Professional Documents
Culture Documents
by
Roger M. Zimmerman
S&ndia National Laboratories
Albuquerque, NM
Daniel P. Zerga
Parsons Brinckerhoff Quade and Douglas
San Francisco, CA
ABSTRACT
Mgblth
This report was prepared under the requirements for Quality Assurance
Level II!. D
ii
CONTENTS
iii
CONTENTS (continued)
iv
CONTENTS (concluded)
• ea_
V
LIST OF FIGURES
6-1 Schematics Showing a Burn Cut and an Angle Cut ................ 6-5
6-2 Plan View Showing Blast Rounds ................................ 6-8
6-3 "Hex Burn" Blast Design for Rounds 4 and 5 .................... 6-9
6-4 "V-Cut" Blast Design for Round 6B ............... ,............. 6-11
6-5 "Triangular Burn Cut" for Rounds 7 through 12 ................. 6-12
6-6 Final Ground Support for Demonstration Drift ................... 6-16
vi
LIST OF TABLES
Table
vii
ACKNOWLEDGMENTS
From EG&G
Don Mason For skill in developing the software for the data
acquistion system and help in keeping it operating
From REECo
Don Hembre For assistance as REECO pr<lect manager in the planning "
and conduction of the drilling and mining activities
viii
ACKNOWLEDGMENTS (concluded)
ix/x
1.0 INTRODUCTION
i.I Ba__ekground
(YMP) (DOE, 1980). G-Tunnel, ]ocated in Rainier Mesa on the NTS, inter-
sects layers of welded and nonwelded tuffs that have thermal and mechanical
properties and ntress states (Zimmerman and Finley, 1987) similar to the
tuffs in Yucca Mountain. The welded tuff mining (WTM) experiment consists
of rock mechanics measurements and evaluations needed to ensure that tech-
predictions of the behavior of the host rock for operating periods over
closure. These predictions are made through numerical models that have to
be developed, verified, and validated. Field-scale tests document the
response of the host rock to excavations and thermal pulses, and the
resulting data are used to confirm the adequacy of the numerical models in
with rock mass convergence resulting from the excavation process. These
provide preliminary assessments that will help guide future analytical and
experimental activities.
I-i
Insitu site characterization is planned as part of future ES rock
testing discussed in this report includes many testing concepts planned for
1.2 Purpose
Measurements were made in a jointed rock mass before, during, and after the
excavation process. This is the flrst tlme that this has been done in
either welded or nonwelded tuffs.
• apply two new methods to measure rock mass responses to the mining
process and
1-2
1.3 Contents of Report
this report are the experiment layout, pertinent geology, theldata acquisi-
tion system, and mining and instrumentation details. For the latter, each
1-3/1-4
2.0 EXPERIMENT LAYOUTS AND GEOLOGY
(GTUF) using two drifts. Figure 2-1 shows a plan view of the two drifts.
The first drift constructed was the 12-Drift extension. The drift was
mined from the U12.g.12 drift that forms a major dr_ft in the G-Tunnel
network. The 12-Drift contains the tunnel rail system and is loc_ted in
tion drift preferably would be at the same level as the mine-by drift, but
it was located at a lower elevation co minimize expenses during this
developmental effort. Boreholes were drilled from the 12-Drift into the
rock mass into which the lemonstrat!on Drift would be mined so that
measurements could be made before, during, and after the excavation. The
Demonstration Drift is located in welded tuff and has the cross-sectional
Figure 2-1 shows the measurement stations that were used for both tbe
structural features (see Section 2.2) are shown in the figure. The
state,Lm were normally located after each mining round. Two stations, C
and E, were l_ated at predetermined distances because of the presence of
statlon-dependent _,_qtrumentation originating from the 12-Drlft.
2-i
2-2
,v
#3 NONWELDED TUFF
#2 _.._
. \ _..._. I / #4
\ /
\ I _"_"_-L..
\ I _f2 /
MODERATELY \ _1 I /
WELDED TUFF \ I I / #3
\ i I /
I i /
\ / I I
I /
/
GEOLOGIC CONTACT \ t /
DENSEL'Y WELDED _.
. TU,':-F . // \\ \ I / #4
/
/ _, /
/
I /
RUBBLE ZONE I /
/
./--- #5
VITRIC WE /
TUFF /
11I---_$11+111=,
III" =_111_11_111 #
/ DEMONSTRATION
/ DRIFT
I I
NONWELDED TUFF // /
/ I /
/
,1I/'_'''- LONG BOREHOLE
/ /1 (STATIONS B,D,& F)
I /
/ t I
/ I
I /
/ I
// f / I MPBX (STATIONS C & E)
-'=iii--" , /
/
/
I
I SCALE
12-DRIFT I I , I
"_ I 3m
I
IEIII
#6
,,=,,
2-3
"_- identified by station and position number. MPBXs were located only at
through 4 in Figure 2-2, were located at Stations B, D, and F and were used
The pertinent dimensions and drilling methods for ali of the boreholes
_ Figure 2-1 shows the major geologic structures, including a fault and
fractures. These were visually mapped from the inside of the drift by the
z -2.5 m) was also observed in the 12-Drift, where it has a 3.6-m displace-
logs for the 12 boreholes driven from the 12-Drift before the mining was
started. In some cases, it was hard to identify unit contacts, and these
omissions are evident in the figures. The unit contacts in figures show
the influence of the fault, located between Stations C and D. The location
- of the Demonstration Drift is shown in each figure with the dashed lines.
