Neguma - Local Government Enhancement Sector Project
450m3 CAPACITY GROUND RESERVOIR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Qty up to Qty for Total
No Previous Bill This Bill Quantity
Length Width Depth

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

41 Applying non toxic water proofing (Approved


by the Engineer) on internal wall including
bottom of ground reservoir
m2 1.00 12.440 3.240 40.31
1.00 12.220 0.400 4.89
1.00 12.440 0.100 1.24
1.00 12.000 1.200 14.40
2.00 1.410 0.400 1.13
2.00 0.800 0.340 0.54
1.00 12.000 0.900 10.80
1.00 2.820 0.100 0.28
1.00 2.820 3.240 9.14
1.00 1.160 0.590 0.68
1.00 12.440 0.360 4.48
2.00 10.860 0.100 2.17
2.00 10.860 2.690 58.43
2.00 10.930 0.400 8.74
1.00 0.940 0.920 0.86
4.00 0.530 0.400 0.85
4.00 0.200 2.610 2.09
4.00 0.200 0.100 0.08
1.00 3.635 0.400 1.45
1.00 5.850 0.100 0.59
1.00 5.850 3.240 18.95
1.00 3.980 0.590 2.35
2.00 10.900 2.650 57.77
2.00 10.900 0.100 2.18
2.00 10.965 0.400 8.77
1.00 0.830 0.900 0.75
3.00 12.000 2.660 95.76
1.00 6.830 0.100 0.68
1.00 6.830 2.670 18.24
2.00 11.000 0.100 2.20
2.00 11.000 2.650 58.30
2.00 11.050 0.400 8.84
2.00 0.900 0.870 1.57
1.00 5.820 0.100 0.58
1.00 5.820 2.700 15.71
1.00 5.585 0.400 2.23
2.00 11.000 0.100 2.20
2.00 11.000 2.700 59.40
2.00 11.050 0.400 8.84
1.00 5.850 0.100 0.59
1.00 5.850 2.670 15.62
Pura Neguma - Local Government Enhancement Sector Project
450m3 CAPACITY GROUND RESERVOIR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Qty up to Qty for Total
No Previous Bill This Bill Quantity
Length Width Depth

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… …………………………………………………………


…………………………………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
1.00 5.640 0.400 2.26
1.00 12.000 2.320 27.84
1.00 12.450 0.100 1.25
1.00 12.450 2.680 33.37
1.00 12.225 0.400 4.89
1.00 2.860 0.100 0.29
1.00 2.860 2.680 7.66
1.00 2.590 0.400 1.04
2.00 0.405 0.395 0.32
2.00 0.370 0.275 0.20
2.00 0.530 0.520 0.55
2.00 0.750 0.530 0.80
CUMULATIVE QTY 625.14 625.14
BOQ QTY 485.00 - 485.00
EXCESS QTY 140.14 140.14

42 Apply two coats of Bituminous Paint on the


external surfaces of ground reservoir &
Chamber including base, up to floor level
m2 2.00 2.93 13.16 77.118
2.00 0.66 2.93 3.868
2.00 3.52 1.76 12.387
2.00 0.59 0.50 0.66 0.389
1.00 13.05 2.93 38.237
1.00 13.05 3.51 45.806
1.00 58.89 0.60 35.334
213.14 - 213.14

Pipe Work
Inlet

200 mm dia. DI Double Flanged pipe


51 approximately 600 mm long with Puddle Flange Nos 1.00
1.00 - 1.00

150 mm dia. DI Flange & Plain Ended 600 mm


long pipe with puddle Flange at 150 mm from
59 Plain End Nos 1.00
1.00 - 1.00
Pura Neguma - Local Government Enhancement Sector Project
450m3 CAPACITY GROUND RESERVOIR
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Description Unit Nos Qty up to Qty for Total
No Previous Bill This Bill Quantity
Length Width Depth

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… …………………………………………………………


…………………………………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
450m3 CAPACITY GROUND RESERVOIR
BAR SCHEDULE
Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 09
Period Up to :- 30th June 2021
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 12th July 2021

No.Of Length of
Item Bar Type & Size Space No.Of bars in Total Length of each mm each Total length Weight per Weight (kg) Shape & Demension
Mark mem: each No. m
A B C mm m
Kurb Wall
1A T 10 1.0 527.0 527.0 200.0 200.0 105.40 0.617 65.03

1B T 10 1.0 16.0 16.0 6000.0 6000.0 96.00 0.617 59.23

1B T 10 1.0 4.0 4.0 2020.0 2020.0 8.08 0.617 4.99

1B T 10 1.0 4.0 4.0 4520.0 4520.0 18.08 0.617 11.16

Total Carried To Summary 140.41

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the Contract Certified & Recommanded as per
the Contractor

………………….………………… …………………………………………………. ………………………………………………… ...…….…………………………………………. ……………………………………………….


Pura Neguma - Local Government Enhancement Sector Project
450m3 CAPACITY GROUND RESERVOIR
BAR SCHEDULE
Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 09
Period Up to :- 30th June 2021
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 12th July 2021

No.Of Length of
Item Bar Type & Size Space No.Of bars in Total Length of each mm each Total length Weight per Weight (kg) Shape & Demension
Mark mem: each No. m
A B C mm m
Contractor Technical officer of Consultant/RDC Asst . QS RDC Asst . QS SPCU Senior Engineer/Compliance Officer SPCU
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP HOUSE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
CLASS D - DEMOLITION AND SITE CLEARANCE
Site Preparation

Clearing site, including removal of bushes, scrub,


shrub and undergrowth and grubbing up roots and
cutting down small trees not exceeding 500 mm girth.
1 Rate to include removal of debris from site m2 150.00 73.00 10,950.00 150.00 10,950.00 - 150.00 10,950.00
CLASS E - EXCAVATON & EARTHWORKS -
Excavation for wall foundation, Cable and pipe
duct trench and the like, in any material other
than rock including compacting bottom of
excavation
-
2 Excavating top soil for an average depth of 150 mm m 3
18.0 1,659.00 29,862.00 15.19 25,200.21 - 15.19 25,200.21
3 Excavation for column bases in any material other
than top soil, rock or artificial hard material with
maximum depth not exceeding 1.5 m from existing
ground level
m3 6.6 1,065.00 7,029.00 2.28 2,428.20 - 2.28 2,428.20
4 Excavation for rubble strip foundation in any material
other than top soil, rock or artificial hard material with
maximum depth not exceeding 1.5m from existing
ground level.
m3 8.5 1,065.00 9,052.50 9.54 10,160.10 - 9.54 10,160.10
TOTAL CARRIED FORWARD 56,893.50 48,738.51 - 48,738.51

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP HOUSE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 56,893.50 48,738.51 - 48,738.51
5 Excavation for cable & Pipe duct in dry earth filling
with maximum depth not exceeding 1.5 m
commencing from finished ground level
m3 10.0 1,145.00 11,450.00
Excavation in Soft Rock / Rock -
6 Soft disintegrated rock/boulders (not requiring
blasting) m3 10.00 4,725.00 47,250.00
7 Hard Rock (Controlled Blasting) m3 5.00 13,125.00 65,625.00
Earth Filling -
8 Filling to structures, to make up levels with imported
natural material other than Top soil or Rock, watered
and well compacted to 98% compaction, as directed
by the Engineer (Compaction reports should be
provided)
m3 35.00 2,474.00 86,590.00
CLASS F - IN SITU CONCRETE -
Provision and placing of Concrete Grade 25
(Reinforced concrete) (Rate to include for cube
and slump tests as directed)
-
9 Grade 25 Mass Concrete m3 2.6 18,390.00 47,814.00 0.84 15,447.60 - 0.84 15,447.60
10 Grade 25 Reinforced Concrete m 3
5.6 19,440.00 108,864.00 5.60 108,864.00 - 5.60 108,864.00
- -
TOTAL CARRIED FORWARD 424,486.50 173,050.11 - - 173,050.11

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP HOUSE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 424,486.50 173,050.11 - 173,050.11


CLASS G - CONCRETE ANCILLARIES
Formwork
(Plane Vertical)
11 Masonry Work m2 2.20 1,295.00 2,849.00 2.20 2,849.00 - 2.20 2,849.00
- -
12 To sides of column shafts, with width exceeding 0.2 m
but not exceeding 0.4 m.
m2 8.0 1,295.00 10,360.00 8.00 10,360.00 8.00 10,360.00
- -
13 To sides of base of cable/pipe duct with width
exceeding 0.1 m but not exceeding 0.2 m - - - -
m 33.4 259.00 8,650.60
14 To sides of walls of cable/pipe duct with width
exceeding 0.2 m but not exceeding 0.4 m - - - -
m2 40.1 1,295.00 51,929.50
15 To sides and soffit of lintols m2 1.7 1,295.00 2,201.50 - - - -
Reinforcement - - - - -
Mild steel bar reinforcement cut to length, bent to
shape, placed in position and tied with GI wire - - - -
-
16 6 mm dia kg 49.00 169.00 8,281.00 49.00 8,281.00 49.00 8,281.00
- -
Tor steel bar reinforcement cut to length, bent to
shape, placed in position and tied with GI wire - - - -
-
17 12 mm dia. kg 200.00 169.00 33,800.00 200.00 33,800.00 200.00 33,800.00
- -
18 16 mm dia. kg 300.00 169.00 50,700.00 300.00 50,700.00 300.00 50,700.00
- -
TOTAL CARRIED FORWARD 593,258.10 279,040.11 - 279,040.11

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP HOUSE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP HOUSE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 593,258.10 279,040.11 - - 279,040.11

CLASS U – BRICK WORK, BLOCK WORK AND


MASONRY -
Brick Work -
19 225 mm thick vertical straight, common brick walls in
1:6 cement and sand mortar m2 115.0 3,922.00 451,030.00 115.00 451,030.00 115.00 451,030.00
- -
Brick Steps
20 Brick steps (3 nrs) as shown in the drawing, including
16 mm thick 1:3 cement sand rendering, finished
smooth with approved colour cement floating, as
directed by the Engineer (appr. Size of a step
1,400x250x125 mm)
Item Lump Sum 5,491.50
Rubble work
21 450 mm thick vertical straight, rubble masonry walls
of foundation, in cement and sand 1:5 mortar m2 19.70 5,932.00 116,860.40 19.70 116,860.40 19.70 116,860.40

Damp Proof Course - - -


22 20 mm thick damp proof course on 300 mm wide
rubble foundation in 1:3 cement and sand mortar and
treated with two coats of hot tar blinded with sand - -
m 32.0 1,050.00 33,600.00
TOTAL CARRIED FORWARD 1,200,240.00 846,930.51 - 846,930.51

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP HOUSE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 1,200,240.00 846,930.51 - 846,930.51


CLASS V - PAINTING
23 Prepare surface and apply one coat of primer and two
coats of emulsion paint to all internal walls as
directed by the Engineer m2 114.5 542.00 62,059.00
24 Prepare surface and apply one coat of filler and two
coats of weather shield paint to all external walls as
directed by the Engineer
m2 115.0 612.00 70,380.00
CLASS X – MISCELLANEOUS WORK -
Rain Water Disposal -
25 Zinc Aluminium coated colour bonded plain sheet eave
gutter 470 mm giirth fixed with and including
standard gutter brackets.
m 30.00 1,890.00 56,700.00 29.60 55,944.00 - 29.60 55,944.00
26 100 x 100 mm Square type Zinc Aluminium coated
colour bonded plain sheet down pipe fixed to
column/wall with and including standard down pipe
brackets and necessary fittings, bends, shoe etc., fixed
complete .
m 32.00 2,310.00 73,920.00
Bitumen Filling -
27 12 mm thick bitumen filling around pump base; All
complete as per Engineer's instructions(bitumen m 33.0 473.00 15,609.00
sealent)
TOTAL CARRIED FORWARD 1,478,908.00 902,874.51 - 902,874.51

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP HOUSE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 1,478,908.00 902,874.51 - 902,874.51
Doors and Windows. -
28 Roller Shutter door (Type RD3). All complete to
smooth working order, as directed by the Engineer.
Overall Size 4,000x3,500 mm
nr 1.0 382,200.00 382,200.00
29 Timber panelled door with 75x10 mm rebated frame
and 28 mm thick sash and 300 mm high slats on top
(Type D1), Overall size 1,200x2,700 mm
nr 2.0 124,459.00 248,918.00
30 Glazed window with 75x100 mm rebated timber
frame and 28 mm thick sash including 300 mm high
slats at top; Overall size 1,200x1,650 mm
nr 2.0 76,059.00 152,118.00
31 Glazed window with 75x100 mm rebated timber
frame and 280 mm thick sash; Overall size
2,400x1,650 mm
nr 1.0 14,138.00 14,138.00
Floor Finishes
32 16 mm thick cement rendering on concrete floor slab
in 1:3 cement sand mortar, finished smooth with neat
red cement float
m2 43.0 905.00 38,915.00
33 100 mm high 20 mm thick skirting in 1:3 cement and
sand mortar finished smooth with neat red cement
float.
m 32.0 181.00 5,792.00
TOTAL CARRIED FORWARD 2,320,989.00 902,874.51 - 902,874.51

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP HOUSE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 2,320,989.00 902,874.51 - 902,874.51

Wall Finishes -
34 16 mm thick internal wall plastering in 1:1:5 cement,
lime and sand mortar finished smooth with lime putty
on brick walls and concrete columns. Rate to include
for door and window reveals
m2 115.0 752.00 86,480.00 115.00 86,480.00 115.00 86,480.00
- -
35 20 mm thick external wall plastering in 1:1:5 cement,
lime and sand mortar finished semi-rough on brick
walls and concrete columns. Rate to include for door
and window reveals
m2 115.0 731.00 84,065.00 115.00 84,065.00 115.00 84,065.00

Roof Work and Ceiling -


36 Supply, Fabricate & fixing of Zinc Aluminium coated
colour bonded profile sheet roof on Category "A "
timber frame including 50 X 175 mm Ridge plate , 50
X100 mm Rafters, 50 X 50 mm reepers, 75 X 100
mm Wall plate etc. All timber works to be treated
with two coats of good quality wood preservative
approved by the Engineer. Rate to be include for
Ridging with Zink Alumn Colour bonded ridge caps.

m2 131.0 5,775.00 756,525.00 131.00 756,525.00 131.00 756,525.00


- -
TOTAL CARRIED FORWARD 3,248,059.00 1,829,944.51 - 1,829,944.51

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 08: CONSTRUCTION OF HIGH LIFT PUMP HOUSE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT
Supplying FORWARD
& Fixing of 305 mm gith 0.47 mm thick 3,248,059.00 1,829,944.51 - 1,829,944.51
37 Zinc Aluminium colour bond valance board and barge
board fixed with MS 32x5mm brackets at 900 mm
C/c. Rates shall include for application of one coat of
anti corrosive paint and finishing coat of enamel paint
for MS brackets as per instruction given by the m 50.0 2,100.00 105,000.00 49.08 103,068.00 - 49.08 103,068.00
Engineer.
Electrical Installation -
38 10 mm2 4C PVC/PVC/Cu main incoming cable from
main control panel to distribution board
m 10.0 3,675.00 36,750.00
39 Three phase distribution board with 63A, 4 pole main
switch, 2 nr of 32A 2 pole current operated trip switch,
1 nr of 63A 4 pole current operated trip switch and 6
way MCB incorporated in one plastic box having
transparent front lid nr 1.0 84,000.00 84,000.00
40 4'-0", 40w single fluorescent fitting prismatic diffuser
type; Including point wiring nr 2.0 7,875.00 15,750.00
41 Wall brackets outdoor type lamp 20W; Including point
wiring nr 6.0 5,250.00 31,500.00
42 Exhaust fan of approved type and quality; All complete
with prior approval of the Engineer nr 1.0 15,750.00 15,750.00
43 13 Amp. switched socket outlet, flush type. nr 3.0 7,875.00 23,625.00
44 16 Amp. Wall mounted three phase industrial
switched socket outlet nr 10.0 15,750.00 157,500.00
45 Earthing system according to IEE regulations Item Lump Sum 15,750.00
Total Carried Over to Summary … 3,733,684.00 1,933,012.51 - 1,933,012.51

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
HIGH LIFT PUMP HOUSE
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Quantity
Length Width Depth Previous Bill Bill

Site Preparation
1 Clearing site, including removal of bushes,
scrub, shrub and undergrowth and grubbing
up roots and cutting down small trees not
exceeding 500 mm girth. Rate to include m
2

removal of debris from site


150.00
150.00 - 150.00

Excavating top soil for an average depth of


2 150 mm m3 1.00 7.50 13.50 0.15 15.19
15.19 - 15.19

3 Excavation for column bases in any material


other than top soil, rock or artificial hard
material with maximum depth not exceeding
1.5 m from existing ground level
m3 12.00 0.25 0.25 0.775 0.58
m3 12.00 0.90 0.90 0.175 1.70
2.28 - 2.28
4 Excavation for rubble strip foundation in any
material other than top soil, rock or artificial
hard material with maximum depth not
exceeding 1.5m from existing ground level.

m3 1.00 35.60 0.625 0.45 10.01


m3 12.00 0.25 0.25 0.625 (0.47)
CUMULATIVE QTY 9.54 9.54
BOQ QTY 8.50 - 8.50
EXCESS QTY 1.04 1.04

CLASS F - IN SITU CONCRETE


9 Grade 25 Mass Concrete m3 1.00 35.60 0.05 0.45 0.80
1.00 0.90 0.05 0.90 0.04
0.84 - 0.84

10 Grade 25 Reinforced Concrete m3 12.00 0.25 0.25 3.875 2.91


m3 12.00 0.90 0.90 0.175 1.70
m3 2.00 5.95 0.30 0.250 0.89
m3 2.00 12.30 0.30 0.250 1.85
m3 2.00 12.30 0.40 0.225 2.21
m3 1.00 5.95 0.40 0.225 0.54
m3 1.00 1.60 0.40 0.225 0.14
m3 3.00 5.95 0.40 0.225 1.61
CUMULATIVE QTY 11.85 11.85
BOQ QTY 5.60 - 5.60
EXCESS QTY 6.25 6.25

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
HIGH LIFT PUMP HOUSE
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Quantity
Length Width Depth Previous Bill Bill

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Formwork
(Plane Vertical)
11 Masonry Work m2 4.00 5.95 0.300 7.14
m2 4.00 12.30 0.300 14.76
m2 12.00 0.36 0.175 0.76
m2 4.00 12.30 0.40 19.68
m2 2.00 5.95 0.40 4.76
m2 2.00 1.60 0.40 1.28
m2 9.00 5.95 0.300 16.07
CUMULATIVE QTY 64.45 64.45
BOQ QTY 2.20 - 2.20
EXCESS QTY 62.25 62.25

To sides of column shafts, with width


12 exceeding 0.2 m but not exceeding 0.4 m. m2 12.00 3.875 0.50 23.25
CUMULATIVE QTY 23.25 23.25
BOQ QTY 8.00 - 8.00
EXCESS QTY 15.25 15.25

Reinforcement
Mild steel bar reinforcement cut to length,
bent to shape, placed in position and tied
with GI wire

16 6 mm dia kg 201.69
kg 35.16
CUMULATIVE QTY 236.85 236.85
BOQ QTY 49.00 - 49.00
EXCESS QTY 187.85 187.85

Tor steel bar reinforcement cut to length,


bent to shape, placed in position and tied
with GI wire

17 12 mm dia. kg 396.40
CUMULATIVE QTY 396.40 396.40
BOQ QTY 200.00 - 200.00
EXCESS QTY 196.40 196.40

18 16 mm dia. kg 394.61
kg 154.05
CUMULATIVE QTY 548.66 548.66
BOQ QTY 300.00 - 300.00
EXCESS QTY 248.66 248.66

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
HIGH LIFT PUMP HOUSE
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Quantity
Length Width Depth Previous Bill Bill

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

CLASS U – BRICK WORK, BLOCK WORK


AND MASONRY
Brick Work
19 225 mm thick vertical straight, common
brick walls in 1:6 cement and sand mortar m2 1.00 12.30 4.60 56.58
m2 1.00 1.65 1.20 (1.98)
m2 0.50 6.50 1.63 5.30
m2 1.00 6.50 4.60 29.90
m2 1.00 1.20 2.00 (2.40)
m2 0.50 6.50 1.63 5.30
m2 1.00 6.50 4.60 29.90
m2 1.00 1.65 1.20 (1.98)
m2 1.00 3.55 4.00 (14.20)
m2 1.00 12.30 4.60 56.58
m2 2.00 5.00 0.23 4.600 (10.35)
CUMULATIVE QTY 152.65 152.65
BOQ QTY 115.00 - 115.00
EXCESS QTY 37.65 37.65

Rubble work
21 450 mm thick vertical straight, rubble
masonry walls of foundation, in cement and
sand 1:5 mortar m2 2.00 12.30 1.10 27.06
2.00 5.55 1.10 12.21
CUMULATIVE QTY 39.27 39.27
BOQ QTY 19.70 - 19.70
EXCESS QTY 19.57 19.57
Rain Water Disposal
25 Zinc Aluminium coated colour bonded plain
sheet eave gutter 470 mm giirth fixed with
and including standard gutter brackets.
m 1.00 14.80 14.80
1.00 14.80 14.80
29.60 - 29.60

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
HIGH LIFT PUMP HOUSE
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Quantity
Length Width Depth Previous Bill Bill
Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Wall Finishes
34 16 mm thick internal wall plastering in 1:1:5
cement, lime and sand mortar finished
smooth with lime putty on brick walls and
concrete columns. Rate to include for door
and window reveals
m2 1.00 12.30 4.60 56.58
m2 1.00 1.65 1.20 (1.98)
m2 0.50 6.50 1.63 5.30
m2 1.00 6.50 4.60 29.90
m2 1.00 1.20 2.00 (2.40)
m2 0.50 6.50 1.63 5.30
m2 1.00 6.50 4.60 29.90
m2 1.00 1.65 1.20 (1.98)
m2 1.00 3.55 4.00 (14.20)
m2 1.00 12.30 4.60 56.58
Windows Reveals m2 2.00 5.70 0.26 2.93
Door Reveals m2 1.00 6.40 0.26 1.66
Roller Door Reveals m2 1.00 11.10 0.26 2.89
CUMULATIVE QTY 170.48 170.48
BOQ QTY 115.00 - 115.00
EXCESS QTY 55.48 55.48

35 20 mm thick external wall plastering in 1:1:5


cement, lime and sand mortar finished semi-
rough on brick walls and concrete columns.
Rate to include for door and window reveals

m2 1.00 12.30 4.60 56.58


m2 1.00 1.65 1.20 (1.98)
m2 0.50 6.50 1.63 5.30
m2 1.00 6.50 4.60 29.90
m2 1.00 1.20 2.00 (2.40)
m2 0.50 6.50 1.63 5.30
m2 1.00 6.50 4.60 29.90
m2 1.00 1.65 1.20 (1.98)
m2 1.00 3.55 4.00 (14.20)
m2 1.00 12.30 4.60 56.58
CUMULATIVE QTY 163.00 163.00
BOQ QTY 115.00 - 115.00
EXCESS QTY 48.00 48.00
Pura Neguma - Local Government Enhancement Sector Project
HIGH LIFT PUMP HOUSE
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Quantity
Length Width Depth Previous Bill Bill

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Roof Work and Ceiling


36 Supply, Fabricate & fixing of Zinc
Aluminium coated colour bonded profile
sheet roof on Category "A " timber frame
including 50 X 175 mm Ridge plate , 50
X100 mm Rafters, 50 X 50 mm reepers,
75 X 100 mm Wall plate etc. All timber
works to be treated with two coats of good
quality wood preservative approved by the
Engineer. Rate to be include for Ridging
with Zink Alumn Colour bonded ridge caps.

m2 2.00 14.80 4.87 144.15


CUMULATIVE QTY 144.15 144.15
BOQ QTY 131.00 - 131.00
EXCESS QTY 13.15 13.15

37
Supplying & Fixing of 305 mm gith 0.47 mm
thick Zinc Aluminium colour bond valance
board and barge board fixed with MS
32x5mm brackets at 900 mm C/c. Rates
shall include for application of one coat of
anti corrosive paint and finishing coat of
enamel paint for MS brackets as per
instruction given by the Engineer.
m 2.00 14.80 29.60
4.00 4.87 19.48
49.08 - 49.08
Pura Neguma - Local Government Enhancement Sector Project
HIGH LIFT PUMP HOUSE
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Work Done Work Done
Item Description Unit Nos Qty up to Qty for This Total
No Quantity
Length Width Depth Previous Bill Bill

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
HIGH LIFT PUMP HOUSE
BAR SCHEDULE
Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 11
Period Up to :- 31st August 2021
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 24th September 2021

No.Of Total Length of


Item Bar Type & Size Space No.Of bars in Length of each mm each Total length Weight Weight (kg) Shape &
Mark mem: each No. per m Demension
A B C D E mm m

CONC.BEAM TO
SUPPORT
I SECTION 9 T 16 3.0 5.0 15.0 6500.0 6500.0 97.50 1.580 154.05

10 R 6 3.0 44.0 132.0 350.0 200.0 350.0 200.0 100.0 1200.0 158.40 0.222 35.16

11 T 16 1.0 5.0 5.0 5000.0 5000.0 25.00 1.580 39.50

12 R 6 1.0 35.0 35.0 350.0 200.0 350.0 200.0 100.0 1200.0 42.00 0.222 9.32

Total Carried To Summary 238.03

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the Contract Certified & Recommanded as per
the Contractor

………………….………………… …………………………………………………. ………………………………………………… ...…….…………………………………………. ……………………………………………….


Contractor Technical officer of Consultant/RDC Asst . QS RDC Asst . QS SPCU Senior Engineer/Compliance Officer SPCU
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Site Clearing and Anchoring
1 General clearing of the site (premises of 175 m3 Water
Tower) including removal of hedges, bushes, etc.
m2 230.00 73.00 16,790.00 230.00 16,790.00 230.00 16,790.00
- -
Rate shall include for compacting, dewatering &
Supporting sides of excavation, where necessary -
2 Excavation for base, trenches and the like, commencing
from existing ground level, in any material other than
rock, including compacting bottom of excavation
-
Rate to include for removing surplus excavated earth and
deposited at the direction of Engineer within the site
boundaries at suitable places not disturbing the surface
drainage; Rate to include cost of dewatering, Planking &
Strutting, if necessary. - -
2.1 Depth not exceeding 1.0 m m3 100.00 1,065.00 106,500.00 96.71 102,996.15 - 96.71 102,996.15
2.2 Depth exceeding 1.0 m but not exceeding 2.0 m m3 85.00 1,145.00 97,325.00 85.00 97,325.00 - 85.00 97,325.00
- -
Excavation in Rock - - - -
3 Extra-over for above item no. 2 for excavation of soft
rock, (Provisional Quantity)(No blasting required) m3 10.00 4,725.00 47,250.00 10.00 47,250.00 - 10.00 47,250.00
- -
4 Extra-over for above items no. 2 & 3 for excavation in
hard rock (Provisional Quantity)(Controlled blasting)
m3 10.00 13,125.00 131,250.00 10.00 131,250.00 - 10.00 131,250.00
- -
Earth Filling -
5 Earth filling under floors, using imported earth (other
than top soil or rock) to 95% compaction, as directed by
the Engineer (Compaction reports should be provided)

m3 42.00 2,474.00 103,908.00


TOTAL CARRIED FORWARD 503,023.00 395,611.15 - 395,611.15

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 503,023.00 395,611.15 - 395,611.15
6 Back filling around the structure with selected excavated
material (other than top soil or rock) to 95%
compaction as directed by the Engineer (Compaction
reports should be provided) m3 98.00 830.00 81,340.00 98.00 81,340.00 - 98.00 81,340.00
- -
7 Drilling and rock anchoring with 1 m deep 25 mm tor
steel dowels including grouting the holes as per drawing nr 16 1,418.00 22,688.00 -
(Provisional Quantity)
Plain Concrete -
8 Providing and placing of Grade 15 plain concrete in all
levels where specified, including proper compaction,
curing etc. as per the direction of Engineer

m3 15.00 16,834.00 252,510.00 7.68 129,285.12 - 7.68 129,285.12


9 Providing and placing of 75 mm thick Grade 20 floor
concrete using 20 mm aggregates, including proper
compaction, curing etc. as per the direction of Engineer
m3 2.5 17,416.00 43,540.00
RCC Concrete
10 Providing and placing of G25 concrete in base at all levels
where specified, including Scaffolding, proper
compaction, curing, etc., but excluding form work &
reinforcement as per the direction of Engineer (Ready
Mixed Concrete)
m3 40 19,965.00 798,600.00 40.00 798,600.00 - 40.00 798,600.00

11 Providing and placing of G25 concrete in columns at all


levels, including Scaffolding, proper compaction, curing,
etc., but excluding form work & reinforcement as per the
direction of engineer (Ready Mixed Concrete)

m3 24.00 22,065.00 529,560.00 21.02 463,806.30 - 21.02 463,806.30


TOTAL CARRIED FORWARD 2,231,261.00 1,868,642.57 - 1,868,642.57

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 2,231,261.00 1,868,642.57 - 1,868,642.57
12 Providing and placing of G25 concrete in braces at all
levels including Scaffolding, proper compaction, curing,
etc., but excluding form work & reinforcement as per the
direction of Engineer (Ready Mixed Concrete)
m3 10.5 22,065.00 231,682.50 7.36 162,398.40 - 7.36 162,398.40
13 Providing and placing of G25 concrete in cantilever
platforms at all levels including Scaffolding, proper
compaction, curing, etc., but excluding form work &
reinforcement as per the direction of Engineer (Ready
Mixed Concrete) m3 6.00 22,065.00 132,390.00 1.35 29,787.75 - 1.35 29,787.75
14 Providing and placing of G 35A concrete in beams, slab,
walls and roof of tank at all levels including Scaffolding,
proper compaction, curing, etc., but excluding form work
& reinforcement as per the direction of Engineer (Ready
Mixed Concrete) m3 37.5 25,043.00 939,112.50 34.18 855,963.74 - 34.18 855,963.74
Form work - -
15 Providing, fabrication and fixing to correct levels, line
and plumb, plain form work made up of 12 mm plywood
for all types of RCC works at all levels including
necessary strutting, scaffolding, access and working
platforms, bracings, leaving necessary openings, etc.

m2 350.0 1,295.00 453,250.00 350.00 453,250.00 - 350.00 453,250.00


- -
16 Masonry Work/ Ferro Cement Works. m2 275.0 1,295.00 356,125.00
Reinforcement steel -
17 Supplying, cutting, bending, placing and binding in
position reinforcement steel in all diameters as per the
rebar drawings and bar schedule
t 23 168,587.00 3,877,501.00 18.19 3,066,993.76 0.554 93,456.25 18.75 3,160,450.01
TOTAL CARRIED FORWARD 8,221,322.00 6,437,036.22 93,456.25 6,530,492.47

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 8,221,322.00 6,437,036.22 93,456.25 6,530,492.47
Galvanized Iron (GI), Mild Steel (MS) and Stainless
Steel (SS) work
Note: All Galvanized iron & Mild steel surfaces should be
free from rust and painted using approved colour by the
Engineer. Rate to include for,
Mild Steel (MS)- Apply two coats of Anticorrosive and
two coats of enamel paint
18 Providing, fabrication and fixing of MS ladder from
ground level to Platform No. 1 with all necessary fittings,
bracings and supports as depicted in the drawing
Item Lump Sum 38,719.00
19 Providing, fabrication and fixing of MS ladder from
Platform No. 1 to Platform No. 2 with all necessary
fittings, bracings and supports as depicted in the
drawing
Item Lump Sum 39,375.00
20 Providing, fabrication and fixing of MS ladder from
Platform No. 2 to Platform No. 3 with all necessary
fittings, bracings and supports as depicted in the
drawing
Item Lump Sum 52,500.00
21 Providing, fabrication and fixing of MS ladder from
Platform No. 3 to Platform No. 4 with all necessary
fittings, bracings and supports as depicted in the
drawing
Item Lump Sum 39,375.00
TOTAL CARRIED FORWARD 8,391,291.00 6,437,036.22 93,456.25 6,530,492.47

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 8,391,291.00 6,437,036.22 93,456.25 6,530,492.47


22 Providing, fabrication and fixing of MS ladder from
Platform No. 4 to the roof of tank with all necessary
fittings, bracings and supports as depicted in the
drawing Item Lump Sum 57,750.00
23 Providing, fabrication and fixing of SS ladder inside the
tank with all necessary fittings as depicted in the Item Lump Sum 69,300.00
drawing
24 Providing, fabrication and fixing of GI hand rail for
Platform No. 1 with all necessary fittings & accessories as Item Lump Sum 18,900.00
depicted in the drawing
25 Providing, fabrication and fixing of GI hand rail for
Platform No. 2 with all necessary fittings & accessories as
depicted in the drawing Item Lump Sum 18,900.00
26 Providing, fabrication and fixing of GI hand rail for
Platform No. 3 with all necessary fittings & accessories as
depicted in the drawing Item Lump Sum 81,900.00
27 Providing, fabrication and fixing of GI hand rail for
Platform No. 4 with all necessary fittings & accessories as
depicted in the drawing
Item Lump Sum 18,900.00
28 Providing, fabrication and fixing of GI hand rail around
roof of tank with all necessary fittings & accessories as Item Lump Sum 175,728.00
depicted in the drawing
Miscellaneous
29 Providing and fixing of approved type lightening
protection system as depicted in the drawing Item Lump Sum 126,000.00
30 Providing and fixing of 04 Nos. 450x900 mm windows
with Copper fly mesh screen lightening protection
system as depicted in the drawing
Item Lump Sum 85,050.00
TOTAL CARRIED FORWARD 9,043,719.00 6,437,036.22 93,456.25 6,530,492.47
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
BROUGHT FORWARD 9,043,719.00 6,437,036.22 93,456.25 6,530,492.47
31 Providing and fixing of 04 Nos. Sky lights with 12 mm
thick 225 mm dia armoured glass as depicted in the Item Lump Sum 21,000.00
32 drawing
2,100 mm high 600 mm wide 375 mm thick brick work
with 1:5 cement sand mortar as depicted in the drawing m3 4 15,687.00 62,748.00
33 1:3 plastering finished semi rough on brick work m2 30 705.00 21,150.00
34 Applying non toxic water proofing paint (Approved by
the Engineer) on internal wall os tank including bottom Item Lump Sum 436,800.00
35 Prepare and apply approved type one coat of filler and
two coats of weather proof emulsion paint to specified
colour in external walls
m2 665 612.00 406,980.00
36 Apply two coats of reflective type paint on top of the
Tank m2 125 2,100.00 262,500.00
Pipe Work
Outlet
37 Supply & Installation of approximately 4,000 mm long,
200 mm DI D/F pipes nr 2 73,527.00 147,054.00
38 Supply & Installation of approximately 3,600 mm long
200 mm DI D/F pipe nr 1 68,303.00 68,303.00
39 Supply & Installation of approximately 1,000 mm long
200 mm DI D/F pipe nr 1 34,073.00 34,073.00
40 Supply & Installation of approximately 1,150 mm long
200 mm DI F/PE pipe nr 1 31,772.00 31,772.00
TOTAL CARRIED FORWARD 10,536,099.00 6,437,036.22 93,456.25 6,530,492.47

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 10,536,099.00 6,437,036.22 93,456.25 6,530,492.47


