Professional Documents
Culture Documents
BELGRADE, 2012
Publisher: Public Enterprise Roads of Serbia, Bulevar kralja Aleksandra 282,
Belgrade
Edition:
CONTENTS
PE Roads of Serbia i
Serbian Road Supervision Manual Legislation and Contracts
PE Roads of Serbia 1
Legislation and Contracts Serbian Road Supervision Manual
Materials (Materijali) are things of all kinds Supervising Engineer (Nadzorni organ) is
(other than Plant Plant) intended to be or the person who makes supervision defined in
which already represent a part of the the Law on Planning and Construction.
Permanent Works, including the supply-only
materials to be supplied by the Contractor Supervision/Supervisor (Stručni nadzor) is
under the Contract. defined in the Law on Planning and
Construction.
1
Taking-Over Certificate (Potrvrda o
The terms designating persons or parties comprise prijemu) is a certificate for the taking-over of
companies and other legal persons.
2
In the Red Book, the term „Engineer” is translated in the Works, issued by the Engineer with
Serbian as “Nadzorni organ”, which is not in accordance approval of the Employer.
with regulations in the RS.
2 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
Temporary Works (Privremeni radovi) are - Law on planning and construction, Official
all temporary works required for the Gazette of the RS, No. 72/09, 81/09,
execution and completion of the Permanent 64/10, 24/11
Works, and for the remedying of any defects. - Law on public roads, Official Gazette of
the RS, No. 105/05, 123/07
Tender (Ponuda) represents the signed offer - Law on railway, Official Gazette of the RS,
by the Contractor to the Employer and all the No. 18/05; the new Law on Railway is in
additional documents the Contractor the procedure.
submitted with it. - Law on Ratification of the Aarhus
convention on access to information,
Time for Completion (Rok za završetak) is public participation in decision-making
the time for the completion of Works or of the and the right to legal protection in
Section from the Commencement Date. environmental matters, Official Gazette of
the RS, No. 38/09
Unforeseeable (Nepredvidivo) is a situation - Law on Ratification of the Espoo
which an experienced contractor could not convention on environmental impact
have foreseen prior to the submission of the assessment in a transboundary Context,
Tender. Official Gazette, No. RS 102/07
- Law on state survey and real estate
Variation (Izmena) is any ordered or cadastre, Official Gazette of the RS, No.
approved change to the Works. 72/09 and 18/10
- Law on strategic environmental impact
Works (Radovi) comprise the Permanent assessment, Official Gazette of the RS,
Works and/or Temporary Works according to No. 135/04 and 88/10
the Contract. - Law on waste management, Official
Gazette of the RS, No. 36/09 and 88/10
1.1.2 REFERENCE DOCUMENTS - Law on water, Official Gazette of the RS,
No. 30/10
- Mining law, Official Gazette of the RS, No.
1.1.2.1 Laws 34/06
- Occupational safety and health law,
- Fire safety law, Official Gazette of the RS, Official Gazette of the RS, No. 101/05
No. 111/09 - Public procurement act, Official Gazette of
- Law of contract and torts (Law on the RS, No. 116/08
obligations), Official Gazette of SFRY, No. - Road traffic safety law, Official Gazette of
29/78, 39/85, 45/89 and 57/89 and Official the RS, No. 41/09, 53/10, 101/11.
Gazette of SRY, No. 31/93 and Official
Gazette of the Serbia and Montenegro,
No. 1/03 – The Constitutional Charter 1.1.2.2 Rulebooks
- Law on agricultural land, Official Gazette
of the RS, No. 62/06, 65/08 and 41/09. - Rulebook on content and method for
The new law is in the procedure. conducting expert supervision, Official
- Law on air protection, Official Gazette of Gazette of the RS, No. 7/10
the RS, No. 36/09 - Rulebook on content and method for
- Law on arbitration, Official Gazette of the conducting technical control of the
RS, No. 46/06 detailed design, Official Gazette of the
- Law on environmental impact RS, No. 93/11
assessment, Official Gazette of the RS, - Rulebook on content and method for
No. 135/04 and 36/09 conducting the technical examination of a
- Law on environmental protection, Official structure and issuing usage permits,
Gazette of the RS, No. 135/04, 36/09, Official Gazette of the RS, No. 93/11
72/09 - Rulebook on content and method for
- Law on free access to information of issuing building permits, Official Gazette
public importance, Official Gazette of the of the RS, No. 93/11
RS, No. 120/04, 54/07, 104/09, 36/10 - Rulebook on content and method for
- Law on integrated environmental pollution keeping inspection books and
prevention and control , Official Gazette of construction diaries, Official Gazette of
the RS, No. 135/04 the RS, No. 105/03
- Law on noise protection, Official Gazette - Rulebook on content and method for
of the RS, No. 36/09 and 88/10 observing soil and the structure during
use, Official Gazette of the RS, No. 93/11
PE Roads of Serbia 3
Legislation and Contracts Serbian Road Supervision Manual
- Rulebook on obligatory elements of the - Rulebook on the license for the work of
bidding documentation in public geodetic organization and geodetic
procurement procedures, Official Gazette licenses, Official Gazette of the RS, No.
