Professional Documents
Culture Documents
Lecture 15(8)
埋立部 area
Reclaimed
桟橋部
Pier section Slit Column
スリット柱
Rubble mound
前面マ ウン at the
ド
front of seawall
(捨石) Cellular
鋼管矢 seawall
板井筒 with
steel pipe sheet pile
Tsuchida, Takashi
Hiroshima University
Topics 2
Ground Improvement Method of Soft Clayey
Ground in Seaport and Airport Projects
1. History of ground improvement of soft clay ground
- Replacement method -
2. Vertical Drain method
2.1 Design of vertical drain method
2.2 How to determine horizontal coefficient of consolidation
2.3 Case studies: Kansai International Airport and Tokyo International
2.4 Vacuum consolidation method
3. Sand Compaction Pile Method and Deep Cement Mixing Method
3.1 Sand compaction pile method
3.2 Deep mixing method
4. Artificial Geo-Materials and case studies
4.1 Cement treated soil, Pneumatic Mixing Method
4.2 Lightweight treated soil
4.3 Tokyo International Airport 4th runway project
4.4 Artificial sealing geo-material
Case Studies
B-Runway
A-Runway
1st Navigation
C-Runway Channel
Tama River of Tokyo Port
Taxiway Bridge
・Due to the soft soil ground conditions at the site, 1849 driven steel pipe piles with a
diameter ranging from 0.9 m to 1.6 m and a length exceeding 70 m are required to
support the jacket structures.
1,100m
Reclaimed
Area
45m
Taxiway Bridge
63m
Specially equipped crane barge
Each jacket structure needed to be placed on pre-installed piles with high accuracy.
The size of jacket structure 63 m in length and 45 m in width is the maximum possible
size in consideration of available work barges and carrying vessels. The runway
platform consists of a total of 198 of these jacket structures, each weighing about
1300–1,600 t .
9
Pneumatic Mixing Method
Pneumatic flow and mixing in pipe
Injection of Mixing by
stabilizer turbulent flow
(Cement)
Plug flow
Stone
Stone
Dredging and replacement
by sand Mountain Sand
Mountain Sand
soft clay 1 SCP60% SCP60%
soft clay 2 Sand Drain Method
SCP 30%
soft clay 3
Placement of Pneumatic
Placement vessel of PM treated soil mixing treated soil
Pipe Mixing
Treated Soil
Filling of
Mountain Soil
Pneumatic Pneumatic
Typical cross section of shelving bank revetment
Mixing Mixing
Embankment 2
Embankment 1
Transportation Transportation
Pipe Pipe
Pneumatic transport
vessel Transportation Pipe
φ=35cm
Design strength of PM
treated soil
The dredged clay is put in the pneumatic transportation vessel after removing the
foreign substances.
Strength of pneumatic mixing treated soil
埋立部
Reclaimed area
桟橋部
Pier section スリット柱
Slit Column
前面マ
Rubble ウン
mound at ド
the
front (捨石)
of seawall Cellular seawall with鋼管矢板井筒
steel pipe sheet pile
16
Plane View of reclamation/pier connection structure
Reclaimed area
Existing
Steel pipe Seaside
Airport sheet pile
17
Technical points of reclamation/pier connection structure
Upper Structure
(Wave-Dissipation Type Seawall) Expansion/Contraction Device
・Slit column structure is used to ・To adjust the deformation due to
dissipate waves. temperature change or earthquake
伸縮装置
A.P. +13.7m 渡り桁 AP+13.7
Lightweight
軽量混合処理土 treated soil
管中混合固化処理土
Pnuematic treated soil
前面マウンド
(捨石)
A.P. -18.0m
AP-18.0 中仕切堤
SCP method
高置換SCP 低置換
SCP
Lightweight Soil and Pneumatic
①-C SCP mixing treated soil for reduce the
A.P. -36.0m
AP-36.0
seismic earth pressure and the
settlement of back filling
②-C
A.P. -60.0m
AP-60.0 鋼管矢板井筒
Cellular seawall with steel pipe sheet pile
・Use of large diameter steel pipe sheet pile
③-S (φ1600)
Rubble mounds and ground
improvement by Sand Compaction ・Use of high tensile strength joint of steel pipe
Pile (SCP) method were made to sheet pile to reduce the deformation of
reduce the lateral movement of seawall
・Driven to the base layer to reduce the
seawall structure. settlements. 18
Connection Structure
Cellular seawall with steel pipe sheet pile
Reclaimed area
Pier Section
19
Connection Structure
Dry-up Inside of Cell
Corrosion proof
for overlapping
concrete
20
Foam Treated Soil
Cement-Foam-Clay
Continuous Mixer
Flow test
Density measurement 21
Placement of Foam Treated Soil
Special vessel for mixing and treatment
of lightweight treated soil
Berge transporting
dredging
22
Unit weight and strength of foam treated soil
Target Target
1.02g/cm3 200 kPa
Placed
Target in air
1.12g/cm3
Elevation (m)
Placed
Elevation (m)
Target
in air 1.17g/cm3
Placed
in water Placed
in water
-20 -20
Depth (m)
Depth (m)
-30 -30
-40 -40
-50 -50
-60 -60
-70 -70
Steel Pier Side Landfill Side
24
Construction of connecting area
25
Conclusions
In the project of Tokyo International Airport, ground improvement
technique and new geomaterials were used in various parts of the
constructions.