41 Supply & Installation of approximately 600 mm long 200
mm DI F/PE pipe with Puddle flange welded at 100 mm
distance from plain end
nr 1 32,629.00 32,629.00
42 Supply & Installation of 200 mm DI D/F Sluice valve nr 1 78,645.00 78,645.00
43 Supply & Installation of 200 mm DI D/F 900 Duck foot
bend nr 1 41,496.00 41,496.00
44 Supply & Installation of 200 mm DI Couplings. nr 2 23,555.00 47,110.00
Inlet -
45 Supply & Installation of 2,675 mm long 150 mm DI D/F
pipes nr 2 47,962.00 95,924.00
46 Supply & Installation of 4,000 mm long 150 mm DI D/F
pipes nr 3 61,040.00 183,120.00
47 Supply & Installation of 1,600 mm long 150 mm DI D/F
pipe nr 1 36,945.00 36,945.00
48 Supply & Installation of 150 mm DI Flange adaptor nr 1 16,672.00 16,672.00
49 Supply & Installation of 150 mm DI D/F 900 Duck foot nr 1 25,407.00 25,407.00
bend
50 Supply & Installation of 150 mm DI D/F 900 short radius nr 2 18,746.00 37,492.00
bend
51 Supply & Installation of 150 mm DI D/F 900 long radius
bend
nr 1 25,517.00 25,517.00
52 Supply & Installation of 150 mm DI couplings nr 2 16,672.00 33,344.00
Over flow & Scour -
53 Supply & Installation of 100 mm DI D/F Bell mouth nr 1 9,593.00 9,593.00
54 Supply & Installation of approximately 3,000 mm long nr 1 37,450.00 37,450.00
100 mmCARRIED
TOTAL DI D/F pipeFORWARD 11,237,443.00 6,437,036.22 93,456.25 6,530,492.47

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 09: CONSTRUCTION OF 13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

BROUGHT FORWARD 11,237,443.00 6,437,036.22 93,456.25 6,530,492.47


55 Supply & Installation of approximately 1,100 mm long nr 1 27,507.00 27,507.00
100 mm DI D/F pipe with puddle flange welded at
56 Supply
middle & Installation of approximately 1,500 mm long nr 1 26,568.00 26,568.00
57 100 mm
Supply & DI D/F pipe of 100 mm DI D/F Duck foot bends
Installation nr 2 16,727.00 33,454.00
58 Supply & Installation of approximately 1,150 mm long nr 1 24,019.00 24,019.00
59 100 mm&DI
Supply D/F pipe of 600 mm long 100 mm DI F/PE
Installation
pipe with puddle flange welded at 100 mm distance from
plain end nr 1 18,260.00 18,260.00
60 Supply and installation of approximately 1,200 mm long nr 2 20,750.00 41,500.00
61 100 mm&DI,
Supply F/PE pipes
Installation of 100 mm DI couplings nr 2 12,583.00 25,166.00
62 Supply & Installation of 100 mm DI D/F Sluice valve nr 1 32,793.00 32,793.00
63 Supply & Installation of 100 mm x 100 mm DI all flange nr 1 17,786.00 17,786.00
64 Equal
SupplyTee
and installation of approximately 850 mm long nr 1 18,173.00 18,173.00
100 mm DI F/PE pipe
65 Supply & Installation of 100 mm DI Flange adaptor nr 1 11,818.00 11,818.00
66 Supply & Installation of approximately 4,000 mm long nr 2 48,180.00 96,360.00
67 100 mm&DIInstallation
Supply D/F pipes of approximately 2,400 mm long
nr 1 34,839.00 34,839.00
100 mm DI D/F pipe
68 Supply & Installation of 600 mmx750 mm DI manhole
cover with frame to provide access through the roof slab nr 1 62,511.00 62,511.00
of tank with all necessary fittings as directed by Engineer
Total Carried Over to Summary … 11,708,197.00 6,437,036.22 93,456.25 6,530,492.47

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done


Item Qty up to Work Done Total
No Description Unit Nos Qty for This
Length Constant Depth Previous Bill
Quantity
Bill

Site Clearing and Anchoring


General clearing of the site (premises of 175
1 m3 Water Tower) including removal of m2
hedges, bushes, etc. 236.00
CUMULATIVE QTY 236.00 236.00
BOQ QTY 230.00 - 230.00
EXCESS QTY 6.00 6.00

2 Excavation for base, trenches and the like,


commencing from existing ground level, in
any material other than rock, including
compacting bottom of excavation

2.1 Depth not exceeding 1.0 m m3 3.14 30.80 1.00 96.71


96.71 - 96.71

2.2 Depth exceeding 1.0 m but not exceeding


2.0 m m3 3.14 30.80 0.88 85.11
CUMULATIVE QTY 85.11 85.11
BOQ QTY 85.00 - 85.00
EXCESS QTY 0.11 0.11

Excavation in Rock
Soft & hard rock Qty m3 3.14 30.80 1.41 136.36
136.36 - 136.36

Extra-over for above item no. 2 for


excavation of soft rock, (Provisional
3 Quantity)(No blasting required) m3 111.67
CUMULATIVE QTY 111.67 111.67
BOQ QTY 10.00 - 10.00
EXCESS QTY 101.67 101.67

4 Extra-over for above items no. 2 & 3 for


excavation in hard rock (Provisional m3
Quantity)(Controlled blasting)
24.69
CUMULATIVE QTY 24.69 24.69
BOQ QTY 10.00 - 10.00
EXCESS QTY 14.69 14.69

Earth Filling

Back filling around the structure with


selected excavated material (other than top
soil or rock) to 95% compaction as directed
by the Engineer (Compaction reports should
6 be provided)) m3 1.00 30.800 3.140 1.600 116.05 75%
CUMULATIVE QTY 116.05 116.05
BOQ QTY 98.00 - 98.00
EXCESS QTY 18.05 18.05

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done


Item Qty up to Work Done Total
No Description Unit Nos Qty for This
Length Constant Depth Previous Bill
Quantity
Bill

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Plain Concrete
8 Providing and placing of Grade 15 plain
concrete in all levels where specified,
including proper compaction, curing etc. as
per the direction of Engineer
m3 3.14 32.62 0.08 7.68
7.68 - 7.68
RCC Concrete

Providing and placing of G25 concrete in


base at all levels where specified, including
Scaffolding, proper compaction, curing, etc.,
but excluding form work & reinforcement as
per the direction of Engineer (Ready Mixed
10 Concrete) m3 2 28.57 0.50 0.90 25.71
19.78 0.30 0.80 4.75
12.60 3.14 0.45 17.80
CUMULATIVE QTY 48.26 48.26
BOQ QTY 40.00 - 40.00
EXCESS QTY 8.26 8.26
RCC Concrete
Providing and placing of G25 concrete in
columns at all levels, including Scaffolding,
proper compaction, curing, etc., but
11 excluding form work & reinforcement as per
the direction of engineer (Ready Mixed
Concrete)
m3 8.00 3.50 0.60 0.38 6.38
m3 8.00 1.15 0.60 0.38 2.06
m3 8.00 1.70 0.60 0.38 3.06
m3 8.00 2.845 0.60 0.375 5.12
m3 8.00 2.445 0.600 0.375 4.40
21.02 - 21.02
Providing and placing of G25 concrete in
braces at all levels including Scaffolding,
proper compaction, curing, etc., but
12 excluding form work & reinforcement as per
the direction of Engineer (Ready Mixed
Concrete)
m3 8.00 3.890 0.15 0.525 2.45
m3 8.00 3.890 0.15 0.525 2.45
m3 8.00 3.890 0.15 0.525 2.45
7.36 - 7.36
13 Providing and placing of G25 concrete in
cantilever platforms at all levels including
Scaffolding, proper compaction, curing, etc.,
but excluding form work & reinforcement as
per the direction of Engineer (Ready Mixed
Concrete)
m3 1.00 5.750 1.200 0.125 0.86
m3 1.00 5.750 0.375 0.225 0.49
1.35 - 1.35

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done


Item Qty up to Work Done Total
No Description Unit Nos Qty for This
Length Constant Depth Previous Bill
Quantity
Bill

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
RCC Concrete
14 Providing and placing of G 35A concrete in
beams, slab, walls and roof of tank at all
levels including Scaffolding, proper
compaction, curing, etc., but excluding form
work & reinforcement as per the direction of
Engineer (Ready Mixed Concrete)

m3 8.00 0.737 0.950 0.375 2.10


m3 8.00 0.737 2.075 0.375 4.59
m3 8.00 0.600 0.975 0.375 1.76
m3 8.00 0.300 0.450 0.375 (0.41)
m3 1.00 5.576 0.225 0.225 0.28
m3 1.00 19.782 0.300 0.450 2.67
m3 8.00 0.600 1.900 0.375 3.42
m3 1.00 19.360 3.140 0.150 9.12
m3 1.00 0.600 3.140 0.150 (0.28)
m3 2.00 4.100 3.140 0.025 0.64
m3 2.00 4.250 3.140 0.097 2.59
m3 2.00 0.900 3.140 0.025 0.14
m3 2.00 0.837 3.140 0.040 0.21
m3 1.00 19.360 3.140 0.920 55.93
m3 1.00 16.810 3.140 0.920 (48.56)
m3 1.00 0.810 3.140 0.400 1.02
m3 1.00 0.600 3.140 0.400 (0.75)
m3 2.00 0.030 3.140 0.100 0.02
m3 2.00 0.040 3.140 0.200 0.05
34.54 - 34.54

Form work
15 Providing, fabrication and fixing to correct
levels, line and plumb, plain form work made
up of 12 mm plywood for all types of RCC
works at all levels including necessary
strutting, scaffolding, access and working
platforms, bracings, leaving necessary
openings, etc.
m2 1.00 34.85 0.30 10.45
m2 1.00 17.27 0.30 5.18
m2 1.00 22.29 0.15 3.34
m2 8.00 3.50 1.95 54.60
m2 8.00 2.06 0.53 8.65
m2 8.00 1.84 0.53 7.73
m2 8.00 3.90 0.50 0.30 4.68
m2 16.00 0.38 1.15 6.87
m2 16.00 0.60 1.15 10.99
m2 16.00 0.32 0.53 (2.68)
m2 8.00 1.95 1.70 26.52

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done


Item Qty up to Work Done Total
No Description Unit Nos Qty for This Quantity
Length Constant Depth Previous Bill
Bill & Certified as per the Contract
Checked
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Columns m2 8.00 2.85 1.95 44.38
Beam m2 8.00 2.00 0.58 9.33
m2 8.00 1.83 0.53 7.69
m2 8.00 2.06 0.53 8.65
Columns m2 8.00 2.45 1.95 38.14
Beam m2 8.00 1.95 0.30 4.67
m2 8.00 1.83 0.53 7.69
m2 8.00 2.06 0.53 8.65
Platform m2 1.00 1.20 5.75 6.90
m2 1.00 13.90 0.13 1.74
m2 1.00 0.98 5.75 5.61
m2 8.00 1.95 1.90 29.64
m2 1.00 6.28 0.78 0.23 1.10
m2 1.00 6.28 1.00 0.23 1.41
m2 1.00 6.28 0.89 0.23 1.25
m2 1.00 6.28 3.00 0.45 8.48
m2 1.00 6.28 3.30 0.45 9.33
m2 1.00 6.28 3.15 0.30 5.93
m2 16.00 0.73 0.95 11.10
m2 16.00 0.73 2.08 24.23
m2 16.00 0.60 0.98 9.36
m2 16.00 0.30 0.45 (2.16)
m2 16.00 0.38 0.50 3.00
m2 8.00 0.38 1.05 3.15
m2 8.00 0.38 2.12 6.36
m2 2.00 4.40 3.14 0.48 13.13
m2 2.00 0.78 3.14 0.48 2.31
m2 2.00 4.10 3.14 0.48 12.23
m2 2.00 0.90 3.14 0.48 2.68
m2 2.00 4.40 3.14 1.20 33.16
m2 2.00 0.78 3.14 1.20 5.84
m2 2.00 4.10 3.14 1.20 30.90
m2 2.00 0.90 3.14 1.20 6.78
m2 2.00 0.90 3.14 1.60 9.04
m2 2.00 0.78 3.14 1.60 7.79
m2 2.00 3.50 3.14 1.20 26.38
m2 2.00 3.33 3.14 1.20 25.06
CUMULATIVE QTY 498.99 68.26 567.25
BOQ QTY 350.00 350.00
EXCESS QTY 148.99 68.26 217.25
Pura Neguma - Local Government Enhancement Sector Project
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done


Item Qty up to Work Done Total
No Description Unit Nos Qty for This
Length Constant Depth Previous Bill
Quantity
Bill

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Reinforcement steel
17
Supplying, cutting, bending, placing and
binding in position reinforcement steel in all
diameters as per the rebar drawings and bar
schedule t 4.120
t 3.040
t 0.790
t 0.164
t 4.588
t 0.987
t 2.289
t 1.394
t 0.266
t 0.55
17.638 0.55 18.19
Pura Neguma - Local Government Enhancement Sector Project
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done


Item Qty up to Work Done Total
No Description Unit Nos Qty for This
Length Constant Depth Previous Bill
Quantity
Bill

Prepared Checked as per the Contract Checked & Recommanded as Checked & Certified as per the Contract
per the Contract

……………………………… …………………………………………………………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
BAR SCHEDULE
Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No.Of Total Length of Total length Weight per


Item Bar Type & Size Space No.Of bars in Length of each mm each Weight (kg) Shape & Demension
Mark mem: each No. m
A B C D E mm m

Tank Walls 82 T 12 1.0 5.0 5.0 6000.0 6000.0 30.00 0.888 26.64

83 T 12 1.0 80.0 80.0 6000.0 6000.0 480.00 0.888 426.24


83 T 12 1.0 20.0 20.0 5300.0 5300.0 106.00 0.888 94.13

PLATFORM
No.06 84 T 10 1.0 1.0 1.0 375.0 1550.0 375.0 2300.0 2.30 0.617 1.42

85 T 10 1.0 1.0 1.0 375.0 1400.0 375.0 2150.0 2.15 0.617 1.33

86 T 10 1.0 1.0 1.0 375.0 1100.0 375.0 1850.0 1.85 0.617 1.14

87 T 10 1.0 1.0 1.0 1350.0 1350.0 1.35 0.617 0.83

88 T 10 1.0 5.0 5.0 450.0 400.0 850.0 4.25 0.617 2.62

Total Carried To Summary 554.35

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the Contract Certified & Recommanded as per
the Contractor

………………….………………… …………………………………………………. ………………………………………………… ...…….…………………………………………. ……………………………………………….


Pura Neguma - Local Government Enhancement Sector Project
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
BAR SCHEDULE
Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No.Of Total Length of Total length


Item Bar Type & Size Space No.Of bars in Length of each mm each Weight per Weight (kg) Shape & Demension
Mark mem: each No. m
A B C D E mm m
Contractor Technical officer of Consultant/RDC Asst . QS RDC Asst . QS SPCU Senior Engineer
Local Government Enhancement Sector Project (LGESP)
(Additional Financing)

JMS No.:
JOIN MEASUREMENT SHEET (JMS)
Date:

Project Name: Construction of Water Supply Scheme for Karuwalagaswewa Pradeshiya Sabha
Project No.: NWP-AF-WS-CKD-15
Client: Chairman - Karuwalagaswewa Pradeshiya Sabha
Consultant: Resources Development Consultants (Pvt) Ltd.
Contractor: Sanken Construction (Pvt) Ltd.
Location:
Description of Measurement

Excavation in Hard Rock


No Length of 3D Average Length Radius
Volume (m3) Remark
x y z
1 1.70 1.30 1.30 1.43 0.72 1.54
2 2.50 2.20 0.70 1.80 0.90 3.05
3 1.30 1.20 1.30 1.27 0.63 1.06
4 1.90 1.10 0.90 1.30 0.65 1.15
5 1.70 1.30 1.40 1.47 0.73 1.65
6 1.30 1.40 1.20 1.30 0.65 1.15
7 1.90 1.10 1.00 1.33 0.67 1.24
9 1.50 1.30 1.30 1.37 0.68 1.34
10 1.80 1.40 1.00 1.40 0.70 1.44
11 1.40 1.20 1.20 1.27 0.63 1.06
12 2.00 1.20 1.40 1.53 0.77 1.89
13 1.60 1.20 1.00 1.27 0.63 1.06
14 1.30 1.20 1.30 1.27 0.63 1.06
15 1.30 1.20 1.30 1.27 0.63 1.06
16 2.54 1.10 1.10 1.58 0.79 2.06
17 1.80 1.20 1.20 1.40 0.70 1.44
18 1.90 1.10 1.20 1.40 0.70 1.44

TOTAL 24.69
Agreed by :
Contractor Consultant Puraneguma
Name : Name : Name :
Designation : Designation : Designation :
Signature
Signature : Signature :
:
Date : Date : Date :
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
BAR SCHEDULE

#REF!
Bar No.Of Total Length of Total
Type & No.Of Length of each mm each length Weight Weight Shape &
Item Space bars in
Mark Size mem: each No. per m (kg) Demension
A B C D E mm m
Foundation
1 T 20 1.0 88.0 88.0 2925.0 2925.0 257.40 2.467 635.01
Bottom
Reinforcement 2 T 20 1.0 88.0 88.0 3110.0 3110.0 273.68 2.467 675.17

3 T 16 1.0 6.0 6.0 6000.0 6000.0 36.00 1.579 56.84


T 16 1.0 1.0 1.0 3800.0 3800.0 3.80 1.579 6.00

4 T 16 1.0 6.0 6.0 6000.0 6000.0 36.00 1.579 56.84


T 16 1.0 1.0 1.0 2150.0 2150.0 2.15 1.579 3.39

5 T 16 1.0 5.0 5.0 6000.0 6000.0 30.00 1.579 47.37


T 16 1.0 1.0 1.0 5650.0 5650.0 5.65 1.579 8.92

6 T 16 1.0 5.0 5.0 6000.0 6000.0 30.00 1.579 47.37


T 16 1.0 1.0 1.0 4000.0 4000.0 4.00 1.579 6.32

7 T 16 1.0 5.0 5.0 6000.0 6000.0 30.00 1.579 47.37


T 16 1.0 1.0 1.0 2325.0 2325.0 2.33 1.579 3.68

8 T 16 1.0 4.0 4.0 6000.0 6000.0 24.00 1.579 37.90


T 16 1.0 1.0 1.0 5830.0 5830.0 5.83 1.579 9.21

9 T 16 1.0 4.0 4.0 6000.0 6000.0 24.00 1.579 37.90


T 16 1.0 1.0 1.0 4175.0 4175.0 4.18 1.579 6.60

10 T 16 1.0 4.0 4.0 6000.0 6000.0 24.00 1.579 37.90


T 16 1.0 1.0 1.0 2500.0 2500.0 2.50 1.579 3.95

............................... ............................... .............................


Prepared By Checked By Certified By
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
BAR SCHEDULE

#REF!
Bar No.Of Total Length of Total
Type & No.Of Length of each mm each length Weight Weight Shape &
Item Space bars in
Mark Size mem: each No. per m (kg) Demension
A B C D E mm m
C/F 1727.74
B/F 1727.74

11 T 20 1.0 12.0 12.0 6000.0 6000.0 72.00 2.467 177.62


T 20 1.0 12.0 12.0 1625.0 1625.0 19.50 2.467 48.11

12 T 20 1.0 8.0 8.0 6000.0 6000.0 48.00 2.467 118.42

13 T 20 1.0 8.0 8.0 5325.0 5325.0 42.60 2.467 105.09

14 T 20 1.0 8.0 8.0 6000.0 6000.0 48.00 2.467 118.42

Foundation
15 T 20 1.0 14.0 14.0 5175.0 5175.0 72.45 2.467 178.73
Top
Reinforcement 16 T 20 1.0 8.0 8.0 5125.0 5125.0 41.00 2.467 101.15

18 T 20 1.0 8.0 8.0 5050.0 5050.0 40.40 2.467 99.67

19 T 20 1.0 8.0 8.0 4850.0 4850.0 38.80 2.467 95.72

20 T 20 1.0 8.0 8.0 4450.0 4450.0 35.60 2.467 87.83

21 T 20 1.0 8.0 8.0 4100.0 4100.0 32.80 2.467 80.92

22 T 20 1.0 8.0 8.0 3725.0 3725.0 29.80 2.467 73.52

23 T 20 1.0 4.0 4.0 3975.0 3975.0 15.90 2.467 39.23

............................... ............................... .............................


Prepared By Checked By Certified By
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
BAR SCHEDULE

#REF!
Bar No.Of Total Length of Total
Type & No.Of Length of each mm each length Weight Weight Shape &
Item Space bars in
Mark Size mem: each No. per m (kg) Demension
A B C D E mm m

C/F 3052.17

............................... ............................... .............................


Prepared By Checked By Certified By
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
BAR SCHEDULE

#REF!
Bar No.Of Total Length of Total
Type & No.Of Length of each mm each length Weight Weight Shape &
Item Space bars in
Mark Size mem: each No. per m (kg) Demension
A B C D E mm m
B/F 3052.17
Curcular Beam 24 T 20 1.0 4.0 4.0 6000.0 6000.0 24.00 2.467 59.21
in Foundation T 20 1.0 1.0 1.0 1475.0 1475.0 1.48 2.467 3.65
(Bottom R/F)
25 T 20 1.0 4.0 4.0 6000.0 6000.0 24.00 2.467 59.21
T 20 1.0 1.0 1.0 1960.0 1960.0 1.96 2.467 4.84

26 T 20 1.0 4.0 4.0 6000.0 6000.0 24.00 2.467 59.21


T 20 1.0 1.0 1.0 1280.0 1280.0 1.28 2.467 3.16

27 T 20 1.0 3.0 3.0 6000.0 6000.0 18.00 2.467 44.41


T 20 1.0 1.0 1.0 5550.0 5550.0 5.55 2.467 13.69

28 T 20 1.0 3.0 3.0 6000.0 6000.0 18.00 2.467 44.41


T 20 1.0 1.0 1.0 4860.0 4860.0 4.86 2.467 11.99

29 T 20 1.0 3.0 3.0 6000.0 6000.0 18.00 2.467 44.41


T 20 1.0 1.0 1.0 4170.0 4170.0 4.17 2.467 10.29

30 T 16 1.0 4.0 4.0 6000.0 6000.0 24.00 1.579 37.90


T 16 1.0 1.0 1.0 1650.0 1650.0 1.65 1.579 2.61

31 T 16 1.0 4.0 4.0 6000.0 6000.0 24.00 1.579 37.90


T 16 1.0 1.0 1.0 2200.0 2200.0 2.20 1.579 3.47

C/F 3492.53

............................... ............................... .............................


Prepared By Checked By Certified By
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
13 m HIGH, 175 m3 CAPACITY OVERHEAD TANK
BAR SCHEDULE

#REF!
Bar No.Of Total Length of Total
Type & No.Of Length of each mm each length Weight Weight Shape &
Item Space bars in
Mark Size mem: each No. per m (kg) Demension
A B C D E mm m
B/F 3492.53

32 T 16 1.0 4.0 4.0 6000.0 6000.0 24.00 1.579 37.90

35 T 16 1.0 3.0 3.0 6000.0 6000.0 18.00 1.579 28.42


T 16 1.0 1.0 1.0 3800.0 3800.0 3.80 1.579 6.00

36 T 10 1.0 288.0 288.0 2160.0 2160.0 622.08 0.617 383.82

Additional T 20 1.0 64.0 64.0 1200.0 1200.0 76.80 2.467 189.47


(stool & Other) T 20 1.0 22.0 22.0 1460.0 1460.0 32.12 2.467 79.24
T 20 1.0 1.0 1.0 1960.0 1960.0 1.96 2.467 4.84
T 20 1.0 1.0 1.0 1280.0 1280.0 1.28 2.467 3.16

Total Carried To Summary 4225.38

............................... ............................... .............................


Prepared By Checked By Certified By
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
BILL NO. 10: RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Note :
Rate to include removing of existing pipes as
directed by the Engineer and hand over all
removed items to Karuwalagaswewa
Pradeshiya Sabha
1 Supplying and fixing of Zinc Aluminium Sheet tank
lid, including locking arrangement as per
instructions given by the Engineer.

a. Karuwalagaswewa PS nr 1 8,400.00 8,400.00


b. Neelamalapura nr 1 8,400.00 8,400.00 0.70 5,880.00 - 0.70 5,880.00
2 Replace the existing GI Inlet line with new 80 mm Item Lump Sum 16,275.00
3 dia. DI pipes
Replace at Karuwalagaswewa
the existing GI Inlet line with PS new
tank with
100
all
mmnecessary
dia. pipes and fittings
DI Double as directed
Flanged by the
pipes at
Engineer. Rate totank
Neelamalapura include
withfor
all providing
necessaryand fixing
Pipes &
all the necessary
fittings rubber
as directed by packings, rag bolts,
the Engineer. RateM.S.
to
straps, Primer
include Compound,
for providing Masticallsealer
and fixing & Denso
the necessary
Tape
rubberand other accessories
packings, as per
rag bolts, M.S. instructions
straps, Primer
given by the Mastic
Compound, Engineer to good
Sealer working
& Denso order.
Tape and other
accessories as per instructions given by the
Engineer to good working order.

Item Lump Sum 19,425.00


TOTAL CARRIED FORWARD 52,500.00 5,880.00 - 5,880.00

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
BILL NO. 10: RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Note :

BROUGHT FORWARD 52,500.00 5,880.00 - 5,880.00

4 Replace the existing GI Outlet line with new 100


mm dia. DI Double Flanged pipes at
Neelamalapura tank with all necessary Pipes &
fittings as directed by the Engineer. Rate to
include for providing and fixing all the necessary
rubber packings, rag bolts, M.S. straps, Primer
Compound, Mastic Sealer & Denso Tape and other
accessories as per instructions given by the
Engineer to good working order.

Item Lump Sum 19,425.00


5 Replace the existing GI Outlet line with new 150
mm dia. DI pipes at Karuwalagaswewa PS tank
with all necessary pipes and fittings as directed by
the Engineer. Rate to include for providing and
fixing all the necessary rubber packing, rag bolts,
M.S. straps, Primer Compound, Mastic sealer &
Denso Tape and other accessories as per
instructions given by the Engineer to good working
order.

Item Lump Sum 26,250.00


TOTAL CARRIED FORWARD 98,175.00 5,880.00 - 5,880.00

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
BILL NO. 10: RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Note :

BROUGHT FORWARD 98,175.00 5,880.00 - 5,880.00


6
Replace the existing GI Washout line with new
100 mm dia. DI pipes at Karuwalagaswewa PS
tank with all necessary pipes and fittings as
directed by the Engineer. Rate to include for
providing and fixing all the necessary rubber
packing, rag bolts, M.S. straps, Primer Compound,
Mastic sealer & Denso Tape and other accessories
as per instructions given by the Engineer to good
working order.
Item Lump Sum 26,250.00
7
Replace the existing GI Overflow line with the
new 100 mm dia. DI pipes at Karuwalagaswewa
PS tank with all necessary pipes and fittings as
directed by the Engineer. Rate to include for
providing and fixing all the necessary rubber
packing, rag bolts, M.S. straps, Primer Compound,
Mastic sealer & Denso Tape and other accessories
as per instructions given by the Engineer to good
working order.
Item Lump Sum 26,250.00
TOTAL CARRIED FORWARD 150,675.00 5,880.00 - 5,880.00

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
BILL NO. 10: RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Note :
………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 150,675.00 5,880.00 - 5,880.00


8
Supplying and fixing 100 mm dia. DI Double
Flange (D/F) Sluice Valve for the Outlet pipe for
Neelamalapura tank with all necessary
fittings ,work complete as per instructions given by
the Engineer.
nr 1 32,790.00 32,790.00
9
Supplying and fixing 150 mm dia. DI Double Flange
(D/F) Sluice Valve for the Outlet pipe for
Karuwalagaswewa PS tank with all necessary
fittings ,work complete as per instructions given by
the Engineer.
nr 1 56,849.00 56,849.00
10
Supplying and fixing 80 mm dia. DI Double Flange
(D/F) Sluice Valve for the Washout pipe for
Neelamalapura tank with all necessary
fittings ,work complete as per instructions given by
the Engineer.
nr 1 25,912.00 25,912.00
11 Supplying and fixing 100 mm dia. DI Double
Flange (D/F) Sluice Valve for the Washout pipe
for Karuwalagaswewa PS tank with all necessary
fittings,work complete as per instructions given by
the Engineer.
nr 1 32,790.00 32,790.00
TOTAL CARRIED FORWARD 299,016.00 5,880.00 - 5,880.00

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
BILL NO. 10: RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Note :

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 299,016.00 5,880.00 - 5,880.00


12
Construction of Overflow Chamber, internal
dimensions 900x 900 mm and average depth 1.5 m,
including 150 mm thick base slab and 100 mm
thick walls, Pre-cast reinforced concrete cover slab
comprising of SS lifting handles on slab as per
instructions given by the Engineer.
-
a. Karuwalagaswewa PS nr 1 76,834.00 76,834.00
b. Neelamalapura nr 1 76,834.00 76,834.00
13
Applying two coats of non toxic Water Proofing
Paint to inner surface of the Tank , approved by
the Engineer. Rate to include cleaning the inner
surface of the tank & finish smooth.

a. Karuwalagaswewa PS m2 80.00 2,736.00 218,880.00 - -


b. Neelamalapura m2 50.00 2,736.00 136,800.00 -
14
Applying two coats of Reflective type Paint of
approved colour to outer surface of the Tank, - -
approved by the Engineer. Rate to include cleaning
the outer surface of the tank & finish smooth.

a. Karuwalagaswewa PS m2 80.00 1,890.00 151,200.00 80.00 151,200.00 - 80.00 151,200.00


- -
b. Neelamalapura m2 50.00 1,890.00 94,500.00 48.45 91,570.50 - 48.45 91,570.50
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
BILL NO. 10: RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Note :
TOTAL CARRIED FORWARD 1,054,064.00 248,650.50 - 248,650.50

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

BROUGHT FORWARD 1,054,064.00 248,650.50 - 248,650.50

15 16 mm thick plastering to Columns, Beams, Sides of


slab & soffit of Slab in cement and sand mortar -
(1:5) finished semi rough with wooden float
a. Karuwalagaswewa PS m2 315.00 679.00 213,885.00 216.56 147,044.24 - 216.56 147,044.24
b. Neelamalapura m2 200.00 679.00 135,800.00 181.21 123,041.59 - 181.21 123,041.59
16
Applying two coats of Weather Shield Paint in
approved colour including one coat primer outside -
the tank support structure (Columns, Beams &
Tank Base)
a. Karuwalagaswewa PS m2 300.00 612.00 183,600.00 216.56 132,534.72 - 216.56 132,534.72
b. Neelamalapura m2 175.00 612.00 107,100.00 175.00 107,100.00 - 175.00 107,100.00
- - -
17
Applying two coats of Zinc Phosphate paint to GI
hand rails, Ladders and GI pipes (Inlet, Outlet,
Washout, Overflow) for Neelamalapura tank
using approved colour as per Engineer's
instructions.
m2 65.00 1,680.00 109,200.00
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
BILL NO. 10: RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Note :
TOTAL CARRIED FORWARD 1,803,649.00 758,371.05 - 758,371.05

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)

………………………………………………………………
Technical Officer (PS)
BROUGHT FORWARD 1,803,649.00 758,371.05 - 758,371.05
18
Supplying, fixing 300 mm wide M.S. ladder with 50
mm X 12 mm stringers and 20 mm rungs at 300
mm centers supplied with 75X75X9.5 mm angle
cleat 50X12 mm flat iron bent to shape, welded to
the ladder and fixed to concrete blocks with rag
bolts at Karuwalagaswewa PS tank . Rate to include
for galvanizing.

I From ground to platform 1 Item Lump Sum 50,400.00


II From platform 1 to platform 2 Item Lump Sum 50,400.00
III From platform 2 to dome. Item Lump Sum 50,400.00
19
Providing, fabrication and fixing of 40 mm dia. GI
medium class hand rail for Karuwalagaswewa PS
tank 900 mm high with all necessary fittings
around the slab and ladders. Rate to include for two
coats of Zinc Phosphate paint.
m 40.00 8,925.00 357,000.00
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
BILL NO. 10: RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 30th May 2022

ITEM
DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Note :
20
Supply & fixing Pipe bracket comprising of 75 x 6
mm flat iron strap to Neelamalapura Tank
including all accessories. (80 mm &100 mm dia.
Pipes)
nr 8 1,575.00 12,600.00
Total Carried Over to Summary … 2,324,449.00 758,371.05 - 758,371.05

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

1 Supplying and fixing of Zinc Aluminium Sheet


tank lid, including locking arrangement as per
instructions given by the Engineer.
b. Neelamalapura nr 1 1.00 70%
0.70 0.70

14 Applying two coats of Reflective type Paint of


approved colour to outer surface of the Tank,
approved by the Engineer.
a. Karuwalagaswewa PS m2 2.00 3.15 3.14 2.80 55.39
m2 1.00 2.00 3.14 5.38 33.79
CUMULATIVE QTY 89.18 89.18
BOQ QTY 80.00 - 80.00
EXCESS QTY 9.18 9.18

b. Neelamalapura m2 1 2.00 3.14 4.89 30.69


1 2.13 3.14 2.75 18.35
1 3.14 0.19 (0.59)
48.45 48.45

15 16 mm thick plastering to Columns, Beams,


Sides of slab & soffit of Slab in cement and sand
mortar (1:5) finished semi rough with wooden
float
a. Karuwalagaswewa PS m2 24.00 13.53 0.33 107.16
m2 48.00 0.33 0.33 (5.23)
m2 72.00 2.67 0.33 63.44
m2 18.00 2.67 0.33 15.86
m2 1.00 1.40 0.10 0.14
m2 1.00 0.60 0.40 0.24
m2 1.00 2.20 0.10 0.22
m2 1.00 0.80 0.60 0.48
m2 1.00 6.28 0.49 3.08
m2 1.00 3.14 10.56 33.16
m2 6.00 2.67 0.33 (5.29)
m2 6.00 0.33 0.33 (0.65)
m2 1.00 19.78 0.20 3.96
216.56 216.56

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

…………………………… ………………………………………………… ……………………………………………………………………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

b. Neelamalapura m2 16.00 0.35 13.52 75.71


8.00 0.34 0.34 5.00 4.62
16.00 2.95 0.34 4.00 64.19
4.00 2.95 0.34 (4.01)
12.00 2.95 0.36 12.74
1.00 2.88 3.14 2.88 25.95
1.00 2.10 3.14 2.10 (13.85)
2.00 2.88 3.14 0.20 3.61
1.00 2.10 3.14 2.10 13.85
4.00 2.95 0.34 (4.01)
1.00 0.67 1.30 0.87
1.00 1.18 1.30 1.53
181.21 181.21
16 Applying two coats of Weather Shield Paint in
approved colour including one coat primer
outside the tank support structure
a. Karuwalagaswewa PS m2 24.00 13.53 0.33 107.16
m2 48.00 0.33 0.33 (5.23)
m2 72.00 2.67 0.33 63.44
m2 18.00 2.67 0.33 15.86
m2 1.00 1.40 0.10 0.14
m2 1.00 0.60 0.40 0.24
m2 1.00 2.20 0.10 0.22
m2 1.00 0.80 0.60 0.48
m2 1.00 6.28 0.49 3.08
m2 1.00 3.14 10.56 33.16
m2 6.00 2.67 0.33 (5.29)
m2 6.00 0.33 0.33 (0.65)
m2 1.00 19.78 0.20 3.96
216.56 216.56
b. Neelamalapura m2
m2 16.00 0.35 13.52 75.71
m2 8.00 0.34 0.34 5.00 4.62
m2 16.00 2.95 0.34 4.00 64.19
m2 4.00 2.95 0.34 (4.01)
m2 12.00 2.95 0.36 12.74
m2 1.00 2.88 3.14 2.88 25.95
m2 1.00 2.10 3.14 2.10 (13.85)
m2 2.00 2.88 3.14 0.20 3.61
m2 1.00 2.10 3.14 2.10 13.85
m2 4.00 2.95 0.34 (4.01)
m2 1.00 0.67 1.30 0.87
m2 1.00 1.18 1.30 1.53
CUMULATIVE QTY 181.21 181.21
BOQ QTY 175.00 - 175.00
EXCESS QTY 6.21 6.21

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract
Pura Neguma - Local Government Enhancement Sector Project
RENOVATION OF EXISTING WATER TOWER AT KARUWALAGASWEWA PS AREA (60m3) & NEELAMALAPURA (30m3).
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement
Item Work Done Work Done Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Constant Depth Previous Bill Bill

…………………………… ………………………………………………… ……………………………………………………………………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Annexure 01
Pura Neguma - Local Government Enhancement Sector Project
Supply of DI pipes for Transmission lines of Karuwalagaswewa WSS

Project Name :- Supply of DI pipes for Transmission lines of Karuwalagaswewa WSS


Note
(1) All spigot and socket pipes shall be of class C 40.
(2) All flange pipes shall be of class PN 16.
(3) All fittings except tees & crosses shall be PN 16.
(4) All tees and crosses shall be PN 16.

