Professional Documents
Culture Documents
The following Particular Conditions of Contract (PCC) shall supplement the General
Conditions of Contract and both shall be read together. Clauses of the General Conditions of
Contract not specifically amended or supplemented shall remain in effect.
Whenever there is a conflict, the provisions in the PCC shall prevail over the General
Conditions of Contract.
1 GENERAL PROVISIONS
1.1 DEFINITIONS
1.1.1 The Contract
1.1.1.4 Add the following at the end of the paragraph:
‘Letter of Tender’ is synonymous with ‘Letter of Bid’.
1.1.1.5 Add the following at the end of the paragraph:
The ‘Employer’s Requirements’ means the Technical Specifications
(General and Particular), the Technical data sheet forming Volume 3;
the Drawings and the Contract Documents and any additions and other
supporting documents modifications to such documents in accordance
with the contract.
1.1.1.6 Add the following at the end of the paragraph:
The ‘Schedule’ means the Schedule of Prices forming part of the tender
and Contract Documents.
1.1.1.8 Add the following at the end of the paragraph:
The word ‘Tender’ is synonymous with the word ‘Bid,’ the word
"Tenderer" with "Bidder", the word "Tendering" with "Bidding" and the
words "Tender Documents" with "Bidding Documents" and the words
‘Letter of Tender’ with ‘Letter of Bid’.
1.1.1.9 Add the following at the end of the paragraph:
The words ‘Appendix to Bid’ is synonymous with ‘Appendix to
Tender’.
1.1.2 Parties and Persons
1.1.2.2 Replace the whole text of this Sub-Clause with the following:
The ‘Employer’ means the Omega Energy Developer Pvt. Ltd.
1.1.2.4 Replace the whole text of this Sub-Clause with the following:
The “Engineer” is the Consultant appointed by the Employer, and will
act as ‘The Engineer’ for the purposes of this contract. The Contractor
will be notified in writing by the Employer in the event of any change
in the Engineer.
1
Particular Conditions of Contract (PCC)
1.1.2.12 ‘Other Contractors’ or ‘Others’ means any party or parties which have
a direct contract with the Employer for work related to this project
outside the scope of this Contract, including their subcontractors.
1.1.2.13 ‘Financier’ means the financing institution/s of the Project.
1.1.2.14 ‘Resident Engineer’ means an assistant to the Engineer who will be
resident on the Site and is appointed from time to time by the
Engineer under Sub-Clause 3.2 and notified to the Contractor.
1.1.4 Money and Payments
1.1.4.2 Replace the whole text with the following:
Contract Price’ means the sum stated in the Letter of Acceptance as
payable to the Contractor for the execution and completion of the
works subject to such additions thereto or deductions therefrom as
may be made under the provisions of the contract and remedying of
any defects therein in accordance with the provisions of the contract.
1.1.4.6 Replace the whole text with the following:
The Foreign Currencies’ mean/s United States Dollar (USD) or
Indian Rupees (INR) or Nepalese Rupees, in which part of the
Contract Price is payable.
1.1.4.8 Replace the whole text with the following:
‘The Local Currency’ mean/s the Nepalese Rupee (NRs).
1.1.6 Other Definitions
1.1.6.2 Replace the whole text with the following:
The Country means Nepal
1.1.6.7 Replace the whole text with the following:
‘Site’ means the places where the Permanent Works are to be
executed, including access roads, site installations, workshops,
storage and working areas, and to which Plant and Materials are to be
delivered, and any other places as may be specified in the Contract as
forming part of the Site.
1.2 INTERPRETATIONS
1.3 COMMUNICATIONS
When a notice is issued to the Engineer by the Contractor, a copy shall be sent
to the Employer, in respect of the followings and also in other cases stated
elsewhere in the Contract:
(i) claims as per Sub-Clause 1.9, 4.12, 4.24, 16.1, 17.4, 19.4;
(ii) delivery to Site of Plant or other major items as per Sub-Clause
4.16;
(iii) prolonged suspension as per Sub-Clause 8.11;
(iv) variation requests as per Sub-Clause 13.1 and Value Engineering
as per Sub-Clause 13.2; and
(v) application for a Taking-Over Certificate as per Sub-Clause 19.1.
The Contract shall in all respects be read and construed in conformity with the
laws of Nepal.
The Contract shall be construed and interpreted according to the English
language, which shall be the language for all communications between the
Employer, the Engineer and the Contractor, as well as for all contract
documents, technical information and data, literature, books, drawings,
standards, test data, instructions, directions, and all documents,
correspondence, or submittals.
Delete the documents listed as (a) to (h) in the sub clause and substitute the
following:
4
Particular Conditions of Contract (PCC)
1.6 CONTRACT AGREEMENT
The Base Date, the Accepted Contract Amount and, if known at the time of
signing the Contract Agreement, the Commencement Date and the Completion
Date shall be entered into the Contract Agreement.
1.7 ASSIGNMENT
‘The Contractor shall supply to the Engineer and the Employer the number and
types of Contractor’s documents as stipulated in the Technical Specifications
or elsewhere in the Contract, but shall otherwise supply a minimum of two
copies of the Contractor’s Documents to the Employer together with one copy
of the electronic version thereof and three copies to the Engineer together with
one copy of the electronic version thereof.
In addition to any other Contractor’s Documents necessary under the Contract,
the Contractor shall be responsible for the preparation of detailed
manufacturing and installation drawings, subject to the Engineer’s approval, in
accordance with the Specifications using AutoCAD software (with approved
version) based on the drawings issued in the Tender documents and any other
drawings as may be issued from time to time by the Engineer. Such detailed
manufacturing and installation drawings shall include, detailed drawings for
Mechanical, Electrical and Hydro-mechanical components.
In accordance with the Specifications, the Contractor’s Documents shall also
include all necessary detailed calculations for the Permanent Works as well as
all Temporary Works (please delete TemporaryWorks Works) including
manufacturing and installation stages, subject to the Engineer’s approval.
In the preparation of the calculations and drawings, the Contractor shall
anticipate and be responsible for updating the Contractor’s Documents to
incorporate the following;
- Changes to suit modification arising from the encountered conditions
revealed during construction, including instructions issued by the
Engineer;
5
Particular Conditions of Contract (PCC)
- Drawing revisions issued by the Engineer and/or other contractors
required by the construction of the Civil Works and Hydro-mechanical
Works and arising from the specified liaison with other contractors.
The Contractor shall also be responsible for the preparation and submission for
approval of “as-built” drawings and documents for the Works as finally
constructed, subject to the approval of the Engineer.
All such Contractor’s Documents shall be subject to the approval of the
Engineer and the Employer prior to commencement of work covered by the
drawings and documents, and in his planning of the work the Contractor shall
allow 1430 d days for obtaining the approval or detailed comments of the
Engineer.
“Each of the Parties shall treat the Contract Document and details of the
Contract as private and confidential, except to the extent necessary to carry out
their respective obligations under the Contract or to comply with applicable
Laws and save insofar as may be necessary for the purposes of the Contract.
Each of them shall not publish or disclose any particulars of the design and of
the Works prepared by the other Party without the prior consent of the other
Party. However, the Contractor shall be permitted to disclose any publicly
available information, or, with the prior consent of the Employer, information
otherwise reasonably required to establish its qualifications to compete for
other projects. If any dispute arises as to the necessity of any publication or
disclosure of the details of the Contract, the same shall be referred to the
Employer whose determination shall be final. The Contractor shall ensure that
the requirements imposed on the Contractor by this Sub-Clause apply equally
to each Subcontractor.”
6
Particular Conditions of Contract (PCC)
Applicable law shall be the prevailing laws of Nepal and the Contract shall in
all respects be read and construed in conformity with the Laws of Nepal.
2 THE EMPLOYER
2.2 PERMITS, LICENSES OR APPROVALS
The Contractor shall be responsible for obtaining all import permits, licenses or
approvals etc. for his own machinery only and contractor’s equipment, and the
Employer shall not incur any liability towards the Contractor except for
issuance of P.B.G on behalf of contractor whose bank issuance charges may be
debited to the contractor..
The Contractor shall inform the Engineer and Employer in writing of the
details of the Equipment, Plants and Materials to be imported into Nepal for
the use on the Works at least 4556 days prior to arrival of shipment at
disembarkation port, and shall submit a formal written request for assistance
from the Employer for importation processing for contractor’s equipment.
The Employer will assist the Contractor to obtain the necessary permits for the
imports into Nepal. Import license fees or any other charges shall be at the cost
of the Contractor. The Contractor shall be responsible for all transport,
including from the point of entry into Nepal to the Site or location of the
Works.
The Contractor shall determine and be fully responsible for payment of all
import licenses, fees or other such charges as may be imposed by the local or
any en-route customs authorities for his own machinery, plants and equipment.
However, in case of any provisional bank guarantee is to be provided for
import of machinery, the same will be provided by Employer and all the costs
incurred for issuance of the same shall be deducted from the contractor.
3 THE ENGINEER
3.1 ENGINEER’S DUTIES AND AUTHORITY
Amend Sub-Clause 3.1 by replacing the word “may” in the first sentence of the
third paragraph with the word “shall”.
7
Particular Conditions of Contract (PCC)
The Employer undertakes not to impose further constraints on the Engineer's
authority, except as agreed with the Contractor.
The Employer will promptly inform the Contractor of any change to the
authority attributed to the Engineer.
