Professional Documents
Culture Documents
This is a classic Damn Interesting article which originally appeared on 12 April 2006
The concept as delivered by LeMessurier was quite sound, in fact it was elegant and
technically brilliant. At only 25,000 tons, the steel superstructure of the building was
remarkably light compared to other skyscrapers, such as the Empire State Building’s
60,000 ton skeleton. Because of the stilted design and low weight, his plans also included
a tuned mass damper, a 410-ton block of concrete housed in the upper floors of the
building, floating on a thick film of oil and controlled by an automatic system. This
substantial piece of stabilizing equipment was intended to cut the building’s sway in half
by converting the kinetic energy of swaying into friction.
LeMessurier first became aware of the building’s weakness in 1978, about a year after its
completion. An engineering student contacted him to ask some technical questions about
the design, which he was delighted to address. The student’s professor had expressed
doubts regarding the strength of a stilted skyscraper where the support columns were not
on the corners. “Listen, I want you to tell your teacher that he doesn’t know what the hell
he’s talking about,” LeMessurier told the student, “because he doesn’t know the problem
that had to be solved.” He went on to explain how the building’s framing geometry
worked perfectly with the stilts in such positions, allowing it to withstand very forceful
winds, even from a diagonal angle.
But the conversation got him thinking, and he started doing some calculations on just
how much diagonal wind the structure could withstand. He was particularly interested in
the effects of an engineering change made during construction which had seemed benign
at the time: numerous joints were secured with bolts rather than welds. Normally such a
change was acceptable, but the Citicorp Center’s design was unusually sensitive to
diagonal winds, which the builders hadn’t realized. The results of his calculations were
troubling.
He took his calculations to fellow engineer Alan Davenport, who was an expert on the
behavior of buildings in high-wind conditions. Davenport found that seventy-mile-per-
hour gusts would be sufficient to break the bolts holding the joints, resulting in structural
failure. Such winds were not unknown in New York, indeed storms with such strength
occurred about once every sixteen years on average. Hurricane season was fast
approaching, and now only two men in the world knew that Citicorp’s new $175 million
tower and its occupants were vulnerable to destruction by catastrophic collapse.
Horrified, LeMessurier fled to his island hideaway on Sebago Lake to refine the findings
and consider his options. Because he faced possible litigation, bankruptcy, and
professional disgrace he contemplated suicide, but he was struck with the realization that
he held the information to initiate extraordinary events which could save thousands of
lives. The following day he started making phone calls. After speaking with corporate
lawyers and consulting with Leslie Robertson– an engineer who helped design the World
Trade Center– LeMessurier went to Cambridge to inform Hugh Stubbins, Jr., the
building’s architect. Stubbins winced when he heard the news.
Together they flew to New York City to confront the executive officers of Citicorp with
the dilemma. “I have a real problem for you, sir,” LeMessurier said to Citicorp’s
executive vice-president, John S. Reed. The two men outlined the design flaw and
described their proposed solution: to systematically reinforce all 200+ bolted joints by
welding two-inch-thick steel plates over them.
Work began immediately, and continued around the clock for three months. Welders
worked all night, and carpenters labored during the day. In case of imminent disaster, an
evacuation plan was put in place for the surrounding area, but the general public knew
nothing of the circumstances… the press was on strike at that time, so news of the repairs
did not disseminate to the populace. About halfway into the repairs Hurricane Ella
formed, and it appeared to be on a collision course with Manhattan, but fortunately the
storm veered out to sea rather than testing the limits of the half-repaired building. The
reinforcements were completed in September of 1978, and the entire structure was re-
evaluated for safety. Following the repairs, the building was found to be one of the most
sturdy skyscrapers in the world. Despite the success, the crisis was kept hidden from the
public for almost twenty years, until an article appeared in the New Yorker in 1995.