ITEM RATE (Rs.)


DESCRIPTION UNIT QTY AMOUNT (Rs.)
NO.

SUPPLY OF DI PIPE , FITTINGS, MANHOLE


COVERS AND SPECIALS WITH NECESSARY SS
NUT & BOLTS(8.8) WITH SUITABLE TWO
NUMBER OF SS WASHERS, GASKETS &
RUBBERINGS(OF EPDM MATERIAL) FOR EACH
FLANGE JOINT(N 16), COUPLING AND FLANGED
SPECIALS.
NECESSARY DENSO MASTIC, DENSO PASTE,
DENSO TAPE & PVC GUARD TAPE FOR JOINT
PROTECTION IS INCLUDED.
AS PER DI PIPES', FITTINGS' AND SPECIALS'
SPECIFICATIONS, ALL NECESSARY ACCESORIES,
TOOLS AND EQUIPMENTS FOR INSTALLATIONS
TO BE PROVIDED PROVIDED BY THE SUPPLIER.

(1). All spigot and socket pipes shall be of class C


40
(2). All flange pipes shall be of class C40 (or C 40 in
case of screwed for factory welded flanges)
(3). All fitting including tees & crosses shall be of
class C 40
(4). All flanges shall be PN 16 unless otherwise
stated.

1 DI Double Flange DI Pipe

150mm diameter 500mm long double flanged DI


1.1 Nos 1
pipe
100mm diameter 5000mm long double flanged DI
1.2 Nos 11
pipe
100mm diameter 3000mm long double flanged DI
1.3 Nos 2
pipe
100mm diameter 1000mm long double flanged DI
1.4 Nos 6
pipe
100mm diameter 2500mm long double flanged DI
1.5 pipe Nos 2

1.6 100mm diameter 500mm long double flanged DI Nos 1


pipe
80mm diameter 3000mm long double flanged DI
1.7 Nos 1
pipe
80mm diameter 5000mm long double flanged DI
1.8 Nos 5
pipe
ITEM RATE (Rs.)
NO. DESCRIPTION UNIT QTY AMOUNT (Rs.)

80mm diameter 2500mm long double flanged DI


1.9 Nos 2
pipe
80mm diameter 500mm long double flanged DI
1.10 Nos 1
pipe

2 DI Flanged and Spigot DI Pipe


150mm diameter 1000mm long flanged and spigot
2.1 Nos 1
DI Pipe

2.2 100mm diameter 1000mm long flanged and spigot Nos 9


DI Pipe
80mm diameter 1000mm long flanged and spigot
2.2 Nos 3
DI Pipe

3 DI Double Flange DI Pipe with Puddle


100mm diameter 1500mm long double flanged DI
3.1 pipe Nos 4
with puddle(puddle welded at site)
150mm diameter 1500mm long double flanged DI
3.2 pipe Nos 6
with puddle(puddle welded at site)

4 DI Flanged and Spigot DI Pipe with Puddle


80mm diameter 1000mm long flanged and spigot
4.1 DI Pipe Nos 7
with puddle welded 475mm away from flanged
end

80mm diameter 1000mm long flanged and spigot


DI Pipe
4.2 with puddle welded at 450mm away from flanged Nos 4
end

100mm diameter 1000mm long flanged and spigot


DI Pipe
4.3 with puddle welded at 450mm away from flanged Nos 4
end

150mm diameter 1000mm long flanged and spigot


DI Pipe
4.4 Nos 4
with puddle welded at 450mm away from flanged
end

200mm diameter 1000mm long flanged and spigot


DI Pipe
4.5 with puddle welded at 475mm away from flanged Nos 2
end

5 DI Spigot(plainended) pipe with Puddle


5.1 80mm diameter 1000mm long spigot DI pipe Nos 4
with puddle(puddle welded at site)
100mm diameter 1000mm long spigot DI pipe
5.2 with puddle(puddle welded at site) Nos 4

150mm diameter 1000mm long spigot DI pipe


5.3 Nos 4
with puddle(puddle welded at site)
200mm diameter 1000mm long spigot DI pipe
5.4 Nos 2
with puddle(puddle welded at site)
ITEM RATE (Rs.)
NO. DESCRIPTION UNIT QTY AMOUNT (Rs.)

6 DI Socket &Spigot Pipe


6.1 80mm diameter 6000mm long socket & spigot pipe Nos 2

100mm diameter 6000mm long socket & spigot


6.2 Nos 8
pipe

6.3 150mm diameter 6000mm long socket & spigot Nos 10


pipe

7 DI(DI/PVC) Step Coupling


7.1 80mm/90mm(DI/PVC ) DI step coupling Nos 22
7.2 100mm/110mm(DI/PVC ) DI step coupling Nos 21
7.3 150mm/160mm(DI/PVC ) DI step coupling Nos 18
7.4 200mm/225mm(DI/PVC ) DI step coupling Nos 4

8 DI Double Flanged Bend


150mm diameter DI 90o double flanged bend (long
8.1 radius) Nos 2
8.2 100mm diameter DI 45o double flanged bend Nos 16
100mm diameter DI 90o double flanged bend (long
8.3 radius) Nos 2

80mm diameter DI 90o double flanged bend (long


8.4 Nos 2
radius)
8.5 80mm diameter DI 45o double flanged bend Nos 4

9 DI All Fanged Tee


9.1 150mm x 50mm diameter all flanged tee Nos 3
9.2 100mm x 50mm diameter all flanged tee Nos 6
9.3 80mm x 50mm diameter all flanged tee Nos 1

10 DI Double Orifice Air Valve


50mm diameter flanged DI double orifice air valve
10.1 with Nos 5
isolating cock/valve(fixed to flange branch)

11 DI Single Orifice Air Valve


50mm diameter flanged DI single orifice air valve
11.1 with Nos 5
isolating cock/valve(fixed to flange branch)
25mm diameter DI single orifice screwed down
11.2 type Nos 7
(with isolating cock) air valve

12 DI Double Flanged Sluice Valve


80mm diameter DI double flanged sluice
12.1 Nos 7
valve(knob type)

13 DI Flange Adaptor
13.1 80mm/90mm DI flange adaptor Nos 11
13.2 100mm/110mm DI flange adaptor Nos 8
13.3 150mm/1600mm DI flange adaptor Nos 10
13.4 200mm/225mm DI flange adaptor Nos 2
ITEM RATE (Rs.)
NO. DESCRIPTION UNIT QTY AMOUNT (Rs.)

14 DI Manhole Covers for Valve Chambers


Heavy duty Lockable, 600mm diameter Clear
Opening
14.1 Square frame D-400(WV embedded on top of Nos 7
manhole lid)
(non-ventilated type)

Heavy duty Lockable, 600mm diameter Clear


Opening
14.2 Square frame D-400(SV embedded on top of Nos 14
manhole lid)
(non-ventilated type)

Heavy duty Lockable, 600mm diameter Clear


Opening
14.3 Square frame D-400(DOAV embedded on top of Nos 5
manhole lid)
(ventilated type)

Heavy duty Lockable, 600mm diameter Clear


Opening
14.4 Square frame D-400(SOAV embedded on top of Nos 7
manhole lid)
(ventilated type)

15 DI Double Flanged Gate Valve


15.1 80mm diameter DI double flanged gate valve(knob t Nos 4
15.2 100mm diameter DI double flanged gate valve(knob Nos 4
15.3 150mm diameter DI double flanged gate valve(knob Nos 4
15.4 200mm diameter DI double flanged gate valve(knob Nos 2

Brass Clamp Saddle with gunmetal thread


16 inside
90mmx25mm Brass clamp saddle with gunmetal
16.1 thread inside Nos 3

16.2 110mmx25mm Brass clamp saddle with gunmetal Nos 1


thread inside
160mmx25mm Brass clamp saddle with gunmetal
16.3 Nos 2
thread inside
225mmx25mm Brass clamp saddle with gunmetal
16.4 thread inside Nos 1

25mm diameter Stainless steel pipe of 150mm


17 long both sides threaded(suit to 25mm Nos 7
diameter DI single orifice screwed down type
(with isolating cock) air valve)

18 DI Couplings
150mm diameter DI coupling Nos 1

Stainless Steel Pipe Brackets(50mmx6mm),


Stainless Steel Rag bolts(12mmdiameter),
19 Stainless Steel Nuts with Washers(suit to 12mm
rag bolt) and 10mm thick neoprene belts suit to
brackets
19.1 SS PipeBrackets suit to 80mm Di pipe Nos 5
19.2 SS PipeBrackets suit to 100mm Di pipe Nos 18
ITEM RATE (Rs.)
NO. DESCRIPTION UNIT QTY AMOUNT (Rs.)

19.3 12mm diameter SS ragbolt with SS nut & SS washer Nos 46


19.4 25mmx10mmxLength neoprene belts Nos 25
Note:Please refer the Drawings included in the
related Bid Document

Total Amount LKR

Grand Total:
……………………………………………………………………………………………….
Amount in words(withjout VAT):
……………………………………………………………………………………………….
Contractors Name:
……………………………………………………………………………………………….
Contractors Signature:

Witness 01:
……………………………………………………………………………………………….
Witness 02:
……………………………………………………………………………………………….
VAT registration No:
……………………………………………………………………………………………….

Company Seal
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
TOTAL PIPE FITTING

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Description DPR Date Zone No DPR No IPC NO nos Total Remark
No
PIPE FITTING
FIXING OF FITTINGS (All uPVC fittings
4.00 are to be Type PNT 11)

4.2 225mm x 450 bends. 22.04.27 CO 43 IPC 18 1.00 1.00


Cumulative Claim 1.00
Previous Claim -
This Bill Claim 1.00

4.6 160mm x 450 bends. 22.04.27 CO 43 IPC 18 1.00 1.00


Cumulative Claim 1.00
Previous Claim -
This Bill Claim 1.00

4.10 110mm x 450 bends. 20.10.26 06 02 IPC 03 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

4.11 110mm x 22.500 bends. 20.09.24 03 17 IPC 02 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

4.12 110mm x 11.250 bends. 20.09.26 03 18 IPC 02 2.00


20.11.30 03 26 IPC 04 1.00 3.00
Cumulative Claim 3.00
Previous Claim 3.00
This Bill Claim -

4.13 90mm x 900 bends. 22.01.31 04 78 IPC 15 1.00


14.02.22 04 82 IPC 16 1.00 2.00
Cumulative Claim 2.00
Previous Claim 2.00
This Bill Claim -

4.14 90mm x 450 bends. 20.08.26 03 03 IPC 02 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

4.15 90mm x 22.500 bends. 20.08.26 03 03 IPC 02 1.00


20.09.10 03 06 IPC 02 2.00
20.11.9 01 07 IPC 04 1.00
20.11.13 04 09 IPC 04 1.00 5.00
Cumulative Claim 5.00
Previous Claim 5.00
This Bill Claim -
Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per
Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
TOTAL PIPE FITTING

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Description DPR Date Zone No DPR No IPC NO nos Total Remark
No
……………………………… ……………………………………… ………………………………………………………… ……………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
4.17 63mm x 900 bends. 21.02.02 04 37 IPC 06 1.00
21.03.13 04 51 IPC 07 1.00
21.08.11 01 29 IPC 11 1.00 3.00
Cumulative Claim 3.00
Previous Claim 3.00
This Bill Claim -

4.18 63mm x 450 bends. 21.08.03 02 08 IPC 11 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

4.28 160 x 90mm uPVC Tee 22.03.24 GM 52 IPC 18 1.00 1.00


Cumulative Claim 1.00
Previous Claim -
This Bill Claim 1.00

4.30 110 x 110mm uPVC Tee 20.10.15 03 22 IPC 03 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

4.31 110 x 90 mm uPVC Tee 20.09.23 03 16 IPC 02 1.00


20.11.28 04 26 IPC 04 1.00
20.12.09 CT 11 IPC 04 1.00
20.12.10 CT 12 IPC 04 1.00
20.12.11 CT 13 IPC 04 1.00
20.12.12 CT 14 IPC 04 1.00
20.12.16 CT 15 IPC 04 1.00
21.04.02 04 64 IPC 08 1.00
21.04.05 04 65 IPC 08 1.00 9.00
Cumulative Claim 9.00
Previous Claim 9.00
This Bill Claim -

4.32 110 x 63mm uPVC Tee 20.09.24 03 17 IPC 02 1.00


20.10.08 03 19 IPC 03 1.00
20.11.28 03 25 IPC 04 1.00
20.11.30 03 26 IPC 04 1.00
21.03.27 04 57 IPC 07 1.00 5.00
Cumulative Claim 5.00
Previous Claim 5.00
This Bill Claim -

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per
Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
TOTAL PIPE FITTING

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Description DPR Date Zone No DPR No IPC NO nos Total Remark
No

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
4.33 90 x 90 mm uPVC Tee 20.09.19 03 13 IPC 02 1.00
20.11.7 01 06 IPC 04 1.00
20.11.12 04 08 IPC 04 1.00
20.11.13 04 09 IPC 04 1.00
20.11.24 04 18 IPC 04 1.00
21.12.21 02 61 IPC 14 1.00
21.12.22 CO 25 IPC 14 1.00
22.01.15 CO 36 IPC 15 1.00
22.03.15 01 82 IPC 18 1.00 9.00
Cumulative Claim 9.00
Previous Claim 8.00
This Bill Claim 1.00

4.34 90 x 63mm uPVC Tee 20.09.21 03 14 IPC 02 1.00


20.11.13 04 09 IPC 04 1.00
20.11.20 04 15 IPC 04 1.00
21.03.22 04 54 IPC 07 1.00
21.08.19 01 36 IPC 11 1.00
21.10.12 07 29 IPC 12 1.00
21.10.14 07 31 IPC 12 1.00
21.11.12 07 63 IPC 13 1.00
21.12.19 02 60 IPC 14 1.00
22.01.25 CO 37 IPC 15 1.00
22.02.01 04 79 IPC 16 1.00 11.00
Cumulative Claim 11.00
Previous Claim 11.00
This Bill Claim -

4.35 63 x 63 mm uPVC Tee 21.01.16 04 31 IPC 05 2.00


21.01.19 04 33 IPC 05 1.00
21.06.14 02 03 IPC 09 2.00
21.07.15 03 57 IPC 10 1.00 6.00
Cumulative Claim 6.00
Previous Claim 6.00
This Bill Claim -

4.45 110 -90 mm uPVC reducer 20.10.15 03 22 IPC 03 1.00


21.10.25 07 44 IPC 12 1.00 2.00
Cumulative Claim 2.00
Previous Claim 2.00
This Bill Claim -

4.37 160 dia uPVC Repair socket. 21.12.18 GM 31 IPC 14 1.00 1.00
Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per
Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
TOTAL PIPE FITTING

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Description DPR Date Zone No DPR No IPC NO nos Total Remark
No Checked & Recommanded as per the Checked & Certified as per
Contract the Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
4.40 63 dia uPVC Repair socket. 21.12.28 03 70 IPC 14 1.00
21.12.27 03 69 IPC 14 1.00
21.12.28 03 71 IPC 14 1.00
21.12.13 07 80 IPC 14 1.00
21.12.14 07 81 IPC 14 1.00
21.12.18 05 02 IPC 14 1.00 6.00
Cumulative Claim 6.00
Previous Claim 6.00
This Bill Claim -

4.46 110 -63 mm uPVC reducer. 21.12.27 03 69 IPC 14 1.00


21.12.28 03 71 IPC 14 1.00
21.12.13 07 80 IPC 14 1.00 3.00
Cumulative Claim 3.00
Previous Claim 3.00
This Bill Claim -

4.47 90 - 63 mm uPVC reducer. 21.12.28 03 70 IPC 14 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

4.50 160mm x 900 bends. 21.12.07 GM 14 IPC 14 1.00 1.00


22.03.24 GM 52 IPC 18 1.00 1.00
Cumulative Claim 2.00
Previous Claim 1.00
This Bill Claim 1.00

4.70 160mm x 22.500 bends. 22.01.11 GM 41 IPC 15 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

4.80 160mm x 11.250 bends. 21.12.23 CO 26 IPC 14 1.00


21.12.20 GM 32 IPC 14 2.00 3.00
Cumulative Claim 3.00
Previous Claim 3.00
This Bill Claim -

CROSSINGS
Crossing Type (D)
12.16 For 110 mm dia. PVC up to 6.0 m 21.04.23 01 18 IPC 08 1.00
21.09.30 07 19 IPC 12 1.00
21.10.08 07 27 IPC 12 1.00
21.10.22 07 39 IPC 12 1.00
21.10.22 07 39 IPC 12 1.00
21.10.30 07 53 IPC 12 1.00
21.11.27 07 68 IPC 13 1.00
21.11.29 07 70 IPC 13 1.00
21.11.27 07 72 IPC 14 1.00 9.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
TOTAL PIPE FITTING

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Description DPR Date Zone No DPR No IPC NO nos Total Remark
No
Cumulative Claim 9.00
Previous Claim 9.00
This Bill Claim -
Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per
Contract the Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
12.17 For 90 mm dia. PVC up to 6.0 m 21.03.29 04 58 IPC 08 1.00 1.00
Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -
17 MISCELLANEOUS
Excavation
17.1 Excavation of soft disintegrated rock
(No blasting required) in pipe trenches
(Provisional quantity)
21.12.19 03 69 0+019.9 0+027.9 2.88
21.12.19 03 69 0+087.9 0+099.9 4.43
21.12.31 03 73 0+081.3 0+069.7 3.48
22.01.07 GM 38 7+734 7+626 6.48
22.01.08 GM 39 7+626 7+530 6.75
22.01.23 GM 45 7+741 7+733 2.34
22.01.25 GM 47 4+693 4+705 3.24
22.01.26 GM 48 4+623.5 4+638.5 3.51
22.01.28 GM 49 4+573 4+581 2.16
22.01.31 GM 51 4+424.5 4+415.5 2.43
22.02.09 08 34 7+994.6 7+988.4 1.30
22.02.10 08 35 7+953.9 7+947.15 1.50
22.02.20 08 44 6+146.39 6+136.2 1.88
22.03.06 08 48 5+855.2 5+747.2 6.75
22.03.14 01 81 0+637 0+629 1.44
22.03.25 GM 53 5+141.62 5+243.62 3.13
22.04.27 CO 43 1+292.18 1+279.7 2.63
Cumulative Claim 56.33
Previous Claim 42.38
This Bill Claim 13.95
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
TOTAL PIPE FITTING

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Description DPR Date Zone No DPR No IPC NO nos Total Remark
No

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per
Contract the Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
1.00 PIPE WORK
1.1 PNT 11 - 160mm
Pipe Laying
4 68 21.03.03 0+312 0+324 m 12.00 12.00 12.00

Total Qty 12.00 12.00


90% of Pipe Laying Qty 10.80 - 10.80
05% of Pressure Testing Qty
Total Qty 10.80 10.80
As per the Previous Qty - IPC 10.80
Current Qty -

Checked & Recommanded as per the


Prepared Checked as per the Contract Contract Checked & Certified as per the Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Zone No DPR Location Previous Current


Description Unit Nos Length Breadth Depth Total Qty
No No From To Qty Qty
1.00 PIPE WORK
1.2 PNT 11 - 110mm
Pipe Laying
6 2 20.10.26 3+018.60 3+085.16 m 90.56 90.56 90.56
6 3 20.10.27 3+085.16 3+181.16 m 96.00 96.00 96.00
6 5 20.10.28 4+400.50 4+244.50 m 156.00 156.00 156.00
6 8 20.10.29 4+244.50 4+184.50 m 60.00 60.00 60.00
PM 5 20.11.02 1+770 1+866 m 96.00 96.00 96.00
PM 6 20.11.03 1+866 2+070 m 204.00 204.00 204.00
PM 7 20.11.04 2+070 2+160 m 90.00 90.00 90.00
PM 8 20.11.07 2+160 2+286 m 126.00 126.00 126.00
PM 9 20.11.23 2+286 2+310 m 24.00 24.00 24.00
PM 10 20.12.07 4+184.5 3+980.5 m 204.00 204.00 204.00
PM 11 20.12.08 3+980.5 3+884.5 m 96.00 96.00 96.00
PM 12 20.12.09 2+310 2+436 m 126.00 126.00 126.00
PM 13 20.12.10 2+436 2+550 m 114.00 114.00 114.00
PM 14 20.12.12 2+618.2 2+738.2 m 120.00 120.00 120.00
PM 15 20.12.14 2+738.2 2+822.2 m 84.00 84.00 84.00
PM 16 20.12.15 2+822.2 2+924.2 m 102.00 102.00 102.00
PM 17 20.12.16 2+924.2 3+020.2 m 96.00 96.00 96.00
PM 18 20.12.17 3+020.2 3+116.2 m 96.00 96.00 96.00
PM 19 20.12.18 3+116.2 3+152.2 m 36.00 36.00 36.00
Pressure Testing
PM 01 21.01.11 3+884.5 4+400.5 m 516.00 516.00 516.00
PM 02 21.01.11 2+994.6 3+181.16 m 186.56 186.56 186.56
PM 03 21.01.21 1+770.0 2+550.0 m 780.00 780.00 780.00
PM 04 21.01.26 2+618.2 3+152.2 m 534.00 534.00 534.00
Total Qty 2016.56 2016.56
90% of Pipe Laying Qty 1814.90 - 1814.90
05% of Pressure Testing Qty 100.83 100.83
Total Qty 1915.73 1915.73
As per the Previous Qty - IPC 1915.73
Current Qty -

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
……………………………… ……………………………………… ………………………………………………………… ……………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location
Item No Zone No DPR Description Unit Nos Length Breadth Depth Previous Current Total Qty
No Qty Qty
From To
2.00 PIPE WORK
2.2 PNT 7 - 160mm
Pipe Laying
GM 1 21.11.23 2+198.5 2+240.5 m 42.00 42.00 42.00
GM 2 21.11.25 2+240.5 2+294.5 m 54.00 54.00 54.00
GM 3 21.11.26 2+294.5 2+378.5 m 84.00 84.00 84.00
GM 4 21.11.27 2+378.5 2+426.5 m 48.00 48.00 48.00
GM 5 21.11.29 0+073 0+043 m 24.00 24.00 24.00
GM 8 21.11.29 4+945.00 4+921.00 m 30.00 30.00 30.00
GM 6 21.11.30 0+043 0+002.5 m 36.00 36.00 36.00
GM 7 21.12.01 6+750 6+642 m 108.00 108.00 108.00
GM 9 21.12.04 6+642 6+522 m 120.00 120.00 120.00
GM 10 21.12.05 2+426.5 2+432.5 m 6.00 6.00 6.00
GM 11 21.12.06 6+522 6+450 m 72.00 72.00 72.00
GM 12 21.12.07 3+409.2 3+547.2 m 138.00 138.00 138.00
GM 13 21.12.07 2+432.5 2+492.5 m 60.00 60.00 60.00
GM 14 21.12.07 4+945 4+994.21 m 48.00 48.00 48.00
GM 15 21.12.08 3+547.2 3+697.2 m 150.00 150.00 150.00
GM 16 21.12.08 2+492.5 2+582.5 m 90.00 90.00 90.00
GM 17 21.12.08 4+994.21 5+042.21 m 48.00 48.00 48.00
GM 18 21.12.09 2+582.5 2+702.5 m 120.00 120.00 120.00
GM 19 21.12.09 3+697.2 3+877.2 m 180.00 180.00 180.00
GM 20 21.12.10 3+877.2 3+997.2 m 120.00 120.00 120.00
GM 21 21.12.10 0+696 0+654 m 42.00 42.00 42.00
GM 22 21.12.10 0+622.3 0+580.3 m 42.00 42.00 42.00
GM 23 21.12.11 0+580.3 0+526.3 m 54.00 54.00 54.00
GM 24 21.12.11 3+997.2 4+195.2 m 198.00 198.00 198.00
GM 25 21.12.11 0+492.3 0+438.5 m 54.00 54.00 54.00
Total C/F 1,968.00 1,968.00

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location
Item No Zone No DPR Description Unit Nos Length Breadth Depth Previous Current Total Qty
No Qty Qty
From To

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 1968.00 1968.00
GM 26 21.12.13 3+409.2 3+199.2 m 210.00 210.00 210.00
GM 27 21.12.13 0+438.5 0+304.5 m 114.00 114.00 114.00
GM 28 21.12.14 3+199.2 3+074.2 m 120.00 120.00 120.00
GM 29 21.12.16 2+715.5 2+865.5 m 150.00 150.00 150.00
GM 30 21.12.17 2+865.5 2+955.5 m 90.00 90.00 90.00
GM 31 21.12.18 2+955.5 3+074.2 m 25.00 25.00 25.00
GM 32 21.12.20 2+190 2+105.48 m 83.00 83.00 83.00
CO 24 21.12.21 2+007.48 2+055.48 m 48.00 48.00 48.00
CO 25 21.12.22 1+851.48 1+803.48 m 48.00 48.00 48.00
CO 26 21.12.23 1+803.48 1+700.72 m 102.00 102.00 102.00
CO 27 21.12.27 1+700.72 1+610.72 m 90.00 90.00 90.00
CO 28 21.12.28 1+610.72 1+538.72 m 72.00 72.00 72.00
CO 29 21.12.29 1+538.08 1+490.72 m 48.00 48.00 48.00
GM 33 21.12.29 6+032.7 6+092.7 m 60.00 60.00 60.00
CO 30 21.12.30 1+490.72 1+430.72 m 60.00 60.00 60.00
GM 34 21.12.30 6+092.7 6+182.7 m 90.00 90.00 90.00
GM 35 21.12.31 6+182.7 6+296.7 m 114.00 114.00 114.00
CO 31 21.12.31 1+430.72 1+370.72 m 60.00 60.00 60.00
CO 32 22.01.01 1+375.98 1+363.98 m 6.00 6.00 6.00
GM 36 22.01.04 0+073 0+133 m 60.00 60.00 60.00
GM 37 22.01.05 7+854 7+734 m 120.00 120.00 120.00
GM 38 22.01.07 7+734 7+626 m 108.00 108.00 108.00
GM 39 22.01.08 7+626 7+530 m 96.00 96.00 96.00
GM 40 22.01.10 6+750 6+918 m 168.00 168.00 168.00
GM 41 22.01.11 6+966.4 7+045.23 m 78.00 78.00 78.00
CO 33 22.01.12 1+363.98 1+261.98 m 102.00 102.00 102.00
Total C/F 4,290.00 - 4,290.00

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location
Item No Zone No DPR Description Unit Nos Length Breadth Depth Previous Current Total Qty
No Qty Qty
From To

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 4,290.00 - 4,290.00
CO 34 22.01.13 1+262.72 1+172.72 m 90.00 90.00 90.00
CO 35 22.01.14 1+117.52 1+045.92 m 72.00 72.00 72.00
CO 36 22.01.15 1+045.92 0+901.52 m 144.00 144.00 144.00
GM 42 22.01.19 4+921 4+849 m 72.00 72.00 72.00
GM 43 22.01.20 4+849 4+777 m 72.00 72.00 72.00
GM 44 22.01.22 6+450 6+414 m 36.00 36.00 36.00
GM 45 22.01.23 4+777 4+723 m 54.00 54.00 54.00
GM 46 22.01.24 6+414 6+318 m 96.00 96.00 96.00
GM 47 22.01.25 4+723 4+657 m 66.00 66.00 66.00
CO 37 22.01.25 0+900.78 0+792.78 m 108.00 108.00 108.00
CO 38 22.01.26 0+792.78 0+726.78 m 66.00 66.00 66.00
CO 39 22.01.26 0+342.5 0+372.5 m 30.00 30.00 30.00
GM 48 22.01.26 4+657 4+609 m 48.00 48.00 48.00
GM 49 22.01.28 4+594.5 4+498.5 m 96.00 96.00 96.00
GM 51 22.01.31 4+438.5 4+390.5 m 48.00 48.00 48.00
GM 52 24.03.22 5+050.21 5+141.62 m 91.41 90.00 90.00
GM 53 25.03.22 5+141.62 5+243.62 m 102.00 102.00 102.00
Pressure Testing
GM 5 22.02.01 6+918.0 6+318.0 m 600.00 600.00 600.00
GM 6 22.02.09 2+055.0 1+172.72 m 882.76 882.76 882.76
GM 7 2+715.5 2+980.5 m 379.00 379.00
22.02.17 379.00
3+074.2 3+188.2 m - -
GM 8 22.02.18 7+854.0 7+530.0 m 324.00 324.00 324.00
GM 10 22.02.12 1+117.52 0+727.57 m 389.95 389.95 389.95
GM 4 22.01.24 3+193.2 4+195.2 m 1,002.00 1,002.00 1,002.00
Total Qty 5,388.00 192.00 5,580.00
90% of Pipe Laying Qty 4,849.20 172.80 5,022.00
05% of Pressure Testing Qty 178.89 - 178.89
Total Qty 5,028.09 172.80 5,200.89
As per the Previous Qty - IPC 5,028.09
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location
Item No Zone No DPR Description Unit Nos Length Breadth Depth Previous Current Total Qty
No Qty Qty
From To
Current Qty 172.80

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
2.00 PIPE WORK
2.3 PNT 7 - 110mm
Pipe Laying
3 16 20.09.23 0+000 0+089.075 m 89.08 89.08 89.08
3 17 20.09.24 0+089.075 0+139.288 m 50.21 50.21 50.21
3 18 20.09.26 0+139.288 0+182.288 m 43.00 43.00 43.00
3 19 20.10.08 0+182.28 0+326.56 m 144.33 144.33 144.33
3 20 20.10.09 0+326.56 0+482.56 m 156.00 156.00 156.00
3 21 20.10.13 0+482.56 0+632.56 m 150.00 150.00 150.00
4 26 20.11.28 0+012.4 0+162.52 m 150.00 150.00 150.00
3 25 20.11.28 0+632.56 0+812.68 m 180.00 180.00 180.00
3 26 20.11.30 0+812.68 0+903.535 m 222.00 222.00 222.00
3 27 20.12.01 1+123.5 1+153.535 m 210.00 210.00 210.00
3 28 20.12.02 1+360.535 1+480.535 m 120.00 120.00 120.00
1 9 21.03.11 -(0+793) -(0+715) m 78.00 78.00 78.00
1 10 21.03.12 -(0+715) -(0+637) m 78.00 78.00 78.00
1 11 21.03.13 -(0+637) -(0+571) m 66.00 66.00 66.00
1 12 21.03.17 -(0+571) -(0+487) m 84.00 84.00 84.00
1 13 21.03.18 -(0+487) -(0+439) m 48.00 48.00 48.00
1 14 21.03.19 0+128 0+182 m 54.00 54.00 54.00
1 15 21.03.20 0+182 0+260 m 78.00 78.00 78.00
1 16 21.03.22 0+260 0+308 m 48.00 48.00 48.00
1 17 21.03.23 0+308 0+314 m 6.00 6.00 6.00
4 57 21.03.27 2+179.8 2+263.92 m 84.12 84.12 84.12
4 59 21.03.29 2+263.92 2+341.92 m 78.00 78.00 78.00
4 60 21.03.30 2+341.92 2+371.92 m 30.00 30.00 30.00
4 62 21.03.31 2+371.92 2+395.92 m 24.00 24.00 24.00
4 64 21.04.02 0+162.52 0+252.64 m 90.00 90.00 90.00
Total C/F 2,360.74 2,360.74

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 2360.74 2,360.74
4 65 21.04.05 0+252.64 0+306.76 m 54.00 54.00 54.00
4 66 21.04.07 0+306.76 0+402.76 m 96.00 96.00 96.00
1 18 21.04.23 0+314.00 0+386.00 m 72.00 72.00 72.00
1 19 21.04.24 0+386.00 0+416.00 m 30.00 30.00 30.00
7 42 21.10.23 4+452 4+608 m 156.00 156.00 156.00
7 44 21.10.25 4+608 4+734 m 126.00 126.00 126.00
Pressure Testing
3 1 20.12.22 0+000 0+903.535 m 903.54 903.54 903.54
3 4 21.01.11 1+180.56 1+480.56 m 300.00 300.00 300.00
3 5 21.01.11 0+991.56 1+153.56 m 162.00 162.00 162.00
1 2 21.06.29 0+793 0+439 m 354.00 354.00 354.00
4 18 21.07.19 0+012.4 0+402.76 m 390.36 390.36 390.36
1 4 21.10.07 0+128 0+416 m 288.00 288.00 288.00
7 10 21.11.16 4+452 5+628.1 m 282.00 282.00 282.00

Total Qty 2894.74 2894.74


90% of Pipe Laying Qty 2605.26 - 2605.26
05% of Pressure Testing Qty 133.99 133.99
Total Qty 2739.26 2739.26
As per the Previous Qty - IPC 2739.26
Current Qty -

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
2.00 PIPE WORK
2.4 PNT 7 - 90mm
Pipe Laying
3 1 20.08.24 0+015.00 0+105.00 m 90.00 90.00 90.00
3 2 20.08.25 0+105.00 0+237.00 m 132.00 132.00 132.00
4 1 20.08.25 0+358.4 0+322.4 m 36.00 36.00 36.00
3 3 20.08.26 0+237.00 0+359.90 m 122.97 122.97 122.97
3 4 20.08.27 0+359.90 0+545.90 m 186.00 186.00 186.00
3 5 20.08.28 0+545.90 0+617.90 m 72.00 72.00 72.00
3 6 20.09.10 0+617.90 0+648.97 m 31.00 31.00 31.00
3 6 20.09.10 0+991.50 1+093.50 m 102.00 102.00 102.00
3 7 20.09.11 1+093.50 1+303.50 m 210.00 210.00 210.00
3 8 20.09.12 1+303.50 1+435.50 m 132.00 132.00 132.00
3 9 20.09.14 1+435.50 1+645.50 m 210.00 210.00 210.00
3 10 20.09.15 1+645.50 1+813.50 m 168.00 168.00 168.00
3 11 20.09.16 0+648.94 0+888.94 m 240.00 240.00 240.00
3 12 20.09.18 0+888.94 0+978.94 m 168.00 168.00 168.00
3 13 20.09.19 1+000.00 1+192.00 m 192.00 192.00 192.00
3 14 20.09.21 1+192.00 1+408.328 m 216.32 216.32 216.32
3 15 20.09.23 1+408.328 1+504.328 m 96.00 96.00 96.00
2 1 20.09.24 0+000.00 0+162.00 m 162.00 162.00 162.00
2 2 20.09.25 0+162.00 0+264.00 m 102.00 102.00 102.00
3 12 20.09.18 0+888.94 0+978.94 m (168.00) (168.00) (168.00)
3 12 20.09.18 0+888.94 0+978.94 m 90.00 90.00 90.00
4 2 20.09.30 0+000.00 0+270.00 m 270.00 270.00 270.00
4 3 20.10.02 0+270.00 0+348.00 m 78.00 78.00 78.00
4 3 20.10.02 0+322.40 0+214.40 m 108.00 108.00 108.00
4 4 20.10.03 0+214.40 0+022.40 m 192.00 192.00 192.00
Total C/F 3,238.29 3,238.29