-
tions had been summarized for use here, and the results are in Table 2-2.
It should be noted that th_ normal fault was not noticed when mining
the 12-Drift because there was i_o significant change in the rock mass
2_4
2-5
a
2-6
z
2-8
T___BLE 2-2, STRATIGRAPHIC DESCRIPTION*
Lithologic
. Sequence Location** . Description
2-9
for stratigraphic contacts and sugges ed a fault was present. A fault with
densely welded tuff was thickening in the direction of the intended mining.
The descriptions obtained from the 12-Drift cores showed that the densely
welded tuff did not thicken and, in fact, showed that the floor of the
Station E. Two options were considered" (i> continue the drift along the
original grade and keep the roof in the densely welded tuff or (2) ramp up
slightly and keep the entire drift in the densely welded tuff, but keep
2-10
3.0 DATA ACQUISITION SYSTEMS (DASs)
2 Digital Voltmeter-Scanner,
3 Desktop Computer,
The Hewlett Packard (HP) 3497 digital voltmeter-scanner was the DAS
voltage monitoring unit used to record sensor outputs. The sensors were
B
3-1
conv%, lH
lH ii _.7_ _--
,Tg'_t_,'iL j II oi_'rA Iii _ DOWNHOLE ALCOVE
CoHi:98iiEB E R
t
---J _l77UJ!!711
--- _ h ,
DIGITAL
IN;'UTS
,,_ _ _ _I VOLTAOB
EXCITATION
3-2
under continuous excitation from power supplies located in the Instrumen-
directly to the sensors. Different power supplies were used for different
Output signals from the sensors were stored on two HP 7912 hard disks,
Raw output voltages were stored on one disk and converted data were stored
on the other Converted data were calculated from software stored in the
computer. The computer could provide for conversions from voltages to the
manipulation,
Data were converted from raw voltages using calibration factors and
initial values stored in the calibration file. The calibration file was
power supply (UPS). The UPS was connected to the tunnel instrumentation
power line; thus, it was under continuous charge. The UPS was used to
provide (i) continuous and constant voltage power to the DAS and power
(3) uninterrupted power if there was a loss of line power. The UPS could
Table 3-1 lists the number of and different types of instruments that
" were monitored on the DAS. Different sensors are identified with acronyms
for la'er convenience. Also included in the table are descriptions of the
3-3
3-4
3.1.3 __ata Operations
The normal mode of oper-'_ion was for the data to be recorded and
stored on the HP 7912 har_! _..sKs at G-Tunnel, and then ali available files
latter Was used because it was necessary to make changes in the calibration
file as new instruments were brought on line and because a complete record
of ali calibration activities was wanted. The time records were expressed
3-5
6, View and edit the calibration file. A new file number was auto-
Manual data were recorded on special forms that were designed for each
3-6
! [II
3-7/3-8
4.0 DAS CONNECTED INSTRUMENTATION DESCRIPTIONS
anchors in the rock and the sensing unit on the surface can be used to help
describe rock mass stiffness and strength behavior as well as to measure
the relaxation phenomena in the rock mass that occurs around an opening.
testing.
An MPBX consists primarily of (i) a head, (2) the collar pipe, (3)the
rods, and (4) the anchors (Figure 4-1). The head contains the sensors.
Usually the head has a removable cover to protect the sensors. The main
_nction of the head is to serve as a fixture to transfer movements of rod
ends to appropriate sensors. MPBXs can have sensors that are manually read
or monitored by the DAS. 'rhe sensors that are monitored by a DAS operate
The collar pipe serves to fix the head to the end of the borehole.
Collar pipes are designed by the manufacturers for various purposes. For
instance, the collar pipe for the Irad MPBX contained some of the sensing
4-1
_-2
relatively insensitive to thermal gradients. Friction reduction is
grout or loose rocks do not interfere with the rod movements. Special
metals, such as invar, are used in MPBXs for environments with thermal
gradients. Ali WTM work was planned for ambient temperatures, which remain
quite stable in the tuff in G-Tunnel, and stainless steel rods were used in
all MPBXs.
anical, hydraulic, and grouted. Grouted anchors had been selected for use
in the fractured welded tuff in other work (Zimmerman et al., 1986) and
Table 4,1 summarizes the MPBX anchor locations and identifies the data
Irad (Model 4500-6 anchor) MPBXs were used in the WTM evaluations.
The model is designed for use with a dlal gage micrometer or a sonic probe.
