Professional Documents
Culture Documents
Table of Contents
1 Purpose ..................................................................................... 3
2 Scope for Vessels .......................................................................... 3
2.1 Precaution prior to Starting ....................................................... 3
2.2 Isolation Procedure ................................................................. 3
2.3 Vessel Emptying Procedure ........................................................ 3
2.4 Gas Purging Procedure ............................................................. 4
3 Cleaning Procedure ....................................................................... 5
3.1 Alternative Cleaning Procedures.................................................. 5
3.1.1 High Pressure Water Jetting .................................................... 5
3.1.2 Steam Cleaning ................................................................... 5
3.1.3 Chemical Cleaning................................................................ 6
4 Preparation for Vessel Entry............................................................. 6
4.1 Precautions for Entry ............................................................... 6
4.2 Conditions for Entry................................................................. 6
HSE Procedure for Cleaning Vessels which contain Gas or
Hydrocarbons at Wafa Desert Plant
Contract No.:
C/0531/WA/05
Doc. No.: UW.3.HSE.022 Rev.: 1 Page 3 of 6
1 PURPOSE
This following sections outline the recommended steps that should be followed
prior to and during the course of internal cleaning or gas purging of vessels in
preparation for vessel entry at the Wafa Plant.
This procedure is to be used in conjunction with the following MOG
procedures and any other relevant HSEQ procedures.
• MOG-HSEQ-SF-WI-062 Work Instructions Confined Space Entry for Wafa
Field
• MOG-HSEQ-SF-P-024 Corporate Permit to Work Procedure - Onshore
3 CLEANING PROCEDURE
Cleaning is required to ensure complete removal of traces of hydrocarbon
deposits which is a pre-requisite for vessel entry. Activities such as internal
inspection and repair necessitate vessel entry.
Note: All cleaning activities mentioned in this section must be carried out
from outside of the vessel.
• Remove all nozzles and manholes;
• Open drain valves to allow wash down fluids to flow through;
• Hose down vessel internal walls thoroughly using service water through
the available openings. This may require several hours;
• Personnel shall not enter or even put their head into the vessel during
this work;
• Allow the vessel to dry out after flushing;
• If required install ventilation fans to accelerate drying process;
• Conduct gas test at conclusion of drying prior to entry – HSEQ;
• Hosing can be repeated if required;
• Further washing with water or even scrubbing maybe required upon
entry to ensure suitable cleanliness for inspection work;
3.1 Alternative Cleaning Procedures
Should water hosing be found to be ineffective; the following alternatives can
be considered once agreed with Production and Laboratory personnel.
Note: Application of below alternatives must be from outside of the vessel.
3.1.1 High Pressure Water Jetting
Water jetting with high pressure should be the first option when hosing fails.
This work is accomplished from outside of the manholes using lances powered
by high pressure pumps.
Operators must be properly trained and protected whilst engaged in this
operation.
Alternatively, HP pumps can be rigged with manual or automated rotating
nozzles that provide a thorough sweep wash of the vessel doing away with
entry during washing. Such rigs can also be used where gas tight flange
operation is required.
3.1.2 Steam Cleaning
The use of steam may be utilized to dislodge specific deposits. The
appropriate safety precautions shall be taken when steam is used.
Introduction of steam can also be prior to removal of all nozzles and manholes
to increase steam containment hence effectiveness.
Note that suitability of the vessel for steam cleaning has to be first clarified.
HSE Procedure for Cleaning Vessels which contain Gas or
Hydrocarbons at Wafa Desert Plant
Contract No.:
C/0531/WA/05
Doc. No.: UW.3.HSE.022 Rev.: 1 Page 6 of 6