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 3238.29 3,238.29
4 5 20.10.05 0+000.00 0+198.00 m 198.00 198.00 198.00
4 6 20.10.06 0+198.00 0+330.00 m 132.00 132.00 132.00
4 6 20.10.06 0+000.00 0+018.00 m 18.00 18.00 18.00
3 22 20.10.15 0+000.00 0+096.375 m 96.38 96.38 96.38
3 23 20.10.16 0+096.375 0+336.375 m 240.00 240.00 240.00
3 24 20.10.17 0+586.70 0+460.70 m 126.00 126.00 126.00
1 1 20.10.31 0+306.00 0+426.00 m 120.00 120.00 120.00
1 2 20.11.2 0+426 0+606 m 180.00 180.00 180.00
1 3 20.11.3 0+606 0+732 m 180.00 180.00
180.00
1 3 20.11.3 0+000.0 0+054 m - -
1 4 20.11.5 0+113.2 0+131.2 m 66.00 66.00 66.00
1 4 20.11.5 0+054 0+102 m - -
1 5 20.11.6 0+131.2 0+257.2 m 126.00 126.00 126.00
1 6 20.11.7 0+257.2 0+419.528 m 168.00 168.00 168.00
1 6 20.11.7 0+000.0 0+006.00 m - -
1 7 20.11.9 0+419.528 0+443.528 m 24.00 24.00 24.00
1 7 20.11.9 0+006.00 0+174.44 m 168.00 168.00 168.00
1 8 20.11.11 0+174.44 0+264.44 m 90.00 90.00 90.00
4 7 20.11.11 0+008.6 0+080.6 m 72.00 72.00 72.00
4 8 20.11.12 0+214.40 0+260.6 m 180.00 180.00 180.00
4 9 20.11.13 0+260.6 0+464.6 m 201.80 201.80 201.80
4 10 20.11.14 0+000 0+149 m 149.00 149.00 149.00
4 11 20.11.16 0+336.375 0+173 m 24.00 24.00 24.00
4 11 20.11.16 0.+239.5 0.+341.5 m 102.00 102.00 102.00
4 12 20.11.17 0+000 0+233 m 233.00 233.00 233.00
4 12 20.11.17 0+282.2 0+294.2 m 12.00 12.00 12.00
Total C/F 6,144.46 6,144.46

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To & Recommanded as per the
Checked
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 6144.46 6,144.46
4 13 20.11.18 0+294.2 0+342.2 m 48.00 48.00 48.00
4 13 20.11.18 0+120 0+282 m 162.00 162.00 162.00
4 14 20.11.19 0+282 0+528 m 246.00 246.00 246.00
4 15 20.11.20 0+528 0+648.304 m 120.00 120.00 120.00
4 16 20.11.21 0+648.304 0+720.304 m 72.00 72.00 72.00
4 17 20.11.23 0+720.304 0+726.304 m 6.00 6.00 6.00
4 18 20.11.24 0+021 0+177.328 m 156.00 156.00 156.00
4 18 20.11.24 0+000 0+008.6 m 8.60 8.60 8.60
4 19 20.11.25 0+177.328 0+183.328 m 6.00 6.00 6.00
4 19 20.11.25 0+250.128 0+352.128 m 102.00 102.00 102.00
4 20 20.11.25 0+000 0+090 m 90.00 90.00 90.00
4 21 20.11.26 0+090 0+234 m 144.00 144.00 144.00
4 22 20.11.26 0+006.4 0+186.4 m 180.00 180.00 180.00
4 23 20.11.27 0+234 0+306 m 72.00 72.00 72.00
4 24 20.11.27 0+012.5 0+036.5 m 24.00 24.00 24.00
4 25 20.11.27 0+186.4 0+366.4 m 180.00 180.00 180.00
4 27 20.11.28 0+036.5 0+234.5 m 198.00 198.00 198.00
4 28 20.12.08 0+234.5 0+336.5 m 102.00 102.00 102.00
4 46 21.03.06 0+233 0+282.4 m 49.40 49.40 49.40
4 47 21.03.06 0+173 0+239.1 m 67.00 67.00 67.00
4 54 21.03.22 0+004.4 0+088.5 m 84.10 84.10 84.10
4 55 21.03.23 0+088.5 0+178.5 m 90.00 90.00 90.00
4 56 21.03.24 0+178.5 0+220.5 m 42.00 42.00 42.00
3 41 21.03.25 0+336.375 0+413.175 m 106.80 106.80 106.80
4 58 21.03.29 0+220.5 0+298.5 m 78.00 78.00 78.00
4 61 21.03.31 0+298.5 0+352.5 m 54.00 54.00 54.00
Total C/F 8,632.36 8,632.36
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 8632.36 8,632.36
4 63 21.04.01 0+352.5 0+400.5 m 48.00 48.00 48.00
4 67 21.04.18 0+009.7 0+033.7 m 24.00 24.00 24.00
1 20 21.04.27 0+006 0+084 m 78.00 78.00 78.00
1 21 21.04.28 0+084 0+120 m 36.00 36.00 36.00
1 22 21.04.29 0+120 0+150 m 30.00 30.00 30.00
1 23 21.04.30 0+150 0+222 m 72.00 72.00 72.00
1 24 21.05.03 0+222 0+234 m 12.00 12.00 12.00
4 69 21.05.03 0+010 0+130 m 120.00 120.00 120.00
4 70 21.05.04 0+130 0+208 m 78.00 78.00 78.00
4 71 21.05.06 0+208 0+334 m 126.00 126.00 126.00
4 72 21.05.07 0+014.5 0+068.5 m 54.00 54.00 54.00
4 73 21.05.08 0+068.5 0+158.5 m 90.00 90.00 90.00
3 46 21.05.08 0+000 0+004.2 m 4.20 4.20 4.20
4 74 21.05.10 0+158.5 0+248.5 m 90.00 90.00 90.00
4 75 21.06.11 0+025.2 0+085.2 m 60.00 60.00 60.00
4 76 21.06.12 0+325.8 0+271.8 m 54.00 54.00 54.00
7 1 21.06.21 7+820.8 7+730.8 m 90.00 90.00 90.00
7 2 21.06.22 7+730.8 7+597.8 m 108.00 108.00 108.00
7 3 21.06.26 7+945 7+777 m 168.00 168.00 168.00
7 4 21.06.28 7+777 7+711 m 66.00 66.00 66.00
7 5 21.06.30 7+597.8 7+489.8 m 108.00 108.00 108.00
7 6 21.07.01 7+489.8 7+387.8 m 102.00 102.00 102.00
7 7 21.08.11 7+387.8 7+279.8 m 108.00 108.00 108.00
7 8 21.08.12 7+279.8 7+207.8 m 72.00 72.00 72.00
7 9 21.08.13 7+207.8 7+135.8 m 72.00 72.00 72.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
7 10 21.08.14 7+135.8 7+045.8 m 90.00 90.00 90.00
Total C/F 10,592.56 10,592.56

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 10592.56 10,592.56
4 75 21.08.19 0+010 0+000 m 10.00 10.00 10.00
1 36 21.08.19 1+234 1+179.9 m 54.10 54.10 54.10
1 37 21.08.20 1+179.9 1+143.9 m 36.00 36.00 36.00
7 11 21.08.21 7+045.8 6+967.8 m 78.00 78.00 78.00
7 12 21.08.23 6+967.8 6+877.8 m 90.00 90.00 90.00
7 13 21.08.24 6+877.8 6+775.8 m 102.00 102.00 102.00
7 14 21.08.25 6+775.8 6+703.8 m 72.00 72.00 72.00
7 15 21.09.07 6+686.3 6+656.3 m 30.00 30.00 30.00
7 16 21.09.27 6+656.3 6+596.3 m 60.00 60.00 60.00
7 17 21.09.28 6+596.3 6+494.3 m 102.00 102.00 102.00
7 18 21.09.29 6+494.3 6+428.3 m 66.00 66.00 66.00
7 19 21.09.30 6+428.3 6+380.3 m 48.00 48.00 48.00
7 20 21.10.01 6+380.3 6+368.3 m 12.00 12.00 12.00
7 21 21.10.02 7+630.1 7+612.1 m 18.00 18.00 18.00
7 22 21.10.02 6+368.3 6+278.3 m 90.00 90.00 90.00
7 23 21.10.05 6+278.3 6+128.3 m 150.00 150.00 150.00
7 24 21.10.06 7+612.1 7+576.1 m 36.00 36.00 36.00
7 25 21.10.06 6+128.3 6+044.3 m 84.00 84.00 84.00
7 26 21.10.07 6+044.3 5+864.3 m 180.00 180.00 180.00
7 27 21.10.08 5+864.3 5+696.3 m 168.00 168.00 168.00
7 28 21.10.11 5+696.3 5+535.0 m 138.00 138.00 138.00
1 38 21.10.11 1+143.9 1+95.9 m 48.00 48.00 48.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
1 39 21.10.12 1+95.9 1+77.90 m 18.00 18.00 18.00
7 29 21.10.12 5+535.0 5+356.4 m 126.00 126.00 126.00
7 30 21.10.13 5+356.4 5+116.4 m 240.00 240.00 240.00
1 40 21.10.13 0+234 0+258 m 24.00 24.00 24.00
Total C/F 12,672.66 12,672.66

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 12672.66 12,672.66
1 41 21.10.14 0+258 0+348 m 90.00 90.00 90.00
7 31 21.10.14 5+116.4 4+972.3 m 144.00 144.00 144.00
1 42 21.10.15 0+348 0+426 m 78.00 78.00 78.00
7 32 21.10.15 4+972.3 4+797.3 m 156.00 156.00 156.00
7 36 21.10.21 7+576.1 7+510.1 m 66.00 66.00 66.00
7 38 21.10.21 4+791.3 4+498.3 m 234.00 234.00 234.00
7 39 21.10.22 4+498.3 4+324.3 m 174.00 174.00 174.00
7 40 21.10.22 7+510.1 7+426.1 m 84.00 84.00 84.00
7 43 21.10.23 7+411.1 7+273.1 m 138.00 138.00 138.00
7 44 21.10.25 4+734 4+748 m 24.00 24.00 24.00
7 45 21.10.25 7+273.1 7+123.1 m 150.00 150.00 150.00
7 46 21.10.26 4+758 4+902 m 144.00 144.00 144.00
7 47 21.10.26 7+123.1 7+063.1 m 60.00 60.00 60.00
7 48 21.10.28 4+902 5+028 m 126.00 126.00 126.00
7 50 21.10.29 5+028 5+220 m 192.00 192.00 192.00
7 51 21.10.29 7+063.1 6+925.1 m 138.00 138.00 138.00
7 53 21.10.30 5+220 5+292 m 72.00 72.00 72.00
7 54 21.10.30 6+925.1 6+781.1 m 114.00 114.00 114.00
7 56 21.10.31 6+781.1 6+721.1 m 60.00 60.00 60.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
7 61 21.11.04 5+292 5+352 m 60.00 60.00 60.00
1 43 21.11.04 1+672 1+588 m 84.00 84.00 84.00
1 44 21.11.05 1+588 1+390 m 198.00 198.00 198.00
1 45 21.11.06 1+390 1+228 m 162.00 162.00 162.00
1 46 21.11.06 0+846 0+702 m 144.00 144.00 144.00
7 62 21.11.06 5+352 5+532 m 180.00 180.00 180.00
7 63 21.11.12 5+532 5+628.1 m 96.00 96.00 96.00
Total C/F 15,840.66 15,840.66

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 15840.66 15,840.66
1 47 21.11.19 0+001.7 0+076.3 m 78.00 78.00 78.00
7 65 21.11.21 6+685.1 6+577.1 m 108.00 108.00 108.00
7 66 21.11.22 6+559.1 6+451.1 m 108.00 108.00 108.00
7 67 21.11.23 6+451.1 6+343.2 m 90.00 90.00 90.00
3 67 21.11.26 0+006 0+108 m 102.00 102.00 102.00
7 68 21.11.27 6+343.2 6+247.2 m 96.00 96.00 96.00
3 68 21.11.27 0+108 0+138 m 30.00 30.00 30.00
7 69 21.11.28 6+247.2 6+139.2 m 108.00 108.00 108.00
7 70 21.11.29 6+139.2 6+031.2 m 108.00 108.00 108.00
7 71 21.11.30 6+031.2 5+995.2 m 36.00 36.00 36.00
7 72 21.12.01 5+995.2 5+905.2 m 90.00 90.00 90.00
7 73 21.12.02 5+905.2 5+821.2 m 84.00 84.00 84.00
7 74 21.12.03 5+759.2 5+663.2 m 96.00 96.00 96.00
7 75 21.12.04 5+663.2 5+639.2 m 24.00 24.00 24.00
1 48 21.12.06 1+228 1+102 m 126.00 126.00 126.00
7 76 21.12.07 5+639.2 5+537.2 m 102.00 102.00 102.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
1 49 21.12.07 1+102 0+970 m 132.00 132.00 132.00
7 77 21.12.08 5+537.2 5+495.2 m 42.00 42.00 42.00
1 50 21.12.08 0+970 0+862 m 108.00 108.00 108.00
7 78 21.12.09 5+495.2 5+375.2 m 120.00 120.00 120.00
1 51 21.12.09 0+862 0+778 m 84.00 84.00 84.00
1 52 21.12.09 0+720 0+660 m 60.00 60.00 60.00
7 79 21.12.10 5+375.2 5+339.2 m 36.00 36.00 36.00
1 53 21.12.10 0+598.5 0+467.5 m 126.00 126.00 126.00
Total C/F 17,934.66 17,934.66

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 17934.66 17,934.66
1 54 21.12.11 0+467.5 0+443.5 m 24.00 24.00 24.00
1 55 21.12.12 0+443.5 0+347.5 m 96.00 96.00 96.00
1 56 21.12.13 0+347.5 0+245.5 m 102.00 102.00 102.00
1 57 21.12.14 0+245.5 0+143.5 m 102.00 102.00 102.00
1 58 21.12.15 0+143.5 0+017.5 m 126.00 126.00 126.00
2 9 21.12.17 0+076.30 0+232.3 m 156.00 156.00 156.00
3 69 21.12.19 0+007.9 0+157.9 m 150.00 150.00 150.00
2 60 21.12.19 0+232.3 0+377.4 m 145.00 145.00 145.00
2 63 21.12.20 0+377.4 0+467.4 m 90.00 90.00 90.00
2 61 21.12.21 0+467.4 0+476.8 m 93.00 93.00 93.00
3 71 21.12.21 0+018 0+084 m 66.00 66.00 66.00
3 70 21.12.21 0+157.90 0+249.70 m 42.00 42.00 42.00
2 62 21.12.22 0+542.80 0+476.80 m 66.00 66.00 66.00
CO 26 21.12.23 1+736.08 1+688.08 m 48.00 48.00 48.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
CO 27 21.12.27 1+688.08 1+604.08 m 84.00 84.00 84.00
CO 28 21.12.28 1+604.08 1+526.08 m 78.00 78.00 78.00
CO 29 21.12.29 1+526.08 1+484.08 m 42.00 42.00 42.00
CO 30 21.12.30 1+484.08 1+429.98 m 54.00 54.00 54.00
CO 31 21.12.31 1+429.72 1+375.98 m 54.00 54.00 54.00
Total C/F 19,552.66 19,552.66

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

Total B/F 19552.66 19,552.66


6 3 22.01.01 1+637 1+601 m 36.00 36.00 36.00
CO 32 22.01.01 1+370.72 1+364.72 m 12.00 12.00 12.00
6 4 22.01.02 1+601 1+408 m 102.00 102.00 102.00
CO 33 22.01.12 1+375.98 1+273.98 m 102.00 102.00 102.00
CO 34 22.01.13 1+261.98 1+171.98 m 90.00 90.00 90.00
CO 35 22.01.14 1+115.58 1+061.58 m 54.00 54.00 54.00
CO 36 22.01.15 1+061.52 0+905.48 m 156.00 156.00 156.00
1 61 22.01.17 0+022.5 0+142.5 m 120.00 120.00 120.00
6 5 22.01.18 1+408 1+294 m 72.00 72.00 72.00
1 62 22.01.18 0+142.5 0+244.5 m 102.00 102.00 102.00
1 63 22.01.19 0+244.5 0+358.5 m 114.00 114.00 114.00
1 64 22.01.20 0+358.5 0+478.5 m 120.00 120.00 120.00
1 65 22.01.21 0+478.5 0+628.5 m 150.00 150.00 150.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
1 66 22.01.22 0+628.5 0+754.5 m 126.00 126.00 126.00
1 67 22.01.23 0+754.5 0+862.5 m 108.00 108.00 108.00
1 68 22.01.24 0+862.5 0+976.5 m 114.00 114.00 114.00
CO 37 22.01.25 0+921.68 0+813.58 m 108.00 108.00 108.00
CO 38 22.01.26 0+813.58 0+747.58 m 66.00 66.00 66.00
CO 39 22.01.26 0+719.58 0+689.58 m 30.00 30.00 30.00
1 69 22.01.26 0+976.5 1+096.50 m 120.00 120.00 120.00
1 70 22.01.29 1+096.50 1+216.5 m 120.00 120.00 120.00
1 71 22.01.30 1+216.5 1+342.5 m 126.00 126.00 126.00
4 78 22.01.31 0+400.5 0+408.5 m 90.00 90.00 90.00

Total C/F 21,790.66 - 21,790.66

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 21790.66 21,790.66
4 79 22.02.01 0+087.235 0+164.035 m 78.10 78.10 78.10
0+000.00 0+001.3 m
4 80 22.02.02 0+001.3 0.055.3 m 54.00 54.00 54.00
4 81 22.02.03 0+055.3 0+115.3 m 60.00 60.00 60.00
1 72 22.02.10 1+342.5 1+450.5 m 108.00 108.00 108.00
1 73 22.02.11 1+450.5 1+528.5 m 78.00 78.00 78.00
1 74 22.02.12 1+528.5 1+618.5 m 90.00 90.00 90.00
4 82 22.02.14 0+115.3 0+230.03 m 114.74 114.74 114.74
1 75 22.02.14 1+618.5 1+630.5 m 12.00 12.00 12.00
1 76 22.02.25 1+630.5 1+672.5 m 54.00 54.00 54.00
0+022.5 0+010.5 m
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
1 80 09.03.22 0+702.0 0+672.0 m 30.00 30.00 30.00
1 81 14.03.22 0+672.0 0+606.0 m 66.00 66.00 66.00
1 82 15.03.22 0+606.0 0+521.9 m 84.10 84.00 84.00
1 83 18.03.22 0+521.9 0+383.9 m 138.00 138.00 138.00
4 83 20.03.22 0+120.0 0+036.0 m 84.00 84.00 84.00
4 84 21.03.22 0+036.0 0+012.0 m 24.00 24.00 24.00

Total C/F 22,439.50 426.00 22,865.50

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 22,439.50 426.00 22,865.50
Pressure Testing
3 2 20.12.22 0+460.7 0+586.7 m 126.00 126.00 126.00
3 3 20.12.22 0+015 0+978.97 m 963.97 963.97 963.97
4 1 20.12.23 0+022.4 0+358.4 m 336.00 336.00 336.00
4 2 20.12.23 0+000 0+330 m 330.00 330.00 330.00
4 3 20.12.23 0+000 0+348 m 348.00 348.00 348.00
4 4 20.12.31 0+000 0+306 m 306.00 306.00 306.00
4 5 21.01.11 0+012.5 0+336.5 m 324.00 324.00 324.00
3 6 21.01.11 0+545.9 0+617.9 m 72.00 72.00 72.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
2 1 21.01.11 0+000 0+264 m 264.00 264.00 264.00
1 1 21.02.24 0+306 0+732 m 426.00 426.00 426.00
3 12 21.3.31 0+000 0+413.175 m 413.18 413.18 413.18
4 19 21.07.19 0+004.4 0+400.5 m 396.10 396.10 396.10
4 20 21.07.19 0+009.7 0+345.7 m 336.00 336.00 336.00
4 21 21.08.24 0+000 0+334 m 334.00 334.00 334.00
4 22 21.08.27 0+264 0+464.7 m 200.70 200.70 200.70
4 22 21.08.27 0+000 0+342.4 m 342.40 342.40 342.40
4 23 21.08.28 0+000 0+264 m 264.00 264.00 264.00
4 23 21.08.28 0+000 0+342.0 m 342.00 342.00 342.00
4 23 21.08.28 0+003 0+180.1 m 180.00 180.00 180.00
1 7 21.10.21 0+006 0+426 m 420.00 420.00 420.00
7 1 21.10.26 7+820.8 7+652.6 m 162.00 162.00 162.00
7 2 21.10.26 7+633.8 6+703.8 m 930.00 930.00 930.00
Total C/F 7,816.35 426.00 7,816.35

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 7816.35 426.00 7,816.35
Pressure Testing
7 3 21.10.26 6+686.3 5+690.3 m 996.00 996.00 996.00
7 4 21.10.26 5+667 5+474.9 m 192.10 192.10 192.10
7 9 21.11.20 0+002 0+506 m 504.00 504.00 504.00
7 6 21.11.13 5+422.41 4+960.3 m 462.10 462.10 462.10
7 5 21.11.12 7+820.8 7+658.8 m 162.00 162.00 162.00
7 10 21.11.16 4+452 5+628.1 m 894.10 894.10 894.10
7 9 21.11.20 0+002 0+506 m 504.00 504.00 504.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
7 11 22.01.10 5+339.2 5+759.2 m 420.00 420.00 420.00
7 12 22.01.10 6+559.1 5+821.2 m 737.90 737.90 737.90
7 13 22.01.20 6+557.1 6+397.1 m 160.00 160.00 160.00
7 14 22.01.20 7+630.1 7+426.1 m 204.00 204.00 204.00
7 15 22.01.20 7+411.1 6+577.1 m 834.00 834.00 834.00
CO 4 22.01.21 1+183.98 1+736.08 m 552.10 552.10 552.10
0+405.0 0+408.5 403.57 403.57
0+000.0 0+164.035
4 19 22.02.18 0+000.00 0+230.035 403.57
CO 3 22.02.22 1+115.58 0+731.38 384.2 384.20 384.20
4 20 22.02.28 0+006.4 0+366.4 360.0 360.00 360.00
Total Qty 22,439.50 426.00 22,865.50
90% of Pipe Laying Qty 20,195.55 383.40 20,578.95
05% of Pressure Testing Qty 779.32 - 779.32
Total Qty 20,974.87 383.40 21,358.27
As per the Previous Qty - IPC 20,974.87
Current Qty 383.40

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
2.00 PIPE WORK
2.5 PNT 7 - 63mm
Pipe Laying
4 29 21.01.12 0+013 0+133 m 120.00 120.00 120.00
4 30 21.01.13 0+133 0+289 m 156.00 156.00 156.00
4 31 21.01.16 0+289 0+325.6 m 36.16 36.16 36.16
4 31 21.01.16 0+000 0+050 m 50.00 50.00 50.00
4 31 21.01.16 0+000 0+050 m 50.00 50.00 50.00
4 32 21.01.18 0+015 0+123 m 108.00 108.00 108.00
4 33 21.01.19 0+123 0+309.08 m 186.08 186.08 186.08
4 34 21.01.23 0+000 0+170 m 170.00 170.00 170.00
4 35 21.01.26 0+007.5 0+115.5 m 108.00 108.00 108.00
4 36 21.01.27 0+115.5 0+255.5 m 140.00 140.00 140.00
4 37 21.02.02 0+255.5 0+343.86 m 88.00 88.00 88.00
4 38 21.02.03 0+005.5 0+121.5 m 116.00 116.00 116.00
4 39 21.02.05 0+008 0+136 m 128.00 128.00 128.00
4 40 21.02.06 0+136 0+272 m 136.00 136.00 136.00
4 41 21.02.08 0+008 0+076 m 68.00 68.00 68.00
4 42 21.02.19 0+002.6 0+094.6 m 92.00 92.00 92.00
4 43 21.02.22 0+094.6 0+202.6 m 108.00 108.00 108.00
4 44 21.02.23 0+076 0+164 m 88.00 88.00 88.00
3 29 21.02.23 0+006 0+066 m 60.00 60.00 60.00
4 45 21.02.24 0+164 0+200 m 36.00 36.00 36.00
3 30 21.02.25 0+066 0+206 m 140.00 140.00 140.00
3 31 21.02.26 0+206 0+290 m 84.00 84.00 84.00
3 32 21.03.03 0+290 0+490 m 200.00 200.00 200.00
3 33 21.03.04 0+490 0+558 m 68.00 68.00 68.00
3 34 21.03.04 0+008 0+100 m 92.00 92.00 92.00
Total C/F 2,628.24 2,628.24

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 2628.24 2,628.24
3 35 21.03.05 0+100 0+192 m 92.00 92.00 92.00
4 48 21.03.09 0+008 0+040 m 32.00 32.00 32.00
3 36 21.03.10 0+192 0+352 m 160.00 160.00 160.00
4 49 21.03.10 0+040 0+144 m 104.00 104.00 104.00
3 37 21.03.11 0+352 0+552 m 200.00 200.00 200.00
3 38 21.03.12 0+552 0+644 m 92.00 92.00 92.00
3 39 21.03.12 0+007 0+075 m 68.00 68.00 68.00
4 50 21.03.12 0+144 0+049 m 152.00 152.00 152.00
3 40 21.03.13 0+075 0+213 m 144.00 144.00 144.00
4 51 21.03.13 0+005 0+105 m 100.00 100.00 100.00
4 52 21.03.16 0+005 0+049 m 44.00 44.00 44.00
4 53 21.03.20 0+049 0+104 m 104.00 104.00 104.00
3 42 21.05.05 0+008 0+122 m 114.00 114.00 114.00
3 43 21.05.06 0+122 0+212 m 90.00 90.00 90.00
3 44 21.05.07 0+212 0+272 m 60.00 60.00 60.00
3 45 21.05.08 0+272 0+326 m 54.00 54.00 54.00
3 47 21.05.10 0+326 0+398 m 72.00 72.00 72.00
2 3 21.06.14 0+265.3 0+373.46 m 108.00 108.00 108.00
2 4 21.06.18 0+013.5 0+091.5 m 78.00 78.00 78.00
3 48 21.06.18 0+122 0+482 m 84.00 84.00 84.00
2 5 21.06.19 0+091.5 0+145.5 m 54.00 54.00 54.00
3 49 21.06.19 0+482 0+524 m 42.00 42.00 42.00
3 50 21.06.21 0+009 0+147 m 138.00 138.00 138.00
3 51 21.06.22 0+147 0+171 m 24.00 24.00 24.00
3 52 21.06.22 0+006 0+090 m 84.00 84.00 84.00
3 53 21.07.02 0+090 0+144 m 54.00 54.00 54.00
Total C/F 4,976.24 4,976.24

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To & Recommanded as per the
Checked
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 4,976.24 4,976.24
2 6 21.07.02 0+373 0+385 m 12.00 12.00 12.00
2 7 21.07.02 0+000 0+048 m 48.00 48.00 48.00
3 54 21.07.03 0+144 0+210 m 66.00 66.00 66.00
3 55 21.07.12 0+210 0+240 m 30.00 30.00 30.00
3 56 21.07.14 0+240 0+378 m 138.00 138.00 138.00
3 57 21.07.15 0+006 0+162 m 156.00 156.00 156.00
3 58 21.07.16 0+162 0+216 m 54.00 54.00 54.00
3 59 21.07.19 0+000 0+132 m 132.00 132.00 132.00
3 60 21.07.20 0+132 0+156 m 24.00 24.00 24.00
3 61 21.07.26 0+004 0+106 m 102.00 102.00 102.00
3 62 21.07.27 0+106 0+196 m 90.00 90.00 90.00
3 63 21.07.28 0+196 0+208 m 12.00 12.00 12.00
3 64 21.07.28 0+006 0+054 m 48.00 48.00 48.00
2 8 21.08.02 0+145.5 0+235.84 m 90.34 90.34 90.34
1 27 21.08.03 0+206 0+284 m 78.00 78.00 78.00
2 9 21.08.03 0+235.84 0+289.841 m 54.00 54.00 54.00
1 28 21.08.04 0+284 0+350 m 66.00 66.00 66.00
2 10 21.08.04 0+289.841 0+379.84 m 90.00 90.00 90.00
2 11 21.08.05 0+379.84 0+391.84 m 12.00 12.00 12.00
2 12 21.08.05 0+048 0+066 m 18.00 18.00 18.00
2 13 21.08.06 0+066 0+156 m 90.00 90.00 90.00
2 14 21.08.07 0+156 0+252 m 96.00 96.00 96.00
2 15 21.08.09 0+000 0+013.7 m 13.70 13.70 13.70
1 29 21.08.11 0+350 0+452.36 m 102.00 102.00 102.00
1 30 21.08.12 0+452.36 0+542.36 m 90.00 90.00 90.00
1 31 21.08.13 0+542.36 0+570.86 m 28.50 28.50 28.50
Total C/F 6,716.78 6,716.78
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 6716.78 6,716.78
1 32 21.08.14 0+301.5 0+151.5 m 150.00 150.00 150.00
1 33 21.08.16 0+151.5 0+007.5 m 144.00 144.00 144.00
1 34 21.08.17 0+448.52 0+544.52 m 96.00 96.00 96.00
1 35 21.08.18 0+544.52 0+598.52 m 54.00 54.00 54.00
1 25 21.07.30 0+002 0+074 m 72.00 72.00 72.00
1 26 21.07.31 0+074 0+206 m 132.00 132.00 132.00
7 33 21.10.16 0+009.0 0+153.0 m 144.00 144.00 144.00
7 34 21.10.18 0+153.0 0+303.0 m 150.00 150.00 150.00
7 35 21.10.19 0+303.0 0+333.0 m 30.00 30.00 30.00
7 37 21.10.21 0+333 0+405 m 72.00 72.00 72.00
7 41 21.10.22 0+405 0+429 m 24.00 24.00 24.00
7 49 21.10.28 0+002 0+086 m 84.00 84.00 84.00
7 52 21.10.29 0+086 0+266 m 180.00 180.00 180.00
7 55 21.10.30 0+266 0+392 m 126.00 126.00 126.00
7 57 21.10.31 0+392 0+506 m 114.00 114.00 114.00
7 58 21.11.01 0+004 0+100 m 96.00 96.00 96.00
7 59 21.11.02 0+100 0+136 m 36.00 36.00 36.00
7 60 21.11.03 0+002.5 0+200.5 m 198.00 198.00 198.00
3 65 21.11.16 0+025 0+115 m 90.00 90.00 90.00
3 66 21.11.17 0+115 0+175 m 60.00 60.00 60.00
7 80 21.12.13 4+450.88 4+452.00 m 2.50 2.50 2.50
7 81 21.12.13 0+002 0+000 m 2.00 2.00 2.00
6 1 21.12.14 0+007.7 0+103.7 m 96.00 96.00 96.00
6 2 21.12.15 0+103.7 0+247.7 m 144.00 144.00 144.00
5 1 21.12.17 0+004 0+070 m 66.00 66.00 66.00
5 2 21.12.18 0+005.4 0+073.08 m 69.80 69.80 69.80
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
Total C/F 9,149.08 9,149.08

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 9149.08 9,149.08
3 73 21.12.23 0+002.5 0+092.5 m 90.00 90.00 90.00
3 74 21.12.24 0+004 0+096 m 96.00 96.00 96.00
3 69 21.12.27 0+000.0 0+007.0 m 7.00 7.00 7.00
3 70 21.12.28 0+000.0 0+008.0 m 8.00 8.00 8.00
3 71 21.12.28 0+000.0 0+006.0 m 6.00 6.00 6.00
Pressure Testing
4 6 21.01.19 0+013.0 0+325.6 m 312.60 312.60 312.60
4 6 21.01.19 0+000 0+050 m 50.00 50.00 50.00
4 6 21.01.19 0+000 0+050 m 50.00 50.00 50.00
4 9 21.01.26 0+015 0+309.08 m 294.08 294.08 294.08
4 9 21.01.26 0+000 0+170 m 170.00 170.00 170.00
4 10 21.02.06 0+007.5 0+343.86 m 336.36 336.36 336.36
4 11 21.02.06 0+005.5 0+121.5 m 116.00 116.00 116.00
4 12 21.02.16 0+008 0+272 m 264.00 264.00 264.00
4 13 21.02.25 0+002.6 0+202.6 m 200.00 200.00 200.00
4 14 21.03.03 0+008 0+200 m 192.00 192.00 192.00
3 9 21.03.16 0+008 0+644 m 636.00 636.00 636.00
3 10 21.03.16 0+007 0+213 m 206.00 206.00 206.00
3 11 21.03.16 0+006 0+558 m 552.00 552.00 552.00
4 15 21.03.17 0+008 0+296 m 288.00 288.00 288.00
4 16 21.03.17 0+005 0+105.361 m 100.36 100.36 100.36
4 17 21.03.24 0+005 0+153 m 148.00 148.00 148.00
3 13 21.06.29 0+008 0+524 m 516.00 516.00 516.00
3 14 21.07.14 0+009 0+171 m 162.00 162.00 162.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
3 14 21.07.14 0+009 0+171 m 162.00 162.00 162.00
2 2 21.08.19 0+373.46 0+256.46 m 752.00 752.00 752.00
Total C/F 5,507.40 5,507.40

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 5507.40 5,507.40
Pressure Testing
3 15 21.10.07 0+006 0+372 m 372.00 372.00 372.00
1 5 21.10.07 0+301.5 0+007.5 m 294.00 294.00 294.00
1 6 21.10.11 0+448.52 0+598.528 m 150.00 150.00 150.00
1 8 21.10.21 0+002 0+578.861 m 568.86 568.86 568.86
3 16 21.11.22 0+025 0+175 m 150.00 150.00 150.00
7 7 21.11.20 0+002.5 0+200.5 m 198.00 198.00 198.00
7 8 21.11.20 0+009 0+429 m 420.00 420.00 420.00
3 16 21.11.22 0+025 0+175 m 150.00 150.00 150.00
3 17 21.12.24 0+006 0+216.08 m 204.08 204.08 204.08
3 17 21.12.24 0+000 0+156 m 156.00 156.00 156.00
3 18 21.12.24 0+004 0+208 m 204.00 204.00 204.00
GM 3 22.01.20 2+007.48 1+851.48 m 156.00 156.00 156.00

Total Qty 9,356.08 9,356.08


Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
90% of Pipe Laying Qty 8,420.47 - 8,420.47
05% of Pressure Testing Qty 426.52 - 426.52
Total Qty 8,846.99 - 8,846.99
As per the Previous Qty - IPC 8,846.99
Current Qty -

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
3.00 PIPE WORK
common trench
3.10 160mm dia. PNT 11 & 225mm dia. PNT 7
Pipe Laying
CO 43 27.04.22 1+442.8 1+456.208 m 13.41 12.94 12.94
CO 43 27.04.22 1+292.18 1+279.7 m 12.48

Total Qty - 12.94 12.94


90% of Pipe Laying Qty - 11.65 11.65
05% of Pressure Testing Qty
Total Qty - 11.65 11.65
As per the Previous Qty - IPC -
Current Qty 11.65

Checked & Recommanded as per the


Prepared Checked as per the Contract Contract Checked & Certified as per the Contract
……………………………… ……………………………………… ………………………………………………………… ……………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Location Previous Current


No Zone No DPR No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
3.00 PIPE WORK
common trench
3.20 160mm dia. PNT 11 & 90mm dia. PNT 7
Pipe Laying
4 CO/19 21.04.08 0+033.7 0+006 m 6.00 6.00 6.00

4 CO/20 21.04.24 0+039.7 0+111.7 m 72.00 72.00 72.00


0+006 0+078

4 CO/21 21.04.28 0+111.7 0+201.7 m 90.00 90.00 90.00


0+078 0+168

4 CO/22 21.04.11 0+201.7 0+291.7 m 90.00 90.00 90.00


0+168 0+258

4 CO/23 21.04.12 0+291.7 0+345.7 m 54.00 54.00 54.00


0+258 0+312
Total Qty 312.00 312.00
90% of Pipe Laying Qty 280.80 - 280.80
05% of Pressure Testing Qty
Total Qty 280.80 280.80
As per the Previous Qty - IPC 280.80
Current Qty -

Checked & Recommanded as per the


Prepared Checked as per the Contract Contract Checked & Certified as per the Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 10th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
3.00 PIPE WORK
3.3 common trench
160mm dia. PNT 7 & 63mm dia. PNT 7
Pipe Laying
CO 24 21.12.21 1+929.48 2+007.48 m 78.00 78.00 78.00
CO 25 21.12.22 1+929.48 1+851.48 m 78.00 78.00 78.00

