You are on page 1of 29

REPUBLIC OF SERBIA

TRANSPORT REHABILITATION PROJECT

SERBIAN ROAD SUPERVISION


MANUAL

1. LEGISLATION AND CONTRACTS

BELGRADE, 2012
Publisher: Public Enterprise Roads of Serbia, Bulevar kralja Aleksandra 282,
Belgrade

Edition:

No. Date Description of amendments


1 30.04.2012 First edition
Serbian Road Supervision Manual Legislation and Contracts

CONTENTS

1.1 INTRODUCTION ............................................................................................................1


1.1.1 TERMINOLOGY .............................................................................................................1
1.1.2 REFERENCE DOCUMENTS .........................................................................................3
1.1.2.1 Laws................................................................................................................................3
1.1.2.2 Rulebooks .......................................................................................................................3
1.1.2.3 Regulations .....................................................................................................................4
1.1.2.4 Other ...............................................................................................................................5
1.2 CONTRACTS .................................................................................................................5
1.2.1 CONDITIONS OF CONTRACT ACCORDING TO FIDIC...............................................5
1.2.1.1 Contract types.................................................................................................................5
1.2.1.2 General Conditions according to the Red Book .............................................................7
1.2.1.3 Particular Conditions according to FIDIC......................................................................13
1.2.1.4 Contract sample according to FIDIC.............................................................................20
1.2.2 CONTRACT CONDITIONS ACCORDING TO MFI......................................................22
1.2.2.1 Institutions of the MDB and MFI ...................................................................................22
1.2.2.2 The Harmonised MDB version of the Red Book – the Pink Book ................................22
1.2.3 OTHER CONDITIONS OF THE CONTRACT ..............................................................22
1.2.3.1 Contract sample of the PE Roads of Serbia .................................................................23

PE Roads of Serbia i
Serbian Road Supervision Manual Legislation and Contracts

requirements regarding the provision of


adequate quality, guarantees, insurance,
1.1 INTRODUCTION required documentation, methods of
execution of the work, protection of the
environment and people, health and safety,
The area of road infrastructure is principally the calculation of and compensation for
regulated by two laws – the Law of Public completed work, preparation of the
Roads and the Law of Planning and documentation regarding the taking-over,
Construction, and it lies within the assigning maintenance and management,
competence of both the Ministry for registration at the Public Registry, etc.
Infrastructure and Energy, and the Ministry of
the Environment, Mining and Spatial
Planning. All operational laws are listed in 1.1.1 TERMINOLOGY
item 1.1.2 Reference Documents.

Investments into road infrastructure are Accepted Contract Amount (Prihvaćena


implemented based on a contract that has ugovorna cena) is the amount accepted in
been concluded between the Employer and the Letter of Acceptance.
the Contractor. The construction contract
defines at the very least the following: the Commencement Date (Datum početka) is
Employer and the Contractor, as well as their the date of the commencement of works.
authorised representatives, the type of work,
contract value, method of calculation of the Conditions (Uslovi) are the General
completed works (turn-key principle/fixed Conditions and Particular Conditions of the
price or price by quantity unit) and deadlines Contract.
for the completion of the work. Apart from
this, a contract mostly contains certain Contract (Ugovorna dokumentacija)
appendices which depend on the applied comprises the text of the Contract Agreement
contract type, and on the type of work. itself, the Letter of Acceptance, the Tender,
the Conditions, the Specifications, the
The Professional Supervisor i.e. the Drawings, the Schedules and other
Engineer, must be fully acquainted with the documents (if any) specified in the text of the
contract in order to be able to perform his Contract Agreement or in the Letter of
activities properly and professionally. In Acceptance.
addition to professional supervision he must
also be acquainted with the terms and Contract Agreement (Ugovor) is a
conditions defined during the contracting of document concluded between the Employer
works i.e. he must be acquainted with the and the Contractor in the form enclosed with
tender documentation. The Professional Particular Conditions.
Supervisor must also be acquainted with the
authority and obligations given by the Contract Price (Ugovorna cena) represents
Employer. the amount of the Contract (the sum of all
bills of quantities’ positions and the estimated
Technical control of the quantity and the quantity of those positions) with all
quality of the work alone is insufficient. The adjustements in accordance with the
Professional Supervisor should work to the Contract.
benefit of the Employer by complying with
duties, obligations and responsibilities for the Contractor’s Documents (Dokumentacija
sake of all contracting parties. The Izvođača) are calculations, computer
professional supervisor should keep the programmes and other software, drawings,
Employer informed by means of reporting. manuals, scale models and other documents
Apart from this, he should feel responsible for of a technical nature supplied by the
the entire project. Contractor under the Contract.

Each construction project is performed based Defects Notification Period (Rok za


on the construction contract. The Public prijavljivanje nedostataka) is the period
Procurement Law stipulates the method of given for notifying defects in the Works or in
the assignment of construction works when a Section; this period lasts for 12 months
the Employer is an organisation financed from the issuance of the Taking-Over
from the budget. By setting out the tender Certificate, if not otherwise stipulated by the
requirements for the construction of a certain Contract.
structure, the Employer sets special

PE Roads of Serbia 1
Legislation and Contracts Serbian Road Supervision Manual

Dispute Adjudication Board - DAB MDB (Multilateralna razvojna banka) is a


(Komisija za rešavanje sporova - KRS) multilateral bank for development.
consists of one or three persons nominated
in the Contract, if the Contract stipulates an MFI (Multirateralne finansijske institucije)
arbitration clause. are multilateral financial institutions.

Drawings (Crteži) are drawings of the Particular Conditions (Posebni uslovi


Works, as well as any additional and Ugovora) represent an addition and
modified drawings issued by (or on behalf of) amendment to the General conditions of the
the Employer. Contract.
1
Employer (Investitor) is the person Party (Ugovorna strana) is the Employer or
designated in the Contract as the Employer the Contractor.
along with his legal successors (according to
the Law on Public Procurements). Performance Certificate (Potvrda o
valjanom izvršenju) is the document signed
2
Engineer (Inženjer) is the person appointed by the Engineer in accordance with the
by the Employer to the role of supervision as Employer certifying that the Contractor has
per the requirements of the Contract. fulfilled all the obligations of the Contract.

FIDIC is an abbreviation for the International Performance Security (Garancija za


Federation of Consulting Engineers valjano izvršenje posla) is a guarantee for
(Fédération Internationales des Ingénieurs- proper performance.
Conseils).
Plant (Oprema, Postrojenje) are apparatus,
Final Payment Certificate (Konačna machinery and vehicles intended to form or
situacija) represents the entire amount that forming part of the Permanent Works.
the contractor is entitled to according to the
Contract. Schedules (Tabele) are the documents
completed by the Contractor which represent
General Conditions (Opšti uslovi a part of the Tender (bill of quantities, data,
Ugovora) are the contracting conditions lists, price-lists).
according to FIDIC publications or other
general conditions defined by the Employer. Section (Sekcija) represents a part of the
Works specified in the Contract as a Section.
Goods (Dobra) are the Equipment,
Materials, Plant and Temporary Works of the Site (Gradilište) is the location where the
Contractor. Permanent Works take place; the Site
includes the working area and areas for the
Interim Payment Certificate (Privremena storage of Plants and Materials.
situacija) means a payment certificate
issued by the Contractor, other than the Final Specification (Specifikacija ili tehnički
Payment Certificate. uslovi) is a document within the Contract
which specifies the Works.
Letter of Acceptance (Potvrda o
prihvatanju ponude) is the document of the Subcontractor (Podizvođač) is the person
formal acceptance of the Tender, signed by designated in the Contract as a subcontractor
the Employer. of a part of the Works.

Materials (Materijali) are things of all kinds Supervising Engineer (Nadzorni organ) is
(other than Plant Plant) intended to be or the person who makes supervision defined in
which already represent a part of the the Law on Planning and Construction.
Permanent Works, including the supply-only
materials to be supplied by the Contractor Supervision/Supervisor (Stručni nadzor) is
under the Contract. defined in the Law on Planning and
Construction.

1
Taking-Over Certificate (Potrvrda o
The terms designating persons or parties comprise prijemu) is a certificate for the taking-over of
companies and other legal persons.
2
In the Red Book, the term „Engineer” is translated in the Works, issued by the Engineer with
Serbian as “Nadzorni organ”, which is not in accordance approval of the Employer.
with regulations in the RS.