“The Engineer shall obtain the specific approval of the Employer before taking
any of the following actions under the-following Sub-Clauses of these
Conditions:
(i) Sub-Clause 4.4 [Subcontractors]: consenting to the subcontracting of any
part of the Works, and approval of the relevant subcontractors, under Sub-
Clause 4.4;
(ii) Sub-Clause 4.12 [Unforeseeable Physical Conditions]: Agreeing to or
determining an extension of time and/or additional cost;
(iii) Sub-Clause 8.4 [Extension of Time for Completion]: Agreeing to or
determining an extension of time;
(iv) Sub-Clause 8.8 [Suspension of Work]: Instructing the Contractor to
suspend the progress of the Works under Sub-Clause 8.8 which would be
liable to give rise to a determination under Sub-Clause 8.9;
(v) Sub-Clause 10.1 [Taking Over of the Works and Sections]: Issuing a
Taking oOver Certificate-
Not Applicable
(vi) Sub-Clause 13.1 [Right to Vary]: Instructing a Variation-Not Applicable
(vii) Sub-Clause 13.3 [Variation Procedure]: Approving a proposal for
Variation submitted by the Contractor in accordance with Sub-Clause 13.1
[Right to Vary] or 13.2 [Value Engineering],-Not Applicable
(viii) Sub-Clause 20.1 [Contractor’s Claims]: Determining an additional
payment for Claims-Not Applicable
Notwithstanding the obligation, as set out above, to obtain approval, if, in the
opinion of the Engineer, an emergency occurs affecting the safety of life or of
the Works or of adjoining property, he may, without relieving the Contractor of
any of his duties and responsibility under the Contract, instruct the Contractor
to execute all such work or to do all such things as may, in the opinion of the
Engineer, be necessary to abate or reduce the risk. The Contractor shall
forthwith comply, despite the absence of approval of the Employer, with any
such instruction of the Engineer. Within 7 days of having issued such
emergency instructions, the Engineer shall submit written documentation of
8
Particular Conditions of Contract (PCC)
such instructions to the Employer. The Engineer shall determine an addition to
the Contract Price, in respect of such instruction, in accordance with Clause 13
[Variations and Adjustments] and shall notify the Contractor accordingly, with
a copy to the Employer together with the justification of emergency
occurrence.
The Engineer will coordinate the activities of the various contractors working
at the site. In addition to this Lot 02 Hydromechanical Works Contract, the
Employer has tendered or will tender contracts for, but not limited to the
following:
Lot 03 - Construction of Civil Structures
Lot 05 - Electromechanical Works
Lot 06 - Transmission Line and Interconnection Works
The Contractor will be expected to cooperate with the other contractors and to
furnish support facilities specifically called for in the Specifications.
(To be specified). In addition, each contractor must afford to the others, safe
and reasonable access, clean and clutter free work areas, temporary services
called for in the Specifications, space in construction yards for storage, pre-
fabrication yards and pre-assembly of materials and equipment, such other
cooperation and assistance as may be reasonably implied. The Engineer will
conduct regularly scheduled coordination meetings amongst those contractors
requiring interfacing, and the Engineer will endeavor to keep each contractor
adequately informed as to schedule, impending activities, and assistance
required by other contractors, all to the extent required by the Work. The
Contractor will be expected to participate in all coordination meetings when
and as requested by the Engineer and will be expected to comply with the
subsequent implementation of all activities agreed to as arising therefrom. In
the event disputes arise between contractors, either during the coordination
meetings or subsequent implementation of activities, the Engineer will issue
instructions in writing as specified under this Sub-Clause 3.1.
4 THE CONTRACTOR
4.1 CONTRACTOR’S GENERAL OBLIGATIONS
The Contractor shall, in accordance with the Contract, with due care and
diligence, complete the Works within the Time for Completion. In the event
that an item mentioned in the Schedule of Price fall short in the description of
one or more of its components, but such components are deemed necessary for
that item to serve the purpose it was intended to, then the Contractor is
compelled under this Contract to execute such item complete will all its
components that would guarantee its functionality, and to do so with no
additional cost and with no extra time allowance.
Replace the first two paragraph of this Sub-Clause with the following:
The Contractor shall obtain at his own cost a Performance Security for his
proper performance under the Contract in the amount of the percentage of the
Accepted Contract Amount stipulated in the Appendix to Tender. The
Contractor shall deliver the Performance Security to the Employer within 21
days after signing of the detailed contract agreement and shall simultaneously
submit a copy to the Engineer.
10
Particular Conditions of Contract (PCC)
The Performance Security shall be in the form of irrevocable either from a
Nepalese Bank or from a Foreign Bank, as stipulated by the Employer in the
Volume 1 Part 7 Contact Forms.
The bank guarantee shall be issued by a class “A” commercial bank located in
Nepal or by a foreign bank counter guaranteed by a class “A” commercial bank
acceptable to the Employer located in Nepal. The foreign bank issuing the
Performance Security must have as a minimum of an “A” Rating determined
by one of the following rating agencies: Moody’s, Standard and Poor’s, Fitch
or DBRS (Dominion Bond Rating Service). The Performance Security shall be
denominated in the types and proportions of currencies in which the Contract
Price is payable.
Without limitation to the provisions of the preceding paragraph, whenever the
Engineer determines an addition to the Contract Price as a result of a change in
cost and/or legislation or as a result of a variation amounting to more than 25%
of the portion of the Contract price payable in a specific currency, the
Contractor, at the Engineer’s written request, shall promptly increase the value
of the Performance Security in that currency by equal percentage. The
Performance Security of a joint venture shall be in the name of the joint
venture.
11
Particular Conditions of Contract (PCC)
4.4 SUBCONTRACTORS
In order to obtain the Engineer’s consent pursuant to (b) above, the Contractor
shall submit an application to use these Subcontractors together with all
necessary supporting documents, which shall also include not less than the
following information for each Subcontract to the satisfaction of the Engineer:
(i) The name, address, telephone and fax numbers and email address of the
Sub-Contractor;
(vi) Confirmation that the proposed Subcontract agreement includes all the
necessary terms and conditions and covers all obligations and
responsibilities contained in the Contract in so far as these apply to the
Subcontractor including with respect to assignment and subcontracting
and the requirement for the Engineer’s prior consent thereof.
In the event of approved subcontracting the Contractor shall ensure that the
Subcontractor does not further sub-let his Subcontract. The Contractor shall be
responsible for keeping a log showing following information of all
Subcontractors engaged in the Works:
Name and address of the Subcontractors
Date of Subcontract
Works included in the Subcontract
Commencement of Subcontract
Completion of Subcontract
Value of Subcontract
Payment
12
Particular Conditions of Contract (PCC)
The Contractor shall include in his monthly reports to the Engineer details of
all Subcontracts entered into, the names of the Subcontractors concerned, and
the numbers and types of staff and labour from each Subcontractor present on
Site during the month.
If requested by the Engineer, the Contractor shall provide copies of any
documents such as wage sheets and details of the names and employment
references for the Subcontractor's staff and labour on Site, invoices for the
supply of materials to be used by the Subcontractor, etc.
4.6 CO-OPERATION
13
Particular Conditions of Contract (PCC)
4.7 SETTING OUT
Delete the following words from the second paragraph of this Sub-Clause:
‘’but the contractor shall use reasonable efforts to verify their accuracy before
they are used. However, final points shall be considered as given by the
Employer.’’
“The Contractor shall notify the Engineer and Employer within 48 hours or as
soon as reasonably possible after the occurrence of any accident which has
resulted in damage or loss of property, disability or loss of human life, or
which has or which could reasonably be foreseen to have a material impact on
the environment and shall submit to the Engineer and Employer no later than
28 days after the occurrence of such an event, a summary report thereof.”
The Contractor acknowledges that he has satisfied himself as to the nature and
location of the Works and the general and local conditions, including but not
limited to those bearing upon transportation, disposal, handling and storage of
Goods, availability of water, roads, access to the site, coordination with other
contractors, and conflicts, if any. Any failure by the Contractor to become
acquainted with the available information and existing conditions shall not be a
basis for relief from successfully performing the Works and shall not, in any
case whatsoever, constitute for additional compensation.
The Employer shall provide necessary access to all areas at site for execution
and completion of the works as requested by the contractor.
If the Contractor finds discrepancies in or omissions from the Contract
Documents, or if the Contractor is in doubt as to their meaning, the Contractor
shall notify the Engineer or his authorized representative. The Contractor shall
not proceed without direction in writing from the Engineer or his authorized
representative.
If the Contractor considers it necessary for his own purposes, in order to fulfill
his obligations under the Contract and execute the Works, he may conduct,
after seeking and obtaining approval from the Engineer, additional site
14
Particular Conditions of Contract (PCC)
investigations including subsurface investigations. A copy of the interim and
final records, test results and reports from all such additional site investigations
shall be submitted to the Engineer within 7 days of their receipt by the
Contractor. Such activities shall be carried out without prejudice, by the
Contractor on its own.
15
Particular Conditions of Contract (PCC)
• Cost of bank guarantees or payment or other surety securities required
under this Contract.
• Any kind of taxes, duties, charges, surcharges in Nepal or abroad for
contractor’s equipment or machinery whether stipulated in the Contract
documents or not and as may be required.
• Cost of any freight for imported materials including sea-worthy and/or
tropicalized packing, if required, and all other handling, and transport to
the Site of labor, materials, supplies, equipment, plant, etc.
•
• Cost of environmental protection measures, monitoring and reporting, and
all health and safety measures which are in addition to those items in the
Price Lists and as may be required in accordance with any regulations-Not
Applicable
• All expenses for royalties, licenses, liabilities and the like in connection
with the Works. Not Applicable
• Services for normal and/or specified material tests (including laboratory tests). The
particular tests will be fixed by the Engineer and shall be executed in approved laboratories.