Total Qty 156.00 156.00


90% of Pipe Laying Qty 140.40 - 140.40
05% of Pressure Testing Qty
Total Qty 140.40 140.40
As per the Previous Qty - IPC 140.40
Current Qty -

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
3.00 PIPE WORK
3.4 common trench
110mm dia. PNT 11 & 160mm dia. PNT 7
Pipe Laying
CT 16 20.12.17 0.00 0+462 m 48.00 48.00 48.00
0+000 0+048

CT 17 20.12.18 0+517.4 0+595.4 m 78.00 78.00 78.00


0+103.4 0+181.4

Total Qty 126.00 126.00


90% of Pipe Laying Qty 113.40 - 113.40
05% of Pressure Testing Qty
Total Qty 113.40 113.40
As per the Previous Qty - IPC 113.40
Current Qty -

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
3.00 PIPE WORK
common trench
3.50 110mm dia. PNT 11 & 110mm dia. PNT 7
Pipe Laying
CT 11 20.12.09 0+000 0+120 m 120.00 120.00 120.00
0+409.92 0+530.04

CT 12 20.12.10 0+120 0+210 m 90.00 90.00 90.00


0+530.04 0+620.16

CT 13 20.12.11 0+210 0+288 m 78.00 78.00 78.00


0+620.16 0+698.28

CT 14 20.12.12 0+288 0+366 m 78.00 78.00 78.00


0+698.28 0+776.4

CT 15 20.12.16 0+366 0+414 m 78.00 78.00 78.00


0+776.4 0+854.4

Total Qty 444.00 444.00


90% of Pipe Laying Qty 399.60 - 399.60
05% of Pressure Testing Qty
Total Qty 399.60 399.60
As per the Previous Qty - IPC 399.60
Current Qty -

Checked & Recommanded as per the


Prepared Checked as per the Contract Contract Checked & Certified as per the Contract
……………………………… ……………………………………… ………………………………………………………… ……………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
PREVIOUS TOTAL LENGTH OF PIPE LAYING, PRESSURE TESTING & FITTINGS

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
3.00 PIPE WORK
common trench
3.60 110mm dia. PNT 11 & 90mm dia. PNT 7
Pipe Laying
6 R1 20.10.24 2+994.60 3+018.60 m 24.00 24.00 24.00
6 1 20.10.27 0+350.00 0+374.00 m 24.00 24.00 24.00
6 2 20.10.28 0+374.00 0+458.00 m 84.00 84.00 84.00
6 3 20.10.29 0+458.00 0+500.00 m 42.00 42.00 42.00
6 4 20.10.31 0+500.00 0+524.00 m 24.00 24.00 24.00
CT 5 20.11.12 0+524 0+554 m 30.00 30.00 30.00
CT 6 20.11.13 0+554 0+608 m 54.00 54.00 54.00
CT 7 20.11.17 0+608 0+704 m 96.00 96.00 96.00
CT 8 20.11.18 0+704 0+752 m 48.00 48.00 48.00
CT 9 20.11.20 0+824 0+874 m 54.00 54.00 54.00
CT 10 20.11.21 1+536 1+446 m 90.00 90.00 90.00
CO 42 01.04.22 3+517.3 3+541.3 m 24.00 24.00 24.00
CO 42 01.04.22 3+225.16 3+249.16 m
CO 45 05.04.22 3+421.3 3+463.3 m 42.00 45.00 45.00
CO 45 05.04.22 3+123.16 3+171.16 m 48.00
CO 44 06.04.22 3+463.3 3+517.3 m 54.00 54.00 54.00
CO 44 06.04.22 3+171.16 3+225.16 m
Total Qty 570.00 123.00 693.00
90% of Pipe Laying Qty 513.00 110.70 623.70
05% of Pressure Testing Qty
Total Qty 513.00 110.70 623.70
As per the Previous Qty - IPC 513.00
Current Qty 110.70

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
……………………………… ……………………………………… ………………………………………………………… ……………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
Precasting Chamber

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Precasting Air Valve Chamber Compare With BOQ


Complete of Transport and Concreting Balance fixing DI lid and
Item Description Unit Qty. Casting up to 0.6m Placing chamber Walls (as per site completing chamber Finishing Total Complete
No. Height at site requirement) as per the drawing Chamber

Claiming precentage 40% 5% 15% 30% 10%


Air Valves
Supply and fixing of Air valves complete including
construction of Valve Chamber
11.7 225 mm uPVC main, Single small orifice 25mm dia. Air
Valve Branch Saddle with Gunmetal Thread insert,
with isolated cock
nr 1.00 0.40 0.35
11.8 160 mm uPVC main, Single small orifice 25mm dia.
Air Valve Branch Saddle with Gunmetal Thread insert,
with isolated cock .
nr 5.00 2.00 1.75
11.9 110 mm uPVC main, Single small orifice 25mm dia.
Air Valve Branch Saddle with Gunmetal Thread insert,
with isolated cock .
nr 3.00 1.20 1.05
11.10 90 mm uPVC main, Single small orifice 25mm dia. Air
Valve Branch Saddle with Gunmetal Thread insert,
with isolated cock.
nr 1.00 0.40 0.40
11.11 63 mm uPVC main, Single small orifice 25mm dia. Air
Valve Branch Saddle with Gunmetal Thread insert,
with isolated cock.
nr 1.00 0.40 0.40
11.12 160 mm uPVC main, Double orifice 50 mm dia. Air
Valve with isolated Valve & 80 mm dia. Flange. nr 9.00 3.60 3.60
11.13 110 mm uPVC main, Double orifice 50 mm dia. Air
Valve with isolated Valve & 80 mm dia. Flange.
nr 2.00 0.80 0.80

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the Checked & Certified as per the Contract
Contract

…………………………………. …………………………………………………………. ………………………………………………………… …………………………………………………………


…………………………………………… …………………………………………………
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
Precasting Chamber

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Contractor Technical officer of Consultant/RDC Asst . QS RDC Asst . QS SPCU Senior Engineer/Compliance Officer SPCU

Precasting Washout Chamber Compare With BOQ


Complete of Transport and Concreting Balance fixing DI lid and
Item Description Unit Qty. Casting up to 0.6m Placing chamber Walls (as per site completing chamber Finishing Total Complete
No. Height at site requirement) as per the drawing Chamber

Claiming precentage 40% 5% 15% 30% 10%


Washout Valves
Supply and fixing of Washout valves complete
including the construction of Valve Chamber. All
as per shown in detail on drawing. No. NWP/
AF /WS /CKD -15 /KGW/TP-08,
NWP/AF/WS/CKD-15/KGW/ TP- 07

11.1 160mm uPVC main, 80 mm Sluice valve nr 5.00 2.00 2.00


11.2 110mm uPVC main, 80 mm Sluice valve nr 7.00 2.80 2.80
11.3 90mm uPVC main, 80 mm Sluice valve nr 11.00 4.40 4.40
11.4 63mm uPVC main 50mm sluice valve nr 3.00 1.20 1.20

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the Checked & Certified as per the Contract
Contract

…………………………………. …………………………………………………………. ………………………………………………………… …………………………………………………………


…………………………………………… …………………………………………………
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
Precasting Chamber

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Contractor Technical officer of Consultant/RDC Asst . QS RDC Asst . QS SPCU Senior Engineer/Compliance Officer SPCU

Precasting Gate Valve Chamber Compare With BOQ

Item Complete of Transport and Concreting Balance fixing DI lid and Finishing
Description Unit Qty. Casting up to 0.6m Placing chamber Walls (as per site completing chamber Total Complete
No. Chamber
Height at site requirement) as per the drawing
Claiming precentage 40% 5% 15% 30% 10%
Gate Valves
Supply & Fixing of Section valves complete,
including construction of Valve Chamber as shown
in detail on drawings no. NWP/AF/WS/CKD-15/
KGW/TP-05, NWP/AF/WS/CKD-15/ KGW/TP-06,

11.14 225 mm uPVC main nr 2 0.80 0.80


11.15 160 mm uPVC main nr 5 2.00 2.00
11.16 110 mm uPVC main nr 5 2.00 2.00
11.17 90 mm uPVC main nr 8 3.20 3.20

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the Checked & Certified as per the Contract
Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
Precasting Chamber

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

…………………………………. …………………………………………………………. ………………………………………………………… …………………………………………………………


…………………………………………… …………………………………………………
Contractor Technical officer of Consultant/RDC Asst . QS RDC Asst . QS SPCU Senior Engineer/Compliance Officer SPCU
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS SPECIALS AND VALVES .

PVC Pipe Laying


1 PNT11
( Consider 1m ) 160mm 110mm 90mm 63mm
Table B- PVC/1 Supply Cost 1,315.00 636.00 467.00 230.00
Add 9% of supply cost
According to 9% 118.35 57.24 42.03 20.70
NWSDB
Circular New Supply Cost 1,433.35 693.24 509.03 250.70
Add 20% of new supply cost as handling, O&P
20% 286.67 138.65 101.81 50.14
Total Supply Cost including O. & P. 1,720.02 831.89 610.84 300.84

Table B- PVC/4 Excavation 333.00 242.00 242.00 206.00


Table B- PVC/1 Laying 269.00 269.00 195.00 165.00
Table B- PVC/7 Flushing & Disinfection 27.00 17.00 14.00 14.00
Table B- PVC/7 Pressure Testing. 39.00 24.00 18.00 18.00
Table B- PVC/6 Dewatering(Allow 5%) 9.35 7.00 7.00 7.00
Table B- PVC/5 Earth Work Support(Allow 5%) 89.65 89.65 82.20 82.20
Total Cost 767.00 648.65 558.20 492.20
5.40% 41.42 35.03 30.14 26.58
Add 27% Overheads & Profits 207.09 175.14 150.71 132.89
1,015.51 858.81 739.06 651.67

Supplying & Laying Cost 2,736.00 1,691.00 1,350.00 953.00

2 PNT7
( Consider 1m ) 225 mm 160mm 110mm
Table B- PVC/1 Supply Cost 1,908.00 912.00 450.00
Add 9% of supply cost
According to 9% 171.72 82.08 40.50
NWSDB
Circular New Supply Cost 2,079.72 994.08 490.50
Add 20% of new supply cost as handling, O&P
20% 415.94 198.82 98.10
Total Supply Cost including O. & P. 2,495.66 1,192.90 588.60

Table B- PVC/4 Excavation 430.00 333.00 242.00


Table B- PVC/1 Laying 347.00 269.00 269.00
Table B- PVC/7 Flushing & Disinfection 41.00 27.00 17.00
Table B- PVC/7 Pressure Testing. 60.00 39.00 24.00
Table B- PVC/6 Dewatering(Allow 5%) 11.70 9.35 7.00
Table B- PVC/5 Earth Work Support(Allow 5%) 97.15 89.65 89.65
Total Cost 986.85 767.00 648.65
5.40% 53.29 41.42 35.03
Add 27% Overheads & Profits 266.45 207.09 175.14
1,306.59 1,015.51 858.81

Supplying & Laying Cost 3,802.00 2,208.00 1,447.00


2 PNT7
( Consider 1m ) 90mm 63mm
Table B- PVC/1 Supply Cost 302.00 159.00
Add 9% of supply cost
According to 9% 27.18 14.31
NWSDB
Circular New Supply Cost 329.18 173.31
Add 20% of new supply cost as handling, O&P
20% 65.84 34.66
Total Supply Cost including O. & P. 395.02 207.97

Table B- PVC/4 Excavation 242.00 206.00


Table B- PVC/1 Laying 195.00 165.00
Table B- PVC/7 Flushing & Disinfection 14.00 12.00
Table B- PVC/7 Pressure Testing. 18.00 16.00
Table B- PVC/6 Dewatering(Allow 5%) 7.00 6.00
Table B- PVC/5 Earth Work Support(Allow 5%) 82.20 92.85
Total Cost 558.20 497.85
Add 27% Overheads & Profits 150.71 134.42
708.91 632.27

Supplying & Laying Cost 1,104.00 840.00

3 Common Trench laying

3.1 Item 03 - Common Trench PNT11 PNT7


Total Cost
( Consider 1m ) 160mm 225mm
Table B- PVC/1 Supply Cost 1,315.00 1,908.00
Add 9% of supply cost
9% 118.35 171.72
New Supply Cost 1,433.35 2,079.72
Add 20% of new supply cost as handling, O&P
20% 286.67 415.94
Total Supply Cost including O. & P. 1,720.02 2,495.66 4,215.68

Table B- PVC/4 Excavation 592.00


Table B- PVC/1 Laying 269.00 347.00 616.00
Table B- PVC/7 Flushing & Disinfection 27.00 41.00 68.00
Table B- PVC/7 Pressure Testing. 39.00 60.00 99.00
Table B- PVC/6 Dewatering 15.30 - 15.30
Table B- PVC/5 Earth Work Support 97.15 - 97.15
Total Cost 1,487.45
Add 27% Overheads & Profits 401.61
1,889.06

Supplying & Laying Cost 6,105.00


3.2 Item 03 - Common Trench PNT11 PNT7
Total Cost
( Consider 1m ) 160mm 90mm
Table B- PVC/1 Supply Cost 1,315.00 302.00
Add 9% of supply cost
9% 118.35 27.18
New Supply Cost 1,433.35 329.18
Add 20% of new supply cost as handling, O&P
20% 286.67 65.84
Total Supply Cost including O. & P. 1,720.02 395.02 2,115.04

Table B- PVC/4 Excavation 592.00


Table B- PVC/1 Laying 269.00 195.00 464.00
Table B- PVC/7 Flushing & Disinfection 27.00 14.00 41.00
Table B- PVC/7 Pressure Testing. 39.00 18.00 57.00
Table B- PVC/6 Dewatering 15.30 - 15.30
Table B- PVC/5 Earth Work Support 97.15 - 97.15
Total Cost 1,266.45
Add 27% Overheads & Profits 341.94
1,608.39

Supplying & Laying Cost 3,723.00

3.3 PVC Pipe Laying


Item 03 - Common Trench PNT7 PNT7
Total Cost
( Consider 1m ) 160mm 63mm
Table B- PVC/1 Supply Cost 912.00 159.00
Add 9% of supply cost
9% 82.08 14.31
New Supply Cost 994.08 173.31
Add 20% of new supply cost as handling, O&P
20% 198.82 34.66
Total Supply Cost including O. & P. 1,192.90 207.97 1,400.87

Table B- PVC/4 Excavation 592.00


Table B- PVC/1 Laying 269.00 165.00 434.00
Table B- PVC/7 Flushing & Disinfection 27.00 12.00 39.00
Table B- PVC/7 Pressure Testing. 39.00 16.00 55.00
Table B- PVC/6 Dewatering 15.30 - 15.30
Table B- PVC/5 Earth Work Support 97.15 - 97.15
Total Cost 1,232.45
Add 27% Overheads & Profits 332.76
1,565.21

Supplying & Laying Cost 2,966.00


3.4 PVC Pipe Laying
Item 03 - Common Trench PNT11 PNT7
Total Cost
( Consider 1m ) 110mm 160 mm
Table B- PVC/1 Supply Cost 636.00 912.00
Add 9% of supply cost
9% 57.24 82.08
New Supply Cost 693.24 994.08
Add 20% of new supply cost as handling, O&P
20% 138.65 198.82
Total Supply Cost including O. & P. 831.89 1,192.90 2,024.78

Table B- PVC/4 Excavation 592.00


Table B- PVC/1 Laying 269.00 269.00 538.00
Table B- PVC/7 Flushing & Disinfection 17.00 27.00 44.00
Table B- PVC/7 Pressure Testing. 24.00 39.00 63.00
Table B- PVC/6 Dewatering 15.30 - 15.30
Table B- PVC/5 Earth Work Support 97.15 - 97.15
Total Cost 1,349.45
Add 27% Overheads & Profits 364.35
1,713.80

Supplying & Laying Cost 3,739.00

3.5 PVC Pipe Laying


Item 03 - Common Trench PNT11 PNT7
Total Cost
( Consider 1m ) 110mm 110 mm
Table B- PVC/1 Supply Cost 636.00 450.00
Add 9% of supply cost
9% 57.24 40.50
New Supply Cost 693.24 490.50
Add 20% of new supply cost as handling, O&P
20% 138.65 98.10
Total Supply Cost including O. & P. 831.89 588.60 1,420.49

Table B- PVC/4 Excavation 592.00


Table B- PVC/1 Laying 269.00 269.00 538.00
Table B- PVC/7 Flushing & Disinfection 17.00 17.00 34.00
Table B- PVC/7 Pressure Testing. 24.00 24.00 48.00
Table B- PVC/6 Dewatering 15.30 - 15.30
Table B- PVC/5 Earth Work Support 97.15 - 97.15
Total Cost 1,324.45
Add 27% Overheads & Profits 357.60
1,682.05

Supplying & Laying Cost 3,103.00


3.6 PVC Pipe Laying
Item 03 - Common Trench PNT11 PNT7
Total Cost
( Consider 1m ) 110mm 90 mm
Table B- PVC/1 Supply Cost 636.00 302.00
Add 9% of supply cost
9% 57.24 27.18
New Supply Cost 693.24 329.18
Add 20% of new supply cost as handling, O&P
20% 138.65 65.84
Total Supply Cost including O. & P. 831.89 395.02 1,226.90

Table B- PVC/4 Excavation 592.00


Table B- PVC/1 Laying 269.00 195.00 464.00
Table B- PVC/7 Flushing & Disinfection 17.00 14.00 31.00
Table B- PVC/7 Pressure Testing. 24.00 18.00 42.00
Table B- PVC/6 Dewatering 15.30 - 15.30
Table B- PVC/5 Earth Work Support 97.15 - 97.15
Total Cost 1,241.45
Add 27% Overheads & Profits 335.19
1,576.64
Supplying & Laying Cost 2,804.00

4 PVC Bends 225 mm Dia.


( Consider 1nr ) 90 0 45 0 22.5 0 11.25 0
Table B- PVC/2 Supply Cost 8,518.00 8,518.00 5,679.00 5,679.00
Add 9% of supply cost
According to 9% 766.62 766.62 511.11 511.11
NWSDB
Circular New Supply Cost 9,284.62 9,284.62 6,190.11 6,190.11
Add 20% of new supply cost as handling, O&P
20% 1,856.92 1,856.92 1,238.02 1,238.02
Total Supply Cost including O. & P. 11,141.54 11,141.54 7,428.13 7,428.13

Table B- PVC/2 Laying 434.00 434.00 434.00 434.00


Table B- COM/4 Thrust block 2,796.00 1,678.00 559.00 187.00
Lubricants 50.00 50.00 50.00 50.00
Total 3,280.00 2,162.00 1,043.00 671.00
27% 885.60 583.74 281.61 181.17
4,165.60 2,745.74 1,324.61 852.17
15,307.00 13,887.00 8,753.00 8,280.00

4 PVC Bends 160 mm Dia.


( Consider 1nr ) 90 0 45 0 22.5 0 11.25 0
Table B- PVC/2 Supply Cost 2,892.00 2,169.00 1,735.00 1,735.00
Add 9% of supply cost
According to 9% 260.28 195.21 156.15 156.15
NWSDB
Circular New Supply Cost 3,152.28 2,364.21 1,891.15 1,891.15
Add 20% of new supply cost as handling, O&P
20% 630.46 472.84 378.23 378.23
Total Supply Cost including O. & P. 3,782.74 2,837.05 2,269.38 2,269.38

Table B- PVC/2 Laying 362.00 362.00 362.00 362.00


Table B- COM/4 Thrust block 1,305.00 559.00 373.00 187.00
Lubricants 50.00 50.00 50.00 50.00
Total 1,717.00 971.00 785.00 599.00
27% 463.59 262.17 211.95 161.73
2,180.59 1,233.17 996.95 760.73
5,963.00 4,070.00 3,266.00 3,030.00

4 PVC Bends 110 mm Dia.


( Consider 1nr ) 90 0 45 0 22.5 0 11.25 0
Table B- PVC/2 Supply Cost 1,476.00 1,083.00 1,083.00 1,083.00
Add 9% of supply cost
According to 9% 132.84 97.47 97.47 97.47
NWSDB
Circular New Supply Cost 1,608.84 1,180.47 1,180.47 1,180.47
Add 20% of new supply cost as handling, O&P
20% 321.77 236.09 236.09 236.09
Total Supply Cost including O. & P. 1,930.61 1,416.56 1,416.56 1,416.56

Table B- PVC/2 Laying 209.00 209.00 209.00 209.00


Table B- COM/4 Thrust block 559.00 187.00 187.00 150.00
Lubricants 50.00 50.00 50.00 50.00
Total 818.00 446.00 446.00 409.00
27% 220.86 120.42 120.42 110.43
1,038.86 566.42 566.42 519.43
2,969.00 1,983.00 1,983.00 1,936.00

4 PVC Bends 90 mm Dia.


( Consider 1nr ) 90 0 45 0 22.5 0 11.25 0
Table B- PVC/2 Supply Cost 1,035.00 890.00 796.00 796.00
Add 9% of supply cost
According to 9% 93.15 80.10 71.64 71.64
NWSDB
Circular New Supply Cost 1,128.15 970.10 867.64 867.64
Add 20% of new supply cost as handling, O&P
20% 225.63 194.02 173.53 173.53
Total Supply Cost including O. & P. 1,353.78 1,164.12 1,041.17 1,041.17

Table B- PVC/2 Laying 209.00 209.00 209.00 209.00


Table B- COM/4 Thrust block 187.00 187.00 187.00 122.00
Lubricants 50.00 50.00 50.00 50.00
Total 446.00 446.00 446.00 381.00
27% 120.42 120.42 120.42 102.87
566.42 566.42 566.42 483.87
1,920.00 1,731.00 1,608.00 1,525.00

4 PVC Bends 63 mm Dia.


( Consider 1nr ) 90 0 45 0 22.5 0 11.25 0
Table B- PVC/2 Supply Cost 226.00 226.00 188.00 188.00
Add 9% of supply cost
According to 9% 20.34 20.34 16.92 16.92
NWSDB
Circular New Supply Cost 246.34 246.34 204.92 204.92
Add 20% of new supply cost as handling, O&P
20% 49.27 49.27 40.98 40.98
Total Supply Cost including O. & P. 295.61 295.61 245.90 245.90

Table B- PVC/2 Laying 167.00 167.00 167.00 167.00


Table B- COM/4 Thrust block 187.00 187.00 187.00 122.00
Lubricants 50.00 50.00 50.00 50.00
Total 404.00 404.00 404.00 339.00
27% 109.08 109.08 109.08 91.53
513.08 513.08 513.08 430.53
809.00 809.00 759.00 676.00
4.21 PVC Tees
( Consider 1nr ) 225x225 225x160 225x110 225x90
Table B- PVC/2 Supply Cost 93,402.00 61,894.00 61,894.00 61,894.00
Add 9% of supply cost
According to 9% 8,406.18 5,570.46 5,570.46 5,570.46
NWSDB Circular
New Supply Cost 101,808.18 67,464.46 67,464.46 67,464.46
Add 20% of new supply cost as handling, O&P
20% 20,361.64 13,492.89 13,492.89 13,492.89
Total Supply Cost including O. & P. 122,169.82 80,957.35 80,957.35 80,957.35

Table B- PVC/2 Laying 723.00 687.00 578.00 578.00


Table B- COM/4 Thrust block 5,050.00 2,050.00 2,050.00 2,050.00
Lubricants 50.00 50.00 50.00 50.00
Total 5,823.00 2,787.00 2,678.00 2,678.00
27% 1,572.21 752.49 723.06 723.06
7,395.21 3,539.49 3,401.06 3,401.06
129,565.00 84,497.00 84,358.00 84,358.00

( Consider 1nr ) 225x63 160x160 160x110 160x90


Table B- PVC/2 Supply Cost 61,894.00 15,474.00 15,474.00 15,312.00
Add 9% of supply cost
According to 9% 5,570.46 1,392.66 1,392.66 1,378.08
NWSDB
Circular New Supply Cost 67,464.46 16,866.66 16,866.66 16,690.08
Add 20% of new supply cost as handling, O&P
20% 13,492.89 3,373.33 3,373.33 3,338.02
Total Supply Cost including O. & P. 80,957.35 20,239.99 20,239.99 20,028.10

Table B- PVC/2 Laying 578.00 650.00 542.00 542.00


Table B- COM/4 Thrust block 2,050.00 932.00 932.00 932.00
Lubricants 50.00 50.00 50.00 50.00
Total 2,678.00 1,632.00 1,524.00 1,524.00
27% 723.06 440.64 411.48 411.48
3,401.06 2,072.64 1,935.48 1,935.48
84,358.00 22,313.00 22,175.00 21,964.00

( Consider 1nr ) 160x63 110x110 110x90 110x63


Table B- PVC/2 Supply Cost 16,880.00 8,412.00 7,074.00 6,610.00
Add 9% of supply cost
According to 9% 1,519.20 757.08 636.66 594.90
NWSDB
Circular New Supply Cost 18,399.20 9,169.08 7,710.66 7,204.90
Add 20% of new supply cost as handling, O&P
20% 3,679.84 1,833.82 1,542.13 1,440.98
Total Supply Cost including O. & P. 22,079.04 11,002.90 9,252.79 8,645.88

Table B- PVC/2 Laying 542.00 434.00 434.00 434.00


Table B- COM/4 Thrust block 932.00 373.00 373.00 373.00
Lubricants 50.00 50.00 50.00 50.00
Total 1,524.00 857.00 857.00 857.00
27% 411.48 231.39 231.39 231.39
1,935.48 1,088.39 1,088.39 1,088.39
24,015.00 12,091.00 10,341.00 9,734.00
( Consider 1nr ) 90x90 90x63 63x63
Table B- PVC/2 Supply Cost 5,447.00 5,447.00 3,265.00
Add 9% of supply cost
According to 9% 490.23 490.23 293.85
NWSDB
Circular New Supply Cost 5,937.23 5,937.23 3,558.85
Add 20% of new supply cost as handling, O&P
20% 1,187.45 1,187.45 711.77
Total Supply Cost including O. & P. 7,124.68 7,124.68 4,270.62

Table B- PVC/2 Laying 434.00 434.00 250.00


Table B- COM/4 Thrust block 187.00 187.00
Lubricants 50.00 50.00 50.00
Total 671.00 671.00 300.00
27% 181.17 181.17 81.00
852.17 852.17 381.00
7,977.00 7,977.00 4,652.00

4.36 PVC - Repair Sockets


( Consider 1nr ) 225 mm 160 mm 110 mm 90 mm
Table B- PVC/2 Supply Cost 3,709.00 1,413.00 689.00 468.00
Add 9% of supply cost
According to 9% 333.81 127.17 62.01 42.12
NWSDB
Circular New Supply Cost 4,042.81 1,540.17 751.01 510.12
Add 20% of new supply cost as handling, O&P
20% 808.56 308.03 150.20 102.02
Total Supply Cost including O. & P. 4,851.37 1,848.20 901.21 612.14

Table B- PVC/2 Laying 362.00 326.00 217.00 217.00


Lubricants 50.00 50.00 50.00 50.00
Total 412.00 376.00 267.00 267.00
27% 111.24 101.52 72.09 72.09
523.24 477.52 339.09 339.09
5,375.00 2,326.00 1,240.00 951.00

PVC - Repair Sockets


( Consider 1nr ) 63mm
Table B- PVC/2 Supply Cost 265.00
Add 9% of supply cost
According to 9% 23.85
NWSDB
Circular New Supply Cost 288.85
Add 20% of new supply cost as handling, O&P
20% 57.77
Total Supply Cost including O. & P. 346.62

Table B- PVC/2 Laying 126.00


Lubricants 50.00
Total 176.00
27% 47.52
223.52
570.00
4.41 PVC - Reducer
( Consider 1nr ) 225-160 mm 225-110 mm 160-110 mm 160-90 mm
Table B- PVC/2 Supply Cost 11,200.00 12,000.00 8,000.00 9,360.00
Add 9% of supply cost
According to 9% 1,008.00 1,080.00 720.00 842.40
NWSDB
Circular New Supply Cost 12,208.00 13,080.00 8,720.00 10,202.40
Add 20% of new supply cost as handling, O&P
20% 2,441.60 2,616.00 1,744.00 2,040.48
Total Supply Cost including O. & P. 14,649.60 15,696.00 10,464.00 12,242.88

Table B- PVC/2 Laying 250.00 250.00 188.00 188.00


Lubricants 50.00 50.00 50.00 50.00
Total 300.00 300.00 238.00 238.00
27% 81.00 81.00 64.26 64.26
381.00 381.00 302.26 302.26
15,031.00 16,077.00 10,766.00 12,545.00

( Consider 1nr ) 110-90 mm 110-63 mm 90-63mm


Table B- PVC/2 Supply Cost 3,900.00 3,900.00 3,489.00
Add 9% of supply cost
According to 9% 351.00 351.00 314.01
NWSDB
Circular New Supply Cost 4,251.00 4,251.00 3,803.01
Add 20% of new supply cost as handling, O&P
20% 850.20 850.20 760.60
Total Supply Cost including O. & P. 5,101.20 5,101.20 4,563.61

Table B- PVC/2 Laying 167.00 167.00 167.00


Lubricants 50.00 50.00 50.00
Total 217.00 217.00 217.00
27% 58.59 58.59 58.59
275.59 275.59 275.59
5,377.00 5,377.00 4,839.00

4.48 PVC - End Cap


( Consider 1nr ) 90 mm 63 mm
Table B- PVC/2 Supply Cost 209.00 55.00
Add 9% of supply cost
According to 9% 18.81 4.95
NWSDB
Circular New Supply Cost 227.81 59.95
Add 20% of new supply cost as handling, O&P
20% 45.56 11.99
Total Supply Cost including O. & P. 273.37 71.94

Table B- PVC/2 Laying 63.00 63.00


Lubricants 50.00 50.00
Total 113.00 113.00
27% 30.51 30.51
143.51 143.51
417.00 215.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 11: SUPPLY & LAYING OF uPVC AND DI PIPES, FITTINGS, SPECIALS AND VALVES
EXTRA WORK 01 - ROAD CROSSING

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 03
Period Up to :- 31st October 2020
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 19th November 2020

Extra Work 01. u'PVC Common Trench (110mm Dia. PNT 11& Per Rate 15.2M At Murukkatuwana Junction
90mm Dia. PNT 7 ) Road Crossing - 15.2M

S. No Description Quantity Unit Rate (LKR) Amount (LKR) Remarks

1.00 Material
1.1 ABC 4.02 Cu 7,167.00 28,811.34
1.2 Quarry Dust 2.46 Cu 8,167.00 20,090.82

2.00 Labour
2.1 Fitter 1.00 Day 2,300.00 2,300.00
2.2 Unskill 6.00 Day 1,725.00 10,350.00

3.00 Machinary
3.1 JCB 10.50 Day 3,500.00 36,750.00
3.2 Wacker 1.00 Day 3,000.00 3,000.00

4.00 Staff
4.1 Technical Officer 1.00 Day 1,500.00 1,500.00
4.2 Supervisor 1.00 Day 1,000.00 1,000.00

Total Construction cost 103,802.16


Add 27% O/H & P 28,026.58
Cost for 15.2M - Length Road Crossing 131,828.74

Say 131,828.74

Prepared Checked & Certified as per the Contract Checked & Certified as per the Contract Checked & Certified as per the
Contract

………………………… ………………………………………….. …………………………………………………… ……………………………………………..


Contractor TO of Consultant/RDC Asst . QS RDC Eng. Water Supply (RDC)

Checked & Certified as per the Checked & Certified as per the Contract Checked & Certified as per the
Contract Contract

………………………………………….. ……………………………………………. ……………………………………………


Asst . QS SPCU Asst. Engineer SPCU Engineer SPCU
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

LT ELECTRICAL EQUIPMENT & CABLES AT WATER TREATMENT PLANT


1 Supply & Installation of floor mounted electrical
panels for:
·      Main power incoming section,
·      Motor starter for High Lift Pumps
(HL New Tank, HL Neelamalapura, HL PS)
·      Motor starter for Blower
Above starter panels shall be complete with
necessary switchgears, suitable starters for
pumps, surge arresters and all other accessories
as per the Specifications

Rate to include all power and control cables


within the panel, level monitoring system &
other accessories as per the Specifications
Refer separate particular pump specifications for
starter section. Starter panel layout diagram and
design details should be approved by the
engineer before fabrication (Detailed list of items
required should be attached separately with
reference to this BOQ No.) Starter panel layout
diagram should be approved by the engineer
before fabrication.

Item Lump Sum 2,307,197.00


2 Supply of suitably rated power cables (4 core,
minimum 50mm2, CU/ XLPE / SWA / PVC) from
Main Panel to CEB Point as directed by the
Engineer.
m 80.00 5,660.00 452,800.00
3 Supply of suitably rated power cable for HL PS (4
core minimum 6 mm 2 CU/PVC/SWA/PVC +
Earth Cable) from starter panel to motor Junction
Box as directed by the Engineer.
m 40.00 1,376.00 55,040.00
4 Supply of suitably rated power cable for HL New
Tank (4 core, minimum 10 mm 2 CU/PVC/PVC)
from starter panel to motor Junction Box as
directed by the Engineer.
m 20.00 1,985.00 39,700.00

TOTAL CARRIED FORWARD 2,854,737.00


BROUGHT FORWARD 2,854,737.00

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

5 Supply of suitably rated power cable for HL


Neelamalapura (4 core, minimum 10 mm 2
CU/PVC/PVC) from starter panel to motor
Junction Box as directed by the Engineer
m 20.00 1,985.00 39,700.00
6 Supply of suitably rated power cable for Air
Blowers (4 core, minimum 6 mm 2
CU/PVC/SWA/PVC ) from starter panel to motor
as directed by the Engineer
m 20.00 1,376.00 27,520.00
7 Supply of suitably rated power cable from main
panel to Chemical house panel board (4 core,
minimum 6 mm2 CU/PVC/SWA/PVC) as directed
by the Engineer.
m 40.00 1,376.00 55,040.00
8 Laying of cables above in Items 2-7 complete
with all accessories as per specifications,
drawings and as instructed by the Engineer.
Rate to include the required modification, cable
trench excavation and filling according to IEE
regulations
Item Lump Sum 315,000.00
9 Supply and Installation of lightning protection
system for the -
Pump House structure & Chemical house
building (Refer specifications) Item Lump Sum 861,000.00
10 Supply & installation of Level signal GSM-
monitoring System for Ground Sump at Water
Treatment Plant, New Tank, PS Tank &
Neelamalapura Tank.
-
Rate to include for that water levels, pump
operation, Lamps for level, and others shall be
displayed in Mimic panel installed at Water
Treatment Plant
Item Lump Sum 840,000.00
GENERAL -
11 All pipes exposed shall be applied with two
coatings of spray Paint of suitable colour
approved by the Engineer.
Item Lump Sum 21,000.00
12 Training of Operation & Maintenance staff and
Handing over the operation manuals and parts
manual of all pumps & accessories
Item Lump Sum 12,600.00

TOTAL CARRIED FORWARD 10,736,071.00


BROUGHT FORWARD 10,736,071.00

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
13 Testing & Commissioning of all pumps and
Equipment supplied under this contract. The
required Test Instruments (Calibration
Certificate, within one year of certification) for
testing program shall be provided by the
Contractor.
Item Lump Sum 21,000.00
GAS CHLORINATORS AND ACCESSORIES -
14 Supply of vacuum type manually adjustable gas
chlorinator system for the treatment plant
having maximum dosage of 1.0 kg/hr. continuous
operation with maximum meter range of 20:1,
for feeding a solution of chlorine into the inlet of
the clear water reservoir.
-
Rate to include for following accessories -
Chlorine dosage indicator control unit, flow tubes
-
Check valve, -
Chlorine gas filter, -
Cylinder connecting valves /gas regulator with
gauges, -
Solution delivery tubes with injector (01 unit), -
Water pressure gauge,
‘Y’ strainer, Gate Valve &
All pipe fittings, connections, Keys & Tools, etc. nr 2 787,500.00 1,575,000.00
15 Installation of the chlorinators and all
accessories in item No. 1 in working order at the
chlorinator house.
Rate to include for breaking of walls, floor etc.,
and making good complete as directed by the
Engineer.
(Refer attached drawing in Section 6- Employer’s
Requirements (6.2 o ) Item Lump Sum 105,000.00
16 Supply of spare parts for the operation of the
Item No. 1 inclusive of all items listed in, the
specifications
-
(Itemized detailed price list of spares in respect
of the items shall be supplied) Item Lump Sum 840,000.00

TOTAL CARRIED FORWARD 24,802,742.00


BROUGHT FORWARD 24,802,742.00

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
17 Supply & Installation of suitably sized three
phase electrical motor driven booster pumping
sets for the above chlorination system .