2 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

Temporary Works (Privremeni radovi) are - Law on planning and construction, Official
all temporary works required for the Gazette of the RS, No. 72/09, 81/09,
execution and completion of the Permanent 64/10, 24/11
Works, and for the remedying of any defects. - Law on public roads, Official Gazette of
the RS, No. 105/05, 123/07
Tender (Ponuda) represents the signed offer - Law on railway, Official Gazette of the RS,
by the Contractor to the Employer and all the No. 18/05; the new Law on Railway is in
additional documents the Contractor the procedure.
submitted with it. - Law on Ratification of the Aarhus
convention on access to information,
Time for Completion (Rok za završetak) is public participation in decision-making
the time for the completion of Works or of the and the right to legal protection in
Section from the Commencement Date. environmental matters, Official Gazette of
the RS, No. 38/09
Unforeseeable (Nepredvidivo) is a situation - Law on Ratification of the Espoo
which an experienced contractor could not convention on environmental impact
have foreseen prior to the submission of the assessment in a transboundary Context,
Tender. Official Gazette, No. RS 102/07
- Law on state survey and real estate
Variation (Izmena) is any ordered or cadastre, Official Gazette of the RS, No.
approved change to the Works. 72/09 and 18/10
- Law on strategic environmental impact
Works (Radovi) comprise the Permanent assessment, Official Gazette of the RS,
Works and/or Temporary Works according to No. 135/04 and 88/10
the Contract. - Law on waste management, Official
Gazette of the RS, No. 36/09 and 88/10
1.1.2 REFERENCE DOCUMENTS - Law on water, Official Gazette of the RS,
No. 30/10
- Mining law, Official Gazette of the RS, No.
1.1.2.1 Laws 34/06
- Occupational safety and health law,
- Fire safety law, Official Gazette of the RS, Official Gazette of the RS, No. 101/05
No. 111/09 - Public procurement act, Official Gazette of
- Law of contract and torts (Law on the RS, No. 116/08
obligations), Official Gazette of SFRY, No. - Road traffic safety law, Official Gazette of
29/78, 39/85, 45/89 and 57/89 and Official the RS, No. 41/09, 53/10, 101/11.
Gazette of SRY, No. 31/93 and Official
Gazette of the Serbia and Montenegro,
No. 1/03 – The Constitutional Charter 1.1.2.2 Rulebooks
- Law on agricultural land, Official Gazette
of the RS, No. 62/06, 65/08 and 41/09. - Rulebook on content and method for
The new law is in the procedure. conducting expert supervision, Official
- Law on air protection, Official Gazette of Gazette of the RS, No. 7/10
the RS, No. 36/09 - Rulebook on content and method for
- Law on arbitration, Official Gazette of the conducting technical control of the
RS, No. 46/06 detailed design, Official Gazette of the
- Law on environmental impact RS, No. 93/11
assessment, Official Gazette of the RS, - Rulebook on content and method for
No. 135/04 and 36/09 conducting the technical examination of a
- Law on environmental protection, Official structure and issuing usage permits,
Gazette of the RS, No. 135/04, 36/09, Official Gazette of the RS, No. 93/11
72/09 - Rulebook on content and method for
- Law on free access to information of issuing building permits, Official Gazette
public importance, Official Gazette of the of the RS, No. 93/11
RS, No. 120/04, 54/07, 104/09, 36/10 - Rulebook on content and method for
- Law on integrated environmental pollution keeping inspection books and
prevention and control , Official Gazette of construction diaries, Official Gazette of
the RS, No. 135/04 the RS, No. 105/03
- Law on noise protection, Official Gazette - Rulebook on content and method for
of the RS, No. 36/09 and 88/10 observing soil and the structure during
use, Official Gazette of the RS, No. 93/11

PE Roads of Serbia 3
Legislation and Contracts Serbian Road Supervision Manual

- Rulebook on obligatory elements of the - Rulebook on the license for the work of
bidding documentation in public geodetic organization and geodetic
procurement procedures, Official Gazette licenses, Official Gazette of the RS, No.
of the RS, No. 98/04 33/10
- Rulebook on occupational safety for - Rulebook on the limits, methods for
conducting construction works, Official measuring emissions, criteria for
Gazette of the RS, No. 53/97 establishing measurement locations and
- Rulebook on preventative measures for recording of data, Official Gazette of the
occupational safety and health during RS No. 54/92 and 30/99
exposure to vibration, Official Gazette of - Rulebook on the method and conditions
the RS, No. 93/11 for acquiring authorization to plan and
- Rulebook on records for public roads and perform geodetic works in engineering-
accompanying structures, as well as technical fields, Official Gazette of the RS,
technical data for those roads, Official No. 59/02
Gazette of SFRY, No. 52/83 and 60/83 - - Rulebook on the method and minimum
corr. and Official Gazette of Serbia and number of quality tests for waste water,
Montenegro No. 1/03 - Constitutional Official Gazette of the RS, No. 47/83 and
charter 13/84
- Rulebook on surveying and cadastre of - Rulebook on the method and process for
lines, Official Gazette of the RS, No. submitting an application for a change to
63/10 a property and declaration of a geodetic
- Rulebook on technical normative and organization, Official Gazette of the RS,
conditions for planning and construction of No. 56/02
tunnels on roads, Official Gazette of - Rulebook on the method for determining
SFRY, No. 656-5 and maintaining a zone of sanitary
- Rulebook on the appearance, content and protection for water supply sources,
positioning of the construction information Official Gazette of the RS, No. 92/08
board, Official Gazette of the RS, No. 4/10 - Rulebook on the methods for
- Rulebook on the categories, testing and measurement of noise, content and scope
classification of waste, Official Gazette of of reporting on noise measurement,
the RS, No. 56/10 Official Gazette of the RS, No. 72/10
- Rulebook on the conditions and method - Rulebook on the minimum warranty
for collecting, transporting, storing and periods for individual types of structures
treatment of waste which is used as or works, Official Gazette of the RS, No.
secondary raw materials or for obtaining 93/11
energy, Official Gazette of the RS, No. - Rulebook on the technical normative
98/10 when handling explosive compounds and
- Rulebook on the conditions which must be placement of explosive in mining, Official
fulfilled by a professional organization for Gazette of SFRY, No. 26/88 and 63/88
measuring noise, Official Gazette of the - Rulebook on the technical normative,
RS, No. 72/10 methodology for drafting technical
- Rulebook on the content of the documentation and control of technical
elaboration of construction site documentation for the execution of
organization, Official Gazette of the RS, geodetic works in engineering-technical
No. 31/92 fields, Official Gazette of the RS, No.
- Rulebook on the content, method, 59/02
conditions of supervision and control of - Rulebook on traffic safety conditions
the execution of geodetic works in which transportation infrastructure and
engineering-technical fields, Official other elements of public roads must fulfil,
Gazette of the RS, No. 59/02 Official Gazette of the RS, No. 50/11
- Rulebook on the creation and keeping of - Rulebook on traffic signalisation, Official
the cadastre of properties, Official Gazette Gazette of the RS, No. 26/10.
of the RS, No. 46/99
- Rulebook on the emission limits, method
and deadlines for measurement and 1.1.2.3 Regulations
recording of data, Official Gazette of the
RS No. 30/97 and 35/97 - Regulation (EU) No 305/2011 of the
European Parliament and of the Council
- Rulebook on the execution of expert
of 9 March 2011 laying down harmonised
supervision, examination and acceptance
conditions for the marketing of
of works, Official Gazette of the RS, No.
construction products and repealing
43/10

4 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

Council Directive 89/106/EEC, Official The Employer and the Contractor may add
Journal of the European Union, 88/11 an Annex to the Contract in cases of:
- Regulation on occupational safety and - Change in the position of the works;
health on temporary and mobile - Change with the entire contract price (in
construction sites, Official Gazette of the accordance with the Public procurement
RS, No. 14/09 act);
- Regulation on depositing waste in dump - Change of deadline for the completion of
sites, Official Gazette of the RS, No. works;
92/10 - Change in the representatives for the
- Regulation on the establishment of house Employer and/or the Contractor;
numbers, marking of buildings with - Other changes.
numbers and marking of names of
settlements, streets and squares, Official In the case of an Annex being added to the
Gazette of the RS, No. 110/03, 137/04 Contract, the Supervisor inspects whether
and 58/06. the Contractor has delivered all the required
documentation required for the Annex and
also checks if all the data is correct.
1.1.2.4 Other

- Special practices in construction, Official 1.2.1 CONDITIONS OF CONTRACT


Gazette of SFRY, No. 18/77. ACCORDING TO FIDIC

1.2 CONTRACTS 1.2.1.1 Contract types

FIDIC is the French abbreviation, for the


The Construction Works Contract is a International Federation of Consulting
temporary service contract where the Engineers. The international federation
Contractor undertakes to build a certain consists of national member associations.
structure according to the given design and The activities of the federation of engineers
within the agreed timeframe and on the include the improvement of the professional
defined plot of land or to perform (on that plot interests of its members, as well as the
of land or on the existing structure) any other exchange of information. Members develop
construction works, and the Employer professional and ethical standards of
undertakes to pay the Contractor a defined consulting engineering in Europe and in
price for those works. The Construction developing countries.
Contract is concluded in written form.
FIDIC publications contain data for consulting
The Serbian language uses the term engineers, employers and contractors in the
“Ugovor“ (Contract Agreement) and form of standard forms for prequalification,
“Ugovorna dokumentacija” (Contract). Most contractual documents and agreements. It is
of the Employers’ requirements are stated in possible to incorporate these forms into
the tender documentation. Therefore, a tender and contractual documentation in
Contract consists of the General and the accordance with the conditions published on
Particular Conditions along with other the official website of FIDIC whose
documentation which makes up part of the secretariat is located in Switzerland.
tender documentation or a part of the Bid of www.fidic.org
the Contractor. The contents of all the
documents which a Contract consists of must ACES (The Association of Consulting
be precisely specified. Engineers of Serbia) is a professional and
non-profit association founded in April 2009
Article 21 of the Law of contract and torts with the objective of promoting the role and
states that usage is only applied if contractual the importance of FIDIC standards in Serbia.
parties agree upon its application or if The activities of the Association include
circumstances imply that they desire its providing support to the implementation of
application. FIDIC standards through the stimulation and
monitoring of the adjustment of the relevant
If the conditions dealing with the same issues regulations of the Republic of Serbia with EU
as the usage represent a part of the tender standards and regulations and then informing
documentation, then these conditions are members about this; the organisation of
applied. FIDIC training, the sale of FIDIC publications,
the organisation of educational and