Irad MPBXs were selected for use in the WTM because of two design features'
The sonic principle used with the Irad units employs time measurements in
the MPBX head, which are transmitted digitally to a readout meter. This
means that the signal in the cable between the MPBX and the readout meter
the possibility that sensors with electronic components could not be used
4-3
TABLE 4-1, MPBX DESCRIPTIVE _NFORMATION
C3 Up i 14.31
(Irad, 6-Anchor) 2 1.22
3 1.65
4 2.94
5 3 95
6 4 94
C6 Down 7 14 32
(Irad, 6-Anchor) 8 1 23
9 1 95
I0 2 96
ii 3 96
12 4 95
CI Left 35 14 00
(Geokon, 6-Anchor) 36 1 25
37 2 00
38 3 O0
39 4 O0
40 5 O0
C5 Right 41 14 00
(Geokon, 6-Anchor) 42 1 25
43 2 00
44 3 00
45 4 O0
46 5 O0
C2 Inclined-Left 59 14.00
(Sinco/Terrametrics, 60 1.25
4 Tensioned Anchor 61 2.00
Rods) 62 3.00
C4 Inclined-Right 63 14.00
(Sinco/Terrametrics, 64 1.25
4 Tensioned Anchor 65 2.00
- Rods) 66 3.00
4-4
TABLE 4-I, MPBX DESCRIPTIVE INFORMATION (ConclUded)
E3 Up 13 14 00
(Irad, 6-Anchor) 14 1 25
15 2 00
16 3 00
17 4 00
18 5 00
E6 Down 19 14 00
(Irad, 6-A,,chor) 20 1 25
21 2 00
22 3 O0
23 4 00
24 5 00
E1 Left 47 14.00
(Sinco/Terrametrics, 48 1.25
6 Tensioned Anchor 49 2.00
Rods) 50 3.00
51 4.00
52 5.0O
E5 Right 53 34 00
(Sinco/Terrametrics, 54 1 25
6 Tensioned Anchor 55 2 00
Rods) 56 3 O0
57 4 00
58 5 00
E2 Inclined-Left 67 14.00
(Sinco/Terrametrics, 68 1.25
4 Tensioned Anchor 69 2.00
• Rods) 70 3.00
E4 Inclined-Right 71 14.00
(Sinco/Terrametrics, 72 1.25
4 Tensioned Anchor 73 2.00
Rods) 74 3.00
4-5
in instruments placed in close proximity to the blast face and manual
measurements might have to be used until the blast face was located some
distance from the instrument. Sonic probes were used for all measurements,
The collar pipe on this model is normally 1,8 m long, The collar pipe
The sonic probe measures the time interval required for a stress
wave to travel between two or more points in a tube containing a magneto-
probe through the rods, and movements of the magnets cause changes in the
time intervals. The time interval measurement is converted to a displace-
ment through an Irad Sonic Probe MB-7 Digital Readout Meter (DRM), The
. Irad MPBX was designed to operate as a manually operated unit, and anchor
a driver circuit and a relay switching circuit to interface with the DAS
and the DRM. These items were configured and controlled with software so
that the normal DAS scan operation would address prescribed channels in the
DRM and transfer the digital distance output to a recorded value in the
DAS.
1986), (2) use of tensioned anchor rods, and (3) a built-in capability ftr
in situ calibrations. The authors wished to evaluate the friction reduc-
4-6
The sensors operate using a direct current LVDT. A DC-LVDT contains
two major components: (I) the body, which contains the electronics, and
(2) the sliding core, which translates with the anchor movement. When the
body and the core results in a voltage output indicating the relative
Geokon, Model A3, 6-anchor rod-type MPBXs were also used. Geokon
MPBXs were selected for use because of two features: (i) simplicity of
electronics and (2) potential for use with short collar pipes. The sensors
in the Geokon units were linear potentiometers, which have been widely used
The unit had six rods covered with Schedule 40 PVC protective tubing.
The normal sequence for the installation and operation of all MPBXs at
I. blasting a recess;
4-7
6. installing the instrument head in the collar pipe and connecting
Figure 4-1 also shows details associated with the protection of the
MPBXs in the rock. Each head was recessed and covered with a protective
the recesses. The channels were welded together to provide continuity and
Recesses and cover plates were not used with Units C7 and E7 because
their heads were located in the premined 12-Drift,
masses are available commercially, but only devices that are not easily
dislodged during blasting activities are suitable for determining excava-
tion effects. A BSM suitable for such applications was tested and evalu-
called a vibrating wire stressmeter (VWS). The VWS forms a rigid inclusion
in the rock mass, which means that the stressmeter is considerably stiffer
than the surrounding rock. The device is wedged in a borehole. The
4-8
wedging action keeps the stressmeter i_L piace during monitoring, and it is
Changes in the stress field normal to the borehole are reflected in changes
Cook and Ames (1979) at SNL found !that there were difficulties in
setting VWSs in relatively soft rocks. They redesigned the VWS units to
increase the sizes of the platens and to decrease the stiffness. They
vibrating wire sensor. The VWS require!s a special data logger to read its
i
output. The SNL-designed BSM is a speclal version of the VWS and consists
of an outer body with an external shape similar to the VWS. The SNL-
designed BSM can be read with a conventional data logger. Johnstone et al.
suggest that a smaller platen, such as is used with the VWS, would be a
solution. The readily available techno].ogy and experiences with the BSMs
at SNL and the simplicity of the data logging requirements led to selection
four alloy grid strain gages (gage factor of 2.05). The strain gages have
a thermal coefficient of expansion to match the brass plug that they are
bonded to. Two of the strain gages read the compression of the plug and
configuration.
diameter (AQ size). Figure 4-2a shows a diagram of the unit. The other
4-9
II
I IIIIIII
AQBORE HOLE
WEDGE
.... I_-_ = I'_. llll- lli=- lli_.lJJJ_J_ Eill
UPPER PLATEN __1-_ Hl)-_-lH=_-I11
-_tllEjll-_]l.l_ll_llt_--lll_-L]l_-1!lT_';
llllpl =---III
=-lll-=:=lll
=--
STRESSMETER SENSOR II ':1--_
LOWER PLATEN
SHIM
NQ BORE HOLE
4-10
BSM, identified as 6N, was modified by Science Applications International
dlame:er (NQ size). Borehoi8 D4 was drilled larger than DI and was the
same diameter as the nearby borehole injection (BI) holes. The 6N unit was
modified for use by adding special bearing plates to the original unit, as
shown in Figure 4-2b. The extra bearing plates were bonded to the smaller
BSM with Hardman 5-min epoxy.
