You are on page 1of 6

Picture-1 (Left) - A tall tower vessel resting on skirt and on Foundation.

Picture-2 (Right) - A small vertical vessel resting on legs and on fpundation.

Now you will follow the following steps to start the foundation load calculation
and design:

Step-1 :  Review of vessel drawing (Vendor Equipment Drawing)

You need to review Vessel drawings from foundation design point of view and
check whether you have all the following information:

 Vessel Erection weight       (De1):  


 Vessel Empty weight          (De2):    
 Vessel Operating weight    (Do):    
 Vessel Hydrotest weight     (Dt):     
 Wind Shear and Moment
 Seismic Shear and Moment (if the Project site is at Seismic zone)
 Total Height of vessel
 Vessel Center of Gravity location for Seismic load calculation and
application
 Anchor bolt location (Bolt circle Dia) with respect to center of vessel
and also bolt offset with respect to Plant North line.
 Anchor bolt supporting detail ( Anchor bolt size and  detail of anchor
chair)
 Base plate detail

Step-2 :  Verification of foundation location, elevation and external fittings loads

You need to review Plot plan, Equipment location drawings and  3 -D Models
and check whether you have all the  following information:

 Verify the area available for foundation.


 Verify Foundation location and Elevation
 Pipe supports and Nozzle loads on Equipment (Dp)
 Location and size of Platforms around the vessel
 Locations of underground pipes
 Electrical and Instrument duct banks
 Locations and extent of adjacent foundations
 Verify the location and extent of new/existing foundations not
shown in 3D model or plot plan.
Step-3 :  Description of Foundation Loads:

Please follow this section to understand the different loads on foundation:

Vessel Erection weight  (De1):  The erection weight is the fabricated weight of the
vessel, plus internals, platforms, etc., that are actually erected with the vessel. Data
from Equipment drawing.

Vessel Empty weight   (De2):  The empty weight is the in-place weight of the completed
vessel, including the fabricated weight of the vessel, plus the weight of internals, piping,
insulation, and platforms, but excluding the weight of fluids or products which will be
contained in the vessel during operation. Data from Equipment drawings.    

Vessel Operating weight  (Do):    Vessel Empty weight  (De2)  +  Weight of Fluid
inside the vessel. Data from Equipment drawings.

Vessel Hydrotest weight    (Dt):     Vessel Empty weight  (De2)  + Weight of test
water

Pipe supports and Nozzle loads on Equipment (Dp): Please Coordinate with the


Pipe Stress Group for determination of nozzle loads and loads due to pipe supports
attached to the vessel.

Wind Shear and Moment: You will find this load data in vendor drawings.
However, you have to calculate this load based on project design basis. During
wind load calculation, you need to consider the pipes and platforms attached
with the vessel. Compare both the data (vendor load data and your calculated
data) and apply the critical one for foundation design.

Seismic Shear and Moment (if the Project site is at Seismic zone): You will find
this load data in vendor drawings. However, you have to calculate this load
based on project design basis. During seismic load calculation, you need to
consider the pipes and platforms attached with the vessel. Compare both the
data (vendor load data and your calculated data) and apply critical one for
foundation design.

Step-4 :  Pedestal Sizing Criteria:

Concrete pedestals supporting vertical vessels shall be sized according to the


following criteria: 

Face-to-face pedestal size shall be the larger of the following:


(a)      Bolt circle + 175mm

(b)      Bolt circle + 8 x bolt diameters

(c)      Bolt circle + sleeve diameter + 150mm

(d)     Diameter of baseplate + 100mm

(e)     Bolt circle + 2 x (minimum bolt edge distance)

Pedestals having a diameter or least dimension across sides that is equal to or


greater than 1.5m shall be octagonal in shape.  All other pedestals shall be
square in shape.  For ease of forming, use multiples of 25mm for each
octagonal side or side of square.

 It is desirable to make the pedestal deep enough to contain the anchor bolts
and keep them out of the mat.

Step-5 :  Anchor Bolt Check:

Design of anchor bolts shall be based on the following considerations. Corrosion


allowance  should be considered when required by the project design  criteria.