• Cost of field surveys. The required points of reference and benchmarks
will be indicated by the Engineer. Not Applicable
• Cost of all other Contractor's obligations under this Contract.
• Site, head office and other support office overheads and profits.
All Contract prices shall be fixed for the duration of the Contract.
At the end of the second paragraph of this Sub-Clause add the following:
16
Particular Conditions of Contract (PCC)
‘The Contractor shall reinstate only damaged properties whether public or
private which are damaged in consequence of the execution and/or
maintenance of the Works to a condition as specified and at least equal to that
existing before his first entry on them.
If in the opinion of the Engineer the Contractor shall have failed to take prompt
action with respect to his obligations in the matter of reinstatement, the
Engineer will inform the Contractor in writing of his opinion, with a copy to
the Employer, in which circumstances the Employer reserves the right to
employ others to do the necessary reinstatement work and to deduct the cost
thereof from any money due or which shall become due from the Employer to
the Contractor.’
(d) The Contractor shall deliver and store products, materials and equipment in
accordance with manufacturer’s recommendations and by methods and means
that will prevent damage, deterioration and loss including theft. Delivery
schedules shall be controlled to minimize long-term storage of products at site
and overcrowding of construction spaces. In particular, the Contractor shall
ensure coordination to warrant minimum holding or storage times for
flammable, hazardous, easily damaged or sensitive materials to deteriorate or
be subject to theft and other sources of loss.
Re-handling costs or midway storage costs due to any reason whatsoever shall
be borne by Employer.
17
Particular Conditions of Contract (PCC)
4.17 CONTRACTORS EQUIPMENT
18
Particular Conditions of Contract (PCC)
4.18 PROTECTION OF THE ENVIRONMENT
BEFORE THE START OF THE FIRST PARAGRAPH OF THIS SUB-CLAUSE ADD THE
FOLLOWING HEADING:
GENERAL REQUIREMENT
NOT APPLICABLE
19
Particular Conditions of Contract (PCC)
THE PURPOSE OF THE EMP IS TO IDENTIFY AND ADDRESS ALL MODERATE
TO SIGNIFICANT NEGATIVE IMPACTS ON THE ENVIRONMENT ARISING FROM
ACTIVITIES UNDER THE CONTRACT, TO ENSURE THAT THE IMPACTS ARE
PREVENTED OR MITIGATED, OR THAT RESIDUAL IMPACTS ARE CONFINED TO
A SHORT PERIOD, AND TO SPECIFY THE ACTIONS TO BE IMPLEMENTED BY
THE CONCERNED PARTY INDICATED TO HAVE THE RESPONSIBILITY.
20
Particular Conditions of Contract (PCC)
A TIME SCHEDULE AND ASSIGNMENT OF RESPONSIBILITY FOR THE
MONITORING ACTIVITIES, AND PROCEDURES FOR DETERMINING WHEN
MITIGATION MEASURES ARE TO BE IMPLEMENTED;
GENERAL REQUIREMENTS
CONTROL OF NOISE
WITHIN 120 DAYS AFTER THE COMMENCEMENT DATE THE CONTRACTOR SHALL
PREPARE AND SUBMIT THE DRAFT EMP TO THE ENGINEER WITH A COPY TO THE
EMPLOYER FOR REVIEW. WITHIN 14 DAYS AFTER RECEIVING THE DRAFT EMP
AFTER DUE CONSULTATION WITH THE EMPLOYER THE ENGINEER SHALL SUBMIT
TO THE CONTRACTOR ANY REQUESTS FOR AMENDMENT WITH RESPECT TO THE
DRAFT EMP. THE CONTRACTOR SHALL INCORPORATE THE AMENDMENTS
REQUESTED AND SHALL ISSUE THE FINAL EMP FOR THE CONTRACT.
(NOT APPLICABLE)
Delete the whole text of this Sub-Clause and substitute by the following:
The contractor shall be responsible for the provision of all construction power
and other services he may require during the construction and erection of
equipment.
The Contractor shall, at his own cost other than in accordance with any
arrangement which may be stipulated in the Specification, be responsible for
the provision of all construction power, and other services he may require.
No separate payment shall be made for the cost of construction power, water
and gas. It shall be deemed to be covered by related items.
Employer shall supply water free of cost however the accessories required for
water supply Water Supply shall be arranged and supplied by Employer to the
by contractor Free of Cost.
The Contractor shall keep a Site Diary wherein full details of all work carried
out each day shall be recorded. The Site Diary may be prepared in sections
relating to different parts of the works being carried out in different locations.
The Site Diary shall be available for inspection by the Engineer any time
during normal office hours.
The Contractor shall submit before 2:00 pm daily ‘Daily Site Report’ of the
preceding day to the Engineer in an approved format. The Daily Site Report
shall be well organized and legible ad shall include at least the following:
23
Particular Conditions of Contract (PCC)
• By nationality
(i) Major equipment in use,
(ii) Quantities and description of work completed,
(iii) Problems, and
(iv)Contractors 4-week schedule
(v) The contractor shall prepare monthly progress report each month and shall
be submitted to the Engineer in three suitably bound hard (paper) copies in
a format approved by the Engineer and additionally as readable electronic
files, complete with all supporting documents and information as required
by this Sub-Clause. Charts, diagrams, photographs, graphics etc. which in
original are in colour shall be reproduced in all the copies also in colour.
Each monthly progress report shall also be submitted to the Employer in two
similarly bound copies in the same format approved by the Engineer and
additionally one copy as readable electronic files. The reports submitted to the
Employer shall be complete with all supporting documents and information in
all respects similar to the copies to be submitted to the Engineer.
Each monthly report shall include the contents listed in the General Conditions
and additionally shall include at least the following:
(i) record of managerial and superintendence staff on Site during the month,
with names and designations;
(ii) monthly report on Quality Assurance System;
(iii) record of equipment import / re-export shipments;
(iv)monthly Critical Items report;
(v) record of statements and payment certificates to date;
(vi)statement of anticipated Contract Price based on approved, requested and
forecast changes.
The electronic version submitted shall include the updated complete electronic
files from the current Critical Path Method (CPM) design, manufacturing,
delivery, installation programme. The Engineer and the Employer shall be able
to access all information contained within the Contractor's electronic CPM
design, manufacturing, delivery, installation programme without restriction.
In case within 7 days of the receipt of any monthly report the Employer or the
Engineer notifies the Contractor of any discrepancies, omissions or errors in
the report, the Contractor shall promptly correct the report accordingly and
resubmit to the Employer and the Engineer no later than 7 days following such
notification (Not Applicable)
The Contractor shall give notice to the Engineer at the earliest opportunity of specific likely
future events or circumstances which may adversely affect the Works, increase the Contract
Price or delay execution of the Works. The Engineer may require the Contractor to submit
an estimate of the anticipated effect of the future event or circumstances, and/or a proposal
24
Particular Conditions of Contract (PCC)
under Sub-Clause 13.3 [Variation Procedures]. The Contractor shall submit such estimate
and/or proposal as soon as practicable. The Contractor shall co-operate with the Engineer
in making and considering proposals to mitigate the effect of any such event or
circumstances, and in carrying out instructions of the Engineer.
The Contractor shall treat the details of the Contract as private and confidential, save
insofar as may be necessary for the purposes thereof and shall not publish or disclose the
same or any particulars thereof in any trade or technical paper or elsewhere without the
prior written consent of the Employer. If any dispute arises as to the necessity of any
publication or disclosure for the purpose of the Contract the same should be referred to the
Employer whose determination shall be final.
(Not Applicable)
5 DESIGN
5.2 CONTRACTOR'S DOCUMENTS
Provided that the Engineer has, during each review period for any single
Contractor's Document, complied with the requirement to give notice to the
Contractor within 21 days that the submitted item fails (to the extent stated) to
comply with the Contract, the Contractor shall be responsible for any delays or
additional costs which may be incurred as a result of the overall review
procedure for that item of the Contractor's Documents exceeding a period of 42
days, irrespective of the number of review periods therein.
25
Particular Conditions of Contract (PCC)
5.6 AS-BUILT DOCUMENTS
Delete the following words from the third paragraph of this Sub-Clause:
the Contractor shall supply to the Engineer the specified number and types of
copies of the relevant as-built drawings
the Contractor shall supply at his own cost to the Employer and Engineer the
specified number and types of copies of the relevant as-built drawings
26
Particular Conditions of Contract (PCC)
6.1 ENGAGEMENT OF STAFF AND LABOR
The Contractor shall be responsible for the return to the place where they were
recruited, or to their domicile, of all persons that he has recruited and employed
for the purposes of or in connection with the Contract and shall maintain such
persons as are to be so returned in a suitable manner until they have left the
Site or, in the case of persons who are not nationals of and have been recruited
outside Nepal, have left Nepal.
The Contractor shall make any necessary arrangements for the transport, to any
place required for burial, of any of his expatriate employees or members of
their families who may die in Nepal. The Contractor shall also be responsible
for making any arrangements with regard to burial of any of his local
employees who may die while engaged upon the Works.
The Contractor shall be solely responsible for recruiting his labor force and
satisfying the relevant obligations under the Contract and the regulations and
laws in force in Nepal. It is nevertheless a requirement that the Contractor
shall, to the extent practicable and subject to the availability of suitable
candidates, employ staff and labor for the Works with the required
qualifications and experience from the surrounding districts of the Project.