Refer specifications in Section 6-Employer’s


Requirements (6.2 o clause 1.9) nr 2 131,250.00 262,500.00
18 Supply and installation of wall mounted sub
incoming, starter and control panels for booster
pumps supplied as per the specifications.

Starter panel shall be installed at the chlorinator


room of the chemical house
Rate to include for necessary power cables,
control cables, PVC conduits etc. for both local
and remote panel, breaking of walls, floor, etc.
and making good complete as directed by the
Engineer.
Item Lump Sum 577,500.00
19 Supply, Installation and fixing of necessary pipes,
fittings, valves etc. to install booster pumps and
starter panel.
Rate to include Supply & Installation of suction
line of booster pump from clear water reservoir
to the points where the chlorine solution is fed.
Rate to include for breaking of walls, floor, fixing
and laying of pipes, specials, fittings, valves, etc.
and making good complete as directed by the
Engineer.(Refer attached drawing in Section 6-
Employer’s Requirements (6.2 o )

Item Lump Sum 105,000.00


20 Supply and Installation Eye wash system and
fixing of necessary pipes, fittings, valves, etc. to
install the Eye wash system with safety showers
& Emergency Siren (Electrically operated )

Item Lump Sum 189,000.00


21 Supply of spare parts for the operation of the
booster pump sets inclusive of all items listed
under the specifications
-
(Itemized detailed price list of spares in respect
of the items shall be supplied) Item Lump Sum 116,550.00
TOTAL CARRIED FORWARD 51,801,034.00
BROUGHT FORWARD 51,801,034.00

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
22 Supply of safety equipment as specified below .
(Itemized detailed priced list of equipment in
respect of the items shall be supplied)
Gas respirators 4 Nos. (Gas masks)
Chlorine Leak Detector with alarm 01 No.)
Residual Chlorine Test Kit (04 Nos)
Self Breathing Apparatus and Leak absorption
system with Neutralization tank (1 No.)
Full-Body Protection suits ( 01 No.) Item Lump Sum 2,047,500.00
23 Supply and installation of Exhauste Fans (12'') 2
Nos. with wiring, socket outlet, switch, etc. as
directed by the Engineer
Item Lump Sum 42,000.00
24 Supply of detailed literature of the equipment
supplied under this bill, Operator's
manual for safety equipment (3 sets) &
Operation and maintenance manuals for
equipment supplied under this bill (3 sets)
Item Lump Sum 3,150.00
25 Supply and delivery of Cupboard for store tools
and equipment in minimum size of 900 (W)
x 450(T) x 1800(H) mm , to the chemical house
as per specified in Specifications in Section 6-
Employer’s Requirements (6.2 o Clause 1.7.5)

Item Lump Sum 36,750.00


26 Training of operational staff in the use and care
of the chlorinators supplied under this bill . Item Lump Sum 10,500.00
27 Testing, commissioning and handing over the
system to the satisfaction of the Engineer.
Required test Instruments for testing
programme shall be provided by the Contractor.

Item Lump Sum 31,500.00


ALUM DOSING PACKAGE AND ACCESSORIES.
28 Supply of PE circular tanks having 1,000 litre
capacity solution tank for mixing alum; the tank
shall be properly designed for this application
including chemical resistant food quality
coatings on both sides etc., as specified in the
Technical Specifications in Section 6-Employer’s
Requirements (6.2p)
nr 2 21,000.00 42,000.00

TOTAL CARRIED FORWARD 794,499,300.00


BROUGHT FORWARD 394,121,700.00

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
29 Supply of electrically driven stirrer with motor
and gear box suitable for the alum dosing tanks
supplied above including all accessories. nr 2 682,500.00 1,365,000.00
30 Supply of steel sections, nut & bolts and all other
accessories to install and hold the stirrer and
motor arrangement in proper manner as shown
in the drawings and as instructed by the
Engineer.
Item Lump Sum 52,500.00
31 Supply of electrically driven chemical solution
feeding pumps to feed alum to satisfy the
maximum flow rate given in the specifications
including all accessories.
nr 2 1,260,000.00 2,520,000.00
32
Installation of (Items 28,29,30 & 31 above) tanks,
mixers and pumps with supporting arrangement
etc. as instructed by the Engineer.
Item Lump Sum 105,000.00

33 Supply & Installation of pipes & valves, suitable


for feeding of alum dosing pumps arrangement
to satisfy the given flow rate as per the
specifications including all accessories.

Rate to include for the supply of all uPVC pipes &


specials, valves & fittings, brackets, for water
supply from the treated water line near the
chemical house, piping arrangement to get water
for chlorinator booster pumps & water
distribution main to chemical mixing tanks inlet
water supply piping and delivery chemical piping
up to the point of injection with flushing
arrangements, and supporting arrangement,
minor civil works as directed by the Engineer &
to suit the site condition.

Also include rates for steel structures/chemical


pipes tray required to minimize numbers of
bents in delivery pipes (of alum) and ensure
constant indication over considerable length as
directed by Engineer.
Item Lump Sum 577,500.00

TOTAL CARRIED FORWARD ###


BROUGHT FORWARD ###

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
34 Supply of spares as specified in the specifications
and technical literature for Alum mixer & Alum
feeding pump. -
(Itemized detailed price list of spares in respect
of the items shall be supplied) Item Lump Sum 840,000.00
35 Supply & installation of wall mounted main
power-incoming panel with suitably rated MCCB
(for the Alum feeder pump, stirrers and booster
pump, etc.) and Alum stirrer & motor starter
panel with safety precautions with suitably sized
power, earth and control cable to each motor to
starter and starter panel to incoming panel.

-
Rate to include for necessary power cables, PVC
conduits etc., breaking of walls, floor, etc. and
making good complete as directed by the
engineer. Item Lump Sum 630,000.00
36 Testing, commissioning and handing over the
system, to the satisfaction of the Engineer.
Required test Instruments for testing
programme shall be provided by the Contractor.
Item Lump Sum 10,500.00
37 Submission of all documents including technical
literature, O & M manual as per the specifications
- 3 sets. Item Lump Sum 3,150.00

LT ELECTRICAL EQUIPMENT & CABLES AT INTAKE


38 Supply & Installation of Wall mounted electrical
panels for:
·      Main power incoming section,
·      Motor starter for Low Lift Pumps
Above starter panels shall be complete with
necessary switchgears, suitable starters for
pumps, surge arresters and all other accessories
as per the Specifications.

Rate to include all power and control cables


within the panel, level monitoring system &
other accessories as per the Specifications.

TOTAL CARRIED FORWARD ###


BROUGHT FORWARD ###

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Refer separate particular pump specifications for
starter section. Starter panel layout diagram and
design details should be approved by the
engineer before fabrication. (Detailed list of
items required should be attached separately
with reference to this BOQ No.) Starter panel
layout diagram should be approved by the
Engineer before fabrication.
Item Lump Sum 483,000.00
39 Supply and Installation of lightning protection
system for the Low Lift Pump House. Item Lump Sum 525,000.00

SUPPLY AND INSTALLATION OF HIGH LIFT PUMPS AT


40 THE WATER
Supply of EndTREATMENT PLANT
Suction, Vertical Delivery Back
Pull-Out Centrifugal Pumping Set at High lift
Pump House to Neelamalapura Tower
(HLPNMP1 & HLPNMP2), Capacity 26 m3/hr.,
against 85 m Head.
nr 2 1,050,000.00 2,100,000.00
41 Supply of End Suction Vertical Delivery Back
Pull-Out Centrifugal Pumping Set at High lift
Pump House to 175 m3 capacity New Tower
(HLPNT1 & HLPNT2), Capacity 52 m3/hr.,
against 53 m Head.
nr 2 764,474.00 1,528,948.00
42 Supply of Split Casing horizontal double suction
centrifugal pumping set at pump house near
roughing filter to PS tank (HLPPS1 & HLPPS2),
Capacity 12 m3/hr., against 40 m Head.
nr 2 309,467.00 618,934.00
43 Supply of DI pipes, fittings, specials, Preasure
gauges for suction and delivery, non slam type
check valve, sluice valve, foot valve for suction,
DI/ DF reducers, bends, tees and mechanical type
flow meter (Volumetric type) to be installed with
the above pumps under Item No. 40 and other
fittings necessary to complete the pipe line. (Rate
to include for construction of concrete
foundation and valve supporting arrangement,
clamps, brackets with concrete steps, etc.
Detailed list of items and work required should
be attached seperately with reference to the BOQ
item Number.

Item Lump Sum 1,008,000.00


TOTAL CARRIED FORWARD 10,241,150.00
BROUGHT FORWARD 10,241,150.00

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
44 Installation & Fixing of equipment, instruments &
accessories supplied under the above Items 40 &
43, complete with all necessary accessories as
directed by the Engineer.
Item Lump Sum 168,000.00
45 Supply of DI pipes, fittngs, specials, Preasure
gauges for suction and delivery, non slam type
check valve, sluice valve, foot valve for suction,
DI/ DF reducers, bends, tees and mechanical type
flow meter (Volumetric type) to be installed with
the above pumps under Item No. 41 and other
fittings necessary to complete the pipe line .
(Rate to include for construction of concrete
foundation and valve supporting
arrangement/clamps, brackets with concrete
steps, etc. Detailed list of items and work
required should be attached seperately with
reference to the BOQ item Number.

Item Lump Sum 1,148,000.00


46 Installation & Fixing of equipment, instruments &
accessories supplied under the above Items 41 &
45 complete with all necessary accessories as
directed by the Engineer.
Item Lump Sum 168,000.00
47 Supply of DI pipes, fittngs, specials, Preasure
gauges for suction and delivery, non slam type
check valve, sluice valve, foot valve for suction,
DI/ DF reducers, bends, tees and mechanical type
flow meter (Volumetric type) to be installed with
the above pumps under the Item No. 42 and
other necessary fittings to complete the pipe line.
(Rate to include for the construction of concrete
foundation and valve supporting
arrangement/clamps, brackets with concrete
steps, etc. Detailed list of items and work
required should be attached seperately with
reference to the BOQ item Number.

Item Lump Sum 672,000.00

TOTAL CARRIED FORWARD 3,251,317.00


BROUGHT FORWARD 3,251,317.00

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
48 Installation & Fixing of equipment, instruments
& accessories supplied under the above, in Items
42 & 47 complete with all necessary accessories
as directed by the Engineer.

Item Lump Sum 168,000.00


AIR BLOWERS
49 Supply of Electrically Driven Package type Air
Blowers with Motors having capacity of 360
m3/hr. at 5 m head and gate valves, check valve,
specials, pressure gauges for each and necessary
pipe wall brackets and all accessories as per the
specifications.
nr 2 1,162,256.00 2,324,512.00
50 Supply of DI pipes and fittings for the installation
of air blowers supplied under the above item and
other fittings necessary to complete pipeline up
to the filter air inlet common line as directed by
the Engineer; It shall prevent water back flow to
the air blower.

Detailed list of items and works required should


be attached separately with reference to this
BOQ Item .)
Item Lump Sum 406,004.00

51 Installation of Air Blower unit with all


accessories mentioned above, in items No. 49 &
50 with necessary modification at site to connect
the air blower line to the sand Filter.

(Rate to include for construction of suitable


concrete foundations, valve-supporting brackets,
etc.)
Item Lump Sum 252,000.00
PUMP HOUSE LIFTING FACILITY
52 Supply of Manual Trolley & Hoist of Capacity
1,000 kg nr 1 51,797.00 51,797.00
53 Supply of Steel I-section of 254 mm x 146 mm x
31 kg/m nr 1 91,004.00 91,004.00
54 Installation of the Lifting Facility for the Pump
House Item Lump Sum 126,000.00

TOTAL CARRIED FORWARD 38,573,350.00


BROUGHT FORWARD 38,573,350.00

SUPPLY AND INSTALLATION OF LOW LIFT


PUMP FOR INTAKE.
Wet well type Submersible Pump
............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA
INTERIM PAYMNET
BILL NO. 12: SUPPLY & INSTALLATION OF ELECTRICAL & MECHANICAL EQUIPMENT
#REF!
#REF!

ITEM
NO. DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM

RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT


Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
55 Supply of submersible wet well Flange type
pumping set, as specified in the specifications
having capacity of 50 m3/hr. against a total head
of 20 m with pipe fittings, Float switch,
discharge connection, 6 m length Stainless Steel
lifting chain, pressure gauge, submersible cable
up to starter panel as per the Technical
specifications section 6. (LLP1 & LLP2)
nr 2 1,857,240.00 3,714,480.00
56 Supply and delivery of DI pipes, fittings, bends,
DI D/F non-return valves, Mechanical type flow
meter ( Volumetric Type) and Flange Adaptor as
per the schedule of pipes & specials in the
drawing & pipes, couplings sealing, pipe
supports, pipe brackets, etc. to install pump
supplied under item No. 55 above and other
fittings necessary for the complete pipeline up to
the common delivery line.

Item Lump Sum 916,997.00


57 Installation and Fixing of equipment supplied
above in Items 55 & 56 above, complete with all
accessories. Rate to include for construction of
suitable concrete foundations and valve
supporting arrangement, clamps, brackets with
concrete steps "Detailed list of items and works
required should be attached separately with
reference to this BOQ item"
Item Lump Sum 168,000.00

Total Carried Over to Summary … 33,773,873.00

............................ ............................
Checked as per the contract Cerified as per the contract
Consultant TO/ QS Engineer (SPCU)
............................
Prepared
Contractor
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 13: MISCELLANEOUS WORK.

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
1 For Payment of actual charges incurred for Supply &
Installation of Transformer. PS 3,150,000.00 PS 693,044.10 PS 693,044.10
1.1 Percentage adjustment to Provisional Sum for supply &
installation of Transformer in , Item 1(….4…%) Item Lump Sum 126,000.00 4% 27,721.76 4% 27,721.76
2 For Payment of actual charges incurred for Supplying &
Handing over, Tool Kit & lab equipment to
Karuwalagaswewa Pradeshiya Sabha. The following
items should be supplied

36" Chain Wrench - 01 nr


36" Pipe Wrench - 01 nr
12" Pipe Wrench - 01 nr
8" Nose Pliers - 02 nrs
Safety shoes - 06 pairs
Jar Test equipment with necessary test apparatus - 01
nr Item Lump Sum 55,125.00
Construction of Meter Cubicle
3 Construction of Meter Cubicle, Internal size 1,800 x
2,450 mm and 2,400mm high, Covered with 150 mm
thick Concrete Cover slab as per instructions given by
the Engineer. Rate to include for necessary excavation &
earth works, all masonry works, (Wall- plastering &
Painting) as per given detail drawing No. NWP-AF-WS-
CKD-15/KGW/WTP-22.
Item Lump Sum 262,500.00 100% 262,500.00 - 100% 262,500.00
4 Construction of Pump House, approximate size 3 m x 3 m
near the existing Roughing Filter as per the drawing and
as directed by the Engineer. Item Lump Sum 52,500.00
Total Carried Over to Summary … 3,646,125.00 983,265.86 - 983,265.86

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
WATER SUPPLY SCHEME FOR KARUWALAGASWEWA PRADESHIYA SABHA.

RATE BREAKDOWNS FOR YEAR 2019


Note:
1. Supply cost was obtained from the Supplier's quotation
2. Other rates are obtained from NWS & DB rate book for year 2018, 6% was addes to above rates to
convert 2018 rates to 2019 rates.

1. PVC Pipe Laying


PNT11
( Consider 1m ) 160mm 110mm 90mm
Supply Cost 2,200.00 1,052.17 799.65
15% 330.00 157.83 119.95
Total Supply Cost 2,530.00 1,210.00 919.60
Rubber Rings 34.50 15.67 11.83
General Clearance
Excavation 333.00 242.00 242.00
Disposal Excavated Material -
Laying 269.00 269.00 195.00
Flushing & Disinfection 27.00 17.00 14.00
Pressure Testing. 39.00 24.00 18.00
Backfilling (Selected Excavated Material) -
Dewatering 11.22 8.40 8.40
Earth Work Support 107.58 107.58 98.64
Trial Holes
Total Cost 821.30 683.65 587.87
Add 27% Overheads & Profits 221.75 184.58 158.73
1,043.05 868.23 746.60
Add 6% to convert 2018 to 2019 62.58 52.09 44.80
Supplying & Laying Cost 3,636.00 2,130.00 1,711.00
Say 3,640.00 2,130.00 1,710.00

2. PVC Pipe Laying


PNT7
( Consider 1m ) 225 mm 160mm 110mm 90mm 63mm
Supply Cost 2821.74 1,434.78 717.39 508.87 319.63
15% 423.26 215.22 107.61 76.33 47.94
Total Supply Cost 3,245.00 1,650.00 825.00 585.20 367.57

Rubber Rings 56.17 34.50 15.67 11.83 8.50


Excavation 430.00 333.00 242.00 242.00 206.00
Disposal Excavated Material -
Laying 347.00 269.00 269.00 195.00 165.00
Flushing & Disinfection 41.00 27.00 17.00 14.00 12.00
Pressure Testing. 60.00 39.00 24.00 18.00 16.00
Backfilling (Selected Excavated Material)
Dewatering 14.04 11.22 8.40 8.40 7.20
Earth Work Support 116.58 107.58 107.58 98.64 111.42
Trial Holes
Total Cost 1,064.79 821.30 683.65 587.87 526.12
Add 27% Overheads & Profits 287.49 221.75 184.58 158.73 142.05
1,352.28 1,043.05 868.23 746.60 668.17
Add 6% to convert 2018 to 2019 81.14 62.58 52.09 44.80 40.09
Supplying & Laying Cost 4,678.00 2,756.00 1,745.00 1,377.00 1,076.00
Say 4,680.00 2,760.00 1,745.00 1,380.00 1,075.00
3. PVC Bends 225 mm
90 0 45 0 22.5 0 11.25 0
Supply 8,112.57 8,112.57 8,112.57 8,112.57
15% 1,216.89 1,216.89 1,216.89 1,216.89
Total Supply Cost 9,329.46 9,329.46 9,329.46 9,329.46
Laying 434.00 434.00 434.00 434.00
Rubber rings 337.00 337.00 337.00 337.00
thrust block 2,796.00 1,678.00 559.00 187.00
lubricants 50.00 50.00 50.00 50.00
Total 3,617.00 2,499.00 1,380.00 1,008.00
27% 976.59 674.73 372.60 272.16
4,593.59 3,173.73 1,752.60 1,280.16
Add 6% to convert 2018 to 2019 4,869.21 3,364.15 1,857.76 1,356.97
14,199.00 12,694.00 11,187.00 10,686.00
Say 14,200.00 12,695.00 11,190.00 10,685.00

160mm
90 0 45 0 22.5 0 11.25 0
Supply 4,277.57 2,463.22 2,463.22 2,463.22
15% 641.64 369.48 369.48 369.48
Total Supply Cost 4,919.21 2,832.70 2,832.70 2,832.70
Laying 362.00 362.00 362.00 362.00
Rubber rings 207.00 207.00 207.00 207.00
thrust block 1,305.00 559.00 373.00 187.00
lubricants 50.00 50.00 50.00 50.00
Total 1,924.00 1,178.00 992.00 806.00
27% 519.48 318.06 267.84 217.62
2,443.48 1,496.06 1,259.84 1,023.62
Add 6% to convert 2018 to 2019 2,590.09 1,585.82 1,335.43 1,085.04
7,509.00 4,419.00 4,168.00 3,918.00
Say 7,510.00 4,420.00 4,170.00 3,920.00

PVC Bends 110mm


90 0 45 0 22.5 0 11.25 0
Supply 1,433.68 806.57 806.57 806.57
15% 215.05 120.99 120.99 120.99
Total Supply Cost 1,648.73 927.56 927.56 927.56
Laying 209.00 209.00 209.00 209.00
Rubber rings 94.00 94.00 94.00 94.00
thrust block 559.00 187.00 187.00 150.00
lubricants 50.00 50.00 50.00 50.00
Total 912.00 540.00 540.00 503.00
27% 246.24 145.80 145.80 135.81
1,158.24 685.80 685.80 638.81
Add 6% to convert 2018 to 2019 1,227.73 726.95 726.95 677.14
2,876.00 1,655.00 1,655.00 1,605.00
Say 2,880.00 1,655.00 1,655.00 1,605.00

PVC Bends 90mm


90 0 45 0 22.5 0 11.25 0
Supply 961.16 720.94 720.94 720.94
15% 144.17 108.14 108.14 108.14
Total Supply Cost 1,105.33 829.08 829.08 829.08
Laying 209.00 209.00 209.00 209.00
Rubber rings 71.00 71.00 71.00 71.00
thrust block 187.00 187.00 187.00 122.00
lubricants 50.00 50.00 50.00 50.00
Total 517.00 517.00 517.00 452.00
27% 139.59 139.59 139.59 122.04
656.59 656.59 656.59 574.04
Add 6% to convert 2018 to 2019 695.99 695.99 695.99 608.48
1,801.00 1,525.00 1,525.00 1,438.00
Say 1,800.00 1,525.00 1,525.00 1,440.00

PVC Bends 63mm


90 0 45 0 22.5 0 11.25 0
Supply 220.43 284.59 284.59 284.59
15% 33.06 42.69 42.69 42.69
Total Supply Cost 253.49 327.28 327.28 327.28
Laying 167.00 167.00 167.00 167.00
Rubber rings 51.00 51.00 51.00 51.00
thrust block
lubricants 100.00 100.00 100.00 100.00
Total 318.00 318.00 318.00 318.00
27% 85.86 85.86 85.86 85.86
403.86 403.86 403.86 403.86
Add 6% to convert 2018 to 2019 428.09 428.09 428.09 428.09
682.00 755.00 755.00 755.00
Say 685.00 755.00 755.00 755.00

4. PVC Tees 225x225 225x160 225x110 225x90 225x63


Supply 93,402.00 61,894.00 61,894.00 61,894.00 61,894.00
20% 18,680.40 12,378.80 12,378.80 12,378.80 12,378.80
Total Supply Cost 112,082.40 74,272.80 74,272.80 74,272.80 74,272.80
Laying 723.00 687.00 578.00 578.00 578.00
Rubber rings 337.00 207.00 94.00 71.00 51.00
thrust block 2,050.00 2,050.00 2,050.00 2,050.00 2,050.00
lubricants 50.00 50.00 50.00 50.00 50.00
Total 3,160.00 2,994.00 2,772.00 2,749.00 2,729.00
27% 853.20 808.38 748.44 742.23 736.83
4,013.20 3,802.38 3,520.44 3,491.23 3,465.83
Add 6% to convert 2018 to 2019 4,253.99 4,030.52 3,731.67 3,700.70 3,673.78
116,336.00 78,303.00 78,004.00 77,974.00 77,947.00
Say 116,335.00 78,305.00 78,005.00 77,975.00 77,950.00

160x160 160x110 160x90 160x63


Supply 15,474.00 15,474.00 15,312.00 16,880.00
20% 3,094.80 3,094.80 3,062.40 3,376.00
Total Supply Cost 18,568.80 18,568.80 18,374.40 20,256.00
Laying 650.00 542.00 542.00 542.00
Rubber rings 207.00 94.00 71.00 51.00
thrust block 932.00 932.00 932.00 932.00
lubricants 50.00 50.00 50.00 50.00
Total 1,839.00 1,618.00 1,595.00 1,575.00
27% 496.53 436.86 430.65 425.25
2,335.53 2,054.86 2,025.65 2,000.25
Add 6% for 2019 2,475.66 2,178.15 2,147.19 2,120.27
21,044.00 20,747.00 20,522.00 22,376.00
Say 21,045.00 20,750.00 20,525.00 22,375.00

110x110 110x90 110x63


Supply 734.50 78.48 764.17
15% 110.18 11.77 114.63
Total Supply Cost 844.68 90.25 878.80
Laying 434.00 434.00 434.00
Rubber rings 94.00 71.00 51.00
thrust block 373.00 373.00 373.00
lubricants 50.00 50.00 50.00
Total 951.00 928.00 908.00
27% 256.77 250.56 245.16
1,207.77 1,178.56 1,153.16
Add 6% for 2019 1,280.24 1,249.27 1,222.35
2,125.00 1,340.00 2,101.00
Say 2,125.00 1,340.00 2,100.00

90x90 90x63 63x63


Supply 590.37 482.98 155.43
15% 88.56 72.45 23.31
Total Supply Cost 678.93 555.43 178.74
Laying 434.00 434.00 250.00
Rubber rings 71.00 51.00 51.00
thrust block 187.00 187.00 187.00
lubricants 50.00 50.00 50.00
Total 742.00 722.00 538.00
27% 200.34 194.94 145.26
942.34 916.94 683.26
Add 6% for 2019 998.88 971.96 724.26
1,678.00 1,527.00 903.00
Say 1,680.00 1,530.00 905.00
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 13: MISCELLANEOUS WORK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Measurement Work Done Work Done


Item Total
No Description Unit Nos Qty up to Qty for This Quantity
Length Breath Depth Previous Bill Bill

For Payment of actual charges incurred for


3 Supply & Installation of Transformer. PS 693,044.10 693,044.10

Percentage adjustment to Provisional Sum Lump


for supply & installation of Transformer in , Item
Sum
Item 1(….4…%) 27,721.76 27,721.76

Construction of Meter Cubicle


3 Construction of Meter Cubicle, Internal size
1,800 x 2,450 mm and 2,400mm high,
Covered with 150 mm thick Concrete Cover
slab as per instructions given by the Engineer.
Rate to include for necessary excavation &
earth works, all masonry works, (Wall-
plastering & Painting) as per given detail
drawing No.
NWP-AF-WS-CKD-15/KGW/WTP-22.

Item Lump Sum 1.00 1.00

Prepared Checked as per the Contract Checked & Certified as per the Contract
Checked & Recommanded as per the
Contract

…………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
PIPE WORK
GENERAL NOTES FOR LAYING OF PIPES & FITTINGS

Also Rate to include for backfilling of pipe trenches


with selected excavated materials which shall be laid
in layers not exceeding 150 mm thickness and shall
carefully be compacted to achieve not less than 95%
of MDD (Test reports should be produced).

30% amount of work done will be retained until


completion of pressure testing, cleaning and
disinfection to the satisfaction of the Engineer.

Supply, Laying, Jointing or Fixing of PNT 7 uPVC


socket and spigot 6 m long straight pipes (suitable for
1.0 mechanical joints) by push fit joints in trenches with
maximum depth not exceeding 1.5 m. Rate to include
for supplying of joint rings, lubricant, etc.

1.1 110 mm Dia. m 1,803.00 1,863.00 3,358,989.00 1,670.04 3,111,284.52 92.66 172,618.13 1,762.70 3,283,902.65
1.2 90 mm Dia. m 10,421.00 1,748.00 18,215,908.00 3,564.31 6,230,410.38 1,358.10 2,373,955.30 4,922.41 8,604,365.68
1.3 63 mm Dia. m 1,750.00 1,194.00 2,089,500.00 57.95 69,192.30 - 57.95 69,192.30

TOTAL CARRIED FORWARD 23,664,397.00 9,410,887.20 2,546,573.43 11,957,460.63

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 23,664,397.00 9,410,887.20 2,546,573.43 11,957,460.63

FIXING OF FITTINGS (All uPVC fittings are to be


Type PNT 11)
Extra Over Items For Pipe Laying

Supply, Laying and jointing or fixing in open trench


PVC (type PNT 11) fittings. Rate to include for joints
rings, lubricant, etc. and supplying and fixing with
2.0 concrete grade 20 thrust blocks and all other
associated material required for complete installation
as shown in the drawings.
(NWP/AF/WS/CKD-15/KGW/DS-02.)

2.1 110mm x 22.500 bends. nr 3.00 2,292.00 6,876.00


2.2 110mm x 11.250 bends. nr 3.00 2,078.00 6,234.00
2.3 90mm x 22.500 bends. nr 20.00 1,759.00 35,180.00
2.4 90mm x 11.250 bends. nr 20.00 1,656.00 33,120.00
2.5 63mm x 22.500 bends. nr 2.00 832.00 1664.00
2.6 110 x 110mm uPVC Tee nr 5.00 15,374.00 76,870.00
2.7 110 x 63mm uPVC Tee nr 2.00 13,963.00 27,926.00 1.00 13,963.00 - 1.00 13,963.00
2.8 90 x 90 mm uPVC Tee nr 1.00 10,866.00 10,866.00 1.00 10,866.00 1.00 10,866.00 2.00 21,732.00
2.9 90 x 63mm uPVC Tee nr 3.00 10,598.00 31,794.00 1.00 10,598.00 - 1.00 10,598.00
2.10 63 x 63mm uPVC Tee nr 1.00 7,202.00 7,202.00 - - - - -
2.11 110 dia uPVC Repair socket. nr 2.00 1,715.00 3,430.00 2.00 3,430.00 - 2.00 3,430.00
2.12 90 dia uPVC Repair socket. nr 10.00 1,156.00 11,560.00 - - 1.00 1,156.00 1.00 1,156.00
2.13 63 dia uPVC Repair socket. nr 4.00 648.00 2,592.00 - - - - -
2.14 110 -90 mm uPVC reducer. nr 6.00 7,256.00 43,536.00 1.00 7,256.00 - 1.00 7,256.00
TOTAL CARRIED FORWARD 23,963,247.00 9,457,000.20 2,558,595.43 12,015,595.63
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.
Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 23,963,247.00 9,457,000.20 2,558,595.43 12,015,595.63

End Caps Suitable for solvent Cement Joint.


2.15 90mm dia uPVC end cap nr 4.00 1,647.00 6,588.00
2.16 63mm dia uPVC end cap nr 7.00 710.00 4,970.00

3 FIXING OF VALVES & CONSTRUCTION OF VALVE


CHAMBERS

Washout Valves
Supply and fixing of Washout valves complete
including the construction of Valve Chamber. All
as per shown in detail on drawing. No. NWP/
AF /WS /CKD -15 /KGW/TP-06
3.1 110mm uPVC main, 80 mm Sluice valve nr 2.00 321,938.00 643,876.00
3.2 90mm uPVC main, 80 mm Sluice valve nr 6.00 321,938.00 1,931,628.00
Supply and fixing of Air valves complete including
construction of Valve Chamber as shown in detail
on drawing no. NWP/AF/WS/CKD-15/KGW/TP-02

110 mm uPVC main, Single small orifice 25mm dia.


3.3 Air Valve Branch Saddle with Gunmetal Thread insert, nr 2.00 232,447.00 464,894.00
with isolated cock .
90 mm uPVC main, Single small orifice 25mm dia. Air
3.4 Valve Branch Saddle with Gunmetal Thread insert, nr 6.00 232,447.00 1,394,682.00
with isolated cock.

TOTAL CARRIED FORWARD 28,409,885.00 9,457,000.20 2,558,595.43 12,015,595.63


Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 28,409,885.00 9,457,000.20 2,558,595.43 12,015,595.63

Gate Valves
Supply & Fixing of Section valves complete,
including construction of Valve Chamber as
shown in detail on drawings no.
NWP/AF/WS/CKD-15/ KGW/TP-04
3.5 110 mm uPVC main nr 2.00 365,444.00 730,888.00
3.6 90 mm uPVC main nr 8.00 351,347.00 2,810,776.00

4.0 Culvert Crossings


Refer all the related drawings before pricing.
Crossing Type (D)
4.1 For 90 mm dia. PVC up to 6.0 m nr 6.00 16,431.00 98,586.00 3.00 49,293.00 - 3.00 49,293.00
Crossing Type (E)
4.2 80 mm dia (Approx. 5-10 m) nr 2.00 342,011.00 684,022.00

5.0 COLUMN SUPPORT AND PIPE SUPPORT FOR DI


LAYING

5.1 300 x 300 mm Column Support 1 height varies 0.0 - nr 2.00 65,490.00 130,980.00
3.0m
300 x 300 mm Column Support 1 height varies 3.0 -
5.2 6.0m nr 2.00 99,450.00 198,900.00
5.3 450 x 450x 600 mm Pipe Support nr 4.00 6,353.00 25,412.00
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

TOTAL CARRIED FORWARD 33,089,449.00 9,506,293.20 2,558,595.43 12,064,888.63

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
BROUGHT FORWARD 33,089,449.00 9,506,293.20 2,558,595.43 12,064,888.63

6.0 ROAD CROSSING BY HORIZONTAL DRILLING


Pipe Drilling for road crossing using DI pipes with
Horizontal Directional Drilling as directed by the
Horizontal Directional Drilling and supplying &
Engineer.
installation of DI socketed & Spigot pipe. Rates
include for mobilization, excavation for required pits
& trenches, backfilling, compaction and 2 nrs suitable
couplings for every road crossing. (Approximate
drilling length is about 10 m per location). Payments
will be made in separate item beyond the coupling.
6.1 100
Refermm dia . No. NWP-AF-WS-CKD-5/KGW/TP-10
drawing m 26.00 44,450.00 1,155,700.00
7.0 MISCELLANEOUS
Filling
Backfilling of pipe trench with imported soil laid in
7.1 layers not exceeding 150 mm in thickness & 100.00 2,285.00 228,500.00
compacted to achieve > 95% compaction as directed m3
by the Engineer.

Backfilling of pipe trench with imported Gravel laid


in layers not exceeding 150mm in thickness &
7.2 compacted to achieve > 95% compaction as directed m3 50.00 2,285.00 114,250.00
by the Engineer.
Total Carried Over to Summary … 34,587,899.00 9,506,293.20 2,558,595.43 12,064,888.63
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

ITEM DESCRIPTION UNIT QTY AS PER BOQ's PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM
NO.
RATE AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts. Rs. Cts.