of the RS, No. 98/04 33/10
- Rulebook on occupational safety for - Rulebook on the limits, methods for
conducting construction works, Official measuring emissions, criteria for
Gazette of the RS, No. 53/97 establishing measurement locations and
- Rulebook on preventative measures for recording of data, Official Gazette of the
occupational safety and health during RS No. 54/92 and 30/99
exposure to vibration, Official Gazette of - Rulebook on the method and conditions
the RS, No. 93/11 for acquiring authorization to plan and
- Rulebook on records for public roads and perform geodetic works in engineering-
accompanying structures, as well as technical fields, Official Gazette of the RS,
technical data for those roads, Official No. 59/02
Gazette of SFRY, No. 52/83 and 60/83 - - Rulebook on the method and minimum
corr. and Official Gazette of Serbia and number of quality tests for waste water,
Montenegro No. 1/03 - Constitutional Official Gazette of the RS, No. 47/83 and
charter 13/84
- Rulebook on surveying and cadastre of - Rulebook on the method and process for
lines, Official Gazette of the RS, No. submitting an application for a change to
63/10 a property and declaration of a geodetic
- Rulebook on technical normative and organization, Official Gazette of the RS,
conditions for planning and construction of No. 56/02
tunnels on roads, Official Gazette of - Rulebook on the method for determining
SFRY, No. 656-5 and maintaining a zone of sanitary
- Rulebook on the appearance, content and protection for water supply sources,
positioning of the construction information Official Gazette of the RS, No. 92/08
board, Official Gazette of the RS, No. 4/10 - Rulebook on the methods for
- Rulebook on the categories, testing and measurement of noise, content and scope
classification of waste, Official Gazette of of reporting on noise measurement,
the RS, No. 56/10 Official Gazette of the RS, No. 72/10
- Rulebook on the conditions and method - Rulebook on the minimum warranty
for collecting, transporting, storing and periods for individual types of structures
treatment of waste which is used as or works, Official Gazette of the RS, No.
secondary raw materials or for obtaining 93/11
energy, Official Gazette of the RS, No. - Rulebook on the technical normative
98/10 when handling explosive compounds and
- Rulebook on the conditions which must be placement of explosive in mining, Official
fulfilled by a professional organization for Gazette of SFRY, No. 26/88 and 63/88
measuring noise, Official Gazette of the - Rulebook on the technical normative,
RS, No. 72/10 methodology for drafting technical
- Rulebook on the content of the documentation and control of technical
elaboration of construction site documentation for the execution of
organization, Official Gazette of the RS, geodetic works in engineering-technical
No. 31/92 fields, Official Gazette of the RS, No.
- Rulebook on the content, method, 59/02
conditions of supervision and control of - Rulebook on traffic safety conditions
the execution of geodetic works in which transportation infrastructure and
engineering-technical fields, Official other elements of public roads must fulfil,
Gazette of the RS, No. 59/02 Official Gazette of the RS, No. 50/11
- Rulebook on the creation and keeping of - Rulebook on traffic signalisation, Official
the cadastre of properties, Official Gazette Gazette of the RS, No. 26/10.
of the RS, No. 46/99
- Rulebook on the emission limits, method
and deadlines for measurement and 1.1.2.3 Regulations
recording of data, Official Gazette of the
RS No. 30/97 and 35/97 - Regulation (EU) No 305/2011 of the
European Parliament and of the Council
- Rulebook on the execution of expert
of 9 March 2011 laying down harmonised
supervision, examination and acceptance
conditions for the marketing of
of works, Official Gazette of the RS, No.
construction products and repealing
43/10
4 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
Council Directive 89/106/EEC, Official The Employer and the Contractor may add
Journal of the European Union, 88/11 an Annex to the Contract in cases of:
- Regulation on occupational safety and - Change in the position of the works;
health on temporary and mobile - Change with the entire contract price (in
construction sites, Official Gazette of the accordance with the Public procurement
RS, No. 14/09 act);
- Regulation on depositing waste in dump - Change of deadline for the completion of
sites, Official Gazette of the RS, No. works;
92/10 - Change in the representatives for the
- Regulation on the establishment of house Employer and/or the Contractor;
numbers, marking of buildings with - Other changes.
numbers and marking of names of
settlements, streets and squares, Official In the case of an Annex being added to the
Gazette of the RS, No. 110/03, 137/04 Contract, the Supervisor inspects whether
and 58/06. the Contractor has delivered all the required
documentation required for the Annex and
also checks if all the data is correct.
1.1.2.4 Other
PE Roads of Serbia 5
Legislation and Contracts Serbian Road Supervision Manual
informative events – seminars, workshops, and construction, and bears all the risk
panel discussions, professional lectures; except from force majeure;
introduction of new trends in the construction - There is no Engineer;
sector; promotion of the role of a consultant - The price of the works is a lump sum.
engineer in investment ventures; informing - Conditions of contract for electrical and
members of relevant developments in the mechanical works
construction sector and other areas of Yellow Book (old)
significance for providing quality engineering - “Turnkey” system conditions of
consulting services; exchange of experiences contract;
between members and related foreign - Designing and performance of
companies; establishment of new business electrical and mechanical works, as
opportunities in the country and abroad; well as the supply and installation of
improvement of the business climate in the electrical and mechanical equipment at
Republic of Serbia, and improvement of the the location;
profession in general. The establishment of - Technical documentation is created by
the Association was significantly supported the Contractor;
by the US Agency for International - The total price of the works is a lump
Development – USAID. The Association also sum.
cooperates with the World Bank/International - Conditions of Contract for Facilities and
Finance Corporation – IFC. Design - Build
The official web page of ACES is Yellow Book (new)
www.aces.rs - For electrical, mechanical and
construction works according to the
FIDIC publications which have been Contractor’s design;
translated into the Serbian language are: - Part of the design performed by the
- Conditions of Contract for Construction for Employer: contained in the Employer’s
Building and Engineering Works Designed requirements;
by the Employer – Parts I and II - For electrical and mechanical facilities
Red Book Part I and equipment;
- Employer (Investor) provides the entire - Need for modern multi-disciplinary
or almost entire design; contracts recognised for the first time;
- It is possible that the Contractor - Payments according to the lump sum
designs a part of it; based on the payment plan, however,
- Civil engineering and building measurements are also possible;
construction designs; - Engineer administers the contract
- Payment based on the measured (administration), supervises the
quantities and unit prices; production, performance and works,
- Contractual values exceed 500,000 and verifies the payments;
USD; - The procedure for dispute resolution is:
- Engineer administers the contract DAB → amicable settlement →
(administration), supervises the works arbitration.
and verifies all payments; - Client/Consultant Model Services
- The procedure for dispute resolution is: Agreement
Dispute Adjudication Board→ amicable White Book
settlement → arbitration. - Client/Consultant Model Services
Red Book Part II Agreement;
- Guidance for the Preparation of - Recommended for the purpose of
Particular Conditions; feasibility studies and similar studies;
- Forms of Letter of Tender; - For the service of project
- Forms of Contract Agreement; management.