The methods and the methods were summarized as follows:
Foundation of shelving bank revetment
SCP method (inexpensive increase of bearing capacity)
Replacement method (Reuse of excavated clay)
Foundation of gravity type seawall
Cement deep mixing method ( large bearing capacity)
Foundation of runway
Sand drain method (reduction of residual settlements, increase of strength)
Backfill of seawall
Pneumatic mixing treated soil ( reduction of earth pressure and settlement,
inexpensive fill material by reusing the dredged clays)
Lightweight treated soil (reduction of earth pressure, prevention of damage of
piles due to lateral deformation)
Case Study 2
Waste Disposal Facility in Seaport
27
Waste Disposal Facility in Seaport
The safe management of wastes is a key issue in mega cities.
To find a place for waste disposal facility in land is getting
more and more difficult, because the agreements of the
residents near the site would hardly be obtained due to
problems, such as, transportation noise, flying dust, bad Kobe Port
smell and especially potential risk of ground water pollution.
Due to these circumstances, waste disposal sites located in
seaport are more requested especially large cities facing to
sea. One of the advantage of the location in seaport is that
we can construct waste disposal with larger capacity.
Osaka Port
under construction
Cブロック
inland.
Because of strict technical requirements, the construction and
maintaining cost becomes high, and small size waste landfill sites have
lost economical feasibility.
Definition of “Impermeable layer” in technical standard
of Ministry of Environments revised in 1998
more
than 50cm
Covering material more
Covering material
than 50cm
more Clay, k <1.0×10-6 cm/s more
than 50cm
than 5cm Cutoff sheet
Asphalt Concrete
Cutoff sheet k <1.0×10-7 cm/s thickness is more than 1.5mm
thickness is more than 1.5mm
Cutoff sheet
thickness is more than 1.5mm Clay, k <1.0×10-5 cm/s thickness is
more than 5m
Technical Problems of Waste landfill Site in Seaport
Seawall Structures
・All works have to be done under sea water by machine.
・Sheet Pile → Cutoff at joint, Reliability of joint cutoff
・PVC or HDPE Sheet → Protecting layer in marine environment
In the case of inland landfill site, the protecting layer was
constructed by compacted clay layer.
・Earthquake-resistance of cutoff function of seawall structure
Added materials
Bentonite A: expansive in sea water condition
Bentonite B + Sodium Silicate
Niigata sand
Testing method
Consolidation Test
Permeability Test
Observation of micro-structure of soil by SEM and
Mercury Porosimeter
100
60
the gradation curve
NC
NS1
40 NS2
NS3
NS4
20 NS5
新潟砂
YC
0
0.001 0.01 0.1 1 10
粒径 D s (mm)
Mark Sample Bentnite Sodium Siligate Sand Arranged water
content
NC Nagoya clay None None None 130%(2wL)
YC Yokohama Clay None None None 180%
2.5
NC
NBA
NBB
2.0 YC
NC-k
e e
Ratio
NBA-k
間隙比
NBB-k
1.5 YC-k
Void
1.0 Permeability of
clay mixed with
bentonite
0.5
1.0E-09 1.0E-08 1.0E-07 1.0E-06
透水係数
Coefficient k (cm/s) k. (cm/s)
of permeability,
Nagoya clay Nagoya clay +bentonite Nagoya clay +sand
1.0
圧密試験後
3
圧密試験後 圧密試験後
3
0.8 0.8 0.8
Water Surface
Waste landfill
Reinforcement
Protecting layer
by geotextile
Clay guard
impermeable
clay layer
Sandy seabed
Design of Treated Clay
Determination of mix of
gelatification material
500m
Landfill area
Cross Section of Waste Disposal Site in Samukawa Port
220m
obtained. 新居浜港浚渫粘性土
Site at Site D
4.0
4.0
2) The target water content w* 西ポンド堆積粘性土
Soil at Site C
was calculated as, 3.53.5
東ポンド堆積粘性土
Soil at Site A
w* w e * 100 (%)
s 3.03.0
②目標間隙比e *
Void
間隙比 e
Void 2.5
3) The content of bentonite ratio,
ratio
2.5
埋立地中央部堆積粘性土
Soil at Site B
m* (g/cm3 or ton/m3) was e
e 2.0
2.0
calculated as,
1 w*
1.5
1.5
0 100 Target value of
Target value
w w * permeability
s 100 1.01.0 of permeability,
100 w ( s 0 ) s ( 0 w ) k
m* 0.50.5
s w s w -6 -5
*
1.0E-08 1.0E-07
w* 10-8 10-7 透水係数 k (cm/s) 101.0E-06 ①目標透水係数k 1.0E-05
10
10 -5
2.0
2.0
(kN/m2)
ゲル化材添加量=15 kg/m3
Content of sodium
ゲル化材添加量=10 kg/m3
1.5
1.5
silicate 25kg/m
ゲル化材添加量=5
3
kg/m3
ゲル化材無添加
20kg/m3
せん断強さ (kN/m2)
1.0
15kg/m3
10kg/m3
1.0
5kg/m3
0.5
0.5
None
0.0
0 0 7 14 21 28
0 7 14
経過日数 (日) 21 28
Guide Pipe
(φ800 steel)
Tremie Pipe
(8inch)
Valve for
control air pres. Lead
Tremie Pipe
打設状況(全景)
(8inch)
Clay Guard impermeable material
Construction of impermeable layer on sandy seabed in
Samukawa waste landfill site project
East Pond
(Stock Pond)
Mixing machine
GPS
Working Vessel
Antenna
tremie pipe
Flexible Pipe
Control room
Impermeable
Placing of artificial impermeable layer in sea water
(Samukawa Waste Disposal Site)
Summary 1
1. For most of the local communities, to ensure the final waste
disposal site is an urgent need. However, it is getting extremely
difficult to find a land for new disposal site inland, because
the agreement of the residents near the site would hardly be
obtained due to a lot of problems of waste disposal site such as,
transportation noise, flying dust, bad smell and especially
potential risk of ground water pollution. Due to these
circumstances, waste disposal sites located in seaport are
getting more and more important.