The Contractor is encouraged to recognize that, in order to maintain good
community relations as required under the Contract, to the extent that suitable
options for recruiting labor locally exist and provided that other selection
factors are equal he should make every reasonable effort to recruit his
workforce according to the priorities of the local population and in particular
those affected directly by the Project. These priorities should follow the order
of preference of sources for recruitment as given by the following list:
(i) Seriously Project Affected Families (SPAFs)
(ii) Project Affected Families (PAFs)
(iii) Persons from villages directly affected by land expropriation for the
Project
(iv)Lists of the families designated as SPAF and PAF will be provided by the
Employer at the Contractor's request.
(v) In addition, the Contractor shall fulfil the following conditions:
a. The Contractor shall not employ any workman who are suffering
from an infectious disease or are known to be carrying of an
infectious disease and shall if so required have all workmen
engaged on the construction of water-works certified by a medical
officer acceptable to the Employer as a non–carrier of any water
borne disease.
b. Notice shall be posted in conspicuous places and workplaces
concerned to inform the workers of the conditions of work provided
by the Contract.
27
Particular Conditions of Contract (PCC)
c. The Contractor shall be responsible for keeping discipline on the site
and shall obey all policy, labor, health and municipal regulation and
all other regulations that may from time to time require his
observance and he shall instruct his agent, subcontractors and other
employees accordingly. The Contractor shall indemnify the
Employer in respect of all claims that may be made against the
Employer of non-compliance thereof by the Contractor.
d. The Contractor shall keep proper wages books and such other
records as are required by any prevailing Laws of Nepal governing
the employment of labor.
(Not Applicable)
The Contractor shall pay rates of wages and observe conditions of labor not
less favorable than established by the District Development Committee office
where the work is carried out(Not Applicable). In the absence of any rates of
wages or conditions of labor so established, the Contractor shall pay rates of
wages and observe conditions of labor which are not less favorable than the
general circumstances in the trade or industry in which the Contractor is
engaged.
The Contractor shall in dealing with his staff and labor have due regard to all
recognized festivals, days of rest and religious or other customs.
The Contractor shall not recruit or attempt to recruit any personnel and labor
from among persons in the service of the Employer or the Engineer.
Furthermore, if any personnel who is retired or terminated from the service of
the Employer or the Engineer, the Contractor shall not hire the said personnel
within two years of his/her retirement or termination from the Employer or the
Engineer. The foregoing provision shall not exclude the Contractor from
recruiting by means of advertisements place in general circulation media for
any other technical or skilled personnel including engineers required for the
execution of the Works.
The Contractor shall at all times take all reasonable precautions to prevent any
unlawful, riotous or disorderly conduct by or amongst his staff and labor and
28
Particular Conditions of Contract (PCC)
for the preservation of peace and protection of person and property in the
neighborhood of the Works. The Contractor is obliged to notify immediately to
the Engineer of any labor conflict or riot faced by him or his subcontractors
that could influence the progress of the Works.
The Contractor shall be responsible for making all arrangements for and shall
bear all costs relating to the obtaining of all necessary visas, permits,
documents or other official permission for the movement of staff or labor from
place to place and from one country to another as may be necessary for the
purposes of or in connection with the Works.
The Contractor shall be responsible for observance by his sub-contractors of
the provisions for this Sub-Clause.
The cost of complying with this Sub-Clause and of complying with any
relevant laws and regulations in force in Nepal, at the time 28 days before the
submission of the Bid, is to be included in the Accepted Contract Price
The Contractor shall provide and maintain such accommodation and amenities
as he may consider necessary for all his staff and labor, employed for the
purposes of or in connection with the Contract, including water supply (both
for drinking and other purposes) (to be provided by Employer),, electricity
supply, sanitation, cookhouses and other requirements in connection with such
accommodation or amenities. On completion of the Contract, unless otherwise
agreed with the Employer, the temporary camps/housing provided by the
Contractor shall be removed and the site reinstated to its original condition(Not
Applicable), all to the approval of the Engineer.
At his own cost, the Contractor shall at all times take all reasonable precautions
to maintain the health and safety of the Contractor's Personnel. In collaboration
with local health authorities, the Contractor shall ensure that medical staff, first
aid facilities, medicines and sick bay, ambulance service and evacuation
service are available at all times at the Site and at any accommodation for
Contractor's, Employer's and Engineer’s Personnel, and that suitable
arrangements are made for all necessary welfare and hygiene requirements and
for the prevention of epidemics. In the event of any outbreak of disease of an
epidemic nature, the Contractor shall comply with and carry out such
regulations, orders and requirements as may be made by the Government, or
the local medical or sanitary authorities, for the purpose of dealing with and
overcoming the same. The Contractor shall report the outbreak of any epidemic
to the local health authorities as soon as he becomes aware of such epidemic.
The medical staff of the Contractor or any of his Subcontractors shall be
subject to the requirements of the applicable law for registration as practising
medical personnel and shall be fluent in spoken and written English language
29
Particular Conditions of Contract (PCC)
to the satisfaction of the Engineer as well as in the languages of Nepal and the
country of origin of the Contractor's labour as appropriate.
The Contractor shall appoint an Accident Prevention Officer at the Site,
responsible for maintaining safety and protection against accidents. This
person shall be qualified for this responsibility, and shall have the authority to
issue instructions and take protective measures to prevent accidents.
Throughout the execution of the Works, the Contractor shall provide whatever
is required by this person to exercise this responsibility and authority.
The Contractor shall immediately inform the Engineer of the occurrence of any
accident at or about the Site or in connection with the execution of the Works,
and within 24 hours of the occurrence shall submit a report of the accident to
the Engineer. The Contractor shall also report such accident to the competent
authority wherever the applicable law requires such reporting.
The Contractor shall take adequate measures and maintain the safety and
welfare of his employees at work, including those of his Subcontractors. The
responsibility of the Contractor shall include, but not be limited to:
(a)Dissemination of safety instructions, information and measures to be
undertaken at site to the extent that his employees become conversant
with it;
(b) Provision of all stipulated facilities, equipment, procedures and training
of personnel in compliance with the requirements of the Specifications;
(c)Maintenance of such records and making such reports concerning the
safety, health and welfare of persons and damage to property as the
Engineer may from time to time prescribe.
The Contractor shall at all times take the necessary precautions to protect all
staff and labor employed on the Site from insect nuisance, rats, and other pests
and reduce the dangers to health and the general nuisance caused by the same.
If necessary, the Contractor shall provide his staff and labor with suitable
prophylactics for the prevention of related diseases, and shall comply with all
the regulations of the local health authorities in these respects including the
appropriate use of approved insecticides.
The Contractor shall conduct an HIV-AIDS awareness program in the project
areas as required by the approved EMP via an approved service provider, and
shall undertake such other measures as are specified in the Contract to reduce
the risk of the transfer of the HIV virus between and among the Contractor’s
Personnel and the local community, to promote early diagnosis and to assist
affected individuals.
The Contractor shall make all necessary arrangements for the transport, to any
place as required for burial, of any of his expatriate employees or members of
their families. The Contractor shall also be responsible, to the extent required
by the local regulations, for making any arrangements with regards to the
funeral and burial of any of his local employees who may die while engaged
upon the Works.
(Not Applicable)
6.8 Contractor’s Superintendence
30
Particular Conditions of Contract (PCC)
At the end of this Sub-Clause add the following paragraphs:
All staff and labor on the Site shall be provided with identification as follows:
(a) Identification cards incorporating the name, position and photograph of
the person and the name of the direct employer (Contractor,
Subcontractor, etc.).
(b) hard hats with the name of the direct employer.
The Contractor shall be responsible for the observance of the provisions of this
Sub-Clause by all Subcontractors employed by him in the execution of the
Contract.
31
Particular Conditions of Contract (PCC)
6.15 MEASURES AGAINST INSECT AND PEST NUISANCE
The Contractor Employer shall at all times take the necessary precautions to
protect the Contractor’s Personnel employed on the Site from insect and pest
nuisance, and to reduce the danger to their health. The Contractor Employer
shall comply with all the regulations of the local health authorities, including
use of appropriate insecticide.-To be provided by Employer
32
Particular Conditions of Contract (PCC)
worked and wages paid to all workers. These records shall be summarized on
a monthly basis and submitted to the Engineer, and these records shall be
available for inspection by auditors during normal working hours. These
records shall be included in the details to be submitted by the Contractor under
Sub-Clause 6.10 [Records of Contractor’s Personnel and Equipment].
The Contractor shall submit for approval of the Engineer, his detailed method
statement for the execution of such items of work as may be desired by the
Engineer. Approval of such method statement shall neither relieve the
Contractor of his responsibilities under the Contract nor form any basis for
claiming additional costs. As such, the Contractor shall sequence and schedule
33
Particular Conditions of Contract (PCC)
work such that critical work elements are completed without major
interruptions in the progress of the Project.
7.8 ROYALTIES
The Contractor shall be liable for all payments of compensation, if any, levied
in relation to the dumping and/or disposal of any materials, in accordance with
any and all local authorities according to the local self-governance Act (2055
B.S.), local self-governance Regulations (2056 B.S.) or other such laws of
Nepal as are applicable.