- Forms of Dispute Adjudication - Short Form of Contract
Agreement; Green Book
- Conditions of Contract for Design – Build - Short form of contract
and Turnkey - Short execution time (less than 6
Orange Book months);
- The “turnkey” system conditions of - Simple and repetitive works
contract intended for the delivery of a (excavation works represent a good
completely equipped structure (mostly example);
facilities) ready for utilisation; - Contract price is less than 500,000
- The Contractor assumes complete USD;
responsibility for the designing, supply
6 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
PE Roads of Serbia 7
Legislation and Contracts Serbian Road Supervision Manual
The Employer shall provide, at the request of construction site; the authority will be
the Contractor, the required level of responsible for the supervision of the given
assistance to: site. The Supervising Engineer is authorised
- Obtain copies of the Laws of the Country to assign duties and authority to assistants.
relevant to the Contract; The assignment or revocation of any duties
- When the Contractor applies for a permit and authorisations is performed in writing and
or an approval which must be provided in becomes effective upon the delivery of the
accordance with the Laws of the Country. same to the Parties. If the Contractor does
not agree with any decision or instruction
The Employer is obliged to issue (within 28 from an assistant, the Contractor may refer
days as of the day of receipt of the the matter to the Engineer who shall promptly
Contractor’s request) a written confirmation confirm or vary the assistant’s decision.
that the Works will be paid for.
If the Engineer has no objections to the
1.2.1.2.3 Engineer – Supervisor Works, this still does not constitute approval
and it does not influence his right to reject the
Chapter 3 of the General Conditions includes Works, Facilities or Materials.
the Engineer’s Duties and Authority,
Delegation by the Engineer, Instructions of The Engineer may issue to the Contractor (at
the Engineer, Replacement of the Engineer, any time) instructions or modified Drawings.
and Decisions. If this implies a Variation in the price or the
deadline, Clause 13 is applied. If possible,
In the Serbian version of the FIDIC the Engineer’s Instructions to the Contractor
publication, the term “Engineer” is translated should be in written form.
as “Supervising Engineer” and it relates to a
legal entity. In accordance with the If the Employer decides to replace the
Regulations in regards to quality control the Engineer, the Employer shall notify the
“Supervising Engineer” is a physical person Contractor regarding this no less than 42
who performs supervision. Hereinafter the days prior to the intended date of the
term of “Engineer” will be used instead. replacement. The Employer notifies the
Contractor in written form with the name,
The Employer shall appoint the Engineer who address and relevant experience of the new
will carry out the duties assigned to him. The Engineer.
Engineer’s staff shall include qualified
engineers and other professionals who are Before any decisions are made, the Engineer
competent to carry out such duties. should consult both Parties in order to reach
an agreement. The Engineer shall give notice
The duties, the authority, the delegation, the to both parties of each decision or agreement
replacement and the instructions of the along with all supporting particulars.
Engineer are presented in Chapter 3 of the
General Conditions. 1.2.1.2.4 The Contractor
The Engineer is not authorised to amend the The Contractor’s General Obligations,
Contract. Performance Security, Contractor’s
Representative, Subcontractors, Assignment
The Engineer may exercise the authority of Benefit of Subcontract, Co-operation,
implied by the General Conditions if they are Setting Out, Safety Procedures, Quality
not amended along with the Particular Assurance, Site Data, Sufficiency of the
Conditions. Accepted Contract Amount, Unforeseeable
Physical Conditions, Rights of Way and
The Engineer acts on behalf of the Employer. Facilities, Avoidance of Interference, Access
Route, Transport of Goods, Contractor’s
The Engineer is not authorised to relieve Equipment, Protection of the Environment,
either party of any duties, responsibilities or Electricity, Water and Gas, Employer’s
obligations under the Contract. Equipment and Free-Issue Materials,
Progress Reports, Security of the Site,
No single act of the Engineer shall relieve the Contractor’s Operations on Site, and Fossils,
Contractor from responsibility under the are explained in Chapter 4 of the General
Contract. Conditions.
The Engineer must appoint a Supervising For each subcontractor (except for Material
Engineer (a physical person) for each suppliers) the Contractor needs to have the
8 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
Engineer’s approval. The Contractor shall The Contractor will provide the Engineer with
provide the Engineer with proposals (with details of any accidents as soon as possible.
supporting explanations) in written form 28
days prior to the commencement of any work The Engineer is entitled to demand the
by Subcontractors. removal from the Site any employee of the
Contractor who fails to respect the conditions
The Contractor must establish a system of of the Contract, fails to perform their duties in
quality assurance aimed at meeting the a professional manner, disregards safety,
requirements of the Contract. All activities are health and the environment, or behaves in a
controlled by the Engineer. disorderly manner.