3. pushing the BSM to the desired depth and orientation in the hole
(one BSM was installed irleach hole with the sensing direction
vertical);
cable until the shear pin, which couples the wedge to the rest of
5. initializing the BSM on the P 350 Vishay Strain Indicator and then
4-11
4.3 Rock Bolt Load Cell (RBLC)
RBLCs are normally used to monitor changes in rock bolt forces that
occur as a result of' displacement changes in the nearby rock mass. They
ground safety. They were used here to augment the MPBX system in a manner
Rock bolts are tensioned steel reinforcing bars (rebars) that are
placed in percussion drilled holes in the rock mass. The rebars are bonded
or anchored to the rock and contain base plates that transmit the tighten-
ing forces to the rock surrounding the holes. For measurements, an RBLC is
placed at the end of a selected rock bolt to measure the resultant force
that is transmitted to the base plate. The RBLCs contain strain-gaged
elements that are used with Wheatstone bridges to relate force changes to
voltage changes.
Ordinarily, RBLCs are applied under conditions where the rock bolts
are anchored on the ends and the tensile forces are distributed between the
base plates and the anchors. In view of NTS safety considerations in the
GTUF, the rock bolts were fully grouted. Thus, it is assumed that only a
fraction of the total force transmitted to the rock bolt was distributed to
a base plate.
nominal sensitivity of ± 267 N (60 Ibf). Sixteen units were purchased for
the evaluations. Four RBLCs were installed at each of two stations, as
illustrated in Figure 4-3. These were used to monitor changes in the roof
forces. The remaining eight RBLCs were positioned on grout inserts tha,_
4-12
_O_W_LI_SD
"IU_
I
l /
,, I
,, \ l
l_r_nF..B
A.TE.Ly \ _, I
_N
=--Lu'_ \\ I /
\ I /
\ I I
.....,
_,_ I,I
ELY _L
',\ ,, II
X I "_='I I
_oo_o_
__ ..__,o,
o
.... ,,, , 11, i ,,, _
.....
--°-- v J i. _
_
V
-_u__ .......... .......... I ' _ . .....
I
I
UOt_IS_-oSO
_.OI:t:, // I
/
I IV.,----_PBx
/
/ l sc_
t I_U
. _. 3.
i,_.&,a_ce
.3.3
contained hydraulic pressure cells (HPCs) and only the bottom 30 cm of
connecting rock bolts were anchored. The inserts were cast in the sides of
the Demonstration Drift for HPC evaluations, and RBLCs were applied to
surfaces of the inserts (Figure 4-4) to pick up any load that the inserts
might receive. The goal was to observe any RBLC load changes that were
sidering load cell alignment. The base plate bearing against the uneven
rock surface can cause the RBLC and rock bolt to be out of line resulting
in bending stresses in the rock bolts and possibly the RBLCs. The
potential problem was addressed by grouting the base plates to the rock and
by providing a spherical seat between the rock and the RBLC tension plate,
as shown in Figure 4-5. The spherical seats were machined from ANSI 4340
steel by SAIC. The seats were proof tested through the full load range to
establish acceptance. The actual bearing surface was covered with a thin
parts.
nut; and
4-14
III1._1111
BRACES
22 mm STEEL CHANNEL
ROCK BOLT
RBLC (TYPICAL)
IILIm,ll
FLOOR
ELEVATION VIEW
ROCK BOLT
BRACES
PLAN VIEW
4-15
I11 •
t,-
I-- <I:
...I i.....i
0 jn
m Oz °
_"x_ m o
t- 0 "--'- 0 z
rr _i Ow
Z lI:t-
t I . i I ,IL ,f-.t
.._ . rf) _
3:
l I a.
I I r_ _o
- i "
_- I o
"_ I J
0 Z _ I"- "_
Ou,l "- • , :3
a:_- I I 0
' _ _
.._. _
• .
: : '::: :! ":':':':' (1)
....-.....
..-... ,.::::::;:;!/.::..:ii:..!:{ "' ---
:!i:i:ii::ili
I i:i:ii!!.i:.::ii!!! '
:.:,:.'.:._..
-:':'.;
:_
;"::::
:":""' ,/-.Z.:,..I
i
:
..............
' ' ',','.'.:,':".:'2':I
• 'i ::::;!::'_':;!!i:I
,.,
. ......,..
•:;:.,.: ..,.,, :
-:..: -. .... ,
_ _ ,
4-16
6. connecting the leads to the DAS, tightening the nut covering the
,b
torque of approximately 340 N-m (250 ft-lb). The output voltages were
read after installation, and initial forces were set in the reference cali-
bration file. Initial forces were set by manually tightening the external
nuts until forces in the vicinity of 4.0 E+4 N were achieved. No attempt
4-17/4-18
--
5.0 MANUAL MEASUREMENT DESCRIPTIONS
phenomena, TE stations were set at the end of nearly every blast round,
ment is made using a special steel tape and an apparatus containing a dial
The TE has a precision steel tape perforated at fixed intervals and a dlal
device that is used to ensure that the same tension is applied at each
were epoxled into percussion-drilled holes along a 38-cm length, with the
5-1
3.8 cm
....
l EXTENSOMETER
TAPE '
55.9cm ANCHOR
MEASUREMENT
LENGTH
3.8 cm
5-2
i. drill new holes, with either a vertical or horizontal orientation,
in solid rock within i m of a freshly mined face, thus
Q
result of the mining process. The water pressures and flow rates were
measured and combined into a hydraulic quotient (HQ). This testing was a
published results for measurements of flow rate per unit pressure head for
each l-m section of a borehole. His measurements were directed toward
in this study.