Prepared Checked as per the Contract Checked & Recommanded as per Checked as per the Contract Checked & Certified as per
the Contract the Contract

………………….………... ……………………………………… ………………………………… ……..…………………………………. ……………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS (SPCU) Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Location
Zone No DPR Description Unit Nos Length Breadth Depth Previous Current Total Qty
No No Qty Qty
From To
1.00 PIPE WORK
1.1 PNT 7 - 110mm
8 1 21.12.19 4+690.5 4+738.5 m 48.00 48.00 48.00
8 2 21.12.20 4+738.5 4+864.5 m 126.00 126.00 126.00
8 3 21.12.21 4+864.5 4+990.5 m 126.00 126.00 126.00
8 4 21.12.23 4+990.5 5+134.62 m 144.00 144.00 144.00
8 5 21.12.24 5+134.62 5+200.62 m 66.00 66.00 66.00
8 7 21.12.26 5+200.62 5+381.62 m 181.00 181.00 181.00
8 8 21.12.27 5+381.62 5+573.62 m 192.00 192.00 192.00
8 9 21.12.28 5+573.62 5+627.62 m 54.00 54.00 54.00
8 10 21.12.29 5+627.62 5+751.62 m 120.00 120.00 120.00
8 11 21.12.30 5+751.62 5+787.62 m 36.00 36.00 36.00
8 12 21.12.31 5+787.62 5+913.62 m 126.00 126.00 126.00
8 13 22.01.01 5+913.62 5+931.62 m 18.00 18.00 18.00
8 14 22.01.03 5+931.62 6+051.62 m 120.00 120.00 120.00
8 15 22.01.04 6+051.62 6+195.62 m 144.00 144.00 144.00
8 16 22.01.05 6+195.62 6+297.62 m 102.00 102.00 102.00
8 17 22.01.06 6+297.62 6+381.62 m 84.00 84.00 84.00
8 18 22.01.07 6+381.62 6+429.62 m 48.00 48.00 48.00
8 27 22.01.31 6+429.62 6+543.62 m 114.00 114.00 114.00
8 47 22.02.25 5+657.62 5+664.22 m 6.60 6.60 6.60
Pressure Testing
8 3 22.02.27 4+690.5 5+657.62 m 967.12 967.12 967.12
8 4 22.02.27 5+657.62 6+543.62 m 886.00 886.00 886.00
Total Qty 1,855.60 - 1,855.60
90% of Pipe Laying Qty 1,670.04 - 1,670.04
05% of Pressure Testing Qty - 92.66 92.66
Total Qty 1,670.04 92.66 1,762.70
As per the Previous Qty - IPC 1,670.04
Current Qty 92.66

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract
……………………………… ……………………………………… ………………………………………………………… ……………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item DPR Location Previous Current


No Zone No No Description Unit Nos Length Breadth Depth Qty Qty Total Qty
From To
1.00 PIPE WORK
1.2 PNT 7 - 90mm
8 18 22.01.07 6+806.62 6+878.62.71 m 72.00 72.00 72.00
8 19 22.01.08 6+878.62 6+968.72 m 90.00 90.00 90.00
8 20 22.01.09 6+968.72 7+076.72 m 108.00 108.00 108.00
8 21 22.01.10 7+076.72 7+166.72 m 90.00 90.00 90.00
8 22 22.01.11 7+166.72 7+274.72 m 108.00 108.00 108.00
8 23 22.01.12 7+274.72 7+340.72 m 66.00 66.00 66.00
8 24 22.01.22 7+340.72 7+484.78 m 144.00 144.00 144.00
8 25 22.01.24 7+484.78 7+622.78 m 138.00 138.00 138.00
8 26 22.01.25 7+622.78 7+784.78 m 162.00 162.00 162.00
8 28 22.02.01 6+543.62 6+675.72 m 132.00 132.00 132.00
8 29 22.02.03 6+806.32 6+704.22 m 102.00 102.00 102.00
8 30 22.02.04 7+784.78 7+856.72 m 72.00 72.00 72.00
8 31 22.02.05 7+856.72 7+958.78 m 102.00 102.00 102.00
8 32 22.02.06 7+958.78 8+072.78 m 114.00 114.00 114.00
8 33 22.02.07 8+072.78 8+180.78 m 108.00 108.00 108.00
8+180.78 8+198.78 m 174.00 174.00
8 34 22.02.09 8+145.9 7+989.9 m 174.00 0.00 -
8 35 22.02.10 7+989.9 7+827.9 m 162.00 162.00 162.00
8 36 22.02.11 7+827.9 7+743.9 m 84.00 84.00 84.00
8 37 22.02.12 7+743.9 7+515.9 m 228.00 228.00 228.00
8 38 22.02.14 7+515.9 7+269.9 m 246.00 246.00 246.00
8 39 22.02.15 7+269.9 7+125.9 m 144.00 144.00 144.00
8 40 22.02.16 7+125.9 6+975.0 m 126.00 126.00 126.00
8 41 22.02.17 6+975.0 6+759.0 m 216.00 216.00 216.00
8 42 22.02.18 6+653.2 6+455.2 m 198.00 198.00 198.00
6+759.0 6+675.0 m 180.00 180.00
8 43 22.02.19 6+455.2 6+359.2 m 180.00 0.00 -
8 44 22.02.20 6+359.2 6+131.2 m 228.00 228.00 228.00
8 45 22.02.21 6+131.2 5+999.2 m 132.00 132.00 132.00
8 46 22.02.22 5+999.2 5+855.2 m 144.00 144.00 144.00
Total C/F 3,870.00 - 3,870.00

Prepared Checked as per the Contract Checked & Recommanded as per the Contract Checked & Certified as per the Contract
……………………………… ……………………………………… ………………………………………………………… ……………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Total B/F 3,870.00 - 3,870.00
8 48 06.03.22 5+855.2 5+747.2 m 108.00 108.00 108.00
8 49 07.03.22 5+747.2 5+645.2 m 102.00 102.00 102.00
8 50 08.03.22 5+645.2 5+459.2 m 186.00 186.00 186.00
8 51 10.03.22 5+459.2 5+219.1 m 240.10 240.00 240.00
8 52 11.03.22 5+219.1 5+129.1 m 90.00 90.00 90.00
8 53 12.03.22 5+129.1 5+009.1 m 120.00 120.00 120.00
8 54 26.03.22 5+009.1 4+937.1 m 72.00 72.00 72.00
8 55 27.03.22 4+937.1 4+799.1 m 138.00 138.00 138.00
8 56 28.03.22 4+799.1 4+676.1 m 123.00 123.00 123.00
8 57 29.03.22 4+676.1 4+544.1 m 132.00 132.00 132.00
8 58 30.03.22 4+544.1 4+412.1 m 132.00 132.00 132.00
8 59 31.03.22 4+412.1 4+358.1 m 54.00 54.00 54.00
8 60 31.03.22 5+855.2 5+867.2 m 12.00 12.00 12.00
Pressure Testing
8 1 22.02.25 6+704.72 7+554.72 m 850.00 850.00 850.00
8 2 22.02.25 7+554.72 8+198.78 m 644.06 644.06 644.06
8 4 22.02.27 6+543.62 6+675.72 m 132.10 132.10 132.10

Total Qty 3,870.00 1,509.00 5,379.00


90% of Pipe Laying Qty 3,483.00 1,358.10 4,841.10
05% of Pressure Testing Qty 81.31 - 81.31
Total Qty 3,564.31 1,358.10 4,922.41
As per the Previous Qty - IPC 3,564.31
Current Qty 1,358.10

Prepared Checked as per the Contract Checked & Recommanded as per the Contract Checked & Certified as per the Contract
……………………………… ……………………………………… ………………………………………………………… ……………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item Location
Zone No DPR Description Unit Nos Length Breadth Depth Previous Current Total Qty
No No Qty Qty
From To
1.00 PIPE WORK
1.3 PNT 7 - 63mm
8 6 21.12.24 0+000 0+061 m 61.00 61.00 61.00

Pressure Testing
8 3 22.02.27 0+000 0+061 m 61.00 61.00 61.00
-

Total Qty 61.00 61.00


90% of Pipe Laying Qty 54.90 - 54.90
05% of Pressure Testing Qty 3.05 - 3.05
Total Qty 57.95 - 57.95
As per the Previous Qty - IPC 57.95
Current Qty -

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the Contract
Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022
Item
Description Pipe Dia DPR Date Zone DPR Start End Sub Total Quantity
No No No Chanage Chanage (m)

PIPE FITTING
FIXING OF FITTINGS (All uPVC fittings are to
2.00 be Type PNT 11)

Supply, Laying and jointing or fixing in open


trench PVC (type PNT 11) fittings.

2.7 110 x 63mm uPVC Tee 21.12.23 08 04 IPC 14 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

2.9 90 x 63 mm uPVC Tee 22.01.08 08 19 IPC 16 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

2.8 90 x 90 mm uPVC Tee 22.02.01 08 28 IPC 17 1.00 1.00


22.03.08 08 50 IPC 18 1.00 1.00
Cumulative Claim 2.00
Previous Claim 1.00
This Bill Claim 1.00

2.11 110 dia uPVC Repair socket. 25.02.22 08 47 IPC 17 2.00 2.00
Cumulative Claim 2.00
Previous Claim 2.00
This Bill Claim -

2.12 90 dia uPVC Repair socket. 31.03.22 08 60 IPC 18 1.00 1.00


Cumulative Claim 1.00
Previous Claim -
This Bill Claim 1.00

2.14 110 -90 mm uPVC reducer. 01.02.22 08 28 IPC 17 1.00 1.00


Cumulative Claim 1.00
Previous Claim 1.00
This Bill Claim -

4.1 For 90 mm dia. PVC up to 6.0 m 22.02.04 08 30 IPC 17 1.00 1.00


22.02.11 08 36 IPC 17 2.00 2.00
Cumulative Claim 3.00
Previous Claim 3.00
This Bill Claim -

Prepared Checked as per the Contract Checked & Recommanded as per Checked & Certified as per the
the Contract Contract
Pura Neguma - Local Government Enhancement Sector Project
VARIATION ODER NO : 03
CONSTRUCTION OF WATER SUPPLY SCHEME (NELAMALAPURA)
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022
Item
Description Pipe Dia DPR Date Zone DPR Start End Sub Total Quantity
No No No Chanage Chanage (m)
……………………………… ……………………………………… ………………………………………………………… ……………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
DAY WORK SUMMARY

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


Item No Description Unit Qty Rate Amount Remarks
Qty Amount Qty Amount Qty Amount
MACHINARY
1 Asphalt cutter Hrs 25.00 1,500.00 37,500.00
2 Excavator-0.35 m3 Hrs 15.00 1,150.00 17,250.00
3 Excavator-0.45 m3 Hrs 15.00 1,840.00 27,600.00 60.00 110,400.00 8.10 14,904.00 68.10 125,304.00
4 Backhoe loader Hrs 15.00 1,150.00 17,250.00 43.80 50,370.00 - - 43.80 50,370.00
5 Baby dumper Hrs 15.00 517.50 7,762.50 - - -
6 Hand Rammer Day 8.00 805.00 6,440.00 - - -
7 Plate compactor Day 8.00 805.00 6,440.00 - - - - -
8 Concrete mixer Hrs 25.00 718.75 17,968.75 - - - - -
9 Dump truck Day 5.00 4,200.00 21,000.00 - - - - -
10 Boom Truck Day 5.00 15,000.00 75,000.00 - - - - -
11 Water bowser Day 8.00 2,990.00 23,920.00 1.00 2,990.00 - - 1.00 2,990.00
12 Water Pump (2" dia) Hrs 20.00 230.00 4,600.00 4.00 920.00 - 4.00 920.00
13 Sludge pump (4" dia) Hrs 20.00 1,500.00 30,000.00 - -
14 Lorry km 48.00 126.50 6,072.00 67.00 8,475.50 25.00 3,162.50 92.00 11,638.00
15 Truck with tipper km 50.00 126.50 6,325.00 - - -
16 Folk lift Hrs 25.00 1,150.00 28,750.00 - - - - -
17 Air compressor Hrs 25.00 115.00 2,875.00 - - - - -
18 Generator Hrs 25.00 359.38 8,984.38 4.00 1,437.50 4.00 1,437.50 8.00 2,875.00
19 Breaker Day 8.00 4,200.00 33,600.00 0.50 2,100.00 0.50 2,100.00 1.00 4,200.00
20 Grinder (large) Day 8.00 400.00 3,200.00 - - - - -
21 Grinder (medium) Day 8.00 400.00 3,200.00 - - - -
TOTAL CARRIED FORWARD 385,737.63 176,693.00 21,604.00 198,297.00

Prepared Checked as per the Contract Checked & Recommanded as per the Contract Checked as per the Contract Checked & Certified as per
the Contractor
Pura Neguma - Local Government Enhancement Sector Project
DAY WORK SUMMARY

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


Item No Description Unit Qty Rate Amount Remarks
Qty Amount Qty Amount Qty Amount
…………………………... …………………………………………………. ………………………………………………… ...…….…………………………………………. …………………………………………………….
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS SPCU Engineer (SPCU)
BROUGHT FORWARD 385,737.63 176,693.00 21,604.00 198,297.00
22 Angle grinder Hrs 8.00 400.00 3,200.00
LABOURE
24 Un Skilled Day 25.00 1,725.00 43,125.00 32.82 56,614.50 0.88 1,518.00 33.70 58,132.50
25 Pipe layer Day 25.00 2,530.00 63,250.00 3.63 9,171.25 0.50 1,265.00 4.13 10,436.25
26 Mason Day 10.00 2,300.00 23,000.00 4.38 10,074.00 - - 4.38 10,074.00
27 Carpenter Day 8.00 2,300.00 18,400.00 - - -
28 Steel worker Day 10.00 2,300.00 23,000.00 - - -
29 Fitter Day 10.00 2,300.00 23,000.00 4.77 10,959.50 0.38 862.50 5.15 11,822.00
30 Plumber Day 10.00 2,300.00 23,000.00 - - -
31 Welder Day 10.00 2,300.00 23,000.00 - - -
32 Painter Day 8.00 2,300.00 18,400.00 - - -
33 Electrician Day 8.00 2,300.00 18,400.00 - - -
34 Mechanic Day 8.00 2,300.00 18,400.00 - - -
35 Bar bender Day 8.00 2,300.00 18,400.00 - - -
36 Operator Day 8.00 2,300.00 18,400.00 12.50 28,750.00 1.00 2,300.00 13.50 31,050.00
MATERIAL - - -
37 Cement Bags 100.00 920.00 92,000.00 11.00 10,120.00 - 11.00 10,120.00
38 Tor steel kg 250.00 149.50 37,375.00 - - -
39 Mild Steel kg 100.00 155.25 15,525.00 - - -
40 Fine aggregates m3 35.00 3,450.00 120,750.00 1.20 4,136.55 - 1.20 4,136.55
41 Coarse aggregates 1/2" m3 12.00 2,645.00 31,740.00 - - -
42 Coarse aggregates 3/4" m3 10.00 2,530.00 25,300.00 1.21 3,061.30 - 1.21 3,061.30
TOTAL CARRIED FORWARD 1,043,402.63 309,580.10 27,549.50 337,129.60

Prepared Checked as per the Contract Checked & Recommanded as per the Contract Checked as per the Contract Checked & Certified as per
the Contractor
Pura Neguma - Local Government Enhancement Sector Project
DAY WORK SUMMARY

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


Item No Description Unit Qty Rate Amount Remarks
Qty Amount Qty Amount Qty Amount

…………………………... …………………………………………………. ………………………………………………… ...…….…………………………………………. …………………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS SPCU Engineer (SPCU)
BROUGHT FORWARD 1,043,402.63 309,580.10 27,549.50 337,129.60
43 Coarse aggregates 1" m3 15.00 2,415.00 36,225.00
44 Timber planks m3 25.00 1,200.00 30,000.00
45 Timber members m3 1.00 2,875.00 2,875.00
46 Bricks nos 2500.00 17.25 43,125.00
47 Rubble 6"x9" m3 12.00 2,645.00 31,740.00
48 Rubble 6"x4" m3 12.00 2,760.00 33,120.00

Total Carried Over to Summary … 1,220,487.63 309,580.10 27,549.50 337,129.60

Prepared Checked as per the Contract Checked & Recommanded as per the Contract Checked as per the Contract Checked & Certified as per
the Contractor
Pura Neguma - Local Government Enhancement Sector Project
DAY WORK SUMMARY

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 20th May 2022

PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


Item No Description Unit Qty Rate Amount Remarks
Qty Amount Qty Amount Qty Amount

…………………………... …………………………………………………. ………………………………………………… ...…….…………………………………………. …………………………………………………….


Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS SPCU Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 14: DAY WORK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location Measurement
ItemNo Zone DPR No Description Unit Nos Previous Current Total Qty
No From To Length Breath Depth Qty Qty

MACHINARY
3.00 Excavator-0.45 m3

Previously Certified - IPC Hrs 13.30 13.30


8 08.01.2022 -Zone 08 -M19-M01 ,By Road Crossing Hrs 4.00 4.00
GM 20.01.2022 -GM F -E - Cleaning Work ( Heavy Jungle) Hrs 1.50 1.50
GM 21.01.2022 -GM - Cleaning Work ( Heavy Jungle) Hrs 0.60 0.60
8 22.01.2022 -Zone 08 -M15-M07,Cleaning Work ( Heavy Jungle) Hrs 1.80 1.80
8 23.01.2022 -Zone 08 -M05-M19,Cleaning Work ( Heavy Jungle) Hrs 8.40 8.40
1 24.01.2022 -Zone 01 -H68-H70,Cleaning Work ( Heavy Jungle) Hrs 1.00 1.00
8 26.01.2022-Zone 08,Cleaning Work ( Heavy Jungle) Hrs 8.00 8.00
8 27.01.2022-Zone 08,Cleaning Work ( Heavy Jungle) Hrs 8.10 8.10
GM 31.01.2022 GM - Cleaning Work ( Heavy Jungle) 4+426.5 4+398.5 Hrs 2.50 2.50
GM 01.02.2022 GM - Cleaning Work ( Heavy Jungle) 4+330.5 4+263.5 Hrs 4.60 4.60
8 20.02.2022 Zone 08 -M22-M04,Cleaning Work ( Heavy Jungle) Hrs 2.00 2.00
8 07.03.2022 - 6" thickness heavy concrete breaking for pipe laying 5+747.2 5+645.2 Hrs 4.00 4.00
1 14.03.2022 - Jungle clearing for pipe line trace in RDA Road Hrs 2.00 2.00
GM 24.03.2022 - Heavy jungle clearing for pipe laying 5+092.81 5+050.21 Hrs 1.10 1.10
GM 25.03.2022 - Heavy Jungle clearing for pipe layng 5+145.6 5+165.6 Hrs 1.00 1.00
55.80 8.10 63.90

Prepared Checked as per the Contract Checked & Recommanded Checked & Certified as per the Contract
as per the Contract

……………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 14: DAY WORK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location Measurement
ItemNo Zone DPR No Description Unit Nos Previous Current Total Qty
No From To Length Breath Depth Qty Qty

Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

4.00 Backhoe loader

Previously Certified - IPC Hrs 24.50


GM 07.01.2022 -GM - Cleaning Work ( Heavy Jungle) 7+758 7+602 Hrs 3.00 3.00
8 09.01.2022 -Zone 08 -M19-M01 Cleaning Work ( Heavy Jungle) Hrs 3.50 3.50
6 18.01.2022 -Zone 06- B18-B19,Extra Excavation Hrs 2.00 2.00
4 02.02.2022 -Pipe laying in between existing khomba trees & fence Hrs 3.50 3.50
4 03.02.2022 -Zone 04 -P19-P21 Cleaning Work ( Heavy Jungle) Hrs 1.50 1.50
94.30 - 94.30
11 Water bowser

03.02.2022 -Filling water to excisting pipe line for tracing the end of pipe line Day 1.00 1.00
1.00 - 1.00
12 Water Pump (2" dia)

8 08.01.2022 -Zone 08 -M19-M01By Road Crossing Hrs 4.00 4.00


4.00 4.00
14 Lorry

Previously Certified - IPC km 10.00 10.00


8 08.01.2022 Zone 08 -M19-M01 By Road Crossing km 24.00 24.00
7 16.01.2022 Zone 07 Re-Construction Pavement in Pipe Line km 12.00 12.00
7 08.02.2022 Zone 07 Re-Construction Pavement in Pipe Line km 21.00 21.00
8 07.03.2022 - 6" thickness heavy concrete breaking for pipe laying 5+747.2 5+645.2 km 25.00 25.00
67.00 25.00 92.00

Prepared Checked as per the Contract Checked & Recommanded Checked & Certified as per the Contract
as per the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 14: DAY WORK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location Measurement
ItemNo Zone DPR No Description Unit Nos Previous Current Total Qty
No From To Length Breath Depth Qty Qty

……………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

18 Generator

8 08.01.2022 -Zone 08 -M19-M01 By Road Crossing Hrs 4.00 4.00


8 07.03.2022 - 6" thickness heavy concrete breaking for pipe laying 5+747.2 5+645.2 Hrs 4.00 4.00
4.00 4.00 8.00
19 Breaker

8 08.01.2022 -Zone 08 -M19-M01 By Road Crossing Day 0.50 0.50


8 07.03.2022 - 6" thickness heavy concrete breaking for pipe laying 5+747.2 5+645.2 Day 0.50 0.50
0.50 0.50 1.00
LABOURE
24 Un Skilled

Previously Certified - IPC Day 15.63 15.63


GM 07.01.2022,GM - Cleaning Work ( Heavy Jungle) 7+758 7+602 Day 0.38 0.38
GM 07.01.2022 GM - Repair Existing Pipe Line Day 0.25 0.25
GM 08.01.2022 GM - Repair Existing Pipe Line Day 0.19 0.19
8 08.01.2022 Zone 08 -M19-M01 By Road Crossing Day 0.50 0.50
CO 12.01.2022 CO - Repair Existing Pipe Line Day 0.25 0.25
4 12.01.2022 Zone 04 - Repair Existing Pipe Line Day 0.50 0.50
CO 13.01.2022 CO - Repair Existing Pipe Line Day 0.13 0.13
7 16.01.2022 Zone 07 Re-Construction Pavement in Pipe Line Day 1.00 1.00
8 23.01.2022 Zone 08 -M05-M19 Cleaning Work ( Heavy Jungle) Day 1.00 1.00
1 24.01.2022 Zone 01 -H68-H70 Cleaning Work ( Heavy Jungle) Day 0.13 0.13

Prepared Checked as per the Contract Checked & Recommanded


as per the Contract Checked & Certified as per the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 14: DAY WORK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location Measurement
ItemNo Zone DPR No Description Unit Nos Previous Current Total Qty
No From To Length Breath Depth Qty Qty

……………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
GM 26.01.2022 GM & DM - Repair Existing Pipe Line Day 0.25 0.25
8 26.01.2022 Zone 08 Cleaning Work ( Heavy Jungle) Day 2.00 2.00
8 27.01.2022 Zone 08 Cleaning Work ( Heavy Jungle) Day 3.00 3.00
GM 31.01.2022 GM - Cleaning Work ( Heavy Jungle) 4+426.5 4+398.5 Day 0.38 0.38
01.02.2022 90mm dia - Repair Existing Pipe Line Day 0.13 0.13
GM 01.02.2022 GM - Cleaning Work ( Heavy Jungle) 4+330.5 4+263.5 Day 0.50 0.50
4 02.02.2022 Zone 4 - Repair Existing Pipe Line Day 0.13 0.13
4 02.02.2022 -Pipe laying in between existing khomba trees & fence Day 0.88 0.88
4 03.02.2022 -Zone 04 -P19-P21 Cleaning Work ( Heavy Jungle) Day 0.19 0.19
06.02.2022 Making trial pit for existing pump line (intake) Day 1.00 1.00
07.02.2022 Making trial pit for existing pump line (intake) Day 1.00 1.00
7 08.02.2022 Zone 07 Re-Construction Pavement in Pipe Line Day 1.88 1.88
08.02.2022 Making trial pit for existing pump line (intake) Day 1.00 1.00
11.02.2022 Making trial pit for existing pump line (intake) Day 1.00 1.00
8 07.03.2022 - 6" thickness heavy concrete breaking for pipe laying 5+747.2 5+645.2 Day 0.50 0.50
1 14.03.2022 - H50-H41b - Communal water line repairing 0+632 0+620 Day 0.13 0.13
CO 27.04.2022 - Existing 110mm dia pipe laying Day 0.25 0.25

33.29 0.88 34.17

Prepared Checked as per the Contract Checked & Recommanded


as per the Contract Checked & Certified as per the Contract
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 14: DAY WORK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location Measurement
ItemNo Zone DPR No Description Unit Nos Previous Current Total Qty
No From To Length Breath Depth Qty Qty
Checked & Recommanded
as per the Contract Checked & Certified as per the Contract

……………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
25 Pipe layer

8 08.01.2022,Zone 08 -M19-M01 By Road Crossing Day 0.50 0.50


4 12.01.2022,Zone 04 - Repair Existing Pipe Line Day 0.50 0.50
7 16.01.2022,Zone 07 Re-Construction Pavement in Pipe Line Day 1.00 1.00
01.02.2022 90mm dia - Repair Existing Pipe Line Day 0.13 0.13
03.02.2022 -Filling water to excisting pipe line for tracing the end of pipe line Day 1.00 1.00
05.02.2022 - tracing exicisting Pump line from intake to wtp Day 0.50 0.50
8 07.03.2022 - 6" thickness heavy concrete breaking for pipe laying 5+747.2 5+645.2 Day 0.50 0.50
3.63 0.50 4.13
26 Mason

Previously Certified - IPC


7 16.01.2022 Zone 07 Re-Construction Pavement in Pipe Line Day 1.00 1.00
7 08.02.2022 Zone 07 Re-Construction Pavement in Pipe Line Day 1.88 1.88
2.88 - 2.88
29 Fitter

Previously Certified - IPC Day 3.38 3.38


GM 07.01.2022 GM - Repair Existing Pipe Line Day 0.25 0.25
GM 08.01.2022 GM - Repair Existing Pipe Line Day 0.19 0.19
CO 12.01.2022 CO - Repair Existing Pipe Line Day 0.25 0.25
CO 13.01.2022 CO - Repair Existing Pipe Line Day 0.13 0.13
GM 26.01.2022 GM & DM - Repair Existing Pipe Line Day 0.25 0.25
4 02.02.2022 Zone 04 - Repair Existing Pipe Line Day 0.13 0.13
8 06.02.2022 Zone 08 M19 -M01 - Repair Existing Pipe Line Day 0.19 0.19
1 14.03.2022 - H50-H41b - Communal water line repairing 0+632 0+620 Day 0.13 0.13
CO 27.04.2022 - Existing 110mm dia pipe laying Day 0.25 0.25
4.77 0.38 5.14
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 14: DAY WORK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location Measurement
ItemNo Zone DPR No Description Unit Nos Previous Current Total Qty
No From To Length Breath Depth Qty Qty

Prepared Checked as per the Contract Checked & Recommanded Checked & Certified as per the Contract
as per the Contract

……………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
36 Operator

Previously Certified - IPC Day 5.44 5.44


GM 07.01.2022 GM - Cleaning Work ( Heavy Jungle) 7+758 7+602 Day 0.38 0.38
8 08.01.2022 Zone 08 -M19-M01By Road Crossing Day 0.50 0.50
8 09.01.2022 Zone 08 -M19-M01 Cleaning Work ( Heavy Jungle) Day 0.44 0.44
GM 20.01.2022 GM F -E - Cleaning Work ( Heavy Jungle) Day 0.19 0.19
GM 21.01.2022 GM - Cleaning Work ( Heavy Jungle) Day 0.60 0.60
6 18.01.2022 Zone 06- B18-B19 Extra Excavation Day 0.25 0.25
8 22.01.2022 Zone 08 -M15-M07 Cleaning Work ( Heavy Jungle) Day 0.25 0.25
8 23.01.2022 Zone 08 -M05-M19 Cleaning Work ( Heavy Jungle) Day 1.00 1.00
1 24.01.2022 Zone 01 -H68-H70 Cleaning Work ( Heavy Jungle) Day 0.13 0.13
8 26.01.2022 Zone 08 Cleaning Work ( Heavy Jungle) Day 1.00 1.00
8 27.01.2022 Zone 08 Cleaning Work ( Heavy Jungle) Day 1.00 1.00
GM 31.01.2022 GM - Cleaning Work ( Heavy Jungle) 4+426.5 4+398.5 Day 0.38 0.38
GM 01.02.2022 GM - Cleaning Work ( Heavy Jungle) 4+330.5 4+263.5 Day 0.50 0.50
4 03.02.2022 -Zone 04 -P19-P21 Cleaning Work ( Heavy Jungle) Day 0.19 0.19
8 20.02.2022 Zone 08 -M22-M04,Cleaning Work ( Heavy Jungle) Day 0.25 0.25
8 07.03.2022 - 6" thickness heavy concrete breaking for pipe laying 5+747.2 5+645.2 Day 0.50 0.50
1 14.03.2022 - Jungle clearing for pipe line trace in RDA Road Day 0.25 0.25
GM 24.03.2022 - Heavy jungle clearing for pipe laying 5+092.81 5+050.21 Day 0.13 0.13
GM 25.03.2022 - Heavy Jungle clearing for pipe layng 5+145.6 5+165.6 Day 0.13 0.13
12.50 1.00 13.50
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 14: DAY WORK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location Measurement
ItemNo Zone DPR No Description Unit Nos Previous Current Total Qty
No From To Length Breath Depth Qty Qty

Prepared Checked as per the Contract Checked & Recommanded Checked & Certified as per the Contract
as per the Contract

……………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
MATERIAL
37 Cement

Previously Certified - IPC Bags 3.00 3.00


16.01.2022 Zone 07 Re-Construction Pavement in Pipe Line Bags 4.00 4.00
7 08.02.2022 Zone 07 Re-Construction Pavement in Pipe Line Bags 4.00 4.00
11.00 - 11.00
40 Fine aggregates

Previously Certified - IPC m3 0.22 0.22


16.01.2022 Zone 07 Re-Construction Pavement in Pipe Line m3 0.28 0.28
7 08.02.2022 Zone 07 Re-Construction Pavement in Pipe Line m3 0.70 0.70
1.20 - 1.20

42 Coarse aggregates 3/4"

Previously Certified - IPC m3 0.64 0.64


16.01.2022 Zone 07 Re-Construction Pavement in Pipe Line m3 0.57 0.57
1.21 - 1.21
Pura Neguma - Local Government Enhancement Sector Project
BILL NO. 14: DAY WORK
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Location Measurement
ItemNo Zone DPR No Description Unit Nos Previous Current Total Qty
No From To Length Breath Depth Qty Qty

Prepared Checked as per the Contract Checked & Recommanded


as per the Contract Checked & Certified as per the Contract

……………………………… ………………………………………………… ………………………………………………………… …………………………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
EXTRA WORK NO:04 (EXTRA PIPES & FITTINGS COST)

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha

Claim No :- IPC 18 Period Up to :- 30th April 2022 Contract No :- NWP-AF-WS-CKD-15

Contractor :- Sanken Construction (pvt) Ltd Date :- 10th May 2022

PREVIOUSE CLAIM CURRENT CLAIM CUMULATIVE CLAIM


Item No Description Unit Qty Rate Amount Remarks
Qty Amount Qty Amount Qty Amount
PIPE 2021 RATE BOOK
1 1/2''Pipe m 50.00 35.30 1,765.00 35.30 1,765.00
2 1''Pipe m 62.50 111.40 5,695.00 111.40 5,695.00 Table B/PVC 01
3 32mm upvc Pipe m 127.00 16.00 2,032.00 16.00 2,032.00
4 2" upvc Pipe m 142.00 12.00 1,704.00 12.00 1,704.00 Table B/PVC 01
5 63mm upvc Pipe m 256.00 4.00 1,024.00 4.00 1,024.00 Table B/PVC 01
6 75mm upvc Pipe m 355.00 7.50 2,662.50 7.50 2,662.50
7 90mm upvc Pipe m 486.00 18.50 8,991.00 18.50 8,991.00 Table B/PVC 01
8 110mm upvc Pipe m 674.00 2.00 1,348.00 2.00 1,348.00 Table B/PVC 01
- - - -
FITTINGS - - - -
9 1/2''Socket nos 15.00 16.00 240.00 16.00 240.00
10 1''Socket nos 20.00 49.00 775.00 49.00 775.00 Table B/PVC 02
11 32mm R/Socket nos 25.00 2.00 50.00 2.00 50.00
12 2" mm R/Socket nos 74.00 8.00 592.00 8.00 592.00 Table B/PVC 02
13 63mm R/Socket nos 129.00 1.00 129.00 1.00 129.00 Table B/PVC 02
14 75mm R/Socket nos 300.00 4.00 1,200.00 4.00 1,200.00
15 90mm R/Socket nos 340.00 12.00 4,080.00 12.00 4,080.00 Table B/PVC 02
16 110mm R/Socket nos 603.00 1.00 603.00 1.00 603.00 Table B/PVC 02
17 1/2'' Eaqul Tee nos 24.00 1.00 24.00 1.00 24.00 Table B/PVC 02
18 90mmX 50mm R/Tee nos 455.00 1.00 455.00 1.00 455.00 Table B/PVC 02
19 90mm x 1/2''Clamp Saddle nos 434.00 1.00 434.00 1.00 434.00 Table B/PVC 02
-
- -
Total Carried Over to Summary … - 33,803.50 - 33,803.50

Prepared Checked as per the Contract Checked & Recommanded as per the Contract Checked as per the Contract Checked & Certified as per
the Contractor
…………………………... …………………………………………………. ………………………………………………… ...…….…………………………………………
…………………………………………………….
Contractor Consultant TO/QS Consultant ARE/Engineer Asst . QS SPCU Engineer (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
EXTRA WORK NO:04 (EXTRA FITTINGS COST)
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 10th May 2022

Measurement
Item Description Unit Nos Quantity Remark
No Length Breath Depth

22.01.07
GM
75mm upvc Pipe m 4.00
1''Pipe m 2.00
1/2''Pipe m 1.30
75mm Double Socket nos 2.00
1'' Double Socket nos 2.00
1/2'' Double Socket nos 2.00

22.01.08
GM
75mm upvc Pipe m 3.50
1/2''Pipe m 2.00
75mm Double Socket nos 2.00
1/2'' Double Socket nos 2.00

22.01.12
CO/33
50mm upvc Pipe m 8.00
1/2''Pipe m 8.00
50mm Double Socket nos 4.00
1/2'' Double Socket nos 4.00

22.01.13
CO/34
1''Pipe m 8.00
1/2''Pipe m 4.00
1'' Double Socket nos 6.00
1/2'' Double Socket nos 2.00

22.01.26
GM
32mm upvc Pipe m 16.00
1/2''Pipe m 20.00
32mm Double Socket nos 2.00
1/2'' Double Socket nos 6.00

Prepared Checked as per the Contract Checked & Recommanded as per


the Contract Checked & Certified as per the Contract

……………………………… ………………………………………………… …………………………………………………………


…………………………………………………………
Pura Neguma - Local Government Enhancement Sector Project
EXTRA WORK NO:04 (EXTRA FITTINGS COST)
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 10th May 2022

Measurement
Item Description Unit Nos Quantity Remark
No Length Breath Depth
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

CURRENT TOTAL
75mm upvc Pipe m 7.50 7.50 7.50
50mm upvc Pipe m 8.00 8.00 8.00
32mm upvc Pipe m 16.00 16.00 16.00
1''Pipe m 10.00 10.00 10.00
1/2''Pipe m 35.30 35.30 35.30
75mm Double Socket nos 4.00 4.00 4.00
50mm Double Socket nos 4.00 4.00 4.00
32mm Double Socket nos 2.00 2.00 2.00
1'' Double Socket nos 8.00 8.00 8.00
1/2'' Double Socket nos 16.00 16.00 16.00

PREVIOUS TOTAL
90mm upvc Pipe m 18.50 18.50 18.50
90mm R/Socket nos 12.00 12.00 12.00
1/2''Pipe m 101.40 101.40 101.40
1/2''Socket nos 41.00 41.00 41.00
2" upvc Pipe m 4.00 4.00 4.00
2" mm R/Socket nos 4.00 4.00 4.00
1/2'' Eaqul Tee nos 1.00 1.00 1.00
90mmX 50mm R/Tee nos 1.00 1.00 1.00
90mm x 1/2''Clamp Saddle nos 1.00 1.00 1.00
63mm upvc Pipe m 4.00 4.00 4.00
63mm R/Socket nos 1.00 1.00 1.00
110mm upvc Pipe m 2.00 2.00 2.00
110mm R/Socket nos 1.00 1.00 1.00

Prepared Checked as per the Contract Checked & Recommanded as per


the Contract Checked & Certified as per the Contract
Pura Neguma - Local Government Enhancement Sector Project
EXTRA WORK NO:04 (EXTRA FITTINGS COST)
MEASUREMENT SHEET

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 10th May 2022

Measurement
Item Description Unit Nos Quantity Remark
No Length Breath Depth
……………………………… ………………………………………………… ………………………………………………………… …………………………………………………………
Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL USED ON THIS BILL

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item No Description Unit Qty Rate Amount