The Contractor shall be deemed to have The Contractor shall submit to the Engineer
inspected the Site and to have collected all the number of each class of the Contractor’s
details that may influence the Tender or the Personnel and of each type of Contractor’s
Works. Equipment on the Site; the details shall be
submitted each calendar month in the form
If the Contractor encounters any unforeseen approved by the Engineer.
adverse physical conditions, the Contractor is
obliged to immediately inform the Engineer 1.2.1.2.7 Plant, Materials and Workmanship
(within 28 days). If, due to these conditions
the Contract Price or the Deadline changes, Chapter 7 of the General Conditions consists
the provisions of Chapter 13 of the General of: Manner of Execution, Samples,
Conditions shall be applied. Inspection, Testing, Rejection, Remedial
Work, Ownership of Plant and Materials, and
The Contractor is obliged to submit monthly Royalties.
Progress Reports to the Engineer.
Prior to the utilisation of Materials, the
1.2.1.2.5 Nominated Subcontractors Contractor shall submit for the Engineer’s
approval, samples of materials with the
Chapter 5 of the General Conditions explains relevant information.
the definition of the term “nominated
Subcontractor”, Objection to Nomination, The Contractor is obliged to provide all the
Payments to nominated Subcontractors, and required conditions for the inspection of the
Evidence of Payments. Plant, Material and other parts of the Works.
The time and place of the inspection are to
According to Chapter 13 of the General be agreed with the Engineer.
Conditions, the Engineer is authorised to
nominate a Subcontractor. If, as a result of the inspection, any Plant,
Material or other Workmanship is found to be
The Engineer may check whether the defective or otherwise not in accordance with
Subcontractors have been paid by the the Contract, the Engineer may reject it.
Contractor. Unless the Contractor provides
the Engineer with evidence (in written form) The Engineer is entitled to instruct the
that a Subcontractor is not entitled to direct Contractor to remove any Materials and Plant
payment, the Employer may at his sole which are not in accordance with the
discretion make a direct payment of part or Contract; to remove and re-execute any
the entire amount to the nominated Works which are not in accordance with the
Subcontractor. Contract; and to perform any work required
for the safety of the Works.
1.2.1.2.6 Staff and Labour
If not otherwise stipulated in the
Chapter 6 of the General Conditions deals Specifications, the Contractor shall pay all
with the following issues: Engagement of costs for natural Materials obtained from
Staff and Labour, Rates of Wages and outside the Site and for the disposal of
Conditions of Labour, Persons in the Service Materials after demolition and excavation, to
of Employer, Labour Laws, Working Hours, disposal areas specified in the Contract.
Facilities for Staff and Labour, Health and
Safety, Contractor’s Superintendence, 1.2.1.2.8 Commencement, Delays and
Contractor’s Personnel, Records of Suspension
Contractor’s Personnel and Equipment, and
Disorderly Conduct. The contents of Chapter 8 of the General
Conditions are: Commencement of Works,
PE Roads of Serbia 9
Legislation and Contracts Serbian Road Supervision Manual
Time for Completion, Programme, Extension 11.4 of the General Conditions or to issue the
of Time for Completion, Delays Caused by Taking-Over Certificate if the Employer
Authorities, Rate of Progress, Delay requests him to do so.
Damages, Suspension of Work,
Consequences of Suspension, Payment for 1.2.1.2.10 Employer’s Taking Over
Plant and Materials in the Event of
Suspension, Prolonged Suspension, and Chapter 10 of the General Conditions deals
Resumption of Work. with the following issues: Taking Over of the
Works and Sections, Taking Over of Parts of
The Engineer is to notify the Contractor the Works, Interference with Tests on
regarding the Commencement Date at least Completion, and Surfaces Requiring
seven days in advance. Within 28 days of Reinstatement.
receiving notice of the Commencement Date,
the Contractor shall submit a detailed time The Contractor may apply to the Engineer for
programme to the Engineer. If the a Taking-Over Certificate no earlier than 14
programme is no longer in accordance with days prior to the Completion of Works or
actual progress, the Contractor shall submit a Sections. If, within 28 days the Engineer
revised programme. If the Engineer finds no does not issue the Taking-Over Certificate or
objections within 21 days, it shall be deemed if he does not reject the Contractor’s request
that the Contractor is to perform in to issue it, it shall be deemed that the
th
accordance with this programme. Certificate has been issued on the 28 day of
the receipt of the request.
The Engineer may suspend Works, but if the
Contractor is not responsible for the 1.2.1.2.11 Defects Liability
Suspension, then Sub-Clauses 8.9, 8.10 and
The following is explained in Chapter 11 of
8.11 of the General Conditions shall apply.
the General Conditions: Completion of
Outstanding Work and Remedying Defects,
Upon the approval for resuming Works, all
Cost of Remedying Defects, Extension of
Works, Plant and Materials shall be
Defects Notification Period, Failure to
inspected by the Contractor and the
Remedy Defects, Removal of Defective
Engineer. The Contractor shall remedy all
Work, Further Tests, Right of Access,
defects caused by the suspension.
Contractor to Search, Performance
1.2.1.2.9 Tests and Completion Certificate, Unfulfilled Obligations, and
Clearance of Site.
The sections of Chapter 9 of the General
Conditions are: Contractor’s Obligations, After the issuance of the Taking-Over
Delayed Tests, Retesting, and Failure to Certificate, the Contractor shall complete all
Pass Tests on Completion. Works within the period of time as
determined by the Engineer, while during the
The Contractor should notify the Engineer in Defects Notification Period the Contractor
regard to testing 21 days in advance. shall remedy any defects declared by the
Immediately after the Tests have been Employer.
performed on the Works or Sections, the
Contractor is to submit a certified report with The Employer is entitled to extend the
the Tests results to the Engineer. If the Test Defects notification Period.
results are unsatisfactory, Sub-Clause 7.5 is
applied. Should the Contractor fail to remedy any
defects, the Employer is entitled to (among
If the Engineer unduly delays the Tests, Sub- other things) demand from the Engineer an
Clauses 7.4 and/or 10.3 of the General agreement on determining a reasonable
Conditions are applied. reduction in the Contract Price.