B1 testing here involved taking the same type of measurements before and
after the Demonstration Drift was mined through a welded tuff rock
5-3
5-4
formation. BI measurements were taken along the lengths of six boreholes,
V
originated in the 12-Drift, and they were drilled before the mining of the
DemoL_stration Drift.
The HQ is extracted from the cubic law that is used with parallel
[!2,,,:q.lm
(,_/r,)"Hl
113
e - [(2,_,n,Ho,Tw ) ) (5-I)
where
5-5
The HQ quantity is taken as the ratio of [Q/(Ho,Tw,n)] in Equation
5-1, where n is assumed to be unity. The HQ quantity has the generic units
¥
the units of m3/(s,kPa) so that flow rate and[ pressure measurements are
fracture _sing the flow measurements if the length and number of fractures
are known; however, the authors were not primarily interested in determin-
ing either the sizes of the fracture apertures in th_ intervals or the
flow and pressure properties changed as a result of the mining and the
subsequent relaxation of the rock around the opening. Thus, their goal was
p=rmeabillty cart, which had been fabricated for another SNL study. Figure
The key controls for the hydraulic system were valves regulating the
gal/min). The flow rate to the injection piping was regulated until a
desired pressure at the injection packer wa_l achieved. The excess water
was returned to the tank through a bypass valve (Figure 5-3). Once the
desired pressure was achieved, the flow rate in the injection pipe was
(I) flow rate, (2) pressure at the injection interval, and (3) time. Addi-
tional pressure measurements were taken nea:c t_ie flowmeter, which was
5-6
5-7
located on the permeability cart, to provide a better record of the
hydraulic behavior of the flow system. Also, total flow volume was
The flow rate and total flow volume were measured by a flowmeter manu-
factured by Flow Technology (Model FTS). The flowmeter could measure flow
rates up to 6 x I0-4 m3/s (9.5 gal/min). The lowest reading of the flow-
meter was 6 x 10 -7 m3/s (0.01 gal/min). The flow volume was read to the
ments. The straddle packers were commercially available. Figure 5-5 shows
the operator inseruing the perforated injection pipe and straddle packers
into a borehole. The pipe size and number of perforations were selected
after trial pumping tests. The purpose of the perforated pipe was to
maximize the amount of water that could flow with a minimum injection
length and pressure loss. A goal in the design of the packer assembly was
length of 0.69 m; thus, the total length of the packer assembly was 1.66 m.
The injection interval, taken between packer-rock contact points, was
* pipe segments, 19 mm (3/4 in.) in dia. and 2.1 m (7 ft) long, to the packer
assembly and connecting the hose from the permeability cart. The position
" of the measurement interval was determined by measuring the distance from a
5-9
permanent reference point near the collar of the hole to the center of the
organized in a set of five steps. The nominal pattern was to take flow
decreasing injection pressures of 0.2, 0.4, 0.6, 0.4, and 0.2 MPa (30,
60, 90, 60, and 30 psi) for periods of 2 to 3 min. In some cases, the
fracture flow properties were such that the maximum pressure was reduced to
some attainable value and then the other pressures were proportioned
accordingly.
hole. The packers were pressurized to a nominal pressure of 2.4 MPa. The
• water pressures varied from 0 to 0.6 MPa. Thus, there was a pressure
differential along the length of the borehole. Packer and water pressures
This was another developmental effort because measurements of this type had
not previously been taken in a hard rock. The method was selected to
5-11
determine whether it could be used in lieu of usingMPBXs, which were not
et al., 1981).
in these measurements. The figure shows a borehole in the pre- and post-
mined position. After mining, the borehole axis is expected to move toward
the excavated region and deform slightly. Ideally, angle changes in the
before and after the mining process. The borehole deflections are small
(1/206,000).
hole traverse, and the plot of the resulting angle change measurements is
located outside the borehole. The digital readings were manually recorded
Figure 5-7 is a schematic of the BD and shows the angle that can be
5-12
DEMONSTRATION DRIFT
[........... " zf
_" "''.EFO.E.,N,N(_
LECTOMETER BOREHOLE
l III
_ OBSERVATION DRIFT (12-DRIFT)
5-13
_ 5-14
strain-gaged flexible connection. The BD was manufactured so that the
three permanently positioned wheels were the primary reference set for
• traverses and a set of three spring-mounted wheels was used to keep the BD
A specially grooved PVC casing was grouted into each of the boreholes
to ensure good coupling with the rock. The casing, 69.5 mm in diameter,
was purchased in 3.0-m lengths and glued together during installation. The
positions. Specifically, the casing has four small grooves [1.65 x 5.1 mm
(0.065 x 0.2 in.)] cut in the inside wall of the casing at four quadrant
points.
or possibly in cavities cut in rock surfaces. HPCs are planned for use in
5-15
5.4.1 Measurement Principle
connecting pressure lines are cast in concrete. The cell fluid is mercury,
and hydraulic oils are used in the pressure system. After the concrete has
set up, the end of the repressuring tube is squeezed, thus driving the
surrounding the cell. This action integrates the HPC into the concrete
structure. The repressuring llne is fixed so that the mating of the cell
structure. The pressure cell then detects any changes in the concrete
stress field acting normal to the cell, and the changes in the cell
The pressure measurement is made with the aid of the hydraulic system.