PE Roads of Serbia 5
Legislation and Contracts Serbian Road Supervision Manual

informative events – seminars, workshops, and construction, and bears all the risk
panel discussions, professional lectures; except from force majeure;
introduction of new trends in the construction - There is no Engineer;
sector; promotion of the role of a consultant - The price of the works is a lump sum.
engineer in investment ventures; informing - Conditions of contract for electrical and
members of relevant developments in the mechanical works
construction sector and other areas of Yellow Book (old)
significance for providing quality engineering - “Turnkey” system conditions of
consulting services; exchange of experiences contract;
between members and related foreign - Designing and performance of
companies; establishment of new business electrical and mechanical works, as
opportunities in the country and abroad; well as the supply and installation of
improvement of the business climate in the electrical and mechanical equipment at
Republic of Serbia, and improvement of the the location;
profession in general. The establishment of - Technical documentation is created by
the Association was significantly supported the Contractor;
by the US Agency for International - The total price of the works is a lump
Development – USAID. The Association also sum.
cooperates with the World Bank/International - Conditions of Contract for Facilities and
Finance Corporation – IFC. Design - Build
The official web page of ACES is Yellow Book (new)
www.aces.rs - For electrical, mechanical and
construction works according to the
FIDIC publications which have been Contractor’s design;
translated into the Serbian language are: - Part of the design performed by the
- Conditions of Contract for Construction for Employer: contained in the Employer’s
Building and Engineering Works Designed requirements;
by the Employer – Parts I and II - For electrical and mechanical facilities
Red Book Part I and equipment;
- Employer (Investor) provides the entire - Need for modern multi-disciplinary
or almost entire design; contracts recognised for the first time;
- It is possible that the Contractor - Payments according to the lump sum
designs a part of it; based on the payment plan, however,
- Civil engineering and building measurements are also possible;
construction designs; - Engineer administers the contract
- Payment based on the measured (administration), supervises the
quantities and unit prices; production, performance and works,
- Contractual values exceed 500,000 and verifies the payments;
USD; - The procedure for dispute resolution is:
- Engineer administers the contract DAB → amicable settlement →
(administration), supervises the works arbitration.
and verifies all payments; - Client/Consultant Model Services
- The procedure for dispute resolution is: Agreement
Dispute Adjudication Board→ amicable White Book
settlement → arbitration. - Client/Consultant Model Services
Red Book Part II Agreement;
- Guidance for the Preparation of - Recommended for the purpose of
Particular Conditions; feasibility studies and similar studies;
- Forms of Letter of Tender; - For the service of project
- Forms of Contract Agreement; management.
- Forms of Dispute Adjudication - Short Form of Contract
Agreement; Green Book
- Conditions of Contract for Design – Build - Short form of contract
and Turnkey - Short execution time (less than 6
Orange Book months);
- The “turnkey” system conditions of - Simple and repetitive works
contract intended for the delivery of a (excavation works represent a good
completely equipped structure (mostly example);
facilities) ready for utilisation; - Contract price is less than 500,000
- The Contractor assumes complete USD;
responsibility for the designing, supply

6 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

- Without an Engineer, the Employer 10. Employer’s Taking Over


shall appoint a “spokesperson” or a 11. Defects Liability
representative; 12. Measurement and Evaluation
- For civil, mechanical, electrical and 13. Variations and Adjustments
other engineering works; 14. Contract Price and Payment
- All required provisions are defined in 15. Termination by Employer
15 clauses; 16. Suspension and Termination by
- The language is simple; Contractor
- Included in the Standard tendering 17. Risk and Responsibility
document of the World Bank intended 18. Insurance
for simple works; 19. Force Majeure
- Balanced risk distribution; 20. Claims, Disputes and Arbitration.
- Payment based on the total price or on
any other basis; 1.2.1.2.1 General provisions
- The Works are designed by the Chapter 1 of the General Conditions presents
Contractor in the scope specified in the the Definitions of the terms used,
Appendix (Appendix to the Contract);
Interpretation, Communications, Law and
- There are no advance payments, while Language, Priority of Documents, Contract
the value of the monthly balance Agreement, Assignment, Care and Supply of
complies with the Works done; Documents, Delayed Drawings or
- Dispute resolution: Invitation to Instructions, Employer’s Use of Contractor’s
amicable settlement or local arbitration Documents, Contractor’s Use of Employer’s
designated at the beginning (however, Documents, Confidential Details, Compliance
it takes place only after the dispute has with Laws, and Joint and Several Liability.
arisen). The Engineer must be acquainted with the
- Conditions of Contract for Design, Build terminology if he wants to correctly interpret
and Operate Projects the meaning of the individual items in the
Gold Book General Conditions. Individual terms are
- Long-term contracts presented in Item 1.2.1 of this volume.
- DBO (Design – Build – Operate)
access combines design, construction Point 1.5 of the General Conditions (“Priority
and long-term commitment (and of Documents”) is very important. In the
maintenance) in one project with one event of inconsistency between the individual
Contractor; documents (for example, between the survey
- The Contractor is usually either a joint and the drawings), the priority of documents
venture entity or a consortium; is of decisive importance. In the situation of
- For Public Private Partnerships (PPP). ambiguity or discrepancy in the documents,
the Engineer will provide the necessary
There is also a Pink Book (which is explained explanations.
in the chapter Conditions of Contract by MFI).
If the Contractor gives notice to the Engineer
that Works are likely to be delayed due to the
1.2.1.2 General Conditions according to requirement of a drawing or if instructions are
3
the Red Book not delivered within the anticipated
timeframe, the Engineer is responsible for:
The General Conditions of Contract
(hereinafter referred to as: General - An extension of the deadline for the
Conditions) are divided into 20 groups: completion of Works;
1. General Provisions - Payment of any Costs for the Works
2. The Employer according to the Contract Price for those
3. The Engineer and similar Works.
4. The Contractor
1.2.1.2.2 The Employer
5. Nominated subcontractors
6. Staff and Labour The rights and the role of the Employer are
7. Plant, Materials and Workmanship presented in Chapter 2 of the General
8. Commencement, Delays and Suspension Conditions, and these are: The Right of
9. Tests on Completion Access to the Site, Permits, Licences and
Approvals, Employer’s Personnel,
3 Employer’s Financial Arrangements, and
Source: Conditions of Contract for Construction Works
– Part I (Serbian Chamber of Engineers, Belgrade, 2008)
Employer’s Claims.

PE Roads of Serbia 7
Legislation and Contracts Serbian Road Supervision Manual

The Employer shall provide, at the request of construction site; the authority will be
the Contractor, the required level of responsible for the supervision of the given
assistance to: site. The Supervising Engineer is authorised
- Obtain copies of the Laws of the Country to assign duties and authority to assistants.
relevant to the Contract; The assignment or revocation of any duties
- When the Contractor applies for a permit and authorisations is performed in writing and
or an approval which must be provided in becomes effective upon the delivery of the
accordance with the Laws of the Country. same to the Parties. If the Contractor does
not agree with any decision or instruction
The Employer is obliged to issue (within 28 from an assistant, the Contractor may refer
days as of the day of receipt of the the matter to the Engineer who shall promptly
Contractor’s request) a written confirmation confirm or vary the assistant’s decision.
that the Works will be paid for.
If the Engineer has no objections to the
1.2.1.2.3 Engineer – Supervisor Works, this still does not constitute approval
and it does not influence his right to reject the
Chapter 3 of the General Conditions includes Works, Facilities or Materials.
the Engineer’s Duties and Authority,
Delegation by the Engineer, Instructions of The Engineer may issue to the Contractor (at
the Engineer, Replacement of the Engineer, any time) instructions or modified Drawings.
and Decisions. If this implies a Variation in the price or the
deadline, Clause 13 is applied. If possible,
In the Serbian version of the FIDIC the Engineer’s Instructions to the Contractor
publication, the term “Engineer” is translated should be in written form.
as “Supervising Engineer” and it relates to a
legal entity. In accordance with the If the Employer decides to replace the
Regulations in regards to quality control the Engineer, the Employer shall notify the
“Supervising Engineer” is a physical person Contractor regarding this no less than 42
who performs supervision. Hereinafter the days prior to the intended date of the
term of “Engineer” will be used instead. replacement. The Employer notifies the
Contractor in written form with the name,
The Employer shall appoint the Engineer who address and relevant experience of the new
will carry out the duties assigned to him. The Engineer.
Engineer’s staff shall include qualified
engineers and other professionals who are Before any decisions are made, the Engineer
competent to carry out such duties. should consult both Parties in order to reach
an agreement. The Engineer shall give notice
The duties, the authority, the delegation, the to both parties of each decision or agreement
replacement and the instructions of the along with all supporting particulars.
Engineer are presented in Chapter 3 of the
General Conditions. 1.2.1.2.4 The Contractor

The Engineer is not authorised to amend the The Contractor’s General Obligations,
Contract. Performance Security, Contractor’s
Representative, Subcontractors, Assignment
The Engineer may exercise the authority of Benefit of Subcontract, Co-operation,
implied by the General Conditions if they are Setting Out, Safety Procedures, Quality
not amended along with the Particular Assurance, Site Data, Sufficiency of the
Conditions. Accepted Contract Amount, Unforeseeable
Physical Conditions, Rights of Way and
The Engineer acts on behalf of the Employer. Facilities, Avoidance of Interference, Access
Route, Transport of Goods, Contractor’s
The Engineer is not authorised to relieve Equipment, Protection of the Environment,
either party of any duties, responsibilities or Electricity, Water and Gas, Employer’s
obligations under the Contract. Equipment and Free-Issue Materials,
Progress Reports, Security of the Site,
No single act of the Engineer shall relieve the Contractor’s Operations on Site, and Fossils,
Contractor from responsibility under the are explained in Chapter 4 of the General
Contract. Conditions.

The Engineer must appoint a Supervising For each subcontractor (except for Material
Engineer (a physical person) for each suppliers) the Contractor needs to have the

8 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

Engineer’s approval. The Contractor shall The Contractor will provide the Engineer with
provide the Engineer with proposals (with details of any accidents as soon as possible.
supporting explanations) in written form 28
days prior to the commencement of any work The Engineer is entitled to demand the
by Subcontractors. removal from the Site any employee of the
Contractor who fails to respect the conditions
The Contractor must establish a system of of the Contract, fails to perform their duties in
quality assurance aimed at meeting the a professional manner, disregards safety,
requirements of the Contract. All activities are health and the environment, or behaves in a
controlled by the Engineer. disorderly manner.