If the Tests are unduly delayed by the At the request of the Engineer and under his
Contractor, the Engineer instructs him in supervision, the Contractor should establish
writing to perform the Tests within a the cause of the defects.
maximum of 21 days. Upon the expiration of
this time period, the Employer will order the The Engineer shall issue the Performance
Tests at the expense of the Contractor. Certificate within a maximum of 28 days upon
the expiration of the Defects Notification
If the Test results are unsatisfactory, the Period. The Performance Certificate shall be
Engineer is entitled to use Sub-Clause 9.3 or
10 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
the only document deemed to constitute the Certificate, Cessation of the Employer’s
acceptance of the Works. Liability, and Currencies of Payment.
PE Roads of Serbia 11
Legislation and Contracts Serbian Road Supervision Manual
Upon the decision of the Employer to Via the insurance policy of the Contractor's
terminate the Contract, the Engineer should workers, both the Employer and the Engineer
establish the amount due to the Contractor are also entitled to compensation.
for the Work, Goods, Contractor's
Documentation or other items in accordance 1.2.1.2.19 Force Majeure
with the Contract. Payment conditions are
explained in Sub-Clause 15.4 of the General Chapter 19 of the General Conditions covers:
Conditions. Definition of Force Majeure, Notice of Force
Majeure, Duty to Minimise Delay,
1.2.1.2.16 Suspension and Termination by Consequences of Force Majeure, Force
Contractor Majeure Affecting Subcontractor, Optional
Termination, Payment and Release, and
The Contractor’s Entitlement to Suspend Release from Performance.
Work, Termination by Contractor, Cessation
of Work and Removal of Contractor’s One Party shall notify the other Party (within
Equipment, and Payment on Termination a maximum of 14 days) in regards to
represent part of Chapter 16 of the General contractual obligations it is not able to or will
Conditions. not be able to fulfil due to Force Majeure. If
the Contractor suffers any damage or loss to
The Contractor is entitled to suspend Works the Works, Goods or Documentation due to
if the Engineer fails to certify the Interim Force Majeure, the Contractor is entitled to
Payments, if the Employer fails to submit the an extension of time and a reimbursement of
Employer’s Financial Arrangements or if the the costs incurred by these circumstances.
Employer fails to comply with Sub-Clause The Engineer makes the decision regarding
14.7 of the General Conditions. The this – see 3.5 of the General Conditions.
Contractor should notify the Employer
regarding this at least 21 days in advance. If the execution of practically any of the Work
in progress is prevented for a continuous
Sub-Clause 16.2 of the General Conditions period of 84 days by reason of Force Majeure
provides a list for reasons of Termination by or for a discontinuous period exceeding 140
Contractor. days after the notice of the occurrence of
Force Majeure, each Party is entitled to
1.2.1.2.17 Risk and Responsibility terminate the Contract by giving notice to the
other Party. The termination shall take effect
Chapter 17 of the General Conditions covers 7 days from the termination notice. In these
Indemnities, Contractor’s Care of the Works, circumstances the Engineer will determine
Employer’s Risks, Consequences of the value of the completed Works and will
Employer’s Risks, Intellectual and Industrial issue the Payment Certificate.
Property Rights, and Limitation of Liability.
1.2.1.2.20 Claims, Disputes and Arbitration
If risks on the Employer’s side cause any
damage to the Works, Goods or Chapter 20 covers the following: Contractor’s
Documentation of the Contractor, the Claims, Appointment of the Dispute
Contractor shall immediately inform the Adjudication Board, Failure to Agree on the
Engineer of any such occurrence and shall Composition of the Dispute Adjudication
remedy the damage and the losses Board, Obtaining Dispute Adjudication
12 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
PE Roads of Serbia 13
Legislation and Contracts Serbian Road Supervision Manual
1.1.2.11 “Joint Venture” is: a consortium Sub-Clause 14.3 shall be deleted, and the
of companies which has agreed to perform following shall be added:
the Works under the Contract and on the (a) The operative law is the legislation of the
basis of mutual agreement. Republic of Serbia.
(b) The ruling language for interpretation for
1.1.2.1 “Authorized person of the Employer, all contractors shall be the Serbian
of the Bidder i.e. the Subcontractor” is a language.
person who, according to the law regulating
infractions, is responsible for an infraction 1.10 Employer’s use of the Contractor’s
caused by his actions or by an error made by documents
the Supervising Engineer in charge. The last paragraph has been added and it
reads as follows:
1.1.3 Dates, tests, deadlines and For all eventual variations in the design that
completion occur during construction, the Contractor is
obliged to suggest measures to be
1.1.3.2 “Commencement Date” is undertaken, as well as to make a financial
determined by mutual agreement and is a assessment of the measures in accordance
signed document between the Contractor, with the Contract.
the Engineer and the Employer, which
defines the date of the commencement of New Sub-Clause:
Works. The Time for Completion is defined
by Sub-Clause 8.2 and it commences with 1.15 Confidential information
the date at which the Contract came into The Contractor shall deem the entire
effect. contents of the Contract as private and
confidential information and will treat it as
1.1.4 Money and payment such and with such a purpose, and will not
disclose it partly or in its entirety in any
1.1.4.4 “Discharge” (Clause 14.12) is a commercial or technical magazine or in other
“Record of the final account of executed place without the prior written consent of the
works ”. Employer. In the case of a dispute regarding
the necessity of publication or disclosure of
1.1.4.7 “Interim Payment Certificate” is the information for the purposes of the
created on the data from approved “Book of Contract, this decision shall be made by the
quantities”, a document relating to the Employer.
determination of the quantity of the Works
carried out. 3 THE ENGINEER
1.1.4.12 “Unit Price” is the price per unit of 3.1 Obligations and authority of the
quantity indicated in the bill of quantities of Engineer
the bid.