The Employer or the Engineer shall give the Contractor not less than 7 days'
notice of the Commencement Date. The Commencement Date shall be the date
at which the following precedent conditions have all been fulfilled to the
satisfaction of the Engineer and the Employer or the Engineer’s notification
recording the agreement of both Parties on such fulfilment and instructing to
commence the Work is received by the Contractor:
(i) The Contract Agreement has been duly signed by the Parties
concerned;
(ii) The Contractor has submitted to the Employer the Performance
Security in accordance with Sub-Clause 4.2
(iii) The detailed programme of work in accordance with Sub-Clause 8.3
has been submitted by the Contractor to the Engineer for approval;
(iv) In case the Contractor is a Joint Venture of more than one Partner, the
final Joint Venture Agreement has been submitted by the Contractor
and approved by the Employer.
(v) Advance Payment has been released by the Employer to the contractor
and receipt of the same is acknowledged by the contractor
34
Particular Conditions of Contract (PCC)
The Employer shall not be liable for any delay or Cost which may be incurred
by the Contractor due to a delay in the Commencement Date resulting from the
failure of these conditions precedent to be fulfilled by the notified date and the
Contractor is not entitled to terminate the Contract under Sub-Clause 16.2
[Termination by Contractor] as above.
The Contractor shall commence the design and execution of the Works as soon
as is reasonably practicable but in any case not exceeding 21 days after the
Commencement Date, and shall then proceed with the works with due
expedition and without delay.
8.3: PROGRAMME
Replace the first paragraph and sub-paragraph (a), (b), (c) and (d) with the
followings:
The Contractor shall submit a detailed time programme to the Engineer prior to
the Commencement Date to be notified under Sub-Clause 8.1 [Commencement
of Works]. The Contractor shall also submit a revised programme whenever
the previous programme is inconsistent with actual progress or with the
Contractor's obligations and in any event the programme shall be revised every
three months to reflect the actual progress on site.
The detailed time programme shall show all activities and sequences of
operations for the orderly design, manufacture, delivery and installation of the
Plant and the completion of the Works and shall be drawn to a monthly time
scale commencing with the Commencement Date. It shall show in detail
intermediate milestone dates for all engineering, procurement, and construction
activities. Activity descriptions shall be discrete so that the actual and
scheduled work progress can be determined. The Contractor will identify the
critical paths both on activity listing and graphic display showing in detail the
followings:
1) Work Programme:
a) within 21 days of the Engineer’s written notice to commence, the
Contractor shall submit to the Engineer a detailed construction
schedule,
b) The schedule shall be in precedence (activity on node) format, prepared
under Critical Path Method (CPM) format, utilizing the computer
software MS Project 2007 or similar, showing the proposed date of
commencement and completion of each activity required under the
contract. (Not Applicable)
c) The schedule shall conform to the working times and times of
completion stipulated in the Contract, (Not Applicable)
d) The activity network shall be drawn to a time scale shown with
weekends and holidays,
e) A tabular list shall be provided listing all activities showing activity
description, start and finish dates, duration assigned,
35
Particular Conditions of Contract (PCC)
f) The number, descriptions, and days shown shall be identical with those
shown on the associated precedence diagram.
2) Site mobilization schedule:
a) The Contractor shall submit the mobilization schedule showing the plan
for construction of camps and other temporary facilities and the
Contractor’s plan for start of work.
3) Material delivery schedule
a) The Contractor shall submit the materials procurement plan and
delivery schedule to meet the targeted progress in the work schedule.
b) The procurement of materials and equipment should ensure a stock of
all materials and equipment required for execution of Work onsite
ready for use and in an amount sufficient to avoid any delay due to
delivery time or interruption of supply. This reserve shall be sufficient
for at least one month. The materials are to be properly stored and
handled to avoid any damage.
4) Construction drawings/shop drawings Schedule:
a) The Contractor at his own cost shall prepare the construction
drawings/shop drawings and submit to the Engineer for approval.
b) The construction drawings/shop drawings should be submitted at least
28 days prior to the Contractor’s plan for start of construction or
fabrication of each unit of work
5) A supporting report which includes
a) A general description of the methods which the Contractor intends to
adopt, and of the major stages, in the execution of the Works, and
b) Details showing the Contractor’s reasonable estimate of the number of
each class of Contractor’s Personnel and of each type of Contractor’s
Equipment, required on the Site.
If the Contractor, during the execution of the Works, shall see it necessary to
make any modification to the detailed time programme, he shall immediately
submit said modifications to the Engineer for review. The Contractor's
submittal to the Engineer shall include his recommendations and means to
resolve the impact of these modifications on other contractors’ work. The
Contractor's submittal of these recommendations, and the review of the
Engineer thereto, shall not relieve the Contractor of his responsibilities and
duties under the Contract.
In addition to the detailed time programme, the Contractor shall provide the
following documents and information:
A. 30-day Work Programme
Within 28 days after the Commencement Date the Contractor shall submit to
the Engineer a 90-day Engineering Programme in bar chart format. This 90-
day Engineering Programme shall include submittal dates for drawings,
36
Particular Conditions of Contract (PCC)
calculations, reports and documentation related to design, as well as all those
items required for review and/or interface with any equipment/design work to
be provided by others. Submittals indicated shall also include all documents
submitted by the Contractor to the Engineer and information to be received by
the Contractor from the Engineer.
The 90-day Engineering Programme shall be prepared showing in detail all
activities, their descriptions, durations and dependencies on a daily time scale
for the first 30 day period, and on a weekly time scale for the balance of the 90
day period. In preparing the 90-day Engineering Programme the Contractor
shall utilise the same subdivision of work activities developed in the detailed
time programme. The 90-day Engineering Programme shall be updated and
resubmitted by the Contractor monthly, displaying actual progress for the
previous 30-day period as well as the forecast progress for the next 90-day
period.
B. 90-day Installation Programme
Not less than 28 days prior to the start of work on Site the Contractor shall
submit to the Engineer a 90-day Installation Programme in bar chart format.
For lump sum price items of the Contract the activity subdivisions shall
correspond to the elements comprising each payment stage of the lump sum
price item. The 90-day Installation Programme shall be prepared so as to show
in detail all activities, their descriptions, durations and dependencies on a daily
time scale for the first 30-day period, and on a weekly time scale for the
balance of the 90-day period. In preparing the 90-day Installation Programme
the Contractor shall utilise the same subdivision of work activities developed
in the detailed time programme. The 90-day Installation Programme shall be
resubmitted by the Contractor every month, displaying actual progress for the
previous 30-day period as well as the forecast progress for the next 90-day
period.
(Not Applicable)
8.4 Extension of Time for Completion
At the end of the last paragraph of this Sub-Clause, add the followings:
Extensions of the Time for Completion shall not be granted for delays caused
by an inadequate work force, faulty workmanship, or delay in design,
manufacture and delivery of the Plant and equipment and Completion of the
Works, providing or importing plant, equipment, construction materials, non-
availability due to break-down or importation delays of construction plant,
equipment and transportation arrangements or the failure of the Contractor to
place orders for plant, equipment or materials in sufficient time in advance to
ensure delivery when needed or due to inadequate planning, inefficiency or
negligence, etc., by the Contractor, or its subcontractors.
In the event the Contractor’s performance of this Contract is delayed or
interfered with by acts of the Employer or other contractors, the Contractor
may request an extension of the Time for Completion, however and shall be
liable for delay damages and increase in contract price for the idle payment
charges., he shall not be entitled to any increase in the Contract Price or to
damages or additional compensation and or prolongation cost as a consequence
37
Particular Conditions of Contract (PCC)
of such delays.(Contractor to be entitled for delay damages and
compensation or increase in contract price)
The Contractor shall maintain a record of all strikes which directly affect the
operations of the Contractor at the Site. Except in such cases where the strikes
renders work impossible for a whole day or more in the Engineer’s opinion, the
Contractor shall not be entitled to an extension of the Time for Completion. An
extension granted because of the strikes shall be an extension of time only and
no claim for extra payment shall accrue because of such extension being
granted. (Contractor liable to receive payment and compensation for any
charges or losses incurred due to idle labor charges.)
Delete the following words from the first paragraph of this Sub-Clause:
These delay damages shall be the sum stated in the Appendix to Tender, which
shall be paid for every week week which shall elapse between the relevant
Time for Completion and the date stated in the Taking-Over Certificate.
These delay damages shall, for the whole of the Works or for any Section, be
the sum stated in the Appendix to Tender, which shall be paid for every day
which shall elapse between the relevant Time for Completion and the date
stated in the Taking Over Certificate for the whole of the Works or for the
Section, as the case may be.
Add the following new paragraphs at the end of the first paragraph of this
Sub-Clause:
38
Particular Conditions of Contract (PCC)
the portion will be calculated pro-rata on the portion of the original delay
described in (a) which has been recovered by the next Milestone, subject
nevertheless to the full deduction of the value determined by the Engineer of
all costs or material loss incurred by the Employer as a result of the default
described in (a).
Replace the whole text of the last paragraph of this Sub-Clause with the
followings:
The Contractor shall not be entitled to payment for costs incurred in making
good any deterioration, defect or loss caused by the Contractor’s failure to
fulfil its obligations under the Contract, including failure to take the measures
specified in Sub-Clause 8.8.
39
Particular Conditions of Contract (PCC)
10.1 TAKING OVER OF THE WORKS AND SECTIONS
The issue of the Taking-Over Certificate for whole of the Works marks the
beginning of the Defect Notification Period.
Although any part of the Works, at the sole discretion of the Employer, may be
taken over by the Employer either through the issue of a Taking-Over
Certificate for this part or by the use or occupation of this part by the
Employer, nevertheless it is the Employer's intention that this will not take
place and that only one Taking-Over Certificate is to be issued for the whole of
the Works.
The issue of any Taking-over Certificate for a section or a part of the Works
shall in no way be considered as the Taking-Over Certificate for the whole of
the Works and thus does not mark the beginning of the Defects Notification
Period.