The Contractor shall be deemed to have The Contractor shall submit to the Engineer
inspected the Site and to have collected all the number of each class of the Contractor’s
details that may influence the Tender or the Personnel and of each type of Contractor’s
Works. Equipment on the Site; the details shall be
submitted each calendar month in the form
If the Contractor encounters any unforeseen approved by the Engineer.
adverse physical conditions, the Contractor is
obliged to immediately inform the Engineer 1.2.1.2.7 Plant, Materials and Workmanship
(within 28 days). If, due to these conditions
the Contract Price or the Deadline changes, Chapter 7 of the General Conditions consists
the provisions of Chapter 13 of the General of: Manner of Execution, Samples,
Conditions shall be applied. Inspection, Testing, Rejection, Remedial
Work, Ownership of Plant and Materials, and
The Contractor is obliged to submit monthly Royalties.
Progress Reports to the Engineer.
Prior to the utilisation of Materials, the
1.2.1.2.5 Nominated Subcontractors Contractor shall submit for the Engineer’s
approval, samples of materials with the
Chapter 5 of the General Conditions explains relevant information.
the definition of the term “nominated
Subcontractor”, Objection to Nomination, The Contractor is obliged to provide all the
Payments to nominated Subcontractors, and required conditions for the inspection of the
Evidence of Payments. Plant, Material and other parts of the Works.
The time and place of the inspection are to
According to Chapter 13 of the General be agreed with the Engineer.
Conditions, the Engineer is authorised to
nominate a Subcontractor. If, as a result of the inspection, any Plant,
Material or other Workmanship is found to be
The Engineer may check whether the defective or otherwise not in accordance with
Subcontractors have been paid by the the Contract, the Engineer may reject it.
Contractor. Unless the Contractor provides
the Engineer with evidence (in written form) The Engineer is entitled to instruct the
that a Subcontractor is not entitled to direct Contractor to remove any Materials and Plant
payment, the Employer may at his sole which are not in accordance with the
discretion make a direct payment of part or Contract; to remove and re-execute any
the entire amount to the nominated Works which are not in accordance with the
Subcontractor. Contract; and to perform any work required
for the safety of the Works.
1.2.1.2.6 Staff and Labour
If not otherwise stipulated in the
Chapter 6 of the General Conditions deals Specifications, the Contractor shall pay all
with the following issues: Engagement of costs for natural Materials obtained from
Staff and Labour, Rates of Wages and outside the Site and for the disposal of
Conditions of Labour, Persons in the Service Materials after demolition and excavation, to
of Employer, Labour Laws, Working Hours, disposal areas specified in the Contract.
Facilities for Staff and Labour, Health and
Safety, Contractor’s Superintendence, 1.2.1.2.8 Commencement, Delays and
Contractor’s Personnel, Records of Suspension
Contractor’s Personnel and Equipment, and
Disorderly Conduct. The contents of Chapter 8 of the General
Conditions are: Commencement of Works,

PE Roads of Serbia 9
Legislation and Contracts Serbian Road Supervision Manual

Time for Completion, Programme, Extension 11.4 of the General Conditions or to issue the
of Time for Completion, Delays Caused by Taking-Over Certificate if the Employer
Authorities, Rate of Progress, Delay requests him to do so.
Damages, Suspension of Work,
Consequences of Suspension, Payment for 1.2.1.2.10 Employer’s Taking Over
Plant and Materials in the Event of
Suspension, Prolonged Suspension, and Chapter 10 of the General Conditions deals
Resumption of Work. with the following issues: Taking Over of the
Works and Sections, Taking Over of Parts of
The Engineer is to notify the Contractor the Works, Interference with Tests on
regarding the Commencement Date at least Completion, and Surfaces Requiring
seven days in advance. Within 28 days of Reinstatement.
receiving notice of the Commencement Date,
the Contractor shall submit a detailed time The Contractor may apply to the Engineer for
programme to the Engineer. If the a Taking-Over Certificate no earlier than 14
programme is no longer in accordance with days prior to the Completion of Works or
actual progress, the Contractor shall submit a Sections. If, within 28 days the Engineer
revised programme. If the Engineer finds no does not issue the Taking-Over Certificate or
objections within 21 days, it shall be deemed if he does not reject the Contractor’s request
that the Contractor is to perform in to issue it, it shall be deemed that the
th
accordance with this programme. Certificate has been issued on the 28 day of
the receipt of the request.
The Engineer may suspend Works, but if the
Contractor is not responsible for the 1.2.1.2.11 Defects Liability
Suspension, then Sub-Clauses 8.9, 8.10 and
The following is explained in Chapter 11 of
8.11 of the General Conditions shall apply.
the General Conditions: Completion of
Outstanding Work and Remedying Defects,
Upon the approval for resuming Works, all
Cost of Remedying Defects, Extension of
Works, Plant and Materials shall be
Defects Notification Period, Failure to
inspected by the Contractor and the
Remedy Defects, Removal of Defective
Engineer. The Contractor shall remedy all
Work, Further Tests, Right of Access,
defects caused by the suspension.
Contractor to Search, Performance
1.2.1.2.9 Tests and Completion Certificate, Unfulfilled Obligations, and
Clearance of Site.
The sections of Chapter 9 of the General
Conditions are: Contractor’s Obligations, After the issuance of the Taking-Over
Delayed Tests, Retesting, and Failure to Certificate, the Contractor shall complete all
Pass Tests on Completion. Works within the period of time as
determined by the Engineer, while during the
The Contractor should notify the Engineer in Defects Notification Period the Contractor
regard to testing 21 days in advance. shall remedy any defects declared by the
Immediately after the Tests have been Employer.
performed on the Works or Sections, the
Contractor is to submit a certified report with The Employer is entitled to extend the
the Tests results to the Engineer. If the Test Defects notification Period.
results are unsatisfactory, Sub-Clause 7.5 is
applied. Should the Contractor fail to remedy any
defects, the Employer is entitled to (among
If the Engineer unduly delays the Tests, Sub- other things) demand from the Engineer an
Clauses 7.4 and/or 10.3 of the General agreement on determining a reasonable
Conditions are applied. reduction in the Contract Price.

If the Tests are unduly delayed by the At the request of the Engineer and under his
Contractor, the Engineer instructs him in supervision, the Contractor should establish
writing to perform the Tests within a the cause of the defects.
maximum of 21 days. Upon the expiration of
this time period, the Employer will order the The Engineer shall issue the Performance
Tests at the expense of the Contractor. Certificate within a maximum of 28 days upon
the expiration of the Defects Notification
If the Test results are unsatisfactory, the Period. The Performance Certificate shall be
Engineer is entitled to use Sub-Clause 9.3 or

10 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

the only document deemed to constitute the Certificate, Cessation of the Employer’s
acceptance of the Works. Liability, and Currencies of Payment.

1.2.1.2.12 Measurement and Evaluation The Engineer shall deliver an Interim


Payment Certificate for the first instalment of
The contents of Chapter 12 of the General the advance payment after the Employer
Conditions are: Works to be Measured, obtains the Performance Security.
Method of Measurement, Evaluation, and
Omissions. A request for the issuance of the Interim
Payment Certificate is submitted by the
If the Engineer requires any part of the Works Contractor in the form approved by the
to be measured, the Contractor shall provide Engineer. Along with the application for the
him with assistance in the measurement issuance of the Interim Payment Certificate,
process or with the provision of relevant data. the Contractor will also deliver the Progress
The prices of individual items will be the Report for the given month.
Contract Prices. For Works that are not
defined by the Contract, the price of similar The Engineer controls the instalments (the
Works shall be applied. amount of the Interim Payments) if the
Contract includes a schedule of payments
The Engineer decides on how Omissions specifying the instalments.
influence the variation of the Contract Price,
based on a detailed notice submitted to the No amount will be certified or paid until the
Contractor. Engineer receives and approves the
Performance Security.
1.2.1.2.13 Variations and Adjustments
The Engineer is entitled to make any
The titles of the Sub-Clauses of Chapter 13
correction or modification in any Payment
of the General Conditions are: Right to Vary,
Certificate that should have been made in
Value Engineering, Variation Procedure,
any of the previous Payment Certificates.
Payment in Applicable Currencies,
The Interim Payment Certificate shall not be
Provisional Sums, Daywork, Adjustments for
deemed to be a document which confirms the
Changes in Legislation, and Adjustments for
acceptance, approval, consent or satisfaction
Changes in Cost.
of the Engineer.
An order for variation and/or the modification
After the issuance of the Taking-Over
of the Works may be issued only by the
Certificate the Engineer approves the
Engineer.
payment of the first instalment of the
Retention Money to the Contractor. Upon the
The Value Engineering and the Variation
expiration of the Defects Notification Period,
Procedure commence on the basis of the
the Engineer approves the payment of the
written proposal of the Contractor.
rest of the Retention Money to the
Contractor.
The Engineer is entitled to approve the
Provisional Sums for Works that still do not
When the Contractor submits the Statement
have an agreed price (see Sub-Clause 13.5
at Completion, the Engineer certifies it.
of the General Conditions).
If the Engineer does not agree with or cannot
The Contractor’s reasons for a variance in
certify any part of a draft final statement, the
price will be explained.
Contractor shall submit the additional
1.2.1.2.14 Contract Price and Payment information required by the Engineer and
shall make the agreed modifications. The
Chapter 14 of the General Conditions agreed statement is then referred to as the
comprises the following: The Contract Price, Final Statement. Within 28 days of receiving
Advance Payment, Application for Interim the Final Statement and the Discharge, the
Payment Certificates, Schedule of Payments, Engineer will deliver to the Employer the
Plant and Materials intended for the Works, Final Payment Certificate which shall state
Issue of Interim Payment Certificates, the total amount due and the balance (if any)
Payment, Delayed Payment, Payment of due by the Employer to the Contractor or by
Retention Money, Statement at Completion, the Contractor to the Employer.
Application for Final Payment Certificate,
Discharge, Issue of Final Payment

PE Roads of Serbia 11
Legislation and Contracts Serbian Road Supervision Manual

1.2.1.2.15 Termination by the Employer according to the Engineer’s instructions. The


Engineer decides on the right to extend the
Chapter 15 deals with the following: Notice to Completion Time and the payment of all
Correct, Termination by Employer, Valuation expenses incurred by this delay. The
at Date of Termination, Payment after Engineer makes a decision regarding this –
Termination, and Employer’s Entitlement to see 3.5 of the General Conditions.
Termination for Convenience.
1.2.1.2.18 Insurance
Should the Contractor fail to fulfil any
obligations under the Contract, the Engineer Chapter 18 deals with the following: General
shall require the Contractor to correct the Requirements for Insurances, Insurance for
failure within a reasonable period of time. Works and Contractor’s Equipment,
Insurance against Injury to Persons and
The examples of Termination by Employer Damage to Property, and Insurance for
are explained. Contractor’s Personnel.