Tension Check: 

The maximum tension force in the anchor bolts (Tmax) may be calculated
according with following formula:

Tmax  =  4*M / (Nb x BCD)  -  (De1 or De2) / Nb

Where,  M = total maximum moment on foundation


              BCD = Bolt circle diameter
               Nb = no. of anchor bolt

Use De1 or De2 whichever is critical.

The above formula provides a conservative value of Tmax compared to the


concrete transformed section method.

Shear Check:
When anchor bolts are utilized to resist shear, the unit shear per bolt shall be
calculated as follows:

Vmax = V / Nb    where, V = total shear force on anchor bolt.

When oversized anchor bolt holes are provided in the vessel base plates or
when anchor bolt sleeves that are not grout-filled are used, anchor bolts should
be designed to resist tension only. 

Frictional resistance to shear between the vessel base plate and the concrete or
grouted bearing surface shall be utilized to resist shears induced by wind or by
other static loads.  Frictional resistance shall not be employed to resist shear
induced by seismic loads.  For seismic-induced shear, adequate mechanical
means shall be provided to resist horizontal shear, either by means of properly
detailed anchor bolt / bolt hole arrangements or through a combination of
anchor bolts, shear lugs, or other anchorage devices.  The static coefficient of
friction between steel and concrete or between steel and cementitious grout
shall be considered as 0.4 or specified in project design criteria.

Tension Shear Interaction check:

When anchor bolts are subjected to combined shear and tension loads, the
design shall be based on satisfying  interaction formula (say Appendix-d of ACI
318).

Please note that anchor bolt edge distance, spacing and load capacity shall
be as per project design criteria.

Step-6 :  Load combinations for foundation sizing / Pile loads and  Foundation


design:

You need to create the load combination per your project design criteria.
However, I have created this load combination based on ACI 318:

Load combination for Foundation sizing and Pile load calculation (un-factored
load calculation): 

 LC1:  Do + Dp
 LC2:  (De1 or De2) + Wind
 LC3:  De2 + Seismic
 LC4:  Do + Dp + Wind
 LC5:  Do + Dp + Seismic
 LC6:  Dt + 025*Wind

Load combination for Pedestal and Foundation design (factored load


calculation): 

 LC7:  1.4*(Do + Dp)


 LC8:  0.75 [1.4 De2 (or 1.4 De1)] 1.6 Wind
 LC9:  1.2 De2 +1.0 E
 LC10:  0.75 (1.4 Do + 1.4 Dp)  1.6 Wind
 LC11:  1.2 (Do + Dp)  1.0 E
 LC12:  0.75 (1.4 Dt)   1.6 (0.25 W)

The weight of the foundation and of the soil on top of the foundation shall be
included as dead load in all of these load combinations.
 

Now from above steps, you have learnt the following:

 Different types of loads on foundation


 Different criterias  for the pedestal sizing
 Maximum tension and shear force on each anchor bolt
 A sample load combinations.

To complete the foundation design, your work will be to create following


calculation sheets:

o A calculation sheet for anchor bolt embedment length check (ex:


ACI 318 appendix-D).

o A calculation sheet for foundation sizing (considering soil bearing


pressure, Sliding, Buoyancy and overturning) or pile load (tension,
compression and shear on each pile) calculation and check with
soil consultant for acceptable values.

o A calculation sheet for foundation and pedestal reinforcement


calculation per your project design criteria.
 For typical Platform and foundation for a Vertical
Vessel / Tower click here  
Discussions:

Question from visitor: What is the reference of anchor bolt tension calculation
formula?
Answer from Subhro:  Refer "ASCE task committee on anchor bolt design" clause
#3.5.1.1 - vessel anchor bolt design.

Question from visitor: How do I calculate the wind load on vertical vessel?
Answer from Subhro:  Refer "Wind load and anchor bolts design for petrochemical
facility by ASCE"

I hope this page will be very helpful to you to understand the basic foundation
loads of a Vertical Vessel / Tower.

Please donate generously for more development of this site:

Copyright 2009. All rights reserved. Please do not print or copy of this page or any
part of this page without written permission from Subhro Roy.
Disclaimer: This page is prepared based on experience on Civil Engineering Design.
All definitions and most of the explanations are taken from different text books and
international design codes, which are referenced in the contents. Any similarity of the
content or part of with any company document is simply a coincidence. Subhro Roy is
not responsible for that.

You might also like