The Project will include other contracts, in particular Lot 03 Construction of
Civil Structures, Lot 05 Electromechanical Works, Lot 06 Transmission Line
and Interconnection Works, for the execution of the various other works on the
Project which will be performed concurrently with the Works under this
Contract.
For the purpose of the execution of the overall Project, portions of the Works
under this Contract must be constructed to specific stages either to enable work
by the Employer’s other contractors to proceed or continue or to facilitate the
commissioning of the Project.
The Employer’s other contractors as well as the personnel of the Employer and
Engineer and other affected authorities and organizations will also require joint
use of facilities such as roads, site installation areas and other general site
services in connection with such other Works, and the Contractor will make
every reasonable effort to facilitate these activities within the performance of
the Works.
These activities by the Employer's other contractors, the related supervision
activities by the Employer's and the Engineer's personnel and the Project-
related activities of other affected authorities and organizations shall under no
circumstances be considered to constitute the use or occupation of any part of
the Works pursuant to this Sub-Clause and shall not be grounds for the issue of
any Taking-Over Certificates.
40
Particular Conditions of Contract (PCC)
11.3 EXTENSION OF DEFECTS NOTIFICATION PERIOD
Amend this Sub-Clause by inserting the following at the end of the first
sentence of the first paragraph:
The Contractor shall not delay any work whilst awaiting a response but shall
proceed with the varied work immediately upon receipt of an instruction to that
effect from the Engineer on the basis of the description of the programme for
the work included with the instruction.
The contractor however can choose to delay any work if the response to his
variation claim has not been settled within 3014 days of filing of claim.
The Contractor shall familiarize himself with the rules and regulations with
regard to income tax, customs, duties, other taxes, clearing of goods (Not
applicable) and equipment, immigration, transportation and the like, as are
applicable under the laws of Government of Nepal, and it will be necessary for
him to follow the required procedures regardless of any assistance
whichassistance, which may be provided by the Employer.
The Contractor shall pay all duties, taxes, fees and contributions levied in
Nepal in Nepalese Rupees as directed by the relevant governmental department
or office or any other authorized local statutory agency or body in accordance
with the relevant rules and regulations.
The Final Payment Certificate pursuant to Sub-Clause 14.13 shall be issued
only after submission by the Contractor to the Employer of an Income Tax
Clearance Certificate from the Government of Nepal for himself and any
foreign Subcontractors or Nominated Subcontractors employed on the Works.
(Not Applicable)
14.2 Advance Payment
Amend this Sub-Clause by replacing the fifth paragraph with the following:
43
Particular Conditions of Contract (PCC)
In the event that errors found in the certificate before and after the date of its
payment, the amount of error shall be adjusted in subsequent certificate in the
amount following that in which the error was found
The Engineer may by any Interim Payment Certificate make any correction or
modification in any previous Interim Payment Certificate which has been
issued by the Engineer, and shall have authority, if any work is not being
carried out to his satisfaction, to omit or reduce the value of such work in any
Interim Payment Certificate.
14.7 PAYMENT
within 56 days
within 30 days
within 56 days
within 30 days.
Within 42 days following the date of receipt of the Contractor's Statement and
the required supporting documents with respect to each Interim Payment, the
Engineer shall return to the Contractor a copy of the Interim Payment
Certificate issued in accordance with Sub-Clause 14.6 relating to that
Statement.
44
Particular Conditions of Contract (PCC)
With respect to the Final Payment Certificate, the Engineer shall return to the
Contractor a copy of the Payment Certificate for the Final Payment within 56
days following the date of receipt of the Contractor's Final Statement and the
required supporting documents in accordance with Sub-Clause 14.11.
Payment of the amount due in foreign currency under each Payment Certificate
shall be made by means of an irrevocable confirmed international Letter of
Credit payable in the Contractor’s home Country in favor of the Contractor for
the balance of the foreign currency portion of the Contract Price. The Letter of
Credit shall be in place after signing of the Contract Agreement. However, the
payment of the amount due in local currency portion shall be paid by issuing
Bank Cheques payable to the Contractor’s account in any commercial bank in
Nepal. (Not applicable, all payments to be made through Irrevocable
Letter of Credit Only)
The charges related to opening of the Letter of Credit shall be borne by the
Employer, whereas any charges related to the Contractor’s nominated bank
shall be borne by the Contractor.
Add the following wording at the end of the first paragraph in this Sub-
Clause 14.8:
In the event that any item for payment within a Statement is in dispute and the
respective Statement submitted by the Contractor does not include satisfactory
justification or substantiation with respect to that item, the period of delay for
the payment of that item shall be deemed to commence on the date, subsequent
to the date of the Statement, on which the Contractor submits the justification
or substantiation to the satisfaction of the Engineer.
Delete the second paragraph of this Sub-Clause 14.8 and substitute by the
following:
These financing charges shall be calculated at the annual rates indicated in the
Appendix to Tender and shall be paid in the currencies indicated in the
Appendix to Tender.
Delete the whole text of this Sub-Clause and Substitutes the following:
"When the Taking-Over Certificate has been issued for the whole of the Works
and the Works have passed all specified tests (including the Tests after
Completion, if any), the first half of the Retention Money shall be certified by
the Engineer for payment to the Contractor against bank guarantee issued by a
reputable bank or financial institution. The bank guarantee shall allow payment
on first demand. The bank guarantee will be released after completion of
Defects Notification Period. The Contractor shall ensure that the guarantee is
45
Particular Conditions of Contract (PCC)
in the amounts and currencies of the first half of the Retention Money and is
valid and enforceable until the expiry of Defects Notification Period and
remedied any defects, as specified for the Performance Security in Sub-Clause
4.2. No payment of Retention Money shall be certified or paid when a Taking-
Over Certificate is issued for a Section or part of the Works.
After the latest of the expiry dates of the Defects Notification Periods, the
outstanding balance of the Retention Money shall be certified by the Engineer
for payment to the Contractor. Then, the Employer shall return the outstanding
balance of the retention money to the Contractor within 28 days after receiving
a copy of the Performance Certificate including following documents:
(a) Documentary evidence from the concerned Inland Revenue Office as
proof of submission of income statement and payment of all applicable
corporate income tax on any profits realized from this Contract and of all
personal income tax of the Contractor’s personnel, both local and
expatriate.
(b) Documentary evidence from the concerned Customs Office of Nepal as
proof of having removed all duty-exempt contractor’s Equipment and
Plant from Nepal or for Contractor’s equipment and Plant which have
been sold in Nepal that Duty thereon has been duly paid by the purchaser.
(In the case of materials and plant incorporated into the Works, no such
certificate or payment of Duty is required.)
However, if any work remains to be executed under Clause 11, the Engineer
shall be entitled to withhold certification of the estimated cost of such work
until it has been executed.
When calculating these proportions, no account shall be taken of any
adjustments under Sub-Clause 13.7 [Adjustments for Changes in Legislation]
and Sub-Clause 13.8 [Adjustments for Changes in Cost]."
(Not Applicable)
14.10 Statement at Completion
Add the following new paragraph after sub-paragraph (c.) of this Sub-
Clause:
The Contractor shall submit with his Statement at Completion the Income Tax
Clearance Certificate(s) from the tax authorities evidencing the payment of
Income Taxes due under the laws of Nepal with respect to the corporate tax,
tax withholding from personnel of the Contractor and his Subcontractors.
The Statement at Completion shall thus be the Contractor’s total statement for
all sums he considers to be his entitlement under the Contract except the
Retention Money (Not applicable) and other Works that may arise or as may
be instructed during the Defects Notification Period.
46
Particular Conditions of Contract (PCC)
14.11 APPLICATION FOR FINAL PAYMENT CERTIFICATE
At the end of sub-paragraph (b) of this Sub-Clause add the following words:
15 TERMINATION BY EMPLOYER
48
Particular Conditions of Contract (PCC)
FOLLOWING COMPLETION OF THE WORKS THE EMPLOYER
SHALL THEN GIVE FURTHER NOTICE THAT THE
CONTRACTOR'S EQUIPMENT AND TEMPORARY WORKS
WHICH WERE USED BY THE EMPLOYER OR OTHER
ENTITIES FOR COMPLETION OF THE WORKS WILL BE
RELEASED TO THE CONTRACTOR AT OR NEAR THE SITE.
(NOT APPLICABLE)
49
Particular Conditions of Contract (PCC)
(i) deliberately destroying, falsifying, altering or concealing of evidence
material to the investigation or making false statements to
investigators in order to materially impede a GoN or Employer
investigation into allegations of a corrupt, fraudulent, coercive or
collusive practice; and/or threatening, harassing or intimidating any
party to prevent it from disclosing its knowledge of matters relevant to
the investigation or from pursuing the investigation; or
(ii) acts intended to materially impede the exercise of the GoN, Employer
or Financier’s inspection and audit rights.
The Contractor’s staff and labor will be liable to pay personal income taxes in
the Employer’s country in respect of such of their salaries and wages as are
chargeable under the laws and regulations for the time being in force, and the
Contractor shall perform such duties in regard to such deductions thereof as
may be imposed on him by such laws and regulations.
Delete the following words from the first line of sub-paragraph (a) of this
Sub-Clause:
Provided that any of the events referred to under (a) and (b) above occurs, the
Contractor shall prior to giving a Termination Notice serve notice (hereinafter
called a “Preliminary Notice”) on the Employer by registered letter stating that
the amount due under the relevant certificate has not been paid and requiring
payment or issue (as the case may be) of the relevant certificate in accordance
with the Contract within 14 days of the date of receipt of the Preliminary
Notice by the Employer. Only if payment or issue of the relevant certificate has
not been effected within such a 14-day period shall the Contractor be entitled
to issue a Termination Notice.