1.00 225mm x 45 Bends (PNT 11 Bends)
0
nos 1.00 8,249.19 8,249.19
4.00 160mm x 900 Bends (PNT 11 Bends) nos 1.00 3,236.82 3,236.82
5.00 160mm x 450 Bends (PNT 11 Bends) nos 1.00 2,688.27 2,688.27
25.00 90mm x 90mm Tee (PNT 11 uPVC Tee) nos 2.00 4,900.00 9,800.00
35.00 110mm Dia (PNT 11 uPVC Pipe) lm 123.00 652.41 80,246.43
36.00 160mm Dia (PNT 11 uPVC Pipe) lm 12.94 1,391.88 18,010.93
39.00 225mm Dia (PNT 7 uPVC Pipe) lm 12.94 1,825.53 23,622.36
64.00 160mm x 90mm Tee (PNT 11 uPVC Tee) nos 1.00 24,330.00 24,330.00
73.00 160mm Dia (PNT 7 uPVC Pipe) lm 192.00 1,464.07 281,101.44
76.00 90mm Dia (PNT 7 uPVC Pipe) lm 549.00 577.12 316,838.88
101.00 90mm Dia (PNT 7 uPVC Pipe) lm 1,509.00 704.56 1,063,181.04
115.00 90mm Dia (PNT 11 uPVC Repair Socket) nos 1.00 756.76 756.76
69.00 QT Bar 10mm (12M Length) Ton 0.766 146,000.00 111,836.00
100.00 4mm GI Wire Kg 168.52 333.33 56,172.26
99.00 50'x 3mm GI Wire Mesh Roll 2.00 23,231.48 46,462.96
56.00 250mm Dia. D/F Short Radius Bend 90deg Nos 1.00 31,500.00 31,500.00
1.1.8 150mm Dia DI D/F 2250 mm long Nos 1.00 50,100.00 50,100.00
5.5.2 250mm Dia F/PE 1000 mm long pipe with puddle, Nos
puddle welded @ site 1.00 74,500.00 74,500.00
4.3.1 250mm Dia DI D/F 2000 mm long (Puddle welded @ Nos
Site) 1.00 128,250.00 128,250.00
Total 2,330,883.34

Prepared Checked as per the Contract Checked & Recommanded as Checked & Certified as
per the Contract per the Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE BREAKDOWN

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

Item No Description Amount Remarks


(a) Total Material at Site for Bill No : 01 to 17 63,954,773.69 Previously Certified

(b) Total Material at Site for Bill No : 16

Total Material at Cost for Bill No (a+b) 63,954,773.69

(c) Material used upto this Bill - 18 2,330,883.34

(d) Total Material at Site ( a + b - c ) 61,623,890.35

Material at Site for this month - 80% 49,299,112.28

Prepared Checked as per the Contract Checked & Recommanded as Checked & Certified as
per the Contract per the Contract

……………………………… ……………………………………… ………………………………………………………… ……………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

1.0 225mm x 450 Bends (PNT 11 Bends) nos 8.00 7.00 1.00 8,249.19 57,744.33
2.0 225mm x 22.50 Bends (PNT 11 Bends)
0
nos 8.00 8.00 - 6,402.15 51,217.20
3.0 225mm x 11.250 Bends (PNT 11 Bends) nos 6.00 6.00 - 5,319.20 31,915.20
4.0 160mm x 90 Bends (PNT 11 Bends)
0
nos 35.00 33.00 2.00 3,236.82 106,815.06
5.0 160mm x 450 Bends (PNT 11 Bends) nos 36.00 35.00 1.00 2,688.27 94,089.45
6.0 160mm x 22.5 Bends (PNT 11 Bends)
0
nos 28.00 27.00 1.00 2,322.30 62,702.10
7.0 160mm x 11.25 Bends (PNT 11 Bends)
0
nos 18.00 15.00 3.00 2,322.30 34,834.50
8.0 110mm x 900 Bends (PNT 11 Bends) nos 20.00 20.00 - 1,339.04 26,780.80
9.0 110mm x 45 Bends (PNT 11 Bends)
0
nos 26.00 24.00 2.00 1,033.07 24,793.68
10.0 110mm x 22.5 Bends (PNT 11 Bends)
0
nos 24.00 20.00 4.00 935.86 18,717.20
11.0 110mm x 11.250 Bends (PNT 11 Bends) nos 14.00 10.00 4.00 935.86 9,358.60
12.0 90mm x 90 Bends (PNT 11 Bends)
0
nos 20.00 13.00 7.00 861.81 11,203.53
13.0 90mm x 450 Bends (PNT 11 Bends) nos 20.00 19.00 1.00 772.61 14,679.59
14.0 90mm x 22.5 Bends (PNT 11 Bends)
0
nos 24.00 18.00 6.00 654.07 11,773.26
15.0 90mm x 11.25 Bends (PNT 11 Bends)
0
nos 4.00 3.00 1.00 654.07 1,962.21
16.0 63mm x 900 Bends (PNT 11 Bends) nos 20.00 16.00 4.00 316.78 5,068.48
17.0 63mm x 45 Bends (PNT 11 Bends)
0
nos 20.00 20.00 - 316.78 6,335.60
18.0 63mm x 22.5 Bends (PNT 11 Bends)
0
nos 16.00 16.00 - 316.78 5,068.48
19.0 63mm x 11.250 Bends (PNT 11 Bends) nos 4.00 4.00 - 316.78 1,267.12
20.0 160mm x 160mm Tee (PNT 11 uPVC Tee) nos 3.00 3.00 - 14,390.00 43,170.00
21.0 160mm x 110mm Tee (PNT 11 uPVC Tee) nos 3.00 3.00 - 13,690.00 41,070.00
22.0 110mm x 110mm Tee (PNT 11 uPVC Tee) nos 6.00 5.00 1.00 6,500.00 32,500.00
23.0 110mm x 90mm Tee (PNT 11 uPVC Tee) nos 20.00 11.00 9.00 6,100.00 67,100.00
24.0 110mm x 63mm Tee (PNT 11 uPVC Tee) nos 10.00 1.00 9.00 5,700.00 5,700.00
25.0 90mm x 90mm Tee (PNT 11 uPVC Tee) nos 15.00 4.00 11.00 4,900.00 19,600.00
26.0 90mm x 63mm Tee (PNT 11 uPVC Tee) nos 26.00 15.00 11.00 4,450.00 66,750.00
27.0 63mm x 63mm Tee (PNT 11 uPVC Tee) nos 10.00 4.00 6.00 3,110.00 12,440.00
28.0 225mm Dia (PNT 11 uPVC Repair Socket) nos 5.00 5.00 - 5,756.76 28,783.80
29.0 160mm Dia (PNT 11 uPVC Repair Socket) nos 25.00 17.00 8.00 2,615.32 44,460.44
30.0 110mm Dia (PNT 11 uPVC Repair Socket) nos 25.00 23.00 2.00 1,135.14 26,108.22
31.0 90mm Dia (PNT 11 uPVC Repair Socket) nos 32.00 17.00 15.00 756.76 12,864.92
32.0 160-110mm (PNT 11 uPVC Reducer) nos 3.00 3.00 - 5,240.00 15,720.00
33.0 63mm Dia (PNT 11 uPVC End Cap) nos 60.00 60.00 - 66.25 3,975.00
34.0 90mm Dia (PNT 11 uPVC Pipe) lm 100.00 100.00 - 538.47 53,847.00
35.0 110mm Dia (PNT 11 uPVC Pipe) lm 6,950.00 3,856.44 3,093.56 652.41 2,515,980.02
36.0 160mm Dia (PNT 11 uPVC Pipe) lm 1,880.00 1,543.06 336.94 1,391.88 2,147,754.35

C/F 5,714,150.14

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

B/F 5,714,150.14
37.0 110mm Dia (PNT 7 uPVC Pipe) lm 7,560.00 4,221.26 3,338.74 453.31 1,913,539.37
38.0 160mm Dia (PNT 7 uPVC Pipe) lm 825.00 - 825.00 927.81 -
39.0 225mm Dia (PNT 7 uPVC Pipe) lm 500.00 487.06 12.94 1,825.53 889,142.64
40.0 Filter Media Gravel 2.5 -5.0mm m3 1.50 1.50 - 16,000.00 24,000.00
41.0 Filter Media Gravel 5.0 - 10.0mm m3 1.50 1.50 - 18,000.00 27,000.00
42.0 Filter Media Gravel 10.0 - 20.0mm m3 2.00 2.00 - 25,000.00 50,000.00
43.0 Filter Media Gravel 20.0 -40.0mm m3 2.00 2.00 - 25,000.00 50,000.00
44.0 Filter Media Gravel 40.0 -60.0mm m3 2.50 2.50 - 25,000.00 62,500.00
45.0 225mm x 90 Bends (PNT 11 Bends)
0
nos 6.00 6.00 - 8,292.05 49,752.30
46.0 63mm Dia (PNT 11 uPVC Repair Socket) nos 33.00 27.00 6.00 418.92 11,310.84
47.0 90mm Dia (PNT 11 uPVC End Cap) nos 30.00 17.00 13.00 251.22 4,270.74
48.0 QT Bar 10mm (12M Length) Ton 3.006 3.01 126,000.00 -
49.0 QT Bar 12mm (12M Length) Ton 7.000 7.000 126,000.00 -
50.0 QT Bar 25mm (12M Length) Ton 4.671 4.671 126,000.00 -
51.0 DN 150mm D/F Pipe 500mm with Puddle nos 6.00 5.00 1.00 28,000.00 140,000.00
52.0 DN 250mm F/PE Pipe 500mm with Puddle nos 1.00 1.00 - 27,200.00 27,200.00
53.0 DN 250mm Puddle Flange nos 1.00 1.00 - 6,100.00 6,100.00
54.0 GI Pipe 6''x5.4 / 5.8m nos 24.00 16.33 7.67 37,037.04 604,814.86
55.0 Penstock Door Frame & Other Accessories nos 1.00 1.00 - 178,525.00 178,525.00
56.0 250mm Dia. D/F Short Radius Bend 90deg Nr 2.00 1.00 1.00 31,500.00 31,500.00
57.0 280mm Dia (PNT 11 uPVC Pipe) lm 126.00 126.00 - 6,474.72 815,814.72
58.0 110mm Dia (PNT 11 uPVC Pipe) lm 18.00 18.00 - 952.35 17,142.30
59.0 90mm Dia (PNT 11 uPVC Pipe) lm 12.00 12.00 - 786.08 9,432.96
60.0 160mm Dia (PNT 11 uPVC Pipe) lm 36.00 36.00 - 2,031.34 73,128.24
61.0 63mm Dia (PNT 11 uPVC End Cap) nos 20.00 20.00 - 77.91 1,558.20
62.0 110mm x 450 Bends (PNT 11 Bends) nos 2.00 2.00 - 1,033.07 2,066.14
63.0 110mm x 90mm Tee (PNT 11 uPVC Tee) nos 1.00 1.00 - 12,260.00 12,260.00
64.0 160mm x 90mm Tee (PNT 11 uPVC Tee) nos 5.00 4.00 1.00 24,330.00 97,320.00
65.0 90mm x 90mm Tee (PNT 11 uPVC Tee) nos 18.00 18.00 - 5,830.00 104,940.00
66.0 280mm Dia (PNT 11 uPVC Pipe) lm 30.00 26.90 3.10 6,474.72 174,169.97
67.0 63mm Dia Tapered Core Tapered Flange Set 6.00 6.00 - 4,178.71 25,072.26
68.0 90mm x 450 Bends (PNT 11 Bends) nos 8.00 8.00 - 772.61 6,180.88
69.0 QT Bar 10mm (12M Length) Ton 7.46 6.97 0.49 146,000.00 1,018,204.00
70.0 QT Bar 12mm (12M Length) Ton 5.08 5.08 - 146,000.00 741,680.00
71.0 QT Bar 25mm (12M Length) Ton 2.00 2.00 - 146,000.00 292,000.00
72.0 110mm x 900 Tee (PNT 11 Tee) nos 7.00 7.00 - 12,260.00 85,820.00
73.0 160mm Dia (PNT 7 uPVC Pipe) lm 9,225.00 4,344.00 4,881.00 1,464.07 6,359,920.08
74.0 90mm Dia (PNT 7 uPVC Pipe) lm 8,592.00 8,592.00 366.34
75.0 90mm Dia (PNT 7 uPVC Pipe) lm 1,500.00 1,500.00 366.34
76.0 90mm Dia (PNT 7 uPVC Pipe) lm 20,790.76 7,090.26 13,700.50 577.12 4,091,930.85
77.0 225mm Dia (PNT 7 uPVC Pipe) lm 399.96 399.96 - 2,882.39 1,152,840.70
C/F 24,865,287.20

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

B/F 24,865,287.20
78.0 63mm Dia (PNT 7 uPVC Pipe) lm 7,164.00 2,433.92 4,730.08 298.70 727,011.90
79.0 63mm Dia (PNT 7 uPVC Pipe) lm 5,034.00 5,034.00 191.58
80.0 160mm Dia (PNT 11 uPVC Pipe) lm 219.96 219.96 - 2,202.72 484,510.29
81.0 280mm x 900 Bends (PNT 11 Bends) Bell nos 2.00 1.00 1.00 18,334.64 18,334.64
82.0 280mm x 900 Bends (PNT 11 Bends) gum nos 5.00 2.00 3.00 29,362.58 58,725.16
83.0 280mm x 450 Bends (PNT 11 Bends) nos 2.00 2.00 - 18,291.78 36,583.56
84.0 225mm x 900 Bends (PNT 11 Bends) nos 2.00 2.00 - 8,292.05 16,584.10
85.0 110mm x 900 Bends (PNT 11 Bends) nos 1.00 1.00 - 1,334.04 1,334.04
86.0 90mm x 900 Bends (PNT 11 Bends) nos 1.00 1.00 - 861.81 861.81
87.0 160mm x 900 Bends (PNT 11 Bends) nos 2.00 2.00 - 3,236.82 6,473.64
88.0 160mm x 450 Bends (PNT 11 Bends) nos 2.00 2.00 - 2,688.34 5,376.68
89.0 63mm x 450 Bends (PNT 11 Bends) nos 3.00 2.00 1.00 316.78 633.56
90.0 90mm x 450 Bends (PNT 11 Bends) nos 7.00 7.00 - 772.61 5,408.27
91.0 110mm Dia (PNT 7 uPVC Pipe) lm 300.00 300.00 - 715.22 214,566.00
92.0 90mm Dia (PNT 11 uPVC Pipe) lm 60.00 60.00 - 786.08 47,164.80
93.0 63mm Dia (PNT 7 uPVC Pipe) lm 951.96 951.96 - 298.70 284,350.45
94.0 225mmx160mm Dia (PNT11 uPVC Reducer Socket) nos 1.00 1.00 - 18,716.93 18,716.93
95.0 160mmx110mm Dia (PNT11 uPVC Reducer Socket) nos 3.00 3.00 - 5,240.00 15,720.00
96.0 110mmx90mm Dia (PNT11 uPVC Reducer Socket) nos 10.00 9.00 1.00 2,900.00 26,100.00
97.0 110mmx63mm Dia (PNT11 uPVC Reducer Socket) nos 3.00 - 3.00 8,071.43 -
98.0 110mmx63mm Dia (PNT11 uPVC Reducer Tee) nos 5.00 5.00 - 5,700.00 28,500.00
99.0 50'x 3mm GI Wire Mesh Roll 7.00 - 7.00 23,231.48 -
100.0 4mm GI Wire Kg 318.00 318.00 333.33 -
101.0 90mm Dia (PNT 7 uPVC Pipe) lm 10,420.98 5,041.98 5,379.00 704.56 3,552,377.43
102.0 63mm Dia (PNT 7 uPVC Pipe) lm 1,749.96 1,688.96 61.00 363.39 613,751.17
103.0 110mm Dia (PNT 7 uPVC Pipe) lm 1,803.00 1,803.00 873.57 -
104.0 110mm x 22.50 Bends (PNT 11 Bends) nos 3.00 3.00 - 1,411.00 4,233.00
105.0 110mm x 11.250 Bends (PNT 11 Bends) nos 3.00 3.00 - 1,411.00 4,233.00
106.0 90mm x 22.50 Bends (PNT 11 Bends) nos 20.00 20.00 - 994.00 19,880.00
107.0 90mm x 11.250 Bends (PNT 11 Bends) nos 20.00 20.00 - 994.00 19,880.00
108.0 63mm x 22.50 Bends (PNT 11 Bends) nos 2.00 2.00 - 353.00 706.00
109.0 110mm x 110mm Tee (PNT 11 uPVC Tee) nos 5.00 5.00 - 8,990.00 44,950.00
110.0 110mm x 63mm Tee (PNT 11 uPVC Tee) nos 2.00 1.00 1.00 12,240.00 12,240.00
111.0 90mm x 90mm Tee (PNT 11 uPVC Tee) nos 1.00 1.00 5,830.00 -
112.0 90mm x 63mm Tee (PNT 11 uPVC Tee) nos 3.00 3.00 - 8,620.00 25,860.00
113.0 63mm x 63mm Tee (PNT 11 uPVC Tee) nos 1.00 1.00 - 3,180.00 3,180.00
114.0 63mm Dia (PNT 11 uPVC Repair Socket) nos 4.00 4.00 - 418.92 1,675.68
115.0 90mm Dia (PNT 11 uPVC Repair Socket) nos 10.00 9.00 1.00 756.76 6,810.84
116.0 110mm Dia (PNT 11 uPVC Repair Socket) nos 2.00 - 2.00 1,135.00 -
117.0 110mmx90mm Dia (PNT11 uPVC Reducer Socket) nos 6.00 5.00 1.00 3,280.00 16,400.00
118.0 63mm Dia (PNT 11 uPVC End Cap) nos 7.00 7.00 - 83.59 585.13
119.0 90mm Dia (PNT 11 uPVC End Cap) nos 4.00 4.00 - 320.13 1,280.52

C/F 31,190,285.81

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

B/F 31,190,285.81
DI TOTAL ODER
1.0 Double Flange DI Pipe
1.1 150mm Diameter
1.1.1 5500 mm long Nos 9.00 9.00 78,540.00 706,860.00
1.1.2 4000 mm long Nos 6.00 6.00 63,600.00 381,600.00
1.1.3 3500 mm long Nos 2.00 2.00 59,100.00 118,200.00
1.1.4 3000 mm long Nos 3.00 3.00 54,600.00 163,800.00
1.1.5 1500 mm long Nos 4.00 4.00 41,100.00 164,400.00
1.1.6 2675 mm long Nos 2.00 2.00 54,600.00 109,200.00
1.1.7 1600 mm long Nos 1.00 1.00 45,600.00 45,600.00
1.1.8 2250 mm long Nos 1.00 - 1.00 50,100.00 -
1.1.9 500 mm long Nos 1.00 1.00 32,100.00 32,100.00
1.1.10 5800 mm long Nos 1.00 1.00 102,600.00 102,600.00
1.1.11 5000 mm long Nos 1.00 1.00 73,304.00 73,304.00
-
1.2 100mm Diameter -
1.2.1 5500 mm long Nos 20.00 20.00 64,500.00 1,290,000.00
1.2.2 5000 mm long Nos 4.00 4.00 60,500.00 242,000.00
1.2.3 4000 mm long Nos 20.00 20.00 52,500.00 1,050,000.00
1.2.4 3500 mm long Nos 6.00 6.00 48,500.00 291,000.00
1.2.5 3000 mm long Nos 3.00 3.00 44,500.00 133,500.00
1.2.6 2000 mm long Nos 7.00 7.00 36,500.00 255,500.00
1.2.7 1500 mm long Nos 1.00 1.00 32,500.00 32,500.00
1.2.8 1150 mm long Nos 1.00 1.00 32,500.00 32,500.00
1.2.9 2400 mm long Nos 1.00 1.00 40,500.00 40,500.00
1.2.10 1800 mm long Nos 1.00 1.00 36,500.00 36,500.00
1.2.11 1000 mm long Nos 4.00 4.00 28,500.00 114,000.00
1.2.12 5800 mm long Nos 2.00 2.00 80,080.00 160,160.00
1.2.13 5100 mm long Nos 1.00 1.00 64,500.00 64,500.00
1.2.14 3100 mm long Nos 1.00 1.00 48,500.00 48,500.00
-
1.3 80mm Diameter -
1.3.1 5500mm long Nos 8.00 8.00 66,000.00 528,000.00
1.3.2 4000mm long Nos 8.00 8.00 52,500.00 420,000.00
1.3.3 3500mm long Nos 6.00 6.00 48,000.00 288,000.00
1.3.4 2000mm long Nos 3.00 3.00 34,500.00 103,500.00
1.3.5 1500mm long Nos 15.00 15.00 30,000.00 450,000.00
1.3.6 3200mm long Nos 1.00 1.00 48,000.00 48,000.00
1.3.7 5000mm long Nos 1.00 1.00 61,500.00 61,500.00
1.3.8 5700mm long Nos 1.00 1.00 75,500.00 75,500.00
-
1.4 200mm Diameter -
1.4.1 4000 mm long Nos 2.00 2.00 89,000.00 178,000.00
1.4.2 3600 mm long Nos 1.00 1.00 89,000.00 89,000.00
1.4.3 1000 mm long Nos 1.00 1.00 50,000.00 50,000.00
1.4.4 500 mm long Nos 1.00 1.00 43,500.00 43,500.00

C/F 39,214,109.81

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

B/F 39,214,109.81

1.5 250mm Diameter -


1.5.1 2100 mm long Nos 1.00 1.00 110,500.00 110,500.00
-
2.0 Plainended DI Pipe -
2.1 150mm diameter -
2.1.1 5000 mm long Nos 2.00 2.00 52,360.00 104,720.00
2.1.2 4000 mm long Nos 2.00 2.00 41,890.00 83,780.00
2.1.3 3000 mm long Nos 4.00 4.00 31,420.00 125,680.00
2.1.4 2000 mm long Nos 3.00 3.00 20,950.00 62,850.00
-
2.2 80mm diameter -
2.2.1 3000 mm long Nos 4.00 4.00 27,000.00 108,000.00
-
2.3 100mm diameter -
2.3.1 3000 mm long Nos 5.00 5.00 25,880.00 129,400.00
-
3.0 Flange and Plainended Pipe -
3.1 150mm Diameter -
3.1.1 1000 mm long Nos 10.00 10.00 22,800.00 228,000.00
-
3.2 100mm Diameter -
3.2.1 1000 mm long Nos 22.00 22.00 18,250.00 401,500.00
3.2.2 1200 mm long Nos 2.00 2.00 22,250.00 44,500.00
3.2.3 850 mm long Nos 1.00 1.00 18,250.00 18,250.00
3.2.4 1500 mm long Nos 2.00 2.00 22,250.00 44,500.00
3.2.5 1800 mm long Nos 2.00 2.00 26,250.00 52,500.00
-
3.3 80mm Diameter -
3.3.1 1000 mm long Nos 22.00 22.00 17,250.00 379,500.00
-
3.4 200mm Diameter -
3.4.1 1150 mm long Nos 1.00 1.00 38,000.00 38,000.00
3.4.2 2000 mm long Nos 1.00 1.00 44,500.00 44,500.00
3.4.3 1000 mm long Nos 1.00 1.00 31,500.00 31,500.00
-
4.0 Double Flange pipe with puddle -
4.1 100mm diameter -
4.1.1 1500 mm long (Puddle welded @ site) Nos 4.00 4.00 42,750.00 171,000.00
4.1.2 1100 mm long (Puddle @ Center) Nos 1.00 1.00 42,750.00 42,750.00
4.1.3 500 mm long (Puddle @ Center) Nos 2.00 2.00 34,750.00 69,500.00
4.1.4 1500 mm long (Puddle welded @ site) Nos 2.00 2.00 42,750.00 85,500.00

4.2 150mm diameter -


4.2.1 1500 mm long (Puddle welded @ Site) Nos 20.00 20.00 54,900.00 1,098,000.00
4.2.2 1500 mm long (Puddle @ Center) Nos 4.00 4.00 54,900.00 219,600.00
4.2.3 500 mm long (Puddle welded @ Site) Nos 1.00 1.00 45,900.00 45,900.00

C/F 42,954,039.81
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

B/F 42,954,039.81

4.3 250mm diameter -


4.3.1 2000 mm long (Puddle welded @ Site) Nos 1.00 - 1.00 128,250.00 -

5.0 Flange and Plainended pipe with puddle -


5.1 80mm diameter -

5.1.1 1000 mm long pipe with puddle, puddle 475 mm


from flange end Nos 30.00 30.00 25,500.00 765,000.00

5.1.2 1000 mm long pipe with puddle, pudle 450 mm Nos 8.00 8.00 25,500.00 204,000.00
from flange end
1500 mm long pipe with puddle, puddle welded @
5.1.3 site Nos 1.00 1.00 30,000.00 30,000.00

5.1.4 300 mm long pipe with puddle, puddle welded @ Nos 1.00 1.00 21,000.00 21,000.00
site

5.2 100mm diameter -


5.2.1 1000 mm long pipe with puddle, puddle 450 mm Nos 6.00 6.00 28,500.00 171,000.00
from flange end
600 mm long pipe with puddle, puddle 100 mm
5.2.2 from flange end Nos 1.00 1.00 28,500.00 28,500.00

5.2.3 500 mm long pipe with puddle, puddle welded @ Nos 1.00 1.00 24,500.00 24,500.00
site
5.2.4 300 mm long pipe with puddle, puddle welded @ Nos 1.00 1.00 24,500.00 24,500.00
site

5.3 150mm diameter -


5.3.1 1000 mm long pipe with puddle, puddle 450 mm Nos 5.00 5.00 36,600.00 183,000.00
from flange end
5.3.2 800 mm long pipe with puddle, puddle welded @ Nos 1.00 1.00 36,600.00 36,600.00
site

5.4 200mm diameter -


5.4.1 1000 mm long pipe with puddle, puddle 450 mm
from flange end Nos 2.00 2.00 50,000.00 100,000.00

5.4.2 600 mm long pipe with puddle, puddle 100 mm Nos 1.00 1.00 50,000.00 50,000.00
from plain end

5.5 250mm diameter -


5.5.1 2500
site
mm long pipe with puddle, puddle welded @ Nos 1.00 1.00 110,500.00 110,500.00

5.5.2 1000 mm long pipe with puddle, puddle welded @ Nos 1.00 1.00 74,500.00 -
site

6.0 Plainended pipe with puddle -


6.1 80mm diameter -

6.1.1 1000 mm long pipe with puddle, puddle 520 mm Nos 8.00 8.00 25,500.00 204,000.00
from end

C/F 44,906,639.81
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

B/F 44,906,639.81

6.2 100mm diameter -


1000 mm long pipe with puddle, puddle 520 mm
6.2.1 from end Nos 6.00 6.00 28,500.00 171,000.00

6.3 150mm diameter -


6.3.1 1000 mm long pipe with puddle, puddle 520 mm Nos 5.00 5.00 36,600.00 183,000.00
from end

6.4 200mm diameter -


1000 mm long pipe with puddle, puddle 520 mm
6.4.1 from end Nos 2.00 2.00 50,000.00 100,000.00

7.0 Socket and Spigot Pipe -


7.1 80mm Diameter -
7.1.1 6000 mm long Pipe Nos 4.00 4.00 59,000.00 236,000.00
7.1.2 3000 mm long Pipe Nos 4.00 4.00 27,000.00 108,000.00

7.2 100mm Diameter -


7.2.1 6000 mm long Pipe Nos 5.00 5.00 58,000.00 290,000.00
7.2.2 3000 mm long Pipe Nos 5.00 5.00 25,880.00 129,400.00

7.3 150mm Diameter -


7.3.1 6000 mm long Pipe Nos 3.00 3.00 75,000.00 225,000.00
7.3.2 3000 mm long Pipe Nos 3.00 3.00 31,420.00 94,260.00

9.0 Step Coupling -


9.1 150mm diameter -
9.1.1 150mm dia / 160mm dia Nos 34.00 34.00 14,500.00 493,000.00
9.1.2 150mm dia Nos 6.00 6.00 14,500.00 87,000.00

9.2 100mm diameter -


9.2.1 100mm dia / 110mm dia Nos 32.00 32.00 9,500.00 304,000.00
9.2.2 100mm dia Nos 10.00 10.00 9,500.00 95,000.00

9.3 80mm diameter -


9.3.1 80mm dia / 90mm dia Nos 68.00 68.00 8,500.00 578,000.00
9.3.2 80mm dia Nos 8.00 8.00 8,500.00 68,000.00

9.4 200mm diameter -


9.4.1 200mm dia / 225mm dia Nos 4.00 4.00 18,900.00 75,600.00

10.0 Double Flange Bend -


10.1 150mm Diameter -
10.1.1 45 0 Nos 16.00 16.00 19,900.00 318,400.00
10.2 100mm Diameter -
10.2.1 45 0 Nos 40.00 40.00 12,900.00 516,000.00
10.3 80mm Diameter -
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

10.3.1 45 0 Nos 44.00 44.00 11,900.00 523,600.00


C/F 49,501,899.81

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

B/F 49,501,899.81

11.0 All Flange Tee -


11.1 150mm Diameter -
11.1.1 50 mm Nos 4.00 4.00 37,000.00 148,000.00
11.1.2 50 mm Nos 8.00 8.00 37,000.00 296,000.00

11.2 100mm Diameter -


11.2.1 50 mm Nos 12.00 12.00 23,000.00 276,000.00
11.2.2 100 mm Nos 1.00 1.00 24,000.00 24,000.00

11.3 80mm Diameter -


11.3.1 50 mm Nos 11.00 11.00 19,000.00 209,000.00

11.4 250mm Diameter -


11.4.1 150 mm Nos 1.00 1.00 89,000.00 89,000.00
11.4.2 250 mm Nos 1.00 1.00 103,000.00 103,000.00

12.0 Air Valve - Double Orifice -


12.1 50mm Diameter -
12.1.1 with isolating cock Nos 22.00 22.00 36,000.00 792,000.00

13.0 Air Valve - Single Orifice -


13.1 50mm Diameter -
13.1.1 with isolating cock Nos 13.00 13.00 12,100.00 157,300.00

13.2 25mm Diameter (Single Orifice) -


13.2.1 with isolating cock (Screwed down type) Nos 22.00 22.00 19,800.00 435,600.00

14.0 Sluice Valve -


14.1 80mm Diameter -
14.1.1 Knob type Nos 31.00 31.00 29,500.00 914,500.00
14.1.2 Wheel Type Nos 2.00 2.00 29,500.00 59,000.00

14.2 50 mm Diameter -
14.2.1 Knob Type Nos 3.00 3.00 19,900.00 59,700.00
-
14.3 100mm Diameter -
14.3.1 Knob type Nos 2.00 2.00 38,500.00 77,000.00
14.3.2 Wheel Type Nos 1.00 1.00 38,500.00 38,500.00

14.4 150mm Diameter -


14.4.1 Knob type Nos 4.00 4.00 62,000.00 248,000.00
14.4.2 Wheel Type Nos 1.00 1.00 62,000.00 62,000.00

14.5 200mm Diameter -


14.5.1 Wheel Type Nos 1.00 1.00 99,500.00 99,500.00
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

C/F 53,589,999.81

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

B/F 53,589,999.81

14.6 250mm Diameter -


14.6.1 Knob type Nos 1.00 1.00 150,000.00 150,000.00
14.6.2 Wheel Type Nos 2.00 2.00 150,000.00 300,000.00

15.0 Flange Adaptor -


15.1 80mm Diameter -
15.1.1 80mm Flange Adaptor Nos 45.00 45.00 8,500.00 382,500.00

15.2 100mm Diameter -


15.2.1 100mm Flange Adaptor Nos 17.00 17.00 9,300.00 158,100.00

15.3 150mm Diameter -


15.3.1 150mm Flange Adaptor Nos 23.00 23.00 13,500.00 310,500.00
15.3.2 160mm / 150mm Flange Adaptor Nos 9.00 9.00 13,500.00 121,500.00

15.4 200mm Diameter -


15.4.1 200mm Flange Adaptor Nos 3.00 3.00 18,500.00 55,500.00

15.5 250mm Diameter -


15.5.1 250mm Flange Adaptor to 280mm uPVC Nos 10.00 10.00 24,500.00 245,000.00

16.0 Manhole Cover -


16.1 Non - Ventilated -
Lockable, 600mm Clear Opening Square frame D-
16.1.1 400 Nos 54.00 54.00 48,500.00 2,619,000.00

16.2 Ventilated -
Lockable, 600mm Clear Opening Square frame D-
16.2.1 400 Nos 32.00 32.00 49,500.00 1,584,000.00

16.2.2 600 x 750 Squire Type Nos 1.00 1.00 67,500.00 67,500.00

17.0 Gate Valve -


17.1 80mm Diameter -
17.1.1 Knob Type Nos 8.00 8.00 29,500.00 236,000.00

17.2 100mm Diameter -


17.2.1 Knob Type Nos 6.00 6.00 38,500.00 231,000.00

17.3 150mm Diameter -


17.3.1 Knob Type Nos 5.00 5.00 62,000.00 310,000.00

17.4 200mm Diameter -


17.4.1 Knob Type Nos 2.00 2.00 99,500.00 199,000.00
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

C/F 60,559,599.81

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)

B/F 60,559,599.81

18.0 Clamp Saddle with gunmetal thread in side -


18.1 225 x 25 Nos 1.00 1.00 20,350.00 20,350.00
18.2 160 x 25 Nos 5.00 5.00 10,890.00 54,450.00
18.3 110 x 25 Nos 3.00 3.00 8,690.00 26,070.00
18.4 90 x 25 Nos 12.00 12.00 6,550.00 78,600.00
18.5 63 x 25 Nos 1.00 1.00 5,450.00 5,450.00

19.0 Duck Foot Bend D/F -


19.1 200mm Diameter -
19.1.1 90 0 Nos 1.00 1.00 56,000.00 56,000.00
19.2 150mm Diameter -
19.2.1 90 0 Nos 1.00 1.00 39,000.00 39,000.00
19.3 100mm Diameter -
19.3.1 90 0 Nos 2.00 2.00 39,000.00 78,000.00
-
20.0 Couplings -
20.1 100mm Diameter Nos 2.00 2.00 9,500.00 19,000.00
20.2 150mm Diameter Nos 3.00 3.00 14,500.00 43,500.00
20.3 200mm Diameter Nos 2.00 2.00 18,900.00 37,800.00

21.0 Double Flange Short Radius -


21.1 150mm x 90 0 Nos 2.00 2.00 19,900.00 39,800.00
21.2 80mm x 90 0 Nos 3.00 3.00 11,900.00 35,700.00
21.3 100mm x 90 0 Nos 2.00 2.00 12,900.00 25,800.00

22.0 Double Flange Long Radius -


22.1 150mm x 90 Nos 6.00 6.00 38,000.00 228,000.00
22.2 100mm x 90 Nos 6.00 6.00 24,000.00 144,000.00
22.3 200mm x 90 Nos 2.00 2.00 49,000.00 98,000.00
22.4 250mm x 90 Nos 2.00 2.00 75,000.00 150,000.00

23.0 Bell Mouth Flange Type -


23.1 100 mm Diameter Nos 2.00 2.00 10,900.00 21,800.00
23.2 150 mm Diameter Nos 1.00 1.00 14,900.00 14,900.00

24.0 Quick Opening Valve -


24.1 100mm Diameter Nos 1.00 1.00 26,400.00 26,400.00

25.0 Double Flange Taper Core Taper flange -


25.1 100mm Diameter Nos 2.00 2.00 7,540.00 15,080.00
25.2 80mm Diameter Nos 1.00 1.00 5,720.00 5,720.00
Pura Neguma - Local Government Enhancement Sector Project
MATERIAL AT SITE

Project Name :- Construction of Water Supply Scheme For Karuwalagaswewa Pradeshiya Sabha
Claim No :- IPC 18
Period Up to :- 30th April 2022
Contract No :- NWP-AF-WS-CKD-15
Contractor :- Sanken Construction (pvt) Ltd
Date :- 30th May 2022

No Item Unit Recived Qty Balance Qty Used Qty Rate Used Metrial Value

26.0 Double Flange Reducer Socket -


26.1 100mm x 80mm Nos 1.00 1.00 9,900.00 9,900.00

TOTAL 61,832,919.81
80% Claim Amount 49,466,335.85

Prepared Checked as per the Contract Checked & Recommanded as per the Checked & Certified as per the
Contract Contract

……………………………… ………………………………………………… ………………………………… …………………………………………


Contractor Consultant To/Qs Consultant ARE/Engineer Engineer/To (SPCU)