At the end of the Sub-Clause the following
1.1.6 Other definitions shall be added:
The Engineer shall obtain special approval
1.1.6.2 “Country” refers to the Republic of from the Employer prior to:
Serbia. (a) Approving the hand-over of any Works
pursuant to Clause 4.4 of the General
1.1.6.5 “Laws” means the entire national (or Conditions and the Particular Conditions
state) legislation, rulebooks, regulations, of the Contract;
decrees, statutory and other laws, as well as (b) Approving additional expenses defined by
all regulations and the delegated legislation Clause 13;
of any established authoritative body of the (c) Determining the time extension for
Republic of Serbia. completion of works pursuant to Clause
8.4;
1.1.6.10 “Construction diary and Inspection (d) Approving variations (pursuant to Clause
book” are to be kept for the complete period 13);
of the execution of Works in accordance with (e) Determining the price pursuant to Clause
the Regulations on the contents and manner 12.
of keeping the construction diary and If in the opinion of the Engineer an
inspection book. emergency arises that might bring the lives of
people, the Works or property into danger,
1.4 The law and the language the Engineer is entitled to instruct the
14 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
Contractor to perform all the work or activities The Performance Security shall be issued
which in his opinion may be necessary in either:
order to eliminate or reduce the risk; at the (a) by a bank in the country of the Employer,
same time, the Engineer should not break the or
above mentioned obligation of seeking (b) by a foreign bank acceptable to the
permission. At the same time, the Contractor Employer.
is not relieved of any duty or responsibility Notwithstanding the limitations of the
under the Contract. The Contractor shall act previous paragraph, each time the Engineer
in accordance with all such instructions given determines an increase of the Contractual
by the Engineer, despite the fact that the Price due to variations in costs and/or due to
Employer has not given his approval. The legislation, or as a result of discrepancies
Engineer shall determine the extra amount exceeding 10% of the share of the agreed
for the contractual price regarding his value of the Works, the Contractor shall
instructions and pursuant to Clause 12, and immediately increase by a corresponding
shall inform the Contractor accordingly, and percentage the value of the Performance
will deliver a copy to the Employer. Security.
Until then the Employer is entitled to retain
4 THE CONTRACTOR security to the amount of 10% of the increase
of the agreed price of the Works.
4.1 Contractor’s general obligations
At the end of Sub-Clause 4.1 the following 4.3 Contractor’s representative
shall be added: The last sentence of Sub-Clause 4.3 shall be
The Contractor will immediately notify the deleted, and the following will be added:
Employer and the Engineer of any error, If the Contractor’s Representative or his
omission, deficiency or other defect in the managerial staff do not speak fluent Serbian,
design, plans, list of works and geodetic data the Contractor shall provide an interpreter
(markings of the relative height, control points who will be at their disposal during work
for the road routes and for objects) as well as hours.
of the other information relating to the Works
which the Contractor would come across 4.4 Subcontractors
during the review of the Contract or during The first paragraph of Sub-Clause 4.4 has
the execution of the Works. Should the been amended and now reads as follows:
Contractor fail to do this, thus causing delays The Contractor is allowed to assign to the
or other consequential deviations from the Subcontractors (for subcontracting) up to a
Contract, then the Contractor shall have no maximum of __% of the total value of the
right to submit a request for cost redemption Works.
and shall be deemed responsible for such
consequences on the occasion of the Lines (b), (c) and (d) of the second paragraph
Employer suffering any damages. shall be deleted.
The Contractor shall keep the Book of Below line (a) a new line (b) has been added
quantities and provide the Inspection book. and it reads as follows:
The Contractor needs to have the written
4.2 Performance Security consent of the Employer for all
The first and the second motions of Sub- subcontractors not listed in the Bid and prior
Clause 4.2 have been completely amended to their engagement on certain Works.
and now read as follows: Should the Contractor establish after the
The Contractor shall provide the Employer conclusion of the Contract that there is the
with Performance Security (fulfilment of the need for the engagement of a subcontractor
Contract) within 10 (ten) working days from for the purpose of the execution of Works,
the day of the conclusion of the Contract.” the Contractor shall send this suggestion to
The Performance Security shall be given in the Employer. The Employer shall, within 14
the form of a bank guarantee. A copy of the days from the receipt of the proposal
guarantee shall be sent to the Engineer. regarding the new subcontractor (and on the
When the joint bid of a group of contractors occasion of the submission of the supporting
has been selected as the most favourable documents regarding the fulfilment of
one, the group of contractors is obliged to conditions), check both the suitability and
reach an agreement regarding the capacity of the subcontractor and decide on
submission of a joint bid for the performance whether he will approve the engagement of
of works, and to select one of the partners the newly announced subcontractor. The
from the group of contractors as the Employer cannot reasonably reject the
employer for the Performance Security. proposal of the Contractor regarding the
PE Roads of Serbia 15
Legislation and Contracts Serbian Road Supervision Manual
engagement of a new subcontractor. The At the end of Sub-Clause 6.8 the following
newly declared subcontractor must fulfil the shall be added:
same conditions valid for the subcontractor A relevant number of the supervising staff of
named by the Contractor in the bid. All the Contractor must have an active
documentation for the new subcontractor knowledge of the Serbian language or a
shall be enclosed with the application, as sufficient number of interpreters must be at
stipulated by provisions_______________ of their disposal on the site during work hours
the said public procurement. (as defined in Sub-Clause 1.4).