Upon the decision of the Employer to Via the insurance policy of the Contractor's
terminate the Contract, the Engineer should workers, both the Employer and the Engineer
establish the amount due to the Contractor are also entitled to compensation.
for the Work, Goods, Contractor's
Documentation or other items in accordance 1.2.1.2.19 Force Majeure
with the Contract. Payment conditions are
explained in Sub-Clause 15.4 of the General Chapter 19 of the General Conditions covers:
Conditions. Definition of Force Majeure, Notice of Force
Majeure, Duty to Minimise Delay,
1.2.1.2.16 Suspension and Termination by Consequences of Force Majeure, Force
Contractor Majeure Affecting Subcontractor, Optional
Termination, Payment and Release, and
The Contractor’s Entitlement to Suspend Release from Performance.
Work, Termination by Contractor, Cessation
of Work and Removal of Contractor’s One Party shall notify the other Party (within
Equipment, and Payment on Termination a maximum of 14 days) in regards to
represent part of Chapter 16 of the General contractual obligations it is not able to or will
Conditions. not be able to fulfil due to Force Majeure. If
the Contractor suffers any damage or loss to
The Contractor is entitled to suspend Works the Works, Goods or Documentation due to
if the Engineer fails to certify the Interim Force Majeure, the Contractor is entitled to
Payments, if the Employer fails to submit the an extension of time and a reimbursement of
Employer’s Financial Arrangements or if the the costs incurred by these circumstances.
Employer fails to comply with Sub-Clause The Engineer makes the decision regarding
14.7 of the General Conditions. The this – see 3.5 of the General Conditions.
Contractor should notify the Employer
regarding this at least 21 days in advance. If the execution of practically any of the Work
in progress is prevented for a continuous
Sub-Clause 16.2 of the General Conditions period of 84 days by reason of Force Majeure
provides a list for reasons of Termination by or for a discontinuous period exceeding 140
Contractor. days after the notice of the occurrence of
Force Majeure, each Party is entitled to
1.2.1.2.17 Risk and Responsibility terminate the Contract by giving notice to the
other Party. The termination shall take effect
Chapter 17 of the General Conditions covers 7 days from the termination notice. In these
Indemnities, Contractor’s Care of the Works, circumstances the Engineer will determine
Employer’s Risks, Consequences of the value of the completed Works and will
Employer’s Risks, Intellectual and Industrial issue the Payment Certificate.
Property Rights, and Limitation of Liability.
1.2.1.2.20 Claims, Disputes and Arbitration
If risks on the Employer’s side cause any
damage to the Works, Goods or Chapter 20 covers the following: Contractor’s
Documentation of the Contractor, the Claims, Appointment of the Dispute
Contractor shall immediately inform the Adjudication Board, Failure to Agree on the
Engineer of any such occurrence and shall Composition of the Dispute Adjudication
remedy the damage and the losses Board, Obtaining Dispute Adjudication

12 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

Board’s Decision, Amicable Settlement, The Particular Conditions are created by


Arbitration, Failure to Comply with Dispute indicating the article number and the
Adjudication Board’s Decision, and Expiry of amendment of the precisely defined word,
Dispute Adjudication Board’s Appointment. sentence or paragraph for each clause of the
General Conditions of the Contract to be
If the Contractor considers himself entitled to amended or supplemented, or by writing the
any extension of Time for Completion and/or following: at the end of the article, the
any additional payment, the Contractor will following text shall be added:.................. (in
notify the Engineer no later than 28 days accordance with the requirements of the
after the Contractor has become aware or Employer).
should have become aware of the event or
circumstances giving rise to the claim. After These Conditions of the Contract contain
this period of time the Employer is General Conditions and together they
discharged from all liability regarding the constitute the Conditions of the Contract for
claim. Construction Works, first edition 1999,
published by Federation Internationale des
Within 42 days from the receipt of the fully Ingenieurs-Conseils (FIDIC); they also
detailed claim, the Engineer will make a contain (in addition) the supplements and
decision regarding his acceptance or amendments of the General Conditions.
rejection of the claim, and will give an
explanation for this decision. 1.2.1.3.1 An example of Particular
Conditions
If not otherwise stipulated in the Contract, the
Dispute Adjudication Board (DAB) will consist An example is given herein of the
of three members. The Employer and the amendments to the General Conditions with
Contractor shall each appoint one member, Particular Conditions according to individual
approve these two members and will then chapters, clauses and sub-clauses.
agree upon a third member.
1 GENERAL PROVISIONS
1.2.1.2.21 Appendix: General Conditions of
Dispute Adjudication Board The following shall be added:
Agreement
1.1 Definitions
The Appendix to the General Conditions In the Conditions of the Contract (hereinafter
explains the general provisions regarding the referred to as “these Conditions”) containing
Dispute Adjudication Board, the qualifications Particular Conditions and the General
required of the Board members, obligations Conditions, the terms and expressions shall
of a Board member, and the obligations of convey the meanings as defined below. The
both the Employer and the Contractor terms designating persons or parties shall be
towards the DAB. companies and other legal persons, except
where the context requires otherwise.

1.2.1.3 Particular Conditions according 1.1.2 Contractual parties and persons


to FIDIC
1.1.2.2 “Employer” is the Public enterprise
The General Conditions of the contract of Roads of Serbia, Bulevar Kralja
according to FIDIC do not change. All Aleksandra 282, Belgrade
variations are formulated in the Particular
Conditions. The Particular Conditions of a 1.1.2.4 “Engineer” is _________
Contract contain the variations of the articles
of the General Conditions, where the relevant 1.1.2.8 “Subcontractor” is a business entity
regulations of RS are applied and additional (legal or physical person) engaged by the
requirements of the Employer are added. The bidder with whom the Employer has
Particular Conditions have greater legal concluded a contract for the execution of
authority than the General Conditions. public works in accordance with the Public
procurement act, and which (as such)
In the Conditions of the Contract for supplies goods or provides services i.e.
Construction Works – Part II, the guidelines construction works that are directly
for the preparation of the Particular connected with the subject of public
Conditions have been given. procurement.

PE Roads of Serbia 13
Legislation and Contracts Serbian Road Supervision Manual

1.1.2.11 “Joint Venture” is: a consortium Sub-Clause 14.3 shall be deleted, and the
of companies which has agreed to perform following shall be added:
the Works under the Contract and on the (a) The operative law is the legislation of the
basis of mutual agreement. Republic of Serbia.
(b) The ruling language for interpretation for
1.1.2.1 “Authorized person of the Employer, all contractors shall be the Serbian
of the Bidder i.e. the Subcontractor” is a language.
person who, according to the law regulating
infractions, is responsible for an infraction 1.10 Employer’s use of the Contractor’s
caused by his actions or by an error made by documents
the Supervising Engineer in charge. The last paragraph has been added and it
reads as follows:
1.1.3 Dates, tests, deadlines and For all eventual variations in the design that
completion occur during construction, the Contractor is
obliged to suggest measures to be
1.1.3.2 “Commencement Date” is undertaken, as well as to make a financial
determined by mutual agreement and is a assessment of the measures in accordance
signed document between the Contractor, with the Contract.
the Engineer and the Employer, which
defines the date of the commencement of New Sub-Clause:
Works. The Time for Completion is defined
by Sub-Clause 8.2 and it commences with 1.15 Confidential information
the date at which the Contract came into The Contractor shall deem the entire
effect. contents of the Contract as private and
confidential information and will treat it as
1.1.4 Money and payment such and with such a purpose, and will not
disclose it partly or in its entirety in any
1.1.4.4 “Discharge” (Clause 14.12) is a commercial or technical magazine or in other
“Record of the final account of executed place without the prior written consent of the
works ”. Employer. In the case of a dispute regarding
the necessity of publication or disclosure of
1.1.4.7 “Interim Payment Certificate” is the information for the purposes of the
created on the data from approved “Book of Contract, this decision shall be made by the
quantities”, a document relating to the Employer.
determination of the quantity of the Works
carried out. 3 THE ENGINEER

1.1.4.12 “Unit Price” is the price per unit of 3.1 Obligations and authority of the
quantity indicated in the bill of quantities of Engineer
the bid.
At the end of the Sub-Clause the following
1.1.6 Other definitions shall be added:
The Engineer shall obtain special approval
1.1.6.2 “Country” refers to the Republic of from the Employer prior to:
Serbia. (a) Approving the hand-over of any Works
pursuant to Clause 4.4 of the General
1.1.6.5 “Laws” means the entire national (or Conditions and the Particular Conditions
state) legislation, rulebooks, regulations, of the Contract;
decrees, statutory and other laws, as well as (b) Approving additional expenses defined by
all regulations and the delegated legislation Clause 13;
of any established authoritative body of the (c) Determining the time extension for
Republic of Serbia. completion of works pursuant to Clause
8.4;
1.1.6.10 “Construction diary and Inspection (d) Approving variations (pursuant to Clause
book” are to be kept for the complete period 13);
of the execution of Works in accordance with (e) Determining the price pursuant to Clause
the Regulations on the contents and manner 12.
of keeping the construction diary and If in the opinion of the Engineer an
inspection book. emergency arises that might bring the lives of
people, the Works or property into danger,
1.4 The law and the language the Engineer is entitled to instruct the