50
Particular Conditions of Contract (PCC)
16.4 PAYMENT ON TERMINATION
AMEND SUB-CLAUSE 17.3 BY REPLACING THE FIRST LINE WITH THE FOLLOWING:
THE EMPLOYER’S RISKS, INSOFAR AS THEY DIRECTLY AFFECT THE DESIGN AND
EXECUTION OF THE WORKS IN THE COUNTRY WHERE THE PERMANENT WORKS
ARE TO BE EXECUTED, ARE:
Amend Sub-Clause 17.6 by replacing the first paragraph with the following:
51
Particular Conditions of Contract (PCC)
“Neither Party shall be liable to the other Party for loss of use of any Works,
loss of profit, loss of any contract or for any indirect or consequential loss or
damage which may be suffered by the other Party in connection with the
Contract, other than as specifically provided in Sub-Clause 8.7 [Delay
Damages]; Sub-Clause 11.2 [Cost of Remedying Defects]; Sub-Clause 15.4
[Payment after Termination]; Sub-Clause 16.4 [Payment on Termination];
Sub-Clause 17.1 [Indemnities]; Sub-Clause 17.4 (b) [Consequences of
Employer’s Risks] and Sub-Clause 17.5 [Intellectual and Industrial Property
Rights].”
17.7 SECURITY
The Contract makes provision under Clause 17 [Risks and Responsibility] and
19 [Force Majeure] for the allocation of risks. The Contractor shall note that
the extent of the Employer’s liability under Clause 17 is limited only to
rectifying the loss or damage which has occurred to the Works, Goods or
Contractor’s Documents; it does not cover other costs that may have been
incurred by the Contractor.
The Contractor shall note that the definitions of Employer’s Risks under Sub-
Clause 17.3 (a), (b) and (c) shall not include acts of disruption by individuals
or groups acting for financial gain or attempting to disrupt the activities of the
Contractor, ordinary criminality, thefts, (Not Applicable and Employer shall be
liable for such losses incurred by the contractor due to local issues) or labor
conflicts or any other inconveniences that may occur during peace time
working conditions and no claim under Clause 17 will be accepted for such
acts.
18 INSURANCE
18.1 GENERAL REQUIREMENTS FOR INSURANCE
Delete the following text from the first paragraph of this Sub-Clause:
In this Clause, "insuring Party”, means, for each type of insurance, the Party
responsible for effecting and maintaining the insurance specified in the
relevant Sub-Clause.
In this Clause, "insuring Party”, means the Contractor for each type of
insurance, at his own expense, responsible for effecting and maintaining the
insurance specified in the relevant Sub-Clause.
52
Particular Conditions of Contract (PCC)
Each Party shall comply with the conditions stipulated in each of the insurance
policies. The insuring Party shall keep the insurers informed of any relevant
changes to the execution of the Works and ensure that insurance is maintained
in accordance with this Clause.
The Contractor’s risks are risks other than those defined under Employer’s
Risks. Any amounts not insured or not recovered from the insurers shall be
borne by the Contractor.
In the third line of the first paragraph of this Sub-Clause after the words:
In the case of Plant the coverage by insurance shall be not less than the full
replacement value including delivery charges to Site.
Delete the following words from the fourth paragraph of this Sub-Clause:
53
Particular Conditions of Contract (PCC)
Unless otherwise stated in the Particular Conditions, insurances under this Sub-
Clause:
Add the following sentence at the end of the first paragraph of this Sub-
Clause:
The scope of cover of this insurance shall cover activities connected with this
Contract at any location within Nepal, in addition to activities at the Site.
Delete the following words from the third paragraph of this Sub-Clause:
Add the following new sub-paragraphs (e), (f) and (g) after sub-paragraph
(d):
54
Particular Conditions of Contract (PCC)
the Employer will be passed to the Contractor who shall likewise
inform the Employer and the Engineer of any such claim which is
submitted directly to him by a claimant. The Contractor shall do
everything necessary including notifying the insurers of claim
received, to ensure that claims are settled properly and expeditiously
and shall keep the Employer and the Engineer informed as to the
progress made towards settlement, failure to which the Employer shall
be entitled to make direct payment to claimants of all outstanding
amounts due to them in the Employer’s opinion and without prejudice
to any other method of recovery to deduct by way set-off the amounts
so paid from any sums or which become due from the Employer to the
Contractor.
Add the following wording at the end of the first paragraph of this Sub-
Clause:
The minimum cover for personal injury or death insurance for each
Contractor’s Personnel shall be NRs. 1.0 million with no limit on the number
of occurrences.
55
Particular Conditions of Contract (PCC)
be additional to any mandatory insurance required in terms of the legislation of
Nepal.
For the avoidance of doubt Force Majeure shall not include any unavailability
of Contractor’s Equipment, labor or Goods except as may be covered by
subparagraphs (i) to (v) above. The Contractor shall note that the definitions of
Force Majeure under Sub-Clause 19.1 shall not include normal acts of
disruption by individuals or groups acting for financial gain or attempting to
disrupt the activities of the Contractor, ordinary criminality, thefts, strikes or
labor conflicts or any other inconveniences that may occur during peace time
working conditions and no claim under Clause 19 will be accepted for such
acts. (Not Applicable)
Delete the following texts from the fifth paragraph of this Sub-Clause:
‘or within such other period as may be proposed by the Contractor and
approved by the Engineer’
Add the following sentence after the sub-para (c) of fifth paragraph of this
Sub-Clause:
If the Contractor fails to send a fully detailed claim with full supporting
particulars within such period of 6042 days, the claim shall not be entertained.
(Not applicable)
56
Particular Conditions of Contract (PCC)
Delete the following words from the seventh paragraph of this Sub-Clause:
Each Payment Certificate shall include such amounts for any claim as have
been reasonably substantiated as due under the relevant provision of the
Contract. Unless and until the particulars supplied are sufficient to substantiate
the whole of the claim, the Contractor shall only be entitled to payment for
such part of the claim as he has been able to substantiate.
Delete the following text from the third line of the first paragraph of this
Sub-Clause:
Replace the whole text of the second paragraph of this Sub-Clause by the
following paragraph:
The DAB shall comprise, as stated in the Appendix to Tender, either one or
three suitably qualified persons (“the members”), each of whom shall be fluent
in the language for communication defined in the Contract and shall be a
professional experienced in the type of construction involved in the Works and
with the interpretation of contractual documents. If the number is not so stated
and the Parties do not agree otherwise, the DAB shall comprise three persons.
If the DAB is to comprise three persons, each Party shall nominate one
member for the approval of the other Party. The first two members shall
recommend and the Parties shall agree upon the third member, who shall act as
chairman. The members of the DAB shall be Nepalese Citizen. (Not
applicable)
57
Particular Conditions of Contract (PCC)
The terms of the remuneration of either the sole member or each of the three
members, including the remuneration of any expert whom the DAB consults,
shall be mutually agreed upon by the Parties when agreeing the terms of
appointment. Each Party shall be responsible for paying one-half of this
remuneration.
The terms of the remuneration of either the sole member or each of the three
members, including the remuneration of any expert whom the DAB consults,
shall be mutually agreed upon by the Parties when agreeing the terms of
appointment. Each Party shall be responsible for payment of the remuneration
agreed for their respective nominated members and also paying one-half of this
remuneration of the chairman.
The form of payment will be negotiated with the DAB members in accordance
with the FIDIC guidelines. For the shared payment for the chairman it is
expected that payment will be based on a monthly retainer plus fees and
expenses for actual input when needed, and not on a permanent basis.
(Not Applicable)
Add the following new paragraph to the end of this Sub-Clause:
The Dispute Adjudication Agreement for each member of the three-person
DAB shall be in accordance with the specimen included in Volume 1 Part 3 of
the Bidding Documents.
20.3 Failure to Agree Dispute Adjudication Board
Replace the whole text of the sub-paragraph (b) of this Sub-Clause with the
followings:
(b) either Party fails to nominate a member (for approval by the other Party), or
fails to approve a member nominated by the other Party, of a DAB of three
persons by such date,
20.4 Obtaining Dispute Adjudication Board’s Decision
Add the following at the end of the first paragraph:
If the Contractor fails to refer a dispute to the DAB within such 28 days after
the receipt of the Engineer’s decision, the claim shall no longer be considered
as a valid claim. (Not applicable)
20.6 ARBITRATION
Delete the whole text of this Sub-Clause and substitute by the following
paragraphs:
58
Particular Conditions of Contract (PCC)
Any dispute not settled amicably and in respect of which the DAB’s decision
(if any) has not become final and binding shall be finally settled by arbitration.
The dispute shall be finally settled in accordance with the Rules of Arbitration
of the United Nation Commission on International Trade Law (UNCITRAL).
The number of Arbitrator will be 3 (Three). The arbitration tribunal shall be
formed as follows:
The Employer and the Contractor shall appoint one arbitrator each to the
tribunal and the two arbitrators such appointed shall agree upon a third
arbitrator who will act as the Chairman. In case of failure of the two
Arbitrators appointed by the parties to reach upon a consensus within 30 days
from the appointment of the Arbitrator appointed in the last, the Presiding
Arbitrator (Chairman) shall be appointed by the Appointing Authority defined
in the Appendix to Tender. The Chairman of the three arbitrators shall be of a
nationality which is neither Nepalese nor that of the Contractor or, in case the
Contractor is a Joint Venture, of any of the Partners of the Joint Venture.