In the application the applicant must indicate
the reason that has created the need for the 6.10 Records of the Contractor’s
engagement of the subcontractor at the Personnel and Equipment
Works; the reasons must be fully At the end of Sub-Clause 6.10 the following
corroborated. shall be added:
The main reasons are: The contractor will provide detailed
- Circumstances arising after the signing of information to the Employer and to the
the Contract related to the Works and Engineer as to the type of planned Works,
which the Contractor was not able to work hours, the anticipated number of the
foresee or was not obliged to foresee in Contractor’s personnel of each category, as
the phase of the composition and well as each type of equipment on the site.
submission of his Bid; This detailed information will be delivered at
- The need for additional Works, an least twice a week by email to the Employer
increased number of Works or unforeseen and the Engineer, until the Contractor has
Works which the Contractor is not able to completed all Works known to be unfinished
execute alone; within the Time for Completion indicated in
- Climatic, organisational or technical the Taking-Over Certificate.
circumstances resulting in the necessity of In the situation where for justifiable reasons
engaging a subcontractor in order to have the plan does not match the actual situation,
the contractual Works executed in the the Contractor is obliged to notify the same
scope, with the quality and within the time recipients in regards to this as soon as the
period stipulated by the Contract. changes take place. The Contractor bears
The Engineer is obliged to ascertain as soon the moral and material responsibility for the
as possible whether the conditions indicated accuracy of the information. The Employer is
above have been fulfilled, and to send the entitled to claim for damages caused by
application along with his findings to the incorrect information and the loss of
relevant department of the Employer. The reputation.
task of the department is to study the
application with the proposal again, and in 6.12 Foreign Personnel – additional Sub-
the situation where the conditions have been Clause:
fulfilled – to issue an approval regarding the The Contractor may engage any personnel
Contractor’s proposal. from abroad required for the execution of the
The eventual approval regarding the Works. The Contractor shall ensure that the
Contractor’s proposal does not relieve the personnel are provided with the required
Contractor from responsibility taken over residency visas and work permits. The
under the Contract; the Contractor is still Contractor is responsible for the return of
solely and entirely responsible for the quality these personnel to the place where they were
and timely execution of the contracted recruited or to their domicile. In the event of
Works.” death in the Country of any of the personnel
or members of their families, the Contractor
4.9 Quality assurance shall be responsible for making the
At the beginning of Sub-Clause 4.9 the necessary arrangements for their return or
following shall be added: burial.
The Contractor will provide quality in
accordance with the operating laws and 7 PLANT, MATERIAL AND
technical regulations as well as in compliance WORKMANSHIP
with the General and Particular technical
conditions. 7.1 Manner of Execution
At the end of Sub-Clause 7.1 the following
6 STAFF AND LABOUR shall be added:
Prior to Commencement of the Works the
6.8 Contractor’s Superintendence Contractor shall (at his own expense) provide
a laboratory on the Site with the appropriate
16 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
equipment and personnel for the purpose of 8.4 Extension of Time for Completion
performing tests onsite which are necessary Item (a) of Sub-Clause 8.4 has been
for the execution of the Works specified in amended and reads:
the Contract. Variations (unless an adjustment to the Time
of Completion has been agreed upon under
7.4 Testing Sub-Clause 13.3 (Variation Procedure)) or
The last sentence of Sub-Clause 7.4 is other substantial changes in the quantity of
substituted by the sentence: an item of work in the situation where the
In the situation where the Engineer’s value of the added and/or additional Works
representative was not present during the exceeds 15% of the contracted value of the
testing, the Engineer may deem the results Works.
and records of the testing acceptable, or – in
the case of any doubt – the Engineer may 11 DEFECTS LIABILITY
request retesting.
11.3 Extension of Defects Notification
8 COMMENCEMENT, DELAYS AND Period
SUSPENSION At the end of Sub-Clause 11.3 the following
shall be added:
8.1 Commencement of Works According to the laws of the Republic of
The first sentence of Sub-Clause 8.1 is Serbia the Contractor is responsible for the
substituted by the sentence: defects and errors defined in Sub-Clauses
The Contractor will commence Works 11.2 (a), (b) and (c) that could not have been
dependent upon how quickly he is notified by noticed or which he deems to have been
the Engineer that he may commence Works, unnoticeable before the expiration of the
or he commences Works after the signing of Defects Notification Period pursuant to
the Access to and Possession of the Site. Clause 11.3. The general deadline for the
The Access to and Possession of the Site will limitation of such a liability is the time period
be performed during the time period indicated defined in the Appendix to the Bid and it may
in the Appendix to the Bid, according to the not exceed the period of ____ years for work
validity date of the Contract. on roads, and ____ years for work on bridges
and other structures.
8.3 Programme When the joint bid of a group of contractors
At the end of item (d) (ii) of the Sub-Clause has been selected as the most favourable
8.3, the following shall be added: one, the group of contractors is obliged to
The time programme will contain a reach an agreement in the form of a legally-
harmonised masterplan of progress with the binding legal act regarding the joint
indication of a clear time frame for the performance of Works, and to select one of
individual phases of the Works. Along with the partners from the group of contractors as
the time programme, the Contractor shall the Employer for the remedy of defects within
give the Engineer the Plan of equipment, the warranty period.
machinery, building materials and workforce The warranty period commences either from
for the specified time period. If the Works are the day of starting of the structure for use or
assigned to different Contractors, they shall from the day of the issuance of the Taking-
deliver to the Engineer a mutually Over Certificate, dependent upon which date
harmonised masterplan of progress. Should is earlier. The expiry period of the warranty
the Contractors fail to unify the progress plan shall be 30 days longer than the warranty
among themselves in a timely manner, the period determined by the Contract.