14 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

Contractor to perform all the work or activities The Performance Security shall be issued
which in his opinion may be necessary in either:
order to eliminate or reduce the risk; at the (a) by a bank in the country of the Employer,
same time, the Engineer should not break the or
above mentioned obligation of seeking (b) by a foreign bank acceptable to the
permission. At the same time, the Contractor Employer.
is not relieved of any duty or responsibility Notwithstanding the limitations of the
under the Contract. The Contractor shall act previous paragraph, each time the Engineer
in accordance with all such instructions given determines an increase of the Contractual
by the Engineer, despite the fact that the Price due to variations in costs and/or due to
Employer has not given his approval. The legislation, or as a result of discrepancies
Engineer shall determine the extra amount exceeding 10% of the share of the agreed
for the contractual price regarding his value of the Works, the Contractor shall
instructions and pursuant to Clause 12, and immediately increase by a corresponding
shall inform the Contractor accordingly, and percentage the value of the Performance
will deliver a copy to the Employer. Security.
Until then the Employer is entitled to retain
4 THE CONTRACTOR security to the amount of 10% of the increase
of the agreed price of the Works.
4.1 Contractor’s general obligations
At the end of Sub-Clause 4.1 the following 4.3 Contractor’s representative
shall be added: The last sentence of Sub-Clause 4.3 shall be
The Contractor will immediately notify the deleted, and the following will be added:
Employer and the Engineer of any error, If the Contractor’s Representative or his
omission, deficiency or other defect in the managerial staff do not speak fluent Serbian,
design, plans, list of works and geodetic data the Contractor shall provide an interpreter
(markings of the relative height, control points who will be at their disposal during work
for the road routes and for objects) as well as hours.
of the other information relating to the Works
which the Contractor would come across 4.4 Subcontractors
during the review of the Contract or during The first paragraph of Sub-Clause 4.4 has
the execution of the Works. Should the been amended and now reads as follows:
Contractor fail to do this, thus causing delays The Contractor is allowed to assign to the
or other consequential deviations from the Subcontractors (for subcontracting) up to a
Contract, then the Contractor shall have no maximum of __% of the total value of the
right to submit a request for cost redemption Works.
and shall be deemed responsible for such
consequences on the occasion of the Lines (b), (c) and (d) of the second paragraph
Employer suffering any damages. shall be deleted.
The Contractor shall keep the Book of Below line (a) a new line (b) has been added
quantities and provide the Inspection book. and it reads as follows:
The Contractor needs to have the written
4.2 Performance Security consent of the Employer for all
The first and the second motions of Sub- subcontractors not listed in the Bid and prior
Clause 4.2 have been completely amended to their engagement on certain Works.
and now read as follows: Should the Contractor establish after the
The Contractor shall provide the Employer conclusion of the Contract that there is the
with Performance Security (fulfilment of the need for the engagement of a subcontractor
Contract) within 10 (ten) working days from for the purpose of the execution of Works,
the day of the conclusion of the Contract.” the Contractor shall send this suggestion to
The Performance Security shall be given in the Employer. The Employer shall, within 14
the form of a bank guarantee. A copy of the days from the receipt of the proposal
guarantee shall be sent to the Engineer. regarding the new subcontractor (and on the
When the joint bid of a group of contractors occasion of the submission of the supporting
has been selected as the most favourable documents regarding the fulfilment of
one, the group of contractors is obliged to conditions), check both the suitability and
reach an agreement regarding the capacity of the subcontractor and decide on
submission of a joint bid for the performance whether he will approve the engagement of
of works, and to select one of the partners the newly announced subcontractor. The
from the group of contractors as the Employer cannot reasonably reject the
employer for the Performance Security. proposal of the Contractor regarding the

PE Roads of Serbia 15
Legislation and Contracts Serbian Road Supervision Manual

engagement of a new subcontractor. The At the end of Sub-Clause 6.8 the following
newly declared subcontractor must fulfil the shall be added:
same conditions valid for the subcontractor A relevant number of the supervising staff of
named by the Contractor in the bid. All the Contractor must have an active
documentation for the new subcontractor knowledge of the Serbian language or a
shall be enclosed with the application, as sufficient number of interpreters must be at
stipulated by provisions_______________ of their disposal on the site during work hours
the said public procurement. (as defined in Sub-Clause 1.4).
In the application the applicant must indicate
the reason that has created the need for the 6.10 Records of the Contractor’s
engagement of the subcontractor at the Personnel and Equipment
Works; the reasons must be fully At the end of Sub-Clause 6.10 the following
corroborated. shall be added:
The main reasons are: The contractor will provide detailed
- Circumstances arising after the signing of information to the Employer and to the
the Contract related to the Works and Engineer as to the type of planned Works,
which the Contractor was not able to work hours, the anticipated number of the
foresee or was not obliged to foresee in Contractor’s personnel of each category, as
the phase of the composition and well as each type of equipment on the site.
submission of his Bid; This detailed information will be delivered at
- The need for additional Works, an least twice a week by email to the Employer
increased number of Works or unforeseen and the Engineer, until the Contractor has
Works which the Contractor is not able to completed all Works known to be unfinished
execute alone; within the Time for Completion indicated in
- Climatic, organisational or technical the Taking-Over Certificate.
circumstances resulting in the necessity of In the situation where for justifiable reasons
engaging a subcontractor in order to have the plan does not match the actual situation,
the contractual Works executed in the the Contractor is obliged to notify the same
scope, with the quality and within the time recipients in regards to this as soon as the
period stipulated by the Contract. changes take place. The Contractor bears
The Engineer is obliged to ascertain as soon the moral and material responsibility for the
as possible whether the conditions indicated accuracy of the information. The Employer is
above have been fulfilled, and to send the entitled to claim for damages caused by
application along with his findings to the incorrect information and the loss of
relevant department of the Employer. The reputation.
task of the department is to study the
application with the proposal again, and in 6.12 Foreign Personnel – additional Sub-
the situation where the conditions have been Clause:
fulfilled – to issue an approval regarding the The Contractor may engage any personnel
Contractor’s proposal. from abroad required for the execution of the
The eventual approval regarding the Works. The Contractor shall ensure that the
Contractor’s proposal does not relieve the personnel are provided with the required
Contractor from responsibility taken over residency visas and work permits. The
under the Contract; the Contractor is still Contractor is responsible for the return of
solely and entirely responsible for the quality these personnel to the place where they were
and timely execution of the contracted recruited or to their domicile. In the event of
Works.” death in the Country of any of the personnel
or members of their families, the Contractor
4.9 Quality assurance shall be responsible for making the
At the beginning of Sub-Clause 4.9 the necessary arrangements for their return or
following shall be added: burial.
The Contractor will provide quality in
accordance with the operating laws and 7 PLANT, MATERIAL AND
technical regulations as well as in compliance WORKMANSHIP
with the General and Particular technical
conditions. 7.1 Manner of Execution
At the end of Sub-Clause 7.1 the following
6 STAFF AND LABOUR shall be added:
Prior to Commencement of the Works the
6.8 Contractor’s Superintendence Contractor shall (at his own expense) provide
a laboratory on the Site with the appropriate

16 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

equipment and personnel for the purpose of 8.4 Extension of Time for Completion
performing tests onsite which are necessary Item (a) of Sub-Clause 8.4 has been
for the execution of the Works specified in amended and reads:
the Contract. Variations (unless an adjustment to the Time
of Completion has been agreed upon under
7.4 Testing Sub-Clause 13.3 (Variation Procedure)) or
The last sentence of Sub-Clause 7.4 is other substantial changes in the quantity of
substituted by the sentence: an item of work in the situation where the
In the situation where the Engineer’s value of the added and/or additional Works
representative was not present during the exceeds 15% of the contracted value of the
testing, the Engineer may deem the results Works.
and records of the testing acceptable, or – in
the case of any doubt – the Engineer may 11 DEFECTS LIABILITY
request retesting.
11.3 Extension of Defects Notification
8 COMMENCEMENT, DELAYS AND Period
SUSPENSION At the end of Sub-Clause 11.3 the following
shall be added:
8.1 Commencement of Works According to the laws of the Republic of
The first sentence of Sub-Clause 8.1 is Serbia the Contractor is responsible for the
substituted by the sentence: defects and errors defined in Sub-Clauses
The Contractor will commence Works 11.2 (a), (b) and (c) that could not have been
dependent upon how quickly he is notified by noticed or which he deems to have been
the Engineer that he may commence Works, unnoticeable before the expiration of the
or he commences Works after the signing of Defects Notification Period pursuant to
the Access to and Possession of the Site. Clause 11.3. The general deadline for the
The Access to and Possession of the Site will limitation of such a liability is the time period
be performed during the time period indicated defined in the Appendix to the Bid and it may
in the Appendix to the Bid, according to the not exceed the period of ____ years for work
validity date of the Contract. on roads, and ____ years for work on bridges
and other structures.
8.3 Programme When the joint bid of a group of contractors
At the end of item (d) (ii) of the Sub-Clause has been selected as the most favourable
8.3, the following shall be added: one, the group of contractors is obliged to
The time programme will contain a reach an agreement in the form of a legally-
harmonised masterplan of progress with the binding legal act regarding the joint
indication of a clear time frame for the performance of Works, and to select one of
individual phases of the Works. Along with the partners from the group of contractors as
the time programme, the Contractor shall the Employer for the remedy of defects within
give the Engineer the Plan of equipment, the warranty period.
machinery, building materials and workforce The warranty period commences either from
for the specified time period. If the Works are the day of starting of the structure for use or
assigned to different Contractors, they shall from the day of the issuance of the Taking-
deliver to the Engineer a mutually Over Certificate, dependent upon which date
harmonised masterplan of progress. Should is earlier. The expiry period of the warranty
the Contractors fail to unify the progress plan shall be 30 days longer than the warranty
among themselves in a timely manner, the period determined by the Contract.
harmonisation shall be conducted by the When removing defects within the warranty
Engineer at the expense of the Contractors. period, the Contractor shall execute the
In this case the Contractors are not entitled to works required for the remedying of the
variations in the contracted times for defects________hours per day. All defects
completion and the contract price. that endanger the safety and health of people
Within ten days of the validity of the Contract, must be removed within______hours.
the Contractor will create a Technical
analysis of the Works that shall be verified by 11.9 Performance Certificate
the Engineer. The analysis will be created in At the end of Sub-Clause 11.9 the following
accordance with the guidelines given in shall be added:
Chapter____ –Technical Conditions. Time As a precondition for the issuance of the
programme will be created with a computer Performance Certificate, the Contractor must
programme_____________ and shall include deliver to the Engineer _____ copies of the
the number of daily work hours. Design of the constructed facility