The venue of such Arbitration shall be Kathmandu, Nepal
The arbitration shall be conducted in the language for communications defined
in Sub-Clause 1.4 [Law and Language]
The arbitrators shall have full power to open up, review and revise any
certificate, determination, instruction, opinion or valuation of the Engineer, and
any decision of the DAB, relevant to the dispute. Nothing shall disqualify
representatives of the Parties and the Engineer from being called as a witness
and giving evidence before the arbitrators on any matter whatsoever relevant to
the dispute.
Neither Party shall be limited in the proceedings before the arbitrators to the
evidence or arguments previously put before the DAB to obtain its decision, or
to the reasons for dissatisfaction given in its notice of dissatisfaction. Any
decision of the DAB shall be admissible in evidence in the arbitration.
Arbitration may be commenced prior to or after completion of the Works. The
obligations of the Parties, the Engineer and the DAB shall not be altered by
reason of any arbitration being conducted during the progress of the Works.
59
Particular Conditions of Contract (PCC)
manufacture, sale and transport of the Contractor’s Equipment, Plant, Materials
and supplies to be used on or furnished under the Contract, and on the services
performed under the Contract.
21.2 Local Taxation
UNLESS OTHERWISE SPECIFIED IN THE CONTRACT DOCUMENTS, THE PRICES BID BY THE
CONTRACTOR AND ITS SUPPLIERS AND SUBCONTRACTORS SHALL INCLUDE ALL
DUTIES, IMPORT DUTIES, BUSINESS TAXES, INCOME AND OTHER TAXES THAT MAY BE
LEVIED IN ACCORDANCE WITH THE LAWS AND REGULATIONS IN FORCE OR IN
EFFECT IN NEPAL AS OF THE DATE 28 DAYS PRIOR TO THE CLOSING DATE FOR
SUBMISSION OF BIDS IN THE EMPLOYER'S COUNTRY ON THE EQUIPMENT, PLANT,
MATERIALS AND SUPPLIES (PERMANENT, TEMPORARY AND CONSUMABLE)
ACQUIRED FOR THE PURPOSE OF THE CONTRACT AND ON THE SERVICES
PERFORMED UNDER THE CONTRACT. NOTHING IN THE CONTRACT SHALL RELIEVE
THE CONTRACTOR FROM HIS RESPONSIBILITY TO PAY ANY TAX THAT MAY BE
LEVIED IN THE EMPLOYER’S COUNTRY ON PROFITS MADE BY HIM IN RESPECT OF
THE CONTRACT.
(NOT APPLICABLE)
60
Particular Conditions of Contract (PCC)
responsible for transport from the Port of Disembarkation to the Site or
location of the Works.
The Contractor shall determine and be fully responsible for payment of all
import licenses, fees or other such charges as may be imposed by the local or
any en-route customs authorities.
The Contractor shall determine these rates and their amounts at the time of
tender and takes full responsibility for including such costs within its tender.
(Not applicable)
21.5 Duties on Equipment, Plants and Materials
The Contractor shall familiarize himself with the rules and regulations with
regard to income tax, customs, duties, other taxes, clearing of goods and
equipment, immigration, transportation and the like, as are applicable under the
laws of Government of Nepal, and it will be necessary for him to follow the
required procedures regardless of any assistance which may be provided by the
Employer.
The Contractor shall pay all duties, taxes, fees and contributions levied in
Nepal in Nepalese Rupees as directed by the relevant governmental department
or office or any other authorized local statutory agency or body in accordance
with the relevant rules and regulations. Exchange rates between Nepalese
Rupees and foreign currency for taxation purposes shall be the prevailing
exchange rates at the time of the payment.
The following special conditions shall apply to Registration for Tax under this
Contract:
The Contractor and any foreign Subcontractors or Nominated Subcontractors
employed on the Works, if not already registered in Nepal, shall be required to
be registered with the concerned Inland Revenue Office for the purpose of the
Contract. The Contractor shall complete this registration no later than 28 days
after the date of signing the Contract Agreement. Certified copies of the
Income Tax Registration Certificate(s) shall be submitted to the Employer
within 14 days after registration.
The following special tax conditions shall apply to 'advance income tax' under
this Contract:
Advance Income Tax assessed in accordance with the prevailing Income Tax
Act of Nepal. A TDS (Tax Deductions at Source) at the rate of 1.5% of the
amount due before the addition of VAT shall be deducted from each payment
certificate under the Contract prior to payment to the Contractor. Each of such
‘Advance Income Tax’ deductions shall be deposited to the concerned tax
authorities and copies of the deposit slip will be provided to the Contractor.
The following special tax conditions shall apply to Import Duty and Value
Added Tax (VAT) for the Hydromechanical equipment imported for this
Project under this Contract:
Value Added Tax (VAT) shall be imposed according to prevailing laws and
regulations of Government of Nepal, on all equipment and plants purchased for
use in the contract Works. The Contractor shall submit request with VAT bills
61
Particular Conditions of Contract (PCC)
to the Inland Revenue Office of GoN for reimbursement of the paid VAT
within the prescribed time, if applicable.
VAT is not applicable on import of the metal parts of Hydromechanical
equipment required for the project under this contract.
A special customs duty rate of 1% of the CIF to port of entry value shall be
paid on Hydromechanical equipment imported by the Contractor for executing
the Project under this Contract.
The Contractor shall state separately in his Statements (payment invoices) the
amounts paid at this special customs duty rate of 1% and these amounts shall
be reimbursed by the Employer to the Contractor.
The following special tax conditions shall apply to Customs Duty (import tax)
for Contractor’s construction equipment and machinery under this Contract:
Notwithstanding the provisions of this document, Contractor's Plant and
Equipment, including essential tools thereof, imported by the Contractor for
the sole purpose of executing the Contract, and taken out of Nepal (except the
spare parts) upon completion of the Works shall be exempt from payment of
customs duties and taxes levied in Nepal.
In order to be eligible for this exemption the Contractor shall be required to
deposit the amount or provide a bank guarantee to the Government of Nepal
Customs Department, with a copy to the Employer, equal to the amount of
applicable customs duties assessed in accordance with the prevailing laws,
rules and regulations of Nepal for those imported items at the time of import.
The amounts of the deposits so provided will be refunded, or the bank
guarantees cancelled by the Nepal Customs Department, after the submission
to the Nepal Customs Department of the re-export certificates with respect to
these items issued by the Customs Department.
If the Contractor disposes of any of these imported items (except the spare
parts) in Nepal, he shall pay all customs duties and taxes applicable on such
items under the laws and regulations of Nepal in force at that time.
In the event that the value of the imported spare parts for each item of the
construction equipment and machinery exceeds 10% of the CIF to port of entry
value of the respective item of imported construction equipment and
machinery, the Contractor shall be liable to pay all applicable taxes and duties
on the import of these imported spare parts.
Contractor shall re-export all the equipment, plant and materials
within 90 (Ninety) days after the issue of the Taking Over Certificate for whole
of the Works except that, if agreed by the Employer, any specifically identified
items of Equipment etc. which are required by the Contractor for the sole
purpose of executing activities under the Contract during the Defects
Notification Period may remain in Nepal but shall be re-exported within 90
days after Defects Notification Period.
Within ninety (90) days after the issue of Taking Over Certificate for whole of
the Works, any Plant or materials imported under this special rate and
exemption which have not been incorporated in the Works or consumed in
performance of the Works shall be taken out of Nepal or, if disposed of in
62
Particular Conditions of Contract (PCC)
Nepal, the Contractor shall pay all additional duties and taxes applicable under
the laws and regulations of Nepal in force at the time.
The Contractor shall maintain records satisfactory to the Employer
documenting incorporation into the Works or consumption in performance of
the Works of all Plant and materials imported into Nepal. If any of such Plant
and/or materials imported into Nepal or otherwise supplied to the Project at a
special or preferential rate of Customs Duties or taxes, are found to be used,
appropriated or misused, or used for any other purposes other than this Project,
the Contractor will be held fully responsible, and liable to pay customs duties,
taxes and/or any penalties as may be imposed by any GoN authority, and in
accordance with the laws and regulations of Nepal.
In case, the Government of Nepal allows any concessions/ exemption in the
importation of plants, equipment and materials including any kind of lumpsum
exemptions in the local taxes especially for hydropower projects, the Contract
Price shall be adjusted accordingly to the benefit of the Employer.
Except only the exclusion of duties and taxes as provided above, the bid prices
shall include all other duties, taxes, fees and contributions that may be levied
according to the laws and regulations in effect in Nepal on the date 28 days
prior to the closing date for submission of bids on Contractor's Equipment,
Plant and materials (whether permanent, temporary or consumable) acquired
for the purpose of the Contract, on services performed under the Contract and
on revenue received under the Contract.
The Custom duties for Equipment, Plant and materials which will be
incorporated in to the Permanent Works, shall be paid by the Contractor at the
time of importation. The Employer shall reimburse such paid custom duties to
the Contractor upon submission of relevant documentary evidence.
The provisions of this Clause shall apply equally to foreign subcontractors or
nominated subcontractors of the Contractor employed on the Works.
Road cess shall be applied in accordance with the prevailing laws and
regulations of Nepal.
63
Particular Conditions of Contract (PCC)
to maintain sufficient stock at Site or shortage of materials shall in no case be
the reasons for any claims including time extension.
(Not applicable)
64
Particular Conditions of Contract (PCC)