Fluid is pumped into the pressure line, and it bears against the diaphragm.
When the input hydraulicpressure is slightly greater than the cell fluid
and the hydraulic fluid is pumped back to a reservoir near the hydraulic
pump in the return line. In this testing, grout was substituted for
concrete.
5.4.2 MeasurementEquipment
Glotzl Concrete Stress Cells, Model B 10/20, were used in the grout
30.4 MPa (4400 psi) with a reported accuracy of ± 30 kPa. Each unit was
pump, and the pressure was read directly with a pressure gage provided with
The main purpose for using the HPCs was to evaluate installation
procedures that might be used in the ES. The authors were concerned about
5-16
/% ' ,
!iil ,'F,'SSU
ECELL
CELL FLUID '_'' " ^ i ' " ,
JO
RETURNLINE---_'_ -^' A ::
.i' ""_'
^ , '" ^'. ", ^, ,' 'I
' . ' . A A ,/
PRESSURE
LINE
FROM HYDRAULICPUMP
II ' ' ^' ' , ,( , :/v
- ' ' . " ._
- c;.ou'r
5 - I-_
JI,. I
(I) falling concrete disturbing the HPC placement, and (2) air pockets
forming around the HPCs during the concrete placement. They attempted to
Figure 5-9 shows the testing concept. A wedge-shaped cavity was mined
into two ribs of the Demonstration Drift. The cavity was covered with a
cavity (see Figure 4-4). The plywood held the HPCs in configurations
expected for the 0.3-m-thick ES liner. An opening was made at the top of
the plywood so that a stiff grout, a substitute for concrete, was pumped in
to fill the cavity, forming a grout insert. After the grout had hardened,
the pressure cells were activated to establish the lockoff pressure, and
Only one technique was used in grouting the inserts for the HPCs, and
no meaningful procedure developments evolved. As a matter of record, the
1851 kg/m 3
The grout was pumped in at a rate of 0.06 m3/min. Approximately 1.5 m3 was
pumped into the left insert and 1.6 m3 into the right insert.
In one case, the grout was to hold the PVC casing in p].ace for the BD
measurements, and in the other, the grout was to hold the MPBX anchors in
piace.
5-18
15.2 cm -.J 53.3 ©m
a, 2.1m .I _ _HPCs
I
45.7 cmp -_
21.6 cm
i i iii
S3.3 ©m
_..2om
__ 0 0 I
1 I A
0,3 ,4 0 I I
_" #B INSERT PLAN VIEW
5-19
Two types of grout were used, Sulfa_set was used as a fast-settlng,
sufficient to pump through the various size grout tubes, The intent was to
reach the maximum viscosity that could be pumped through the t_bes so the
The grouting process for the BD tubing was started first and required
started in Hole B1 with uncertain success° The casing had a 6,4-mm feed
tube near the bottom of the hole, and there was a bleed llne at the top.
In this way, the grout would be pumped into the bottom to completely fill
the annulus between the outside of the casing and the borehole surface,
The grouting scheme was to put a slug of water on top of the grout column
at the bottom of the hole, When the hole was fully grouted, the water
would appear in the bleed line, and the hole would be assumed to be fully
grouted, The bleed llne would not fit betweer the casing and the borehole
wall; it had to be located within the casing and a seal provided at the
should fill the annulus, Approximately five times this amount of grout was
pumped into the hole, and no water showl_d in the bleed tube, Water did
showed in the other holes probably because of its increased viscosity, The
end of the shift arrived, and still the hole had not been filled up and the
0,08 m3 of grout was pumped into the bleed tube to attempt to close the
upper part of the annulus, The inside of the casing was cleaned, and it
holes should be enlarged, and Holes B4, FI, and F4 were reamed out to a
diameter of 96 mm, For these holes, five grout tubes, 9,5 mm in diameter,
and a slmilar-slzed bleed tube were added to the outside of the casing
5-20
. NOTE: CLOSE-UP SHOWS GROUT TUBING
ANGLE CUT, SO AS NOT TO
HANG-UP ON BOREHOLE WALLS.
ASSEMBLY
j
_ 9.1 m
< .... _ 12.2 m
< .... > 15.2 m
< ..... 18.3 m
4
/ COLLAR PiPE
/ FOAM RUBBER ANCHORS
I I I I-" _l SEPARATORS
STAGE 1
--_{ GROUT l< STAGE 2 GROUT _1
----o 1 2
o 3
GROUT o 4
TUBES o 5
o 6
rl
5-21
bleed tube was located at a distance of 18.3 m. The collar of the casing
was sealed with a Sulfaset to prevent grout flow into the drift, The
the grout showedby return flow in the next longest tube, the first tube
was closed off, the pumping was switched to the return tube, and the
shutoff/switching process was repeated until the grout was observed in the
longest tube. The grouting procedure was terminated at this showing. This
staged grouting procedure worked weil, and the expected amount of grout was
added to each of the holes. There was no check of the adequacy of the
grouting, but the second process gave the authors more confidence that the
Groutiug for the MPBXs was similar in nature to the BD casings, but
the MPBXs required more preparation. The MPBXs required separation of the
anchors so that they could act independently. This meant that the grout
by fabricating cardboard donuts near the anchors. The donuts were under-
The first two MPBXs that were grouted in were C7 and E7. The general
procedures used with the most recent BD casing installations were tried.