PE Roads of Serbia 17
Legislation and Contracts Serbian Road Supervision Manual

____________________ in printed form, and occurrence and his proposed measures


one copy in electronic form including without delay; during the joint insight into the
inventories, final quantities and other report the Engineer enters it into the Record
documents prepared by the Contractor at his which the Engineer then submits without
own expense simultaneously with the delay to the Employer along with the
completion of the Works and with the proposal of the measures, no later than three
appropriately qualified technical personnel in days from his insight into the documents.
order to present the state of the completed In the situation of a variation in contractual
Works. The design documentation must be deadlines, both the Employer and the
submitted to the Employer in 4 (four) printed Contractor shall arrange the time variation by
copies and 1 (one) copy in electronic form. way of an Annex to the basic Contract, no
The design documentation in electronic form later than the expiration date of the related
shall be prepared in the following formats: contractual deadline.
Graphics in vector formats .dwg and .dxf;
Text in .doc format; 13.8 Adjustments for Changes in Cost
Spreadsheets will be in .xls format. Sub-Clause 13.8 has been completely
amended and reads as follows:
12 MEASUREMENT AND All unit prices from the bill of quantities
EVALUATION supplied in the bid are fixed and are not
subject to variation, except for the
12.1 Works to be measured prices________________ which will be
At the end of the last paragraph of Sub- calculated without handling fees according to
Clause 12.1 the following shall be added: verifiable actual costs based on the invoices
All measurements performed in order to of the contractors engaged at the Works of
determine the quantity of the completed the road closure.
Works, shall be entered into the calculation
plans and they constitute a part of the Book 14 CONTRACT PRICE
of quantities. 14.3 Application for the Interim Payment
Certificates
13 VARIATIONS AND ADJUSTMENTS The first paragraph of the Sub-Clause has
been amended and now reads as follows:
13.3 Variation Procedure The Contractor shall submit to the Employer
At the end of Sub-Clause 13.3 the following ______ of copies of the Interim Payment
shall be added: Certificate at the end of each month prior to
The Employer and the Contractor will the ___the day of the following month. The
conclude (without delay) an Annex to the certificates must be signed by authorised
basic Contract with the Contractor for the representative of the Contractor, and the
completion of all additional work, surplus Engineer must verify them in the format
work, as well as shortages and unforeseen approved by the Employer. The Engineer will
work in the case of the variation of the review the Interim Payment Certificate within
contractual deadlines or in the case of the ____ days, and the Employer will pay the
replacement of a subcontractor, and within undisputed part of the Payment within____
the time period required for its preparation, days from the day of completion of the
approval and the signing of this Annex. service.
- Unforeseen works (works not included in In the situation where a joint bid of a group of
the contract, but must be completed); contractors has been selected as the most
- Additional works (works that has not been favourable one, the interim and the final
contracted and are not necessary for the payment certificate will be signed by the
fulfilment of the Contract, but the partner who is simultaneously the employer
procuring entity demands its execution); of the Performance Security. In the situation
- Excess works (the quantities of completed where a joint bid of a group of contractors
works exceed the contracted quantity of has been selected as the most favourable
Work); one, the Employer shall pay the undisputed
- Lacking works (the negative deviation of parts of the Certificates into the account of
completed work in relation to the the partner who is at the same time the
contracted quantity of Work). employer of the Performance Security.
The Contractor may perform unforeseen
Work without the consent of the Employer, if, 14.6 Issue of Interim Payment Certificates
due to the urgency of the Work he is unable Sub-Clause 14.6 (c) has been added and
to request such a consent. The Contractor reads as follows:
shall inform the Engineer regarding the

18 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

The Employer shall retain ____ percent of The Contractor is not entitled to suspend
the Works price for which the payment has Works in the case of a part of the payment
been approved until the Contractor submits being disputed by both Parties for which
to the Employer an amended Performance reason the Engineer has not approved the
Security as stipulated by Clause 4.2 of the part of the payment i.e. the Employer has not
Particular Conditions. made the payment.

14.13 Issue of the Final Payment 18 INSURANCE


Certificate
At the end of Sub-Clause 14.13 the following 18.1 General Requirements for Insurance
paragraph shall be added: At the end of Sub-Clause 18.1 the following
If the Employer and the Contractor in the shall be added:
Record of the final account of executed The Contractor is entitled to enter into all
works, Sub-Clause 14.12, establish that due insurance contracts relating to the Contract
to deficiencies in the quality of the completed with authorised insurance companies
work that the Employer has the right to a approved by the Employer and in accordance
financial deduction, then such financial with the regulations of the Republic of Serbia.
deductions shall be calculated in the Final
Payment Certificate. 18.2 Insurance for Works and the
Contractor’s Equipment
14.15 Currencies of Payment At the beginning of Sub-Clause 18.2 the
At the end of the last paragraph of Sub- following shall be added:
Clause 14.15 the following shall be added: According to Sub-Clause 18.2 it is not
The Employer will pay the Contractor the required that insurance covers the losses or
Contract Price in a payable currency into the risks indicated in Sub-Clause 17.3 in Sub-
bank account or accounts indicated in the Clauses (a), (b), (d), (e), and (f).
Contract.
18.3 Insurance against Injury to Persons
15 TERMINATION BY EMPLOYER and Damage to Property
At the end of Sub-Clause 18.3 the following
15.2 Termination by Employer shall be added:
In the first paragraph of 15.2 a new line (g) The minimum insurance amount according to
shall be added: Sub-Clause 18.3 is _____________ RSD.
(g) if the Contractor without the prior written
consent of the Employer replaces the 18.4 Insurance for the Contractor’s
management contractor or the subcontractor, Personnel
or if he assigns the Works to a subcontractor At the end of Sub-Clause 18.4 the following
which is not indicated in the Contract. shall be added:
The insurance shall be in accordance with
16 SUSPENSION AND TERMINATION the laws and legislation of the Republic of
BY CONTRACTOR Serbia and will be conducted through
registration with the relevant agencies of
16.1 Contractor’s Entitlement to Suspend local authorities and at the expense of the
Work Contractor. Should the Contractor fail to
The first paragraph shall be deleted and comply with these laws, the Contractor shall
replaced with the following paragraph: be subject to sanctions under the Contract
Should the Engineer fail to issue the and according to the laws and regulations of
Certificate pursuant to Sub-Clause 14.6 the Republic of Serbia.
(Issuance of Interim Payment Certificates) or
should the Employer fail to comply with Sub- 20 CLAIMS, DISPUTES AND
Clause 2.4 (Employer’s Financial ARBITRATION
Arrangements) and Sub-Clause 14.7 Sub-Clauses 20.2 and 20.3 shall be deleted
(Payment) for the undisputed part of the as well as the second paragraph of Sub-
payment, the Contractor will suspend Works Clause 20.4. They will be replaced with the
(or decrease the speed of Works) after the following:
expiration of a minimum of 21 days from the The Engineer acts in the capacity of DAB in
date of the notification of the Employer until accordance with Sub-Clause 20.4 justly and
the Contractor receives the Payment impartially and at the expense of the
Certificate or another appropriate certificate Employer. Should the Employer intend to
or the payment, all dependent upon the replace the Engineer, the Employer’s
situation and as described in the notification. notification in the sense of Sub-Clause 3.4

PE Roads of Serbia 19
Legislation and Contracts Serbian Road Supervision Manual

shall contain the explained proposal for


replacement.

ADDITIONAL CLAUSES

21 FEES AND DUTIES

21.1 Foreign Duties


The prices offered by the Contractor shall
comprise all taxes, customs fees and other
duties that relate to the production,
processing, sale and transportation of the
Contractor’s equipment out of the Country, as
well as to the installation, materials and
products that will be applied or installed
under the Contract, and to the services
provided under the Contract.

21.2 Local Duties


The prices offered by the Contractor include
all customs fees, import-related customs
fees, taxes, income taxes and other duties
that may be assessed for taxation according
to the laws and regulations that have been in
effect 14 days prior to the opening of the bids
in the Republic of Serbia, and that relate to
the Contractor’s equipment, installations,
materials and products (permanent,
temporary and disposable) which have been
supplied for the needs of the Contract, and
the services provided under the Contract. No
provision of the Contract relieves the
Contractor from the payment of any fees and
duties prescribed in the Country for the profit
obtained on the basis of the Contract.

21.3 Income Taxes pertaining to


Personnel
The Contractor’s team, personnel and
workforce shall be subject to personal
income taxation in the Republic of Serbia in
the respect of the taxation of their personal
incomes in accordance with the laws and
regulations effective at the given time, and
the Contractor shall fulfil all obligations in the
sense of reduction as is stipulated by these
laws and regulations.