harmonisation shall be conducted by the When removing defects within the warranty
Engineer at the expense of the Contractors. period, the Contractor shall execute the
In this case the Contractors are not entitled to works required for the remedying of the
variations in the contracted times for defects________hours per day. All defects
completion and the contract price. that endanger the safety and health of people
Within ten days of the validity of the Contract, must be removed within______hours.
the Contractor will create a Technical
analysis of the Works that shall be verified by 11.9 Performance Certificate
the Engineer. The analysis will be created in At the end of Sub-Clause 11.9 the following
accordance with the guidelines given in shall be added:
Chapter____ –Technical Conditions. Time As a precondition for the issuance of the
programme will be created with a computer Performance Certificate, the Contractor must
programme_____________ and shall include deliver to the Engineer _____ copies of the
the number of daily work hours. Design of the constructed facility
PE Roads of Serbia 17
Legislation and Contracts Serbian Road Supervision Manual
18 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
The Employer shall retain ____ percent of The Contractor is not entitled to suspend
the Works price for which the payment has Works in the case of a part of the payment
been approved until the Contractor submits being disputed by both Parties for which
to the Employer an amended Performance reason the Engineer has not approved the
Security as stipulated by Clause 4.2 of the part of the payment i.e. the Employer has not
Particular Conditions. made the payment.
PE Roads of Serbia 19
Legislation and Contracts Serbian Road Supervision Manual
ADDITIONAL CLAUSES
20 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
CONTRACT AGREEMENT
1. In this Agreement words and expressions shall have the same meanings as are respectively
assigned to them in the Conditions of Contract hereinafter referred to.
2. The following documents shall be deemed to form and be read and construed as part of this
Agreement:
a. The Letter of Acceptance dated___________
b. The Letter of Tender dated______________
c. The Addenda nos___________
d. The Conditions of Contract
e. The Specification
f. The Drawings, and
g. The completed Schedules
4. The Employer hereby covenants to pay the Contractor, in consideration of the execution and
completion of the Works and the remedying of defects therein, the Contract Price at the times
and in the manner prescribed by the Contract.
In witness whereof the parties hereto have caused this Agreement to be executed the day and
For and on behalf of the Employer in the presence For and on behalf of the Contractor in the presence
of of
PE Roads of Serbia 21
Legislation and Contracts Serbian Road Supervision Manual
22 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
and his employees, the financial 1.2.3.1 Contract sample of the PE Roads
requirements of the contractor and his own of Serbia
resources, selection criteria, etc.
A Contract sample between the Employer
If the Employer does not utilise the FIDIC and the Contractor according to PE Roads of
publication for the General Conditions, then Serbia is given below.
the Employer composes his own conditions
defining his requirements. The requirements
are described in Volume 2 “Construction
Supervision” of the SRSM book (Serbian
road supervision manual) and they relate to
all the construction stages up to the final
statement. With well prepared tender
documentation, problems that frequently
arise during construction may be avoided.
Such problems include: An increase in the
contract price, delays in completion, poor
quality construction, non-compliance with the
relevant legislation, an unnecessary impact
on the environment, etc. Therefore, the
objective of the tender documentation, along
with the contract documents, is to provide the
Employer with a permanent and cost-
effective structure.
PE Roads of Serbia 23
CONTRACT
Entered into by and between the Contractual Parties
and
Article 1
The Contracting Authority assigns and the Contractor accepts and undertakes to execute the works
on......
based on the accepted bid of Contractor No. ..... from ..... year, all in accordance with the Law on
Planning and Construction, the Law on Public Roads, technical documentation and tender
documentation which constitute a part of this Contract.
Article 2
The Parties state in mutual consent that the total value of the works from Article 1 of this Contract
is:
Written in words……………………………………………………………………....
Article 3
Article 4
The offered unit prices from the estimated bill of quantities shall not be amended due to the
increase (excess) or decrease (deficit) quantity of works defined in the estimated bill of quantities.
The unit price for any unforeseen and additional works shall be determined based on the analyses
and corrections of the prices’ analysis provided by the Contractor pursuant to the General
Conditions and Appendices enclosed with the bid.
Article 5
The amount of the advance payment is ......% from the total agreed contract value of the works.
24 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts
Article 6
For the security of the Employer and for the purposes of removal of the defects in the works, the
Contractor shall retain the amount of .....% from the total value of the works (from each monthly
instalment) until the completion of the works.
Upon the completion of the works and upon the positive technical acceptance of the works, a half
of the total retained amount (...%) shall be returned to the Contractor, while the other half shall be
returned to him at the end of the warranty period.
COMPLETION PERIOD
Article 7
Article 8
Should the Contractor suggest an amendment or a supplement to the approved design, and should
such a proposal be adopted by the Employer thus attaining a more rational solution and cost-
effectiveness regarding the construction process, the Contractor is entitled to a premium of the
amount of ..... from the sum thus saved.
Article 9
The accepted bid of the Contractor with all Appendices to the bid;
Particular Conditions of the Contract;
General Conditions of the Contract;
Technical documentation;
Bank guarantee for the Performance Security;
Agreement of joint bidding (if two or more partners submitted a joint bid).
Article 10
The Employer and the Contractor agree to resolve all disputes arising from this Contract primarily
in the way defined in the tender documentation and by mutual agreement.
Article 11
This Contract comes into effect on the date it is signed by the Contractor and by the Employer.
The Contract is drawn in .... identical copies of which the Employer keeps .... copies, and
........copies belong to the Contractor.
Contractor Employer
PE Roads of Serbia 25