The major difference was that the ends of grout tubes were placed near the
anchors. The longest tube served as tile last return tube, and grout return
The borehole grouting procedures for the MPBXs installed in the Demon-
occurred in two stages in those holes, and there were some differences in
the procedures for up (roof) and down (floor) holes. A foam packer was
added to the end of the MPBX collar. This packer served the purpose of
helping to separate the grout column from the collar pipe. Six 9.5-mm-dia.
5-22
tubes were connected to the MPBX anchor assembly. Two tubes were located
along the pipe between the collar and foam packer and the remaining four
" were located between the foam packer and the deepest anchor.
consisted of pumping Sulfaset into the shortest tube and filling the void
up to the next tube. The Sulfaset was used to establish a good borehole
seal at the bottom of the grout column and to ensure that the pipeand ali
grout tubes were firmly installed. After the Sulfaset cured for approxi-
of the four tubes was terminated above the packer, the next longest was
terminated above the five anchors, and the remaining two were terminated
step in ensuring full grouting in the space between the next deepest anl
deepest anchors, the grouting procedure was changed when the grout column
reached the next longest grout tube. When grout returned from this line,
the grout operation was stopped, the line was cleaned, and the grout in the
borehole was allowed to set up for a period of 2 hr. Then, the grout was
pumped in the next longest line and stc,pped when there was return in the
line that was beyond the deepest anchor. At the termination of pumping,
ali lines were closed and the grout was allowed to cure for at least 2 days
For the down holes, the Stage i grouting consisted of pumping Sulfaset
in the space between the collar and foam packer. The Sulfaset was allowed
to harden for 2 hr to set up a good seal for the collar pipe. Next, the
_re_t was added to the longest tube, and the pump/shutoff/switch procedure
was followed until there was grout return in the tube nearest the foam
packer.
5-23/5-24
6.0 MINING ACTIVITIES
focus was on providing information for the ES because this is the next
results are also applicable to repository designs. The limits were that
mining of a relatively short, 29.6 m long, drift. This meant that there
of the following"
6-1
less maintenance. Second, drift dimensions are more exact as a
face advances equal to one-half the round width (6.1 In) are
3. Evaluate Fragmentation.
6-2
systems. The goal in these evaluations was to document the muck
indicate smooth blasting and presplitting as the two most commonly used
detonated last, and the final slab of rock is explosively driven into the
cavity formed from previously blasted rock that was nearer to the center of
the round. The low-density perimeter charges minimize the damage to the
first. This causes a bounding crack defining the shape of the opening. In
marly cases, the perimeter is blasted separately from the remainder of the
for more perimeter holes and the extra step in the mining cycle. Smooth
concept of blasting to a "free face." That is, the explosive energy is not
6-3
completely confined in the rock but is used to move the fragmented rock
away from its resting piace. There are two popular techniques to initiate
a "free face" when smooth blasting a full-face heading' the burn cut and
the angle cut. In competent rock, the burn cut is preferred over the angle 4
cut chiefly because there can be greater advance per round while allowing
The basic principle of a burn cut blast pattern is that the empty
hole(s) (burn holes) in the center of the pattern act as the free face to
the burn reliever holes, as shown in Figure 6-1. Different types of holes
are identified with special symbols in the figure. The explosive energy of
the reliever holes is used to break a wedge of rock toward the empty burn
hole, which enlarges the free face of the burn hole to include the burn
(stope) holes break to the enlarging void area to further expand the blast
opening. The lifters (along the floor) and perimeter holes (around walls
wedge of rock near the central portion of the round to provide the needed
6-1. These holes are loaded with explosives, which are fired first and
usually in pairs, resulting in the wedge of rock exploding into the drift.
As with the burn cut, the subsequent production holes follow in sequence
and break into the newly opened wedge area. Again the lifters and
use of the "lookout angle." To maintain the uniform shape of the drift
cross section from one round to the next, the perimeter holes have to be
important that the "lookout angle" be as small as possible and that ali
perimeter holes should be nearly parallel so that the spacing between holes
6-4
r
6-5
6.2.2 Smooth Blasting Factors
Once the burn or angle cut technique is selected for a round, there
are a number of factors that have to be considered. These relate to the
physical details associated with blasting a round. They are summarized and
discussed here so that descriptive quantities have a reference base. The
initial cut in the rock. For the burn cut, they are called burn
relievers, and for an angle cut, they are called angle holes.
6-6
7. Production explosive type--A description of the explosives used
Figure 6-2 shows a plan view illustrating the individual blast rounds.
Rounds are identified by number. The mining was conducted in four stages,
excavated so that a twin boom drill Jumbo could be positioned for full-face
the welded tuff. The drilling for rib removal had to be performed using
Stage II was the start of full-face mining using the drilling jumbo.
° Stage II blasting consisted of two rounds that were shot using a hex burn
cut design. Figure 6-3 shows the details. Different symbols are used to
6-7
6-8
Two factors influenced the mining for Stage III. The end of Round 5
was the location for the Station C instrumentation. First, it was decided
that the rounds between Station C and E would be short rounds so that the
drift convergence studies would be enhanced. The second factor was the
#
observation that the rock quality was deteriorating somewhat because of the
presence of the fault beyond Station C. A burn cut was used for Round 6A;
blast pattern was selected for Round 6B, The V-cut blast design is shown
in Figure 6-4. The next Round, 7A, was still in the fault/shear zone, but
the central part was in relatively competent welded tuff and a burn cut was
used. The ].ast round for Stage III was a short round needed to reach the
complete this last stage with full 3.0-m rounds. However, it was necessary
to replace drills on the jumbo, and only 2.4-m long drill steels were
readily available. Thus, the last five rounds were shorter. All blast
patterns for Stage IV were essentially the same. A triangular burn cut was
2. reduce drilling,
6.2.3.2 Explosives
The explosives used were selected from those normally available at the
NTS. Two types of explosives were used for general production hole
for use in the perimeter holes. These explosives are briefly discussed.