1.2.1.4 Contract sample according to


FIDIC

A Contract sample between the Employer


and the Contractor according to FIDIC is
provided below.

20 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

CONTRACT AGREEMENT

This Agreement made the______________day of __________20_______________


between__________________________of______________ (hereinafter called “the Employer”) of
the one part
and__________________________of______________ (hereinafter called: “the Contractor”) of the
other part.

Whereas the Employer desires that the Works known as ________________________shall be


executed by the Contractor, and has accepted a Tender by the Contractor for the execution and
completion of these Works and the remedying of any defects therein,

The Employer and the Contractor agree as follows:

1. In this Agreement words and expressions shall have the same meanings as are respectively
assigned to them in the Conditions of Contract hereinafter referred to.

2. The following documents shall be deemed to form and be read and construed as part of this
Agreement:
a. The Letter of Acceptance dated___________
b. The Letter of Tender dated______________
c. The Addenda nos___________
d. The Conditions of Contract
e. The Specification
f. The Drawings, and
g. The completed Schedules

3. In consideration of the payments to be made by the Employer to the Contractor as hereinafter


mentioned, the Contractor hereby covenants with the Employer to execute and complete the
Works and remedy any defects therein, in conformity with the provisions of the Contract.

4. The Employer hereby covenants to pay the Contractor, in consideration of the execution and
completion of the Works and the remedying of defects therein, the Contract Price at the times
and in the manner prescribed by the Contract.

In witness whereof the parties hereto have caused this Agreement to be executed the day and

Signed by: _____________________ Signed by: _____________________

For and on behalf of the Employer in the presence For and on behalf of the Contractor in the presence
of of

Witness: _____________________ Witness: _____________________

Name: _____________________ Name: _____________________

Address: _____________________ Address: _____________________

Date: _____________________ Date: _____________________

PE Roads of Serbia 21
Legislation and Contracts Serbian Road Supervision Manual

Standard documents and rules are applicable


1.2.2 CONTRACT CONDITIONS for international and national investment
ACCORDING TO MFI procedures without the licensing of the
Conditions. The rules are accessible to the
public on the following web-pages:
1.2.2.1 Institutions of the MDB and MFI
The WB Group:
MDB (Multilateral Development Bank) http://web.worldbank.org/WBSITE/EXTERNA
institutions are supranational institutions L/PROJECTS/PROCUREMENT/0,,contentM
founded by sovereign states as their DK:20060840~menuPK:84282~pagePK:842
shareholders. 69~piPK:60001558~theSitePK:84266,00.html

As lenders and donors their objective is to aid http://web.worldbank.org/WBSITE/EXTERNA


developing countries economically and L/PROJECTS/PROCUREMENT/0,,contentM
socially by providing support to their DK:20060840~menuPK:84282~pagePK:842
economic and social development. 69~piPK:60001558~theSitePK:84266,00.html

The main members of the MDB are: the EBRD:


African Development Bank, Asian http://www.ebrd.com/pages/workingwithus/pr
Development Bank, European Bank for ocurement/project.shtml
Reconstruction and Development (EBRD),
Inter-American Development Bank Group, EIB:
World Bank, Black Sea Trade and http://www.eib.org/projects/publications/guide
Development Bank, Caribbean Development -to-procurement.htm
Bank, Central American Bank for Economic
Integration, Corporación Andina de Fomento, EAR:
East African Development Bank and West http://ec.europa.eu/europeaid/tender/geninfo/
African Development Bank. index_en.htm

MFI (Multilateral Financial Institutions) are


similar to MDB institutions, but sometimes 1.2.2.2 The Harmonised MDB version of
they are classified separately due to the the Red Book – the Pink Book4
focus of their financing on certain project
types. The MFI are: the European The Pink Book is the amended version of the
Commission, European Investment Bank, Red Book.
International Fund for Agricultural
Development, Islamic Development Bank, All differences between the Red Book (1999
Nederlandse Financieringsmaatschappij voor edition) and the Pink Book have been dealt
Ontwikkelingslanden NV, Nordic Investment with in detail on the web-page:
Bank, OPEC Fund for International
Development. http://www.fenwickelliott.co.uk/fidic-red-book-
1999-and-mdb-harmonised-edition-pink-
The following institutions were involved in the book-compared
publishing of the FIDIC “Pink Book”: the
African Development Bank, Asian
Development Bank, Black Sea Trade and 1.2.3 OTHER CONDITIONS OF THE
Development Bank, Caribbean Development CONTRACT
Bank, European Bank for Reconstruction and
Development, Inter-American Development
Tender documentation is usually divided into
Bank, Islamic Development Bank, Nordic
chapters. The Employer creates the chapters
Development Fund, World Bank.
serving as a form of preparation for bidders;
the Employer writes down all his
The MDB institutions have agreed that the
requirements and expectations regarding the
“Pink Book” will always be applied in
time schedule, quality, method of execution
construction works where designs are
of the works, the capacity of the contractor
created by the Employer.

Therefore, MDB contracts are basically 4


similar to the conditions previously described Source: Conditions of Contract for Construction, and
Engineering Work designed by the Employer, Multilateral
in the FIDIC contracts. They differ only in Development Bank Harmonised Edition, FIDIC; June
certain provisions. 2010

22 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

and his employees, the financial 1.2.3.1 Contract sample of the PE Roads
requirements of the contractor and his own of Serbia
resources, selection criteria, etc.
A Contract sample between the Employer
If the Employer does not utilise the FIDIC and the Contractor according to PE Roads of
publication for the General Conditions, then Serbia is given below.
the Employer composes his own conditions
defining his requirements. The requirements
are described in Volume 2 “Construction
Supervision” of the SRSM book (Serbian
road supervision manual) and they relate to
all the construction stages up to the final
statement. With well prepared tender
documentation, problems that frequently
arise during construction may be avoided.
Such problems include: An increase in the
contract price, delays in completion, poor
quality construction, non-compliance with the
relevant legislation, an unnecessary impact
on the environment, etc. Therefore, the
objective of the tender documentation, along
with the contract documents, is to provide the
Employer with a permanent and cost-
effective structure.

The tender documentation should contain the


following:
- Instructions for the execution of the Works
including criteria regarding the level of
quality of construction required i.e. quality
of the installed materials and equipment –
the required measurements, tests and
quality assurance;
- A Programme with the defined
commencement date and time required
for completion;
- Definition of the documents provided by
the contractor i.e. by the employer;
- The methods for the implementation of
the Works including transportation routes,
dump sites, environmental protection and
occupational health and safety;
- Precise criteria and conditions for the
increase of the price;
- Financial security – guarantees and
insurances;
- Payment conditions (advance payments,
premiums, payment certificates, payment
of undisputed portions, penalties);
- Approval of the subcontractors and
responsibility for their work;
- Conditions for taking-over the Works;
- Warranty period – duration, conditions
regarding the quality upon expiration;
- Conditions for the final taking-over and
calculations;
- Dispute resolution.

PE Roads of Serbia 23
CONTRACT
Entered into by and between the Contractual Parties

(details of the Employer)

and

(details of the Contractor)

SUBJECT OF THE CONTRACT

Article 1

The Contracting Authority assigns and the Contractor accepts and undertakes to execute the works
on......

based on the accepted bid of Contractor No. ..... from ..... year, all in accordance with the Law on
Planning and Construction, the Law on Public Roads, technical documentation and tender
documentation which constitute a part of this Contract.

VALUE OF THE WORKS

Article 2

The Parties state in mutual consent that the total value of the works from Article 1 of this Contract
is:

.…………………………………………RSD excluding Value Added Tax, and including


.…………………………………………RSD of Value Added Tax (18%)
TOTAL:.…………....…………………..RSD

Written in words……………………………………………………………………....

Article 3

The value of the works is fixed.

Article 4

The offered unit prices from the estimated bill of quantities shall not be amended due to the
increase (excess) or decrease (deficit) quantity of works defined in the estimated bill of quantities.

The unit price for any unforeseen and additional works shall be determined based on the analyses
and corrections of the prices’ analysis provided by the Contractor pursuant to the General
Conditions and Appendices enclosed with the bid.

Article 5

The amount of the advance payment is ......% from the total agreed contract value of the works.

24 PE Roads of Serbia
Serbian Road Supervision Manual Legislation and Contracts

Article 6

For the security of the Employer and for the purposes of removal of the defects in the works, the
Contractor shall retain the amount of .....% from the total value of the works (from each monthly
instalment) until the completion of the works.
Upon the completion of the works and upon the positive technical acceptance of the works, a half
of the total retained amount (...%) shall be returned to the Contractor, while the other half shall be
returned to him at the end of the warranty period.

COMPLETION PERIOD

Article 7

The completion period is ....... days.

Article 8

Should the Contractor suggest an amendment or a supplement to the approved design, and should
such a proposal be adopted by the Employer thus attaining a more rational solution and cost-
effectiveness regarding the construction process, the Contractor is entitled to a premium of the
amount of ..... from the sum thus saved.

Article 9

Appendices to this Contract are:

The accepted bid of the Contractor with all Appendices to the bid;
Particular Conditions of the Contract;
General Conditions of the Contract;
Technical documentation;
Bank guarantee for the Performance Security;
Agreement of joint bidding (if two or more partners submitted a joint bid).

Article 10

The Employer and the Contractor agree to resolve all disputes arising from this Contract primarily
in the way defined in the tender documentation and by mutual agreement.

Article 11

This Contract comes into effect on the date it is signed by the Contractor and by the Employer.

The Contract is drawn in .... identical copies of which the Employer keeps .... copies, and
........copies belong to the Contractor.

Contractor Employer

PE Roads of Serbia 25

You might also like