ANFO, a prill-type explosive (ammonium nitrate and fuel oil), was used
in the production and lifter holes for much of the Stage I mining. The
6-10
_
6-11
6-12
ANFO prills are blown into a hole and pneumatically loaded to a density of
approximately 0,95 g/cm 3, This entity yields a load of about 1.49 kg/m for
holes approximately 45 mm in diameter. A cartridge of Hercodyne was
located at the back of the holes and served as a primer booster to activate
the ANFO, It was difficult malntaining quallty control in loading the ANFO
in this particular rock type; thus, it was not used in the three remaining
blasting stages,
high explosive. Cartridges are available in diameters of 25- and 32-mm and
in lengths of 203 and 406 mm, Hercodyne cartridges can be tamped into
holes to achieve higher densities, The normal load concentrations are 0.64
and 0,91 kg/m for the two hole sizes, The last cartridge in a charge
used in ali perimeter holes and usually in the burn holes. Cartridges are
22 mm in diameter and 0,61 m long and can be coupled together to form a
diameter product might have been preferred, lt was Judged that the basic
NTS-supplied explosives.
Ali blast holes were sequenced for detonation with LP Nonel Primadet
delay detonators, These nonelectric caps were usually placed at the bottom
of the blast hole in the first loaded cartridge. A normal delay pattern
consisted of 16 delays, The total elapsed time for the 16 delay i1_tervals
was 9.6 ms, Lead-in lines from individual blast holes were tied to a
" single length of explosive cord (E Cord), This cord detonates at a high
velocity of 7000 m/s, A blasting cap and safety fuse were used to activate
6-13
6.2.3.3 Drilling for Blasting
twin boom drill jumbo would De necessary. A drill jumbo was not available
¢] the NTS for the experiment; thus, one was leased that was suitable for
(I) drilling a full face with a single setup and (2) drilling a 3-m round.
A used Eimco Secoma drill jumbo was leased based on size, availability, and
cost considerations. The drill jumbo was equipped with two Gardner Denver
D93 drifter drills. These drills came with 32-mm by 3.7-m drill steels and
44-mm dia production bits, both button and X-type bits. Also, 76- and
impractical to drill with the drill jumbo or when the drill jumbo was down
for repairs. Jacklegs were used to drill the rib (side wall) excavations
grouted rock bolts for ground support for the Demonstration Drift. The
first was the rock mass classifications where this type of ground support
would be at the upper end of the ranges in both systems (Langkopf and
Gnirk, 1986). The second was the evidence in G- ,nnel that rock bolts and
tuff up to 4.9 m wide. The third was the nominal rule of thumb used in
that rock bolts and wire mesh can be used with a minimum of a 1.2-m spacing
between the bolts, and the lcr _hs of the bolts are a minimum of one-half
long and spaced in a 1.5- x 1.5-m pattern, with welded wire mesh. The
recommended wire mesh was 9-gauge wire welded in a 10.2- x lO.2-cm grid.
6-14
_, , n r, ,, +iFlr; iii11 ,,
Included in the recommendation wa_ the provision that the rock bolts and
mesh would be installed along with the excavation. SNL made two changes to
these recommendations. The first was that a woven wire (chain link) mesh
, would be used. The welded wire mesh was re_._mmended because a better view
of the rock _urface could be available and the welded wire mesh could be
used with shotcrete if necessary. Woven wire mesh, made from ll-gauge
G-Tunnel. The second change was related to the use of the woven wire mesh,
which was available in rolls 2.4 m wide. The rock bolt pattern was changed
from 1.5 x 1.5 m to 1.5 x 1.2 m to accommodate the width of the woven wire
aspects in the mining. Thus, the final design shape and ground support
drift was too short to conclusively select one ground support method over
grouts or other types of ground support have more promise for repository
applications.
grout, was used in the two rows immediately following Station E (Round 8).
they generally set faster and cure to higher ultimate strengths. Expansive
cement grouts were used for the next two rows of bolts (Round 9) after the
gypsum-based grouts.
6-15
6-16
The next two rows of holes, after the cement-based grouts (Round i0)
were used, were fitted with Swellex rock bolts. Swellex bolts are
friction-type rock bolts that are inserted and expanded against the hole
surface with water pressure. They are easily installed and are well suited
The final ground support for the remainder of the drift was a
by weight of fibers.
6-17/6-18
i
7.0 SUMMARY
layout, the pertinent geology, the DAS, the mining activities, and the
instrumentation. Instrumentation discussion was divided into two major
7-1/7-2
8,0 REFERENCES
_ 8-1
Zimmerman, R • M ., and W . C . Vollendorf, "Geotechnical Field Measurements,
G-Tunnel, Nevada Test Site," SAND81-1971, Sandia National Laboratories,
Albuquerque, NM, May 1982. (HQS.880517.1720)
q
8-2
APPENDIX
|
This report contains no data from or for inclusion in the RIB,
A-I/A-2
, ii, , , , ii n
,lp,